PRINCE2® & Six-Sigma for Data Projects
    The training and consultancy team at Attra Partners writes:

    The recent economic crisis has lead to increasing regulatory focus within banking and finance. Particular
    focus has been on the accuracy of client and market data which has led many leading financial institutions
    to establish data quality and governance functions. Industry opinion is that considerable benefits will result
    in the overall management of data and it's deserved treatment as a fundamental asset will finally be
    recognised. Institutions of all types can no longer afford to haphazardly create and proliferate data within
    their organizations without appropriate governance. The lessons have been learned - quality data is the
    fuel of the modern day enterprise.

    The evolution and establishment of these data quality functions is gradually maturing with the adoption of
    structured approaches, tools & techniques. With extensive experience in the Data Management domain,
    Hany Choueiri has developed a high level framework (using PRINCE2 and Six-Sigma) which can be
    adopted for improved governance of data centric projects. The white paper/high level framework has
    recently been published with case studies underway. Familiarity with PRINCE2 and Six-Sigma is assumed
    in the following diagrams.

    If you have any questions or comments please email sales@attrapartners.com




     Copyright © 2009 Attra Partners Limited. All rights reserved. Reproduction in whole or in part in any form or medium without
                                    express written permission of Attra Partners Ltd is prohibited

Attra Partners Limited is an affiliate of Rovsing Management A/S.   PRINCE2® is a Registered Trademark of the
Rovsing Management A/S is an accredited ATO by the APMG on          Office of Government Commerce in the
behalf of the OGC (Office of Government Commerce U.K.).             United Kingdom and other countries.
PRINCE2
   PRINCE2® integrated with Six-Sigma (DMAIC)                                                                                               (Processes)
   (for Reference & Data Quality Projects)
                                                                                                       One or more       One or more
                                                       Stage #1                 Stage #2               Management Stages Management Stages
                                                                                          Six-Sigma            Six-Sigma               Six-Sigma
                                       Starting-up a                                      (Measure)
                                                                                       Six-Sigma               (Improve)                (Control)
                                          Project                Initiation                (Analyze)
                                                                                       (Improve)
     Project                                                       Stage                     Measure          Execute Data            Develop the
                                        Pre-project                                     Execute Data
                                                                                      Execute Data
     Mandate                                                                             Remediation
                                                                                      Remediation             Remediation              Controls


            Directing              DP                               Give ad-hoc Direction                                Authorize Project Closure

            Executive                     Authorize                    Authorize the                    Authorize a Stage
         Senior Supplier(s)               Initiation                      Project                       or Exception Plan
          Senior User(s)

                                                                                                                         ...
           Managing                    SU                                      SB                SB               SB     ...                   CP
         Project Manager                                                  IP                      CS              CS
                                                                                                                         ...                     CS


           Delivering
          Team Manager                                                                            MP              MP     ...                    MP


                           SU – Staring       MP – Managing         IP – Initiating     SB – Stage      DP – Directing   CS – Controlling   CP – Closing
          PRINCE2          up a Project       Product Delivery      a Project           Boundaries      a Project        a Stage            a Project

          Six-Sigma

Attra Partners Limited is an affiliate of Rovsing Management A/S.              PRINCE2® is a Registered Trademark of the
Rovsing Management A/S is an accredited ATO by the APMG on                     Office of Government Commerce in the
behalf of the OGC (Office of Government Commerce U.K.).                        United Kingdom and other countries.
PRINCE2
   PRINCE2® integrated with Six-Sigma (DMAIC)                                                                       (Processes)
   (for Reference & Data Quality Projects)


    NOTES:
     The Six-Sigma Define phase is mapped onto the PRINCE2 Starting-Up a Project (SU) process. The specific activity
      within SU (not shown in the diagram) being Prepare the Outline Business Case .

     The Six-Sigma Measure and Analyze can be executed in Stage 2 of a PRINCE2 project (or split across a number of
      Stages for very large and complex Data Quality remediation)

     The Managing aStage Boundary (SB) at the end of Stage 2 gives the Project board the opportunity to review the
      status and ensure that accurate analysis has been conducted, and that the ultimate root causes(s) have been
      identified. Authorization to proceed to the next stage (Stage 3) can be given in the Directing a Project Process (DP)
      within the Authorize a Stage or Exception Plan PRINCE2 activity.

     Stage 3 can implement the Six-Sigma Improve phase, which is the heart of the data remediation and quality
      improvement. It may also involve typically involve IT system enhancements and process improvements in order to
      remediate the root cause of the data quality problems. Manual remediation efforts may also involve individuals from the
      Senior User community to assist with data validation.

     Stage 4 can implement the Six-Sigma Control phase which in this model represents the development of the necessary
      Controls (not their implementation). The execution of the Controls can commence post Project Closure after hand-
      over to the most relevant operations group (see next note)

     During the PRINCE2 Closing a Project Process (CP), product handover is undertaken (via the Hand-Over Products
      PRINCE2 activity within CP) and should include not only remediated data, but also the Controls developed during the
      project. These Controls will be executed regularly by the operational groups in order to ensure that the data
      remediation is permanent and no further data corruption occurs



Attra Partners Limited is an affiliate of Rovsing Management A/S.   PRINCE2® is a Registered Trademark of the
Rovsing Management A/S is an accredited ATO by the APMG on          Office of Government Commerce in the
behalf of the OGC (Office of Government Commerce U.K.).             United Kingdom and other countries.
PRINCE2
                                                                                                                               (Organization)
   PRINCE2® integrated with Six-Sigma (DMAIC)
   (for Reference & Data Quality Projects)

                                                  Corporate or programme management


                                                          Project Board
                      Senior User(s)                                                                  Senior Supplier(s)
                                                                    Executive
                                                                                                  Data Quality Stream Lead
                Business Function Head                                                                    IT Lead
                                                           (Head of Data Quality)
                  Asset Class Owner                                                                    Offshore Lead           2



          1 Business, User & Supplier                                                                 Change Authority
                   Project Assurance
                                                    3         Project Manager
                                                                                                       Project Support

                                                              Team Manager(s)



                                              4                Team members

           Typical User Assurance responsibilities can reside with a                  PRINCE2 qualification and a good appreciation of the
      1    RTB/BAU (business as usual) reporting function                        3    Six-Sigma philosophy are paramount.
           In cases where a partially offshore/onshore model is                  4    Team Members typically consist of strong Data Analysts.
     2     adopted, board representation by a senior offshore lead is                 Some Data Modelling expertise may also be beneficial to
           desirable                                                                  help identify weaknesses in the current data landscape

Attra Partners Limited is an affiliate of Rovsing Management A/S.        PRINCE2® is a Registered Trademark of the
Rovsing Management A/S is an accredited ATO by the APMG on               Office of Government Commerce in the
behalf of the OGC (Office of Government Commerce U.K.).                  United Kingdom and other countries.

PRINCE2 and Six-Sigma

  • 1.
    PRINCE2® & Six-Sigmafor Data Projects The training and consultancy team at Attra Partners writes: The recent economic crisis has lead to increasing regulatory focus within banking and finance. Particular focus has been on the accuracy of client and market data which has led many leading financial institutions to establish data quality and governance functions. Industry opinion is that considerable benefits will result in the overall management of data and it's deserved treatment as a fundamental asset will finally be recognised. Institutions of all types can no longer afford to haphazardly create and proliferate data within their organizations without appropriate governance. The lessons have been learned - quality data is the fuel of the modern day enterprise. The evolution and establishment of these data quality functions is gradually maturing with the adoption of structured approaches, tools & techniques. With extensive experience in the Data Management domain, Hany Choueiri has developed a high level framework (using PRINCE2 and Six-Sigma) which can be adopted for improved governance of data centric projects. The white paper/high level framework has recently been published with case studies underway. Familiarity with PRINCE2 and Six-Sigma is assumed in the following diagrams. If you have any questions or comments please email sales@attrapartners.com Copyright © 2009 Attra Partners Limited. All rights reserved. Reproduction in whole or in part in any form or medium without express written permission of Attra Partners Ltd is prohibited Attra Partners Limited is an affiliate of Rovsing Management A/S. PRINCE2® is a Registered Trademark of the Rovsing Management A/S is an accredited ATO by the APMG on Office of Government Commerce in the behalf of the OGC (Office of Government Commerce U.K.). United Kingdom and other countries.
  • 2.
    PRINCE2 PRINCE2® integrated with Six-Sigma (DMAIC) (Processes) (for Reference & Data Quality Projects) One or more One or more Stage #1 Stage #2 Management Stages Management Stages Six-Sigma Six-Sigma Six-Sigma Starting-up a (Measure) Six-Sigma (Improve) (Control) Project Initiation (Analyze) (Improve) Project Stage Measure Execute Data Develop the Pre-project Execute Data Execute Data Mandate Remediation Remediation Remediation Controls Directing DP Give ad-hoc Direction Authorize Project Closure Executive Authorize Authorize the Authorize a Stage Senior Supplier(s) Initiation Project or Exception Plan Senior User(s) ... Managing SU SB SB SB ... CP Project Manager IP CS CS ... CS Delivering Team Manager MP MP ... MP SU – Staring MP – Managing IP – Initiating SB – Stage DP – Directing CS – Controlling CP – Closing PRINCE2 up a Project Product Delivery a Project Boundaries a Project a Stage a Project Six-Sigma Attra Partners Limited is an affiliate of Rovsing Management A/S. PRINCE2® is a Registered Trademark of the Rovsing Management A/S is an accredited ATO by the APMG on Office of Government Commerce in the behalf of the OGC (Office of Government Commerce U.K.). United Kingdom and other countries.
  • 3.
    PRINCE2 PRINCE2® integrated with Six-Sigma (DMAIC) (Processes) (for Reference & Data Quality Projects) NOTES:  The Six-Sigma Define phase is mapped onto the PRINCE2 Starting-Up a Project (SU) process. The specific activity within SU (not shown in the diagram) being Prepare the Outline Business Case .  The Six-Sigma Measure and Analyze can be executed in Stage 2 of a PRINCE2 project (or split across a number of Stages for very large and complex Data Quality remediation)  The Managing aStage Boundary (SB) at the end of Stage 2 gives the Project board the opportunity to review the status and ensure that accurate analysis has been conducted, and that the ultimate root causes(s) have been identified. Authorization to proceed to the next stage (Stage 3) can be given in the Directing a Project Process (DP) within the Authorize a Stage or Exception Plan PRINCE2 activity.  Stage 3 can implement the Six-Sigma Improve phase, which is the heart of the data remediation and quality improvement. It may also involve typically involve IT system enhancements and process improvements in order to remediate the root cause of the data quality problems. Manual remediation efforts may also involve individuals from the Senior User community to assist with data validation.  Stage 4 can implement the Six-Sigma Control phase which in this model represents the development of the necessary Controls (not their implementation). The execution of the Controls can commence post Project Closure after hand- over to the most relevant operations group (see next note)  During the PRINCE2 Closing a Project Process (CP), product handover is undertaken (via the Hand-Over Products PRINCE2 activity within CP) and should include not only remediated data, but also the Controls developed during the project. These Controls will be executed regularly by the operational groups in order to ensure that the data remediation is permanent and no further data corruption occurs Attra Partners Limited is an affiliate of Rovsing Management A/S. PRINCE2® is a Registered Trademark of the Rovsing Management A/S is an accredited ATO by the APMG on Office of Government Commerce in the behalf of the OGC (Office of Government Commerce U.K.). United Kingdom and other countries.
  • 4.
    PRINCE2 (Organization) PRINCE2® integrated with Six-Sigma (DMAIC) (for Reference & Data Quality Projects) Corporate or programme management Project Board Senior User(s) Senior Supplier(s) Executive Data Quality Stream Lead Business Function Head IT Lead (Head of Data Quality) Asset Class Owner Offshore Lead 2 1 Business, User & Supplier Change Authority Project Assurance 3 Project Manager Project Support Team Manager(s) 4 Team members Typical User Assurance responsibilities can reside with a PRINCE2 qualification and a good appreciation of the 1 RTB/BAU (business as usual) reporting function 3 Six-Sigma philosophy are paramount. In cases where a partially offshore/onshore model is 4 Team Members typically consist of strong Data Analysts. 2 adopted, board representation by a senior offshore lead is Some Data Modelling expertise may also be beneficial to desirable help identify weaknesses in the current data landscape Attra Partners Limited is an affiliate of Rovsing Management A/S. PRINCE2® is a Registered Trademark of the Rovsing Management A/S is an accredited ATO by the APMG on Office of Government Commerce in the behalf of the OGC (Office of Government Commerce U.K.). United Kingdom and other countries.