Quadriga Project Profiles
By Lindsay Law
In recent years we have experienced an awakening in a need for the conservation
of our heritage. A specialist approach is needed which combines a thorough
understanding of traditional building crafts and the latest advances in technology.
Quadrigas’ work illustrates how traditional, as well as contemporary repair solutions,
can be used in conservation, restoration and preservation.
Quadriga Contracts Ltd, Gadbrook House, Gadbrook Park, Rudheath, Northwich, CW9 7RG. Telephone: 01606 330888
In-situ Restoration & Coating to
Afflecks Palace, Manchester
Removal of non-microporous coating Applied silicon paint which is totally
microporous
Afflecks Palace, Manchester
Finished façade showing all stucco work restored
Concrete Repair
The Royal Liver Building
Programme of works:
External repair and restoration of the building’s four main domes and eight smaller domes,
the refurbishment of the two spiral staircases and the replacement of the timber speaker
housing in the West Tower.
Concrete Repair and Waterproofing
Loose haunchings where removed and re-haunched with an epoxy primer and rapid
setting concrete. Kemper system applied to cupola’s.
Middlesbrough College
This once derelict bonded warehouse façade has been structurally repaired by Quadriga
using Helical bar reinforcement and brickwork restoration. A great example of bringing
old and new architectural styles together. All 1800 original bricks
of this façade where re-used.
The Pier Head Building, Cardiff
The Pier Head Building is a very grand example of Victorian architecture.
The terracotta with ferrous dowels resulted in corrosion/expansion along
with cracking/spalling of the detail to this 1802 building.
Resin bonding and pinning proved to be a very useful repair technique for
this historic building project.
Resin Bonding & Pinning
Gargoyles where painstakingly put back together like a jigsaw using steel pins and resin
bonding. The final piece was resin bonded together and then fixed to the steel armature
Projecting from the façade.
A fully restored gargoyle drainage outlet
and duck head ornate relief fully restored
Relief Panel Restored
Corroding steelwork behind this relief panel to the Pier Head Building had caused
structural fracturing of the terracotta which had to be removed, steel blasted
and a bitumen based protective coat applied.
This was followed by the installation of new terracotta.
Terracotta Restoration
New Bond Street
Working from old photographs and what detail remained of the original façade,
we were able to recreate what had been at No27 previously using our in house
terracotta designer.
Terracotta Restoration
New Bond Street, C1930
We produced full detail design shop drawings for the manufacture and installation
of the new frontage
27 New Bond Street, London
Some original detail did get uncovered which gave us the opportunity
to take accurate presses of the relief work
27 New Bond Street, London
The finished façade complete with brass window frames has now recreated
what is a beacon of historic ceramic architecture back on this most prestigious of London streets.
It is a testament to the skills and craftsmanship still available today.
Victoria Station, Manchester
Heritage Package
Internal and external refurbishment of the 1844 George Stephenson designed
Victorian station commenced for Quadriga in 2013
Victoria Station, Manchester
Internal concourse facades cleaned and restored using the Doff system. The roof was
replaced but the roof lines where maintained.
Victoria Station, Manchester
Cleaning and restoration of
damaged and defective
mosaic floors which had been
left to decay over many
years.
Large sections of the ornate
plastered ceilings had to be
taken down and replaced
due to dry and wet rot.
Victoria Station, Manchester
Cracked and missing glazed
Victorian tiles were re-made
in situ by skilled operatives in
the traditional way and
sprayed using a unique mix
glaze.
Victoria Station, Manchester
Pumpkin Bar Dome roof restored externally
and internally, including a full overhaul of the leaded stained glass.

Project Profiles - V1

  • 1.
    Quadriga Project Profiles ByLindsay Law In recent years we have experienced an awakening in a need for the conservation of our heritage. A specialist approach is needed which combines a thorough understanding of traditional building crafts and the latest advances in technology. Quadrigas’ work illustrates how traditional, as well as contemporary repair solutions, can be used in conservation, restoration and preservation. Quadriga Contracts Ltd, Gadbrook House, Gadbrook Park, Rudheath, Northwich, CW9 7RG. Telephone: 01606 330888
  • 2.
    In-situ Restoration &Coating to Afflecks Palace, Manchester Removal of non-microporous coating Applied silicon paint which is totally microporous
  • 3.
    Afflecks Palace, Manchester Finishedfaçade showing all stucco work restored
  • 4.
    Concrete Repair The RoyalLiver Building Programme of works: External repair and restoration of the building’s four main domes and eight smaller domes, the refurbishment of the two spiral staircases and the replacement of the timber speaker housing in the West Tower.
  • 5.
    Concrete Repair andWaterproofing Loose haunchings where removed and re-haunched with an epoxy primer and rapid setting concrete. Kemper system applied to cupola’s.
  • 6.
    Middlesbrough College This oncederelict bonded warehouse façade has been structurally repaired by Quadriga using Helical bar reinforcement and brickwork restoration. A great example of bringing old and new architectural styles together. All 1800 original bricks of this façade where re-used.
  • 7.
    The Pier HeadBuilding, Cardiff The Pier Head Building is a very grand example of Victorian architecture. The terracotta with ferrous dowels resulted in corrosion/expansion along with cracking/spalling of the detail to this 1802 building. Resin bonding and pinning proved to be a very useful repair technique for this historic building project.
  • 8.
    Resin Bonding &Pinning Gargoyles where painstakingly put back together like a jigsaw using steel pins and resin bonding. The final piece was resin bonded together and then fixed to the steel armature Projecting from the façade. A fully restored gargoyle drainage outlet and duck head ornate relief fully restored
  • 9.
    Relief Panel Restored Corrodingsteelwork behind this relief panel to the Pier Head Building had caused structural fracturing of the terracotta which had to be removed, steel blasted and a bitumen based protective coat applied. This was followed by the installation of new terracotta.
  • 10.
    Terracotta Restoration New BondStreet Working from old photographs and what detail remained of the original façade, we were able to recreate what had been at No27 previously using our in house terracotta designer.
  • 11.
    Terracotta Restoration New BondStreet, C1930 We produced full detail design shop drawings for the manufacture and installation of the new frontage
  • 12.
    27 New BondStreet, London Some original detail did get uncovered which gave us the opportunity to take accurate presses of the relief work
  • 13.
    27 New BondStreet, London The finished façade complete with brass window frames has now recreated what is a beacon of historic ceramic architecture back on this most prestigious of London streets. It is a testament to the skills and craftsmanship still available today.
  • 14.
    Victoria Station, Manchester HeritagePackage Internal and external refurbishment of the 1844 George Stephenson designed Victorian station commenced for Quadriga in 2013
  • 15.
    Victoria Station, Manchester Internalconcourse facades cleaned and restored using the Doff system. The roof was replaced but the roof lines where maintained.
  • 16.
    Victoria Station, Manchester Cleaningand restoration of damaged and defective mosaic floors which had been left to decay over many years. Large sections of the ornate plastered ceilings had to be taken down and replaced due to dry and wet rot.
  • 17.
    Victoria Station, Manchester Crackedand missing glazed Victorian tiles were re-made in situ by skilled operatives in the traditional way and sprayed using a unique mix glaze.
  • 18.
    Victoria Station, Manchester PumpkinBar Dome roof restored externally and internally, including a full overhaul of the leaded stained glass.