SlideShare a Scribd company logo
1 of 107
Operations
             Management
               Chapter 3 –
               Project Management

                             PowerPoint presentation to accompany
                             Heizer/Render
                             Principles of Operations Management, 7e
                             Operations Management, 9e
© 2008 Prentice Hall, Inc.                                             3–1
Outline
                Global Company Profile: Bechtel
                 Group
                The Importance of Project
                 Management
                Project Planning
                              The Project Manager
                              Work Breakdown Structure
                Project Scheduling

© 2008 Prentice Hall, Inc.                                3–2
Outline - Continued

                Project Controlling
                Project Management Techniques:
                 PERT and CPM
                              The Framework of PERT and CPM
                              Network Diagrams and Approaches
                              Activity-on-Node Example
                              Activity-on-Arrow Example

© 2008 Prentice Hall, Inc.                                       3–3
Outline - Continued
                Determining the Project Schedule
                              Forward Pass
                              Backward Pass
                              Calculating Slack Time and Identifying
                               the Critical Path(s)
                Variability in Activity Times
                              Three Time Estimates in PERT
                              Probability of Project Completion

© 2008 Prentice Hall, Inc.                                              3–4
Outline - Continued
                Cost-Time Trade-Offs and Project
                 Crashing
                A Critique of PERT and CPM
                Using Microsoft Project to Manage
                 Projects
                              Creating a Project Schedule Using MS
                               Project
                              Tracking Progress and Managing
                               Costs Using MS Project
© 2008 Prentice Hall, Inc.                                            3–5
Learning Objectives
            When you complete this chapter you
            should be able to:
                             1. Create a work breakdown
                                structure
                             2. Draw AOA and AON networks
                             3. Complete both forward and
                                backward passes for a project
                             4. Determine a critical path


© 2008 Prentice Hall, Inc.                                      3–6
Learning Objectives
            When you complete this chapter you
            should be able to:
                             5. Calculate the variance of activity
                                times
                             6. Crash a project
                             7. Use Microsoft Project software
                                to create a project



© 2008 Prentice Hall, Inc.                                           3–7
Bechtel Projects
              Building 26 massive distribution centers in just
               two years for the internet company Webvan
               Group ($1 billion)
              Constructing 30 high-security data centers
               worldwide for Equinix, Inc. ($1.2 billion)
              Building and running a rail line between London
               and the Channel Tunnel ($4.6 billion)
              Developing an oil pipeline from the Caspian Sea
               region to Russia ($850 million)
              Expanding the Dubai Airport in the UAE ($600
               million), and the Miami Airport in Florida ($2
               billion)

© 2008 Prentice Hall, Inc.                                        3–8
Bechtel Projects
              Building liquid natural gas plants in Yemen $2
               billion) and in Trinidad, West Indies ($1 billion)
              Building a new subway for Athens, Greece ($2.6
               billion)
              Constructing a natural gas pipeline in Thailand
               ($700 million)
              Building 30 plants for iMotors.com, a company
               that sells refurbished autos online ($300 million)
              Building a highway to link the north and south of
               Croatia ($303 million)



© 2008 Prentice Hall, Inc.                                          3–9
Strategic Importance of
                               Project Management
              Microsoft Windows Vista Project:
                          hundreds of programmers
                          millions of lines of code
                          hundreds of millions of dollars cost
              Hard Rock Cafe Rockfest Project:
                          100,000 + fans
                          planning began 9 months in advance

© 2008 Prentice Hall, Inc.                                        3 – 10
Project Characteristics

                  Single unit
                  Many related activities
                  Difficult production planning and
                   inventory control
                  General purpose equipment
                  High labor skills


© 2008 Prentice Hall, Inc.                             3 – 11
Examples of Projects
              Building Construction




                                         Research Project

© 2008 Prentice Hall, Inc.                                   3 – 12
Management of Projects
             1. Planning - goal setting, defining the
                project, team organization
             2. Scheduling - relates people, money,
                and supplies to specific activities
                and activities to each other
             3. Controlling - monitors resources,
                costs, quality, and budgets; revises
                plans and shifts resources to meet
                time and cost demands
© 2008 Prentice Hall, Inc.                              3 – 13
Project Management
                                  Activities
          Planning
                                                               Scheduling
                   Objectives
                                                                   Project activities
                   Resources
                                                                   Start & end times
                   Work break-down
                    schedule                                       Network
                   Organization




                         Controlling
                              Monitor, compare, revise, action
© 2008 Prentice Hall, Inc.                                                         3 – 14
Project Planning,
              Scheduling, and Controlling




               Figure 3.1

          Before             Start of project   During
          project               Timeline        project
© 2008 Prentice Hall, Inc.                                3 – 15
Project Planning,
              Scheduling, and Controlling




               Figure 3.1

          Before             Start of project   During
          project               Timeline        project
© 2008 Prentice Hall, Inc.                                3 – 16
Project Planning,
              Scheduling, and Controlling




               Figure 3.1

          Before             Start of project   During
          project               Timeline        project
© 2008 Prentice Hall, Inc.                                3 – 17
Project Planning,
              Scheduling, and Controlling




               Figure 3.1

          Before             Start of project   During
          project               Timeline        project
© 2008 Prentice Hall, Inc.                                3 – 18
Project Time/cost estimates
                           Planning,
                          Budgets
              Scheduling, and Controlling
                          Engineering diagrams
                          Cash flow charts
                                  Material availability details



                                                Budgets
                                                Delayed activities report
                                                Slack activities report


     CPM/PERT
     Gantt charts
     Milestone charts
     Cash flow schedules

               Figure 3.1

          Before             Start of project                     During
          project               Timeline                          project
© 2008 Prentice Hall, Inc.                                                  3 – 19
Project Planning
       Establishing objectives
       Defining project
       Creating work
        breakdown structure
       Determining
        resources
       Forming organization




© 2008 Prentice Hall, Inc.                      3 – 20
Project Organization
           Often temporary structure
           Uses specialists from entire company
           Headed by project manager
                        Coordinates activities
                        Monitors schedule
                         and costs
           Permanent
            structure called
            ‘matrix organization’

© 2008 Prentice Hall, Inc.                          3 – 21
A Sample Project
                                     Organization
                                                       President


             Human                                                          Quality
            Resources            Marketing   Finance           Design                 Production
                                                                             Mgt


                             Project 1       Project
                                             Manager
                                                             Mechanical      Test
                                                                                      Technician
                                                              Engineer     Engineer


                             Project 2       Project
                                             Manager
                                                              Electrical   Computer
                                                                                      Technician
                                                              Engineer     Engineer
       Figure 3.2


© 2008 Prentice Hall, Inc.                                                                         3 – 22
Project Organization
                              Works Best When
                1. Work can be defined with a specific
                   goal and deadline
                2. The job is unique or somewhat
                   unfamiliar to the existing organization
                3. The work contains complex
                   interrelated tasks requiring specialized
                   skills
                4. The project is temporary but critical to
                   the organization
                5. The project cuts across organizational
                   lines
© 2008 Prentice Hall, Inc.                                    3 – 23
Matrix Organization
                             Marketing   Operations   Engineering   Finance

           Project 1


           Project 2


           Project 3


           Project 4




© 2008 Prentice Hall, Inc.                                                    3 – 24
The Role of
                             the Project Manager
             Highly visible
             Responsible for making sure that:

                    All necessary activities are finished in order
                     and on time
                    The project comes in within budget
                    The project meets quality goals
                    The people assigned to the project receive
                     motivation, direction, and information

© 2008 Prentice Hall, Inc.                                            3 – 25
The Role of
                             the Project Manager
             Highly visible
             Responsible for making sure that: should be:
                               Project managers
                                        Good coaches
                    All necessary activities are finished in order
                     and on time        Good communicators
                    The project comes in withinorganize activities
                                        Able to budget
                                          from a variety of disciplines
                    The project meets quality goals
                    The people assigned to the project receive
                     motivation, direction, and information

© 2008 Prentice Hall, Inc.                                                3 – 26
Ethical Issues
              Bid rigging – divulging confidential information
               to give some bidders an unfair advantage
              “Low balling” contractors – try to “buy” the
               project by bidding low and hope to renegotiate
               or cut corners
              Bribery – particularly on international projects
              Expense account padding
              Use of substandard materials
              Compromising health and safety standards
              Withholding needed information
              Failure to admit project failure at close
© 2008 Prentice Hall, Inc.                                        3 – 27
Work Breakdown Structure
                Level
                1. Project
                2.           Major tasks in the project
                3.            Subtasks in the major tasks
                4.              Activities (or work packages)
                                to be completed


© 2008 Prentice Hall, Inc.                                      3 – 28
Work Breakdown Structure
                             Level ID
                 Level       Number     Activity
                      1      1.0        Develop/launch Windows Vista OS
                      2      1.1           Develop of GUIs
                      2      1.2           Ensure compatibility with earlier
                                           Windows versions
                      3      1.21             Compatibility with Windows ME
                      3      1.22             Compatibility with Windows XP
                      3      1.23             Compatibility with Windows 2000
                      4      1.231                 Ensure ability to import files

                                                                             Figure 3.3

© 2008 Prentice Hall, Inc.                                                                3 – 29
Project Scheduling
           Identifying precedence
            relationships
           Sequencing activities
           Determining activity
            times & costs
           Estimating material &
            worker requirements
           Determining critical
            activities
© 2008 Prentice Hall, Inc.                        3 – 30
Purposes of Project
                                 Scheduling
             1. Shows the relationship of each activity to
                others and to the whole project
             2. Identifies the precedence relationships
                among activities
             3. Encourages the setting of realistic time
                and cost estimates for each activity
             4. Helps make better use of people, money,
                and material resources by identifying
                critical bottlenecks in the project
© 2008 Prentice Hall, Inc.                                   3 – 31
Scheduling Techniques
                    1. Ensure that all activities are
                       planned for
                    2. Their order of performance is
                       accounted for
                    3. The activity time estimates are
                       recorded
                    4. The overall project time is
                       developed

© 2008 Prentice Hall, Inc.                               3 – 32
Project Management
                                 Techniques
                                     Gantt chart
                                     Critical Path Method
                                      (CPM)
                                     Program Evaluation
                                      and Review
                                      Technique (PERT)




© 2008 Prentice Hall, Inc.                                   3 – 33
A Simple Gantt Chart

                                             Time
                                J   F   M   A M J   J   A   S

               Design
               Prototype
               Test
               Revise
               Production



© 2008 Prentice Hall, Inc.                                      3 – 34
Service For A Delta Jet
                                Deplaning
          Passengers
                                Baggage claim
          Baggage               Container offload
                                Pumping
          Fueling
                                Engine injection water
          Cargo and mail        Container offload
                                Main cabin door
          Galley servicing
                                Aft cabin door
          Lavatory servicing    Aft, center, forward
          Drinking water        Loading
                                First-class section
          Cabin cleaning
                                Economy section
          Cargo and mail        Container/bulk loading
                                Galley/cabin check
          Flight services
                                Receive passengers
          Operating crew        Aircraft check
          Baggage               Loading
          Passengers            Boarding
                                                         0   10        20       30    40
           Figure 3.4                                             Time, Minutes
© 2008 Prentice Hall, Inc.                                                           3 – 35
Project Control Reports
               Detailed cost breakdowns for each task
               Total program labor curves
               Cost distribution tables
               Functional cost and hour summaries
               Raw materials and expenditure forecasts
               Variance reports
               Time analysis reports
               Work status reports

© 2008 Prentice Hall, Inc.                                3 – 36
PERT and CPM
                  Network techniques
                  Developed in 1950’s
                              CPM by DuPont for chemical plants (1957)
                              PERT by Booz, Allen & Hamilton with the
                               U.S. Navy, for Polaris missile (1958)
                  Consider precedence relationships and
                   interdependencies
                  Each uses a different estimate of
                   activity times

© 2008 Prentice Hall, Inc.                                                3 – 37
Six Steps PERT & CPM

            1. Define the project and prepare the
               work breakdown structure
            2. Develop relationships among the
               activities - decide which activities
               must precede and which must follow
               others
            3. Draw the network connecting all of
               the activities

© 2008 Prentice Hall, Inc.                            3 – 38
Six Steps PERT & CPM

            4. Assign time and/or cost estimates
               to each activity
            5. Compute the longest time path
               through the network – this is called
               the critical path
            6. Use the network to help plan,
               schedule, monitor, and control the
               project

© 2008 Prentice Hall, Inc.                            3 – 39
Questions PERT & CPM
                            Can Answer
             1. When will the entire project be
                completed?
             2. What are the critical activities or tasks in
                the project?
             3. Which are the noncritical activities?
             4. What is the probability the project will be
                completed by a specific date?


© 2008 Prentice Hall, Inc.                                     3 – 40
Questions PERT & CPM
                            Can Answer
             5. Is the project on schedule, behind
                schedule, or ahead of schedule?
             6. Is the money spent equal to, less than, or
                greater than the budget?
             7. Are there enough resources available to
                finish the project on time?
             8. If the project must be finished in a shorter
                time, what is the way to accomplish this
                at least cost?
© 2008 Prentice Hall, Inc.                                     3 – 41
A Comparison of AON and
                 AOA Network Conventions
                   Activity on              Activity           Activity on
                   Node (AON)               Meaning           Arrow (AOA)
                                         A comes before
     (a) A                   B       C   B, which comes
                                         before C             A       B       C
                       A                                          A
                                         A and B must both
    (b)                          C       be completed
                                         before C can start               C
                       B                                          B
                                 B
                                         B and C cannot
    (c)                 A                begin until A is                 B
                                         completed                A
    Figure 3.5
                                 C                                        C
© 2008 Prentice Hall, Inc.                                                        3 – 42
A Comparison of AON and
                 AOA Network Conventions
                   Activity on      Activity           Activity on
                   Node (AON)       Meaning           Arrow (AOA)

                                 C and D cannot
                  A          C   begin until both       A    C
     (d)                         A and B are
                                 completed
                  B          D                          B    D

                                 C cannot begin
                                 until both A and B
                  A          C   are completed; D      A      C
    (e)                          cannot begin until         Dummy activity
                                 B is completed. A
                  B          D   dummy activity is
                                 introduced in AOA     B      D
    Figure 3.5
© 2008 Prentice Hall, Inc.                                            3 – 43
A Comparison of AON and
                 AOA Network Conventions
                   Activity on         Activity            Activity on
                   Node (AON)          Meaning            Arrow (AOA)

                                     B and C cannot
                                     begin until A is
                                     completed. D
                  A          B   D   cannot begin            A      B       D
                                     until both B and
      (f)                            C are completed.    Dummy
                                     A dummy                            C
                             C                           activity
                                     activity is again
                                     introduced in
                                     AOA.


    Figure 3.5
© 2008 Prentice Hall, Inc.                                                      3 – 44
AON Example
            Milwaukee Paper Manufacturing's
            Activities and Predecessors
                                                                 Immediate
              Activity                   Description            Predecessors
                A            Build internal components               —
                     B       Modify roof and floor                   —
                     C       Construct collection stack              A
                     D       Pour concrete and install frame        A, B
                      E      Build high-temperature burner           C
                      F      Install pollution control system        C
                     G       Install air pollution device           D, E
                     H       Inspect and test                       F, G

                                                                    Table 3.1
© 2008 Prentice Hall, Inc.                                                      3 – 45
AON Network for
                                 Milwaukee Paper

                                            Activity A
                             A    (Build Internal Components)


            Start


                                         Activity B
      Start                  B    (Modify Roof and Floor)
     Activity

                                                                Figure 3.6
© 2008 Prentice Hall, Inc.                                              3 – 46
AON Network for
                                 Milwaukee Paper
                             Activity A Precedes Activity C

                             A             C


            Start



                             B              D

                                 Activities A and B
                                 Precede Activity D           Figure 3.7
© 2008 Prentice Hall, Inc.                                            3 – 47
AON Network for
                                 Milwaukee Paper

                                                       F
                             A           C

                                                 E
            Start                                           H


                             B            D            G

                                  Arrows Show Precedence
                                       Relationships
                                                           Figure 3.8
© 2008 Prentice Hall, Inc.                                       3 – 48
AOA Network for
                                   Milwaukee Paper
                                                 C
                                         2              4
                                             (Construct
                                               Stack)
                                                                           F
                                                                 Co (In
                                nt nal



                                                                   nt sta
                                  s)
                              ne e r




                                                        (Build Burner)
                        o m ld A




                                                        (Build Burner)
                                                                      ro ll
                           po Int




                                                                        ls
                                                                          )
                       C ui




                                                                                                H
                                             Dummy                                                       7
                        (B




                                                               E
                  1                                                                     6
                                                               E
                                             Activity                                       (Inspect/
                                                                                              Test)
                   Ro (M B                                               G
                     of od                                                      ll
                       / F i fy                                             st a io n
                          lo
                             or                                           In lut e)
                                                                         ( l ic
                               )                D                         Po ev
                                         3              5                    D
                                             (Pour
                                           Concrete/
                                         Install Frame)                                                 Figure 3.9
© 2008 Prentice Hall, Inc.                                                                                      3 – 49
Determining the Project
                                   Schedule
             Perform a Critical Path Analysis
                  The critical path is the longest path
                   through the network
                  The critical path is the shortest time in
                   which the project can be completed
                  Any delay in critical path activities
                   delays the project
                  Critical path activities have no slack
                   time
© 2008 Prentice Hall, Inc.                                     3 – 50
Determining the Project
                                   Schedule
             Perform a Critical Path Analysis
                   Activity    Description                      Time (weeks)
                     A         Build internal components              2
                     B         Modify roof and floor                  3
                     C         Construct collection stack             2
                     D         Pour concrete and install frame        4
                     E         Build high-temperature burner          4
                     F         Install pollution control system       3
                     G         Install air pollution device           5
                     H         Inspect and test                       2
                               Total Time (weeks)                    25
                                                                         Table 3.2
© 2008 Prentice Hall, Inc.                                                       3 – 51
Determining the Project
                                   Schedule
             Perform a Critical Path Analysis
                                                Earliest start (ES) =   earliest time at
                             Activity   Description an activity can start, Time (weeks)
                                                which                       assuming
                               A        Build internal components been completed
                                                all predecessors have              2
                               B        Modify roof and floor
                                                Earliest finish (EF) =             3
                                                                        earliest time at
                               C        Construct collection stack be finished 2
                                                which an activity can
                               D        Pour concrete and(LS) = frame
                                                Latest start install               4
                                                                        latest time at
                               E        Build high-temperature can start so as to not
                                                which an activity burner           4
                               F        Install delay the completion time of the entire
                                                 pollution control system          3
                                                project
                               G        Install air pollution device               5
                                                Latest finish (LF) =    latest time by
                               H        Inspect and testactivity has to be finished so
                                                which an                           2
                                        Total Time (weeks) the completion time of Table 3.2
                                                                                   25
                                                as to not delay
© 2008 Prentice Hall, Inc.                      the entire project                         3 – 52
Determining the Project
                                   Schedule
             Perform a Critical Path Analysis
                             Activity Name
                              or Symbol
                                             A            Earliest
                         Earliest      ES         EF       Finish
                          Start


                        Latest         LS         LF       Latest
                         Start               2             Finish


       Figure 3.10                               Activity Duration
© 2008 Prentice Hall, Inc.                                           3 – 53
Forward Pass
             Begin at starting event and work forward
              Earliest Start Time Rule:

                         If an activity has only a single immediate
                          predecessor, its ES equals the EF of the
                          predecessor
                         If an activity has multiple immediate
                          predecessors, its ES is the maximum of
                          all the EF values of its predecessors

                       ES = Max {EF of all immediate predecessors}

© 2008 Prentice Hall, Inc.                                             3 – 54
Forward Pass
             Begin at starting event and work forward
              Earliest Finish Time Rule:

                         The earliest finish time (EF) of an activity
                          is the sum of its earliest start time (ES)
                          and its activity time



                                   EF = ES + Activity time




© 2008 Prentice Hall, Inc.                                               3 – 55
ES/EF Network for
                                  Milwaukee Paper

              ES                              EF = ES + Activity time
                                  Start
                             0            0


                                   0




© 2008 Prentice Hall, Inc.                                              3 – 56
ES/EF Network for
                                  Milwaukee Paper
                                                    EF of A =
                                  ES                ES of A + 2
                                 of A
                                            A
                Start                   0       2
         0                   0

                   0

                                            2



© 2008 Prentice Hall, Inc.                                        3 – 57
ES/EF Network for
                                      Milwaukee Paper
                                     A
                                 0       2

                                     2                          EF of B =
                                              ES                ES of B + 3
         0
                Start
                             0               of B
                                                        B
                   0                                0       3


                                                        3
© 2008 Prentice Hall, Inc.                                                3 – 58
ES/EF Network for
                                      Milwaukee Paper
                                     A           C
                                 0       2   2       4

                                     2           2

                Start
         0                   0

                   0

                                     B
                                 0       3

                                     3



© 2008 Prentice Hall, Inc.                               3 – 59
ES/EF Network for
                                      Milwaukee Paper
                                     A              C
                                 0        2     2       4

                                     2              2

                Start
         0                   0
                                         = Max (2, 3)           D
                   0
                                                            3       7
                                     B
                                 0        3

                                     3
                                                                4
© 2008 Prentice Hall, Inc.                                              3 – 60
ES/EF Network for
                                      Milwaukee Paper
                                     A           C
                                 0       2   2       4

                                     2           2

                Start
         0                   0

                   0

                                     B           D
                                 0       3   3       7

                                     3           4



© 2008 Prentice Hall, Inc.                               3 – 61
ES/EF Network for
                                      Milwaukee Paper
                                     A           C                       F
                                 0       2   2       4               4       7

                                     2           2                       3

                Start                                        E                         H
         0                   0                           4       8                13       15

                   0                                         4                         2

                                     B           D                       G
                                 0       3   3       7               8       13

                                     3           4                       5
                                                                                  Figure 3.11

© 2008 Prentice Hall, Inc.                                                                 3 – 62
Backward Pass
             Begin with the last event and work backwards

              Latest Finish Time Rule:

                   If an activity is an immediate predecessor
                     for just a single activity, its LF equals the
                     LS of the activity that immediately follows
                     it
                   If an activity is an immediate predecessor
                     to more than one activity, its LF is the
                     minimum of all LS values of all activities
                     that immediately follow it
                 LF = Min {LS of all immediate following activities}

© 2008 Prentice Hall, Inc.                                             3 – 63
Backward Pass
             Begin with the last event and work backwards

              Latest Start Time Rule:

                     The latest start time (LS) of an activity is
                      the difference of its latest finish time (LF)
                      and its activity time


                                LS = LF – Activity time




© 2008 Prentice Hall, Inc.                                            3 – 64
LS/LF Times for
                                         Milwaukee Paper
                                     A                C                       F
                                 0        2       2       4               4       7

                                     2                2                       3

                Start                                             E                         H
         0                   0                                4       8                13       15
                                                                                       13       15
                   0                                              4                         2

                                     B        LS = LF – Activity time
                                                    D               G
                                 0        3       3       7               8       13

                                     3                4                       5    LF = EF
                                                                                  of Project
© 2008 Prentice Hall, Inc.                                                                      3 – 65
LS/LF Times for
                                         Milwaukee Paper
                                     A            C                  F
                                 0        2   2       4          4       7

                                                                10       13
                                     2            2                  3

                Start                                     E                        H
         0                   0
                                                    LF = Min(LS of
                                                       4     8                13       15
                                                  following activity)         13       15
                   0                                      4                        2

                                     B            D                  G
                                 0        3   3       7          8       13

                                     3            4                  5



© 2008 Prentice Hall, Inc.                                                             3 – 66
LS/LF Times for
                                         Milwaukee Paper
                                              LF = Min(4, 10)


                                     A             C                        F
                                 0        2    2       4               4        7

                                               2       4               10       13
                                     2             2                        3

                Start                                          E                          H
         0                   0                             4       8                 13       15

                                                           4       8                 13       15
                   0                                           4                          2

                                     B             D                        G
                                 0        3    3       7               8        13
                                                                       8        13
                                     3             4                        5



© 2008 Prentice Hall, Inc.                                                                    3 – 67
LS/LF Times for
                                         Milwaukee Paper
                                     A            C                        F
                                 0        2   2       4               4        7

                                 0        2   2       4               10       13
                                     2            2                        3

                Start                                         E                          H
         0                   0                            4       8                 13       15

          0                  0                            4       8                 13       15
                   0                                          4                          2

                                     B            D                        G
                                 0        3   3       7               8        13
                                 1        4   4       8               8        13
                                     3            4                        5



© 2008 Prentice Hall, Inc.                                                                   3 – 68
Computing Slack Time
             After computing the ES, EF, LS, and LF times
             for all activities, compute the slack or free
             time for each activity

                     Slack is the length of time an activity can
                      be delayed without delaying the entire
                      project


                             Slack = LS – ES   or   Slack = LF – EF



© 2008 Prentice Hall, Inc.                                            3 – 69
Computing Slack Time
                   Earliest Earliest    Latest   Latest               On
                    Start    Finish      Start   Finish    Slack    Critical
          Activity   ES        EF         LS       LF     LS – ES    Path

                 A             0    2     0        2         0        Yes
                 B             0    3     1        4         1         No
                 C             2    4     2        4         0        Yes
                 D             3    7     4        8         1         No
                 E             4    8     4        8         0        Yes
                 F             4    7    10       13         6         No
                 G             8   13     8       13         0        Yes
                 H            13   15    13       15         0        Yes

                                                                    Table 3.3

© 2008 Prentice Hall, Inc.                                                      3 – 70
Critical Path for
                                         Milwaukee Paper
                                     A            C                        F
                                 0        2   2       4               4        7

                                 0        2   2       4               10       13
                                     2            2                        3

                Start                                         E                          H
         0                   0                            4       8                 13       15

          0                  0                            4       8                 13       15
                   0                                          4                          2

                                     B            D                        G
                                 0        3   3       7               8        13
                                 1        4   4       8               8        13
                                     3            4                        5



© 2008 Prentice Hall, Inc.                                                                   3 – 71
ES – EF Gantt Chart
                             for Milwaukee Paper
                                  1   2   3   4   5   6   7   8   9   10 11 12 13 14 15 16

        A Build internal
          components
        B Modify roof and floor
        C Construct collection
          stack
        D Pour concrete and
          install frame
        E Build high-
          temperature burner
        F Install pollution
          control system
        G Install air pollution
          device
        H Inspect and test

© 2008 Prentice Hall, Inc.                                                              3 – 72
LS – LF Gantt Chart
                             for Milwaukee Paper
                                  1   2   3   4   5   6   7   8   9   10 11 12 13 14 15 16

        A Build internal
          components
        B Modify roof and floor
        C Construct collection
          stack
        D Pour concrete and
          install frame
        E Build high-
          temperature burner
        F Install pollution
          control system
        G Install air pollution
          device
        H Inspect and test

© 2008 Prentice Hall, Inc.                                                              3 – 73
Variability in Activity Times

              CPM assumes we know a fixed time
               estimate for each activity and there
               is no variability in activity times
              PERT uses a probability distribution
               for activity times to allow for
               variability



© 2008 Prentice Hall, Inc.                            3 – 74
Variability in Activity Times

             Three time estimates are required
                         Optimistic time (a) – if everything goes
                          according to plan
                         Pessimistic time (b) – assuming very
                          unfavorable conditions
                         Most likely time (m) – most realistic
                          estimate



© 2008 Prentice Hall, Inc.                                           3 – 75
Variability in Activity Times
           Estimate follows beta distribution
           Expected time:
                      t = (a + 4m + b)/6
           Variance of times:
                        v = [(b – a)/6]2




© 2008 Prentice Hall, Inc.                      3 – 76
Variability in Activity Times
           Estimate follows beta distribution
           Expected time:                                 Figure 3.12

                           t = (a + 4m + b)/6
               Probability of
           Variance of times:
               1 in 100 of                     Probability
                Probability




               < a occurring                   of 1 in 100 of
                              v = [(b − a)/6]2 > b occurring

                                                               Activity
                                                                Time

                              Optimistic   Most Likely   Pessimistic
                               Time (a)     Time (m)      Time (b)

© 2008 Prentice Hall, Inc.                                                3 – 77
Computing Variance
                                          Most                     Expected
                             Optimistic   Likely   Pessimistic       Time              Variance
      Activity                   a          m           b        t = (a + 4m + b)/6    [(b – a)/6]2

            A                    1          2          3                  2               .11
            B                    2          3          4                  3               .11
            C                    1          2          3                  2               .11
            D                    2          4          6                  4               .44
            E                    1          4          7                  4              1.00
            F                    1          2          9                  3              1.78
            G                    3          4         11                  5              1.78
            H                    1          2          3                  2               .11

                                                                                      Table 3.4

© 2008 Prentice Hall, Inc.                                                                        3 – 78
Probability of Project
                                  Completion
                     Project variance is computed by
                     summing the variances of critical
                     activities
                             σ 2 =pProject variance

                                = ∑ (variances of activities
                                    on critical path)




© 2008 Prentice Hall, Inc.                                     3 – 79
Probability of Project
                                 Completion
                 Project variance is computed by
                 summing the variances of critical
               Project variance
                 activities
               σ 2 =p.11 + .11 + 1.00 + 1.78 + .11 = 3.11


               Project standard deviation
               σp =           Project variance

                         =    3.11 = 1.76 weeks

© 2008 Prentice Hall, Inc.                                  3 – 80
Probability of Project
                                 Completion
                PERT makes two more assumptions:

                  Total project completion times follow a
                   normal probability distribution
                  Activity times are statistically
                   independent




© 2008 Prentice Hall, Inc.                                   3 – 81
Probability of Project
                                 Completion
                                    Standard deviation = 1.76 weeks




                                         15 Weeks
                                 (Expected Completion Time)
                 Figure 3.13

© 2008 Prentice Hall, Inc.                                            3 – 82
Probability of Project
                                 Completion
           What is the probability this project can
           be completed on or before the 16 week
           deadline?

                                   due    expected date
                               Z = date – of completion /σ p

                                = (16 wks – 15 wks)/1.76
                                             Where Z is the number of
                                = 0.57     standard deviations the due
                                           date or target date lies from
                                            the mean or expected date
© 2008 Prentice Hall, Inc.                                                 3 – 83
Probability of Project
                                      Completion
                             From Appendix I
           What is the probability this project can
                         .00    .01       .07    .08
           be completed on or before the 16 week
                    .1 .50000 .50399    .52790 .53188
           deadline? .53983 .54380
                    .2                  .56749 .57142

                                      due    expected date
                              .5 Z.69146 .69497 completion /σ
                                   = date − of      .71566 .71904
                                                              p
                              .6   .72575   .72907     .74857   .75175
                                   = (16 wks − 15 wks)/1.76
                                                  Where Z is the number of
                                   = 0.57       standard deviations the due
                                                date or target date lies from
                                                 the mean or expected date
© 2008 Prentice Hall, Inc.                                                      3 – 84
Probability of Project
                                 Completion

                                       0.57 Standard deviations
                   Probability
                   (T ≤ 16 weeks)
                   is 71.57%




                                      15    16           Time
                                    Weeks   Weeks
                 Figure 3.14

© 2008 Prentice Hall, Inc.                                        3 – 85
Determining Project
                               Completion Time

                             Probability
                               of 0.99

                                                                   Probability
                                                                     of 0.01



                                                   2.33 Standard           Z
                             From Appendix I         deviations
                                               0               2.33
                 Figure 3.15

© 2008 Prentice Hall, Inc.                                                       3 – 86
Variability of Completion
                   Time for Noncritical Paths
                Variability of times for activities on
                 noncritical paths must be
                 considered when finding the
                 probability of finishing in a
                 specified time
                Variation in noncritical activity
                 may cause change in critical path


© 2008 Prentice Hall, Inc.                                3 – 87
What Project Management
                     Has Provided So Far
               The project’s expected completion time
                is 15 weeks
               There is a 71.57% chance the equipment
                will be in place by the 16 week deadline
               Five activities (A, C, E, G, and H) are on
                the critical path
               Three activities (B, D, F) are not on the
                critical path and have slack time
               A detailed schedule is available

© 2008 Prentice Hall, Inc.                                   3 – 88
Trade-Offs And Project
                                   Crashing
            It is not uncommon to face the
            following situations:
                       The project is behind schedule
                       The completion time has been
                        moved forward

                          Shortening the duration of the
                         project is called project crashing
© 2008 Prentice Hall, Inc.                                    3 – 89
Factors to Consider When
                      Crashing A Project
              The amount by which an activity is
               crashed is, in fact, permissible
              Taken together, the shortened
               activity durations will enable us to
               finish the project by the due date
              The total cost of crashing is as small
               as possible

© 2008 Prentice Hall, Inc.                              3 – 90
Steps in Project Crashing

             1. Compute the crash cost per time period.
                If crash costs are linear over time:

                   Crash cost   (Crash cost – Normal cost)
                   per period = (Normal time – Crash time)

             2. Using current activity times, find the
                critical path and identify the critical
                activities


© 2008 Prentice Hall, Inc.                                   3 – 91
Steps in Project Crashing
            3. If there is only one critical path, then
               select the activity on this critical path
               that (a) can still be crashed, and (b) has
               the smallest crash cost per period. If
               there is more than one critical path, then
               select one activity from each critical path
               such that (a) each selected activity can
               still be crashed, and (b) the total crash
               cost of all selected activities is the
               smallest. Note that the same activity may
               be common to more than one critical
               path.
© 2008 Prentice Hall, Inc.                                   3 – 92
Steps in Project Crashing

             4. Update all activity times. If the desired
                due date has been reached, stop. If not,
                return to Step 2.




© 2008 Prentice Hall, Inc.                                  3 – 93
Crashing The Project
                   Time (Wks)             Cost ($)     Crash Cost Critical
         Activity Normal Crash        Normal     Crash Per Wk ($) Path?

               A              2   1   22,000    22,750      750    Yes
               B              3   1   30,000    34,000    2,000     No
               C              2   1   26,000    27,000    1,000    Yes
               D              4   2   48,000    49,000    1,000     No
               E              4   2   56,000    58,000    1,000    Yes
               F              3   2   30,000    30,500      500     No
               G              5   2   80,000    84,500    1,500    Yes
               H              2   1   16,000    19,000    3,000    Yes

                                                                  Table 3.5

© 2008 Prentice Hall, Inc.                                                    3 – 94
Crash and Normal Times
                       and Costs for Activity B
                      Activity
                      Cost
                                             Crash

                      $34,000 —                                   Crash Cost – Normal Cost
                                                  Crash Cost/Wk =
                                                                  Normal Time – Crash Time
                      $33,000 —
       Crash                                                     $34,000 – $30,000
       Cost $32,000 —                                          =
                                                                       3–1
                      $31,000 —                                  $4,000
                                                               =         = $2,000/Wk
                                                                 2 Wks
                      $30,000 —

                                 —
                                                                     Normal
       Normal
       Cost
                                          |           |         |
                                          1           2        3         Time (Weeks)
     Figure 3.16
                                     Crash Time            Normal Time
© 2008 Prentice Hall, Inc.                                                              3 – 95
Critical Path And Slack
               Times For Milwaukee Paper
                                     A           C                        F
                                 0       2   2       4               4        7

                                 0       2   2       4               10       13
                                     2           2                        3

                Start            Slack = 0   Slack = 0       E       Slack = 6          H
         0                   0                           4       8                 13       15

          0                  0                           4       8                 13       15
                   0                                         4                          2

                                     B           D       Slack = 0        G        Slack = 0
                                 0       3   3       7               8        13
                                 1       4   4       8               8        13
                                     3           4                        5

                                 Slack = 1   Slack = 1               Slack = 0
                                                                                    Figure 3.17
© 2008 Prentice Hall, Inc.                                                                  3 – 96
Advantages of PERT/CPM
              1. Especially useful when scheduling and
                 controlling large projects
              2. Straightforward concept and not
                 mathematically complex
              3. Graphical networks help highlight
                 relationships among project activities
              4. Critical path and slack time analyses help
                 pinpoint activities that need to be closely
                 watched

© 2008 Prentice Hall, Inc.                                     3 – 97
Advantages of PERT/CPM

              5. Project documentation and graphics
                 point out who is responsible for various
                 activities
              6. Applicable to a wide variety of projects
              7. Useful in monitoring not only schedules
                 but costs as well




© 2008 Prentice Hall, Inc.                                  3 – 98
Limitations of PERT/CPM
             1. Project activities have to be clearly
                defined, independent, and stable in their
                relationships
             2. Precedence relationships must be
                specified and networked together
             3. Time estimates tend to be subjective and
                are subject to fudging by managers
             4. There is an inherent danger of too much
                emphasis being placed on the longest, or
                critical, path

© 2008 Prentice Hall, Inc.                                  3 – 99
Project Management Software

                     There are several popular packages
                      for managing projects
                              Primavera
                              MacProject
                              Pertmaster
                              VisiSchedule
                              Time Line
                              Microsoft Project


© 2008 Prentice Hall, Inc.                                 3 – 100
Using Microsoft Project




                                                  Program 3.1
© 2008 Prentice Hall, Inc.                                      3 – 101
Using Microsoft Project




                                                  Program 3.2

© 2008 Prentice Hall, Inc.                                  3 – 102
Using Microsoft Project




                                                  Program 3.3

© 2008 Prentice Hall, Inc.                                  3 – 103
Using Microsoft Project




                                                  Program 3.4

© 2008 Prentice Hall, Inc.                                  3 – 104
Using Microsoft Project




                                                  Program 3.5

© 2008 Prentice Hall, Inc.                                  3 – 105
Using Microsoft Project




                                                  Program 3.6
© 2008 Prentice Hall, Inc.                                      3 – 106
Using Microsoft Project




                                                 Program 3.7


© 2008 Prentice Hall, Inc.                                     3 – 107

More Related Content

What's hot (20)

Heizer 06
Heizer 06Heizer 06
Heizer 06
 
Heizer 13
Heizer 13Heizer 13
Heizer 13
 
Heizer 16
Heizer 16Heizer 16
Heizer 16
 
Heizer 09
Heizer 09Heizer 09
Heizer 09
 
Heizer supp 06
Heizer supp 06Heizer supp 06
Heizer supp 06
 
Heizer 10
Heizer 10Heizer 10
Heizer 10
 
Heizer 14
Heizer 14Heizer 14
Heizer 14
 
Heizer supp 07
Heizer supp 07Heizer supp 07
Heizer supp 07
 
Heizer om10 ch08
Heizer om10 ch08Heizer om10 ch08
Heizer om10 ch08
 
Heizer mod a
Heizer mod aHeizer mod a
Heizer mod a
 
operation management chapter 2
operation management chapter 2operation management chapter 2
operation management chapter 2
 
Heizer 11
Heizer 11Heizer 11
Heizer 11
 
Introduction to Human Resource Management - HRM Dessler 12e Chapter 01
Introduction to Human Resource Management - HRM Dessler 12e Chapter 01Introduction to Human Resource Management - HRM Dessler 12e Chapter 01
Introduction to Human Resource Management - HRM Dessler 12e Chapter 01
 
Heizer mod b
Heizer mod bHeizer mod b
Heizer mod b
 
Operations And Productivity
Operations And ProductivityOperations And Productivity
Operations And Productivity
 
HRM Dessler CH# 02
HRM Dessler CH# 02HRM Dessler CH# 02
HRM Dessler CH# 02
 
Chapter 9 layout strategies
Chapter 9 layout strategiesChapter 9 layout strategies
Chapter 9 layout strategies
 
Heizer mod c
Heizer mod cHeizer mod c
Heizer mod c
 
Heizer 17
Heizer 17Heizer 17
Heizer 17
 
Operations Management CHAPTER 1
Operations Management CHAPTER 1Operations Management CHAPTER 1
Operations Management CHAPTER 1
 

Similar to Heizer 03

360_ch03
360_ch03360_ch03
360_ch03
ryaekle
 
Adrian Smith CV - 20151113
Adrian Smith CV - 20151113Adrian Smith CV - 20151113
Adrian Smith CV - 20151113
Adrian Smith
 
Kepner Tregoe Developing Your Hr Project Management Skills
Kepner Tregoe  Developing Your Hr Project Management SkillsKepner Tregoe  Developing Your Hr Project Management Skills
Kepner Tregoe Developing Your Hr Project Management Skills
Jessica Booth
 
Project management in pharmaceutical generic industry basics and standards
Project management in pharmaceutical generic industry basics and standardsProject management in pharmaceutical generic industry basics and standards
Project management in pharmaceutical generic industry basics and standards
Jayesh Khatri
 

Similar to Heizer 03 (20)

Heizer om10 ch03
Heizer om10 ch03Heizer om10 ch03
Heizer om10 ch03
 
360_ch03
360_ch03360_ch03
360_ch03
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec doms
 
Slides 2015 for contact 1
Slides 2015 for contact 1Slides 2015 for contact 1
Slides 2015 for contact 1
 
Qimonda Pm Foils
Qimonda Pm FoilsQimonda Pm Foils
Qimonda Pm Foils
 
Bechtel project planning example
Bechtel project planning exampleBechtel project planning example
Bechtel project planning example
 
T343
T343T343
T343
 
best note.pptx
best note.pptxbest note.pptx
best note.pptx
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
 
Adrian Smith CV - 20151113
Adrian Smith CV - 20151113Adrian Smith CV - 20151113
Adrian Smith CV - 20151113
 
T347 Asm Iweb
T347 Asm IwebT347 Asm Iweb
T347 Asm Iweb
 
Kepner Tregoe Developing Your Hr Project Management Skills
Kepner Tregoe  Developing Your Hr Project Management SkillsKepner Tregoe  Developing Your Hr Project Management Skills
Kepner Tregoe Developing Your Hr Project Management Skills
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Project management in pharmaceutical generic industry basics and standards
Project management in pharmaceutical generic industry basics and standardsProject management in pharmaceutical generic industry basics and standards
Project management in pharmaceutical generic industry basics and standards
 
MCP3
MCP3MCP3
MCP3
 
T348 Asm Iweb
T348 Asm IwebT348 Asm Iweb
T348 Asm Iweb
 
T348 Asm Iweb
T348 Asm IwebT348 Asm Iweb
T348 Asm Iweb
 
Project Management !!!
Project Management !!! Project Management !!!
Project Management !!!
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
Brochure for pmvt
Brochure for pmvtBrochure for pmvt
Brochure for pmvt
 

More from Rizwan Khurram

Information Technology Project Management - part 11
Information Technology Project Management - part 11Information Technology Project Management - part 11
Information Technology Project Management - part 11
Rizwan Khurram
 
Information Technology Project Management - part 10
Information Technology Project Management - part 10Information Technology Project Management - part 10
Information Technology Project Management - part 10
Rizwan Khurram
 
Information Technology Project Management - part 09
Information Technology Project Management - part 09Information Technology Project Management - part 09
Information Technology Project Management - part 09
Rizwan Khurram
 
Information Technology Project Management - part 08
Information Technology Project Management - part  08Information Technology Project Management - part  08
Information Technology Project Management - part 08
Rizwan Khurram
 
Information Technology Project Management - part 05
Information Technology Project Management - part 05Information Technology Project Management - part 05
Information Technology Project Management - part 05
Rizwan Khurram
 
Information Technology Project Management - part 04
Information Technology Project Management - part 04Information Technology Project Management - part 04
Information Technology Project Management - part 04
Rizwan Khurram
 
Information Technology Project Management - part 02
Information Technology Project Management - part 02Information Technology Project Management - part 02
Information Technology Project Management - part 02
Rizwan Khurram
 
Information Technology Project Management - part 01
Information Technology Project Management - part 01Information Technology Project Management - part 01
Information Technology Project Management - part 01
Rizwan Khurram
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
Rizwan Khurram
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
Rizwan Khurram
 
Total employee involvement
Total employee involvementTotal employee involvement
Total employee involvement
Rizwan Khurram
 

More from Rizwan Khurram (20)

Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.
 
Information Technology Project Management - part 11
Information Technology Project Management - part 11Information Technology Project Management - part 11
Information Technology Project Management - part 11
 
Information Technology Project Management - part 10
Information Technology Project Management - part 10Information Technology Project Management - part 10
Information Technology Project Management - part 10
 
Information Technology Project Management - part 09
Information Technology Project Management - part 09Information Technology Project Management - part 09
Information Technology Project Management - part 09
 
Information Technology Project Management - part 08
Information Technology Project Management - part  08Information Technology Project Management - part  08
Information Technology Project Management - part 08
 
Information Technology Project Management - part 07
Information Technology Project Management - part 07Information Technology Project Management - part 07
Information Technology Project Management - part 07
 
Information Technology Project Management - part 05
Information Technology Project Management - part 05Information Technology Project Management - part 05
Information Technology Project Management - part 05
 
Information Technology Project Management - part 04
Information Technology Project Management - part 04Information Technology Project Management - part 04
Information Technology Project Management - part 04
 
Information Technology Project Management - part 02
Information Technology Project Management - part 02Information Technology Project Management - part 02
Information Technology Project Management - part 02
 
Information Technology Project Management - part 01
Information Technology Project Management - part 01Information Technology Project Management - part 01
Information Technology Project Management - part 01
 
Information Technology Project Management - part 12
Information Technology Project Management - part 12Information Technology Project Management - part 12
Information Technology Project Management - part 12
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Vision and mission
Vision and missionVision and mission
Vision and mission
 
Total employee involvement
Total employee involvementTotal employee involvement
Total employee involvement
 

Heizer 03

  • 1. Operations Management Chapter 3 – Project Management PowerPoint presentation to accompany Heizer/Render Principles of Operations Management, 7e Operations Management, 9e © 2008 Prentice Hall, Inc. 3–1
  • 2. Outline  Global Company Profile: Bechtel Group  The Importance of Project Management  Project Planning  The Project Manager  Work Breakdown Structure  Project Scheduling © 2008 Prentice Hall, Inc. 3–2
  • 3. Outline - Continued  Project Controlling  Project Management Techniques: PERT and CPM  The Framework of PERT and CPM  Network Diagrams and Approaches  Activity-on-Node Example  Activity-on-Arrow Example © 2008 Prentice Hall, Inc. 3–3
  • 4. Outline - Continued  Determining the Project Schedule  Forward Pass  Backward Pass  Calculating Slack Time and Identifying the Critical Path(s)  Variability in Activity Times  Three Time Estimates in PERT  Probability of Project Completion © 2008 Prentice Hall, Inc. 3–4
  • 5. Outline - Continued  Cost-Time Trade-Offs and Project Crashing  A Critique of PERT and CPM  Using Microsoft Project to Manage Projects  Creating a Project Schedule Using MS Project  Tracking Progress and Managing Costs Using MS Project © 2008 Prentice Hall, Inc. 3–5
  • 6. Learning Objectives When you complete this chapter you should be able to: 1. Create a work breakdown structure 2. Draw AOA and AON networks 3. Complete both forward and backward passes for a project 4. Determine a critical path © 2008 Prentice Hall, Inc. 3–6
  • 7. Learning Objectives When you complete this chapter you should be able to: 5. Calculate the variance of activity times 6. Crash a project 7. Use Microsoft Project software to create a project © 2008 Prentice Hall, Inc. 3–7
  • 8. Bechtel Projects  Building 26 massive distribution centers in just two years for the internet company Webvan Group ($1 billion)  Constructing 30 high-security data centers worldwide for Equinix, Inc. ($1.2 billion)  Building and running a rail line between London and the Channel Tunnel ($4.6 billion)  Developing an oil pipeline from the Caspian Sea region to Russia ($850 million)  Expanding the Dubai Airport in the UAE ($600 million), and the Miami Airport in Florida ($2 billion) © 2008 Prentice Hall, Inc. 3–8
  • 9. Bechtel Projects  Building liquid natural gas plants in Yemen $2 billion) and in Trinidad, West Indies ($1 billion)  Building a new subway for Athens, Greece ($2.6 billion)  Constructing a natural gas pipeline in Thailand ($700 million)  Building 30 plants for iMotors.com, a company that sells refurbished autos online ($300 million)  Building a highway to link the north and south of Croatia ($303 million) © 2008 Prentice Hall, Inc. 3–9
  • 10. Strategic Importance of Project Management  Microsoft Windows Vista Project:  hundreds of programmers  millions of lines of code  hundreds of millions of dollars cost  Hard Rock Cafe Rockfest Project:  100,000 + fans  planning began 9 months in advance © 2008 Prentice Hall, Inc. 3 – 10
  • 11. Project Characteristics  Single unit  Many related activities  Difficult production planning and inventory control  General purpose equipment  High labor skills © 2008 Prentice Hall, Inc. 3 – 11
  • 12. Examples of Projects  Building Construction  Research Project © 2008 Prentice Hall, Inc. 3 – 12
  • 13. Management of Projects 1. Planning - goal setting, defining the project, team organization 2. Scheduling - relates people, money, and supplies to specific activities and activities to each other 3. Controlling - monitors resources, costs, quality, and budgets; revises plans and shifts resources to meet time and cost demands © 2008 Prentice Hall, Inc. 3 – 13
  • 14. Project Management Activities  Planning  Scheduling  Objectives  Project activities  Resources  Start & end times  Work break-down schedule  Network  Organization  Controlling  Monitor, compare, revise, action © 2008 Prentice Hall, Inc. 3 – 14
  • 15. Project Planning, Scheduling, and Controlling Figure 3.1 Before Start of project During project Timeline project © 2008 Prentice Hall, Inc. 3 – 15
  • 16. Project Planning, Scheduling, and Controlling Figure 3.1 Before Start of project During project Timeline project © 2008 Prentice Hall, Inc. 3 – 16
  • 17. Project Planning, Scheduling, and Controlling Figure 3.1 Before Start of project During project Timeline project © 2008 Prentice Hall, Inc. 3 – 17
  • 18. Project Planning, Scheduling, and Controlling Figure 3.1 Before Start of project During project Timeline project © 2008 Prentice Hall, Inc. 3 – 18
  • 19. Project Time/cost estimates Planning, Budgets Scheduling, and Controlling Engineering diagrams Cash flow charts Material availability details Budgets Delayed activities report Slack activities report CPM/PERT Gantt charts Milestone charts Cash flow schedules Figure 3.1 Before Start of project During project Timeline project © 2008 Prentice Hall, Inc. 3 – 19
  • 20. Project Planning  Establishing objectives  Defining project  Creating work breakdown structure  Determining resources  Forming organization © 2008 Prentice Hall, Inc. 3 – 20
  • 21. Project Organization  Often temporary structure  Uses specialists from entire company  Headed by project manager  Coordinates activities  Monitors schedule and costs  Permanent structure called ‘matrix organization’ © 2008 Prentice Hall, Inc. 3 – 21
  • 22. A Sample Project Organization President Human Quality Resources Marketing Finance Design Production Mgt Project 1 Project Manager Mechanical Test Technician Engineer Engineer Project 2 Project Manager Electrical Computer Technician Engineer Engineer Figure 3.2 © 2008 Prentice Hall, Inc. 3 – 22
  • 23. Project Organization Works Best When 1. Work can be defined with a specific goal and deadline 2. The job is unique or somewhat unfamiliar to the existing organization 3. The work contains complex interrelated tasks requiring specialized skills 4. The project is temporary but critical to the organization 5. The project cuts across organizational lines © 2008 Prentice Hall, Inc. 3 – 23
  • 24. Matrix Organization Marketing Operations Engineering Finance Project 1 Project 2 Project 3 Project 4 © 2008 Prentice Hall, Inc. 3 – 24
  • 25. The Role of the Project Manager Highly visible Responsible for making sure that:  All necessary activities are finished in order and on time  The project comes in within budget  The project meets quality goals  The people assigned to the project receive motivation, direction, and information © 2008 Prentice Hall, Inc. 3 – 25
  • 26. The Role of the Project Manager Highly visible Responsible for making sure that: should be: Project managers  Good coaches  All necessary activities are finished in order and on time  Good communicators  The project comes in withinorganize activities  Able to budget from a variety of disciplines  The project meets quality goals  The people assigned to the project receive motivation, direction, and information © 2008 Prentice Hall, Inc. 3 – 26
  • 27. Ethical Issues  Bid rigging – divulging confidential information to give some bidders an unfair advantage  “Low balling” contractors – try to “buy” the project by bidding low and hope to renegotiate or cut corners  Bribery – particularly on international projects  Expense account padding  Use of substandard materials  Compromising health and safety standards  Withholding needed information  Failure to admit project failure at close © 2008 Prentice Hall, Inc. 3 – 27
  • 28. Work Breakdown Structure Level 1. Project 2. Major tasks in the project 3. Subtasks in the major tasks 4. Activities (or work packages) to be completed © 2008 Prentice Hall, Inc. 3 – 28
  • 29. Work Breakdown Structure Level ID Level Number Activity 1 1.0 Develop/launch Windows Vista OS 2 1.1 Develop of GUIs 2 1.2 Ensure compatibility with earlier Windows versions 3 1.21 Compatibility with Windows ME 3 1.22 Compatibility with Windows XP 3 1.23 Compatibility with Windows 2000 4 1.231 Ensure ability to import files Figure 3.3 © 2008 Prentice Hall, Inc. 3 – 29
  • 30. Project Scheduling  Identifying precedence relationships  Sequencing activities  Determining activity times & costs  Estimating material & worker requirements  Determining critical activities © 2008 Prentice Hall, Inc. 3 – 30
  • 31. Purposes of Project Scheduling 1. Shows the relationship of each activity to others and to the whole project 2. Identifies the precedence relationships among activities 3. Encourages the setting of realistic time and cost estimates for each activity 4. Helps make better use of people, money, and material resources by identifying critical bottlenecks in the project © 2008 Prentice Hall, Inc. 3 – 31
  • 32. Scheduling Techniques 1. Ensure that all activities are planned for 2. Their order of performance is accounted for 3. The activity time estimates are recorded 4. The overall project time is developed © 2008 Prentice Hall, Inc. 3 – 32
  • 33. Project Management Techniques  Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) © 2008 Prentice Hall, Inc. 3 – 33
  • 34. A Simple Gantt Chart Time J F M A M J J A S Design Prototype Test Revise Production © 2008 Prentice Hall, Inc. 3 – 34
  • 35. Service For A Delta Jet Deplaning Passengers Baggage claim Baggage Container offload Pumping Fueling Engine injection water Cargo and mail Container offload Main cabin door Galley servicing Aft cabin door Lavatory servicing Aft, center, forward Drinking water Loading First-class section Cabin cleaning Economy section Cargo and mail Container/bulk loading Galley/cabin check Flight services Receive passengers Operating crew Aircraft check Baggage Loading Passengers Boarding 0 10 20 30 40 Figure 3.4 Time, Minutes © 2008 Prentice Hall, Inc. 3 – 35
  • 36. Project Control Reports  Detailed cost breakdowns for each task  Total program labor curves  Cost distribution tables  Functional cost and hour summaries  Raw materials and expenditure forecasts  Variance reports  Time analysis reports  Work status reports © 2008 Prentice Hall, Inc. 3 – 36
  • 37. PERT and CPM  Network techniques  Developed in 1950’s  CPM by DuPont for chemical plants (1957)  PERT by Booz, Allen & Hamilton with the U.S. Navy, for Polaris missile (1958)  Consider precedence relationships and interdependencies  Each uses a different estimate of activity times © 2008 Prentice Hall, Inc. 3 – 37
  • 38. Six Steps PERT & CPM 1. Define the project and prepare the work breakdown structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities © 2008 Prentice Hall, Inc. 3 – 38
  • 39. Six Steps PERT & CPM 4. Assign time and/or cost estimates to each activity 5. Compute the longest time path through the network – this is called the critical path 6. Use the network to help plan, schedule, monitor, and control the project © 2008 Prentice Hall, Inc. 3 – 39
  • 40. Questions PERT & CPM Can Answer 1. When will the entire project be completed? 2. What are the critical activities or tasks in the project? 3. Which are the noncritical activities? 4. What is the probability the project will be completed by a specific date? © 2008 Prentice Hall, Inc. 3 – 40
  • 41. Questions PERT & CPM Can Answer 5. Is the project on schedule, behind schedule, or ahead of schedule? 6. Is the money spent equal to, less than, or greater than the budget? 7. Are there enough resources available to finish the project on time? 8. If the project must be finished in a shorter time, what is the way to accomplish this at least cost? © 2008 Prentice Hall, Inc. 3 – 41
  • 42. A Comparison of AON and AOA Network Conventions Activity on Activity Activity on Node (AON) Meaning Arrow (AOA) A comes before (a) A B C B, which comes before C A B C A A A and B must both (b) C be completed before C can start C B B B B and C cannot (c) A begin until A is B completed A Figure 3.5 C C © 2008 Prentice Hall, Inc. 3 – 42
  • 43. A Comparison of AON and AOA Network Conventions Activity on Activity Activity on Node (AON) Meaning Arrow (AOA) C and D cannot A C begin until both A C (d) A and B are completed B D B D C cannot begin until both A and B A C are completed; D A C (e) cannot begin until Dummy activity B is completed. A B D dummy activity is introduced in AOA B D Figure 3.5 © 2008 Prentice Hall, Inc. 3 – 43
  • 44. A Comparison of AON and AOA Network Conventions Activity on Activity Activity on Node (AON) Meaning Arrow (AOA) B and C cannot begin until A is completed. D A B D cannot begin A B D until both B and (f) C are completed. Dummy A dummy C C activity activity is again introduced in AOA. Figure 3.5 © 2008 Prentice Hall, Inc. 3 – 44
  • 45. AON Example Milwaukee Paper Manufacturing's Activities and Predecessors Immediate Activity Description Predecessors A Build internal components — B Modify roof and floor — C Construct collection stack A D Pour concrete and install frame A, B E Build high-temperature burner C F Install pollution control system C G Install air pollution device D, E H Inspect and test F, G Table 3.1 © 2008 Prentice Hall, Inc. 3 – 45
  • 46. AON Network for Milwaukee Paper Activity A A (Build Internal Components) Start Activity B Start B (Modify Roof and Floor) Activity Figure 3.6 © 2008 Prentice Hall, Inc. 3 – 46
  • 47. AON Network for Milwaukee Paper Activity A Precedes Activity C A C Start B D Activities A and B Precede Activity D Figure 3.7 © 2008 Prentice Hall, Inc. 3 – 47
  • 48. AON Network for Milwaukee Paper F A C E Start H B D G Arrows Show Precedence Relationships Figure 3.8 © 2008 Prentice Hall, Inc. 3 – 48
  • 49. AOA Network for Milwaukee Paper C 2 4 (Construct Stack) F Co (In nt nal nt sta s) ne e r (Build Burner) o m ld A (Build Burner) ro ll po Int ls ) C ui H Dummy 7 (B E 1 6 E Activity (Inspect/ Test) Ro (M B G of od ll / F i fy st a io n lo or In lut e) ( l ic ) D Po ev 3 5 D (Pour Concrete/ Install Frame) Figure 3.9 © 2008 Prentice Hall, Inc. 3 – 49
  • 50. Determining the Project Schedule Perform a Critical Path Analysis  The critical path is the longest path through the network  The critical path is the shortest time in which the project can be completed  Any delay in critical path activities delays the project  Critical path activities have no slack time © 2008 Prentice Hall, Inc. 3 – 50
  • 51. Determining the Project Schedule Perform a Critical Path Analysis Activity Description Time (weeks) A Build internal components 2 B Modify roof and floor 3 C Construct collection stack 2 D Pour concrete and install frame 4 E Build high-temperature burner 4 F Install pollution control system 3 G Install air pollution device 5 H Inspect and test 2 Total Time (weeks) 25 Table 3.2 © 2008 Prentice Hall, Inc. 3 – 51
  • 52. Determining the Project Schedule Perform a Critical Path Analysis Earliest start (ES) = earliest time at Activity Description an activity can start, Time (weeks) which assuming A Build internal components been completed all predecessors have 2 B Modify roof and floor Earliest finish (EF) = 3 earliest time at C Construct collection stack be finished 2 which an activity can D Pour concrete and(LS) = frame Latest start install 4 latest time at E Build high-temperature can start so as to not which an activity burner 4 F Install delay the completion time of the entire pollution control system 3 project G Install air pollution device 5 Latest finish (LF) = latest time by H Inspect and testactivity has to be finished so which an 2 Total Time (weeks) the completion time of Table 3.2 25 as to not delay © 2008 Prentice Hall, Inc. the entire project 3 – 52
  • 53. Determining the Project Schedule Perform a Critical Path Analysis Activity Name or Symbol A Earliest Earliest ES EF Finish Start Latest LS LF Latest Start 2 Finish Figure 3.10 Activity Duration © 2008 Prentice Hall, Inc. 3 – 53
  • 54. Forward Pass Begin at starting event and work forward Earliest Start Time Rule:  If an activity has only a single immediate predecessor, its ES equals the EF of the predecessor  If an activity has multiple immediate predecessors, its ES is the maximum of all the EF values of its predecessors ES = Max {EF of all immediate predecessors} © 2008 Prentice Hall, Inc. 3 – 54
  • 55. Forward Pass Begin at starting event and work forward Earliest Finish Time Rule:  The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) and its activity time EF = ES + Activity time © 2008 Prentice Hall, Inc. 3 – 55
  • 56. ES/EF Network for Milwaukee Paper ES EF = ES + Activity time Start 0 0 0 © 2008 Prentice Hall, Inc. 3 – 56
  • 57. ES/EF Network for Milwaukee Paper EF of A = ES ES of A + 2 of A A Start 0 2 0 0 0 2 © 2008 Prentice Hall, Inc. 3 – 57
  • 58. ES/EF Network for Milwaukee Paper A 0 2 2 EF of B = ES ES of B + 3 0 Start 0 of B B 0 0 3 3 © 2008 Prentice Hall, Inc. 3 – 58
  • 59. ES/EF Network for Milwaukee Paper A C 0 2 2 4 2 2 Start 0 0 0 B 0 3 3 © 2008 Prentice Hall, Inc. 3 – 59
  • 60. ES/EF Network for Milwaukee Paper A C 0 2 2 4 2 2 Start 0 0 = Max (2, 3) D 0 3 7 B 0 3 3 4 © 2008 Prentice Hall, Inc. 3 – 60
  • 61. ES/EF Network for Milwaukee Paper A C 0 2 2 4 2 2 Start 0 0 0 B D 0 3 3 7 3 4 © 2008 Prentice Hall, Inc. 3 – 61
  • 62. ES/EF Network for Milwaukee Paper A C F 0 2 2 4 4 7 2 2 3 Start E H 0 0 4 8 13 15 0 4 2 B D G 0 3 3 7 8 13 3 4 5 Figure 3.11 © 2008 Prentice Hall, Inc. 3 – 62
  • 63. Backward Pass Begin with the last event and work backwards Latest Finish Time Rule:  If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it  If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it LF = Min {LS of all immediate following activities} © 2008 Prentice Hall, Inc. 3 – 63
  • 64. Backward Pass Begin with the last event and work backwards Latest Start Time Rule:  The latest start time (LS) of an activity is the difference of its latest finish time (LF) and its activity time LS = LF – Activity time © 2008 Prentice Hall, Inc. 3 – 64
  • 65. LS/LF Times for Milwaukee Paper A C F 0 2 2 4 4 7 2 2 3 Start E H 0 0 4 8 13 15 13 15 0 4 2 B LS = LF – Activity time D G 0 3 3 7 8 13 3 4 5 LF = EF of Project © 2008 Prentice Hall, Inc. 3 – 65
  • 66. LS/LF Times for Milwaukee Paper A C F 0 2 2 4 4 7 10 13 2 2 3 Start E H 0 0 LF = Min(LS of 4 8 13 15 following activity) 13 15 0 4 2 B D G 0 3 3 7 8 13 3 4 5 © 2008 Prentice Hall, Inc. 3 – 66
  • 67. LS/LF Times for Milwaukee Paper LF = Min(4, 10) A C F 0 2 2 4 4 7 2 4 10 13 2 2 3 Start E H 0 0 4 8 13 15 4 8 13 15 0 4 2 B D G 0 3 3 7 8 13 8 13 3 4 5 © 2008 Prentice Hall, Inc. 3 – 67
  • 68. LS/LF Times for Milwaukee Paper A C F 0 2 2 4 4 7 0 2 2 4 10 13 2 2 3 Start E H 0 0 4 8 13 15 0 0 4 8 13 15 0 4 2 B D G 0 3 3 7 8 13 1 4 4 8 8 13 3 4 5 © 2008 Prentice Hall, Inc. 3 – 68
  • 69. Computing Slack Time After computing the ES, EF, LS, and LF times for all activities, compute the slack or free time for each activity  Slack is the length of time an activity can be delayed without delaying the entire project Slack = LS – ES or Slack = LF – EF © 2008 Prentice Hall, Inc. 3 – 69
  • 70. Computing Slack Time Earliest Earliest Latest Latest On Start Finish Start Finish Slack Critical Activity ES EF LS LF LS – ES Path A 0 2 0 2 0 Yes B 0 3 1 4 1 No C 2 4 2 4 0 Yes D 3 7 4 8 1 No E 4 8 4 8 0 Yes F 4 7 10 13 6 No G 8 13 8 13 0 Yes H 13 15 13 15 0 Yes Table 3.3 © 2008 Prentice Hall, Inc. 3 – 70
  • 71. Critical Path for Milwaukee Paper A C F 0 2 2 4 4 7 0 2 2 4 10 13 2 2 3 Start E H 0 0 4 8 13 15 0 0 4 8 13 15 0 4 2 B D G 0 3 3 7 8 13 1 4 4 8 8 13 3 4 5 © 2008 Prentice Hall, Inc. 3 – 71
  • 72. ES – EF Gantt Chart for Milwaukee Paper 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 A Build internal components B Modify roof and floor C Construct collection stack D Pour concrete and install frame E Build high- temperature burner F Install pollution control system G Install air pollution device H Inspect and test © 2008 Prentice Hall, Inc. 3 – 72
  • 73. LS – LF Gantt Chart for Milwaukee Paper 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 A Build internal components B Modify roof and floor C Construct collection stack D Pour concrete and install frame E Build high- temperature burner F Install pollution control system G Install air pollution device H Inspect and test © 2008 Prentice Hall, Inc. 3 – 73
  • 74. Variability in Activity Times  CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times  PERT uses a probability distribution for activity times to allow for variability © 2008 Prentice Hall, Inc. 3 – 74
  • 75. Variability in Activity Times  Three time estimates are required  Optimistic time (a) – if everything goes according to plan  Pessimistic time (b) – assuming very unfavorable conditions  Most likely time (m) – most realistic estimate © 2008 Prentice Hall, Inc. 3 – 75
  • 76. Variability in Activity Times Estimate follows beta distribution Expected time: t = (a + 4m + b)/6 Variance of times: v = [(b – a)/6]2 © 2008 Prentice Hall, Inc. 3 – 76
  • 77. Variability in Activity Times Estimate follows beta distribution Expected time: Figure 3.12 t = (a + 4m + b)/6 Probability of Variance of times: 1 in 100 of Probability Probability < a occurring of 1 in 100 of v = [(b − a)/6]2 > b occurring Activity Time Optimistic Most Likely Pessimistic Time (a) Time (m) Time (b) © 2008 Prentice Hall, Inc. 3 – 77
  • 78. Computing Variance Most Expected Optimistic Likely Pessimistic Time Variance Activity a m b t = (a + 4m + b)/6 [(b – a)/6]2 A 1 2 3 2 .11 B 2 3 4 3 .11 C 1 2 3 2 .11 D 2 4 6 4 .44 E 1 4 7 4 1.00 F 1 2 9 3 1.78 G 3 4 11 5 1.78 H 1 2 3 2 .11 Table 3.4 © 2008 Prentice Hall, Inc. 3 – 78
  • 79. Probability of Project Completion Project variance is computed by summing the variances of critical activities σ 2 =pProject variance = ∑ (variances of activities on critical path) © 2008 Prentice Hall, Inc. 3 – 79
  • 80. Probability of Project Completion Project variance is computed by summing the variances of critical Project variance activities σ 2 =p.11 + .11 + 1.00 + 1.78 + .11 = 3.11 Project standard deviation σp = Project variance = 3.11 = 1.76 weeks © 2008 Prentice Hall, Inc. 3 – 80
  • 81. Probability of Project Completion PERT makes two more assumptions:  Total project completion times follow a normal probability distribution  Activity times are statistically independent © 2008 Prentice Hall, Inc. 3 – 81
  • 82. Probability of Project Completion Standard deviation = 1.76 weeks 15 Weeks (Expected Completion Time) Figure 3.13 © 2008 Prentice Hall, Inc. 3 – 82
  • 83. Probability of Project Completion What is the probability this project can be completed on or before the 16 week deadline? due expected date Z = date – of completion /σ p = (16 wks – 15 wks)/1.76 Where Z is the number of = 0.57 standard deviations the due date or target date lies from the mean or expected date © 2008 Prentice Hall, Inc. 3 – 83
  • 84. Probability of Project Completion From Appendix I What is the probability this project can .00 .01 .07 .08 be completed on or before the 16 week .1 .50000 .50399 .52790 .53188 deadline? .53983 .54380 .2 .56749 .57142 due expected date .5 Z.69146 .69497 completion /σ = date − of .71566 .71904 p .6 .72575 .72907 .74857 .75175 = (16 wks − 15 wks)/1.76 Where Z is the number of = 0.57 standard deviations the due date or target date lies from the mean or expected date © 2008 Prentice Hall, Inc. 3 – 84
  • 85. Probability of Project Completion 0.57 Standard deviations Probability (T ≤ 16 weeks) is 71.57% 15 16 Time Weeks Weeks Figure 3.14 © 2008 Prentice Hall, Inc. 3 – 85
  • 86. Determining Project Completion Time Probability of 0.99 Probability of 0.01 2.33 Standard Z From Appendix I deviations 0 2.33 Figure 3.15 © 2008 Prentice Hall, Inc. 3 – 86
  • 87. Variability of Completion Time for Noncritical Paths  Variability of times for activities on noncritical paths must be considered when finding the probability of finishing in a specified time  Variation in noncritical activity may cause change in critical path © 2008 Prentice Hall, Inc. 3 – 87
  • 88. What Project Management Has Provided So Far  The project’s expected completion time is 15 weeks  There is a 71.57% chance the equipment will be in place by the 16 week deadline  Five activities (A, C, E, G, and H) are on the critical path  Three activities (B, D, F) are not on the critical path and have slack time  A detailed schedule is available © 2008 Prentice Hall, Inc. 3 – 88
  • 89. Trade-Offs And Project Crashing It is not uncommon to face the following situations:  The project is behind schedule  The completion time has been moved forward Shortening the duration of the project is called project crashing © 2008 Prentice Hall, Inc. 3 – 89
  • 90. Factors to Consider When Crashing A Project  The amount by which an activity is crashed is, in fact, permissible  Taken together, the shortened activity durations will enable us to finish the project by the due date  The total cost of crashing is as small as possible © 2008 Prentice Hall, Inc. 3 – 90
  • 91. Steps in Project Crashing 1. Compute the crash cost per time period. If crash costs are linear over time: Crash cost (Crash cost – Normal cost) per period = (Normal time – Crash time) 2. Using current activity times, find the critical path and identify the critical activities © 2008 Prentice Hall, Inc. 3 – 91
  • 92. Steps in Project Crashing 3. If there is only one critical path, then select the activity on this critical path that (a) can still be crashed, and (b) has the smallest crash cost per period. If there is more than one critical path, then select one activity from each critical path such that (a) each selected activity can still be crashed, and (b) the total crash cost of all selected activities is the smallest. Note that the same activity may be common to more than one critical path. © 2008 Prentice Hall, Inc. 3 – 92
  • 93. Steps in Project Crashing 4. Update all activity times. If the desired due date has been reached, stop. If not, return to Step 2. © 2008 Prentice Hall, Inc. 3 – 93
  • 94. Crashing The Project Time (Wks) Cost ($) Crash Cost Critical Activity Normal Crash Normal Crash Per Wk ($) Path? A 2 1 22,000 22,750 750 Yes B 3 1 30,000 34,000 2,000 No C 2 1 26,000 27,000 1,000 Yes D 4 2 48,000 49,000 1,000 No E 4 2 56,000 58,000 1,000 Yes F 3 2 30,000 30,500 500 No G 5 2 80,000 84,500 1,500 Yes H 2 1 16,000 19,000 3,000 Yes Table 3.5 © 2008 Prentice Hall, Inc. 3 – 94
  • 95. Crash and Normal Times and Costs for Activity B Activity Cost Crash $34,000 — Crash Cost – Normal Cost Crash Cost/Wk = Normal Time – Crash Time $33,000 — Crash $34,000 – $30,000 Cost $32,000 — = 3–1 $31,000 — $4,000 = = $2,000/Wk 2 Wks $30,000 — — Normal Normal Cost | | | 1 2 3 Time (Weeks) Figure 3.16 Crash Time Normal Time © 2008 Prentice Hall, Inc. 3 – 95
  • 96. Critical Path And Slack Times For Milwaukee Paper A C F 0 2 2 4 4 7 0 2 2 4 10 13 2 2 3 Start Slack = 0 Slack = 0 E Slack = 6 H 0 0 4 8 13 15 0 0 4 8 13 15 0 4 2 B D Slack = 0 G Slack = 0 0 3 3 7 8 13 1 4 4 8 8 13 3 4 5 Slack = 1 Slack = 1 Slack = 0 Figure 3.17 © 2008 Prentice Hall, Inc. 3 – 96
  • 97. Advantages of PERT/CPM 1. Especially useful when scheduling and controlling large projects 2. Straightforward concept and not mathematically complex 3. Graphical networks help highlight relationships among project activities 4. Critical path and slack time analyses help pinpoint activities that need to be closely watched © 2008 Prentice Hall, Inc. 3 – 97
  • 98. Advantages of PERT/CPM 5. Project documentation and graphics point out who is responsible for various activities 6. Applicable to a wide variety of projects 7. Useful in monitoring not only schedules but costs as well © 2008 Prentice Hall, Inc. 3 – 98
  • 99. Limitations of PERT/CPM 1. Project activities have to be clearly defined, independent, and stable in their relationships 2. Precedence relationships must be specified and networked together 3. Time estimates tend to be subjective and are subject to fudging by managers 4. There is an inherent danger of too much emphasis being placed on the longest, or critical, path © 2008 Prentice Hall, Inc. 3 – 99
  • 100. Project Management Software  There are several popular packages for managing projects  Primavera  MacProject  Pertmaster  VisiSchedule  Time Line  Microsoft Project © 2008 Prentice Hall, Inc. 3 – 100
  • 101. Using Microsoft Project Program 3.1 © 2008 Prentice Hall, Inc. 3 – 101
  • 102. Using Microsoft Project Program 3.2 © 2008 Prentice Hall, Inc. 3 – 102
  • 103. Using Microsoft Project Program 3.3 © 2008 Prentice Hall, Inc. 3 – 103
  • 104. Using Microsoft Project Program 3.4 © 2008 Prentice Hall, Inc. 3 – 104
  • 105. Using Microsoft Project Program 3.5 © 2008 Prentice Hall, Inc. 3 – 105
  • 106. Using Microsoft Project Program 3.6 © 2008 Prentice Hall, Inc. 3 – 106
  • 107. Using Microsoft Project Program 3.7 © 2008 Prentice Hall, Inc. 3 – 107