SlideShare a Scribd company logo
1
Mechanical Components
-COLD WATER BASIN:
Figure 2-1
One of the most critical cooling tower components is the cold water basin, which
collects water and directs it to the sump or pump suction line.
The aim of a cold water basin is to eliminate stagnant water and prevent bacteria
from growing.
They might even have heaters to keep the water from freezing in the event of a
power outage.
-FILLS:
Figure 2-2
2
Another important component of cooling tower parts is fill material or fill media.
This component is, in some ways, the most critical since it determines the
cooling tower's efficiency.
The rate of heat transfer between the cooling and working media is increased
when the contact surface between them is greater. In cooling towers, the main
purpose of fills is to raise the contact surface as much as possible.
Fill media can be either of the film style type or splash style type. The film style
fills, which is used in most cooling towers, produce thick water strips that
increase the rate of heat transfer and also larger evaporation rates. splash style
fills are commonly used in crossflow cooling towers in which water cascades
down on staggered slats that breaks up water droplets to increase the water
surface area.
- Hot Water Distribution Basin:
Figure 2-3
The (hot water) distribution basin is above the fills, which is where the hot
process water collects. They cannot provide a proper flow distribution down the
nozzles to be sprayed over the fills due to corrosion and degradation over time,
resulting in considerable loss of thermal efficiency, and as a result, they are
replaced to prevent such downfalls in the system's performance.
3
-NOZZLES:
Figure 2-4
The nozzles are one of the cooling tower components that can be used in
crossflow cooling towers. Water is lifted to the distribution basins and then
cascaded back over the fill through the nozzles on the hot water basin floor in
crossflow cooling towers.
- Cooling Tower Float Valve:
Figure2-5
4
Water within the tower must be kept at the correct level in order for it to function
properly. Float valves, while needing only minor maintenance over time, have
become one of the most important cooling tower components.
Float valves regulate the water level and, when correctly calibrated, ensure that
no water is lost when the pump shuts down in an overflow.
- Drift Eliminators:
Figure2-6
The drift eliminator is another important cooling tower component. This device's
aim is to catch large water droplets in the cooling tower air stream and reduce
process water loss.
The eliminator directs moisture and water droplets away from the cooling tower
and into another part of the system, stopping them from leaving. After that, the
air and water will be separated and recycled for other purposes.
Apart from the importance of preventing process water loss, the removal of these
large water droplets is motivated by the fact that they contain chemicals and
minerals that are considered harmful to the environment.
5
- Water Distribution Piping:
Figure 2-7
Another critical cooling tower component is the water distribution piping
system. Despite the fact that heat generation points are often located near
cooling towers, the piping system routing and physical dimensions are
determined by the type of tower, site configuration, and topography of the region
in which the site is located.
-COOLING TOWER FANS:
Figure 2-8
6
A draft is generated by natural draft cooling towers without the use of any
mechanical components. Fans are, however, an important component of
mechanical draft, crossflow, and counterflow cooling towers.
One of the factors to remember when it comes to fans is noise. Despite the fact
that they are commonly known to be very noisy, some designs are available with
lower noise levels while still being durable.
-GEAR BOX:
Figure 2-9
Towers with large fans for generating a draft often have gearboxes for changing
the power exerted by the motor on the fan's driveshaft.
The gearbox is one of the cooling tower components that reduces the expense of
the mechanical system by not only changing the rotational speed of the pump but
also serving as a torque multiplier, reducing the size of the motor required.
7
- Driveshafts:
Figure 2-10
The driveshafts transmit the power produced by the motor to the gearbox,
making it one of the cooling tower's most important components.
It should be remembered that since the shaft is in direct contact with the cooling
tower's internal environment, highly corrosion-resistant materials must be used
in their manufacture.
In the event of shaft run out, the driveshafts should be able to be easily
recalibrated.

More Related Content

Similar to project cooling towers.docx

Thermodynamic Analysis of Cooling Tower with Air to Air Heat Exchanger for Re...
Thermodynamic Analysis of Cooling Tower with Air to Air Heat Exchanger for Re...Thermodynamic Analysis of Cooling Tower with Air to Air Heat Exchanger for Re...
Thermodynamic Analysis of Cooling Tower with Air to Air Heat Exchanger for Re...
IJMREMJournal
 
Cooling System - IC Engines : Unit-III
Cooling System - IC Engines : Unit-IIICooling System - IC Engines : Unit-III
Cooling System - IC Engines : Unit-III
S.Vijaya Bhaskar
 
AC end.pdf
AC end.pdfAC end.pdf
AC end.pdf
Mahamad Jawhar
 
AC.docx
AC.docxAC.docx
Water Chilled Airconditioning
Water Chilled AirconditioningWater Chilled Airconditioning
Water Chilled Airconditioning
Aljon Altiche
 
Seminar presentation on cooling tower
Seminar presentation on cooling towerSeminar presentation on cooling tower
Seminar presentation on cooling tower
SAQUIBMANSOORKHAN
 
PERFORMANCE ANALYSIS AND EFFICIENCY IMPROVEMENT OF COOLING TOWER AT MTPS-I
PERFORMANCE ANALYSIS AND EFFICIENCY IMPROVEMENT OF COOLING TOWER AT MTPS-IPERFORMANCE ANALYSIS AND EFFICIENCY IMPROVEMENT OF COOLING TOWER AT MTPS-I
PERFORMANCE ANALYSIS AND EFFICIENCY IMPROVEMENT OF COOLING TOWER AT MTPS-I
IRJET Journal
 
Cooling Tower
Cooling TowerCooling Tower
Cooling Tower
PramodShriwastava1
 
3Ch7.pdf
3Ch7.pdf3Ch7.pdf
Enhancement of the Performance of Hydraulic Power Pack by Increasing Heat Dis...
Enhancement of the Performance of Hydraulic Power Pack by Increasing Heat Dis...Enhancement of the Performance of Hydraulic Power Pack by Increasing Heat Dis...
Enhancement of the Performance of Hydraulic Power Pack by Increasing Heat Dis...
ijceronline
 
cooling tower, Factors Affecting Cooling Tower Performance,Efficient System O...
cooling tower, Factors Affecting Cooling Tower Performance,Efficient System O...cooling tower, Factors Affecting Cooling Tower Performance,Efficient System O...
cooling tower, Factors Affecting Cooling Tower Performance,Efficient System O...
Salman Jailani
 
Cooling tower
Cooling towerCooling tower
Cooling tower
Pranavmaruti
 
cooling tower
cooling towercooling tower
cooling tower
Karnav Rana
 
Hvac systems
Hvac systemsHvac systems
Hvac systems
Husain Baqer
 
cooling tower manufacturer in India
cooling tower manufacturer in Indiacooling tower manufacturer in India
cooling tower manufacturer in India
BluetechCoolingEquip
 
Optimal design of a hyperboloidal cooling tower
Optimal design of a hyperboloidal cooling towerOptimal design of a hyperboloidal cooling tower
Optimal design of a hyperboloidal cooling tower
Sourav Lahiri
 
Study the factors on which efficiency of cooling tower can be critically accl...
Study the factors on which efficiency of cooling tower can be critically accl...Study the factors on which efficiency of cooling tower can be critically accl...
Study the factors on which efficiency of cooling tower can be critically accl...
IJERA Editor
 
IRJET- Optimization of Flat Plate Solar Collector with Novel Heat Collect...
IRJET-  	  Optimization of Flat Plate Solar Collector with Novel Heat Collect...IRJET-  	  Optimization of Flat Plate Solar Collector with Novel Heat Collect...
IRJET- Optimization of Flat Plate Solar Collector with Novel Heat Collect...
IRJET Journal
 
Bs report
Bs reportBs report
Bs report
kellyxc
 
final project.docx
final project.docxfinal project.docx
final project.docx
Mahamad Jawhar
 

Similar to project cooling towers.docx (20)

Thermodynamic Analysis of Cooling Tower with Air to Air Heat Exchanger for Re...
Thermodynamic Analysis of Cooling Tower with Air to Air Heat Exchanger for Re...Thermodynamic Analysis of Cooling Tower with Air to Air Heat Exchanger for Re...
Thermodynamic Analysis of Cooling Tower with Air to Air Heat Exchanger for Re...
 
Cooling System - IC Engines : Unit-III
Cooling System - IC Engines : Unit-IIICooling System - IC Engines : Unit-III
Cooling System - IC Engines : Unit-III
 
AC end.pdf
AC end.pdfAC end.pdf
AC end.pdf
 
AC.docx
AC.docxAC.docx
AC.docx
 
Water Chilled Airconditioning
Water Chilled AirconditioningWater Chilled Airconditioning
Water Chilled Airconditioning
 
Seminar presentation on cooling tower
Seminar presentation on cooling towerSeminar presentation on cooling tower
Seminar presentation on cooling tower
 
PERFORMANCE ANALYSIS AND EFFICIENCY IMPROVEMENT OF COOLING TOWER AT MTPS-I
PERFORMANCE ANALYSIS AND EFFICIENCY IMPROVEMENT OF COOLING TOWER AT MTPS-IPERFORMANCE ANALYSIS AND EFFICIENCY IMPROVEMENT OF COOLING TOWER AT MTPS-I
PERFORMANCE ANALYSIS AND EFFICIENCY IMPROVEMENT OF COOLING TOWER AT MTPS-I
 
Cooling Tower
Cooling TowerCooling Tower
Cooling Tower
 
3Ch7.pdf
3Ch7.pdf3Ch7.pdf
3Ch7.pdf
 
Enhancement of the Performance of Hydraulic Power Pack by Increasing Heat Dis...
Enhancement of the Performance of Hydraulic Power Pack by Increasing Heat Dis...Enhancement of the Performance of Hydraulic Power Pack by Increasing Heat Dis...
Enhancement of the Performance of Hydraulic Power Pack by Increasing Heat Dis...
 
cooling tower, Factors Affecting Cooling Tower Performance,Efficient System O...
cooling tower, Factors Affecting Cooling Tower Performance,Efficient System O...cooling tower, Factors Affecting Cooling Tower Performance,Efficient System O...
cooling tower, Factors Affecting Cooling Tower Performance,Efficient System O...
 
Cooling tower
Cooling towerCooling tower
Cooling tower
 
cooling tower
cooling towercooling tower
cooling tower
 
Hvac systems
Hvac systemsHvac systems
Hvac systems
 
cooling tower manufacturer in India
cooling tower manufacturer in Indiacooling tower manufacturer in India
cooling tower manufacturer in India
 
Optimal design of a hyperboloidal cooling tower
Optimal design of a hyperboloidal cooling towerOptimal design of a hyperboloidal cooling tower
Optimal design of a hyperboloidal cooling tower
 
Study the factors on which efficiency of cooling tower can be critically accl...
Study the factors on which efficiency of cooling tower can be critically accl...Study the factors on which efficiency of cooling tower can be critically accl...
Study the factors on which efficiency of cooling tower can be critically accl...
 
IRJET- Optimization of Flat Plate Solar Collector with Novel Heat Collect...
IRJET-  	  Optimization of Flat Plate Solar Collector with Novel Heat Collect...IRJET-  	  Optimization of Flat Plate Solar Collector with Novel Heat Collect...
IRJET- Optimization of Flat Plate Solar Collector with Novel Heat Collect...
 
Bs report
Bs reportBs report
Bs report
 
final project.docx
final project.docxfinal project.docx
final project.docx
 

More from Mahamad Jawhar

text book Programmable-Logic-Controllers plc.pdf
text book Programmable-Logic-Controllers plc.pdftext book Programmable-Logic-Controllers plc.pdf
text book Programmable-Logic-Controllers plc.pdf
Mahamad Jawhar
 
2.pdf
2.pdf2.pdf
3.pdf
3.pdf3.pdf
1.pdf
1.pdf1.pdf
robotic2.docx
robotic2.docxrobotic2.docx
robotic2.docx
Mahamad Jawhar
 
Power Plant Engineering - (Malestrom) (1).pdf
Power Plant Engineering - (Malestrom) (1).pdfPower Plant Engineering - (Malestrom) (1).pdf
Power Plant Engineering - (Malestrom) (1).pdf
Mahamad Jawhar
 
ref3.pdf
ref3.pdfref3.pdf
ref3.pdf
Mahamad Jawhar
 
I-Section-US-1003.pdf
I-Section-US-1003.pdfI-Section-US-1003.pdf
I-Section-US-1003.pdf
Mahamad Jawhar
 
ref.pdf
ref.pdfref.pdf
lect 01 (1).pdf
lect 01 (1).pdflect 01 (1).pdf
lect 01 (1).pdf
Mahamad Jawhar
 
plasma cutting.pdf
plasma cutting.pdfplasma cutting.pdf
plasma cutting.pdf
Mahamad Jawhar
 
Grad. Proj. Poster Templete akam.docx
Grad. Proj. Poster Templete akam.docxGrad. Proj. Poster Templete akam.docx
Grad. Proj. Poster Templete akam.docx
Mahamad Jawhar
 
project format writting 2.docx
project format writting 2.docxproject format writting 2.docx
project format writting 2.docx
Mahamad Jawhar
 
PLC4.docx
PLC4.docxPLC4.docx
PLC4.docx
Mahamad Jawhar
 
PLC 1 (2).docx
PLC 1 (2).docxPLC 1 (2).docx
PLC 1 (2).docx
Mahamad Jawhar
 
final project1.docx
final project1.docxfinal project1.docx
final project1.docx
Mahamad Jawhar
 
project cooling tower.docx
project cooling tower.docxproject cooling tower.docx
project cooling tower.docx
Mahamad Jawhar
 
robotic.docx
robotic.docxrobotic.docx
robotic.docx
Mahamad Jawhar
 
report project.docx
report project.docxreport project.docx
report project.docx
Mahamad Jawhar
 
robotic lab.docx
robotic lab.docxrobotic lab.docx
robotic lab.docx
Mahamad Jawhar
 

More from Mahamad Jawhar (20)

text book Programmable-Logic-Controllers plc.pdf
text book Programmable-Logic-Controllers plc.pdftext book Programmable-Logic-Controllers plc.pdf
text book Programmable-Logic-Controllers plc.pdf
 
2.pdf
2.pdf2.pdf
2.pdf
 
3.pdf
3.pdf3.pdf
3.pdf
 
1.pdf
1.pdf1.pdf
1.pdf
 
robotic2.docx
robotic2.docxrobotic2.docx
robotic2.docx
 
Power Plant Engineering - (Malestrom) (1).pdf
Power Plant Engineering - (Malestrom) (1).pdfPower Plant Engineering - (Malestrom) (1).pdf
Power Plant Engineering - (Malestrom) (1).pdf
 
ref3.pdf
ref3.pdfref3.pdf
ref3.pdf
 
I-Section-US-1003.pdf
I-Section-US-1003.pdfI-Section-US-1003.pdf
I-Section-US-1003.pdf
 
ref.pdf
ref.pdfref.pdf
ref.pdf
 
lect 01 (1).pdf
lect 01 (1).pdflect 01 (1).pdf
lect 01 (1).pdf
 
plasma cutting.pdf
plasma cutting.pdfplasma cutting.pdf
plasma cutting.pdf
 
Grad. Proj. Poster Templete akam.docx
Grad. Proj. Poster Templete akam.docxGrad. Proj. Poster Templete akam.docx
Grad. Proj. Poster Templete akam.docx
 
project format writting 2.docx
project format writting 2.docxproject format writting 2.docx
project format writting 2.docx
 
PLC4.docx
PLC4.docxPLC4.docx
PLC4.docx
 
PLC 1 (2).docx
PLC 1 (2).docxPLC 1 (2).docx
PLC 1 (2).docx
 
final project1.docx
final project1.docxfinal project1.docx
final project1.docx
 
project cooling tower.docx
project cooling tower.docxproject cooling tower.docx
project cooling tower.docx
 
robotic.docx
robotic.docxrobotic.docx
robotic.docx
 
report project.docx
report project.docxreport project.docx
report project.docx
 
robotic lab.docx
robotic lab.docxrobotic lab.docx
robotic lab.docx
 

Recently uploaded

按照学校原版(Columbia文凭证书)哥伦比亚大学毕业证快速办理
按照学校原版(Columbia文凭证书)哥伦比亚大学毕业证快速办理按照学校原版(Columbia文凭证书)哥伦比亚大学毕业证快速办理
按照学校原版(Columbia文凭证书)哥伦比亚大学毕业证快速办理
uyesp1a
 
按照学校原版(SUT文凭证书)斯威本科技大学毕业证快速办理
按照学校原版(SUT文凭证书)斯威本科技大学毕业证快速办理按照学校原版(SUT文凭证书)斯威本科技大学毕业证快速办理
按照学校原版(SUT文凭证书)斯威本科技大学毕业证快速办理
1jtj7yul
 
一比一原版(Greenwich文凭证书)格林威治大学毕业证如何办理
一比一原版(Greenwich文凭证书)格林威治大学毕业证如何办理一比一原版(Greenwich文凭证书)格林威治大学毕业证如何办理
一比一原版(Greenwich文凭证书)格林威治大学毕业证如何办理
byfazef
 
按照学校原版(AU文凭证书)英国阿伯丁大学毕业证快速办理
按照学校原版(AU文凭证书)英国阿伯丁大学毕业证快速办理按照学校原版(AU文凭证书)英国阿伯丁大学毕业证快速办理
按照学校原版(AU文凭证书)英国阿伯丁大学毕业证快速办理
ei8c4cba
 
一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理
一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理
一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理
xuqdabu
 
按照学校原版(UST文凭证书)圣托马斯大学毕业证快速办理
按照学校原版(UST文凭证书)圣托马斯大学毕业证快速办理按照学校原版(UST文凭证书)圣托马斯大学毕业证快速办理
按照学校原版(UST文凭证书)圣托马斯大学毕业证快速办理
zpc0z12
 
按照学校原版(UVic文凭证书)维多利亚大学毕业证快速办理
按照学校原版(UVic文凭证书)维多利亚大学毕业证快速办理按照学校原版(UVic文凭证书)维多利亚大学毕业证快速办理
按照学校原版(UVic文凭证书)维多利亚大学毕业证快速办理
1jtj7yul
 
一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理
nudduv
 
按照学校原版(UAL文凭证书)伦敦艺术大学毕业证快速办理
按照学校原版(UAL文凭证书)伦敦艺术大学毕业证快速办理按照学校原版(UAL文凭证书)伦敦艺术大学毕业证快速办理
按照学校原版(UAL文凭证书)伦敦艺术大学毕业证快速办理
yizxn4sx
 
按照学校原版(QU文凭证书)皇后大学毕业证快速办理
按照学校原版(QU文凭证书)皇后大学毕业证快速办理按照学校原版(QU文凭证书)皇后大学毕业证快速办理
按照学校原版(QU文凭证书)皇后大学毕业证快速办理
8db3cz8x
 
1比1复刻澳洲皇家墨尔本理工大学毕业证本科学位原版一模一样
1比1复刻澳洲皇家墨尔本理工大学毕业证本科学位原版一模一样1比1复刻澳洲皇家墨尔本理工大学毕业证本科学位原版一模一样
1比1复刻澳洲皇家墨尔本理工大学毕业证本科学位原版一模一样
2g3om49r
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证如何办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证如何办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证如何办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证如何办理
peuce
 
按照学校原版(Birmingham文凭证书)伯明翰大学|学院毕业证快速办理
按照学校原版(Birmingham文凭证书)伯明翰大学|学院毕业证快速办理按照学校原版(Birmingham文凭证书)伯明翰大学|学院毕业证快速办理
按照学校原版(Birmingham文凭证书)伯明翰大学|学院毕业证快速办理
6oo02s6l
 
按照学校原版(UOL文凭证书)利物浦大学毕业证快速办理
按照学校原版(UOL文凭证书)利物浦大学毕业证快速办理按照学校原版(UOL文凭证书)利物浦大学毕业证快速办理
按照学校原版(UOL文凭证书)利物浦大学毕业证快速办理
terpt4iu
 
一比一原版(Monash文凭证书)莫纳什大学毕业证如何办理
一比一原版(Monash文凭证书)莫纳什大学毕业证如何办理一比一原版(Monash文凭证书)莫纳什大学毕业证如何办理
一比一原版(Monash文凭证书)莫纳什大学毕业证如何办理
xuqdabu
 
按照学校原版(Greenwich文凭证书)格林威治大学毕业证快速办理
按照学校原版(Greenwich文凭证书)格林威治大学毕业证快速办理按照学校原版(Greenwich文凭证书)格林威治大学毕业证快速办理
按照学校原版(Greenwich文凭证书)格林威治大学毕业证快速办理
yizxn4sx
 
一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理
xuqdabu
 
按照学校原版(USD文凭证书)圣地亚哥大学毕业证快速办理
按照学校原版(USD文凭证书)圣地亚哥大学毕业证快速办理按照学校原版(USD文凭证书)圣地亚哥大学毕业证快速办理
按照学校原版(USD文凭证书)圣地亚哥大学毕业证快速办理
snfdnzl7
 
一比一原版(KCL文凭证书)伦敦国王学院毕业证如何办理
一比一原版(KCL文凭证书)伦敦国王学院毕业证如何办理一比一原版(KCL文凭证书)伦敦国王学院毕业证如何办理
一比一原版(KCL文凭证书)伦敦国王学院毕业证如何办理
kuehcub
 
LORRAINE ANDREI_LEQUIGAN_GOOGLE CALENDAR
LORRAINE ANDREI_LEQUIGAN_GOOGLE CALENDARLORRAINE ANDREI_LEQUIGAN_GOOGLE CALENDAR
LORRAINE ANDREI_LEQUIGAN_GOOGLE CALENDAR
lorraineandreiamcidl
 

Recently uploaded (20)

按照学校原版(Columbia文凭证书)哥伦比亚大学毕业证快速办理
按照学校原版(Columbia文凭证书)哥伦比亚大学毕业证快速办理按照学校原版(Columbia文凭证书)哥伦比亚大学毕业证快速办理
按照学校原版(Columbia文凭证书)哥伦比亚大学毕业证快速办理
 
按照学校原版(SUT文凭证书)斯威本科技大学毕业证快速办理
按照学校原版(SUT文凭证书)斯威本科技大学毕业证快速办理按照学校原版(SUT文凭证书)斯威本科技大学毕业证快速办理
按照学校原版(SUT文凭证书)斯威本科技大学毕业证快速办理
 
一比一原版(Greenwich文凭证书)格林威治大学毕业证如何办理
一比一原版(Greenwich文凭证书)格林威治大学毕业证如何办理一比一原版(Greenwich文凭证书)格林威治大学毕业证如何办理
一比一原版(Greenwich文凭证书)格林威治大学毕业证如何办理
 
按照学校原版(AU文凭证书)英国阿伯丁大学毕业证快速办理
按照学校原版(AU文凭证书)英国阿伯丁大学毕业证快速办理按照学校原版(AU文凭证书)英国阿伯丁大学毕业证快速办理
按照学校原版(AU文凭证书)英国阿伯丁大学毕业证快速办理
 
一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理
一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理
一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理
 
按照学校原版(UST文凭证书)圣托马斯大学毕业证快速办理
按照学校原版(UST文凭证书)圣托马斯大学毕业证快速办理按照学校原版(UST文凭证书)圣托马斯大学毕业证快速办理
按照学校原版(UST文凭证书)圣托马斯大学毕业证快速办理
 
按照学校原版(UVic文凭证书)维多利亚大学毕业证快速办理
按照学校原版(UVic文凭证书)维多利亚大学毕业证快速办理按照学校原版(UVic文凭证书)维多利亚大学毕业证快速办理
按照学校原版(UVic文凭证书)维多利亚大学毕业证快速办理
 
一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理
 
按照学校原版(UAL文凭证书)伦敦艺术大学毕业证快速办理
按照学校原版(UAL文凭证书)伦敦艺术大学毕业证快速办理按照学校原版(UAL文凭证书)伦敦艺术大学毕业证快速办理
按照学校原版(UAL文凭证书)伦敦艺术大学毕业证快速办理
 
按照学校原版(QU文凭证书)皇后大学毕业证快速办理
按照学校原版(QU文凭证书)皇后大学毕业证快速办理按照学校原版(QU文凭证书)皇后大学毕业证快速办理
按照学校原版(QU文凭证书)皇后大学毕业证快速办理
 
1比1复刻澳洲皇家墨尔本理工大学毕业证本科学位原版一模一样
1比1复刻澳洲皇家墨尔本理工大学毕业证本科学位原版一模一样1比1复刻澳洲皇家墨尔本理工大学毕业证本科学位原版一模一样
1比1复刻澳洲皇家墨尔本理工大学毕业证本科学位原版一模一样
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证如何办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证如何办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证如何办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证如何办理
 
按照学校原版(Birmingham文凭证书)伯明翰大学|学院毕业证快速办理
按照学校原版(Birmingham文凭证书)伯明翰大学|学院毕业证快速办理按照学校原版(Birmingham文凭证书)伯明翰大学|学院毕业证快速办理
按照学校原版(Birmingham文凭证书)伯明翰大学|学院毕业证快速办理
 
按照学校原版(UOL文凭证书)利物浦大学毕业证快速办理
按照学校原版(UOL文凭证书)利物浦大学毕业证快速办理按照学校原版(UOL文凭证书)利物浦大学毕业证快速办理
按照学校原版(UOL文凭证书)利物浦大学毕业证快速办理
 
一比一原版(Monash文凭证书)莫纳什大学毕业证如何办理
一比一原版(Monash文凭证书)莫纳什大学毕业证如何办理一比一原版(Monash文凭证书)莫纳什大学毕业证如何办理
一比一原版(Monash文凭证书)莫纳什大学毕业证如何办理
 
按照学校原版(Greenwich文凭证书)格林威治大学毕业证快速办理
按照学校原版(Greenwich文凭证书)格林威治大学毕业证快速办理按照学校原版(Greenwich文凭证书)格林威治大学毕业证快速办理
按照学校原版(Greenwich文凭证书)格林威治大学毕业证快速办理
 
一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide文凭证书)阿德莱德大学毕业证如何办理
 
按照学校原版(USD文凭证书)圣地亚哥大学毕业证快速办理
按照学校原版(USD文凭证书)圣地亚哥大学毕业证快速办理按照学校原版(USD文凭证书)圣地亚哥大学毕业证快速办理
按照学校原版(USD文凭证书)圣地亚哥大学毕业证快速办理
 
一比一原版(KCL文凭证书)伦敦国王学院毕业证如何办理
一比一原版(KCL文凭证书)伦敦国王学院毕业证如何办理一比一原版(KCL文凭证书)伦敦国王学院毕业证如何办理
一比一原版(KCL文凭证书)伦敦国王学院毕业证如何办理
 
LORRAINE ANDREI_LEQUIGAN_GOOGLE CALENDAR
LORRAINE ANDREI_LEQUIGAN_GOOGLE CALENDARLORRAINE ANDREI_LEQUIGAN_GOOGLE CALENDAR
LORRAINE ANDREI_LEQUIGAN_GOOGLE CALENDAR
 

project cooling towers.docx

  • 1. 1 Mechanical Components -COLD WATER BASIN: Figure 2-1 One of the most critical cooling tower components is the cold water basin, which collects water and directs it to the sump or pump suction line. The aim of a cold water basin is to eliminate stagnant water and prevent bacteria from growing. They might even have heaters to keep the water from freezing in the event of a power outage. -FILLS: Figure 2-2
  • 2. 2 Another important component of cooling tower parts is fill material or fill media. This component is, in some ways, the most critical since it determines the cooling tower's efficiency. The rate of heat transfer between the cooling and working media is increased when the contact surface between them is greater. In cooling towers, the main purpose of fills is to raise the contact surface as much as possible. Fill media can be either of the film style type or splash style type. The film style fills, which is used in most cooling towers, produce thick water strips that increase the rate of heat transfer and also larger evaporation rates. splash style fills are commonly used in crossflow cooling towers in which water cascades down on staggered slats that breaks up water droplets to increase the water surface area. - Hot Water Distribution Basin: Figure 2-3 The (hot water) distribution basin is above the fills, which is where the hot process water collects. They cannot provide a proper flow distribution down the nozzles to be sprayed over the fills due to corrosion and degradation over time, resulting in considerable loss of thermal efficiency, and as a result, they are replaced to prevent such downfalls in the system's performance.
  • 3. 3 -NOZZLES: Figure 2-4 The nozzles are one of the cooling tower components that can be used in crossflow cooling towers. Water is lifted to the distribution basins and then cascaded back over the fill through the nozzles on the hot water basin floor in crossflow cooling towers. - Cooling Tower Float Valve: Figure2-5
  • 4. 4 Water within the tower must be kept at the correct level in order for it to function properly. Float valves, while needing only minor maintenance over time, have become one of the most important cooling tower components. Float valves regulate the water level and, when correctly calibrated, ensure that no water is lost when the pump shuts down in an overflow. - Drift Eliminators: Figure2-6 The drift eliminator is another important cooling tower component. This device's aim is to catch large water droplets in the cooling tower air stream and reduce process water loss. The eliminator directs moisture and water droplets away from the cooling tower and into another part of the system, stopping them from leaving. After that, the air and water will be separated and recycled for other purposes. Apart from the importance of preventing process water loss, the removal of these large water droplets is motivated by the fact that they contain chemicals and minerals that are considered harmful to the environment.
  • 5. 5 - Water Distribution Piping: Figure 2-7 Another critical cooling tower component is the water distribution piping system. Despite the fact that heat generation points are often located near cooling towers, the piping system routing and physical dimensions are determined by the type of tower, site configuration, and topography of the region in which the site is located. -COOLING TOWER FANS: Figure 2-8
  • 6. 6 A draft is generated by natural draft cooling towers without the use of any mechanical components. Fans are, however, an important component of mechanical draft, crossflow, and counterflow cooling towers. One of the factors to remember when it comes to fans is noise. Despite the fact that they are commonly known to be very noisy, some designs are available with lower noise levels while still being durable. -GEAR BOX: Figure 2-9 Towers with large fans for generating a draft often have gearboxes for changing the power exerted by the motor on the fan's driveshaft. The gearbox is one of the cooling tower components that reduces the expense of the mechanical system by not only changing the rotational speed of the pump but also serving as a torque multiplier, reducing the size of the motor required.
  • 7. 7 - Driveshafts: Figure 2-10 The driveshafts transmit the power produced by the motor to the gearbox, making it one of the cooling tower's most important components. It should be remembered that since the shaft is in direct contact with the cooling tower's internal environment, highly corrosion-resistant materials must be used in their manufacture. In the event of shaft run out, the driveshafts should be able to be easily recalibrated.