Lean Manufacturing (PP-REM/PP-KAB)
1. Which of the following master data do you need to make available for repetitive
manufacturing?
Note: There are 3 correct answers to this question.
_ Master records for serial numbers
_ Product cost collector
_ Production supply área
_ Repetitive manufacturing profile
_ Production versión
2. Which of the following efforts can be minimized using the KANBAN procedure?
• Organizational effort to stage material
• Effort for Sales and Operations Planning (sop)
• Effort for master data maintenance
• Organizational effort for capacity planning
3. Which of the following aspects characterize repetitive manufacturing in a manufacturing
plant?
Note: There are 3 correct answers to this question.
_ Continuous material consuption, production flow and output
_ Period-based planning of the quantities to be produced
_ Production without using production orders and without status management
_ Automatic line loading by capacity limits across all production lines
_ Shop fabrication
4. What repetitive manufacturing options can you use to carry out line loading in the SAP
ECC system and thus generate Run Schedule Quantities (RSQ) from normal planned
orders?
Note: There are 3 correct answers to this question
_ Using a planning algorithm from capacity planning
_ Automatic selection of the production versión by applying quota arrangement records in
material requirements planning (MRP)
_ Selecting a suitable repetitive manufacturing profile that contains an option for automatic line
selection.
_ Automatic selection of the production version in material requirements planning (MRP) using
Selection Methods setting.
_ Manual assignment of planned production quantities in a planning table
5. Which of the following activities within the KANBAN procedure normally triggers
subsequent stock posting of the goods receipt?
• Set ‘Container in process’
• Set ‘Container empty’
• Set ‘Contaniner in transport’
• Set ‘Container full’
6. Which of the following master data do you always have to make available for material
replenishment using the KANBAN procedure?
Note: There are 2 correct answers to this question
_ Product cost collector
_ Control cycles
_ Rate Routings
_ Production supply areas
_ Production versions
Production Orders Basics (PP-SFC)
7. In which of the following objects can you activate backflushing of components if you want
to use this functionality during order confirmation?
Note: There are 3 correct answers to this question.
_ Material Master (Finished Product)
_ Material Master (Component)
_ Work Center
_ Production Scheduling Profile
_ Routing
8. Which production order function can no longer be carried out after the order is released?
• Switching sequences
• Posting a godos receipt from production to stock
• Read PP master data
• Posting a godos issue from stock to the production order
9. What are the consequences of a confirmation of an operation?
Note: There are 2 correct answers to this question.
_ Actual costs are posted for the production confirmed
_ Serial numbers are assigned for the confirmed quantity
_ The produced and confirmed quantity is automatically posted to the warehouse stock as a
receipt
_ The operation’s capacity requirements are reduced
10. In production order processing, for which of the following objects can you enter a
confirmation?
Note: There are 3 correct answers to this question
_ Individual Capacity
_ Work Center
_ Trigger Point
_ Operation / Suboperation
_ Order
11. Which one of the following scheduling types cannot be assigned as default to an order
type (production order)?
• Only capacity requirements
• Midpoint
• Backward
• Forward
12. Which of the following requirements for a manufacturing plant can be supported by using
production orders?
Note: There are 3 correct answers to this question
_ Make-to-stock production
_ Orderless production
_ Customer requeriments-dependent production
_ Integrated display of documents (drawings, texts) in the production process
_ Variable calculation of material quantities (production output, material usage) and operation
quantities
13. Which of the following situation occur when a production order is set to technically
Complete (TECO)?
Note: There are 3 correct answers to this question
_ Capacity requirements are delated
_ The order is no longer relevant for M aterial Requirements Planning
_The order and its operations receive the system status locked (LKD)
_ Purchase orders for external operations or non-stock materials are deleted
_ Reservations are deleted
14. Which of the following master data is mandatory for production order processing, when
material reservations and capacity requirements for operations should be genered
automatically?
Note: There are 2 correct answers to this question
_ Document structure
_ Inspections Characteristics
_ Routing
_ Production Versions
_ Material Master Records (product and material component)
15. Which of the following functions ocurr when a production order is created?
Note: There are 3 correct answers to this question
_ Selecting and copying a bill of material
_ Copying a document that is assigned to the material master for the product to be produced
_ Calculating the lead time for the production order
_ Calculating the quantity to be produced on the basis of the available material stock
_ Selecting and copying a routing
Material and Capacity Req. Planning
16. In your interprise, a planning strategy is used in SAP ECC that enables joint planning of all
MRP scheduled assemblies for a finished product to trigger procurement of these
assemblies. It is important to ensure that the finished product is only produced when
there is a customer order is received, of the finished product should be triggered in the
form of make-to-order planning and production
Wich planning strategy covers this scenario?
• Planning at the assembly level (strategy 70)
• Planning with make-to-stock (strategy 10)
• Planning without final assmbly (strategy 50)
• Planning with final assambly (strategy 40)
17. In what order are the individual steps of material requirements planning performed in SAP
ECC?
• 1. Calculation of safety stock 2. Application of the lot-sizing procedure 3. Scheduling 4.
Determination of the procurement type
• 1. Availability check 2. Application of the lot-sizing procedure 3. Determination of the
procurement type 4. Scheduling
• 1. Net requirements calculation 2. Application of the lot-sizing procedure 3. Scheduling 4.
Determination of the procurement type
• 1. Net requeriments calculation 2. Application of the lot-sizing procedure 3. Determination of
the procurement type 4. Scheduling
18. Which data forms the basis for calculating the capacity requirement for an operation?
Note: There are 3 correct answers to this question.
_ Formulas (work center)
_ In-house production time (material master)
_ Transport time (routing)
_ Standard values (routing)
_ Operation control key (routing)
19. Which of the following statements is true for the ATP (available to promise) availability
check in SAP ECC that is triggered from a customer order?
• The ATP check does not confirm against stocks and receipts, it checks consumption against
planning requirements
• An availability check by means of ATP creates fixed links between customer orders and their
confirmed receipts
• The ATP quantity is the quantity still available that can be used to confirm incoming customer
orders
• If the ATP check establishes non-availability, it checks whether it is still possible to procure or
produce in time
20. Which statement regarding lot size procedures is correct?
• If a make-to-order production strategy is in use, a lot for (exact) lot size is always determined
for the corresponding procurement element
• The procurement quantity of a lot size procedure can be specified using a safety time period
profile
• If a long-term lot size is in use, procurement is conducted with a long-term perspective
• The lot size quantity can be influenced using a mínimum quantity and the rounding profile
21. Which of the following statement is true for the simulation mode in the context of
material requirements planning in SAP ECC?
• The simulation mode is used in scenarios in which requirements planning created the
procurement element prematurely in terms of demand
• The simulation mode opens the analysis of the delay time. Manual rescheduling of the receipt
in the finished product and subsequent requirements planning lead to a solution that is
feasible from the requirements planning perspective. However, this solution may lead to a
date/time violation in the finished product
• The simulation mode represents an interactive multilevel form of planning, the result of which
is automatically posted to the database after the planning run
• Assuming a delay time in the ‘critical path’, the simulation mode triggers multilevel bottom-up
scheduling through to the finished product, which therefore receives a delayed receipt
22. Which properties does ECC Master Production Scheduling (MPS) have?
Note: There are 3 correct answers to this question
_ MPS ítems can be define on plant level
_ MPS ítems can be taken into consideration by a standard MRP run (Material Requirements
Planning)
_ The planning of MPS and Non-MPS ítems is always carried out in one planning run
_ MPS ítems can be define don MRP Area level (Material Requirements Planning Area)
_ Non-MPS ítems can be taken into consideration by an MPS run
23. Which of the following features are offered by MRP Areas (Material Requirements
Planning Areas)?
Note: There are 2 correct answers to this question.
_ Make-to-order production is supported by storage location MRP Areas
_ Subcontracting is supported by MRP Areas
_ A storage location may be assigned to different MPR Areas
_ An MRP Area may include different storage locations
24. Which functions lead to a reduction in the capacity requirement for an individual
operation at a work center?
Note: There are 3 correct answers to this question
_ Confirming the operation
_ Setting the status technically complete (TECO)
_ Rescheduling the operation
_ Reducing the order quantity
_ Posting the goods receipt for the production order
25. In your company Planning strategies are used in the SAP ECC demand management that
are based on consumption. Which of the following statements about consumption in true?
Note: There are 2 correct answers to this question
_ Consumption can also take place between order reservations and planned independent
requirements, depending on the strategy.
_ A consumption situation in dynamic and is always restructured with the planning run.
_ Consumption always takes place on the material level between the planned independent
requirements and the planned orders.
_ The consumption parameters (consumption mode and consumption interval) can be set in the
material master or in the MRP group.
26. Which statements are true for ECC Long-term Planning (LTP)?
Note: There are 2 correct answers to this question
_Reorder point planned materials can be included in long-term planning
_ Long-term planning generally is operational planning of important components
_ In case of external procurement, long-term planning creates purchase requisitions.
_ A planning scenario must be released to use it in long-term planning
27. Which of the following are properties of ECC Multi-site planning?
Note: There are 2 correct answers to this question
- When using two-step stock transport order with delivery, the receiving plant is defined as
a customer
- The use of “scope of planning” (cross-plant total planning) is mandatory for Multi-Site
planning.
- Both withdrawal from alternative plant and withdrawal from another plant are defined via
special procurement Keys.
- When using one-step stock transfer posting, transfer stock is created in the receiving
plant.
Production Orders Advanced (PP-SFC)
28. The company that you advise does not want to manage certain value intensive materials in
the warehouse stock instead, the user wishes to control material provision in such a way
that these materials are procured directly for the production and/or process order
How can you fullfill this request?
Note: There are 2 correct answers to this question.
_ Using the procurement type ‘external procurement’ in the material master for the component
_ Using the special procurement key ‘subcontracting’ in the material master for the component
_ Using the special procurement key ‘direct procurement/external procurement’ in the material
master for the component
_ Using the ítem type ‘non stock’ ítem in the bill of material for the material in question
_ Controlling the material in question as a co-product
29. The company you advise wants to control the availability check in so that when a
production and/or process order is created, the following receipts of issues are taken into
account planned orders, purchase orders, production orders, reservations, dependent
requirements. When the production and/or process order is released, only the stock that
is currently freely usable should be taken into consideration.
How can you fulfill this request?
• Enter an appropriate availability checking rule in the order type.
• Differentiated assignment of two different checking rules in check control.
• Activete the freely usable stock in the scope of check
• Enter an appropriate availability checking group in the material master
30. A user you advise wishes to transfer variable process instructions for automated
processing directly to certain work centers and machines in the production department
(for example, ‘feed speed’, ‘pressing pressure’, ‘dry temperature’). The user also wishes to
receive variable as-is messages (such as ‘actual quantities’, ‘actual times’) from these work
centers and machines and to process these messages for feedback concerning production
orders.
Which of the following options would you recommend to implement these requirements?
• SAP Application Link Enabling (ALE)
• Execution Steps (XSteps) and process messages
• ‘Plant data collection’ (PP-PDC) interface
• SAP Business Intelligence (BI)
31. Which options can you offer a user of the SAP ECC system for managing costs (costing and
settlement) with regards to production orders?
Note: There are 2 correct answers to this question
_ Series-based costing
_ Product cost collecting
_ Order-based costing
_ Work center-based costing
32. Which options can you offer someone who uses the SAP ECC system for production orders
and requires support for material supply in production?
Note: There are 3 correct answers to this question
_ Logistics Information System (LIS)
_ Automatic generation of a transport order
_ Material directory
_ Pick list
_ Pull list
33. Which of the following elements do you have to prepare for costing of a production order
to function without errors?
Note: There are 3 correct answers to this question
_ Propose a standard text key in work center
_ Assign a production scheduling profile to the material master (product)
_ Enter formulas for costing in the work center
_ Assign costing variants to order type
_ Use an operation control key with the indicator “costing-relevant”
34. Which of the following possible errors would lead to the message shown?
Note: There are 2 correct answers to this question
_ The material master (product) is set to manual routing selection and valid routing exists.
_ In the material master, plan selection was set to production version. A production version was
created and it is faulty
_ The customizing for the order type is set to manual routing selection and a valid routing exists.
_ There are no valid routings or no routings available on the explosion date.
35. From what point can you no longer use the “Read PP master data” in the production
order?
_ From the release of the production order
_ After printing the order papers
_ After assigning the confirmed quantity of a material component due to carrying out a material
availability check
_ After the first posting of goods movements or confirmation
36. What options for selecting a routing exist when creating a production order?
Note: There are 3 correct answers to this question
_Manual selection
_ Selection on the basis of the routing number in the material master for the material to be
produced
_ Selection on the basis of the production control profile
_ Automatic selection, controlled via settings in Customizing
37. The user you advise request that you make it possible for the user to produce material for
stock, for customer orders, projects, orders ans cost center with productions orders.
Where can you make settings to ensure these options?
_ Valuation plant
_ Settlement profile
_ Serial number profile
_ Production scheduling profile
38. The company you advise wants to carry out the material availability check automatically in
the production order at various points in time. Which of the following options would you
recommend?
Note: There are 2 correct answers to this question
_ Confirmation of the operation that the materials being checked are assigned to
_Creation of the production order
_ Goods receipt for the product produced with the order
_ Goods receipt for a missing part
_ Release of the production order
39. Which of the following prerequisites have to be fulfilled for production orders to be
transferred to a business data entry system via the Plant data Collection (PP-PDC)
interface?
Note: There are 3 correct answers to this question
_ Production orders have been released
_ The application of the PP-PDC interface was activated in the order type for the production order.
_ The material to be produced with a production order was flagged for transfer in its material
master.
_ Execution steps were used to record process instructions in the operation.
_ Production Orders contain at least on operation that contains a work center with a “subsystem
group” assigned to it
40. Which objects can you use in the production order for a material component to propose
the storage location in its reservation?
Note: There are 3 correct answers to this question
_ Material Master (product)
_ Routing
_ Material Master (component)
_ Production Version
_ Work Center
41. For a specific end product, you want to use a planning time fence and fixing type 1 to
ensure that the planning situation in SAP ECC calms down in a short-term time window.
Two customer order arrive at short notice and their receipts should really be within the
planning time fence, due their date/time. Which statement is true with this scenario?
_ newly created planned orders cannot be created by requirements planning before the end of the
planning time fence, at the earliest
_ Requirement planning only examines changes that are relevant to scheduling whitin the planning
time fence ; the customer orders are covered in time.
_ The MRP controller has no possibility of creating planned orders within the planning time fence
_ Within the planning time fence, the newly created planned orders are automatically frozen by
requirement planning (roll forward)
Master Data (LDM)
42. In SAP ECC, you want to map an in-house production process for general warehouse. The
fields in the area of the lot size-dependent in-house production time are to be populated
when the material master for the final product is created. These fields can be maintained
by updating from the scheduling result for the associated routing. You now think that
there could be significant changes to the production times in the routing and decide
against updating the material master.
What problema could this lead to?
• Requirements planning runs up against an exception message in basic dates scheduling
because the material master parameters do not match the scheduling result from the routing.
• Subsequent capacity planning is no longer possible due to the obsolete scheduling
parameters.
• Lead time scheduling, wich occurs by the time that a planned order is converted into a
production order (at the latest), cannot take place on the basis of incorrect basic dates.
• In the course of basic dates scheduling with requirements planning, dependent requirements
request the components from the bill of materials at the wrong times.
43. A final assembly process takes place at three centers, one after the other. The routing,
which consist of three associated operations (10, 20 and 30), plans for a specific BOM
component to be installed during operation 30 and not before. The component should
therefore only be requested at the start of operation 30
What sequence do you follow in master data maintenance in SAP ECC to make this component
available in line with operations during final assembly?
• 1. Create BOM 2. Create work centers 3. Create routing 4. Carry out component assignment in
BOM or routing
• 1. Create BOM 2. Create work centers 3. Create routing 4. Carry out component assignment in
work center
• 1. Create work centers 2. Create routing 3. Create BOM 4. Carry out component assignment in
work center
• 1. Create routing 2. Create work center 3. Create BOM 4. Carry out component assignment in
BOM or routing
44. When maintaining a work center, formulas can be assigned in the scheduling view.
Formulas use formula parameters for calculation.
What can be the origin of the formula parameters used for scheduling?
Note: There are 3 correct answers to this question
_ General operation values in task list
_ User-defined field from operation in task list
_ Standard value from operation in task list
_ General values from work scheduling view in the material master
_ General ítem values in bill of materials
45. The master data for a logistical process is to be stored in the SAP ECC system. In this
context, you require the production versions for subsequent planning and production. You
know a mass maintenance transaction that you could use here
Where else in the SAP ECC system could you define production versions?
• In the work center
• In the material master
• In the repetitive manufacturing profile in Customizing
• In the line routing
46. In SAP ECC, you calculate the standard available capacity for a work center capacity with
the following data: start 7:00:00a.m., end 3:00:00 p.m., break duration: 1 hour, rate of
utilization: 80%, overload 110%, number of individual capacities: 1
How large is the standard available capacity?
• 7 hours
• 5.6 hours
• 6.16 hours
• 8 hours
47. Which of the following activities is necessary for the capacity availability check to be
carried out automatically when a production order is released?
• Activate the availability check and assign the check control to the plant
• Activate the availability check and assign an overall profile in check control for the business
function order release
• Activate the availability check and assign an availability checking group to the material master
for the product to be produced
• Activate the availability check and assign a checking rule to the work center for the operation
to be checked
48. Which information is contained in production versions for selecting routings and bills of
material?
• The routing and BOM alternatives to be used for production
• The plant for which the routing and BOM have to be created
• All the control parameters for selecting routings and bills of material
• The explosión date on which the validity of the routing and bill of material is checked
49. In the task list, there is the possibility to work with suboperations.
What can you do in more detail by using suboperations?
Note: There are 2 correct answers to this question
_ Material component allocation
_ Costing
_ Capacity planning
_ Scheduling
50. The master data for an in-house production process is to be set up in the SAP ECC
system.To do this, you should create a suitable routing that plans for five operation in an
initial sequence (10, 20,30,40,50).There should be an option of relocating operation 30
and 40 to a second sequence on other work centers if there are capacity bottlenecks.
What sequence type would you use to create the second sequence in the system?
_ Substitute sequence
_ Parallel sequence
_ Standard sequence
_ Alternative sequence
51. Which type of objects can be changed with Engineering Change Management?
Note: There are 3 correct answers to this question
_ Material Master
_ Task list
_ Production Version
_ Work Center
_ Bill of materials
52. In modeling in-house production using SAP ECC, bills of material (BOM) are to be recorded
in the system. On which business levels can you create a BOM?
Note: There are 2 correct answers to this question
_ At the business area level
_ AT the client level
_ At the company code level
_ At the plant level
53. A new material with the following properties is to be recorded in SAP ECC: the material in
kept in stock, is externally procured, and is used as a component in the bills of material for
various final products. However, this material may not be purchased directly.
Which standard SAP material type would you use?
_NLAG (non-stock material)
_ FERT (finished product)
_ ROH (raw material)
_ HAWA (trading good)
54. An enterprise based in the USA produces an end product that is used with unit of measure
“pound” (LB). The material is now to be marketed in the EU. A prerequisite for this is that
the material can be sold with the unit “kilogram” (KG). Which of the following solution
does SAP ECC offer?
_In the basic data customizing, you create a unit of measure group that converts pounds to
kilograms. You then assign this to the material master on basic data view 1.
_ In the material master, you create a conversion factor for converting pounds to kilograms on
basic data view 1.
_ This in no need to take any action. There is a general conversion in the central customizing of
units measurements, so thah automatic conversion of pounds to kilograms takes place.
_ You create a new material with a reference to the original material and assign the metric unit
measure to the new material master
55. Which of the following functions are available in the SAP ECC System for leveling overloads
in individual work centers with the capacity planning tools?
Note: There are 3 correct answers to this question
_ Batch size optimization
_ Lot Size optimization
_ Setup time reduction
_ Finite capacity scheduling
_ Midpoint scheduling
Basic on SAP Business Processes (E-Learnings)
56. The Service Desk is available as part of the SAP Solution Manager.
Which functions are included in the scope of the Service Desk?
Note: There are 2 correct answers to this question.
_ Managing SAP Notes
_ Troubleshooting
_ SAP Help
_ Process for processing messages
57. Which of the following statements about the SAP Solution Manager listed is correct?
_Solution manager is a satellite system in a system landscape
_ Solution Manager is an add-on industry solution
_ Solution Manager is a stand-alone system that communicates with other systems in a system
landscape.
_ Solution Manager is part of the SAP ECC System
58. What does SAP ERP mean?
• SAP ERP is an application that an Enterprise can use to manage its business processes
efficiently
• SAP ERP is a planning system in which extended planning processes can be mapped
• SAP ERP is a technological platform on the basis of which customer-specific extensions can be
imported
SAP ERP is a system hardware that includes modules for purchasing, sales and distribution,
materials management, production and so on.
59. Where are the standard operation times for an operation defined?
• Routing
• Maerial Master
• Production Resource/Tool (PRT)
• Work Center
Process Orders (PP-PI)
60. With which functions of the process order can you fulfill the requirements of the Good
Manufacturing Practices (GMP) standard?
Note: There are 3 correct answers to this question
_ Availibility check
_ Resource selection
_ Material identification and reconciliation
_ Batch record
_ Digital signature
61. Which of the following structural elements does a process order have?
Note: There are 3 correct answers to this question.
_ Relationships
_ Item data
_ Characteristic-based process instructions
_ Parallel sequences
_ Phases
62. Which of the following requirements for a manufacturing plant can be supported by using
process manufacturing?
Note: There are 3 correct answers to this question
_ Manufacturing in charge quantities
_ Material requirements planning for production resources
_ Manufacturing without orders
_ Master recipe-based manufacturing
_ Variable calculation of material quantities (product output, material usage)
63. Which of the following master data do you need to provide for process manufacturing?
Note: There are 3 correct answers to this question
_ Production Versions
_ Serial numbers
_ Master Recipe
_Resources
_ Product cost collector
Application Overview and Background
64. Which of the following statements about the planning functions available in SAP ECC are
true?
Note: There are 2 correct answers to this question
_ In demand management (DM) material shortage situations are identified and given requirement
coverage elements
_ Long-term planning (LPT) is a long-term form of forecast planning
_ Material requirements planning (MRP) does not include automatic capacity leveling
_ Master production scheduling (MPS) refers to preferred planning of important materials.
65. Which of the following statements about ATP (Available to promise) checks for material
components are correct?
Note: There are 2 correct answers to this question
_ The ATP checks are automatically performed during MRP (material requirement Planning) runs.
_ ATP checks are used to evaluate the free capacity on a certain work center
_ ATP checks can be carried out automatically when releasing a production order
_ ATP checks can be adjusted to also consider future requirements and receipts
_ ATP checks are mandatory for lead-time scheduling
66. A finished material is to be planned in a controlled manner in the SAP ECC system in the
context of requirements planning. The planned orders are scheduled using what is know
as basic date scheduling) not lead-time scheduling). Which of the following statements is
true for the resulting dependent requirements?
_ In multi-level backward scheduling, dependent requirements are triggered at the start date for
the higher-level assembly
_ If individual material components are explicity assigned to operation during the BOM and
routing maintenance, the requirement date of the dependent requirement for these components
are scheduled at each of the operation start dates.
_ In multi-level backward scheduling, dependent requirements are triggered at the start date for
the higher-level assembly planned order.
_ When customer order is created for the finished product, the dependent requirements are
automatically triggered for the components in the bill of material without a planning run.
67. A user has entered planning strategy group “10” (make to stock production) in the
material master (SAP ECC) of a product. For the coming months, requirements with
requirement type LSF (derived from the main strategy “10”) have been planned. The user
would like to change the requirement type from LSF to VSF planning with final assembly
(in accordance with planning strategy “40” ) for requirements in the production plan that
have alredy been saved. Which of the following statements are applicable in this case?
Note: There are 2 correct answers to this question
_ the present requirement for the product can be changed manually from “LSF” to “VSF” in the
requirement type field in te production plan, so that the new strategy 40 determines the next
planning operation.
_ The user can enter the new planning strategy group “40” in the material master of the product,
but the requirement type is not changed automatically for existing requirements.
_ The planning strategy group can be changed from “10” to “40” in the existing production plan,
and the requirement type for all requirements is changed automatically
_ The user has to change the requirement type for planning strategy “10” to VSF planning with
final assembly in Customizing. The requirement type for all existing requirements in then changed
automatically.
68. A supply chain planning run is to be carried out in the SAP ECC System as an example.
What would be the most effective sequence in which to run through the planning
modules?
_ 1.- Capacity Planning 2.- Sales and Operation planning 3.- Demand management 4.- Long term
planning 5.- Requeriment planning
_ 1.- Long-term planning 2.- Sales and Operation planning 3.- Demand management 4.-
Requirement planning 5.- Capacity planning
_ 1.- Demand management 2.- Sales and operation planning 3.- Capacity planning 4.- Long-term
planning 5.- Requirement planning
_ 1.- Sales and operation planning 2.- Demand management 3.- Long-term planning 4.-
Requirement planning 5.- Capacity planning
Material Requirements Planning (PP-MRP)
69. In SAP ECC, a customer tests the firming options for planned orders. The customer first
sets the manual firming date from the stock/requirements list to firm planned orders that
shall occur in the short term. In the material master, a rolling planning time horizon with
firming type 1 is active. Some planned orders have also been firmed manually already
Which statement applies for the resultant firming situation?
• The firming interval is specified by the firming mechanism that currently stretches further into
the future; all the planned orders within this horizon are firmed only if they were previously
firmed manually
• The firming interval is specified by the planning time fence from the material master, because
this always overrides the manual firming date, all the manually firmed planned orders are
firmed independently of this
• The firming interval is specified by the firming mechanism that currently stretches further into
the future and which firms planned orders that are within it; all the manually firmed planned
orders are firmed independently of this
• The firming interval is specified by the manual firming date because it always overrides the
planning time fence from the material master, all the manually firmed planned orders are
firmed independently of this
70. A customer has been using planning strategies 30 (production by lots) and 10 (anonymous
make-to-stock production) in SAP ECC. The customer wishes to move in part to planning
strategy 40 (planning with final assembly). The issue of ‘consumption’ has an effect here
for the first time
Which properties apply for consumption with planning strategy 40?
Note: There are 2 correct answers to this question
_ Consumption can reduce the originally planned production quantity
_ Consumption can result in the subsequent specification and adjustment of planning elements in
terms of quantity and date, by means of customer orders that arrive
_ Consumption creates a static and binding assignment, between the planned independent
requirements recorded in advance and the customer requirements that arrive, for the entire
procurement process
_ Consumption can lead to an increase of the originally planned overall production quantity
71. A customer wishes to only produce a finished product when customer orders for it are
present. Final assembly should then be carried out at short notice in make-to-order
production. Up until this point, the important assemblies needed in final assembly should
already be available in stock. Provision of these assemblies should therefore be triggered
by planning.
Which options could you offer the customer as useful alternatives in SAP ECC?
Note: There are 2 correct answers to this question
_ The finished product uses strategy 20 (make-to-order production) and all the important
assemblies in the bill of materials for the finished product should be have strategy 70 (planning at
the assembly level)
_ The finished product uses strategy 40 (planning with final assembly) and all the important
assemblies in the bill of material for the finished product should have strategy 70 (planning at the
assembly level)
_ The finished product uses strategy 30 (production by lots) and all the important assemblies in
the bill of material for the finished product should have strategy 70 (planning at the assembly
level)
_ The finished product uses strategy 50 (planning without final assembly) and all the assemblies in
the bill of material for the finished product have no strategy.
72. When analyzing the SAP ECC order report for a planned order for a finished product, you
discover that one of the assemblies will not be available in time for the scheduled final
assembly because of automatic forward scheduling
Which planning procedure would you use to process the problema in order to créate a solution
that is feasible from a requirements planning perspective?
• Total planning online
• Multi-level single-item planning with the ‘simulation mode’ option
• Multi-level single-item planning with the ‘display results before saving’ option
• Interactive single-item planning for the delayed assembly
73. In the Customizing for requirements planning, a Project team notices that the alternatives
P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number
in each of these alternatives represents a firming type.
What does a firming type define?
Note: There are 2 correct answers to this question
_ Handling existing procurement proposals within a planning time fence.
_ Handling existing procurement proposals outside the planning time fence.
_ Handling new procurement proposals that are to be created due to new requirements within the
planning time fence.
_ Handling new requirements within the planning time fence.
74. In the course of a customer project, you are confronted with an SAP ECC system that
shows the error message displayed below when you test requirements planning in plant
1000. Large numbers of materials are already available in plant 1000. As a first step in
solving the problem, you activate requirements planning in the Customizing for plant
1000.
What further steps must you take before you can put requirements planning in plant 1000 into
operation in SAP ECC?
• Create a planning file in Customizing - Specify the plant parameters for plant 1000 in
Customizing
• Implement the planning files in Customizing - Specify the plant parameters for plant 1000
in Customizing
• Implement theplanning files in Customizing - Specify the plant parameters for plant 1000
in the requirement planning views
• Activate requirements planning in Customizing for MRP areas in plant 1000 – Specify the
plant parameters for plant 1000 in the requirement planning views
75. An enterprise wants to use SAP ECC requirements planning together with the NETPL
procedure (net change planning in the planning horizon) The planning horizon is to be set
equally for all materials by default However, some materials are to be given a different
planning horizon. What procedure would you recommend to the project team for setting
the planning horizon in the system side?
_ The planning horizon is set in the MRP groups in Customizing and variant entries are assigned via
the plant parameter settings
_ The planning horizon is set in the plan parameters in Customizing and variant entries are stored
in the material master for the materials in question.
_ The planning horizon is set in customizing using the plant parameter setting and variant entries
are assigned via the MRP groups for the material in question.
_ The planning horizon is set in the MRP groups in customizing and the variant values are stored in
the material master for the materials in question.
76. A material was planned in the context of SAP ECC material requirements planning and the
MRP controller subsequently processed the material by manually converting a specific
planned order into a production order. The MRP controller now accesses the current stock
requeriments list and the MRP list for this material and components two. Which of the
following statements are true for the two lists at this stage?
Note: There are 2 correct answers to this question
_ The MRP list displays the production order
_ The stock requirements list displays the production order
_ The stock requirements list was updated at the precise time it was accessed
_ The MRP list has the status “processed”
77. A project team member analyzes the following situation in SAP ECC in the stock
/requirement list for a finished product: there is only one customer order and one fixed
planned order with a similar quantity amount. The customer order and the planned order
both have deadlines on work days but not on the same work day, the planned order has a
later deadline. The project team member cannot find a rescheduling message referring to
this deadline misalignment in the stock / requirement list.
What reason could there be for the missing message?
Note: There are 2 correct answers to this question
_ Requirement planning has not yet been carried out to update the rescheduling message.
_ The time misalignment falls within the tolerance window defined in Customizing
_ The elements are linked to each other via fixed pegging.
_ The requirement coverage element is outside the rescheduling horizon
78. In the SAP ECC system a material is produced with the help of production order. Though
originally used for rate-based planning only, the planning table is to be used to plan this
material. On the initial screen of the planning table you select this material and then
receive a message informing you that cannot use the planning table for this material.
Which of the following reasons for this message applies?
_The is no valid production version for this material.
_ the series production indicator has not been set
_ There are no requirements present
_ There are no planned orders or production orders present
79. An enterprise wants to absorb the uncertaintly caused by fluctuating demand for a
finished product by means of a buffer variable in SAP ECC. They suggest a dynamic safety
stock. What specifications are used tu calculate the dynamic safety stock?
_The static safety stock per day and the safety time
_The average daily demand and the desired days supply
_ the static safety stock and a material forecast
_ the average daily demand and the safety time.
80. In the course of a project phase, the customer raises some questions concerning
parameters of the procurement type in the material master in the SAP ECC system. Which
of the following procurement type properties apply?
Note: There are 2 correct answers to this question
_If procurement type E (in-house production) is set, external procurement may still be permissible
_ If both procurement types are allowed with entry X, requirements planning assumes in house
production.
_ Procurement types E (in-house production) and F (external procurement) have to be further
refined with special procurements types.
_ A material´s procurement type can always be freely selected between E (in-house production), F
(external procurement) and X (both procurement types)

More Related Content

What's hot

Gestión de Inventarios
Gestión de InventariosGestión de Inventarios
Gestión de Inventarios
Mariano Ortuño
 
Procure to Pay Process
Procure to Pay Process Procure to Pay Process
Procure to Pay Process
Sameer Mittal
 
SAP - Vendor Entries
SAP - Vendor EntriesSAP - Vendor Entries
SAP - Vendor Entries
Kumar M.
 
SAP S4 HANA MM 1709 Overview (mindmap edition) Final
SAP S4 HANA MM 1709 Overview (mindmap edition) FinalSAP S4 HANA MM 1709 Overview (mindmap edition) Final
SAP S4 HANA MM 1709 Overview (mindmap edition) Final
Benedict Yong (杨腾翔)
 
55811936 product-costing-cost-estimation-in-sap
55811936 product-costing-cost-estimation-in-sap55811936 product-costing-cost-estimation-in-sap
55811936 product-costing-cost-estimation-in-sap
Pepa Pencheva
 
SAP STO config
SAP STO configSAP STO config
SAP STO config
samitchak
 
Sales and Operation Planning in SAP
Sales and Operation Planning in SAPSales and Operation Planning in SAP
Sales and Operation Planning in SAP
Ankit Sharma
 
SAP MM Interview questions
SAP MM Interview questionsSAP MM Interview questions
SAP MM Interview questions
IT LearnMore
 
STO movement Type
STO movement TypeSTO movement Type
STO movement Type
Mohammed Azhad
 
Presentación gestion stock
Presentación gestion stockPresentación gestion stock
Presentación gestion stock
farcordd
 
Nif c 4 inventarios
Nif c 4 inventariosNif c 4 inventarios
Nif c 4 inventarios
GabyHasra VTuber
 
Naidu sap sd
Naidu sap sdNaidu sap sd
Naidu sap sd
prateek1201
 
SAP E-Document (Mexico)
SAP E-Document (Mexico) SAP E-Document (Mexico)
SAP E-Document (Mexico)
Surya Padhi
 
SAP MM PP Material requirement planning
SAP MM PP Material requirement planning SAP MM PP Material requirement planning
SAP MM PP Material requirement planning
Lokesh Modem
 
SAP – Non Stock Materials (NLAG)
SAP – Non Stock Materials (NLAG)SAP – Non Stock Materials (NLAG)
SAP – Non Stock Materials (NLAG)
Lorenzo Leonelli (ITIL©, 6σ)
 
SAP ECC Demand planning strategies
SAP ECC Demand planning strategiesSAP ECC Demand planning strategies
SAP ECC Demand planning strategies
Al Joseph
 
Document control, clearing, special gl, taxes SAP Fi
Document control, clearing, special gl, taxes SAP FiDocument control, clearing, special gl, taxes SAP Fi
Document control, clearing, special gl, taxes SAP Fi
Lav Kumar
 
Ckm3 material price analysis
Ckm3 material price analysisCkm3 material price analysis
Ckm3 material price analysis
Libelula5002
 
SAP MM INVOICE VERIFICATION.ppt
SAP MM INVOICE VERIFICATION.pptSAP MM INVOICE VERIFICATION.ppt
SAP MM INVOICE VERIFICATION.ppt
SharmaK5
 
marco conceptual y Niif 1
marco conceptual y Niif 1marco conceptual y Niif 1
marco conceptual y Niif 1
universidad de la costa
 

What's hot (20)

Gestión de Inventarios
Gestión de InventariosGestión de Inventarios
Gestión de Inventarios
 
Procure to Pay Process
Procure to Pay Process Procure to Pay Process
Procure to Pay Process
 
SAP - Vendor Entries
SAP - Vendor EntriesSAP - Vendor Entries
SAP - Vendor Entries
 
SAP S4 HANA MM 1709 Overview (mindmap edition) Final
SAP S4 HANA MM 1709 Overview (mindmap edition) FinalSAP S4 HANA MM 1709 Overview (mindmap edition) Final
SAP S4 HANA MM 1709 Overview (mindmap edition) Final
 
55811936 product-costing-cost-estimation-in-sap
55811936 product-costing-cost-estimation-in-sap55811936 product-costing-cost-estimation-in-sap
55811936 product-costing-cost-estimation-in-sap
 
SAP STO config
SAP STO configSAP STO config
SAP STO config
 
Sales and Operation Planning in SAP
Sales and Operation Planning in SAPSales and Operation Planning in SAP
Sales and Operation Planning in SAP
 
SAP MM Interview questions
SAP MM Interview questionsSAP MM Interview questions
SAP MM Interview questions
 
STO movement Type
STO movement TypeSTO movement Type
STO movement Type
 
Presentación gestion stock
Presentación gestion stockPresentación gestion stock
Presentación gestion stock
 
Nif c 4 inventarios
Nif c 4 inventariosNif c 4 inventarios
Nif c 4 inventarios
 
Naidu sap sd
Naidu sap sdNaidu sap sd
Naidu sap sd
 
SAP E-Document (Mexico)
SAP E-Document (Mexico) SAP E-Document (Mexico)
SAP E-Document (Mexico)
 
SAP MM PP Material requirement planning
SAP MM PP Material requirement planning SAP MM PP Material requirement planning
SAP MM PP Material requirement planning
 
SAP – Non Stock Materials (NLAG)
SAP – Non Stock Materials (NLAG)SAP – Non Stock Materials (NLAG)
SAP – Non Stock Materials (NLAG)
 
SAP ECC Demand planning strategies
SAP ECC Demand planning strategiesSAP ECC Demand planning strategies
SAP ECC Demand planning strategies
 
Document control, clearing, special gl, taxes SAP Fi
Document control, clearing, special gl, taxes SAP FiDocument control, clearing, special gl, taxes SAP Fi
Document control, clearing, special gl, taxes SAP Fi
 
Ckm3 material price analysis
Ckm3 material price analysisCkm3 material price analysis
Ckm3 material price analysis
 
SAP MM INVOICE VERIFICATION.ppt
SAP MM INVOICE VERIFICATION.pptSAP MM INVOICE VERIFICATION.ppt
SAP MM INVOICE VERIFICATION.ppt
 
marco conceptual y Niif 1
marco conceptual y Niif 1marco conceptual y Niif 1
marco conceptual y Niif 1
 

Similar to Preguntas y respuestas examen de SAP PP

Sap mrp materials requirements planning
Sap mrp   materials requirements planningSap mrp   materials requirements planning
Sap mrp materials requirements planning
madhu jetty
 
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
MBA, MSc, Alberto Castellano
 
Sap MRP materials requirements planning
Sap MRP materials requirements planningSap MRP materials requirements planning
Sap MRP materials requirements planning
nagarajusap06
 
Sap mrp
Sap mrpSap mrp
Planning Process and CBP V1.1.ppt
Planning Process and CBP V1.1.pptPlanning Process and CBP V1.1.ppt
Planning Process and CBP V1.1.ppt
SwayamTiwari12
 
Sap mrp-configuration-pp
Sap mrp-configuration-ppSap mrp-configuration-pp
Sap mrp-configuration-pp
Lokesh Modem
 
MRP Theory: Master Schedule, Bill of Material and Lead Times
MRP Theory: Master Schedule, Bill of Material and Lead TimesMRP Theory: Master Schedule, Bill of Material and Lead Times
MRP Theory: Master Schedule, Bill of Material and Lead Times
ejalgfer
 
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead TimesMRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
ejalgfer
 
CAPP, MRP, CRP, CAQC (model 2)
CAPP, MRP, CRP, CAQC (model 2) CAPP, MRP, CRP, CAQC (model 2)
CAPP, MRP, CRP, CAQC (model 2)
Deepika V S
 
Session 6-7-8 MRP.pptx PPC MBA Sem IV IB
Session 6-7-8 MRP.pptx PPC MBA Sem IV IBSession 6-7-8 MRP.pptx PPC MBA Sem IV IB
Session 6-7-8 MRP.pptx PPC MBA Sem IV IB
DrDeeptiSharma12
 
Lect 6.ppt
Lect 6.pptLect 6.ppt
Lect 6.ppt
Umer Butt
 
Material Requirements Planning (MRP).pptx
Material Requirements Planning (MRP).pptxMaterial Requirements Planning (MRP).pptx
Material Requirements Planning (MRP).pptx
IrelynJasmin
 
Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)
jntuhcej
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNING
jntuhcej
 
MRP & ERP.pdf
MRP & ERP.pdfMRP & ERP.pdf
MRP & ERP.pdf
AyzaFatima1
 
Production planning and control - Basic concepts
Production planning and control - Basic conceptsProduction planning and control - Basic concepts
Production planning and control - Basic concepts
gokulfea
 
Erp chapter 3
Erp chapter 3Erp chapter 3
Erp chapter 3
PoonamPangarkar1
 
Material requirement planning (mrp)
Material requirement planning (mrp)Material requirement planning (mrp)
Material requirement planning (mrp)
Somashekar S.M
 
MRP I and MRP II
MRP I and MRP IIMRP I and MRP II
MRP I and MRP II
Sugandha Vidge
 
SCM 304 Supply Chain Management Material Requirements .docx
SCM 304 Supply Chain Management Material Requirements .docxSCM 304 Supply Chain Management Material Requirements .docx
SCM 304 Supply Chain Management Material Requirements .docx
bagotjesusa
 

Similar to Preguntas y respuestas examen de SAP PP (20)

Sap mrp materials requirements planning
Sap mrp   materials requirements planningSap mrp   materials requirements planning
Sap mrp materials requirements planning
 
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
 
Sap MRP materials requirements planning
Sap MRP materials requirements planningSap MRP materials requirements planning
Sap MRP materials requirements planning
 
Sap mrp
Sap mrpSap mrp
Sap mrp
 
Planning Process and CBP V1.1.ppt
Planning Process and CBP V1.1.pptPlanning Process and CBP V1.1.ppt
Planning Process and CBP V1.1.ppt
 
Sap mrp-configuration-pp
Sap mrp-configuration-ppSap mrp-configuration-pp
Sap mrp-configuration-pp
 
MRP Theory: Master Schedule, Bill of Material and Lead Times
MRP Theory: Master Schedule, Bill of Material and Lead TimesMRP Theory: Master Schedule, Bill of Material and Lead Times
MRP Theory: Master Schedule, Bill of Material and Lead Times
 
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead TimesMRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
 
CAPP, MRP, CRP, CAQC (model 2)
CAPP, MRP, CRP, CAQC (model 2) CAPP, MRP, CRP, CAQC (model 2)
CAPP, MRP, CRP, CAQC (model 2)
 
Session 6-7-8 MRP.pptx PPC MBA Sem IV IB
Session 6-7-8 MRP.pptx PPC MBA Sem IV IBSession 6-7-8 MRP.pptx PPC MBA Sem IV IB
Session 6-7-8 MRP.pptx PPC MBA Sem IV IB
 
Lect 6.ppt
Lect 6.pptLect 6.ppt
Lect 6.ppt
 
Material Requirements Planning (MRP).pptx
Material Requirements Planning (MRP).pptxMaterial Requirements Planning (MRP).pptx
Material Requirements Planning (MRP).pptx
 
Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNING
 
MRP & ERP.pdf
MRP & ERP.pdfMRP & ERP.pdf
MRP & ERP.pdf
 
Production planning and control - Basic concepts
Production planning and control - Basic conceptsProduction planning and control - Basic concepts
Production planning and control - Basic concepts
 
Erp chapter 3
Erp chapter 3Erp chapter 3
Erp chapter 3
 
Material requirement planning (mrp)
Material requirement planning (mrp)Material requirement planning (mrp)
Material requirement planning (mrp)
 
MRP I and MRP II
MRP I and MRP IIMRP I and MRP II
MRP I and MRP II
 
SCM 304 Supply Chain Management Material Requirements .docx
SCM 304 Supply Chain Management Material Requirements .docxSCM 304 Supply Chain Management Material Requirements .docx
SCM 304 Supply Chain Management Material Requirements .docx
 

Recently uploaded

Automated software refactoring with OpenRewrite and Generative AI.pptx.pdf
Automated software refactoring with OpenRewrite and Generative AI.pptx.pdfAutomated software refactoring with OpenRewrite and Generative AI.pptx.pdf
Automated software refactoring with OpenRewrite and Generative AI.pptx.pdf
timtebeek1
 
Neo4j - Product Vision and Knowledge Graphs - GraphSummit Paris
Neo4j - Product Vision and Knowledge Graphs - GraphSummit ParisNeo4j - Product Vision and Knowledge Graphs - GraphSummit Paris
Neo4j - Product Vision and Knowledge Graphs - GraphSummit Paris
Neo4j
 
Measures in SQL (SIGMOD 2024, Santiago, Chile)
Measures in SQL (SIGMOD 2024, Santiago, Chile)Measures in SQL (SIGMOD 2024, Santiago, Chile)
Measures in SQL (SIGMOD 2024, Santiago, Chile)
Julian Hyde
 
What is Master Data Management by PiLog Group
What is Master Data Management by PiLog GroupWhat is Master Data Management by PiLog Group
What is Master Data Management by PiLog Group
aymanquadri279
 
原版定制美国纽约州立大学奥尔巴尼分校毕业证学位证书原版一模一样
原版定制美国纽约州立大学奥尔巴尼分校毕业证学位证书原版一模一样原版定制美国纽约州立大学奥尔巴尼分校毕业证学位证书原版一模一样
原版定制美国纽约州立大学奥尔巴尼分校毕业证学位证书原版一模一样
mz5nrf0n
 
Oracle 23c New Features For DBAs and Developers.pptx
Oracle 23c New Features For DBAs and Developers.pptxOracle 23c New Features For DBAs and Developers.pptx
Oracle 23c New Features For DBAs and Developers.pptx
Remote DBA Services
 
E-commerce Development Services- Hornet Dynamics
E-commerce Development Services- Hornet DynamicsE-commerce Development Services- Hornet Dynamics
E-commerce Development Services- Hornet Dynamics
Hornet Dynamics
 
Artificia Intellicence and XPath Extension Functions
Artificia Intellicence and XPath Extension FunctionsArtificia Intellicence and XPath Extension Functions
Artificia Intellicence and XPath Extension Functions
Octavian Nadolu
 
Introducing Crescat - Event Management Software for Venues, Festivals and Eve...
Introducing Crescat - Event Management Software for Venues, Festivals and Eve...Introducing Crescat - Event Management Software for Venues, Festivals and Eve...
Introducing Crescat - Event Management Software for Venues, Festivals and Eve...
Crescat
 
Essentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FMEEssentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FME
Safe Software
 
OpenMetadata Community Meeting - 5th June 2024
OpenMetadata Community Meeting - 5th June 2024OpenMetadata Community Meeting - 5th June 2024
OpenMetadata Community Meeting - 5th June 2024
OpenMetadata
 
Using Query Store in Azure PostgreSQL to Understand Query Performance
Using Query Store in Azure PostgreSQL to Understand Query PerformanceUsing Query Store in Azure PostgreSQL to Understand Query Performance
Using Query Store in Azure PostgreSQL to Understand Query Performance
Grant Fritchey
 
GreenCode-A-VSCode-Plugin--Dario-Jurisic
GreenCode-A-VSCode-Plugin--Dario-JurisicGreenCode-A-VSCode-Plugin--Dario-Jurisic
GreenCode-A-VSCode-Plugin--Dario-Jurisic
Green Software Development
 
Using Xen Hypervisor for Functional Safety
Using Xen Hypervisor for Functional SafetyUsing Xen Hypervisor for Functional Safety
Using Xen Hypervisor for Functional Safety
Ayan Halder
 
Empowering Growth with Best Software Development Company in Noida - Deuglo
Empowering Growth with Best Software  Development Company in Noida - DeugloEmpowering Growth with Best Software  Development Company in Noida - Deuglo
Empowering Growth with Best Software Development Company in Noida - Deuglo
Deuglo Infosystem Pvt Ltd
 
socradar-q1-2024-aviation-industry-report.pdf
socradar-q1-2024-aviation-industry-report.pdfsocradar-q1-2024-aviation-industry-report.pdf
socradar-q1-2024-aviation-industry-report.pdf
SOCRadar
 
KuberTENes Birthday Bash Guadalajara - Introducción a Argo CD
KuberTENes Birthday Bash Guadalajara - Introducción a Argo CDKuberTENes Birthday Bash Guadalajara - Introducción a Argo CD
KuberTENes Birthday Bash Guadalajara - Introducción a Argo CD
rodomar2
 
Transform Your Communication with Cloud-Based IVR Solutions
Transform Your Communication with Cloud-Based IVR SolutionsTransform Your Communication with Cloud-Based IVR Solutions
Transform Your Communication with Cloud-Based IVR Solutions
TheSMSPoint
 
Hand Rolled Applicative User Validation Code Kata
Hand Rolled Applicative User ValidationCode KataHand Rolled Applicative User ValidationCode Kata
Hand Rolled Applicative User Validation Code Kata
Philip Schwarz
 
Neo4j - Product Vision and Knowledge Graphs - GraphSummit Paris
Neo4j - Product Vision and Knowledge Graphs - GraphSummit ParisNeo4j - Product Vision and Knowledge Graphs - GraphSummit Paris
Neo4j - Product Vision and Knowledge Graphs - GraphSummit Paris
Neo4j
 

Recently uploaded (20)

Automated software refactoring with OpenRewrite and Generative AI.pptx.pdf
Automated software refactoring with OpenRewrite and Generative AI.pptx.pdfAutomated software refactoring with OpenRewrite and Generative AI.pptx.pdf
Automated software refactoring with OpenRewrite and Generative AI.pptx.pdf
 
Neo4j - Product Vision and Knowledge Graphs - GraphSummit Paris
Neo4j - Product Vision and Knowledge Graphs - GraphSummit ParisNeo4j - Product Vision and Knowledge Graphs - GraphSummit Paris
Neo4j - Product Vision and Knowledge Graphs - GraphSummit Paris
 
Measures in SQL (SIGMOD 2024, Santiago, Chile)
Measures in SQL (SIGMOD 2024, Santiago, Chile)Measures in SQL (SIGMOD 2024, Santiago, Chile)
Measures in SQL (SIGMOD 2024, Santiago, Chile)
 
What is Master Data Management by PiLog Group
What is Master Data Management by PiLog GroupWhat is Master Data Management by PiLog Group
What is Master Data Management by PiLog Group
 
原版定制美国纽约州立大学奥尔巴尼分校毕业证学位证书原版一模一样
原版定制美国纽约州立大学奥尔巴尼分校毕业证学位证书原版一模一样原版定制美国纽约州立大学奥尔巴尼分校毕业证学位证书原版一模一样
原版定制美国纽约州立大学奥尔巴尼分校毕业证学位证书原版一模一样
 
Oracle 23c New Features For DBAs and Developers.pptx
Oracle 23c New Features For DBAs and Developers.pptxOracle 23c New Features For DBAs and Developers.pptx
Oracle 23c New Features For DBAs and Developers.pptx
 
E-commerce Development Services- Hornet Dynamics
E-commerce Development Services- Hornet DynamicsE-commerce Development Services- Hornet Dynamics
E-commerce Development Services- Hornet Dynamics
 
Artificia Intellicence and XPath Extension Functions
Artificia Intellicence and XPath Extension FunctionsArtificia Intellicence and XPath Extension Functions
Artificia Intellicence and XPath Extension Functions
 
Introducing Crescat - Event Management Software for Venues, Festivals and Eve...
Introducing Crescat - Event Management Software for Venues, Festivals and Eve...Introducing Crescat - Event Management Software for Venues, Festivals and Eve...
Introducing Crescat - Event Management Software for Venues, Festivals and Eve...
 
Essentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FMEEssentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FME
 
OpenMetadata Community Meeting - 5th June 2024
OpenMetadata Community Meeting - 5th June 2024OpenMetadata Community Meeting - 5th June 2024
OpenMetadata Community Meeting - 5th June 2024
 
Using Query Store in Azure PostgreSQL to Understand Query Performance
Using Query Store in Azure PostgreSQL to Understand Query PerformanceUsing Query Store in Azure PostgreSQL to Understand Query Performance
Using Query Store in Azure PostgreSQL to Understand Query Performance
 
GreenCode-A-VSCode-Plugin--Dario-Jurisic
GreenCode-A-VSCode-Plugin--Dario-JurisicGreenCode-A-VSCode-Plugin--Dario-Jurisic
GreenCode-A-VSCode-Plugin--Dario-Jurisic
 
Using Xen Hypervisor for Functional Safety
Using Xen Hypervisor for Functional SafetyUsing Xen Hypervisor for Functional Safety
Using Xen Hypervisor for Functional Safety
 
Empowering Growth with Best Software Development Company in Noida - Deuglo
Empowering Growth with Best Software  Development Company in Noida - DeugloEmpowering Growth with Best Software  Development Company in Noida - Deuglo
Empowering Growth with Best Software Development Company in Noida - Deuglo
 
socradar-q1-2024-aviation-industry-report.pdf
socradar-q1-2024-aviation-industry-report.pdfsocradar-q1-2024-aviation-industry-report.pdf
socradar-q1-2024-aviation-industry-report.pdf
 
KuberTENes Birthday Bash Guadalajara - Introducción a Argo CD
KuberTENes Birthday Bash Guadalajara - Introducción a Argo CDKuberTENes Birthday Bash Guadalajara - Introducción a Argo CD
KuberTENes Birthday Bash Guadalajara - Introducción a Argo CD
 
Transform Your Communication with Cloud-Based IVR Solutions
Transform Your Communication with Cloud-Based IVR SolutionsTransform Your Communication with Cloud-Based IVR Solutions
Transform Your Communication with Cloud-Based IVR Solutions
 
Hand Rolled Applicative User Validation Code Kata
Hand Rolled Applicative User ValidationCode KataHand Rolled Applicative User ValidationCode Kata
Hand Rolled Applicative User Validation Code Kata
 
Neo4j - Product Vision and Knowledge Graphs - GraphSummit Paris
Neo4j - Product Vision and Knowledge Graphs - GraphSummit ParisNeo4j - Product Vision and Knowledge Graphs - GraphSummit Paris
Neo4j - Product Vision and Knowledge Graphs - GraphSummit Paris
 

Preguntas y respuestas examen de SAP PP

  • 1. Lean Manufacturing (PP-REM/PP-KAB) 1. Which of the following master data do you need to make available for repetitive manufacturing? Note: There are 3 correct answers to this question. _ Master records for serial numbers _ Product cost collector _ Production supply área _ Repetitive manufacturing profile _ Production versión 2. Which of the following efforts can be minimized using the KANBAN procedure? • Organizational effort to stage material • Effort for Sales and Operations Planning (sop) • Effort for master data maintenance • Organizational effort for capacity planning 3. Which of the following aspects characterize repetitive manufacturing in a manufacturing plant? Note: There are 3 correct answers to this question. _ Continuous material consuption, production flow and output _ Period-based planning of the quantities to be produced _ Production without using production orders and without status management _ Automatic line loading by capacity limits across all production lines _ Shop fabrication
  • 2. 4. What repetitive manufacturing options can you use to carry out line loading in the SAP ECC system and thus generate Run Schedule Quantities (RSQ) from normal planned orders? Note: There are 3 correct answers to this question _ Using a planning algorithm from capacity planning _ Automatic selection of the production versión by applying quota arrangement records in material requirements planning (MRP) _ Selecting a suitable repetitive manufacturing profile that contains an option for automatic line selection. _ Automatic selection of the production version in material requirements planning (MRP) using Selection Methods setting. _ Manual assignment of planned production quantities in a planning table 5. Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt? • Set ‘Container in process’ • Set ‘Container empty’ • Set ‘Contaniner in transport’ • Set ‘Container full’ 6. Which of the following master data do you always have to make available for material replenishment using the KANBAN procedure? Note: There are 2 correct answers to this question _ Product cost collector _ Control cycles _ Rate Routings _ Production supply areas _ Production versions Production Orders Basics (PP-SFC)
  • 3. 7. In which of the following objects can you activate backflushing of components if you want to use this functionality during order confirmation? Note: There are 3 correct answers to this question. _ Material Master (Finished Product) _ Material Master (Component) _ Work Center _ Production Scheduling Profile _ Routing 8. Which production order function can no longer be carried out after the order is released? • Switching sequences • Posting a godos receipt from production to stock • Read PP master data • Posting a godos issue from stock to the production order 9. What are the consequences of a confirmation of an operation? Note: There are 2 correct answers to this question. _ Actual costs are posted for the production confirmed _ Serial numbers are assigned for the confirmed quantity _ The produced and confirmed quantity is automatically posted to the warehouse stock as a receipt _ The operation’s capacity requirements are reduced 10. In production order processing, for which of the following objects can you enter a confirmation? Note: There are 3 correct answers to this question _ Individual Capacity
  • 4. _ Work Center _ Trigger Point _ Operation / Suboperation _ Order 11. Which one of the following scheduling types cannot be assigned as default to an order type (production order)? • Only capacity requirements • Midpoint • Backward • Forward 12. Which of the following requirements for a manufacturing plant can be supported by using production orders? Note: There are 3 correct answers to this question _ Make-to-stock production _ Orderless production _ Customer requeriments-dependent production _ Integrated display of documents (drawings, texts) in the production process _ Variable calculation of material quantities (production output, material usage) and operation quantities 13. Which of the following situation occur when a production order is set to technically Complete (TECO)? Note: There are 3 correct answers to this question _ Capacity requirements are delated _ The order is no longer relevant for M aterial Requirements Planning _The order and its operations receive the system status locked (LKD) _ Purchase orders for external operations or non-stock materials are deleted _ Reservations are deleted
  • 5. 14. Which of the following master data is mandatory for production order processing, when material reservations and capacity requirements for operations should be genered automatically? Note: There are 2 correct answers to this question _ Document structure _ Inspections Characteristics _ Routing _ Production Versions _ Material Master Records (product and material component) 15. Which of the following functions ocurr when a production order is created? Note: There are 3 correct answers to this question _ Selecting and copying a bill of material _ Copying a document that is assigned to the material master for the product to be produced _ Calculating the lead time for the production order _ Calculating the quantity to be produced on the basis of the available material stock _ Selecting and copying a routing Material and Capacity Req. Planning 16. In your interprise, a planning strategy is used in SAP ECC that enables joint planning of all MRP scheduled assemblies for a finished product to trigger procurement of these assemblies. It is important to ensure that the finished product is only produced when there is a customer order is received, of the finished product should be triggered in the form of make-to-order planning and production Wich planning strategy covers this scenario? • Planning at the assembly level (strategy 70) • Planning with make-to-stock (strategy 10) • Planning without final assmbly (strategy 50)
  • 6. • Planning with final assambly (strategy 40) 17. In what order are the individual steps of material requirements planning performed in SAP ECC? • 1. Calculation of safety stock 2. Application of the lot-sizing procedure 3. Scheduling 4. Determination of the procurement type • 1. Availability check 2. Application of the lot-sizing procedure 3. Determination of the procurement type 4. Scheduling • 1. Net requirements calculation 2. Application of the lot-sizing procedure 3. Scheduling 4. Determination of the procurement type • 1. Net requeriments calculation 2. Application of the lot-sizing procedure 3. Determination of the procurement type 4. Scheduling 18. Which data forms the basis for calculating the capacity requirement for an operation? Note: There are 3 correct answers to this question. _ Formulas (work center) _ In-house production time (material master) _ Transport time (routing) _ Standard values (routing) _ Operation control key (routing) 19. Which of the following statements is true for the ATP (available to promise) availability check in SAP ECC that is triggered from a customer order? • The ATP check does not confirm against stocks and receipts, it checks consumption against planning requirements • An availability check by means of ATP creates fixed links between customer orders and their confirmed receipts • The ATP quantity is the quantity still available that can be used to confirm incoming customer orders
  • 7. • If the ATP check establishes non-availability, it checks whether it is still possible to procure or produce in time 20. Which statement regarding lot size procedures is correct? • If a make-to-order production strategy is in use, a lot for (exact) lot size is always determined for the corresponding procurement element • The procurement quantity of a lot size procedure can be specified using a safety time period profile • If a long-term lot size is in use, procurement is conducted with a long-term perspective • The lot size quantity can be influenced using a mínimum quantity and the rounding profile 21. Which of the following statement is true for the simulation mode in the context of material requirements planning in SAP ECC? • The simulation mode is used in scenarios in which requirements planning created the procurement element prematurely in terms of demand • The simulation mode opens the analysis of the delay time. Manual rescheduling of the receipt in the finished product and subsequent requirements planning lead to a solution that is feasible from the requirements planning perspective. However, this solution may lead to a date/time violation in the finished product • The simulation mode represents an interactive multilevel form of planning, the result of which is automatically posted to the database after the planning run • Assuming a delay time in the ‘critical path’, the simulation mode triggers multilevel bottom-up scheduling through to the finished product, which therefore receives a delayed receipt 22. Which properties does ECC Master Production Scheduling (MPS) have? Note: There are 3 correct answers to this question _ MPS ítems can be define on plant level _ MPS ítems can be taken into consideration by a standard MRP run (Material Requirements Planning) _ The planning of MPS and Non-MPS ítems is always carried out in one planning run
  • 8. _ MPS ítems can be define don MRP Area level (Material Requirements Planning Area) _ Non-MPS ítems can be taken into consideration by an MPS run 23. Which of the following features are offered by MRP Areas (Material Requirements Planning Areas)? Note: There are 2 correct answers to this question. _ Make-to-order production is supported by storage location MRP Areas _ Subcontracting is supported by MRP Areas _ A storage location may be assigned to different MPR Areas _ An MRP Area may include different storage locations 24. Which functions lead to a reduction in the capacity requirement for an individual operation at a work center? Note: There are 3 correct answers to this question _ Confirming the operation _ Setting the status technically complete (TECO) _ Rescheduling the operation _ Reducing the order quantity _ Posting the goods receipt for the production order 25. In your company Planning strategies are used in the SAP ECC demand management that are based on consumption. Which of the following statements about consumption in true? Note: There are 2 correct answers to this question _ Consumption can also take place between order reservations and planned independent requirements, depending on the strategy. _ A consumption situation in dynamic and is always restructured with the planning run. _ Consumption always takes place on the material level between the planned independent requirements and the planned orders. _ The consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
  • 9. 26. Which statements are true for ECC Long-term Planning (LTP)? Note: There are 2 correct answers to this question _Reorder point planned materials can be included in long-term planning _ Long-term planning generally is operational planning of important components _ In case of external procurement, long-term planning creates purchase requisitions. _ A planning scenario must be released to use it in long-term planning 27. Which of the following are properties of ECC Multi-site planning? Note: There are 2 correct answers to this question - When using two-step stock transport order with delivery, the receiving plant is defined as a customer - The use of “scope of planning” (cross-plant total planning) is mandatory for Multi-Site planning. - Both withdrawal from alternative plant and withdrawal from another plant are defined via special procurement Keys. - When using one-step stock transfer posting, transfer stock is created in the receiving plant. Production Orders Advanced (PP-SFC) 28. The company that you advise does not want to manage certain value intensive materials in the warehouse stock instead, the user wishes to control material provision in such a way that these materials are procured directly for the production and/or process order How can you fullfill this request? Note: There are 2 correct answers to this question. _ Using the procurement type ‘external procurement’ in the material master for the component _ Using the special procurement key ‘subcontracting’ in the material master for the component _ Using the special procurement key ‘direct procurement/external procurement’ in the material master for the component _ Using the ítem type ‘non stock’ ítem in the bill of material for the material in question _ Controlling the material in question as a co-product
  • 10. 29. The company you advise wants to control the availability check in so that when a production and/or process order is created, the following receipts of issues are taken into account planned orders, purchase orders, production orders, reservations, dependent requirements. When the production and/or process order is released, only the stock that is currently freely usable should be taken into consideration. How can you fulfill this request? • Enter an appropriate availability checking rule in the order type. • Differentiated assignment of two different checking rules in check control. • Activete the freely usable stock in the scope of check • Enter an appropriate availability checking group in the material master 30. A user you advise wishes to transfer variable process instructions for automated processing directly to certain work centers and machines in the production department (for example, ‘feed speed’, ‘pressing pressure’, ‘dry temperature’). The user also wishes to receive variable as-is messages (such as ‘actual quantities’, ‘actual times’) from these work centers and machines and to process these messages for feedback concerning production orders. Which of the following options would you recommend to implement these requirements? • SAP Application Link Enabling (ALE) • Execution Steps (XSteps) and process messages • ‘Plant data collection’ (PP-PDC) interface • SAP Business Intelligence (BI) 31. Which options can you offer a user of the SAP ECC system for managing costs (costing and settlement) with regards to production orders? Note: There are 2 correct answers to this question _ Series-based costing _ Product cost collecting
  • 11. _ Order-based costing _ Work center-based costing 32. Which options can you offer someone who uses the SAP ECC system for production orders and requires support for material supply in production? Note: There are 3 correct answers to this question _ Logistics Information System (LIS) _ Automatic generation of a transport order _ Material directory _ Pick list _ Pull list 33. Which of the following elements do you have to prepare for costing of a production order to function without errors? Note: There are 3 correct answers to this question _ Propose a standard text key in work center _ Assign a production scheduling profile to the material master (product) _ Enter formulas for costing in the work center _ Assign costing variants to order type _ Use an operation control key with the indicator “costing-relevant” 34. Which of the following possible errors would lead to the message shown? Note: There are 2 correct answers to this question
  • 12. _ The material master (product) is set to manual routing selection and valid routing exists. _ In the material master, plan selection was set to production version. A production version was created and it is faulty _ The customizing for the order type is set to manual routing selection and a valid routing exists. _ There are no valid routings or no routings available on the explosion date. 35. From what point can you no longer use the “Read PP master data” in the production order? _ From the release of the production order _ After printing the order papers _ After assigning the confirmed quantity of a material component due to carrying out a material availability check _ After the first posting of goods movements or confirmation 36. What options for selecting a routing exist when creating a production order? Note: There are 3 correct answers to this question _Manual selection _ Selection on the basis of the routing number in the material master for the material to be produced _ Selection on the basis of the production control profile _ Automatic selection, controlled via settings in Customizing 37. The user you advise request that you make it possible for the user to produce material for stock, for customer orders, projects, orders ans cost center with productions orders. Where can you make settings to ensure these options? _ Valuation plant _ Settlement profile _ Serial number profile _ Production scheduling profile 38. The company you advise wants to carry out the material availability check automatically in the production order at various points in time. Which of the following options would you recommend? Note: There are 2 correct answers to this question _ Confirmation of the operation that the materials being checked are assigned to
  • 13. _Creation of the production order _ Goods receipt for the product produced with the order _ Goods receipt for a missing part _ Release of the production order 39. Which of the following prerequisites have to be fulfilled for production orders to be transferred to a business data entry system via the Plant data Collection (PP-PDC) interface? Note: There are 3 correct answers to this question _ Production orders have been released _ The application of the PP-PDC interface was activated in the order type for the production order. _ The material to be produced with a production order was flagged for transfer in its material master. _ Execution steps were used to record process instructions in the operation. _ Production Orders contain at least on operation that contains a work center with a “subsystem group” assigned to it 40. Which objects can you use in the production order for a material component to propose the storage location in its reservation? Note: There are 3 correct answers to this question _ Material Master (product) _ Routing _ Material Master (component) _ Production Version _ Work Center 41. For a specific end product, you want to use a planning time fence and fixing type 1 to ensure that the planning situation in SAP ECC calms down in a short-term time window. Two customer order arrive at short notice and their receipts should really be within the planning time fence, due their date/time. Which statement is true with this scenario? _ newly created planned orders cannot be created by requirements planning before the end of the planning time fence, at the earliest _ Requirement planning only examines changes that are relevant to scheduling whitin the planning time fence ; the customer orders are covered in time. _ The MRP controller has no possibility of creating planned orders within the planning time fence _ Within the planning time fence, the newly created planned orders are automatically frozen by requirement planning (roll forward)
  • 14. Master Data (LDM) 42. In SAP ECC, you want to map an in-house production process for general warehouse. The fields in the area of the lot size-dependent in-house production time are to be populated when the material master for the final product is created. These fields can be maintained by updating from the scheduling result for the associated routing. You now think that there could be significant changes to the production times in the routing and decide against updating the material master. What problema could this lead to? • Requirements planning runs up against an exception message in basic dates scheduling because the material master parameters do not match the scheduling result from the routing. • Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters. • Lead time scheduling, wich occurs by the time that a planned order is converted into a production order (at the latest), cannot take place on the basis of incorrect basic dates. • In the course of basic dates scheduling with requirements planning, dependent requirements request the components from the bill of materials at the wrong times. 43. A final assembly process takes place at three centers, one after the other. The routing, which consist of three associated operations (10, 20 and 30), plans for a specific BOM component to be installed during operation 30 and not before. The component should therefore only be requested at the start of operation 30 What sequence do you follow in master data maintenance in SAP ECC to make this component available in line with operations during final assembly? • 1. Create BOM 2. Create work centers 3. Create routing 4. Carry out component assignment in BOM or routing • 1. Create BOM 2. Create work centers 3. Create routing 4. Carry out component assignment in work center • 1. Create work centers 2. Create routing 3. Create BOM 4. Carry out component assignment in work center • 1. Create routing 2. Create work center 3. Create BOM 4. Carry out component assignment in BOM or routing
  • 15. 44. When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for scheduling? Note: There are 3 correct answers to this question _ General operation values in task list _ User-defined field from operation in task list _ Standard value from operation in task list _ General values from work scheduling view in the material master _ General ítem values in bill of materials 45. The master data for a logistical process is to be stored in the SAP ECC system. In this context, you require the production versions for subsequent planning and production. You know a mass maintenance transaction that you could use here Where else in the SAP ECC system could you define production versions? • In the work center • In the material master • In the repetitive manufacturing profile in Customizing • In the line routing 46. In SAP ECC, you calculate the standard available capacity for a work center capacity with the following data: start 7:00:00a.m., end 3:00:00 p.m., break duration: 1 hour, rate of utilization: 80%, overload 110%, number of individual capacities: 1 How large is the standard available capacity? • 7 hours • 5.6 hours • 6.16 hours
  • 16. • 8 hours 47. Which of the following activities is necessary for the capacity availability check to be carried out automatically when a production order is released? • Activate the availability check and assign the check control to the plant • Activate the availability check and assign an overall profile in check control for the business function order release • Activate the availability check and assign an availability checking group to the material master for the product to be produced • Activate the availability check and assign a checking rule to the work center for the operation to be checked 48. Which information is contained in production versions for selecting routings and bills of material? • The routing and BOM alternatives to be used for production • The plant for which the routing and BOM have to be created • All the control parameters for selecting routings and bills of material • The explosión date on which the validity of the routing and bill of material is checked 49. In the task list, there is the possibility to work with suboperations. What can you do in more detail by using suboperations? Note: There are 2 correct answers to this question _ Material component allocation _ Costing _ Capacity planning _ Scheduling
  • 17. 50. The master data for an in-house production process is to be set up in the SAP ECC system.To do this, you should create a suitable routing that plans for five operation in an initial sequence (10, 20,30,40,50).There should be an option of relocating operation 30 and 40 to a second sequence on other work centers if there are capacity bottlenecks. What sequence type would you use to create the second sequence in the system? _ Substitute sequence _ Parallel sequence _ Standard sequence _ Alternative sequence 51. Which type of objects can be changed with Engineering Change Management? Note: There are 3 correct answers to this question _ Material Master _ Task list _ Production Version _ Work Center _ Bill of materials 52. In modeling in-house production using SAP ECC, bills of material (BOM) are to be recorded in the system. On which business levels can you create a BOM? Note: There are 2 correct answers to this question _ At the business area level _ AT the client level _ At the company code level _ At the plant level 53. A new material with the following properties is to be recorded in SAP ECC: the material in kept in stock, is externally procured, and is used as a component in the bills of material for various final products. However, this material may not be purchased directly. Which standard SAP material type would you use? _NLAG (non-stock material) _ FERT (finished product) _ ROH (raw material) _ HAWA (trading good)
  • 18. 54. An enterprise based in the USA produces an end product that is used with unit of measure “pound” (LB). The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit “kilogram” (KG). Which of the following solution does SAP ECC offer? _In the basic data customizing, you create a unit of measure group that converts pounds to kilograms. You then assign this to the material master on basic data view 1. _ In the material master, you create a conversion factor for converting pounds to kilograms on basic data view 1. _ This in no need to take any action. There is a general conversion in the central customizing of units measurements, so thah automatic conversion of pounds to kilograms takes place. _ You create a new material with a reference to the original material and assign the metric unit measure to the new material master 55. Which of the following functions are available in the SAP ECC System for leveling overloads in individual work centers with the capacity planning tools? Note: There are 3 correct answers to this question _ Batch size optimization _ Lot Size optimization _ Setup time reduction _ Finite capacity scheduling _ Midpoint scheduling Basic on SAP Business Processes (E-Learnings) 56. The Service Desk is available as part of the SAP Solution Manager. Which functions are included in the scope of the Service Desk? Note: There are 2 correct answers to this question. _ Managing SAP Notes _ Troubleshooting _ SAP Help _ Process for processing messages
  • 19. 57. Which of the following statements about the SAP Solution Manager listed is correct? _Solution manager is a satellite system in a system landscape _ Solution Manager is an add-on industry solution _ Solution Manager is a stand-alone system that communicates with other systems in a system landscape. _ Solution Manager is part of the SAP ECC System 58. What does SAP ERP mean? • SAP ERP is an application that an Enterprise can use to manage its business processes efficiently • SAP ERP is a planning system in which extended planning processes can be mapped • SAP ERP is a technological platform on the basis of which customer-specific extensions can be imported SAP ERP is a system hardware that includes modules for purchasing, sales and distribution, materials management, production and so on. 59. Where are the standard operation times for an operation defined? • Routing • Maerial Master • Production Resource/Tool (PRT) • Work Center Process Orders (PP-PI) 60. With which functions of the process order can you fulfill the requirements of the Good Manufacturing Practices (GMP) standard? Note: There are 3 correct answers to this question _ Availibility check _ Resource selection
  • 20. _ Material identification and reconciliation _ Batch record _ Digital signature 61. Which of the following structural elements does a process order have? Note: There are 3 correct answers to this question. _ Relationships _ Item data _ Characteristic-based process instructions _ Parallel sequences _ Phases 62. Which of the following requirements for a manufacturing plant can be supported by using process manufacturing? Note: There are 3 correct answers to this question _ Manufacturing in charge quantities _ Material requirements planning for production resources _ Manufacturing without orders _ Master recipe-based manufacturing _ Variable calculation of material quantities (product output, material usage) 63. Which of the following master data do you need to provide for process manufacturing? Note: There are 3 correct answers to this question _ Production Versions _ Serial numbers _ Master Recipe _Resources _ Product cost collector
  • 21. Application Overview and Background 64. Which of the following statements about the planning functions available in SAP ECC are true? Note: There are 2 correct answers to this question _ In demand management (DM) material shortage situations are identified and given requirement coverage elements _ Long-term planning (LPT) is a long-term form of forecast planning _ Material requirements planning (MRP) does not include automatic capacity leveling _ Master production scheduling (MPS) refers to preferred planning of important materials. 65. Which of the following statements about ATP (Available to promise) checks for material components are correct? Note: There are 2 correct answers to this question _ The ATP checks are automatically performed during MRP (material requirement Planning) runs. _ ATP checks are used to evaluate the free capacity on a certain work center _ ATP checks can be carried out automatically when releasing a production order _ ATP checks can be adjusted to also consider future requirements and receipts _ ATP checks are mandatory for lead-time scheduling 66. A finished material is to be planned in a controlled manner in the SAP ECC system in the context of requirements planning. The planned orders are scheduled using what is know as basic date scheduling) not lead-time scheduling). Which of the following statements is true for the resulting dependent requirements? _ In multi-level backward scheduling, dependent requirements are triggered at the start date for the higher-level assembly _ If individual material components are explicity assigned to operation during the BOM and routing maintenance, the requirement date of the dependent requirement for these components are scheduled at each of the operation start dates. _ In multi-level backward scheduling, dependent requirements are triggered at the start date for the higher-level assembly planned order. _ When customer order is created for the finished product, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.
  • 22. 67. A user has entered planning strategy group “10” (make to stock production) in the material master (SAP ECC) of a product. For the coming months, requirements with requirement type LSF (derived from the main strategy “10”) have been planned. The user would like to change the requirement type from LSF to VSF planning with final assembly (in accordance with planning strategy “40” ) for requirements in the production plan that have alredy been saved. Which of the following statements are applicable in this case? Note: There are 2 correct answers to this question _ the present requirement for the product can be changed manually from “LSF” to “VSF” in the requirement type field in te production plan, so that the new strategy 40 determines the next planning operation. _ The user can enter the new planning strategy group “40” in the material master of the product, but the requirement type is not changed automatically for existing requirements. _ The planning strategy group can be changed from “10” to “40” in the existing production plan, and the requirement type for all requirements is changed automatically _ The user has to change the requirement type for planning strategy “10” to VSF planning with final assembly in Customizing. The requirement type for all existing requirements in then changed automatically. 68. A supply chain planning run is to be carried out in the SAP ECC System as an example. What would be the most effective sequence in which to run through the planning modules? _ 1.- Capacity Planning 2.- Sales and Operation planning 3.- Demand management 4.- Long term planning 5.- Requeriment planning _ 1.- Long-term planning 2.- Sales and Operation planning 3.- Demand management 4.- Requirement planning 5.- Capacity planning _ 1.- Demand management 2.- Sales and operation planning 3.- Capacity planning 4.- Long-term planning 5.- Requirement planning _ 1.- Sales and operation planning 2.- Demand management 3.- Long-term planning 4.- Requirement planning 5.- Capacity planning Material Requirements Planning (PP-MRP) 69. In SAP ECC, a customer tests the firming options for planned orders. The customer first sets the manual firming date from the stock/requirements list to firm planned orders that shall occur in the short term. In the material master, a rolling planning time horizon with firming type 1 is active. Some planned orders have also been firmed manually already Which statement applies for the resultant firming situation?
  • 23. • The firming interval is specified by the firming mechanism that currently stretches further into the future; all the planned orders within this horizon are firmed only if they were previously firmed manually • The firming interval is specified by the planning time fence from the material master, because this always overrides the manual firming date, all the manually firmed planned orders are firmed independently of this • The firming interval is specified by the firming mechanism that currently stretches further into the future and which firms planned orders that are within it; all the manually firmed planned orders are firmed independently of this • The firming interval is specified by the manual firming date because it always overrides the planning time fence from the material master, all the manually firmed planned orders are firmed independently of this 70. A customer has been using planning strategies 30 (production by lots) and 10 (anonymous make-to-stock production) in SAP ECC. The customer wishes to move in part to planning strategy 40 (planning with final assembly). The issue of ‘consumption’ has an effect here for the first time Which properties apply for consumption with planning strategy 40? Note: There are 2 correct answers to this question _ Consumption can reduce the originally planned production quantity _ Consumption can result in the subsequent specification and adjustment of planning elements in terms of quantity and date, by means of customer orders that arrive _ Consumption creates a static and binding assignment, between the planned independent requirements recorded in advance and the customer requirements that arrive, for the entire procurement process _ Consumption can lead to an increase of the originally planned overall production quantity 71. A customer wishes to only produce a finished product when customer orders for it are present. Final assembly should then be carried out at short notice in make-to-order production. Up until this point, the important assemblies needed in final assembly should already be available in stock. Provision of these assemblies should therefore be triggered by planning.
  • 24. Which options could you offer the customer as useful alternatives in SAP ECC? Note: There are 2 correct answers to this question _ The finished product uses strategy 20 (make-to-order production) and all the important assemblies in the bill of materials for the finished product should be have strategy 70 (planning at the assembly level) _ The finished product uses strategy 40 (planning with final assembly) and all the important assemblies in the bill of material for the finished product should have strategy 70 (planning at the assembly level) _ The finished product uses strategy 30 (production by lots) and all the important assemblies in the bill of material for the finished product should have strategy 70 (planning at the assembly level) _ The finished product uses strategy 50 (planning without final assembly) and all the assemblies in the bill of material for the finished product have no strategy. 72. When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling Which planning procedure would you use to process the problema in order to créate a solution that is feasible from a requirements planning perspective? • Total planning online • Multi-level single-item planning with the ‘simulation mode’ option • Multi-level single-item planning with the ‘display results before saving’ option • Interactive single-item planning for the delayed assembly 73. In the Customizing for requirements planning, a Project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type. What does a firming type define? Note: There are 2 correct answers to this question _ Handling existing procurement proposals within a planning time fence.
  • 25. _ Handling existing procurement proposals outside the planning time fence. _ Handling new procurement proposals that are to be created due to new requirements within the planning time fence. _ Handling new requirements within the planning time fence. 74. In the course of a customer project, you are confronted with an SAP ECC system that shows the error message displayed below when you test requirements planning in plant 1000. Large numbers of materials are already available in plant 1000. As a first step in solving the problem, you activate requirements planning in the Customizing for plant 1000. What further steps must you take before you can put requirements planning in plant 1000 into operation in SAP ECC? • Create a planning file in Customizing - Specify the plant parameters for plant 1000 in Customizing • Implement the planning files in Customizing - Specify the plant parameters for plant 1000 in Customizing • Implement theplanning files in Customizing - Specify the plant parameters for plant 1000 in the requirement planning views • Activate requirements planning in Customizing for MRP areas in plant 1000 – Specify the plant parameters for plant 1000 in the requirement planning views 75. An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon) The planning horizon is to be set equally for all materials by default However, some materials are to be given a different planning horizon. What procedure would you recommend to the project team for setting the planning horizon in the system side?
  • 26. _ The planning horizon is set in the MRP groups in Customizing and variant entries are assigned via the plant parameter settings _ The planning horizon is set in the plan parameters in Customizing and variant entries are stored in the material master for the materials in question. _ The planning horizon is set in customizing using the plant parameter setting and variant entries are assigned via the MRP groups for the material in question. _ The planning horizon is set in the MRP groups in customizing and the variant values are stored in the material master for the materials in question. 76. A material was planned in the context of SAP ECC material requirements planning and the MRP controller subsequently processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock requeriments list and the MRP list for this material and components two. Which of the following statements are true for the two lists at this stage? Note: There are 2 correct answers to this question _ The MRP list displays the production order _ The stock requirements list displays the production order _ The stock requirements list was updated at the precise time it was accessed _ The MRP list has the status “processed” 77. A project team member analyzes the following situation in SAP ECC in the stock /requirement list for a finished product: there is only one customer order and one fixed planned order with a similar quantity amount. The customer order and the planned order both have deadlines on work days but not on the same work day, the planned order has a later deadline. The project team member cannot find a rescheduling message referring to this deadline misalignment in the stock / requirement list. What reason could there be for the missing message? Note: There are 2 correct answers to this question _ Requirement planning has not yet been carried out to update the rescheduling message. _ The time misalignment falls within the tolerance window defined in Customizing _ The elements are linked to each other via fixed pegging. _ The requirement coverage element is outside the rescheduling horizon 78. In the SAP ECC system a material is produced with the help of production order. Though originally used for rate-based planning only, the planning table is to be used to plan this
  • 27. material. On the initial screen of the planning table you select this material and then receive a message informing you that cannot use the planning table for this material. Which of the following reasons for this message applies? _The is no valid production version for this material. _ the series production indicator has not been set _ There are no requirements present _ There are no planned orders or production orders present 79. An enterprise wants to absorb the uncertaintly caused by fluctuating demand for a finished product by means of a buffer variable in SAP ECC. They suggest a dynamic safety stock. What specifications are used tu calculate the dynamic safety stock? _The static safety stock per day and the safety time _The average daily demand and the desired days supply _ the static safety stock and a material forecast _ the average daily demand and the safety time. 80. In the course of a project phase, the customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system. Which of the following procurement type properties apply? Note: There are 2 correct answers to this question _If procurement type E (in-house production) is set, external procurement may still be permissible _ If both procurement types are allowed with entry X, requirements planning assumes in house production. _ Procurement types E (in-house production) and F (external procurement) have to be further refined with special procurements types. _ A material´s procurement type can always be freely selected between E (in-house production), F (external procurement) and X (both procurement types)