PMIMY EVENING TALK

MANAGING COMPLEX PROJECT
Suharti Mohd Ali
Program Director IT Transformation
Celcom Axiata Bhd
What I will Share Tonight

  1      Criteria of A Complex Project

  2      Areas of Work for Scrutiny

  3      Measures of Success

  4      Pitfalls to Look Out For

  5      Question Time




                                         2
What is a Complex Project?
 Budget used to be the sole determinant of complexity,
but not anymore
  any project with more than 3 parties to be managed
  any project with more than 3 systems to be retired in
the process
  any project which impact more than 3 divisions in the
organization totaling more than 300 people
  Any project which require a team structure of more
than 150 people
  any project introducing more than 3 new applications
to the business………



                                                    3
What Makes a Project Complex?


There is now an Institute of Complex Projects
who is in the midst of devising a tool to assess
complexity and complexity levels to help
delivery teams put a structure in place

But the science of determining if a project is
complex or otherwise is the simplest task – the
real test is HOW do we deal with it.




                                              4
Complex legacy landscape was a challenge in
supporting the HSBB agenda ..




 • Numerous and disparate support systems        • 30+ user communities to engage
   catering to different products and lines of
   businesses                                    • 68 level 3 and 210 level 4 business
                                                   processes
 • Legacy, custom-built applications and
   point-to-point data transfers                 • 100+ systems interfaces to develop

 • Increased complexity and time to
   enhance for HSBB transformation


      5
Numerous Vendors


                                                                              PMO & Systems
                                                                                Integrator




                                                                                  Software
                                                                                  Principals


                                                                                               Storage
                                                                         Hardware

     Jointly managed with a single lead SI/PMO (Accenture) to deliver a full-suite of integrated, end-
     to-end BSS/OSS/SDP capabilities …
     ▪ … under a unified program structure focusing on end-to-end deployment of systems, processes
       and organization as a business capability, and
     ▪ … with the right operational and knowledge transfer activities to form a full business solution
       for TM
6                                                                                                        6
Areas of Work for Scrutiny
There are 8 critical areas of work that not only need to be
managed but need scrutiny to its most micro level
                      Program Structure & Governance


                             Release Management

                           Dependency Management


                        Deliverable Sign-Off Management


                          Risks and Issue Management


                         Change Request Management


                            Vendor Management

                                    Tools



                                                              7
Project Organization Chart – Sample Structure
Project governance and reporting structure is set up to ensure roles and
responsibilities are established and lines of escalation are communicated

                                                                                                                           Supervise the overall project progress , ensure
                                                                                         Project Manager                   all scheduled milestones are completed on
                                                                                                                           time.


                                                                    Solution                                                                               Oversee and manage project level dependencies, risks
         Authority for overall solution within project                                                                Release Management                   and issues, monitor delivery progress and vendor
         program, manage and circuit break cross team             Architecture
                                                                                                                                                           management.
         issues, risks and dependencies
                                                                                                                                                Vendor
                                                                                                                                              Management




 Application Teams
                                                                                      Migration                            Testing                          Tech. Arch.                    Business Integration
     Order                   Order                                                     Team                                 Team                              Team                                Team
                                                 Integration
     Capture                 Mgmt
                                                                              Design and develop required                                                Design and implement
                                                   Product
   Web Portal                SR/TT                                            migration tools. Coordinate                                                technical architecture,
                                                   Mgmt                       and perform migration from                                                 infrastructure.
                                                                              legacy into new systems.
    Campaign                                        Other
                           Analytics
    Mgmt                                            Apps…

• Perform analysis and maintain system and data integration                                           User
  through various functional designs.                               E2E Integration                                         Performance                 Business
                                                                                                   Acceptance                                                                      Training               Comms
• Design, build and test business capabilities based on the new         Testing                                               Testing                   Process
                                                                                                     Testing
  process and requirements
• Document and maintain integration requirements.
                                                                  Perform Integration          Coordinate and perform      Coordinate and conduct     Perform business       Plan and perform     Develop change
                                                                  Test to ensure the end-      User Acceptance Test to     performance and volume     process alignment      required training.   and communication
                                                                  to-end solution              ensure the solution is in   test to ensure the         by designing,          Develop required     plans for project.
                                                                  conforms to the level of     line with the               solution performance is    validating and         training materials
                                                                  quality set in the design.   expectations of the         acceptable within          deploying the ‘to-
                                                                                               users.                      defined SLA.               be’ business
                                                                                                                                                      processes


               8
* Proposed structure to be validated & customized by each project team to suite specific project needs
Program Governance
Leadership must be planned in order to closely monitor the Program and keep two-
way communication channel open

                                           • Objective - To provide update on progress of project.
                                           • Frequency - 1 per quarter
                   Board                   • Participants - Board of directors, CIO, PMO team.

                                           • Objective - Discuss project issues and agree upon next steps.
                                           • Frequency - 1 per fortnight
                  Steering
                 Committee                 • Participants - CIO, Steering Committee, PMO team.


                                           • Objective - To provide CIO with progress updates, highlight and
                                           seek direction on project issues.
                CIO updates                • Frequency - 1 per fortnight
                                           • Participants – CIO, Accenture Delivery Lead

                                           • Objective - Review progress, and address key topics at a project
                                           level.
             Project Leadership            • Frequency - 1 per week
                  Meetings                 • Participants (Internal Meeting ) – PMO Team, Delivery Lead,
                                           Leads from different work streams, HR contact (when required)
                                           • Participants (External Meeting ) – Accenture leadership teams and
                                           client leads

               Team Meetings               • Objective – Team leads to review progress of their teams, and any
                                           issues which their team is facing.
                                           • Frequency - 1 per week
                                           • Participants - Team leads with team members
                                                                                    9
Program Governance – External Meetings
A structure was setup with the Client in order to highlight issues and report status of
the overall progress
    Meetings         Type      Frequency                Key Attendees             Purpose of Meeting

                                            • TM Leadership Team: Chee     • To update TM leadership on the
                                                                             overall program status
Systems Steering                 Weekly
Committee                                                                  • To highlight issues and decisions
                    External     (every
                                                                             for Steering Committee guidance
Meeting                         Tuesday)
                                                                             and direction


                                            •                              • To update TM Systems
                                                                             leadership on the overall program
                                 Weekly                                      status
CIO Systems
                    External     (every
Update                                                                     • To highlight issues and decisions
                                 Friday)
                                                                             for IT Leadership guidance and
                                                                             direction

                                            • Nova Leadership:             • Internal Program meeting to run
                                                                             through overall program status &
Nova IT Program                 Weekly                                       potential impacts to the schedule.
Leadership          External     (every
Meeting                        Wednesday)                                  • Any major escalations/issues
                                                                             should be highlighted in the
                                                                             Program Leadership meeting.

                                            • Nova Leadership              • Internal Program meeting to run
                                            • TM Business:                   through overall program status &
                                Weekly                                       potential impacts to the schedule.
iCarePrime Status
                    External     (every
Meeting                                                                    • Any major escalations/issues
                               Thursday)
                                                                             should be highlighted in the
                                                                             Program Leadership meeting.



        10
Program Governance – Vendor Meetings
This structure is replicated with the various Vendors in order to discuss status and
escalate vendor specific issues


      Meetings      Type      Frequency               Key Attendees               Purpose of Meeting

                                          • Nova Leadership:               • To review status of EMC status
                               Weekly     • EMC Leads                        report
 EMC Vendor
                   External    (every                                      • To discuss and escalate EMC
 Status Meeting
                               Friday)                                       issues and status


                                          • Nova Leadership:               • To discuss and escalate Oracle
                                                                             issues and status
                              Weekly
 Oracle Status
                   External    (every
 Meeting
                              Monday)



                                          • Nova Leadership:               • To review and escalate critical
                               Weekly     • Oracle Leads:                    Oracle SRs
 Oracle Critical
                   External     (every
 Account Call
                              Thursday)




         11
Release Management
    What components to be managed?



                             • Score Card
• Release Plan                                     • Status
•    System              •    Report of each   •      tracking
                                                   Each SDLC phase
     Development              phase in SDLC        is tracked with
     Lifecycle (SDLC)                              issues highlighted
     detailed out in a   •
     waterfall chart                           •

•




                                                                  12
Overall Release Plan
     • In order to monitor various releases and phases within the release, an overall release plan is
       created.
     • This will indicate the start & end dates , the duration of each phase, and an RFS date for each
       Release




                                                                  • Each release is depicted by
                                                                    a Waterfall diagram which
                                                                    shows the various phases of
                                                                    the Software Delivery
                                                                    Lifecycle (SDLC)




13
                                                                                                         13
Description of each phase within Release
     Phase      Description
     Plan       • Identify key people within organization and vendors and establish the roles and
                  responsibilities that they play within HSBB program
                • Identify key sponsor from vendors for escalation purpose
                • Establish clear governance model between Telekom Malaysia and other vendors
     Analyze
                • Identify high level requirements, current capabilities and to-be process
                • Identify application requirements

     Design
                • Design end to end solution for business processes
                • Define detailed hardware and software requirement in technical design

     Build      • Configure and customize modules based on solution blueprint.
                • Organize and execute system test as well as end to end testing between
                  applications, external and legacy systems.
     Test       • Integrate and test build components
                • Ensure robustness of system built before go-live
                • Identify, document and correct end-to-end defects encountered during testing
     Deploy
                • Conduct performance verification test
                • Coordinate and communicate complete deployment and migration plan


14                                                                                               14
Deliverables Management
                          • A standard user confirmation agreement is
                            obtained with the users at the start and end
                            of each phase

                          • This is important to ensure
                               Deliverables are complete within each
                               phase
                               The system and related documentation
                               is at the right readiness and quality
                               level before transitioning to next phase
                               All functional groups are aware of the
                               coming phase transition so they can
                               weigh in on whether the system and
                               documentation for the next phase is
                               indeed ready.

                            Lessons Learnt
                               Sessions organized to walkthrough
                               deliverable (group and even 1-on-1)
                               Keep user signoffs to relevant
                               stakeholders (minimal number)
15
                                                                           15
Status Tracking – Plan & Analyze
 Plan       Analyze   Design     Build     Test     Deploy

     • An Excel spreadsheet is used to track all requirements raised by stakeholders
     • Each requirement is tagged to an Application team that will review and provide
       feedback based on
           • whether requirement can be met using Out-Of-The-Box approach or requires
              customization
           • time and cost required to implement all requirements
     • Requirements are then prioritized according to the impact they have on the
       fulfillment of the stakeholders need.




16
                                                                                        16
Status Tracking – Design & Build
 Plan          Analyze        Design    Build         Test          Deploy
 Overall Status              Amber

 Product          Due         Planned                               Application                                 Actual
                  Date                   Siebel         OSM            Granite       OBRM         Portal
                                                                                                                   100%
                 14-Jan-11       100%    100%[100%]    100%[100%]      100%[100%]   100%[100%]      N/A
                                                                                                                  [100%]
   Direct
                                                                                                                   94%
                 25-Feb-11       100%    87.5%[84%]     89%[88%]       100%[100%]    100%[80%]      N/A
                                                                                                                  [93%]
                                                                                                                   85%
    IPVPN        25-Feb-11       100%    97%[95%]       99%[99%]       52%[51%]     94%[81%]        N/A
                                                                                                                  [81%]
 IPWholesale
 GlobalIPVPN                                                                                                       50%
                 4-Mar-11        80%     74%[68%]       64%[59%]       36%[19%]      27%[13%]       N/A
                                                                                             Last week’s % of     [41%]
                                                              This week’s %
   Global
                 4-Mar-11        0%         0%               0%         0%              0%   completion
                                                                                                    N/A         Not Started
  Ethernet                                                    of completion
    HSBC        18-Mar-11        0%         0%               0%           0%            0%          N/A         Not Started


 • Weekly Status Tracking on Design Documents and code for Build deliverables.
 • Design or Build phase progress is tracked by specific Telecom Products and across different
   Application Teams
 • Each team reports this week % completion versus last week’s % completion to ensure
   continuous progress
 • % completion is monitored against % planned to ensure Application team can meet due date
 • The various application team status is compiled to determine overall status of phase
 • An overall status of Red, Amber or Green is determined for the phase based on Actuals vs
   Planned.
        17
Status Tracking –Test
 Plan        Analyze   Design   Build      Test     Deploy

 • Test scenarios are categorised into different domains
 • Test scenarios executed is tracked against planned to monitor progress of testing
 • Number of passed, failed and blocked test conditions due to defects are tracked
   on daily basis.




        18
Status Tracking –Test
 Plan        Analyze   Design    Build      Test     Deploy

 • Issues that cause delay in the actual progress is reported and addressed.
 • Trends of test execution status (e.g. catching up, fallen further behind, progressing
   steadily) is monitored using Test Execution Progress graph.
 • An overall status of Red, Amber or Green is determined for the phase based on
   Actuals vs Planned.




        19
Status Tracking – Deployment Check List
 Plan        Analyze   Design   Build   Test   Deploy




                                                  • In preparation for release RFS,
                                                    production deployment check list is
                                                    communicated to all teams.
                                                  • Ownership of each check point is
                                                    clearly assigned and status
                                                    monitored on daily basis.
                                                  • Issues to be escalated in a timely
                                                    manner.
        20
Dependency Management
• Due to various external parties involvement, dependencies are created to track all tasks/activities that
  requires these parties to complete.
• All Program Dependencies are managed in a central location and the status of each dependency is
  monitored daily.
• An Excel spreadsheet is used to record area of dependency e.g. CSM, description of dependency and
  dependency due date.
• Person-In-Charge (PIC) must be indicated to ensure responsibility and accountability.




        21
Dependency Management
• A summary of dependencies is illustrated in Dependency Tree below.
• Overdue open dependencies are highlighted to the Steering Committee




                                                                        22
Dependency Management
    • The impact of each overdue dependency is further elaborated.
    • Team will discuss with the PIC of the dependency on actions moving forward, and revised due date
    • The outcome of the discussion will be then shared with the Steering Committee



     Traffic
#                                Description                      Status                         Actions
      Light
1     RED      Dorado Complete NBI Delivery Delay                Due date:   • Discussion conducted with Dorado. Dorado
                                                                 28-Feb-11     confirm that delivery will be expedited. The
               • Dorado Development team has initially           15-Apr-11     revised delivery of NBI is on 15-Apr TBD
                 reverted the NBI delivery date                     TBD
                       • Phase 1 (New Install): 1-Apr                        • Dorado PO issues – Dorado did not deliver
                       • Phase 2 (Modify): 15-Apr                              NBI on 1st Apr 2011 or 15-Apr as planned

               • Both test lab and NBI is required to be fully
                 ready and deployed for NOVA SIT test by 1-
                 Apr
2     RED      No onsite support identified for DORADO           Due date:   • Discussion still ongoing between DORADO
                                                                 4-Apr-11      and TM.
                                                                             • Dorado PO Issue – Dorado was unable to
                                                                               provide support by 4-Apr-11


                                                                                                  23
Change Request Management

                        • Over the course of the project
                          lifecycle, changes to the original
                          scope of work is inevitable.
                          Change Requests must be
                          managed to reduce risk of time
                          extension


                        • Roles and Responsibilities of all
                          partiess must be clearly defined ,
                          agreed and communicated.


                        • Process depicted ensures CRs
                          raised are collected, reviewed,
                          approved and implemented
                          following a structured practice.



   24
Vendor Management

                                           A proper agreement must be made
                                           between client and vendors to
                                           ensure adequate support is provided
                                           throughout project lifecycle and post
                                           go-live




 A good escalation model must be
 established to ensure any critical
                                                               Critical
 product defects that impact project
 deadline, causes revenue loss and                            Accounts
 production downtime is resolved
                                                         Escalation to Oracle
 immediately                                            Duty Manager/ Oracle
                                                           On-Site Support



                                                   Service Request Raised on Oracle
                                Hardware                      Metalink

   Software Principals

    25
Vendor Management
 • A weekly meeting with the Vendors should be scheduled.
 • This is necessary in order to summarize the key product defects which have been
   raised by the Program and to ensure that the vendors are fixing defects
   adequately.




    26

More Related Content

What's hot

01 Ts A Pmg Product Write Up
01 Ts A Pmg Product Write Up01 Ts A Pmg Product Write Up
01 Ts A Pmg Product Write Up
Stefan Afendoulis
 
2 trasnformation design_patterns-sandeep_katoch
2 trasnformation design_patterns-sandeep_katoch2 trasnformation design_patterns-sandeep_katoch
2 trasnformation design_patterns-sandeep_katochIBM
 
Visão Geral do Schedule Manager
Visão Geral do Schedule ManagerVisão Geral do Schedule Manager
Visão Geral do Schedule Manager
PLMX -Soluções para Negocios
 
Science Modernisation Strategy v1 0
Science  Modernisation  Strategy v1 0Science  Modernisation  Strategy v1 0
Science Modernisation Strategy v1 0
Salim Sheikh
 
3 hang on_a_minute-ankur_goyal
3 hang on_a_minute-ankur_goyal3 hang on_a_minute-ankur_goyal
3 hang on_a_minute-ankur_goyalIBM
 
Gestión de Gobierno, Riesgos y Reglamentaciones (GRC)
Gestión de Gobierno, Riesgos y Reglamentaciones (GRC)Gestión de Gobierno, Riesgos y Reglamentaciones (GRC)
Gestión de Gobierno, Riesgos y Reglamentaciones (GRC)
Rafael Antona
 
Cmmi constellations.pptx
Cmmi constellations.pptxCmmi constellations.pptx
Cmmi constellations.pptx
André Heijstek
 
Erp Implementation Methodology Wkshp 2.0 120611
Erp Implementation Methodology Wkshp 2.0 120611Erp Implementation Methodology Wkshp 2.0 120611
Erp Implementation Methodology Wkshp 2.0 120611
John Paulson
 
10 tips for Chartering a Project
10 tips for Chartering a Project10 tips for Chartering a Project
10 tips for Chartering a ProjectGlen Alleman
 
[AgileCMMI] Practical Experience Report: Application of Project Management ar...
[AgileCMMI] Practical Experience Report: Application of Project Management ar...[AgileCMMI] Practical Experience Report: Application of Project Management ar...
[AgileCMMI] Practical Experience Report: Application of Project Management ar...
davidobama
 
LeverX - A Comprehensive Guide to SAP PLM 7.01
LeverX - A Comprehensive Guide to SAP PLM 7.01LeverX - A Comprehensive Guide to SAP PLM 7.01
LeverX - A Comprehensive Guide to SAP PLM 7.01
LeverX
 
10 tips for chartering a project (v2)
10 tips for chartering a project (v2)10 tips for chartering a project (v2)
10 tips for chartering a project (v2)Glen Alleman
 
ERP Project Management Primer
ERP Project Management PrimerERP Project Management Primer
ERP Project Management Primer
sureshgk
 
PRINCE2 and Six-Sigma
PRINCE2 and Six-SigmaPRINCE2 and Six-Sigma
PRINCE2 and Six-Sigma
mchouha
 
How to make_it_real-hayden_lindsey
How to make_it_real-hayden_lindseyHow to make_it_real-hayden_lindsey
How to make_it_real-hayden_lindseyIBM
 
Exploiting Tools for Faster, More Acceptable Process Improvement Initiatives
Exploiting Tools for Faster, More Acceptable Process Improvement InitiativesExploiting Tools for Faster, More Acceptable Process Improvement Initiatives
Exploiting Tools for Faster, More Acceptable Process Improvement InitiativesMahesh Singh
 
Biju 2008 Pmi Whitepaper
Biju 2008 Pmi WhitepaperBiju 2008 Pmi Whitepaper
Biju 2008 Pmi Whitepaper
Biju Pillai PMP®,ITIL,COBIT,PRINCE2
 
Intro To CA 2E Change Management
Intro To CA 2E Change ManagementIntro To CA 2E Change Management
Intro To CA 2E Change ManagementADC Austin Tech
 

What's hot (18)

01 Ts A Pmg Product Write Up
01 Ts A Pmg Product Write Up01 Ts A Pmg Product Write Up
01 Ts A Pmg Product Write Up
 
2 trasnformation design_patterns-sandeep_katoch
2 trasnformation design_patterns-sandeep_katoch2 trasnformation design_patterns-sandeep_katoch
2 trasnformation design_patterns-sandeep_katoch
 
Visão Geral do Schedule Manager
Visão Geral do Schedule ManagerVisão Geral do Schedule Manager
Visão Geral do Schedule Manager
 
Science Modernisation Strategy v1 0
Science  Modernisation  Strategy v1 0Science  Modernisation  Strategy v1 0
Science Modernisation Strategy v1 0
 
3 hang on_a_minute-ankur_goyal
3 hang on_a_minute-ankur_goyal3 hang on_a_minute-ankur_goyal
3 hang on_a_minute-ankur_goyal
 
Gestión de Gobierno, Riesgos y Reglamentaciones (GRC)
Gestión de Gobierno, Riesgos y Reglamentaciones (GRC)Gestión de Gobierno, Riesgos y Reglamentaciones (GRC)
Gestión de Gobierno, Riesgos y Reglamentaciones (GRC)
 
Cmmi constellations.pptx
Cmmi constellations.pptxCmmi constellations.pptx
Cmmi constellations.pptx
 
Erp Implementation Methodology Wkshp 2.0 120611
Erp Implementation Methodology Wkshp 2.0 120611Erp Implementation Methodology Wkshp 2.0 120611
Erp Implementation Methodology Wkshp 2.0 120611
 
10 tips for Chartering a Project
10 tips for Chartering a Project10 tips for Chartering a Project
10 tips for Chartering a Project
 
[AgileCMMI] Practical Experience Report: Application of Project Management ar...
[AgileCMMI] Practical Experience Report: Application of Project Management ar...[AgileCMMI] Practical Experience Report: Application of Project Management ar...
[AgileCMMI] Practical Experience Report: Application of Project Management ar...
 
LeverX - A Comprehensive Guide to SAP PLM 7.01
LeverX - A Comprehensive Guide to SAP PLM 7.01LeverX - A Comprehensive Guide to SAP PLM 7.01
LeverX - A Comprehensive Guide to SAP PLM 7.01
 
10 tips for chartering a project (v2)
10 tips for chartering a project (v2)10 tips for chartering a project (v2)
10 tips for chartering a project (v2)
 
ERP Project Management Primer
ERP Project Management PrimerERP Project Management Primer
ERP Project Management Primer
 
PRINCE2 and Six-Sigma
PRINCE2 and Six-SigmaPRINCE2 and Six-Sigma
PRINCE2 and Six-Sigma
 
How to make_it_real-hayden_lindsey
How to make_it_real-hayden_lindseyHow to make_it_real-hayden_lindsey
How to make_it_real-hayden_lindsey
 
Exploiting Tools for Faster, More Acceptable Process Improvement Initiatives
Exploiting Tools for Faster, More Acceptable Process Improvement InitiativesExploiting Tools for Faster, More Acceptable Process Improvement Initiatives
Exploiting Tools for Faster, More Acceptable Process Improvement Initiatives
 
Biju 2008 Pmi Whitepaper
Biju 2008 Pmi WhitepaperBiju 2008 Pmi Whitepaper
Biju 2008 Pmi Whitepaper
 
Intro To CA 2E Change Management
Intro To CA 2E Change ManagementIntro To CA 2E Change Management
Intro To CA 2E Change Management
 

Similar to Dec 2012 Evening Talk - Managing Complex Project

Aceicon epm software
Aceicon epm softwareAceicon epm software
Aceicon epm softwareaceicon
 
McKesson Accelerated Services
McKesson Accelerated ServicesMcKesson Accelerated Services
McKesson Accelerated Services
Mangeserve
 
Skelta Corporate Brochure
Skelta Corporate BrochureSkelta Corporate Brochure
Skelta Corporate Brochure
Schneider Electric
 
Ims Primavera
Ims PrimaveraIms Primavera
Ims Primaveracleary21
 
مناهج التعليم وصناعة البرمجيات
مناهج التعليم وصناعة البرمجياتمناهج التعليم وصناعة البرمجيات
مناهج التعليم وصناعة البرمجيات
Eiman Idris
 
Run sap methodology how to implement end to-end solution operations
Run sap methodology  how to implement end to-end solution operations  Run sap methodology  how to implement end to-end solution operations
Run sap methodology how to implement end to-end solution operations ricardopabloasensio
 
Application Lifecycle Management & VSTS
Application Lifecycle Management & VSTSApplication Lifecycle Management & VSTS
Application Lifecycle Management & VSTS
Microsoft Iceland
 
Strivent Service Offerings Differentiators Web 2 9
Strivent Service Offerings  Differentiators Web 2 9Strivent Service Offerings  Differentiators Web 2 9
Strivent Service Offerings Differentiators Web 2 9John Streit
 
Engineering Project Management Framework white paper
Engineering Project Management Framework white paperEngineering Project Management Framework white paper
Engineering Project Management Framework white paperguestae4c6b
 
Agile project management is systems management
Agile project management is systems managementAgile project management is systems management
Agile project management is systems managementGlen Alleman
 
ITIL® im Microsoft-Umfeld: Einführung in das MOF
ITIL® im Microsoft-Umfeld: Einführung in das MOFITIL® im Microsoft-Umfeld: Einführung in das MOF
ITIL® im Microsoft-Umfeld: Einführung in das MOFDigicomp Academy AG
 
PMI Long Island Chapter
PMI Long Island ChapterPMI Long Island Chapter
PMI Long Island Chapter
NBCUniversal, Inc.
 
Skyward Erp Presentation
Skyward Erp PresentationSkyward Erp Presentation
Skyward Erp Presentation
vishalnvora1
 
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdfPrimavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdfInSync2011
 
Project management best practices
Project management best practicesProject management best practices
Project management best practices
walkerswu
 
Dan Drew Resume
Dan Drew ResumeDan Drew Resume
Dan Drew Resumedrewdw
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned Value
Glen Alleman
 
Stefan Pappe Making S O A Operational
Stefan  Pappe    Making  S O A  OperationalStefan  Pappe    Making  S O A  Operational
Stefan Pappe Making S O A OperationalSOA Symposium
 

Similar to Dec 2012 Evening Talk - Managing Complex Project (20)

Aceicon epm software
Aceicon epm softwareAceicon epm software
Aceicon epm software
 
McKesson Accelerated Services
McKesson Accelerated ServicesMcKesson Accelerated Services
McKesson Accelerated Services
 
Skelta Corporate Brochure
Skelta Corporate BrochureSkelta Corporate Brochure
Skelta Corporate Brochure
 
Ims Primavera
Ims PrimaveraIms Primavera
Ims Primavera
 
مناهج التعليم وصناعة البرمجيات
مناهج التعليم وصناعة البرمجياتمناهج التعليم وصناعة البرمجيات
مناهج التعليم وصناعة البرمجيات
 
Run sap methodology how to implement end to-end solution operations
Run sap methodology  how to implement end to-end solution operations  Run sap methodology  how to implement end to-end solution operations
Run sap methodology how to implement end to-end solution operations
 
Application Lifecycle Management & VSTS
Application Lifecycle Management & VSTSApplication Lifecycle Management & VSTS
Application Lifecycle Management & VSTS
 
Strivent Service Offerings Differentiators Web 2 9
Strivent Service Offerings  Differentiators Web 2 9Strivent Service Offerings  Differentiators Web 2 9
Strivent Service Offerings Differentiators Web 2 9
 
Epm 2010
Epm 2010Epm 2010
Epm 2010
 
Engineering Project Management Framework white paper
Engineering Project Management Framework white paperEngineering Project Management Framework white paper
Engineering Project Management Framework white paper
 
Agile project management is systems management
Agile project management is systems managementAgile project management is systems management
Agile project management is systems management
 
ITIL® im Microsoft-Umfeld: Einführung in das MOF
ITIL® im Microsoft-Umfeld: Einführung in das MOFITIL® im Microsoft-Umfeld: Einführung in das MOF
ITIL® im Microsoft-Umfeld: Einführung in das MOF
 
PMI Long Island Chapter
PMI Long Island ChapterPMI Long Island Chapter
PMI Long Island Chapter
 
Skyward Erp Presentation
Skyward Erp PresentationSkyward Erp Presentation
Skyward Erp Presentation
 
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdfPrimavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
 
Project management best practices
Project management best practicesProject management best practices
Project management best practices
 
Chapter 11
Chapter 11Chapter 11
Chapter 11
 
Dan Drew Resume
Dan Drew ResumeDan Drew Resume
Dan Drew Resume
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned Value
 
Stefan Pappe Making S O A Operational
Stefan  Pappe    Making  S O A  OperationalStefan  Pappe    Making  S O A  Operational
Stefan Pappe Making S O A Operational
 

More from Zulkefle Idris

PMIMY Evening Talk 26 Feb 2014
PMIMY Evening Talk 26 Feb 2014PMIMY Evening Talk 26 Feb 2014
PMIMY Evening Talk 26 Feb 2014Zulkefle Idris
 
Pmimy Evening Talk Oct 2013
Pmimy Evening Talk Oct 2013Pmimy Evening Talk Oct 2013
Pmimy Evening Talk Oct 2013
Zulkefle Idris
 
Pmimy Evening Talk Sept 2013
Pmimy Evening Talk Sept 2013Pmimy Evening Talk Sept 2013
Pmimy Evening Talk Sept 2013
Zulkefle Idris
 
Program Management Experience from DHL Express IT Programs
Program Management Experience from DHL Express IT ProgramsProgram Management Experience from DHL Express IT Programs
Program Management Experience from DHL Express IT Programs
Zulkefle Idris
 
PMIMY Evening Talk flyer Mar 2013
PMIMY Evening Talk flyer Mar 2013PMIMY Evening Talk flyer Mar 2013
PMIMY Evening Talk flyer Mar 2013
Zulkefle Idris
 
Delivering to Budget: Advanced Project Cost Management
Delivering to Budget: Advanced Project Cost ManagementDelivering to Budget: Advanced Project Cost Management
Delivering to Budget: Advanced Project Cost ManagementZulkefle Idris
 
Gaining Maximum Control: Managing Multiple Projects Effectively
Gaining Maximum Control: Managing Multiple Projects EffectivelyGaining Maximum Control: Managing Multiple Projects Effectively
Gaining Maximum Control: Managing Multiple Projects EffectivelyZulkefle Idris
 
EPC Project Risk and Technical Efficiency
EPC Project Risk and Technical EfficiencyEPC Project Risk and Technical Efficiency
EPC Project Risk and Technical EfficiencyZulkefle Idris
 
Enterprise Governance: The Impact of Enterprise Governance on Effective Proje...
Enterprise Governance: The Impact of Enterprise Governance on Effective Proje...Enterprise Governance: The Impact of Enterprise Governance on Effective Proje...
Enterprise Governance: The Impact of Enterprise Governance on Effective Proje...
Zulkefle Idris
 
How to claim your 7 PDUs
How to claim your 7 PDUsHow to claim your 7 PDUs
How to claim your 7 PDUs
Zulkefle Idris
 
01 intro to_entreneurship
01 intro to_entreneurship01 intro to_entreneurship
01 intro to_entreneurshipZulkefle Idris
 
How to choose_a_good_company_name-2
How to choose_a_good_company_name-2How to choose_a_good_company_name-2
How to choose_a_good_company_name-2Zulkefle Idris
 
09 membentuk team_bisnes
09 membentuk team_bisnes09 membentuk team_bisnes
09 membentuk team_bisnesZulkefle Idris
 
The entrepreneur mind_set
The entrepreneur mind_setThe entrepreneur mind_set
The entrepreneur mind_setZulkefle Idris
 
The entrepreneurial process
The entrepreneurial processThe entrepreneurial process
The entrepreneurial processZulkefle Idris
 
01 intro to_entreneurship
01 intro to_entreneurship01 intro to_entreneurship
01 intro to_entreneurshipZulkefle Idris
 

More from Zulkefle Idris (17)

PMIMY Evening Talk 26 Feb 2014
PMIMY Evening Talk 26 Feb 2014PMIMY Evening Talk 26 Feb 2014
PMIMY Evening Talk 26 Feb 2014
 
Pmimy Evening Talk Oct 2013
Pmimy Evening Talk Oct 2013Pmimy Evening Talk Oct 2013
Pmimy Evening Talk Oct 2013
 
Pmimy Evening Talk Sept 2013
Pmimy Evening Talk Sept 2013Pmimy Evening Talk Sept 2013
Pmimy Evening Talk Sept 2013
 
Program Management Experience from DHL Express IT Programs
Program Management Experience from DHL Express IT ProgramsProgram Management Experience from DHL Express IT Programs
Program Management Experience from DHL Express IT Programs
 
PMIMY Evening Talk flyer Mar 2013
PMIMY Evening Talk flyer Mar 2013PMIMY Evening Talk flyer Mar 2013
PMIMY Evening Talk flyer Mar 2013
 
Delivering to Budget: Advanced Project Cost Management
Delivering to Budget: Advanced Project Cost ManagementDelivering to Budget: Advanced Project Cost Management
Delivering to Budget: Advanced Project Cost Management
 
Gaining Maximum Control: Managing Multiple Projects Effectively
Gaining Maximum Control: Managing Multiple Projects EffectivelyGaining Maximum Control: Managing Multiple Projects Effectively
Gaining Maximum Control: Managing Multiple Projects Effectively
 
EPC Project Risk and Technical Efficiency
EPC Project Risk and Technical EfficiencyEPC Project Risk and Technical Efficiency
EPC Project Risk and Technical Efficiency
 
Enterprise Governance: The Impact of Enterprise Governance on Effective Proje...
Enterprise Governance: The Impact of Enterprise Governance on Effective Proje...Enterprise Governance: The Impact of Enterprise Governance on Effective Proje...
Enterprise Governance: The Impact of Enterprise Governance on Effective Proje...
 
How to claim your 7 PDUs
How to claim your 7 PDUsHow to claim your 7 PDUs
How to claim your 7 PDUs
 
01 intro to_entreneurship
01 intro to_entreneurship01 intro to_entreneurship
01 intro to_entreneurship
 
How to choose_a_good_company_name-2
How to choose_a_good_company_name-2How to choose_a_good_company_name-2
How to choose_a_good_company_name-2
 
09 membentuk team_bisnes
09 membentuk team_bisnes09 membentuk team_bisnes
09 membentuk team_bisnes
 
The entrepreneur mind_set
The entrepreneur mind_setThe entrepreneur mind_set
The entrepreneur mind_set
 
09 new venture_team
09 new venture_team09 new venture_team
09 new venture_team
 
The entrepreneurial process
The entrepreneurial processThe entrepreneurial process
The entrepreneurial process
 
01 intro to_entreneurship
01 intro to_entreneurship01 intro to_entreneurship
01 intro to_entreneurship
 

Recently uploaded

ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
agatadrynko
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Avirahi City Dholera
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
balatucanapplelovely
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 

Recently uploaded (20)

ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 

Dec 2012 Evening Talk - Managing Complex Project

  • 1. PMIMY EVENING TALK MANAGING COMPLEX PROJECT Suharti Mohd Ali Program Director IT Transformation Celcom Axiata Bhd
  • 2. What I will Share Tonight 1 Criteria of A Complex Project 2 Areas of Work for Scrutiny 3 Measures of Success 4 Pitfalls to Look Out For 5 Question Time 2
  • 3. What is a Complex Project? Budget used to be the sole determinant of complexity, but not anymore any project with more than 3 parties to be managed any project with more than 3 systems to be retired in the process any project which impact more than 3 divisions in the organization totaling more than 300 people Any project which require a team structure of more than 150 people any project introducing more than 3 new applications to the business……… 3
  • 4. What Makes a Project Complex? There is now an Institute of Complex Projects who is in the midst of devising a tool to assess complexity and complexity levels to help delivery teams put a structure in place But the science of determining if a project is complex or otherwise is the simplest task – the real test is HOW do we deal with it. 4
  • 5. Complex legacy landscape was a challenge in supporting the HSBB agenda .. • Numerous and disparate support systems • 30+ user communities to engage catering to different products and lines of businesses • 68 level 3 and 210 level 4 business processes • Legacy, custom-built applications and point-to-point data transfers • 100+ systems interfaces to develop • Increased complexity and time to enhance for HSBB transformation 5
  • 6. Numerous Vendors PMO & Systems Integrator Software Principals Storage Hardware Jointly managed with a single lead SI/PMO (Accenture) to deliver a full-suite of integrated, end- to-end BSS/OSS/SDP capabilities … ▪ … under a unified program structure focusing on end-to-end deployment of systems, processes and organization as a business capability, and ▪ … with the right operational and knowledge transfer activities to form a full business solution for TM 6 6
  • 7. Areas of Work for Scrutiny There are 8 critical areas of work that not only need to be managed but need scrutiny to its most micro level Program Structure & Governance Release Management Dependency Management Deliverable Sign-Off Management Risks and Issue Management Change Request Management Vendor Management Tools 7
  • 8. Project Organization Chart – Sample Structure Project governance and reporting structure is set up to ensure roles and responsibilities are established and lines of escalation are communicated Supervise the overall project progress , ensure Project Manager all scheduled milestones are completed on time. Solution Oversee and manage project level dependencies, risks Authority for overall solution within project Release Management and issues, monitor delivery progress and vendor program, manage and circuit break cross team Architecture management. issues, risks and dependencies Vendor Management Application Teams Migration Testing Tech. Arch. Business Integration Order Order Team Team Team Team Integration Capture Mgmt Design and develop required Design and implement Product Web Portal SR/TT migration tools. Coordinate technical architecture, Mgmt and perform migration from infrastructure. legacy into new systems. Campaign Other Analytics Mgmt Apps… • Perform analysis and maintain system and data integration User through various functional designs. E2E Integration Performance Business Acceptance Training Comms • Design, build and test business capabilities based on the new Testing Testing Process Testing process and requirements • Document and maintain integration requirements. Perform Integration Coordinate and perform Coordinate and conduct Perform business Plan and perform Develop change Test to ensure the end- User Acceptance Test to performance and volume process alignment required training. and communication to-end solution ensure the solution is in test to ensure the by designing, Develop required plans for project. conforms to the level of line with the solution performance is validating and training materials quality set in the design. expectations of the acceptable within deploying the ‘to- users. defined SLA. be’ business processes 8 * Proposed structure to be validated & customized by each project team to suite specific project needs
  • 9. Program Governance Leadership must be planned in order to closely monitor the Program and keep two- way communication channel open • Objective - To provide update on progress of project. • Frequency - 1 per quarter Board • Participants - Board of directors, CIO, PMO team. • Objective - Discuss project issues and agree upon next steps. • Frequency - 1 per fortnight Steering Committee • Participants - CIO, Steering Committee, PMO team. • Objective - To provide CIO with progress updates, highlight and seek direction on project issues. CIO updates • Frequency - 1 per fortnight • Participants – CIO, Accenture Delivery Lead • Objective - Review progress, and address key topics at a project level. Project Leadership • Frequency - 1 per week Meetings • Participants (Internal Meeting ) – PMO Team, Delivery Lead, Leads from different work streams, HR contact (when required) • Participants (External Meeting ) – Accenture leadership teams and client leads Team Meetings • Objective – Team leads to review progress of their teams, and any issues which their team is facing. • Frequency - 1 per week • Participants - Team leads with team members 9
  • 10. Program Governance – External Meetings A structure was setup with the Client in order to highlight issues and report status of the overall progress Meetings Type Frequency Key Attendees Purpose of Meeting • TM Leadership Team: Chee • To update TM leadership on the overall program status Systems Steering Weekly Committee • To highlight issues and decisions External (every for Steering Committee guidance Meeting Tuesday) and direction • • To update TM Systems leadership on the overall program Weekly status CIO Systems External (every Update • To highlight issues and decisions Friday) for IT Leadership guidance and direction • Nova Leadership: • Internal Program meeting to run through overall program status & Nova IT Program Weekly potential impacts to the schedule. Leadership External (every Meeting Wednesday) • Any major escalations/issues should be highlighted in the Program Leadership meeting. • Nova Leadership • Internal Program meeting to run • TM Business: through overall program status & Weekly potential impacts to the schedule. iCarePrime Status External (every Meeting • Any major escalations/issues Thursday) should be highlighted in the Program Leadership meeting. 10
  • 11. Program Governance – Vendor Meetings This structure is replicated with the various Vendors in order to discuss status and escalate vendor specific issues Meetings Type Frequency Key Attendees Purpose of Meeting • Nova Leadership: • To review status of EMC status Weekly • EMC Leads report EMC Vendor External (every • To discuss and escalate EMC Status Meeting Friday) issues and status • Nova Leadership: • To discuss and escalate Oracle issues and status Weekly Oracle Status External (every Meeting Monday) • Nova Leadership: • To review and escalate critical Weekly • Oracle Leads: Oracle SRs Oracle Critical External (every Account Call Thursday) 11
  • 12. Release Management What components to be managed? • Score Card • Release Plan • Status • System • Report of each • tracking Each SDLC phase Development phase in SDLC is tracked with Lifecycle (SDLC) issues highlighted detailed out in a • waterfall chart • • 12
  • 13. Overall Release Plan • In order to monitor various releases and phases within the release, an overall release plan is created. • This will indicate the start & end dates , the duration of each phase, and an RFS date for each Release • Each release is depicted by a Waterfall diagram which shows the various phases of the Software Delivery Lifecycle (SDLC) 13 13
  • 14. Description of each phase within Release Phase Description Plan • Identify key people within organization and vendors and establish the roles and responsibilities that they play within HSBB program • Identify key sponsor from vendors for escalation purpose • Establish clear governance model between Telekom Malaysia and other vendors Analyze • Identify high level requirements, current capabilities and to-be process • Identify application requirements Design • Design end to end solution for business processes • Define detailed hardware and software requirement in technical design Build • Configure and customize modules based on solution blueprint. • Organize and execute system test as well as end to end testing between applications, external and legacy systems. Test • Integrate and test build components • Ensure robustness of system built before go-live • Identify, document and correct end-to-end defects encountered during testing Deploy • Conduct performance verification test • Coordinate and communicate complete deployment and migration plan 14 14
  • 15. Deliverables Management • A standard user confirmation agreement is obtained with the users at the start and end of each phase • This is important to ensure Deliverables are complete within each phase The system and related documentation is at the right readiness and quality level before transitioning to next phase All functional groups are aware of the coming phase transition so they can weigh in on whether the system and documentation for the next phase is indeed ready. Lessons Learnt Sessions organized to walkthrough deliverable (group and even 1-on-1) Keep user signoffs to relevant stakeholders (minimal number) 15 15
  • 16. Status Tracking – Plan & Analyze Plan Analyze Design Build Test Deploy • An Excel spreadsheet is used to track all requirements raised by stakeholders • Each requirement is tagged to an Application team that will review and provide feedback based on • whether requirement can be met using Out-Of-The-Box approach or requires customization • time and cost required to implement all requirements • Requirements are then prioritized according to the impact they have on the fulfillment of the stakeholders need. 16 16
  • 17. Status Tracking – Design & Build Plan Analyze Design Build Test Deploy Overall Status Amber Product Due Planned Application Actual Date Siebel OSM Granite OBRM Portal 100% 14-Jan-11 100% 100%[100%] 100%[100%] 100%[100%] 100%[100%] N/A [100%] Direct 94% 25-Feb-11 100% 87.5%[84%] 89%[88%] 100%[100%] 100%[80%] N/A [93%] 85% IPVPN 25-Feb-11 100% 97%[95%] 99%[99%] 52%[51%] 94%[81%] N/A [81%] IPWholesale GlobalIPVPN 50% 4-Mar-11 80% 74%[68%] 64%[59%] 36%[19%] 27%[13%] N/A Last week’s % of [41%] This week’s % Global 4-Mar-11 0% 0% 0% 0% 0% completion N/A Not Started Ethernet of completion HSBC 18-Mar-11 0% 0% 0% 0% 0% N/A Not Started • Weekly Status Tracking on Design Documents and code for Build deliverables. • Design or Build phase progress is tracked by specific Telecom Products and across different Application Teams • Each team reports this week % completion versus last week’s % completion to ensure continuous progress • % completion is monitored against % planned to ensure Application team can meet due date • The various application team status is compiled to determine overall status of phase • An overall status of Red, Amber or Green is determined for the phase based on Actuals vs Planned. 17
  • 18. Status Tracking –Test Plan Analyze Design Build Test Deploy • Test scenarios are categorised into different domains • Test scenarios executed is tracked against planned to monitor progress of testing • Number of passed, failed and blocked test conditions due to defects are tracked on daily basis. 18
  • 19. Status Tracking –Test Plan Analyze Design Build Test Deploy • Issues that cause delay in the actual progress is reported and addressed. • Trends of test execution status (e.g. catching up, fallen further behind, progressing steadily) is monitored using Test Execution Progress graph. • An overall status of Red, Amber or Green is determined for the phase based on Actuals vs Planned. 19
  • 20. Status Tracking – Deployment Check List Plan Analyze Design Build Test Deploy • In preparation for release RFS, production deployment check list is communicated to all teams. • Ownership of each check point is clearly assigned and status monitored on daily basis. • Issues to be escalated in a timely manner. 20
  • 21. Dependency Management • Due to various external parties involvement, dependencies are created to track all tasks/activities that requires these parties to complete. • All Program Dependencies are managed in a central location and the status of each dependency is monitored daily. • An Excel spreadsheet is used to record area of dependency e.g. CSM, description of dependency and dependency due date. • Person-In-Charge (PIC) must be indicated to ensure responsibility and accountability. 21
  • 22. Dependency Management • A summary of dependencies is illustrated in Dependency Tree below. • Overdue open dependencies are highlighted to the Steering Committee 22
  • 23. Dependency Management • The impact of each overdue dependency is further elaborated. • Team will discuss with the PIC of the dependency on actions moving forward, and revised due date • The outcome of the discussion will be then shared with the Steering Committee Traffic # Description Status Actions Light 1 RED Dorado Complete NBI Delivery Delay Due date: • Discussion conducted with Dorado. Dorado 28-Feb-11 confirm that delivery will be expedited. The • Dorado Development team has initially 15-Apr-11 revised delivery of NBI is on 15-Apr TBD reverted the NBI delivery date TBD • Phase 1 (New Install): 1-Apr • Dorado PO issues – Dorado did not deliver • Phase 2 (Modify): 15-Apr NBI on 1st Apr 2011 or 15-Apr as planned • Both test lab and NBI is required to be fully ready and deployed for NOVA SIT test by 1- Apr 2 RED No onsite support identified for DORADO Due date: • Discussion still ongoing between DORADO 4-Apr-11 and TM. • Dorado PO Issue – Dorado was unable to provide support by 4-Apr-11 23
  • 24. Change Request Management • Over the course of the project lifecycle, changes to the original scope of work is inevitable. Change Requests must be managed to reduce risk of time extension • Roles and Responsibilities of all partiess must be clearly defined , agreed and communicated. • Process depicted ensures CRs raised are collected, reviewed, approved and implemented following a structured practice. 24
  • 25. Vendor Management A proper agreement must be made between client and vendors to ensure adequate support is provided throughout project lifecycle and post go-live A good escalation model must be established to ensure any critical Critical product defects that impact project deadline, causes revenue loss and Accounts production downtime is resolved Escalation to Oracle immediately Duty Manager/ Oracle On-Site Support Service Request Raised on Oracle Hardware Metalink Software Principals 25
  • 26. Vendor Management • A weekly meeting with the Vendors should be scheduled. • This is necessary in order to summarize the key product defects which have been raised by the Program and to ensure that the vendors are fixing defects adequately. 26