13. In Bangladesh at first the project planning is permitted by the
National parliament, and then it is sent to the National Economic
Council (NEC)
NEC confirms and accepts the plan and then it is launched to
ECNEC for ultimate approving.
From ECNEC, the plan goes to Ministry of Planning
After that it helps to formulate and implement the policies and also
reviews the impact on the projects on the economy.
47. Factors Padma Multi Purpose
Bridge
Dhaka Metro Rail Rooppur Nuclear
Power Plant
Project Type
(Time &
Investment basis)
Development and Self
Financed
Development & JICA Development &
Russia
Decision Making Political/Rational Political/Rational Political/Rational
Gateways passed Four Four Five
Mode of
Operating
Framework
Flexible Flexible Flexible
Time Constraint
Maintained
No No No
Cost Overrun Yes ($ 4.61 Billion
Estimated)
Yes ($11.03 Billion
Estimated)
Yes ($12.65 Billion
Estimated)
Framework
Strictly Followed
No No No
Overall Satisfactory Satisfactory Satisfactory
54. Project Planning Phase need
to be developed
Project Management should
be empowered strictly
Need to increase skilled
manpower
Project Governance
framework need to be
followed strictly
Point of
Emphasis