1 Project Title Combined Sewer Overflow PowAbbyWhyte974
1
Project Title: Combined Sewer Overflow Power Generation Project Report
Department of Mechanical and Construction Engineering
Northumbria University, Newcastle upon Tyne, NE18ST, United Kingdom
Module Title: MSc Advanced Practice
Module Code: KB7056
Author Name : ARATHI REDDY
Id : W20027842
Business Name
Company/business location
North East
Pity Me, Durham
2
Executive Summary
Combined Sewer Overflow Power Generation is a project aimed to determine a range of
power requirements for the environmental remediation solutions that could be implemented at
each CSO. Northumbria University students were tasked to completing the Combined Sewer
Overflow Power Generation, and this report provides them with the information they need to
guarantee that the project is successfully completed and managed. In order to accomplish this,
the report has produced Programs and Schedules that may be implemented to the project based
on the project's characteristics and the needs of the client. Because of this, the report established
Management of relevant training programs for the project based on the demands of the client,
including the requirement for early project delivery and regular client engagement in the project.
On the basis of this, the Northumbria student recommends the most relevant solutions to be
employed in the project, which it is believed will be most effective in achieving the largest
possible benefit for the client.
3
Introduction
The advanced practices semester will help a lot of things to lean in my upcoming projects and
real-time experiences. Each stage of work is very challenging for me and makes me give the best
output to the client and prove myself as the best. Mainly this semester teach me how to engage
the client and what type of work I have to be present in a real-time project, and how to engage in
the project phases and the engagement of work has expressed below.
How students engaged the work
Stage.1
The Northumbrian pupils showed a high level of enthusiasm for the task. The student’s
determination to do their best was evident in their demeanor and positive attitude, which all
indicated how they were going to approach the job. In order to participate in the project, the
students divided themselves into groups, with each group being assigned a specific aspect of the
work.
Stage.2
Each group was led by a group leader, whose primary responsibility was to ensure that the work
flowed smoothly. Each group was given a specific amount of time in which to complete their
tasks. The goal of establishing a time restriction for completion of the task was to ensure that the
entire project was completed on schedule.
Stage.3
The project manager was responsible for ensuring that the project was presented efficiently and
on time. The students devised four distinct steps for delivering high-quality project present ...
1
Project Title: Combined Sewer Overflow Power Generation Project Report
Department of Mechanical and Construction Engineering
Northumbria University, Newcastle upon Tyne, NE18ST, United Kingdom
Module Title: MSc Advanced Practice
Module Code: KB7056
Author Name : ARATHI REDDY
Id : W20027842
Business Name
Company/business location
North East
Pity Me, Durham
2
Executive Summary
Combined Sewer Overflow Power Generation is a project aimed to determine a range of
power requirements for the environmental remediation solutions that could be implemented at
each CSO. Northumbria University students were tasked to completing the Combined Sewer
Overflow Power Generation, and this report provides them with the information they need to
guarantee that the project is successfully completed and managed. In order to accomplish this,
the report has produced Programs and Schedules that may be implemented to the project based
on the project's characteristics and the needs of the client. Because of this, the report established
Management of relevant training programs for the project based on the demands of the client,
including the requirement for early project delivery and regular client engagement in the project.
On the basis of this, the Northumbria student recommends the most relevant solutions to be
employed in the project, which it is believed will be most effective in achieving the largest
possible benefit for the client.
3
Introduction
The advanced practices semester will help a lot of things to lean in my upcoming projects and
real-time experiences. Each stage of work is very challenging for me and makes me give the best
output to the client and prove myself as the best. Mainly this semester teach me how to engage
the client and what type of work I have to be present in a real-time project, and how to engage in
the project phases and the engagement of work has expressed below.
How students engaged the work
Stage.1
The Northumbrian pupils showed a high level of enthusiasm for the task. The student’s
determination to do their best was evident in their demeanor and positive attitude, which all
indicated how they were going to approach the job. In order to participate in the project, the
students divided themselves into groups, with each group being assigned a specific aspect of the
work.
Stage.2
Each group was led by a group leader, whose primary responsibility was to ensure that the work
flowed smoothly. Each group was given a specific amount of time in which to complete their
tasks. The goal of establishing a time restriction for completion of the task was to ensure that the
entire project was completed on schedule.
Stage.3
The project manager was responsible for ensuring that the project was presented efficiently and
on time. The students devised four distinct steps for delivering high-quality project present ...
<
Project Name
>
<
Date
>
<
Surrey College Library RefsdşflmdsşafnaşsRenovatipon
>
8/6/21
<
Surrey College Library RefsdşflmdsşafnaşsRenovatipon
>
8/6/21
1. PROJECT INFORMATION
Project Name
Project Code
The Surrey College Library Renovation Project
Sur-Ren-Lib/02
Project Sponsor
Project Manager
Surinder Kaur / Chief Librarian
MGMT 640-Team Four
Client Sponsor
Client PM
BC Ministry of Education
Library Board
Prepared By
Prepared On
MGMT 640-Team Four
Surrey College
Authorized By
Authorized On
Dr. Sharzad Khosravi
Surrey Library Renovation
2. PROJECT DESCRIPTION
Throughout the renovation of the first floor of the Surrey College Library, this project offers a unique and contemporary library design in the College Library, which is more enhanced energy-efficient and environment-friendly. It is also presumed to be extra supportive of research, artistic project, and society intercommunication.
3. PROJECT JUSTIFICATION/BUSINESS NEED
With a long history and impressive building, the library is a symbol structure of the college. Notwithstanding, it does not cope with the transformation of information retrieval practices in the current generation. It does not present a welcoming and user-friendly setting anymore because of its incapability of providing adequate computing workstation and multimedia devices and additional socializing features demanded by students and faculty. A philanthropic financial grant of a quarter a million CAD was given to the university library from the Ministry of Education, and the library board decided to use the donation on renovating the 1st floor of the College Library.
4. PROJECT OBJECTIVES
This project aims to develop a library design in the Surrey College Library to please library users’ knowledge retrieval routine in the modernized age. Its overall purpose is to improve productivity and enhance the study method for students and faculty in the current information era.5. PROJECT SUCCESS CRITERIA
· Meet users’ demands of computers and networks
· Encourage group inquiry and collaborative activity
· Plan suits the information retrieving practices of library users in the modernized time
· Boost study and research
· Building is energy-efficient and user-friendly
· Extra natural light is let inside the library.
· Users notice the increased area laptop friendly.
· Users detect the study places extremely useful and competent for group talks.
· Computing workstations are massively utilized by library users, and users determine the computers to run really effectively.
· Users notice the fresh location of reference and reserve spaces quite useful and proper for retrieval and discussion
6. HIGH LEVEL SCOPE
Project Exclusions/Out of Scope
· Relocation, circulation, and reference services related to the collections that are stored originally on the first floor
· The warming, cooling, also air conditioning systems of the library ...
Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...Caroline Bilet
Business Case developed during Project Management course at SKEMA Business School
Create a gym that uses the energy produced by the users to power itself
Ibrahim Abubakari, Caroline Bilet, Arthur Lanos, Thomas Leportier, Amelie Meppiel, Kristin Torin, Medhi Thadi
Outcome Based Education (OBE) - A practitioner's experienceRavindra Dastikop
In this webinar the presenter shares his experience of designing , developing and delivering an engineering course based on the principles of OBE. The webinar has two parts. In the first part, it will discuss the experience gained in delivering a OBE enabled course and the second part demonstrates how to implement the course on a cloud-based system that supports the entire life-cycle of implementing OBE process
Improving 180 Blackboard Sites in 180 Days - Christian King & Sandra Thwaites...Blackboard APAC
At many universities, the Blackboard subject site is the primary interface for the student learning experience. If the site is poorly organised, students do not know how to navigate the learning experience, such as when to engage with what content. If assessment criteria are minimally indicated, the quality of submissions suffers. If no tools are used to foster interaction, the learning experience becomes isolating. Conversely, when Bb sites are effectively designed and maintained, the quality of the student learning experience tends to be high. The quality of Bb sites varies across universities and within programs of study. Students who experience a well-designed site in their first semesters come to expect this standard in subsequent semesters.
Bond University thereby undertook a whole-of-university strategic priority project to improve 180 Bb subject sites in 180 days. Associate Deans (Learning & Teaching) in each faculty selected the sites. The initial quality of the sites varied, with many assessed as initially high quality, meaning that improvement meant moving from strength to strength and focusing on elements such as increasing elements of technology enhanced learning. The co-facilitators of this presentation are the academic developers who worked one-on-one with each of the participating academics. Therefore, from their perspectives, the key takeaways for attending delegates will be:
- Identification of challenges and stumbling blocks, as well as success strategies
- Checklists and professional development materials
- Illustration of before and after improvements as exemplars
- Ideas for increasing elements of technology enhanced learning
- Templates for emails, announcements and other communications
A brief introduction and overview of construction management and its application. A guidance for civil engineers teachers and students.
To get these slides please visit
http://www.xubitech.com/
Using recycled concrete aggregates (RCA) for pavements is crucial to achieving sustainability. Implementing RCA for new pavement can minimize carbon footprint, conserve natural resources, reduce harmful emissions, and lower life cycle costs. Compared to natural aggregate (NA), RCA pavement has fewer comprehensive studies and sustainability assessments.
1 Project Title Combined Sewer Overflow PowAbbyWhyte974
1
Project Title: Combined Sewer Overflow Power Generation Project Report
Department of Mechanical and Construction Engineering
Northumbria University, Newcastle upon Tyne, NE18ST, United Kingdom
Module Title: MSc Advanced Practice
Module Code: KB7056
Author Name : ARATHI REDDY
Id : W20027842
Business Name
Company/business location
North East
Pity Me, Durham
2
Executive Summary
Combined Sewer Overflow Power Generation is a project aimed to determine a range of
power requirements for the environmental remediation solutions that could be implemented at
each CSO. Northumbria University students were tasked to completing the Combined Sewer
Overflow Power Generation, and this report provides them with the information they need to
guarantee that the project is successfully completed and managed. In order to accomplish this,
the report has produced Programs and Schedules that may be implemented to the project based
on the project's characteristics and the needs of the client. Because of this, the report established
Management of relevant training programs for the project based on the demands of the client,
including the requirement for early project delivery and regular client engagement in the project.
On the basis of this, the Northumbria student recommends the most relevant solutions to be
employed in the project, which it is believed will be most effective in achieving the largest
possible benefit for the client.
3
Introduction
The advanced practices semester will help a lot of things to lean in my upcoming projects and
real-time experiences. Each stage of work is very challenging for me and makes me give the best
output to the client and prove myself as the best. Mainly this semester teach me how to engage
the client and what type of work I have to be present in a real-time project, and how to engage in
the project phases and the engagement of work has expressed below.
How students engaged the work
Stage.1
The Northumbrian pupils showed a high level of enthusiasm for the task. The student’s
determination to do their best was evident in their demeanor and positive attitude, which all
indicated how they were going to approach the job. In order to participate in the project, the
students divided themselves into groups, with each group being assigned a specific aspect of the
work.
Stage.2
Each group was led by a group leader, whose primary responsibility was to ensure that the work
flowed smoothly. Each group was given a specific amount of time in which to complete their
tasks. The goal of establishing a time restriction for completion of the task was to ensure that the
entire project was completed on schedule.
Stage.3
The project manager was responsible for ensuring that the project was presented efficiently and
on time. The students devised four distinct steps for delivering high-quality project present ...
1
Project Title: Combined Sewer Overflow Power Generation Project Report
Department of Mechanical and Construction Engineering
Northumbria University, Newcastle upon Tyne, NE18ST, United Kingdom
Module Title: MSc Advanced Practice
Module Code: KB7056
Author Name : ARATHI REDDY
Id : W20027842
Business Name
Company/business location
North East
Pity Me, Durham
2
Executive Summary
Combined Sewer Overflow Power Generation is a project aimed to determine a range of
power requirements for the environmental remediation solutions that could be implemented at
each CSO. Northumbria University students were tasked to completing the Combined Sewer
Overflow Power Generation, and this report provides them with the information they need to
guarantee that the project is successfully completed and managed. In order to accomplish this,
the report has produced Programs and Schedules that may be implemented to the project based
on the project's characteristics and the needs of the client. Because of this, the report established
Management of relevant training programs for the project based on the demands of the client,
including the requirement for early project delivery and regular client engagement in the project.
On the basis of this, the Northumbria student recommends the most relevant solutions to be
employed in the project, which it is believed will be most effective in achieving the largest
possible benefit for the client.
3
Introduction
The advanced practices semester will help a lot of things to lean in my upcoming projects and
real-time experiences. Each stage of work is very challenging for me and makes me give the best
output to the client and prove myself as the best. Mainly this semester teach me how to engage
the client and what type of work I have to be present in a real-time project, and how to engage in
the project phases and the engagement of work has expressed below.
How students engaged the work
Stage.1
The Northumbrian pupils showed a high level of enthusiasm for the task. The student’s
determination to do their best was evident in their demeanor and positive attitude, which all
indicated how they were going to approach the job. In order to participate in the project, the
students divided themselves into groups, with each group being assigned a specific aspect of the
work.
Stage.2
Each group was led by a group leader, whose primary responsibility was to ensure that the work
flowed smoothly. Each group was given a specific amount of time in which to complete their
tasks. The goal of establishing a time restriction for completion of the task was to ensure that the
entire project was completed on schedule.
Stage.3
The project manager was responsible for ensuring that the project was presented efficiently and
on time. The students devised four distinct steps for delivering high-quality project present ...
<
Project Name
>
<
Date
>
<
Surrey College Library RefsdşflmdsşafnaşsRenovatipon
>
8/6/21
<
Surrey College Library RefsdşflmdsşafnaşsRenovatipon
>
8/6/21
1. PROJECT INFORMATION
Project Name
Project Code
The Surrey College Library Renovation Project
Sur-Ren-Lib/02
Project Sponsor
Project Manager
Surinder Kaur / Chief Librarian
MGMT 640-Team Four
Client Sponsor
Client PM
BC Ministry of Education
Library Board
Prepared By
Prepared On
MGMT 640-Team Four
Surrey College
Authorized By
Authorized On
Dr. Sharzad Khosravi
Surrey Library Renovation
2. PROJECT DESCRIPTION
Throughout the renovation of the first floor of the Surrey College Library, this project offers a unique and contemporary library design in the College Library, which is more enhanced energy-efficient and environment-friendly. It is also presumed to be extra supportive of research, artistic project, and society intercommunication.
3. PROJECT JUSTIFICATION/BUSINESS NEED
With a long history and impressive building, the library is a symbol structure of the college. Notwithstanding, it does not cope with the transformation of information retrieval practices in the current generation. It does not present a welcoming and user-friendly setting anymore because of its incapability of providing adequate computing workstation and multimedia devices and additional socializing features demanded by students and faculty. A philanthropic financial grant of a quarter a million CAD was given to the university library from the Ministry of Education, and the library board decided to use the donation on renovating the 1st floor of the College Library.
4. PROJECT OBJECTIVES
This project aims to develop a library design in the Surrey College Library to please library users’ knowledge retrieval routine in the modernized age. Its overall purpose is to improve productivity and enhance the study method for students and faculty in the current information era.5. PROJECT SUCCESS CRITERIA
· Meet users’ demands of computers and networks
· Encourage group inquiry and collaborative activity
· Plan suits the information retrieving practices of library users in the modernized time
· Boost study and research
· Building is energy-efficient and user-friendly
· Extra natural light is let inside the library.
· Users notice the increased area laptop friendly.
· Users detect the study places extremely useful and competent for group talks.
· Computing workstations are massively utilized by library users, and users determine the computers to run really effectively.
· Users notice the fresh location of reference and reserve spaces quite useful and proper for retrieval and discussion
6. HIGH LEVEL SCOPE
Project Exclusions/Out of Scope
· Relocation, circulation, and reference services related to the collections that are stored originally on the first floor
· The warming, cooling, also air conditioning systems of the library ...
Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...Caroline Bilet
Business Case developed during Project Management course at SKEMA Business School
Create a gym that uses the energy produced by the users to power itself
Ibrahim Abubakari, Caroline Bilet, Arthur Lanos, Thomas Leportier, Amelie Meppiel, Kristin Torin, Medhi Thadi
Outcome Based Education (OBE) - A practitioner's experienceRavindra Dastikop
In this webinar the presenter shares his experience of designing , developing and delivering an engineering course based on the principles of OBE. The webinar has two parts. In the first part, it will discuss the experience gained in delivering a OBE enabled course and the second part demonstrates how to implement the course on a cloud-based system that supports the entire life-cycle of implementing OBE process
Improving 180 Blackboard Sites in 180 Days - Christian King & Sandra Thwaites...Blackboard APAC
At many universities, the Blackboard subject site is the primary interface for the student learning experience. If the site is poorly organised, students do not know how to navigate the learning experience, such as when to engage with what content. If assessment criteria are minimally indicated, the quality of submissions suffers. If no tools are used to foster interaction, the learning experience becomes isolating. Conversely, when Bb sites are effectively designed and maintained, the quality of the student learning experience tends to be high. The quality of Bb sites varies across universities and within programs of study. Students who experience a well-designed site in their first semesters come to expect this standard in subsequent semesters.
Bond University thereby undertook a whole-of-university strategic priority project to improve 180 Bb subject sites in 180 days. Associate Deans (Learning & Teaching) in each faculty selected the sites. The initial quality of the sites varied, with many assessed as initially high quality, meaning that improvement meant moving from strength to strength and focusing on elements such as increasing elements of technology enhanced learning. The co-facilitators of this presentation are the academic developers who worked one-on-one with each of the participating academics. Therefore, from their perspectives, the key takeaways for attending delegates will be:
- Identification of challenges and stumbling blocks, as well as success strategies
- Checklists and professional development materials
- Illustration of before and after improvements as exemplars
- Ideas for increasing elements of technology enhanced learning
- Templates for emails, announcements and other communications
A brief introduction and overview of construction management and its application. A guidance for civil engineers teachers and students.
To get these slides please visit
http://www.xubitech.com/
Using recycled concrete aggregates (RCA) for pavements is crucial to achieving sustainability. Implementing RCA for new pavement can minimize carbon footprint, conserve natural resources, reduce harmful emissions, and lower life cycle costs. Compared to natural aggregate (NA), RCA pavement has fewer comprehensive studies and sustainability assessments.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
1. Republic of the Philippines
APAYAO STATE COLLEGE
Conner, Apayao
INFRASTRUCTURE DEVELOPMENT UNIT
Page 1 of 7
PROJECT BRIEF
1. PROJECT TITLE: CONTINUATION OF THREE STOREY LIVELIHOOD AND
FOOD TECHNOLOGY BUILDING, PHASE II
2. PROJECT TYPE: BUILDING CONSTRUCTION
3. PROPONENT
3.1 TYPE: STATE UNIVERSITIES AND COLLEGES (SUCs)
3.2 NAME: APAYAO STATE COLLEGE
3.3 ADDRESS: MALAMA, CONNER, APAYAO
4. COVERAGE
4.1 LOCATION:
4.1.1 The proposed project is a continuation of the Livelihood and Food
Technology Building.
4.2 The completion of the building structure is intended to provide adequate
classrooms, smart lecture rooms and laboratory rooms for the programs
located in the Main Campus.
5. DURATION
5.1 Project Identification: The project is identified as one among the priority
needs in terms of physical development for ASC through cost determination,
space/lot availability appraisal, and establishment of the project viability
through this feasibility study. The duration for the aforementioned activities
take about a month.
5.2 Pre-implementation Phase: The necessary activities to be undertaken before
implementation are the following: pre-detailed engineering surveys; design
and drawings development; detailed architectural and engineering design;
acquisition of relevant permits and clearances; and the bidding process. This
particular phase on this project will take a duration of six (6) months.
However for this particular project, all activities herein mentioned
2. Republic of the Philippines
APAYAO STATE COLLEGE
Conner, Apayao
INFRASTRUCTURE DEVELOPMENT UNIT
Page 2 of 7
pertaining to pre-implementation phase have been fulfilled except
for the bidding process for which strict observance of RA 9184 is
needed.
5.3 Implementation phase: As prescribed by law, contract implementation
guidelines for procurement of infrastructure projects shall comply with Annex
E of the revised Implementing Rules and Regulations of the Republic Act
9184. Complete documentation, quality controls procedures as well as
periodic consultation with the contractors shall be persistently carried out.
The estimated number of days to finish the project is 180 Calendar Days.
5.4 Post-completion: After the building structure has been fully finished, the
project will be handed to the General Services Unit of the College in order to
sustain its serviceability and to include in the preventive maintenance
program of all building structures in the campus.
6. FUNDING REQUIREMENT
6.1 COST OF CONSTRUCTION: Php 14,550,000.00
6.2 ENGINEERING AND ADMINISTRATIVE
SERVICES: Php 450,000.00
6.3 TOTAL PROJECT COST: Php 15,000,000.00
7. CONTACT PERSON
7.1 NAME & POSITION :NELIA Z. CAUILAN, PhD. – SUC President II
7.2 ADDRESS :MALAMA, CONNER, APAYAO
7.3 MOBILE PHONE NO. :(0917) 165 6059
7.4 E-MAIL ADDRESS :nel_cauilan08@yahoo.com
8. THE PROJECT
8.1 JUSTIFICATION
Adherence to educational standards along with religiosity in achieving
such bespeaks a culture of quality and excellence not only through the
performance of students but its impact to rural development and poverty
alleviation. While the academic sector of the college pushes to elevate its bar
of performance, necessary instructional facilities including building structures
should be made available to students and faculty. Pushing for a higher level
of accreditation, the BSE Program and other programs in the Main Campus
3. Republic of the Philippines
APAYAO STATE COLLEGE
Conner, Apayao
INFRASTRUCTURE DEVELOPMENT UNIT
Page 3 of 7
have been qualified for Level three and two stages of evaluation which
require more learning facilities and structures.
With this additional infrastructure project, these different programs
will be able to meet the demands and needs of students as well as to comply
with the minimum requirements forwarded by external partners in quality
assurance.
8.2 PROJECT DESCRIPTION
This proposal covers work items to continue the construction of Three
Storey College of Teacher Education Building which include: Structural
Concrete (Columns, Beams, Slab), CHB Works, Rebar Works, Plastering,
Painting and Tileworks.
8.3 OBJECTIVES
The project aims to elevate the bar of performance of the College and
to address the AACCUP and COPC findings and recommendations,
specifically:
8.3.1 to construct a safe, sound and spacious structure as support
facility in the attainment of the goals and objectives of the
different programs in the Main Campus;
8.3.2 to provide and establish permanent and conducive classrooms
and office rooms for efficient and effective delivery of services;
and
8.3.3 to improve academic and board examination performance.
8.4 EXPECTED OUTPUT
8.4.1 Finished Ground Floor of the building accommodating the
following:
8.4.1.1 Classrooms;
8.4.1.2 Laboratory; and
8.4.1.3 Faculty Room.
4. Republic of the Philippines
APAYAO STATE COLLEGE
Conner, Apayao
INFRASTRUCTURE DEVELOPMENT UNIT
Page 4 of 7
8.5 IMPLEMENTATION SCHEDULE
ACTIVITY
YEARS BY QUARTER
2021 2022
1 2 3 4 1 2 3 4
Reprogramming (to fit
exact budget released
by the DBM as reflected
in the NEP)
Bidding
Securing of Building
Permits and other
relevant clearances
Construction stage
Turn-over
8.6 TECHNICAL FEASIBILITY
Risk assessment is a very important part of a project activity. Project
delays are always a concern especially on a project that involves construction.
In cases such as this, risk reduction is one of the key points to be able to
make an activity a success. It is a very important determination factor on
what hazards are available and how to possibly mitigate them. With proper
risk assessment and risk management, a more successful outcome in any
activity may be attainable.
Below are possible risk that may occur prior and during the
implementation of the project:
No. RISK
DEGREE
OF RISK
RISK CONTROL
1 Delayed procurement
process Low
Procurement process shall be done at
the last quarter of the current year
(2021)
5. Republic of the Philippines
APAYAO STATE COLLEGE
Conner, Apayao
INFRASTRUCTURE DEVELOPMENT UNIT
Page 5 of 7
2 Failure of Bidding
Low
Conduct Pre-Bid Conference with
100% attendance of prospect
bidders in order to discuss
requirements set by the BAC.
3 Availability of
Construction Materials Low
Ensure availability of construction
materials within the locality or Region
2.
4 Delayed project
implementation due to
slippage by the
contractor
low
Assignment of Project –In – Charge
per project; Hiring of additional
manpower to reinforce supervision.
5 Delayed project
implementation due to
natural phenomenon
Medium
Strategic scheduling of project
implementation considering the
climatic weather condition of the
Province of Apayao.
8.7 OPERATIONAL FEASIBILITY
The Apayao State College maintains an Infrastructure Development
Unit that overseas the construction of buildings and other facilities in the
college. This is headed by the Director of Infrastructure Development. An
independent monitoring and evaluation committee under the Office of the
President is placed to provide a check and balance in the implementation of
the infrastructure and other projects.
The Infrastructure Unit prepares all the necessary plans and programs
of work of all proposed buildings for construction and approved by the
College President. Meanwhile, when funding is provided, the infrastructure
unit shall implement the project and supervise the construction and
implementation. In every phase of the construction work, the monitoring and
evaluation committee shall monitor and evaluate the progress of the
construction and submit reports and recommendations to the President.
The personnel involved in the operations of the Infrastructure unit are
qualified and licensed engineers.
With the present structure, the college is capable of implementing
infrastructure projects like construction of buildings and the like. Problems
6. Republic of the Philippines
APAYAO STATE COLLEGE
Conner, Apayao
INFRASTRUCTURE DEVELOPMENT UNIT
Page 6 of 7
that may arise during the implementation of the project are immediately
resolved.
8.8 THE COST – BENEFIT ANALYSIS
The proposed project has a total amount of Fifteen Million Pesos (Php
15,000,000.00) for a construction period of almost six months. Since the
implementation is done by phase, consideration for the cost – benefit analysis
will be limited to the scope of works covered by this project. With the
increasing number of enrolment at the Conner Campus and the serviceability
of the proposed project, the following are the assumptions:
1. The average number of students who will utilize the facility for the
first three years after completion is One Thousand Seven Hundred
Fifty (1,750);
2. The average Tuition Fee (excluding other fees) per student per
semester is Php 3,000.00 and the average tuition fee per student
in one year would be Php 6,000.00;
3. The enrolement projections after the completion of the project:
4. The tuition fee per student shall remain to be php 3,000.00 per
semester after the completion of the project.
Comparison of Cost and Benefits (In Million Pesos)
Year Cost
Cumulative
Total
Benefit
Cumulative
Total
1 Php 15,000.00 Php 15,000.00 Php 0.00
2 Php 0.00 Php 6,000.00
3 Php 0.00 Php 9,000.00 Php 15,000.00
4 Php 0.00 Php 12,000.00 Php 27,000.00
Year Projected Enrolment
2 1,000
3 1,500
4 2,000
5 2,500
Average 1,750
7. Republic of the Philippines
APAYAO STATE COLLEGE
Conner, Apayao
INFRASTRUCTURE DEVELOPMENT UNIT
Page 7 of 7
5 Php 0.00 Php 15,000.00 Php 42,000.00
Based on the above table, the total cost of Php 15,000,000.00 can be possibly
recovered on the 5th
year after the project has completed with a total benefit cost
of Php 42,000,000.00. Hence, the project will continue to earn benefits onwards.
8.9 RECOMMENDATION
Taking into consideration the technical, operational and cost benefit
analysis/feasibilities, the proposed project is feasible and can be funded for
implementation.
Prepared and Submitted by: