Project Management Final Report
Fall 2012 – SKEMA Raleigh
Table of content

Part I

Project Plan
A. Project Charter / Scope statement
1. Objectives of the project, requirements definition and constraints
2 Stakeholder analysis
3. Keys to success
B.

C.

Part II

Project Definition
1. Solution/ work product description
2. Work Breakdown Structure
3. High Level schedule
4. Network Diagram and Critical Path
5. List of Milestones and Dependencies including dates
6. Risk Assessment / Response
Finalized schedule
1. Resource requirements and resolution of resource allocation problems
2. Rolled up budget estimates

Project Update
A. Status report
1. Narrative of key events to date
2. Performance indices
3. Project schedule status
B.

Problem solving
1. Description of key problems and issues encountered
2. Responses to the problems and how they affected the project

C.

Management issues
1. Problem description
2. Responses to the issues and how the responses impacts the rest of the project

D.

Revised project estimates
1. Projected cost
2. Schedule

E.

Summary
1. Keys to successfully completing the project
2. Forecast at completion
3. Formal statement of confidence and risk

2
Part I Project Plan
A. Project Charter/Scope statement
1. Objectives of the project, requirements definition and constraints

Project concept
North Carolina State University has recently launched a vast project of transforming the campus into
a green university. The first steps implemented were passive measures such as turning off heating in
unoccupied buildings during holidays. Now NCSU governance is looking for a more proactive way in
order to be awarded “green campus of 2014”. This is why we have been contacted by NCSU in order
to turn Carmichael complex into a sustainable sport center. Our concept is simple: the energy
developed by students while working out on cardio equipments such as dynamo bikes and treadmills
will be transformed into electricity and used for the gymnasium power needs.

Project boundaries
In order to be clear with our stakeholders with what we are responsible for as part of this project, we
have established the following boundaries:

IN
•

Buy, install and connect the
equipment in one fitness
room
• Ensure that there are actual
savings of energy
• Communicate with
stakeholders on the
progresses made

OUT
•

Daily maintenance and
functioning
• Communication on the
modernization to end users
• Student reward system
(incentives to come to the
new gym)

Our job will be restricted to the procurement and installation of new bikes and treadmills able to
produce a quantity of electricity significant enough to reduce the electricity bills of the complex. In
order to do so, we will first do a feasibility studies and benchmarking of suppliers. Then we will take
care of all necessary modifications to be done to the room before installing the new fitness
equipment. It is our responsibility to ensure that bikes and treadmills will generate energy savings.
However, it is not our responsibility to ensure the daily maintenance once the equipment is ready to
use. We won’t be in charge of the communication within NCSU community about this renovation. In
addition, we thought about a system of student reward based on the electricity they will produce in
order to create new incentives for students to go to the gym. However, it is not included in the
current scope. If our stakeholders which to implement this additional time and/or budget must be
allocated.

3
Project objectives
We have two quantifiable objectives to measure the success of our project:
-

Electricity bill must be reduced by 30%
The number of users should also increase by 15%

Project requirements and constraints
While progressing through our project, we have to take into account several requirements and
constraints set by NCSU.
Our requirements are:
-

-

-

-

Keep the existing building. It is impossible to undertake renovation work such as increasing
the size of the fitness room. The building and walls must stay as they are now. Hence we
need to carefully execute the feasibility study in order to have the new equipment fitting
100% to the existing room.
Preserve the users’ experience during modernization process. We should try to minimize the
disturbance caused to gym users during our project. To do so, most of the work will be done
during summer holidays when most of students are not on campus. In addition, our project is
to renovate only one fitness rooms. To other rooms with similar equipments are still
available during the project.
Users should be able to monitor their energy production. It is nice to say to users that they
are producing electricity but it is even better to show them exactly how much they produced.
This will be a new source of motivation for doing exercise and will help to achieve the
increase in number of user. This will have to be taken into account when ordering the
equipment.
Modernized rooms should be able to gain environmental accreditation. The production of
green electricity must be significant enough for the building to be considered as eco-friendly.
This goes along with the objective the University to gain the label of “green campus of 2014”.

In addition to these requirements, we have to deal with the following constraints:
-

-

Make real energy savings (performance). As we said above, the bottom line of the project
really is to produce electricity.
Costs have to stay reasonable. The cost of our project if part of a bigger budget released by
NCSU for their green campus program. It is considered as one of the top priority project for
the University. Hence the funds available are fairly important but costs have to be optimized.
Modernization has to be limited in time (3 to 4 months). The new room must be open during
the first few month of fall semester in order to be available during most of the scholar year.

4
Project Matrix - Time, cost, performance trade-off assessment
Based on these constraints, we have established our project priority matrix:

Time
Constraint

Cost

X

Enhance
Accept

Performance

X
X

Performance is the key for this project. The equipment must produce enough electricity to be used
into the Carmichael complex for us to attain our objectives.
Cost must be enhanced. Our project is part of a bigger one within the University who is conducting
several other projects. So far budget has been allocated to most of these NCSU projects so the
University is limited in terms of releasing additional budget. In addition, NCSU cannot increase too
much tuition fees in order to finance the project. Also, alumni donations are limited.
The project’s duration is accepted. Still the project should avoid large delays but in the hypotheses it
will happen and the room will be closed for longer than expected, 2 other rooms are still available.

5
2. Stakeholder analysis

The chart below provides a global view of our project and its stakeholders.

We have identified 5 major stakeholders on our project:
-

-

-

NCSU Governance: our sponsor for this project. Without them the project won’t exists since
they provide the budget for it. They champion the project and are a major spokesperson to
promote it. They play a crucial role for our project, especially during early phases of scope
development.
Carmichael staff: is also an important stakeholder. The project is done under their
supervision since it will be done inside the building. Also, they will provide us empty rooms
for the storage of equipments free of charge.
Student Body: It will play a key role as voice of the students as it represents our end users. It
has a much smaller authority on the project than the previous two stakeholders.
Student (end users): One of the objectives of our project is also to please students. Their
comments should also be taken into account.
Alumni network: To some extent, alumni are also a distant stakeholder. They are
ambassadors of the University and will contribute to develop the green image of NCSU
outside the campus. Some of their contributions will also fund the upgrading of the
Carmichael Gym.

6
3. Keys to success

Technological Performance
The first key to success of this project is to assure and deliver the expected performance in terms of
electricity production. NCSU is investing money on this project not only to build a better image but
to also have real and measurable gains. Thus, we have go in-depth during the preliminary studies in
order to be sure to comply with our energy savings objectives.

Time management
In addition, time management is important and requires to carefully planning the project schedule.
We can’t afford to accumulate delays during the project and deliver the room in November would be
considered as a failure. Indeed, we will have not preserved the end-users experience of the gym.

Communication with stakeholders
Last but not least, communication with stakeholders is crucial, in particular with our sponsor at the
beginning of the project when elaborating the scope and all necessary documentations. Reports
must be done on a regular basis for the stakeholders to follow how the project is progressing. It
should also be done for important steps such as ordering the equipment (a major post of cost) or
beginning the installation.

B. Project definition
1. Solution / work product description

To begin the GreenWulf project, 3 sets of deliverables were designed to guide the project team in
meeting the objectives and expectation of this project.
First on the list of deliverables is the Feasibility study. In this stage, the team conducts preliminary
studies and report about the project. We research about energy (present consumption of the sports
complex and about renewable energy), provide a cost analysis of the project and look at technical
feasibility studies and the fall out studies.
Second deliverable is the Benchmarking documentation for the equipments. After searching for
equipment suppliers and select some of them, order quotes, we will present a summary for review to
the NCSU team.
We finish with the project completion which happens after testing has been done both by Green
Wulf and the end users and a period of review and acceptance 7 days after the launch of the fitness
room.

7
2. Work breakdown structure

WBS

Nom de la tâche

1.0
GreenWulf Project
1.1
Feasibility studies
1.1.1
Preliminary Studies
1.1.1.1
Energy Study
1.1.1.2
Costing
1.1.1.3
Technical feasibility Study
1.1.1.4
Fallout study (project Benefits)
1.1.2
Preliminary report
1.2
Fitness Equipment
1.2.1
Benchmarking
1.2.1.1
Supplier search
1.2.1.2
Quote requests
1.2.1.3
Supplier selection
1.2.1.4
Banchmarking documentation
1.2.2
Fitness Equipment order
1.2.3
Fitness equipment reception
1.2.3.1
Bikes reception
1.2.3.2
Treadmills reception
1.2.3.3
Equipment Storage
1.3
Equipment intallation
1.3.1
Old equipment tranfer
1.3.1.1
Removal of old equipment
1.3.1.2
Disposal of old equipment
1.3.1.3
Room cleaning
1.3.2
New equipment set-up
1.3.2.1
Equipment Installation
1.3.2.2
Electrical installation
1.3.2.2.1
Layering
1.3.2.2.2
Electrical wiring
1.3.3
Room cleaning
1.4
Closure of the project
1.4.1
Testing by Greenwulf
1.4.2
Testing by Stakeholders
1.4.3
Lauch
1.4.4
Review and acceptance

Duration

Start

Finish

65,43 days
17 days
10 days
10 days
4 days
7 days
2 days
7 days
33 days
11 days
5 days
2 days
2 days
2 days
21 days
1 day
3 hrs
3 hrs
1 day
6,43 days
1,14 days
3 hrs
3 hrs
2 hrs
5 days
1 day
4 days
2 days
2 days
2 hrs
9 days
1 day
1 day
1 day
1 day

Mon 03/06/13
Mon 03/06/13
Mon 03/06/13
Mon 03/06/13
Mon 03/06/13
Mon 03/06/13
Mon 03/06/13
Mon 17/06/13
Wed 26/06/13
Wed 26/06/13
Wed 26/06/13
Wed 03/07/13
Mon 08/07/13
Wed 10/07/13
Fri 12/07/13
Mon 12/08/13
Mon 12/08/13
Mon 12/08/13
Mon 12/08/13
Tue 13/08/13
Tue 13/08/13
Tue 13/08/13
Tue 13/08/13
Tue 13/08/13
Wed 14/08/13
Wed 14/08/13
Thu 15/08/13
Thu 15/08/13
Mon 19/08/13
Wed 21/08/13
Wed 21/08/13
Wed 21/08/13
Thu 22/08/13
Fri 23/08/13
Tue 03/09/13

Wed 04/09/13
Tue 25/06/13
Fri 14/06/13
Fri 14/06/13
Thu 06/06/13
Tue 11/06/13
Tue 04/06/13
Tue 25/06/13
Mon 12/08/13
Thu 11/07/13
Tue 02/07/13
Fri 05/07/13
Tue 09/07/13
Thu 11/07/13
Fri 09/08/13
Mon 12/08/13
Mon 12/08/13
Mon 12/08/13
Mon 12/08/13
Wed 21/08/13
Wed 14/08/13
Tue 13/08/13
Tue 13/08/13
Wed 14/08/13
Wed 21/08/13
Thu 15/08/13
Wed 21/08/13
Mon 19/08/13
Wed 21/08/13
Wed 21/08/13
Wed 04/09/13
Thu 22/08/13
Fri 23/08/13
Mon 26/08/13
Wed 04/09/13

We have divided the Green Wulf project in 4 main subprojects: Feasibility studies ending with the
preliminary report, Fitness equipment which contains the suppliers benchmarking process and the
equipment order, Equipment installation including also electrical installation and project closure with
testing and acceptance by end users.

8
3. High Level schedule

The picture above shows the complete Gantt chart for the initial project. We can see that most of
tasks cannot be done simultaneously. The only period when we have a bit of slack is at the very
beginning with the preliminary studies.

4. Network Diagram and Critical Path

The picture below gives a global view of the Network Diagram and critical path (for a more precise
one showing name of tasks, please refer to the MS project file). As we can see, on 24 tasks, only 5 are
not critical. Thus we can say that our project is very sensitive and any delay in one task will delay the
entire project. This can be explained by the nature of the work performed during the project. For
example the electrical installation tasks of layering and wiring can’t be done before the equipment is
installed in the room.

9
10
5. List of Milestones and Dependencies

Milestone
Preliminary report 1.1.2

Dates
Mon 17/06/13 – Tue
25/06/13(7 days)
Wed 10/07/13 - Thu 11/07/13
(2 Days)
Mon 12/08/13 (1 Day)

Benchmarking documentation
1.2.1.4
Fitness Equipment reception
1.2.3
Electrical wiring 1.3.2.2.2

Mon 19/08/13 - Wed 21/08/13
(2 Day)
Wed 21/08/13 – Thu 22/08/13
(1 Day)

Testing by GreenWulf 1.4.1

Preliminary report is our first milestone. It is the result of all our research and will condition the
entire project especially the requirements for the equipment that will be used for the selection of
suppliers. This brings us to the second milestone, the benchmarking documentation. It is crucial that
we order the good equipment, without that the project will be a failure. For these 2 first milestones,
communication with our sponsor will be important.
The third one is the fitness equipment reception after delivery. We need to check that the equipment
is not damaged and match the order. All the installation will depend on good reception of the
equipment.
The fourth milestone is electrical wiring, the last task in terms of installation. We will be able to check
if the installation has been done properly and that we are ready for testing the equipment.
Testing by Green Wulf is our last milestone. This is the last task were we can potentially readjust the
equipment before opening.
6. Risk Assessment / Response
A major project of like this can be accompanied by certain amount of unforeseen risks, so we came
up with this risk analysis of the GreenWulf project and its remedies:
RISK ASSESSMENT FORM
Risk event

Likelihood

Impact

Accident/injuries
Technical hitches
Bad reviews
Lack of funds

5
4
2
3

4
3
4
5

Detection
difficulty
5
4
3
3

Total
100
48
24
45

11
RISK RESPONSE FORM
Risk event

Response

Contingency plan

Trigger

Accident/injuries

Reduce

Technical hitches

Refer

Fall, cuts &
electric shock
Power cuts

Bad reviews

Reduce

Equipment
malfunction

Transfer

First aid assistant
present
Technical
assistant
Regular report to
stakeholders
Technical
assistant then if
too serious,
Reorder
equipments

Criticisms during
end-user testing
Equipment
doesn’t work

Who is
responsible
Thomas
Ibrahim
Camille
Amélie

Based on this risk assessment, accidents and injuries is most likely of all uncertain events to occur
at 100 points and the least being bad reviews with 24 points.

C. Finalized schedule
1. Resource requirements and resolution of resource allocation problems

The resources required to achieve the project can be split into two main categories:
-

What can be done by our team (group Green Wulf)
What need to be outsourced because we don’t have the required skill sets (group External
Contractors and Supplier)

Group Green Wulf
The beginning of the project consists of doing feasibility studies, selecting the good supplier, the
purchase of the equipment and testing the new room before opening. All these tasks are done by our
team.
In order to transform one fitness room into a sustainable one, Green Wulf needed to invest in
Dynamo bikes and treadmills.
The fitness room in Carmichael measures about 1,200 ft2.
We decided to furnish it with fifteen Dynamo bikes and fifteen treadmills to keep the same capacity
as it was. The procurement process is also assured by our team.

12
Group External Contractors and Supplier
For the rest of the project, we need to hire specialized people for the equipment and electrical
installation as well as for the cleaning.
-

Equipment installation

We hired a crew to remove the old equipment and install the new ones.
-

Electrical installation

We needed to set a new electrical installation up to optimize the energy produced by people on the
Dynamo bikes and the treadmills. Modernizing the room will also reduce the electricity bill by 30%
and enable NCSU to gain an environmental accreditation.
The new electrical installation lied in wiring and layering.
The electrical wiring and layering consist of choosing the right size receptacle boxes, running cable
throughout the room, and making the electrical connections through the walls and the floor.
Moreover, the crew will have to repaint the walls and cover the floor back as well.
-

Cleaning

Besides, we called on a cleaning service twice. First to clean the fitness room after the crew removed
the old equipment and then, before installing the new ones.
The table below summarizes what are our resource requirements:
Type

Research and
documentation

Work 17 220,00 € Green Wulf

400% 60,00 €/hr

Testing

Work

100% 60,00 €/hr

Equipment
installation
Electrical
installation

Work
Work

Cost

Group

Max.
Std. Rate
Units

Resource Name

840,00 € Green Wulf
External
Contractor
External
3 920,00 €
Contractor
External
300,00 €
Contractor
1 520,00 €

Cleaning

Work

Fitness
equipment

Work 33 150,00 € Supplier

300% 80,00 €/hr
200%

140.00
€/hr

200% 75.00 €/hr
100% 0.00 €/hr

Ovt.
Rate

Cost/Use

Accrue At

0.00
0.00 € Prorated
€/hr
0.00
0.00 € Prorated
€/hr
0.00
0.00 € Prorated
€/hr
0.00
0.00 € Prorated
€/hr
0.00
0.00 € Prorated
€/hr
0.00
33 150.00 € Start
€/hr

Thanks to a good planning process, we have been able to make accurate estimates concerning our
resource. The only one who would have been over allocated is Research and documentation since
this resource is used a lot at the beginning. However, we have enough team members to be allocated
to every task.

13
2. Rolled up budget estimates

Cash Flow statement

Cash Flow statement
35000
30000

Dollars

25000
20000
15000
10000
5000
0
03
10
17
24
01
June June June June July

08
July

Cost 6720 2940 2100 2100 1680 34830

15
July

22
July

0

0

02
09
05
12
19
26
29
Sept Sept
Augu Augu Augu Augu
July
emb emb
st
st
st
st
er
er
0

0

3490 2670

0

420

0

The major cash flow is incurred when the equipment is ordered. Afterwards, there are no costs until
the equipment is received.

Phase 1: documentation (preliminary report and benchmarking)
We had established some researches on this market in order to be well informed, to benchmark the
potential suppliers so that we would choose the optimized solution.
All this documentation process cost $17,220.

Phase2: order
Regarding the new equipment, one dynamo bike costs $1,200.
$1,200 x 15 = $18,000.
One treadmill costs $1,000 (x15 = $15,000)
$1,000 x 15 = $15,000.
The delivery costs $75 for each.
$75 x 2 = $150.

Phase3: installation (receiving/installing equipment, electrical installation and cleaning)
As far as the old equipment is concerned, we hired a one truck with a four-man crew for the whole
day, meaning eight hours.
Their minimum service was three hours for $360. So we needed five additional hours. The additional
hour cost $80.
$360 + (5 x $80) = $760.
14
As regards to the new equipment installation:
One Dynamo bike weighed 110 pounds x 15 = 1,650 pounds.
One treadmill weighed 220 pounds x 15 = 3,300 pounds.
In order to carry 4,950 pounds of equipment, we called on the same team for the whole day as well.
$760 x 2 = $1,520.
Finally, two specialized people were hired to complete the electrical wiring and the layering. The
wiring lasted four days as well as the layering.
They were paid $1,960 each.
$1,960 x 2 = $3,920.
The materials for the complete rewiring and layering job were included.
As for the cleaning service, it was composed of two people. They brought their own products, which
were included.
For a 1,200ft2 room, the minimum service was two hours at $75 per hour.
We decided to hire the team for two hours for two different days: after removing the old equipment
and before setting up the new ones.
$75 x 2 hours = $150 for the first day.
$150 x 2 = $300 for the second day.

Phase 4: testing
This is the last phase of the project. We have to test our equipment to assure security of our dynamo
bikes and treadmills. This is done by our team for a cost of $840.

EQUIPMENT ORDER

15 dynamo bikes $18,000
15 treadmills $15,000
Delivery cost $150

$33,150

CLEANING SERVICE

2

One 1,200 ft room
2 hours ($75/hour)
For two days

$300

EQUIPMENT
INSTALLATION

One truck with a
4-man crew included
3 hours for $360 + (5 x
$80)
For two days

$1,520

ELECTRICAL
INSTALLATION

4 days layering and wiring
by 2 specialized people at
$1,960 each

$3,920

Total estimated cost baseline regarding external contractors = $38,890

 Total estimated cost baseline included Green Wulf research and external contractors: $56,950.

15
Part II Project update
A. Status report
1. Narrative of key events to date

Prior to the start of Green Wulf project, the team had followed a seminar in order to perfect
their skills in all aspects of Project Management, lead by the PM Guru, Steve Del Grosso.
Thanks to his effective training and the previous work experiences of team members on similar
projects, Green Wulf has managed to make rather realistic estimates for all the project tasks. Thus, at
the time of the project status, July 17th 2013, GreenWulf project is on schedule and under costs.
The team also managed to write efficiently the preliminary research documents thus shortening the
baseline schedule for the first project milestone. However, the technical feasibility study had to be
extended from 7 to 9 days in order to secure the knowledge that the estimated energy savings
objective will be met, as “failure was not an option”. We had our project sponsor review our report
in order to provide us with the “green light” to move forward on the project.

As for the second milestone, the team as efficiently researched the equipment suppliers but
the first quotes received were much higher than anticipated. Therefore, Green Wulf team had to
negotiate during two more days in order to obtain the most competitive quote possible. The selected
manufacturer is located in Virginia which will minimize delivery costs compared to some other
providers located in California.
At the date of the project status, the equipment has been ordered after submitting the
benchmarking documents to the NCSU governance, our sponsor, for approval. They were satisfied by
our respect of the project priority matrix so far, as the costs were effectively enhanced and the
project had not been too much delayed.

16
2. Performance indices
Status Report : July 17th, 2013
WBS
Task
%
Complete
1.1.1.1
Energy Study
Finished
1.1.1.2
Costing
Finished
Technical
Finished
1.1.1.3
feasibility Study
1.1.1.4
Fallout study
Finished
Preliminary
Finished
1.1.2
report
1.2.1.1 Supplier search Finished
1.2.1.2 Quote requests Finished
Supplier
Finished
1.2.1.3
selection
Banchmarking Finished
1.2.1.4
documentation
Fitness
1.2.2
Equipment
29%
order
Cumulative Totals

EV

AC

PV

CV

SV

4 200.00 €
1 680.00 €

3 780.00 €
1 680.00 €

4 200.00 €
1 680.00 €

420.00 €
0.00 €

0.00 €
0.00 €

2 940.00 €

3 780.00 €

2 940.00 €

-840.00 €

0.00 €

840.00 €

420.00 €

840.00 €

420.00 €

0.00 €

2 940.00 €

2 100.00 €

2 940.00 €

840.00 €

0.00 €

2 100.00 €
840.00 €

1 680.00 €
1 680.00 €

2 100.00 €
840.00 €

420.00 €
-840.00 €

0.00 €
0.00 €

840.00 €

420.00 €

840.00 €

420.00 €

0.00 €

840.00 €

840.00 €

840.00 €

0.00 €

0.00 €

9 613. 50 €

9 613. 50 €

9 613. 50 €

0.00 €

0.00 €

26 833.50 €

25 993. 50 €

26 833, 50 €

840.00 €

0.00 €

As seen from the Earned Value report above, on July 17th, 2013, the project was on schedule and
under cost by 840, 00 €. Since the Fitness Equipment Order task has a fixed cost which amounts to
the total price of the bikes and treadmills plus delivery costs, the cost doesn’t vary with the
percentage of completion of the task. Thus, the Earned Value equals the Actual Cost of work
performed which is also equal to the Planned Value.
3. Project schedule status
The phase 1.1: “feasibility studies” has already been completed. We are on Day 33 so the project
completion is about 47.8%. The GreenWulf project was expected to last 68.86 days according the
WBS and end on Tuesday, August 27, 2013.
The project is currently in phase 1.2.2 of the Work Breakdown Structure. Our team has just ordered
the fitness equipment online which is expected to be delivered in the following days. The activity is
supposed to last 21 days.

17
B. Problem solving
1. Description of key problems and issues encountered
There was a major hurricane that hit North Carolina and its surrounding cities on 5th August 2013.
The hurricane named “Hurricane Rouge (category 2)” due to its unassuming but destructive nature
caused severe damages in most cities and small towns in North Carolina. Consequences of the
hurricane included flooding, complete power shortage for 3 days and an abrupt end to all activities at
offices, schools, etc. following advice of the regional meteorology department. There was a state of
emergency for 3 days.
The aftermath of the hurricane resulted in the loss of all the order we made for equipments as the
driver lost control of the vehicle and plunged in the Lake Johnson in Raleigh. He was advised to stay
at home but wanted to finish his work in order to maximize his paycheck. In addition, the Carmichael
complex suffered from flood and power outage issues.

18
2. Responses to the problems and how they affected the project
First, concerning the lost order, it had no extra-cost on the project’s budget since the manufacturer’s
insurance covers hurricane damages. However, the project team had to order again the fitness
equipment and wait for the delivery before going further in the project.
Secondly, NCSU governance had to arrange the repairs to Carmichael Sports complex that lasted 7
days. In total, due to the hurricane and its aftermath, the Green Wulf project was delayed by 10 days
during which we could not process with the project.

C. Management issues
1. Problem description
In the meantime, our team had to face another challenge: North Carolina State University revised the
project’s budget and since they were pleased by our progresses, they decided to renovate the whole
fitness complex. The university asked us to be in charge of the installation of the 3 fitness rooms in
the Carmichael Gymnasium. It raised some 4 new constraints for our team.
The first constraint was to maintain the users’ experience. Since we had to renovate the whole
fitness center of the gymnasium, we had to find a strategy that will allow students, faculty and staff
to keep on working out during the project duration.
The second constraint is to enhance time. Since the project has a new scope, the project will now
have a completion date further into the fall semester. The project team is expected to meet the new
deadlines and to complete the GreenWulf project as soon as possible in order to offer to students a
sustainable gymnasium rapidly without disturbing the gymnasium life.
The third constraint is the project performance. Since our team will be in charge of the installation of
2 new rooms, we need to deliver a high quality service as stated in the project scope and expected
from the stakeholders.
The final constraint is still to manage the costs due to the limited financing available from NC State
governance.
2. Response to the issues and how the responses impact the whole project

Regarding the new request from North Carolina State University, our team had to find ways to
answer the new constraints.
First, the project team discussed with the NC State committee about the new project scope and
requirements in order to reach a new agreement that matches stakeholders’ expectations with new
deadlines for the operational team.

19
In order to answer the 3 constraints raised by the new request from NC State, our project team
implemented 4 strategies:
- To limit costs, we decided to renegotiate with the suppliers to lower the price or waive the delivery
fees since we will order a bigger quantity.
- To maintain the users’ experience, the GreenWulf project team decided to rotate the fitness rooms
one by one so that at least one room would still be accessible for users whereas the others would be
under renovation.
- To enhance time, the project team is convinced that it will acquire expertise during the first fitness
room installation. The expertise acquired will allow the team to better manage the project tasks for
the two other rooms installation.
- To get a proofed performance, our team extended the feasibility studies to all the fitness rooms.
According to the new request from NC State, our project team rescheduled the entire project in
order to answer the new project scope. The project duration is now 101.86 days and the new
expected completion date is on Thursday, October 24th.
We can find below the new project matrix generated for the GreenWulf master project.
As we can see on the table, Performance remains the constraint.
However, Time came from “accept” to “enhance”. Indeed, time plays a major role in the new project
since we now need to install 3 fitness rooms instead of one and the installation needs to impact the
gymnasium life as low as possible.
Also, Cost came from “enhance” to “accept”. Actually, NC State is willing to finance the gymnasium
so the cost is not a real constraint.
Now, the project has to focus on Performance and Time.

20
D. Revised Project Estimate
1. Projected Cost

Given that our previous orders had been destroyed by the hurricane in North Carolina, order and
fabrication of the new equipment had to start from scratch. Luckily, Green Wulf did not have to take
the cost related to the losses in charge. It was the manufacture’s insurance responsibility.
Furthermore, NCSU and stakeholders were really happy of the project so that we had to extend it to
three fitness rooms.
Regarding the dynamo bikes, we needed to order 15 x 3 fitness rooms = 45,000. The cost per unit
was still $1,200.
$1,200 x 45 = $54,000.
For the treadmill, the manufacturer kept the same price per unit.
$1,000 x 45 = $45,000.
Our equipment supplier did not charge us for the delivery though, because we ordered in huge
quantity.
The delivery cost = $0.
As for the cleaning service, we asked the two people if adding two extra rooms were possible
considering the deadline. They agreed. The price was still $75 per hour for a minimum service of two
hours. But they granted us a 8.33% discount.
It was $300 for one fitness room, including the two-day work. We relied on that basis.
($300 x 3 rooms) x 8.33% = $825.
Regarding the new equipment installation, before the hurricane the four-man crew needed three
days to install the bikes and treadmills. After the hurricane, they needed one day more to complete
the same task and charged us for that extra day.
We paid $1,520 for one fitness room for three-hour work.
The crew granted us a 13.3% discount for the two new rooms. We still had to pay the full price for
the first one.
($1,520 + ($1,760 x 2)) x 13.3% = $4,448
The last but not the least, the two specialized people in electrical wiring and layering came back and
gave us a 15% discount on the total amount.
One room cost $3,960 for eight days.
($3,920 x 3 rooms) x 15% = $9,996 for 24 days.

21
As for the flood damages to the Carmichael complex, NCSU was responsible for the losses.

EQUIPMENT ORDER

45 dynamo bikes $54,000
45 treadmills $45,000
Delivery cost $0

$99,000

CLEANING
SERVICE

Three 1,200 ft2
rooms
2 hours ($75/hour)
8,33% off
For two dates

$825

EQUIPMENT
INSTALLATION

ELECTRICAL
INSTALLATION

One truck with a 4-man
crew for each room +
20% discount for the 2
last rooms for 4 days

4 days layering and
wiring by 2 specialized
people at $1,960 each x
3 rooms

$4,448

$9,996

Total estimated cost baseline regarding external contractors = $114,269

The hurricane as well as the two more fitness rooms modified our internal processes and strategy.
We had to do conduct other researches and documentation not to shake up our project and to be as
closed as possible to our previous deadlines.
This cost us $20,160 (including the test process).
 Total estimated cost baseline included the researches and the external contractors: $134,429.
At the beginning, our baseline cost was $56,950. After the hurricane and the two additional rooms, it
is now $134,429 (a $77,479 extra difference).
Let’s calculate the Cost Performance Index (CPI) to determine if we are under cost, on cost or over
cost regarding our baseline.
CPI = EV / AC
(with EV meaning the Earned Value and AC the Actual Cost)
= 124,629.32 / 123,821
= 1,01
This means that our project is approximately on cost compared to our forecast.

22
2. Schedule

Let’s calculate the Schedule Performance Index (SPI) to determine if we are ahead of schedule, on
schedule or behind schedule.
SPI = EV / PV

(with PV meaning the planned time-phased baseline)

= 124,629.32 / 123,621
= 1,01
This means our project is on schedule.
We can see on the picture below the effect of the hurricane on the initial project. The delivery has
been interrupted and reparations had to be done. After that and once the renegotiation with the
supplier if done, we can reorder the equipment and restart the project.

23
The second change in the schedule is the addition of 2 more rooms to renovate. The second project
starts after the hurricane with a new feasibility studies. It takes less time than the first one since we
already did it once; it is only a matter of adaptation to the new room.

24
E. Summary
1. Keys to successfully completing the projects

In order to meet our overall goal of renovating all 3 fitness rooms and finishing the GreenWulf
Project without any (more) sensitive issues that could limit progression of this project, we have
identified some vital steps in the project that must be managed correctly and they include the
following:

Limiting sensitivity of the project
One of the key sensitive aspects of this project is the fitness equipment order and reception of order.
This is crucial because, the time between order and reception usually takes between 17 to 28 days
and any lapse in time will have to change our plans and the project not progressing to the next level
of equipment installation and layering of electrical lines. Any wrong delivery of product will also
cause this project a great deal so we will have to be very certain about our product orders and
specification.
We also need to take into consideration the initial feasibility reports as any wrong estimation of the
project can lead to performance, time and cost constraints. Therefore the main sensitive aspects of
this stage are energy study, costing and technical feasibility study. This well done is very likely to
prevent any unforeseen issues in the future of the project.

Time management (project duration & delivery end product)
As time is of essence in this project, we will have to make sure tasks are performed on schedule and
by the right expertise. Some projects must parallel to each other. They could both start on the same
day and end at the same finishing time. For instance, whilst fitness equipment orders have been
placed, cleaning and clearing out of old equipments could happen since they do not depend on each
other to start the next phase of the job (Milestones).
In saving time, we will have to seek the service of experts in the various aspects of this project who
can be efficient in task completion. And during the project expansion, the same workers will be used
since they now have a better understanding of the GreenWulf project and will be extra efficient in
delivering good job. This will save the project time and further risks.

Respect end user experience
To guarantee that student and other users are able to still use the sports Complex when school
resumes or even whilst work is still in progress, we will have to rotate from one fitness room to
another after work in each room is completed. We must maintain a great level of support to users of
the Carmichael Complex and kept them updated on the project by communicating with the project
stakeholders.

25
2. Forecast at completion

We are going to look at the Variance Cost at Completion (VAC) to determine which activities have
gone well or not.
It is the difference between EAC and BAC. Negative variance indicates that the project will be
completed over budget. On the contrary, positive VACs mean that the activities will be completed
less than the budgets.
VAC for fitness room 1 = +$992.11
For fitness room 2 = -$146.49
For fitness room 3 = -$146.73
As a result, the fitness room number 1 will be the only one to be completed less than the budgets.
Whereas the fitness rooms number 2 and 3 will be completed over budget.
Here are the activities that have gone well and the ones that have had some issues:

Fitness Rooms

Negative VACs

Fitness Room 1




technical feasibility study
quote requests

Fitness Room 2








bikes reception
treadmills reception
old equipment transfer
removal of old equipment
electrical wiring
fitness equipment
reception



Positive VACs








Feasibility study
energy study
fallout study
preliminary report
supplier search
supplier selection










equipment installation
room cleaning
new equipment set-up
electrical installation
layering
feasibility study
fallout study
report

Fitness equipment
reception
Bikes reception
Treadmills reception



For the other activities, VACs are $0.
Fitness Room 3

26
3. Formal statement of confidence and risk

Having experienced some difficulties before the second phase of the project, we were well prepared
for the second phase of the project even though we have more workload to do. We did a second risk
assessment of and were able to better prepare for any eventualities that could occur.
Also with first phase successfully done, we were more confident about executing the second phase of
the project quicker and even better with all the experience drawn from the initial part of the project. For
instance, we were quite certain of how much energy we could tap from the new rooms because we
have already been able to measure how much energy we tap from the first room.

27

More Related Content

What's hot

Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project PresentationWayne Holley
 
Business plan of khaasiyat
Business plan of khaasiyatBusiness plan of khaasiyat
Business plan of khaasiyat
digant1
 
Japahindi Wedding Project Management Plan
Japahindi Wedding Project Management PlanJapahindi Wedding Project Management Plan
Japahindi Wedding Project Management Plan
Hungyu Lai
 
Tender calling procedure
Tender calling procedureTender calling procedure
Tender calling procedure
Shourya Puri
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
Lwj Welson
 
Business environment in brazil
Business environment in brazilBusiness environment in brazil
Business environment in brazilRoxana Darjan
 
Gym Startup Business Plan Proposal Powerpoint Presentation Slides
Gym Startup Business Plan Proposal Powerpoint Presentation SlidesGym Startup Business Plan Proposal Powerpoint Presentation Slides
Gym Startup Business Plan Proposal Powerpoint Presentation Slides
SlideTeam
 
Wedding event management
Wedding event management Wedding event management
Wedding event management Yo Maruf
 
Turnkey project
Turnkey projectTurnkey project
Turnkey projectzairanieto
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Constructionshillier38
 
catering business proposal
catering business proposalcatering business proposal
catering business proposal
DumebiMordi
 
Business Plan - Web based-wedding-services
Business Plan - Web based-wedding-servicesBusiness Plan - Web based-wedding-services
Business Plan - Web based-wedding-services
Aum e Hani
 
Construction company business plan example
Construction company business plan exampleConstruction company business plan example
Construction company business plan example
upmetrics.co
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
Pui Chun Shian
 
Investment Opportunity Letter
Investment Opportunity LetterInvestment Opportunity Letter
Investment Opportunity Letter
Cole Real Estate Holdings, LLC
 
Building economics final assignment report
Building economics final assignment reportBuilding economics final assignment report
Building economics final assignment report
lucaschinsheng
 
Construction Equipment Proposal Template PowerPoint Presentation Slides
Construction Equipment Proposal Template PowerPoint Presentation SlidesConstruction Equipment Proposal Template PowerPoint Presentation Slides
Construction Equipment Proposal Template PowerPoint Presentation Slides
SlideTeam
 
Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...
Tan Jaden
 
Project management
Project managementProject management
Project management
Aidiel Azhar
 
Sample of development joint venture agreement between owner of land and devel...
Sample of development joint venture agreement between owner of land and devel...Sample of development joint venture agreement between owner of land and devel...
Sample of development joint venture agreement between owner of land and devel...
Green Realtech Projects Pvt. Ltd
 

What's hot (20)

Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 
Business plan of khaasiyat
Business plan of khaasiyatBusiness plan of khaasiyat
Business plan of khaasiyat
 
Japahindi Wedding Project Management Plan
Japahindi Wedding Project Management PlanJapahindi Wedding Project Management Plan
Japahindi Wedding Project Management Plan
 
Tender calling procedure
Tender calling procedureTender calling procedure
Tender calling procedure
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Business environment in brazil
Business environment in brazilBusiness environment in brazil
Business environment in brazil
 
Gym Startup Business Plan Proposal Powerpoint Presentation Slides
Gym Startup Business Plan Proposal Powerpoint Presentation SlidesGym Startup Business Plan Proposal Powerpoint Presentation Slides
Gym Startup Business Plan Proposal Powerpoint Presentation Slides
 
Wedding event management
Wedding event management Wedding event management
Wedding event management
 
Turnkey project
Turnkey projectTurnkey project
Turnkey project
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
catering business proposal
catering business proposalcatering business proposal
catering business proposal
 
Business Plan - Web based-wedding-services
Business Plan - Web based-wedding-servicesBusiness Plan - Web based-wedding-services
Business Plan - Web based-wedding-services
 
Construction company business plan example
Construction company business plan exampleConstruction company business plan example
Construction company business plan example
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Investment Opportunity Letter
Investment Opportunity LetterInvestment Opportunity Letter
Investment Opportunity Letter
 
Building economics final assignment report
Building economics final assignment reportBuilding economics final assignment report
Building economics final assignment report
 
Construction Equipment Proposal Template PowerPoint Presentation Slides
Construction Equipment Proposal Template PowerPoint Presentation SlidesConstruction Equipment Proposal Template PowerPoint Presentation Slides
Construction Equipment Proposal Template PowerPoint Presentation Slides
 
Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...
 
Project management
Project managementProject management
Project management
 
Sample of development joint venture agreement between owner of land and devel...
Sample of development joint venture agreement between owner of land and devel...Sample of development joint venture agreement between owner of land and devel...
Sample of development joint venture agreement between owner of land and devel...
 

Viewers also liked

Gym proposal
Gym proposalGym proposal
Gym proposal
Jesse O'Brien
 
Risk assesment for gym
Risk assesment for gymRisk assesment for gym
Risk assesment for gymajibike
 
Boxing gym risk assesment
Boxing gym risk assesmentBoxing gym risk assesment
Boxing gym risk assesment
eleanorbarter
 
BIM for Conceptual Estimating
BIM for Conceptual EstimatingBIM for Conceptual Estimating
BIM for Conceptual Estimating
Beck Technology, Ltd.
 
Feasibility Study FINAL-1
Feasibility Study FINAL-1Feasibility Study FINAL-1
Feasibility Study FINAL-1Aynsley Griffin
 
Somers town origonal risk assessment
Somers town origonal risk assessmentSomers town origonal risk assessment
Somers town origonal risk assessment
nelemen
 
Computer Literacy Seminar (A Project Management)
Computer Literacy Seminar (A Project Management)Computer Literacy Seminar (A Project Management)
Computer Literacy Seminar (A Project Management)
Ninotchika Pery
 
Bim 5 d_cost estimating
Bim  5 d_cost estimatingBim  5 d_cost estimating
Bim 5 d_cost estimating
Justin Tran
 
Gym Equipment2009
Gym Equipment2009Gym Equipment2009
Gym Equipment2009jeffirving
 
Gym Management System User Manual
Gym Management System User ManualGym Management System User Manual
Gym Management System User Manual
David O' Connor
 
Project presentation
Project presentationProject presentation
Project presentation
Daily Ki Jobs
 
5th Qatar BIM User Day, Live modeling techniques on a single project
5th Qatar BIM User Day, Live modeling techniques on a single project5th Qatar BIM User Day, Live modeling techniques on a single project
5th Qatar BIM User Day, Live modeling techniques on a single project
BIM User Day
 
203wbs Network Gantt Chart
203wbs Network Gantt Chart203wbs Network Gantt Chart
203wbs Network Gantt Chartbtecexpert
 
Wedding Project Charter
Wedding Project CharterWedding Project Charter
Wedding Project Charter
jordan052505
 
Fitness center
Fitness centerFitness center
Fitness center
Yogesh Darji
 
Fitness industry
Fitness industryFitness industry
Fitness industry
Monkhzul Bold
 

Viewers also liked (20)

Gym proposal
Gym proposalGym proposal
Gym proposal
 
Risks assessment
Risks assessment Risks assessment
Risks assessment
 
Risk assesment for gym
Risk assesment for gymRisk assesment for gym
Risk assesment for gym
 
Boxing gym risk assesment
Boxing gym risk assesmentBoxing gym risk assesment
Boxing gym risk assesment
 
BIM for Conceptual Estimating
BIM for Conceptual EstimatingBIM for Conceptual Estimating
BIM for Conceptual Estimating
 
Feasibility Study FINAL-1
Feasibility Study FINAL-1Feasibility Study FINAL-1
Feasibility Study FINAL-1
 
Somers town origonal risk assessment
Somers town origonal risk assessmentSomers town origonal risk assessment
Somers town origonal risk assessment
 
Computer Literacy Seminar (A Project Management)
Computer Literacy Seminar (A Project Management)Computer Literacy Seminar (A Project Management)
Computer Literacy Seminar (A Project Management)
 
Bim 5 d_cost estimating
Bim  5 d_cost estimatingBim  5 d_cost estimating
Bim 5 d_cost estimating
 
Gym Equipment2009
Gym Equipment2009Gym Equipment2009
Gym Equipment2009
 
Gym Management System User Manual
Gym Management System User ManualGym Management System User Manual
Gym Management System User Manual
 
Project presentation
Project presentationProject presentation
Project presentation
 
Project Management - Gym Simulation
Project Management - Gym SimulationProject Management - Gym Simulation
Project Management - Gym Simulation
 
5th Qatar BIM User Day, Live modeling techniques on a single project
5th Qatar BIM User Day, Live modeling techniques on a single project5th Qatar BIM User Day, Live modeling techniques on a single project
5th Qatar BIM User Day, Live modeling techniques on a single project
 
203wbs Network Gantt Chart
203wbs Network Gantt Chart203wbs Network Gantt Chart
203wbs Network Gantt Chart
 
Wedding Project Charter
Wedding Project CharterWedding Project Charter
Wedding Project Charter
 
Fitness center
Fitness centerFitness center
Fitness center
 
Fitness industry
Fitness industryFitness industry
Fitness industry
 
Gym Final Report.ppt
Gym Final Report.pptGym Final Report.ppt
Gym Final Report.ppt
 
MGMT_404 PROJECT FINAL
MGMT_404 PROJECT FINALMGMT_404 PROJECT FINAL
MGMT_404 PROJECT FINAL
 

Similar to Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business School

Assignment 1 ITECH 2250 IT Project Management Techniques.docx
Assignment 1 ITECH 2250 IT Project Management Techniques.docxAssignment 1 ITECH 2250 IT Project Management Techniques.docx
Assignment 1 ITECH 2250 IT Project Management Techniques.docx
sherni1
 
Project management
Project managementProject management
Project management
smumbahelp
 
Pm assignment -5111570030
Pm assignment -5111570030Pm assignment -5111570030
Pm assignment -5111570030
adzoyi
 
1 Project Title Combined Sewer Overflow Pow
1 Project Title Combined Sewer Overflow Pow1 Project Title Combined Sewer Overflow Pow
1 Project Title Combined Sewer Overflow Pow
AbbyWhyte974
 
1 Project Title Combined Sewer Overflow Pow
1 Project Title Combined Sewer Overflow Pow1 Project Title Combined Sewer Overflow Pow
1 Project Title Combined Sewer Overflow Pow
MartineMccracken314
 
Hello Class- This is a very rough draft of the assignment. I have
Hello Class- This is a very rough draft of the assignment. I have Hello Class- This is a very rough draft of the assignment. I have
Hello Class- This is a very rough draft of the assignment. I have
SusanaFurman449
 
IES Faculty - Closing the Performance Gap
IES Faculty - Closing the Performance GapIES Faculty - Closing the Performance Gap
IES Faculty - Closing the Performance Gap
IES VE
 
CME Budget Proposal - Facilities management
CME Budget Proposal - Facilities managementCME Budget Proposal - Facilities management
CME Budget Proposal - Facilities management
ABramall
 
3Worksheet The Project CharterProject NameBurl.docx
3Worksheet The Project CharterProject NameBurl.docx3Worksheet The Project CharterProject NameBurl.docx
3Worksheet The Project CharterProject NameBurl.docx
gilbertkpeters11344
 
Project-Charter_Rubab Tanveer_PTC_AKF_PDF
Project-Charter_Rubab Tanveer_PTC_AKF_PDFProject-Charter_Rubab Tanveer_PTC_AKF_PDF
Project-Charter_Rubab Tanveer_PTC_AKF_PDFRubab Tanveer
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
PRIYANSHU KUMAR
 
Pm0012 – project finance
Pm0012 – project financePm0012 – project finance
Pm0012 – project financesmumbahelp
 
Project Name
 Project Name                                       Project Name
Project Name
TatianaMajor22
 
Assignment 8.14.docx
Assignment 8.14.docxAssignment 8.14.docx
Assignment 8.14.docx
ssuser562afc1
 
Applied Project Management Team Assignment Eco-House Project Management Plan
Applied Project Management Team Assignment Eco-House Project Management PlanApplied Project Management Team Assignment Eco-House Project Management Plan
Applied Project Management Team Assignment Eco-House Project Management Plan
Nicole Heredia
 
Essential Elements of an Executive SummaryBusiness proposalplan.docx
Essential Elements of an Executive SummaryBusiness proposalplan.docxEssential Elements of an Executive SummaryBusiness proposalplan.docx
Essential Elements of an Executive SummaryBusiness proposalplan.docx
debishakespeare
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
TinotendaChivese
 
Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725
Minn Lwin
 
Managing project (snowball)
Managing project (snowball)Managing project (snowball)
Managing project (snowball)
Waseque Uddin Ahmed
 

Similar to Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business School (20)

Assignment 1 ITECH 2250 IT Project Management Techniques.docx
Assignment 1 ITECH 2250 IT Project Management Techniques.docxAssignment 1 ITECH 2250 IT Project Management Techniques.docx
Assignment 1 ITECH 2250 IT Project Management Techniques.docx
 
Project management
Project managementProject management
Project management
 
Pm assignment -5111570030
Pm assignment -5111570030Pm assignment -5111570030
Pm assignment -5111570030
 
1 Project Title Combined Sewer Overflow Pow
1 Project Title Combined Sewer Overflow Pow1 Project Title Combined Sewer Overflow Pow
1 Project Title Combined Sewer Overflow Pow
 
1 Project Title Combined Sewer Overflow Pow
1 Project Title Combined Sewer Overflow Pow1 Project Title Combined Sewer Overflow Pow
1 Project Title Combined Sewer Overflow Pow
 
Hello Class- This is a very rough draft of the assignment. I have
Hello Class- This is a very rough draft of the assignment. I have Hello Class- This is a very rough draft of the assignment. I have
Hello Class- This is a very rough draft of the assignment. I have
 
Project Management Introduction
Project Management IntroductionProject Management Introduction
Project Management Introduction
 
IES Faculty - Closing the Performance Gap
IES Faculty - Closing the Performance GapIES Faculty - Closing the Performance Gap
IES Faculty - Closing the Performance Gap
 
CME Budget Proposal - Facilities management
CME Budget Proposal - Facilities managementCME Budget Proposal - Facilities management
CME Budget Proposal - Facilities management
 
3Worksheet The Project CharterProject NameBurl.docx
3Worksheet The Project CharterProject NameBurl.docx3Worksheet The Project CharterProject NameBurl.docx
3Worksheet The Project CharterProject NameBurl.docx
 
Project-Charter_Rubab Tanveer_PTC_AKF_PDF
Project-Charter_Rubab Tanveer_PTC_AKF_PDFProject-Charter_Rubab Tanveer_PTC_AKF_PDF
Project-Charter_Rubab Tanveer_PTC_AKF_PDF
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Pm0012 – project finance
Pm0012 – project financePm0012 – project finance
Pm0012 – project finance
 
Project Name
 Project Name                                       Project Name
Project Name
 
Assignment 8.14.docx
Assignment 8.14.docxAssignment 8.14.docx
Assignment 8.14.docx
 
Applied Project Management Team Assignment Eco-House Project Management Plan
Applied Project Management Team Assignment Eco-House Project Management PlanApplied Project Management Team Assignment Eco-House Project Management Plan
Applied Project Management Team Assignment Eco-House Project Management Plan
 
Essential Elements of an Executive SummaryBusiness proposalplan.docx
Essential Elements of an Executive SummaryBusiness proposalplan.docxEssential Elements of an Executive SummaryBusiness proposalplan.docx
Essential Elements of an Executive SummaryBusiness proposalplan.docx
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725
 
Managing project (snowball)
Managing project (snowball)Managing project (snowball)
Managing project (snowball)
 

Recently uploaded

5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Jos Voskuil
 
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop.com LTD
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
PaulBryant58
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 

Recently uploaded (20)

5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
 
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 

Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business School

  • 1. GreenWulf Project Sustainable energy on Campus Ibrahim Abubakari Caroline Bilet Arthur Lanos Thomas Leportier Amélie Meppiel Camille Perencin Medhi Thadi Kristin Torin Project Management Final Report Fall 2012 – SKEMA Raleigh
  • 2. Table of content Part I Project Plan A. Project Charter / Scope statement 1. Objectives of the project, requirements definition and constraints 2 Stakeholder analysis 3. Keys to success B. C. Part II Project Definition 1. Solution/ work product description 2. Work Breakdown Structure 3. High Level schedule 4. Network Diagram and Critical Path 5. List of Milestones and Dependencies including dates 6. Risk Assessment / Response Finalized schedule 1. Resource requirements and resolution of resource allocation problems 2. Rolled up budget estimates Project Update A. Status report 1. Narrative of key events to date 2. Performance indices 3. Project schedule status B. Problem solving 1. Description of key problems and issues encountered 2. Responses to the problems and how they affected the project C. Management issues 1. Problem description 2. Responses to the issues and how the responses impacts the rest of the project D. Revised project estimates 1. Projected cost 2. Schedule E. Summary 1. Keys to successfully completing the project 2. Forecast at completion 3. Formal statement of confidence and risk 2
  • 3. Part I Project Plan A. Project Charter/Scope statement 1. Objectives of the project, requirements definition and constraints Project concept North Carolina State University has recently launched a vast project of transforming the campus into a green university. The first steps implemented were passive measures such as turning off heating in unoccupied buildings during holidays. Now NCSU governance is looking for a more proactive way in order to be awarded “green campus of 2014”. This is why we have been contacted by NCSU in order to turn Carmichael complex into a sustainable sport center. Our concept is simple: the energy developed by students while working out on cardio equipments such as dynamo bikes and treadmills will be transformed into electricity and used for the gymnasium power needs. Project boundaries In order to be clear with our stakeholders with what we are responsible for as part of this project, we have established the following boundaries: IN • Buy, install and connect the equipment in one fitness room • Ensure that there are actual savings of energy • Communicate with stakeholders on the progresses made OUT • Daily maintenance and functioning • Communication on the modernization to end users • Student reward system (incentives to come to the new gym) Our job will be restricted to the procurement and installation of new bikes and treadmills able to produce a quantity of electricity significant enough to reduce the electricity bills of the complex. In order to do so, we will first do a feasibility studies and benchmarking of suppliers. Then we will take care of all necessary modifications to be done to the room before installing the new fitness equipment. It is our responsibility to ensure that bikes and treadmills will generate energy savings. However, it is not our responsibility to ensure the daily maintenance once the equipment is ready to use. We won’t be in charge of the communication within NCSU community about this renovation. In addition, we thought about a system of student reward based on the electricity they will produce in order to create new incentives for students to go to the gym. However, it is not included in the current scope. If our stakeholders which to implement this additional time and/or budget must be allocated. 3
  • 4. Project objectives We have two quantifiable objectives to measure the success of our project: - Electricity bill must be reduced by 30% The number of users should also increase by 15% Project requirements and constraints While progressing through our project, we have to take into account several requirements and constraints set by NCSU. Our requirements are: - - - - Keep the existing building. It is impossible to undertake renovation work such as increasing the size of the fitness room. The building and walls must stay as they are now. Hence we need to carefully execute the feasibility study in order to have the new equipment fitting 100% to the existing room. Preserve the users’ experience during modernization process. We should try to minimize the disturbance caused to gym users during our project. To do so, most of the work will be done during summer holidays when most of students are not on campus. In addition, our project is to renovate only one fitness rooms. To other rooms with similar equipments are still available during the project. Users should be able to monitor their energy production. It is nice to say to users that they are producing electricity but it is even better to show them exactly how much they produced. This will be a new source of motivation for doing exercise and will help to achieve the increase in number of user. This will have to be taken into account when ordering the equipment. Modernized rooms should be able to gain environmental accreditation. The production of green electricity must be significant enough for the building to be considered as eco-friendly. This goes along with the objective the University to gain the label of “green campus of 2014”. In addition to these requirements, we have to deal with the following constraints: - - Make real energy savings (performance). As we said above, the bottom line of the project really is to produce electricity. Costs have to stay reasonable. The cost of our project if part of a bigger budget released by NCSU for their green campus program. It is considered as one of the top priority project for the University. Hence the funds available are fairly important but costs have to be optimized. Modernization has to be limited in time (3 to 4 months). The new room must be open during the first few month of fall semester in order to be available during most of the scholar year. 4
  • 5. Project Matrix - Time, cost, performance trade-off assessment Based on these constraints, we have established our project priority matrix: Time Constraint Cost X Enhance Accept Performance X X Performance is the key for this project. The equipment must produce enough electricity to be used into the Carmichael complex for us to attain our objectives. Cost must be enhanced. Our project is part of a bigger one within the University who is conducting several other projects. So far budget has been allocated to most of these NCSU projects so the University is limited in terms of releasing additional budget. In addition, NCSU cannot increase too much tuition fees in order to finance the project. Also, alumni donations are limited. The project’s duration is accepted. Still the project should avoid large delays but in the hypotheses it will happen and the room will be closed for longer than expected, 2 other rooms are still available. 5
  • 6. 2. Stakeholder analysis The chart below provides a global view of our project and its stakeholders. We have identified 5 major stakeholders on our project: - - - NCSU Governance: our sponsor for this project. Without them the project won’t exists since they provide the budget for it. They champion the project and are a major spokesperson to promote it. They play a crucial role for our project, especially during early phases of scope development. Carmichael staff: is also an important stakeholder. The project is done under their supervision since it will be done inside the building. Also, they will provide us empty rooms for the storage of equipments free of charge. Student Body: It will play a key role as voice of the students as it represents our end users. It has a much smaller authority on the project than the previous two stakeholders. Student (end users): One of the objectives of our project is also to please students. Their comments should also be taken into account. Alumni network: To some extent, alumni are also a distant stakeholder. They are ambassadors of the University and will contribute to develop the green image of NCSU outside the campus. Some of their contributions will also fund the upgrading of the Carmichael Gym. 6
  • 7. 3. Keys to success Technological Performance The first key to success of this project is to assure and deliver the expected performance in terms of electricity production. NCSU is investing money on this project not only to build a better image but to also have real and measurable gains. Thus, we have go in-depth during the preliminary studies in order to be sure to comply with our energy savings objectives. Time management In addition, time management is important and requires to carefully planning the project schedule. We can’t afford to accumulate delays during the project and deliver the room in November would be considered as a failure. Indeed, we will have not preserved the end-users experience of the gym. Communication with stakeholders Last but not least, communication with stakeholders is crucial, in particular with our sponsor at the beginning of the project when elaborating the scope and all necessary documentations. Reports must be done on a regular basis for the stakeholders to follow how the project is progressing. It should also be done for important steps such as ordering the equipment (a major post of cost) or beginning the installation. B. Project definition 1. Solution / work product description To begin the GreenWulf project, 3 sets of deliverables were designed to guide the project team in meeting the objectives and expectation of this project. First on the list of deliverables is the Feasibility study. In this stage, the team conducts preliminary studies and report about the project. We research about energy (present consumption of the sports complex and about renewable energy), provide a cost analysis of the project and look at technical feasibility studies and the fall out studies. Second deliverable is the Benchmarking documentation for the equipments. After searching for equipment suppliers and select some of them, order quotes, we will present a summary for review to the NCSU team. We finish with the project completion which happens after testing has been done both by Green Wulf and the end users and a period of review and acceptance 7 days after the launch of the fitness room. 7
  • 8. 2. Work breakdown structure WBS Nom de la tâche 1.0 GreenWulf Project 1.1 Feasibility studies 1.1.1 Preliminary Studies 1.1.1.1 Energy Study 1.1.1.2 Costing 1.1.1.3 Technical feasibility Study 1.1.1.4 Fallout study (project Benefits) 1.1.2 Preliminary report 1.2 Fitness Equipment 1.2.1 Benchmarking 1.2.1.1 Supplier search 1.2.1.2 Quote requests 1.2.1.3 Supplier selection 1.2.1.4 Banchmarking documentation 1.2.2 Fitness Equipment order 1.2.3 Fitness equipment reception 1.2.3.1 Bikes reception 1.2.3.2 Treadmills reception 1.2.3.3 Equipment Storage 1.3 Equipment intallation 1.3.1 Old equipment tranfer 1.3.1.1 Removal of old equipment 1.3.1.2 Disposal of old equipment 1.3.1.3 Room cleaning 1.3.2 New equipment set-up 1.3.2.1 Equipment Installation 1.3.2.2 Electrical installation 1.3.2.2.1 Layering 1.3.2.2.2 Electrical wiring 1.3.3 Room cleaning 1.4 Closure of the project 1.4.1 Testing by Greenwulf 1.4.2 Testing by Stakeholders 1.4.3 Lauch 1.4.4 Review and acceptance Duration Start Finish 65,43 days 17 days 10 days 10 days 4 days 7 days 2 days 7 days 33 days 11 days 5 days 2 days 2 days 2 days 21 days 1 day 3 hrs 3 hrs 1 day 6,43 days 1,14 days 3 hrs 3 hrs 2 hrs 5 days 1 day 4 days 2 days 2 days 2 hrs 9 days 1 day 1 day 1 day 1 day Mon 03/06/13 Mon 03/06/13 Mon 03/06/13 Mon 03/06/13 Mon 03/06/13 Mon 03/06/13 Mon 03/06/13 Mon 17/06/13 Wed 26/06/13 Wed 26/06/13 Wed 26/06/13 Wed 03/07/13 Mon 08/07/13 Wed 10/07/13 Fri 12/07/13 Mon 12/08/13 Mon 12/08/13 Mon 12/08/13 Mon 12/08/13 Tue 13/08/13 Tue 13/08/13 Tue 13/08/13 Tue 13/08/13 Tue 13/08/13 Wed 14/08/13 Wed 14/08/13 Thu 15/08/13 Thu 15/08/13 Mon 19/08/13 Wed 21/08/13 Wed 21/08/13 Wed 21/08/13 Thu 22/08/13 Fri 23/08/13 Tue 03/09/13 Wed 04/09/13 Tue 25/06/13 Fri 14/06/13 Fri 14/06/13 Thu 06/06/13 Tue 11/06/13 Tue 04/06/13 Tue 25/06/13 Mon 12/08/13 Thu 11/07/13 Tue 02/07/13 Fri 05/07/13 Tue 09/07/13 Thu 11/07/13 Fri 09/08/13 Mon 12/08/13 Mon 12/08/13 Mon 12/08/13 Mon 12/08/13 Wed 21/08/13 Wed 14/08/13 Tue 13/08/13 Tue 13/08/13 Wed 14/08/13 Wed 21/08/13 Thu 15/08/13 Wed 21/08/13 Mon 19/08/13 Wed 21/08/13 Wed 21/08/13 Wed 04/09/13 Thu 22/08/13 Fri 23/08/13 Mon 26/08/13 Wed 04/09/13 We have divided the Green Wulf project in 4 main subprojects: Feasibility studies ending with the preliminary report, Fitness equipment which contains the suppliers benchmarking process and the equipment order, Equipment installation including also electrical installation and project closure with testing and acceptance by end users. 8
  • 9. 3. High Level schedule The picture above shows the complete Gantt chart for the initial project. We can see that most of tasks cannot be done simultaneously. The only period when we have a bit of slack is at the very beginning with the preliminary studies. 4. Network Diagram and Critical Path The picture below gives a global view of the Network Diagram and critical path (for a more precise one showing name of tasks, please refer to the MS project file). As we can see, on 24 tasks, only 5 are not critical. Thus we can say that our project is very sensitive and any delay in one task will delay the entire project. This can be explained by the nature of the work performed during the project. For example the electrical installation tasks of layering and wiring can’t be done before the equipment is installed in the room. 9
  • 10. 10
  • 11. 5. List of Milestones and Dependencies Milestone Preliminary report 1.1.2 Dates Mon 17/06/13 – Tue 25/06/13(7 days) Wed 10/07/13 - Thu 11/07/13 (2 Days) Mon 12/08/13 (1 Day) Benchmarking documentation 1.2.1.4 Fitness Equipment reception 1.2.3 Electrical wiring 1.3.2.2.2 Mon 19/08/13 - Wed 21/08/13 (2 Day) Wed 21/08/13 – Thu 22/08/13 (1 Day) Testing by GreenWulf 1.4.1 Preliminary report is our first milestone. It is the result of all our research and will condition the entire project especially the requirements for the equipment that will be used for the selection of suppliers. This brings us to the second milestone, the benchmarking documentation. It is crucial that we order the good equipment, without that the project will be a failure. For these 2 first milestones, communication with our sponsor will be important. The third one is the fitness equipment reception after delivery. We need to check that the equipment is not damaged and match the order. All the installation will depend on good reception of the equipment. The fourth milestone is electrical wiring, the last task in terms of installation. We will be able to check if the installation has been done properly and that we are ready for testing the equipment. Testing by Green Wulf is our last milestone. This is the last task were we can potentially readjust the equipment before opening. 6. Risk Assessment / Response A major project of like this can be accompanied by certain amount of unforeseen risks, so we came up with this risk analysis of the GreenWulf project and its remedies: RISK ASSESSMENT FORM Risk event Likelihood Impact Accident/injuries Technical hitches Bad reviews Lack of funds 5 4 2 3 4 3 4 5 Detection difficulty 5 4 3 3 Total 100 48 24 45 11
  • 12. RISK RESPONSE FORM Risk event Response Contingency plan Trigger Accident/injuries Reduce Technical hitches Refer Fall, cuts & electric shock Power cuts Bad reviews Reduce Equipment malfunction Transfer First aid assistant present Technical assistant Regular report to stakeholders Technical assistant then if too serious, Reorder equipments Criticisms during end-user testing Equipment doesn’t work Who is responsible Thomas Ibrahim Camille Amélie Based on this risk assessment, accidents and injuries is most likely of all uncertain events to occur at 100 points and the least being bad reviews with 24 points. C. Finalized schedule 1. Resource requirements and resolution of resource allocation problems The resources required to achieve the project can be split into two main categories: - What can be done by our team (group Green Wulf) What need to be outsourced because we don’t have the required skill sets (group External Contractors and Supplier) Group Green Wulf The beginning of the project consists of doing feasibility studies, selecting the good supplier, the purchase of the equipment and testing the new room before opening. All these tasks are done by our team. In order to transform one fitness room into a sustainable one, Green Wulf needed to invest in Dynamo bikes and treadmills. The fitness room in Carmichael measures about 1,200 ft2. We decided to furnish it with fifteen Dynamo bikes and fifteen treadmills to keep the same capacity as it was. The procurement process is also assured by our team. 12
  • 13. Group External Contractors and Supplier For the rest of the project, we need to hire specialized people for the equipment and electrical installation as well as for the cleaning. - Equipment installation We hired a crew to remove the old equipment and install the new ones. - Electrical installation We needed to set a new electrical installation up to optimize the energy produced by people on the Dynamo bikes and the treadmills. Modernizing the room will also reduce the electricity bill by 30% and enable NCSU to gain an environmental accreditation. The new electrical installation lied in wiring and layering. The electrical wiring and layering consist of choosing the right size receptacle boxes, running cable throughout the room, and making the electrical connections through the walls and the floor. Moreover, the crew will have to repaint the walls and cover the floor back as well. - Cleaning Besides, we called on a cleaning service twice. First to clean the fitness room after the crew removed the old equipment and then, before installing the new ones. The table below summarizes what are our resource requirements: Type Research and documentation Work 17 220,00 € Green Wulf 400% 60,00 €/hr Testing Work 100% 60,00 €/hr Equipment installation Electrical installation Work Work Cost Group Max. Std. Rate Units Resource Name 840,00 € Green Wulf External Contractor External 3 920,00 € Contractor External 300,00 € Contractor 1 520,00 € Cleaning Work Fitness equipment Work 33 150,00 € Supplier 300% 80,00 €/hr 200% 140.00 €/hr 200% 75.00 €/hr 100% 0.00 €/hr Ovt. Rate Cost/Use Accrue At 0.00 0.00 € Prorated €/hr 0.00 0.00 € Prorated €/hr 0.00 0.00 € Prorated €/hr 0.00 0.00 € Prorated €/hr 0.00 0.00 € Prorated €/hr 0.00 33 150.00 € Start €/hr Thanks to a good planning process, we have been able to make accurate estimates concerning our resource. The only one who would have been over allocated is Research and documentation since this resource is used a lot at the beginning. However, we have enough team members to be allocated to every task. 13
  • 14. 2. Rolled up budget estimates Cash Flow statement Cash Flow statement 35000 30000 Dollars 25000 20000 15000 10000 5000 0 03 10 17 24 01 June June June June July 08 July Cost 6720 2940 2100 2100 1680 34830 15 July 22 July 0 0 02 09 05 12 19 26 29 Sept Sept Augu Augu Augu Augu July emb emb st st st st er er 0 0 3490 2670 0 420 0 The major cash flow is incurred when the equipment is ordered. Afterwards, there are no costs until the equipment is received. Phase 1: documentation (preliminary report and benchmarking) We had established some researches on this market in order to be well informed, to benchmark the potential suppliers so that we would choose the optimized solution. All this documentation process cost $17,220. Phase2: order Regarding the new equipment, one dynamo bike costs $1,200. $1,200 x 15 = $18,000. One treadmill costs $1,000 (x15 = $15,000) $1,000 x 15 = $15,000. The delivery costs $75 for each. $75 x 2 = $150. Phase3: installation (receiving/installing equipment, electrical installation and cleaning) As far as the old equipment is concerned, we hired a one truck with a four-man crew for the whole day, meaning eight hours. Their minimum service was three hours for $360. So we needed five additional hours. The additional hour cost $80. $360 + (5 x $80) = $760. 14
  • 15. As regards to the new equipment installation: One Dynamo bike weighed 110 pounds x 15 = 1,650 pounds. One treadmill weighed 220 pounds x 15 = 3,300 pounds. In order to carry 4,950 pounds of equipment, we called on the same team for the whole day as well. $760 x 2 = $1,520. Finally, two specialized people were hired to complete the electrical wiring and the layering. The wiring lasted four days as well as the layering. They were paid $1,960 each. $1,960 x 2 = $3,920. The materials for the complete rewiring and layering job were included. As for the cleaning service, it was composed of two people. They brought their own products, which were included. For a 1,200ft2 room, the minimum service was two hours at $75 per hour. We decided to hire the team for two hours for two different days: after removing the old equipment and before setting up the new ones. $75 x 2 hours = $150 for the first day. $150 x 2 = $300 for the second day. Phase 4: testing This is the last phase of the project. We have to test our equipment to assure security of our dynamo bikes and treadmills. This is done by our team for a cost of $840. EQUIPMENT ORDER 15 dynamo bikes $18,000 15 treadmills $15,000 Delivery cost $150 $33,150 CLEANING SERVICE 2 One 1,200 ft room 2 hours ($75/hour) For two days $300 EQUIPMENT INSTALLATION One truck with a 4-man crew included 3 hours for $360 + (5 x $80) For two days $1,520 ELECTRICAL INSTALLATION 4 days layering and wiring by 2 specialized people at $1,960 each $3,920 Total estimated cost baseline regarding external contractors = $38,890  Total estimated cost baseline included Green Wulf research and external contractors: $56,950. 15
  • 16. Part II Project update A. Status report 1. Narrative of key events to date Prior to the start of Green Wulf project, the team had followed a seminar in order to perfect their skills in all aspects of Project Management, lead by the PM Guru, Steve Del Grosso. Thanks to his effective training and the previous work experiences of team members on similar projects, Green Wulf has managed to make rather realistic estimates for all the project tasks. Thus, at the time of the project status, July 17th 2013, GreenWulf project is on schedule and under costs. The team also managed to write efficiently the preliminary research documents thus shortening the baseline schedule for the first project milestone. However, the technical feasibility study had to be extended from 7 to 9 days in order to secure the knowledge that the estimated energy savings objective will be met, as “failure was not an option”. We had our project sponsor review our report in order to provide us with the “green light” to move forward on the project. As for the second milestone, the team as efficiently researched the equipment suppliers but the first quotes received were much higher than anticipated. Therefore, Green Wulf team had to negotiate during two more days in order to obtain the most competitive quote possible. The selected manufacturer is located in Virginia which will minimize delivery costs compared to some other providers located in California. At the date of the project status, the equipment has been ordered after submitting the benchmarking documents to the NCSU governance, our sponsor, for approval. They were satisfied by our respect of the project priority matrix so far, as the costs were effectively enhanced and the project had not been too much delayed. 16
  • 17. 2. Performance indices Status Report : July 17th, 2013 WBS Task % Complete 1.1.1.1 Energy Study Finished 1.1.1.2 Costing Finished Technical Finished 1.1.1.3 feasibility Study 1.1.1.4 Fallout study Finished Preliminary Finished 1.1.2 report 1.2.1.1 Supplier search Finished 1.2.1.2 Quote requests Finished Supplier Finished 1.2.1.3 selection Banchmarking Finished 1.2.1.4 documentation Fitness 1.2.2 Equipment 29% order Cumulative Totals EV AC PV CV SV 4 200.00 € 1 680.00 € 3 780.00 € 1 680.00 € 4 200.00 € 1 680.00 € 420.00 € 0.00 € 0.00 € 0.00 € 2 940.00 € 3 780.00 € 2 940.00 € -840.00 € 0.00 € 840.00 € 420.00 € 840.00 € 420.00 € 0.00 € 2 940.00 € 2 100.00 € 2 940.00 € 840.00 € 0.00 € 2 100.00 € 840.00 € 1 680.00 € 1 680.00 € 2 100.00 € 840.00 € 420.00 € -840.00 € 0.00 € 0.00 € 840.00 € 420.00 € 840.00 € 420.00 € 0.00 € 840.00 € 840.00 € 840.00 € 0.00 € 0.00 € 9 613. 50 € 9 613. 50 € 9 613. 50 € 0.00 € 0.00 € 26 833.50 € 25 993. 50 € 26 833, 50 € 840.00 € 0.00 € As seen from the Earned Value report above, on July 17th, 2013, the project was on schedule and under cost by 840, 00 €. Since the Fitness Equipment Order task has a fixed cost which amounts to the total price of the bikes and treadmills plus delivery costs, the cost doesn’t vary with the percentage of completion of the task. Thus, the Earned Value equals the Actual Cost of work performed which is also equal to the Planned Value. 3. Project schedule status The phase 1.1: “feasibility studies” has already been completed. We are on Day 33 so the project completion is about 47.8%. The GreenWulf project was expected to last 68.86 days according the WBS and end on Tuesday, August 27, 2013. The project is currently in phase 1.2.2 of the Work Breakdown Structure. Our team has just ordered the fitness equipment online which is expected to be delivered in the following days. The activity is supposed to last 21 days. 17
  • 18. B. Problem solving 1. Description of key problems and issues encountered There was a major hurricane that hit North Carolina and its surrounding cities on 5th August 2013. The hurricane named “Hurricane Rouge (category 2)” due to its unassuming but destructive nature caused severe damages in most cities and small towns in North Carolina. Consequences of the hurricane included flooding, complete power shortage for 3 days and an abrupt end to all activities at offices, schools, etc. following advice of the regional meteorology department. There was a state of emergency for 3 days. The aftermath of the hurricane resulted in the loss of all the order we made for equipments as the driver lost control of the vehicle and plunged in the Lake Johnson in Raleigh. He was advised to stay at home but wanted to finish his work in order to maximize his paycheck. In addition, the Carmichael complex suffered from flood and power outage issues. 18
  • 19. 2. Responses to the problems and how they affected the project First, concerning the lost order, it had no extra-cost on the project’s budget since the manufacturer’s insurance covers hurricane damages. However, the project team had to order again the fitness equipment and wait for the delivery before going further in the project. Secondly, NCSU governance had to arrange the repairs to Carmichael Sports complex that lasted 7 days. In total, due to the hurricane and its aftermath, the Green Wulf project was delayed by 10 days during which we could not process with the project. C. Management issues 1. Problem description In the meantime, our team had to face another challenge: North Carolina State University revised the project’s budget and since they were pleased by our progresses, they decided to renovate the whole fitness complex. The university asked us to be in charge of the installation of the 3 fitness rooms in the Carmichael Gymnasium. It raised some 4 new constraints for our team. The first constraint was to maintain the users’ experience. Since we had to renovate the whole fitness center of the gymnasium, we had to find a strategy that will allow students, faculty and staff to keep on working out during the project duration. The second constraint is to enhance time. Since the project has a new scope, the project will now have a completion date further into the fall semester. The project team is expected to meet the new deadlines and to complete the GreenWulf project as soon as possible in order to offer to students a sustainable gymnasium rapidly without disturbing the gymnasium life. The third constraint is the project performance. Since our team will be in charge of the installation of 2 new rooms, we need to deliver a high quality service as stated in the project scope and expected from the stakeholders. The final constraint is still to manage the costs due to the limited financing available from NC State governance. 2. Response to the issues and how the responses impact the whole project Regarding the new request from North Carolina State University, our team had to find ways to answer the new constraints. First, the project team discussed with the NC State committee about the new project scope and requirements in order to reach a new agreement that matches stakeholders’ expectations with new deadlines for the operational team. 19
  • 20. In order to answer the 3 constraints raised by the new request from NC State, our project team implemented 4 strategies: - To limit costs, we decided to renegotiate with the suppliers to lower the price or waive the delivery fees since we will order a bigger quantity. - To maintain the users’ experience, the GreenWulf project team decided to rotate the fitness rooms one by one so that at least one room would still be accessible for users whereas the others would be under renovation. - To enhance time, the project team is convinced that it will acquire expertise during the first fitness room installation. The expertise acquired will allow the team to better manage the project tasks for the two other rooms installation. - To get a proofed performance, our team extended the feasibility studies to all the fitness rooms. According to the new request from NC State, our project team rescheduled the entire project in order to answer the new project scope. The project duration is now 101.86 days and the new expected completion date is on Thursday, October 24th. We can find below the new project matrix generated for the GreenWulf master project. As we can see on the table, Performance remains the constraint. However, Time came from “accept” to “enhance”. Indeed, time plays a major role in the new project since we now need to install 3 fitness rooms instead of one and the installation needs to impact the gymnasium life as low as possible. Also, Cost came from “enhance” to “accept”. Actually, NC State is willing to finance the gymnasium so the cost is not a real constraint. Now, the project has to focus on Performance and Time. 20
  • 21. D. Revised Project Estimate 1. Projected Cost Given that our previous orders had been destroyed by the hurricane in North Carolina, order and fabrication of the new equipment had to start from scratch. Luckily, Green Wulf did not have to take the cost related to the losses in charge. It was the manufacture’s insurance responsibility. Furthermore, NCSU and stakeholders were really happy of the project so that we had to extend it to three fitness rooms. Regarding the dynamo bikes, we needed to order 15 x 3 fitness rooms = 45,000. The cost per unit was still $1,200. $1,200 x 45 = $54,000. For the treadmill, the manufacturer kept the same price per unit. $1,000 x 45 = $45,000. Our equipment supplier did not charge us for the delivery though, because we ordered in huge quantity. The delivery cost = $0. As for the cleaning service, we asked the two people if adding two extra rooms were possible considering the deadline. They agreed. The price was still $75 per hour for a minimum service of two hours. But they granted us a 8.33% discount. It was $300 for one fitness room, including the two-day work. We relied on that basis. ($300 x 3 rooms) x 8.33% = $825. Regarding the new equipment installation, before the hurricane the four-man crew needed three days to install the bikes and treadmills. After the hurricane, they needed one day more to complete the same task and charged us for that extra day. We paid $1,520 for one fitness room for three-hour work. The crew granted us a 13.3% discount for the two new rooms. We still had to pay the full price for the first one. ($1,520 + ($1,760 x 2)) x 13.3% = $4,448 The last but not the least, the two specialized people in electrical wiring and layering came back and gave us a 15% discount on the total amount. One room cost $3,960 for eight days. ($3,920 x 3 rooms) x 15% = $9,996 for 24 days. 21
  • 22. As for the flood damages to the Carmichael complex, NCSU was responsible for the losses. EQUIPMENT ORDER 45 dynamo bikes $54,000 45 treadmills $45,000 Delivery cost $0 $99,000 CLEANING SERVICE Three 1,200 ft2 rooms 2 hours ($75/hour) 8,33% off For two dates $825 EQUIPMENT INSTALLATION ELECTRICAL INSTALLATION One truck with a 4-man crew for each room + 20% discount for the 2 last rooms for 4 days 4 days layering and wiring by 2 specialized people at $1,960 each x 3 rooms $4,448 $9,996 Total estimated cost baseline regarding external contractors = $114,269 The hurricane as well as the two more fitness rooms modified our internal processes and strategy. We had to do conduct other researches and documentation not to shake up our project and to be as closed as possible to our previous deadlines. This cost us $20,160 (including the test process).  Total estimated cost baseline included the researches and the external contractors: $134,429. At the beginning, our baseline cost was $56,950. After the hurricane and the two additional rooms, it is now $134,429 (a $77,479 extra difference). Let’s calculate the Cost Performance Index (CPI) to determine if we are under cost, on cost or over cost regarding our baseline. CPI = EV / AC (with EV meaning the Earned Value and AC the Actual Cost) = 124,629.32 / 123,821 = 1,01 This means that our project is approximately on cost compared to our forecast. 22
  • 23. 2. Schedule Let’s calculate the Schedule Performance Index (SPI) to determine if we are ahead of schedule, on schedule or behind schedule. SPI = EV / PV (with PV meaning the planned time-phased baseline) = 124,629.32 / 123,621 = 1,01 This means our project is on schedule. We can see on the picture below the effect of the hurricane on the initial project. The delivery has been interrupted and reparations had to be done. After that and once the renegotiation with the supplier if done, we can reorder the equipment and restart the project. 23
  • 24. The second change in the schedule is the addition of 2 more rooms to renovate. The second project starts after the hurricane with a new feasibility studies. It takes less time than the first one since we already did it once; it is only a matter of adaptation to the new room. 24
  • 25. E. Summary 1. Keys to successfully completing the projects In order to meet our overall goal of renovating all 3 fitness rooms and finishing the GreenWulf Project without any (more) sensitive issues that could limit progression of this project, we have identified some vital steps in the project that must be managed correctly and they include the following: Limiting sensitivity of the project One of the key sensitive aspects of this project is the fitness equipment order and reception of order. This is crucial because, the time between order and reception usually takes between 17 to 28 days and any lapse in time will have to change our plans and the project not progressing to the next level of equipment installation and layering of electrical lines. Any wrong delivery of product will also cause this project a great deal so we will have to be very certain about our product orders and specification. We also need to take into consideration the initial feasibility reports as any wrong estimation of the project can lead to performance, time and cost constraints. Therefore the main sensitive aspects of this stage are energy study, costing and technical feasibility study. This well done is very likely to prevent any unforeseen issues in the future of the project. Time management (project duration & delivery end product) As time is of essence in this project, we will have to make sure tasks are performed on schedule and by the right expertise. Some projects must parallel to each other. They could both start on the same day and end at the same finishing time. For instance, whilst fitness equipment orders have been placed, cleaning and clearing out of old equipments could happen since they do not depend on each other to start the next phase of the job (Milestones). In saving time, we will have to seek the service of experts in the various aspects of this project who can be efficient in task completion. And during the project expansion, the same workers will be used since they now have a better understanding of the GreenWulf project and will be extra efficient in delivering good job. This will save the project time and further risks. Respect end user experience To guarantee that student and other users are able to still use the sports Complex when school resumes or even whilst work is still in progress, we will have to rotate from one fitness room to another after work in each room is completed. We must maintain a great level of support to users of the Carmichael Complex and kept them updated on the project by communicating with the project stakeholders. 25
  • 26. 2. Forecast at completion We are going to look at the Variance Cost at Completion (VAC) to determine which activities have gone well or not. It is the difference between EAC and BAC. Negative variance indicates that the project will be completed over budget. On the contrary, positive VACs mean that the activities will be completed less than the budgets. VAC for fitness room 1 = +$992.11 For fitness room 2 = -$146.49 For fitness room 3 = -$146.73 As a result, the fitness room number 1 will be the only one to be completed less than the budgets. Whereas the fitness rooms number 2 and 3 will be completed over budget. Here are the activities that have gone well and the ones that have had some issues: Fitness Rooms Negative VACs Fitness Room 1   technical feasibility study quote requests Fitness Room 2       bikes reception treadmills reception old equipment transfer removal of old equipment electrical wiring fitness equipment reception  Positive VACs       Feasibility study energy study fallout study preliminary report supplier search supplier selection         equipment installation room cleaning new equipment set-up electrical installation layering feasibility study fallout study report Fitness equipment reception Bikes reception Treadmills reception   For the other activities, VACs are $0. Fitness Room 3 26
  • 27. 3. Formal statement of confidence and risk Having experienced some difficulties before the second phase of the project, we were well prepared for the second phase of the project even though we have more workload to do. We did a second risk assessment of and were able to better prepare for any eventualities that could occur. Also with first phase successfully done, we were more confident about executing the second phase of the project quicker and even better with all the experience drawn from the initial part of the project. For instance, we were quite certain of how much energy we could tap from the new rooms because we have already been able to measure how much energy we tap from the first room. 27