SlideShare a Scribd company logo
1 of 26
Download to read offline
PRODUCTION OF20 MILLION STANDARD CUBIC
FEET PER DAY (0.515 X 106 STANDARD M3/DAY) OF
HYDROGEN OF AT LEAST 95 PER CENT PURITY
HYDROGEN FROM HEAVY FUEL OIL FEEDSTOCKS
B Y
OLANREWAJU, ADEBAYO
BAMIDELE
ADEBAYOOLANREWAJU206@GMAIL.COM
+234 (0) 7037710839
Introduction
General overview of H2
 Hydrogen is a
 colourless,
 odourless,
 tasteless,
 flammable gaseous substance that is the simplest member of
the family of chemical elements.
 Present in all animal and vegetable tissue and in petroleum.
 Manufacture of ammonia and others
Introduction contd.
H2 Demand
 World consumption of both captive and merchant hydrogen will
increase 3.5% annually through 2018 to more than 300billion cubic
meters.
Introduction contd.
 Hydrogen Uses
Introduction contd.
Methods of preparation
 Partial Oxidation (POX)
 It involves an intimate coupling of several complex chemical
reaction of hydrocarbon feed with oxygen at high temperatures to
produce a mixture of hydrogen and carbon monoxide.
 The partial oxidation reaction mechanism involves exothermic,
partial combustion of a portion of a hydrocarbon feed which
supplies heat to the endothermic steam cracking of the balance of
the feed.
 Besides carbon monoxide, hydrogen, carbon dioxide, hydrogen
sulfide, and other trace impurities, partial oxidation produces
soot in non-equilibrium amounts.
 Since the high temperature takes the place of a catalyst, POX is
not limited to the light, clean feedstocks required for steam
reforming.
Method of Preparation contd.
 Others include:
 Advanced Cracking Reaction (ACR)
 Catalytic Partial Oxidation
 Thermochemical (High-temperature) Water Splitting.
Feedstock for H2 Production
 Natural Gas
 Refinery Gas
 Liquid Feeds (LPG & Naphtha)
 Heavy Fuel Oil
DISCUSSION
 Process Design
1. Preparation of a mass balance diagram for the entire plant,
2. Preparation of an energy balance diagram of the flame
reactor and the associated waste heat boiler,
3. Preparation of a Process flow diagram of the entire plant.
Discussion contd.
 Mass Balance
Discussion contd.
 Material Balance Basis
 In order to perform the material balance calculations, an
assumed basis of 1000 kg of Heavy Fuel Oil feed was selected.
Discussion contd.
 From the above, and as calculated on appendix 1, the production
rate was found to be 4.041x108m3/hr.
 Hence, the rate of flow of CO, CO2, N2 into the conversion
system were found to be 4040918m3/hr, 4040918m3/hr and
8081836m3/hr. respectively.
 While CO, CO2 coming out of the quencher were calculated to
242,455,080 m3 and 47,913,742 m3 respectively.
 Also, the amount of CO converted is 238,414,162 m3. Then, H2,
CH4 out of the converter were found to be 271,318,780 m3 and
57,727m3 respectively.
 Finally, the amount of H2 produced in the converter was found
to be 1.329 x 108m3.
Discussion contd.
 Energy Balance
 Energy Balance Diagram for the Flame Reactor and the Associated Waste
Heat Boiler (WHB).

Energy Balance Contd.
 The values of the material streams indicated were
extracted from the mass balance diagram discussed
earlier.
 As indicated in the diagram the mass of steam
produced by waste heat boiler was estimated to be
7930.95kg while energy of the crude gas leaving the
waste heat boiler is 4.537 x 1011 kJ.
 The energy required to produce steam by the waste
heat boiler was estimated to be 22,325,624.25 kJ.
Discussion contd.
 Process Flow Diagram
• The Preliminary Block Flow Diagram
Discussion contd.
 Equipment Schedule for the CO Conversion Section of
the Plant
1. Introduction
• In order to meet the production capacity as stated in the process
description, the process is scheduled to run all day long (24hrs
of the day).
• The following are the various utilities and items of equipment
involved in the CO conversion section of the plant:
• Utilities: Heat supply, Potassium Carbonate (K2CO3), Catalyst
(chromium-promoted iron oxide catalyst), and steam.
• Items of Equipment: A saturator, 2 desaturators, catalyst vessel (2
catalyst beds), trays of iron oxide absorbent, 2 heat exchangers.
Discussion contd.
 Activity Definition/Sequencing
Mechanical Design of the Absorber
 Process Operation Conditions Specification.
Mechanical Design of the Absorber contd.
 Size Specification for the Shell and Catalytic Converter
Components.
Mechanical Design of the Absorber contd.
 Catalyst bed supports
1. It consists of two half circle frames made of alloy steel held together at the
centre by means of bolts to which wire gauze is fitted. The gauze pores will be
big enough to allow the passage of the gas but small enough to prevent the
catalyst particles from passing through it.
 Gas distribution
1. It consists of a conical shaped receiver connected to an elbow pipe which acts as a
means of re-directing the gas. The high pressure at which the gas is to be pumped
will make this erstwhile simple design effective.
Mechanical Design of the Absorber contd.
 Facilities for discharging and charging the catalyst
• The manholes provided by the design are to be used for charging the catalyst
while the catalyst discharge nozzle will facilitate in the catalyst discharge. The
nozzle is designed to taper for ease of collection of the catalyst particles. To push
the particles out of the vessels, compressed air is recommended.
• Choice of construction materials
o Due to the design of the vessel- the number of openings, branches and
the temperature regime expected the best choice for construction will be
alloy steels.
• Facilities for instrumentation
o They have been located to the site at which measurements (gas temperature and
pressure) are to be taken.
Control (Instrumentation) System Design
 Control of liquid level in the hot water circuit: Introduction of
additional tank which will act as a means to remove the
inevitable build-up of water in the circuit.
 The control the temperature levels in the converter, the flow of
the gas stream into the unit is manipulated.
 In the case of the failure of the control system, two solenoid
valves are provided to shut down the entire section by shutting
down the flow of material into the converter and into the whole
section itself.
 Also provided are high and low level alarms for both the
temperature control and the liquid level control.
HSE Considerations
 Wear leather safety gloves and safety shoes when handling
cylinders.
 Protect cylinders from physical damage; do not drag, roll, slide
or drop.
 While moving cylinder, always keep in place removable valve
cover. Never attempt to lift a cylinder by its cap; the cap is
intended solely to protect the valve.
 Keep away from heat, hot surfaces, sparks, open flames and
other ignition sources. There should be no smoking near the
plant. The use of only non-sparking tools is recommended.
CONCLUSION
I. The hydrogen to be produced according to the design work
carried out will be of approximately 96.6% purity which
exceeds the production benchmark of 95% purity for
hydrogen product stream.
II. In order to achieve the production target of 20 million
standard cubic feet of Hydrogen per year at 96.6% purity,
production capacity of 4.041x108m3/hr at the rate of
4.041x108m3/hr. of hydrogen, and oxygen (at 95% purity) are
required.
III. The amount of CO2 converted is 238,414,162 m3 and the
energy requirement of the plant is estimated to 4.537x 1011 kJ
Catalyst bed supports
Gas Distributor
CO Catalytic Convereter

More Related Content

What's hot

Steam Reforming - A Comprehensive Review
Steam Reforming - A Comprehensive ReviewSteam Reforming - A Comprehensive Review
Steam Reforming - A Comprehensive ReviewGerard B. Hawkins
 
Catalyst Breakage in Reformer Tubes
Catalyst Breakage in Reformer TubesCatalyst Breakage in Reformer Tubes
Catalyst Breakage in Reformer TubesGerard B. Hawkins
 
Steam Reforming - (ATM) Approach to Equilibrium
Steam Reforming - (ATM) Approach to EquilibriumSteam Reforming - (ATM) Approach to Equilibrium
Steam Reforming - (ATM) Approach to EquilibriumGerard B. Hawkins
 
Reduction & Startup of Pre-reforming Catalysts
Reduction & Startup of Pre-reforming CatalystsReduction & Startup of Pre-reforming Catalysts
Reduction & Startup of Pre-reforming CatalystsGerard B. Hawkins
 
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Gerard B. Hawkins
 
The role of CCS/CCUS in the Climate Action Plan - Dr S. Julio Friedmann
The role of CCS/CCUS in the Climate Action Plan - Dr S. Julio FriedmannThe role of CCS/CCUS in the Climate Action Plan - Dr S. Julio Friedmann
The role of CCS/CCUS in the Climate Action Plan - Dr S. Julio FriedmannGlobal CCS Institute
 
PLANT DESIGN FOR MANUFACTURING OF HYDROGEN BY STEAM METHANE REFORMING (SMR)
PLANT DESIGN FOR MANUFACTURING OF HYDROGEN BY STEAM METHANE REFORMING (SMR)PLANT DESIGN FOR MANUFACTURING OF HYDROGEN BY STEAM METHANE REFORMING (SMR)
PLANT DESIGN FOR MANUFACTURING OF HYDROGEN BY STEAM METHANE REFORMING (SMR)Priyam Jyoti Borah
 
Steam reforming - The Basics of Reforming
Steam reforming  - The Basics of ReformingSteam reforming  - The Basics of Reforming
Steam reforming - The Basics of ReformingGerard B. Hawkins
 
Calculation of an Ammonia Plant Energy Consumption:
Calculation of an Ammonia Plant Energy Consumption:  Calculation of an Ammonia Plant Energy Consumption:
Calculation of an Ammonia Plant Energy Consumption: Gerard B. Hawkins
 
3. natural gas composition
3. natural gas composition3. natural gas composition
3. natural gas compositionElsayed Amer
 
A case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdf
A case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdfA case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdf
A case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdfPremBaboo4
 
Hydrogen Production through Steam Reforming process.pptx
Hydrogen Production through Steam Reforming process.pptxHydrogen Production through Steam Reforming process.pptx
Hydrogen Production through Steam Reforming process.pptxFAHADMUMTAZ10
 
Principles of Pre-reforming Technology
Principles of Pre-reforming TechnologyPrinciples of Pre-reforming Technology
Principles of Pre-reforming TechnologyGerard B. Hawkins
 
Theory and Practice of Steam Reforming
Theory and Practice of Steam ReformingTheory and Practice of Steam Reforming
Theory and Practice of Steam ReformingGerard B. Hawkins
 
Fuel conversion IBR Boiler HSD to LPG .
Fuel conversion IBR Boiler HSD to LPG .Fuel conversion IBR Boiler HSD to LPG .
Fuel conversion IBR Boiler HSD to LPG .SoorajThakur3
 
Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...
Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...
Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...Global CCS Institute
 
Carbon Capture and Storage breakfast seminar
Carbon Capture and Storage breakfast seminarCarbon Capture and Storage breakfast seminar
Carbon Capture and Storage breakfast seminarBlake Morgan
 

What's hot (20)

Blast furnace gas
Blast furnace gasBlast furnace gas
Blast furnace gas
 
Steam Reforming - A Comprehensive Review
Steam Reforming - A Comprehensive ReviewSteam Reforming - A Comprehensive Review
Steam Reforming - A Comprehensive Review
 
Catalyst Breakage in Reformer Tubes
Catalyst Breakage in Reformer TubesCatalyst Breakage in Reformer Tubes
Catalyst Breakage in Reformer Tubes
 
Steam Reforming - (ATM) Approach to Equilibrium
Steam Reforming - (ATM) Approach to EquilibriumSteam Reforming - (ATM) Approach to Equilibrium
Steam Reforming - (ATM) Approach to Equilibrium
 
Reduction & Startup of Pre-reforming Catalysts
Reduction & Startup of Pre-reforming CatalystsReduction & Startup of Pre-reforming Catalysts
Reduction & Startup of Pre-reforming Catalysts
 
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
 
The role of CCS/CCUS in the Climate Action Plan - Dr S. Julio Friedmann
The role of CCS/CCUS in the Climate Action Plan - Dr S. Julio FriedmannThe role of CCS/CCUS in the Climate Action Plan - Dr S. Julio Friedmann
The role of CCS/CCUS in the Climate Action Plan - Dr S. Julio Friedmann
 
PLANT DESIGN FOR MANUFACTURING OF HYDROGEN BY STEAM METHANE REFORMING (SMR)
PLANT DESIGN FOR MANUFACTURING OF HYDROGEN BY STEAM METHANE REFORMING (SMR)PLANT DESIGN FOR MANUFACTURING OF HYDROGEN BY STEAM METHANE REFORMING (SMR)
PLANT DESIGN FOR MANUFACTURING OF HYDROGEN BY STEAM METHANE REFORMING (SMR)
 
Steam reforming - The Basics of Reforming
Steam reforming  - The Basics of ReformingSteam reforming  - The Basics of Reforming
Steam reforming - The Basics of Reforming
 
Calculation of an Ammonia Plant Energy Consumption:
Calculation of an Ammonia Plant Energy Consumption:  Calculation of an Ammonia Plant Energy Consumption:
Calculation of an Ammonia Plant Energy Consumption:
 
3. natural gas composition
3. natural gas composition3. natural gas composition
3. natural gas composition
 
A case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdf
A case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdfA case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdf
A case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdf
 
Hydrogen Production through Steam Reforming process.pptx
Hydrogen Production through Steam Reforming process.pptxHydrogen Production through Steam Reforming process.pptx
Hydrogen Production through Steam Reforming process.pptx
 
Petroleum 8
Petroleum 8Petroleum 8
Petroleum 8
 
Principles of Pre-reforming Technology
Principles of Pre-reforming TechnologyPrinciples of Pre-reforming Technology
Principles of Pre-reforming Technology
 
Theory and Practice of Steam Reforming
Theory and Practice of Steam ReformingTheory and Practice of Steam Reforming
Theory and Practice of Steam Reforming
 
Fuel conversion IBR Boiler HSD to LPG .
Fuel conversion IBR Boiler HSD to LPG .Fuel conversion IBR Boiler HSD to LPG .
Fuel conversion IBR Boiler HSD to LPG .
 
Secondary Reforming Burners
Secondary Reforming BurnersSecondary Reforming Burners
Secondary Reforming Burners
 
Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...
Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...
Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...
 
Carbon Capture and Storage breakfast seminar
Carbon Capture and Storage breakfast seminarCarbon Capture and Storage breakfast seminar
Carbon Capture and Storage breakfast seminar
 

Similar to PRESENTATION ON HYDROGEN GAS PRODUCTION BY PARTIAL OXIDATION OF HEAVY FUEL OIL FEEDSTOCK

Department Of Chemical
Department Of ChemicalDepartment Of Chemical
Department Of ChemicalSamuel Essien
 
Technologies for Carbon Capture in Oil Refineries
Technologies for Carbon Capture in Oil RefineriesTechnologies for Carbon Capture in Oil Refineries
Technologies for Carbon Capture in Oil Refineriescanaleenergia
 
Chapter 5b -_cracking_ffcu
Chapter 5b -_cracking_ffcuChapter 5b -_cracking_ffcu
Chapter 5b -_cracking_ffcuHelena Francis
 
Hydrogen production in refinery
Hydrogen production in refineryHydrogen production in refinery
Hydrogen production in refineryAnupam Basu
 
Summer Internship on Indian Oil Corporation Limited
Summer Internship on Indian Oil Corporation LimitedSummer Internship on Indian Oil Corporation Limited
Summer Internship on Indian Oil Corporation LimitedAbhishek Anand Thakur
 
Hydrogen Production steam reforming
Hydrogen Production steam reformingHydrogen Production steam reforming
Hydrogen Production steam reformingTanay_Bobde
 
Activation Of Carbon Produced From Coconut Shell By Using Fluidized Bed ...
Activation Of Carbon Produced From Coconut      Shell By Using Fluidized Bed ...Activation Of Carbon Produced From Coconut      Shell By Using Fluidized Bed ...
Activation Of Carbon Produced From Coconut Shell By Using Fluidized Bed ...Ratan Kumar
 
dimpfolderssecondsemforrefiningmodulesslides11hydrogenproduction-091009115333...
dimpfolderssecondsemforrefiningmodulesslides11hydrogenproduction-091009115333...dimpfolderssecondsemforrefiningmodulesslides11hydrogenproduction-091009115333...
dimpfolderssecondsemforrefiningmodulesslides11hydrogenproduction-091009115333...AJAYKUMAR801605
 
PRESENTATION ON INPLANT TRAINING AT MRPL
PRESENTATION ON INPLANT TRAINING AT MRPLPRESENTATION ON INPLANT TRAINING AT MRPL
PRESENTATION ON INPLANT TRAINING AT MRPLAnkit Devatwal
 
AMMONIA PLANT MATERIAL BALANCE.pdf
AMMONIA PLANT MATERIAL BALANCE.pdfAMMONIA PLANT MATERIAL BALANCE.pdf
AMMONIA PLANT MATERIAL BALANCE.pdfPremBaboo4
 
01 fuel and industrial gases
01 fuel and industrial gases01 fuel and industrial gases
01 fuel and industrial gasesNaveen Choudhary
 
5 heat exchanger thermal design of oil system for turbo centrifugal compresso...
5 heat exchanger thermal design of oil system for turbo centrifugal compresso...5 heat exchanger thermal design of oil system for turbo centrifugal compresso...
5 heat exchanger thermal design of oil system for turbo centrifugal compresso...IJCMESJOURNAL
 
technical-packages.pdf |Goel scientific | Canada
technical-packages.pdf |Goel scientific | Canadatechnical-packages.pdf |Goel scientific | Canada
technical-packages.pdf |Goel scientific | CanadaGoelScientific1
 
CO2 EOR Pilot Project
CO2 EOR Pilot ProjectCO2 EOR Pilot Project
CO2 EOR Pilot ProjectAhmed Nour
 

Similar to PRESENTATION ON HYDROGEN GAS PRODUCTION BY PARTIAL OXIDATION OF HEAVY FUEL OIL FEEDSTOCK (20)

Department Of Chemical
Department Of ChemicalDepartment Of Chemical
Department Of Chemical
 
Technologies for Carbon Capture in Oil Refineries
Technologies for Carbon Capture in Oil RefineriesTechnologies for Carbon Capture in Oil Refineries
Technologies for Carbon Capture in Oil Refineries
 
Presentation On Boiler Analysis
Presentation On Boiler AnalysisPresentation On Boiler Analysis
Presentation On Boiler Analysis
 
Air sepration
Air seprationAir sepration
Air sepration
 
Chapter 5b -_cracking_ffcu
Chapter 5b -_cracking_ffcuChapter 5b -_cracking_ffcu
Chapter 5b -_cracking_ffcu
 
Hydrogen production in refinery
Hydrogen production in refineryHydrogen production in refinery
Hydrogen production in refinery
 
Fyppt
FypptFyppt
Fyppt
 
Summer Internship on Indian Oil Corporation Limited
Summer Internship on Indian Oil Corporation LimitedSummer Internship on Indian Oil Corporation Limited
Summer Internship on Indian Oil Corporation Limited
 
Hydrogen Production steam reforming
Hydrogen Production steam reformingHydrogen Production steam reforming
Hydrogen Production steam reforming
 
Activation Of Carbon Produced From Coconut Shell By Using Fluidized Bed ...
Activation Of Carbon Produced From Coconut      Shell By Using Fluidized Bed ...Activation Of Carbon Produced From Coconut      Shell By Using Fluidized Bed ...
Activation Of Carbon Produced From Coconut Shell By Using Fluidized Bed ...
 
Article - 2012 PTQ Q1
Article - 2012 PTQ Q1Article - 2012 PTQ Q1
Article - 2012 PTQ Q1
 
H2P_Energy_Final_Presentation_ENCH_531
H2P_Energy_Final_Presentation_ENCH_531H2P_Energy_Final_Presentation_ENCH_531
H2P_Energy_Final_Presentation_ENCH_531
 
A Modular C2 Splitter - Hydrocarbon Engineering April 2017
A Modular C2 Splitter - Hydrocarbon Engineering April 2017A Modular C2 Splitter - Hydrocarbon Engineering April 2017
A Modular C2 Splitter - Hydrocarbon Engineering April 2017
 
dimpfolderssecondsemforrefiningmodulesslides11hydrogenproduction-091009115333...
dimpfolderssecondsemforrefiningmodulesslides11hydrogenproduction-091009115333...dimpfolderssecondsemforrefiningmodulesslides11hydrogenproduction-091009115333...
dimpfolderssecondsemforrefiningmodulesslides11hydrogenproduction-091009115333...
 
PRESENTATION ON INPLANT TRAINING AT MRPL
PRESENTATION ON INPLANT TRAINING AT MRPLPRESENTATION ON INPLANT TRAINING AT MRPL
PRESENTATION ON INPLANT TRAINING AT MRPL
 
AMMONIA PLANT MATERIAL BALANCE.pdf
AMMONIA PLANT MATERIAL BALANCE.pdfAMMONIA PLANT MATERIAL BALANCE.pdf
AMMONIA PLANT MATERIAL BALANCE.pdf
 
01 fuel and industrial gases
01 fuel and industrial gases01 fuel and industrial gases
01 fuel and industrial gases
 
5 heat exchanger thermal design of oil system for turbo centrifugal compresso...
5 heat exchanger thermal design of oil system for turbo centrifugal compresso...5 heat exchanger thermal design of oil system for turbo centrifugal compresso...
5 heat exchanger thermal design of oil system for turbo centrifugal compresso...
 
technical-packages.pdf |Goel scientific | Canada
technical-packages.pdf |Goel scientific | Canadatechnical-packages.pdf |Goel scientific | Canada
technical-packages.pdf |Goel scientific | Canada
 
CO2 EOR Pilot Project
CO2 EOR Pilot ProjectCO2 EOR Pilot Project
CO2 EOR Pilot Project
 

Recently uploaded

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

PRESENTATION ON HYDROGEN GAS PRODUCTION BY PARTIAL OXIDATION OF HEAVY FUEL OIL FEEDSTOCK

  • 1. PRODUCTION OF20 MILLION STANDARD CUBIC FEET PER DAY (0.515 X 106 STANDARD M3/DAY) OF HYDROGEN OF AT LEAST 95 PER CENT PURITY HYDROGEN FROM HEAVY FUEL OIL FEEDSTOCKS B Y OLANREWAJU, ADEBAYO BAMIDELE ADEBAYOOLANREWAJU206@GMAIL.COM +234 (0) 7037710839
  • 2. Introduction General overview of H2  Hydrogen is a  colourless,  odourless,  tasteless,  flammable gaseous substance that is the simplest member of the family of chemical elements.  Present in all animal and vegetable tissue and in petroleum.  Manufacture of ammonia and others
  • 3. Introduction contd. H2 Demand  World consumption of both captive and merchant hydrogen will increase 3.5% annually through 2018 to more than 300billion cubic meters.
  • 5. Introduction contd. Methods of preparation  Partial Oxidation (POX)  It involves an intimate coupling of several complex chemical reaction of hydrocarbon feed with oxygen at high temperatures to produce a mixture of hydrogen and carbon monoxide.  The partial oxidation reaction mechanism involves exothermic, partial combustion of a portion of a hydrocarbon feed which supplies heat to the endothermic steam cracking of the balance of the feed.  Besides carbon monoxide, hydrogen, carbon dioxide, hydrogen sulfide, and other trace impurities, partial oxidation produces soot in non-equilibrium amounts.  Since the high temperature takes the place of a catalyst, POX is not limited to the light, clean feedstocks required for steam reforming.
  • 6. Method of Preparation contd.  Others include:  Advanced Cracking Reaction (ACR)  Catalytic Partial Oxidation  Thermochemical (High-temperature) Water Splitting.
  • 7. Feedstock for H2 Production  Natural Gas  Refinery Gas  Liquid Feeds (LPG & Naphtha)  Heavy Fuel Oil
  • 8. DISCUSSION  Process Design 1. Preparation of a mass balance diagram for the entire plant, 2. Preparation of an energy balance diagram of the flame reactor and the associated waste heat boiler, 3. Preparation of a Process flow diagram of the entire plant.
  • 10. Discussion contd.  Material Balance Basis  In order to perform the material balance calculations, an assumed basis of 1000 kg of Heavy Fuel Oil feed was selected.
  • 11. Discussion contd.  From the above, and as calculated on appendix 1, the production rate was found to be 4.041x108m3/hr.  Hence, the rate of flow of CO, CO2, N2 into the conversion system were found to be 4040918m3/hr, 4040918m3/hr and 8081836m3/hr. respectively.  While CO, CO2 coming out of the quencher were calculated to 242,455,080 m3 and 47,913,742 m3 respectively.  Also, the amount of CO converted is 238,414,162 m3. Then, H2, CH4 out of the converter were found to be 271,318,780 m3 and 57,727m3 respectively.  Finally, the amount of H2 produced in the converter was found to be 1.329 x 108m3.
  • 12. Discussion contd.  Energy Balance  Energy Balance Diagram for the Flame Reactor and the Associated Waste Heat Boiler (WHB). 
  • 13. Energy Balance Contd.  The values of the material streams indicated were extracted from the mass balance diagram discussed earlier.  As indicated in the diagram the mass of steam produced by waste heat boiler was estimated to be 7930.95kg while energy of the crude gas leaving the waste heat boiler is 4.537 x 1011 kJ.  The energy required to produce steam by the waste heat boiler was estimated to be 22,325,624.25 kJ.
  • 14. Discussion contd.  Process Flow Diagram • The Preliminary Block Flow Diagram
  • 15. Discussion contd.  Equipment Schedule for the CO Conversion Section of the Plant 1. Introduction • In order to meet the production capacity as stated in the process description, the process is scheduled to run all day long (24hrs of the day). • The following are the various utilities and items of equipment involved in the CO conversion section of the plant: • Utilities: Heat supply, Potassium Carbonate (K2CO3), Catalyst (chromium-promoted iron oxide catalyst), and steam. • Items of Equipment: A saturator, 2 desaturators, catalyst vessel (2 catalyst beds), trays of iron oxide absorbent, 2 heat exchangers.
  • 16. Discussion contd.  Activity Definition/Sequencing
  • 17. Mechanical Design of the Absorber  Process Operation Conditions Specification.
  • 18. Mechanical Design of the Absorber contd.  Size Specification for the Shell and Catalytic Converter Components.
  • 19. Mechanical Design of the Absorber contd.  Catalyst bed supports 1. It consists of two half circle frames made of alloy steel held together at the centre by means of bolts to which wire gauze is fitted. The gauze pores will be big enough to allow the passage of the gas but small enough to prevent the catalyst particles from passing through it.  Gas distribution 1. It consists of a conical shaped receiver connected to an elbow pipe which acts as a means of re-directing the gas. The high pressure at which the gas is to be pumped will make this erstwhile simple design effective.
  • 20. Mechanical Design of the Absorber contd.  Facilities for discharging and charging the catalyst • The manholes provided by the design are to be used for charging the catalyst while the catalyst discharge nozzle will facilitate in the catalyst discharge. The nozzle is designed to taper for ease of collection of the catalyst particles. To push the particles out of the vessels, compressed air is recommended. • Choice of construction materials o Due to the design of the vessel- the number of openings, branches and the temperature regime expected the best choice for construction will be alloy steels. • Facilities for instrumentation o They have been located to the site at which measurements (gas temperature and pressure) are to be taken.
  • 21. Control (Instrumentation) System Design  Control of liquid level in the hot water circuit: Introduction of additional tank which will act as a means to remove the inevitable build-up of water in the circuit.  The control the temperature levels in the converter, the flow of the gas stream into the unit is manipulated.  In the case of the failure of the control system, two solenoid valves are provided to shut down the entire section by shutting down the flow of material into the converter and into the whole section itself.  Also provided are high and low level alarms for both the temperature control and the liquid level control.
  • 22. HSE Considerations  Wear leather safety gloves and safety shoes when handling cylinders.  Protect cylinders from physical damage; do not drag, roll, slide or drop.  While moving cylinder, always keep in place removable valve cover. Never attempt to lift a cylinder by its cap; the cap is intended solely to protect the valve.  Keep away from heat, hot surfaces, sparks, open flames and other ignition sources. There should be no smoking near the plant. The use of only non-sparking tools is recommended.
  • 23. CONCLUSION I. The hydrogen to be produced according to the design work carried out will be of approximately 96.6% purity which exceeds the production benchmark of 95% purity for hydrogen product stream. II. In order to achieve the production target of 20 million standard cubic feet of Hydrogen per year at 96.6% purity, production capacity of 4.041x108m3/hr at the rate of 4.041x108m3/hr. of hydrogen, and oxygen (at 95% purity) are required. III. The amount of CO2 converted is 238,414,162 m3 and the energy requirement of the plant is estimated to 4.537x 1011 kJ