SlideShare a Scribd company logo
1 of 39
Procurement of Bulk
Materials Handling
Machines
Richard Morgan
Director
• Stackers
• Reclaimers
• Stacker/Reclaimers
• Shiploaders
• In-pit systems
Equipment Types
• Custom designed
• Long lead Time
• High cost
• Critical elements in supply chain
Features
Identifying requirements
• Configuration
• Specification & procurement documents
• Modularisation
Configuration
Specification
• Define design, material and quality
requirements
• Ensure configuration and performance can be
met realistically
• Good knowledge of the design standards
• Industry experts should be consulted to
ensure that problems are not repeated
• Operators and maintainers should review
• Common practice for shiploaders
• Now possible for land based machines such as
stackers and reclaimers
• Considerable savings in onsite labour.
• Allows procurement from overseas where
costs are lower than in Australia.
• Include transport load cases and sea
fastenings
Modularisation
Type of contract
• Design and Construct (EPC) - Single Contract
• Design and Supply – (Installation &
Commissioning Separate)
• Design Contract – (Supply, Installation &
Commissioning Separate)
Challenges with overseas procurement
• Design
– Design by Experienced OEM - Fabrication
Overseas
– Design by new entrant OEM - Fabrication
Overseas
Challenges with overseas procurement
• Standards
• Materials Substitution
• Fabrication
– Main Structure
– Access
– Machining
– Protective Coatings
– Trial Assembly
Challenges with overseas procurement
• Vendor Items
• Electrical Installation
• Commissioning
Overseas procurement - lessons
• Detailed review of specifications pre award
• Australian Standards discussed pre-award
• Review of the 3D model is needed
• Adequate translation resources needed
• Access design considered throughout the
design phase, not at the end.
• Supplier design 100% prior to placing orders
• Constructability review of design
Effective quality control and supervision
• Design Phase
– Effective Specification
Key Dimensions properly thought out
Interfaces Well Defined
Machine Loads required by other designers
– Owners Engineer Role
– Design Audit
• AS 4324.1 Appendix K guidance for
engagement of a design audit engineer
• Engage Design audit engineer before
specification for machine is finalized
• Involve audit engineer in tender review
Design Audit
Effective quality control and supervision
• Fabrication Phase
– Owners Engineer Role
– Local Inspectors
Shipment, site erection and commissioning
• Modular Construction
• Packing
• Road Transport o/s
• Shipment
• Road Transport in Country
• Erection/Installation Phase
• Cut in
Shipment, site erection and commissioning
• Commissioning
• Deconstruction
Shipment
•
Installation
Deconstruction
THANK YOU

More Related Content

What's hot

Kenya internship
Kenya internshipKenya internship
Kenya internshiphojoman
 
Design process spring 2013
Design process spring 2013Design process spring 2013
Design process spring 2013Bryana Barber
 
RESUME RANDALL V TOINTON 2016
RESUME RANDALL V TOINTON 2016RESUME RANDALL V TOINTON 2016
RESUME RANDALL V TOINTON 2016Randall Tointon
 
2015 Phillip Ballinger Resume MB 20151028 Plain (1)
2015 Phillip Ballinger Resume MB 20151028 Plain (1)2015 Phillip Ballinger Resume MB 20151028 Plain (1)
2015 Phillip Ballinger Resume MB 20151028 Plain (1)Phillip Ballinger
 
Subversion to Perforce in 30 minutes
Subversion to Perforce in 30 minutesSubversion to Perforce in 30 minutes
Subversion to Perforce in 30 minutesPerforce
 
Sagendorf.Roland.resume.v02(2)
Sagendorf.Roland.resume.v02(2)Sagendorf.Roland.resume.v02(2)
Sagendorf.Roland.resume.v02(2)Roland Sagendorf
 
RESUME-MOHAN MUKUND
RESUME-MOHAN MUKUNDRESUME-MOHAN MUKUND
RESUME-MOHAN MUKUNDMukund Mohan
 
John J. Steuby Company Capabilities
John J. Steuby Company CapabilitiesJohn J. Steuby Company Capabilities
John J. Steuby Company Capabilitiesjsalozzo
 
Tin To Professional Resume
Tin To Professional ResumeTin To Professional Resume
Tin To Professional ResumeTin To
 

What's hot (12)

Kenya internship
Kenya internshipKenya internship
Kenya internship
 
Design process spring 2013
Design process spring 2013Design process spring 2013
Design process spring 2013
 
RESUME
RESUMERESUME
RESUME
 
RESUME RANDALL V TOINTON 2016
RESUME RANDALL V TOINTON 2016RESUME RANDALL V TOINTON 2016
RESUME RANDALL V TOINTON 2016
 
Resume New
Resume NewResume New
Resume New
 
2015 Phillip Ballinger Resume MB 20151028 Plain (1)
2015 Phillip Ballinger Resume MB 20151028 Plain (1)2015 Phillip Ballinger Resume MB 20151028 Plain (1)
2015 Phillip Ballinger Resume MB 20151028 Plain (1)
 
Subversion to Perforce in 30 minutes
Subversion to Perforce in 30 minutesSubversion to Perforce in 30 minutes
Subversion to Perforce in 30 minutes
 
Sagendorf.Roland.resume.v02(2)
Sagendorf.Roland.resume.v02(2)Sagendorf.Roland.resume.v02(2)
Sagendorf.Roland.resume.v02(2)
 
William-Ragland Resume
William-Ragland ResumeWilliam-Ragland Resume
William-Ragland Resume
 
RESUME-MOHAN MUKUND
RESUME-MOHAN MUKUNDRESUME-MOHAN MUKUND
RESUME-MOHAN MUKUND
 
John J. Steuby Company Capabilities
John J. Steuby Company CapabilitiesJohn J. Steuby Company Capabilities
John J. Steuby Company Capabilities
 
Tin To Professional Resume
Tin To Professional ResumeTin To Professional Resume
Tin To Professional Resume
 

Viewers also liked

TGA Licensing & Certification Applications: TGA Business Services Portal for ...
TGA Licensing & Certification Applications: TGA Business Services Portal for ...TGA Licensing & Certification Applications: TGA Business Services Portal for ...
TGA Licensing & Certification Applications: TGA Business Services Portal for ...TGA Australia
 
Import clearance procedure
Import clearance procedureImport clearance procedure
Import clearance procedureNits Kedia
 
Top 10 shipping & receiving interview questions with answers
Top 10 shipping & receiving interview questions with answersTop 10 shipping & receiving interview questions with answers
Top 10 shipping & receiving interview questions with answerswillhoward459
 
Freight forwarding presentation
Freight forwarding presentationFreight forwarding presentation
Freight forwarding presentationDanna
 
Procurement best practices
Procurement best practicesProcurement best practices
Procurement best practicesremoeneltigre
 
Warehouse Management System
Warehouse Management SystemWarehouse Management System
Warehouse Management SystemRRChandran
 
Entry level job in Logistics Company
Entry level job in Logistics CompanyEntry level job in Logistics Company
Entry level job in Logistics CompanyManu Pandey
 
Managing warehouse operations. How to manage and run warehouse operations by ...
Managing warehouse operations. How to manage and run warehouse operations by ...Managing warehouse operations. How to manage and run warehouse operations by ...
Managing warehouse operations. How to manage and run warehouse operations by ...Omar Youssef
 
QC Field Engineer 2016
QC Field Engineer 2016QC Field Engineer 2016
QC Field Engineer 2016Michael Nugent
 
Steel building-erection-manual
Steel building-erection-manualSteel building-erection-manual
Steel building-erection-manualPradipat Bubpachat
 
Top 5 structural engineer interview questions with answers
Top 5 structural engineer interview questions with answersTop 5 structural engineer interview questions with answers
Top 5 structural engineer interview questions with answersdianas299
 
Linked in usage
Linked in usageLinked in usage
Linked in usagesrhill93
 

Viewers also liked (20)

CAREER REPORT
CAREER REPORTCAREER REPORT
CAREER REPORT
 
TGA Licensing & Certification Applications: TGA Business Services Portal for ...
TGA Licensing & Certification Applications: TGA Business Services Portal for ...TGA Licensing & Certification Applications: TGA Business Services Portal for ...
TGA Licensing & Certification Applications: TGA Business Services Portal for ...
 
Basic Shipping Documentation.
Basic Shipping Documentation.Basic Shipping Documentation.
Basic Shipping Documentation.
 
Warehouse Management System – WMCentral
Warehouse Management System – WMCentralWarehouse Management System – WMCentral
Warehouse Management System – WMCentral
 
Import clearance procedure
Import clearance procedureImport clearance procedure
Import clearance procedure
 
Top 10 shipping & receiving interview questions with answers
Top 10 shipping & receiving interview questions with answersTop 10 shipping & receiving interview questions with answers
Top 10 shipping & receiving interview questions with answers
 
Freight forwarding presentation
Freight forwarding presentationFreight forwarding presentation
Freight forwarding presentation
 
Procurement best practices
Procurement best practicesProcurement best practices
Procurement best practices
 
Warehouse Management System
Warehouse Management SystemWarehouse Management System
Warehouse Management System
 
Urban Design project 1
Urban Design project 1Urban Design project 1
Urban Design project 1
 
Entry level job in Logistics Company
Entry level job in Logistics CompanyEntry level job in Logistics Company
Entry level job in Logistics Company
 
Warehousing
WarehousingWarehousing
Warehousing
 
Us recruitment
Us recruitmentUs recruitment
Us recruitment
 
Managing warehouse operations. How to manage and run warehouse operations by ...
Managing warehouse operations. How to manage and run warehouse operations by ...Managing warehouse operations. How to manage and run warehouse operations by ...
Managing warehouse operations. How to manage and run warehouse operations by ...
 
Single Belt Oven Conveyor Alignment
Single Belt Oven Conveyor AlignmentSingle Belt Oven Conveyor Alignment
Single Belt Oven Conveyor Alignment
 
QC Field Engineer 2016
QC Field Engineer 2016QC Field Engineer 2016
QC Field Engineer 2016
 
Steel building-erection-manual
Steel building-erection-manualSteel building-erection-manual
Steel building-erection-manual
 
Engineering drawing
Engineering drawingEngineering drawing
Engineering drawing
 
Top 5 structural engineer interview questions with answers
Top 5 structural engineer interview questions with answersTop 5 structural engineer interview questions with answers
Top 5 structural engineer interview questions with answers
 
Linked in usage
Linked in usageLinked in usage
Linked in usage
 

Similar to Bulk Materials Handling Procurement Guide

Naval archtechture and ship constraction introduction
Naval archtechture and ship constraction introductionNaval archtechture and ship constraction introduction
Naval archtechture and ship constraction introductionOlanrewaju O Sulaiman
 
Euro-Rigging presentation 2013
Euro-Rigging presentation 2013Euro-Rigging presentation 2013
Euro-Rigging presentation 2013wesseln
 
Plant Design Engineering Services
Plant Design Engineering ServicesPlant Design Engineering Services
Plant Design Engineering ServicesEnventure
 
Youssef Altaweel- Resume -05-07-2016-
Youssef Altaweel- Resume -05-07-2016-Youssef Altaweel- Resume -05-07-2016-
Youssef Altaweel- Resume -05-07-2016-Youssef Altaweel
 
Easi Engineering an aerotek company
Easi Engineering   an aerotek companyEasi Engineering   an aerotek company
Easi Engineering an aerotek companyAkhil Kumar
 
Standard Design Manual for FRP Composites Gratings
Standard Design Manual for FRP Composites GratingsStandard Design Manual for FRP Composites Gratings
Standard Design Manual for FRP Composites GratingsStrongwell MarketingDept
 
Mouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptxMouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptxZakaria156221
 

Similar to Bulk Materials Handling Procurement Guide (20)

Naval archtechture and ship constraction introduction
Naval archtechture and ship constraction introductionNaval archtechture and ship constraction introduction
Naval archtechture and ship constraction introduction
 
Why EPC
Why EPCWhy EPC
Why EPC
 
The Merits of Structural Steelwork
The Merits of Structural SteelworkThe Merits of Structural Steelwork
The Merits of Structural Steelwork
 
Euro-Rigging presentation 2013
Euro-Rigging presentation 2013Euro-Rigging presentation 2013
Euro-Rigging presentation 2013
 
DFM.ppt
DFM.pptDFM.ppt
DFM.ppt
 
Sydney Resume
Sydney ResumeSydney Resume
Sydney Resume
 
Plant Design Engineering Services
Plant Design Engineering ServicesPlant Design Engineering Services
Plant Design Engineering Services
 
RESUME (11)
RESUME (11)RESUME (11)
RESUME (11)
 
How to avoid Leaky Roofs #PerfectRoof
How to avoid Leaky Roofs #PerfectRoofHow to avoid Leaky Roofs #PerfectRoof
How to avoid Leaky Roofs #PerfectRoof
 
Brochure_Design_Final_11x17_wbleed._Revise
Brochure_Design_Final_11x17_wbleed._ReviseBrochure_Design_Final_11x17_wbleed._Revise
Brochure_Design_Final_11x17_wbleed._Revise
 
Youssef Altaweel- Resume -05-07-2016-
Youssef Altaweel- Resume -05-07-2016-Youssef Altaweel- Resume -05-07-2016-
Youssef Altaweel- Resume -05-07-2016-
 
Vedam Design:- BWTS - Retrofits Services
Vedam Design:-  BWTS - Retrofits Services Vedam Design:-  BWTS - Retrofits Services
Vedam Design:- BWTS - Retrofits Services
 
 
Easi Engineering an aerotek company
Easi Engineering   an aerotek companyEasi Engineering   an aerotek company
Easi Engineering an aerotek company
 
Need fixture for Manufacturing
Need fixture for ManufacturingNeed fixture for Manufacturing
Need fixture for Manufacturing
 
ADLR CONSTRUCTION BROCHURE
ADLR CONSTRUCTION BROCHUREADLR CONSTRUCTION BROCHURE
ADLR CONSTRUCTION BROCHURE
 
CV Dodo NEW
CV Dodo NEWCV Dodo NEW
CV Dodo NEW
 
Standard Design Manual for FRP Composites Gratings
Standard Design Manual for FRP Composites GratingsStandard Design Manual for FRP Composites Gratings
Standard Design Manual for FRP Composites Gratings
 
Resume George LaCasse
Resume George LaCasseResume George LaCasse
Resume George LaCasse
 
Mouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptxMouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptx
 

Recently uploaded

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 

Bulk Materials Handling Procurement Guide

  • 1. Procurement of Bulk Materials Handling Machines Richard Morgan Director
  • 2. • Stackers • Reclaimers • Stacker/Reclaimers • Shiploaders • In-pit systems Equipment Types
  • 3.
  • 4.
  • 5.
  • 6.
  • 7. • Custom designed • Long lead Time • High cost • Critical elements in supply chain Features
  • 8. Identifying requirements • Configuration • Specification & procurement documents • Modularisation
  • 10.
  • 11.
  • 12.
  • 13.
  • 14. Specification • Define design, material and quality requirements • Ensure configuration and performance can be met realistically • Good knowledge of the design standards • Industry experts should be consulted to ensure that problems are not repeated • Operators and maintainers should review
  • 15. • Common practice for shiploaders • Now possible for land based machines such as stackers and reclaimers • Considerable savings in onsite labour. • Allows procurement from overseas where costs are lower than in Australia. • Include transport load cases and sea fastenings Modularisation
  • 16.
  • 17.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22. Type of contract • Design and Construct (EPC) - Single Contract • Design and Supply – (Installation & Commissioning Separate) • Design Contract – (Supply, Installation & Commissioning Separate)
  • 23. Challenges with overseas procurement • Design – Design by Experienced OEM - Fabrication Overseas – Design by new entrant OEM - Fabrication Overseas
  • 24. Challenges with overseas procurement • Standards • Materials Substitution • Fabrication – Main Structure – Access – Machining – Protective Coatings – Trial Assembly
  • 25. Challenges with overseas procurement • Vendor Items • Electrical Installation • Commissioning
  • 26.
  • 27.
  • 28.
  • 29.
  • 30. Overseas procurement - lessons • Detailed review of specifications pre award • Australian Standards discussed pre-award • Review of the 3D model is needed • Adequate translation resources needed • Access design considered throughout the design phase, not at the end. • Supplier design 100% prior to placing orders • Constructability review of design
  • 31. Effective quality control and supervision • Design Phase – Effective Specification Key Dimensions properly thought out Interfaces Well Defined Machine Loads required by other designers – Owners Engineer Role – Design Audit
  • 32. • AS 4324.1 Appendix K guidance for engagement of a design audit engineer • Engage Design audit engineer before specification for machine is finalized • Involve audit engineer in tender review Design Audit
  • 33. Effective quality control and supervision • Fabrication Phase – Owners Engineer Role – Local Inspectors
  • 34. Shipment, site erection and commissioning • Modular Construction • Packing • Road Transport o/s • Shipment • Road Transport in Country • Erection/Installation Phase • Cut in
  • 35. Shipment, site erection and commissioning • Commissioning • Deconstruction

Editor's Notes

  1. We have been involved with materials handling machines at most of the major ports in Australia as well with quite a number of mining operations. These machines are large cost items and their performance is critical to the efficiency and cost effectiveness of the operation. Within the last 10 years there has been a lot of activity in new construction. Many existing machines are also at the end of their design lives and require replacement. However costs have risen dramatically and owners and engineering organisations are actively looking at more cost effective solutions.
  2. The specification for the machine should cover design, material and quality requirements for manufacture and installation, commissioning and hand over to operations, provision of spare parts and requirements for ongoing maintenance. The specification needs to be written to ensure that the configuration and performance parameters upon which the requirements for the machine were determined can be met realistically in practice. Specification of the design requires a good knowledge of the design standards, their limitations and interpretations of the design standards commonly used within the industry. Industry experts should be consulted to ensure that problems commonly encountered on equipment of this type are not repeated should review the specification. The operators and maintainers of the plant have a large influence on the ongoing safe performance of the machine and should also be involved in review of the specification.
  3. A project shipping and transport plan should include details of load-out facilities at the overseas port and should be prepared in conjunction with the shipping agent and local road transport sub-contractor. A detailing ship packing list should be prepared, including all components and equipment. The ship packing list should detail the overall dimensions and weight of each item, therefore allowing a detailed stowage plan to be developed by the freight forwarder. The design engineers need to ensure that the lifting and lashing lugs are captured in the design. Special consideration will need to be given to the packing and quarantine regulations that apply to Australia. The protocol for custom clearance needs to be coordinated with the shipping agent. It large components fabricated overseas will be unloaded and transported to site by road. Due to the restricted space available on site, the major components will often need to be stored off-site in a storage yard and transported when required for erection. Where possible it is desirable to transport the machine to site in as large components as possible. However iot may still be necessary to remove some components such as the counterweights to facilitate safe shipping.
  4. The construction methodology for replacement machines is normally to cordon off an end of the stockpile to allow the existing machines to operate while the new machines are being constructed and commissioned as shown
  5. Once the new machines have been assembled, commissioned, and put into operation, the existing machines can be moved to one end of the yard, the area cordoned off, and the machines deconstructed as shown.