SlideShare a Scribd company logo
1 of 46
Download to read offline
WAREHOUSES - PROJECT TERMIK
Quito, Ecuador
By : BGH Group
Prakhar Gupta
Pia Emilia Bertero
Ziwei Hu
CE 8283
Risk Analysis
New York University
Fall 2016
2
Table of Contents
Part 1. Project Proposal
Introduction
Scope of Work
Design Quality
Cost Estimation
Schedule
Purpose of Risk Management Plan
Part 2. Risk Identification
Procedures
Risk Identification
Part 3: Risk Categories and Organization
Risk Categories and Preliminary Analysis
Influence Diagrams
Part 4. Qualitative and Quantitative Analysis
Part 5. Risk monitoring, Controlling and Reporting
1. Traffic accident
2. Cost increase
3. Policy changes
4. Accessibility
5. Leadership
6. Quality of construction materials
7. Rock bed found after certain depth
8. Contamination of Soil
9. Delay in water and electricity supply
Recommendations
Page
1
1
2
2
3
3
3
4
4
6
11
11
15
20
30
31
32
33
34
36
37
39
41
42
43
Figures
Figure 1. Photograph of the project location
Figure 2. Project Termik referential graph, and chart of areas
Figure 3. Project Termik Summary
Figure 4. Risk Categories of Project Termik
Figure 5. Link between a risk and the affected activities.
Figure 6. Parameters of cost/duration for activities on the schedule
Figure 7. Schedule with activities, cost, duration, start/finish dates
Figure 8. Objective of the quantitative risk analysis.
Figure 9. Distribution Graph of Duration (Without Risk)
Figure 10. Distribution Graph of Duration (With Risk)
Figure 11. Distribution Graph of Finish Date (Without Risk)
Figure 12. Distribution Graph of Finish Date (With Risk)
Figure 13. Distribution Analysis of Finish Date
Figure 14. Distribution Graph of Cost (Without Risk)
Figure 15. Distribution Graph of Cost (With Risk)
Figure 16. Distribution Analysis Graph of Cost
Figure 17. Tornado Cost Sensitivity
Figure 18. Distribution Analysis Graph of Cost before and after risk
Figure 19. Risk Mgmt. Process
Tables
Table 1. Risk Matrix with likelihood and impact
Table 2. Risk Categorization of Project Termik
Table 3. Risk Categories & Qualitative and Quantitative Analysis
Table 4. Probability scale, Impact and scale types, PID from Primavera
Table 5. Risk influence in the project
Table 6. Qualitative analysis with probability of occurrence of risks
Table 7. Quantitative analysis with probability/activities
Influence Diagrams
Influence Diagram 1. Construction and Design Influence Diagram
Influence Diagram 2. Environmental Risk Influence Diagram
Influence Diagram 3. Financial Risks Influence Diagram
Influence Diagram 4. Supply Risks Influence Diagram
Influence Diagram 5. Legal Risks Influence Diagram
Influence Diagram 6. PM Risks Influence Diagram
Influence Diagram 7. Safety Risks Influence Diagram
Page
1
2
11
12
20
20
21
21
24
24
25
25
26
27
27
28
28
29
30
5
13
14
14
15
22
33
16
17
17
18
18
19
19
1
Part 1. Project Proposal
Introduction
Ecuador is a country that uses US dollars and because of it, it's expensive to produce finished
goods. Consequently, commerce is a practiced activity. Importing goods, storage and selling
those products consist an important part of the economy.
The project is located within a residential/industrial zone of the northeast part of Quito,
Ecuador. By being so close to the city and having many different routes to the center and
southern part of Quito, this piece of land is well located for its purpose.
The project is connected to Quito international airport by a recently built highway (dist. 9km
approx.) and many other highways that allow an easy transportation of goods, not only to the
entire city but to smaller cities and the countryside surrounding it.
Site Location
Figure 1. Photograph of the project location Lat: -0.102784 Lon: -78.443866, Google Maps
2
Scope of Work
This project is intended to satisfy storage needs for small and medium businesses. The idea is to
build 14 warehouses in the northeast of the capital, Quito. The space is designed to store goods
of different nature until they reach a final destination. Construction will be broken down into
consecutive phases like: site preparations and permits, land movement and excavation for
foundations, construction of metallic superstructure, Mechanical Electrical and Plumbing (MEP)
Rough-in and interior finishes.
Design Quality
The Project is designed to satisfy the requirement to store finish products for small and medium
businesses until they are delivered to other locations.
Figure 2. Project Termik referential graph, and chart of areas
3
Cost Estimation
We have estimated that the total cost would be around 5.1 million USD, divided into this
phases:
● Preliminary work - $138,351
● Excavation - $485,110
● Walls and sub structural works – $1,500,000
● Metallic Structure – $1,090,000
● Finishing Work – $950,000
● Exterior Work, Other Utilities, Water and Electricity supply – $1,170,000
Schedule
We anticipate the construction will take 14 – 16 months. This estimated schedule will depend
upon the anticipated risk within the projected. We have allocated 6 months for the excavation
and substructure. The other 6 months for the superstructure and the rest of the work is
allocated for 3 months.
Purpose of Risk Management Plan
Understanding all potential risks before the construction starts will help the project team better
prepare itself to go forward successfully. If one of those risk scenarios threatens the project
execution, the team will be prepared and have some mitigation plan to deal with all possible
outcomes.
Our goal is to identify those risks and understand the magnitude they could have and calculate
or determine possible losses. Also, to develop a plan or strategies to deal with them. We are
going to use both quantitative and qualitative analysis techniques to develop an understanding
of the effects of those risks to our project success.
Also with the help of Primavera, a software that will allow us to better plan the project
schedule, manage risks and their influence in the project, we could check if the duration of the
project, the cost and the end date will change once we enter the risks.
4
Part 2. Risk Identification
Procedures:
1. Risk Identification: Through analyzing the concept of operations we can identify
possible risks in every stage of the project by simulating realistic undesirable scenarios.
And we can understand things that can possibly go wrong and how could it effect in the
project.
2. Impact and likelihood: Once we have identified the risks, we can predict how likely is
that risk going to happen. The impact will be calculated by the severity of the losses or
consequences each risk may cause. The likelihood will make us understand the
probability or frequency of that scenario.
3. Risk Assessment: The combination of both impact and likelihood of each risk will help to
understand the project vulnerabilities through Qualitative and Quantitative analysis. It
will also help to decide which risks should be prioritized.
4. Mitigation: For every risk, we can develop a plan to prevent and mitigate every situation
that has been formulated, so we are prepared for the best and worst case scenarios.
5. Identification of Hazards: Physical situations with a potential of an undesirable loss or
consequence will be analyzed. In this case the proper personal protection equipment
will be taken into consideration for hazards and will be inside the risk of personnel
safety. For the construction of the warehouses, it's expected to have mechanical,
thermal, chemical, electrical and information hazards.
6. Risk Management: It's a continuously asses of risk related to uncertainties. It's a
constant practice to prevent, control and minimize losses due to risk exposure. We can
make a plan of action towards management this risks. But risk management will occur
during construction.
5
7. Risk Communication: Communicate possible hazards and ways of procedure against
diverse risks would be a perfect way to prevent losses or consequences. Stakeholders
must be aware of all possible risks and uncertainties, so the process it's inclusive and has
different points of view.
Risk Matrix
# Risk
Consequences or Losses
Likelihood Impact
Environmental Social Budget Schedule Quality
1 Contamination of soil x x x Medium High
2 Rock bed found after certain depth x x Low High
3 Delay in water and electricity supply x x x Medium Medium
4 Delay in Supply of Materials x x High Medium
5 Fail of Formwork during the casting of the concrete x x x x Low High
6 Mismatch of steel structure during erection x x x Low High
7 Slips, Trips and Falls x x x Medium Low
8 Fail of the Object x x x x Low Low
9 Bad weather x x x x Medium Medium
10 Dispute Between Labor Union and management x x x Medium High
11 Political Instability (Change of LAW) x x Medium High
12 Accessibility x x Medium Medium
13 Community protests x Low High
14 Permits x Medium High
15 Insecurity x x x High Medium
16 Corruption x x x Medium Low
17 Environment (DUST) x x High Low
18 Quality of Construction Materials x Medium Medium
19 Leadership x x x x Medium High
20 Material Shortage x x Medium Medium
21 Natural disaster x x Low High
22 Traffic accidents x x Low Low
23 Cost increase x Medium High
24 Policy Change x x High High
25 Lack of workers x x High Medium
26 Personnel Safety x Medium High
27 Equipment Malfunction x Low Medium
28 Currency and Exchange Rate x x x Medium High
29 Inexperience x x x x Medium High
30 Fire Hazards x x x Low High
Table 1. Risk Matrix with likelihood and impact
6
Risk Identification
1. Contamination of soil
Cause – Site located at an industrial area there is a high probability of contamination of soil.
Effect – May have to dig deeper than it is designed for the construction of foundation or will
require to backfill compact soil to provide strong base to the foundation
2. Rock bed found after certain depth
Cause – Possibility of rock bed after certain depth
Effect – It will require rock cutting machine and other Machineries. It will also require extra
labors and man hours which will affect the cost and will delay the schedule estimated for the
excavation of the site
3. Delay in water and electricity supply
Cause – As supply is been given by the government, it has possibility we may not get supply in
time .
Effect – It will delay concrete construction work, as the concrete requires high amount of curing
at initial stage.
4. Delay in supply of materials
Cause – Due to bottlenecks and congestion in the traffic it has high possibility of delay in the
supply if the materials.
Effect – It can affect other work and increase the labor and machinery cost as well.
5. Fail of Formwork During the Casting of the concrete
Cause – Formwork could fail to carry the load of the concrete due week support and tie with
each other.
Effect – May cause serious damage to the worker and laborers. It will also lead to wastage of
material and ultimately to the cost. In a very serious case it may suspend the work for few days.
7
6. Mismatch of Steel Structure During Erection
Cause – Since it is steel structure, fabrication is being done at specific are and then it is brought
to the site. Which may lead to a mismatch during erection.
Effect – Wastage of the material and will suspend work for few hours or a day. And will require
to redesign the parts.
7. Slips, Trips and Falls
Cause – Since it is a steel structure and labors will be working at some heights.
Effect – Fatal accident of labors.
8. Fail of the Object
Cause - Improper designing of the structural if not take properly, Cheap quality used for
construction.
Effect - Serious accident and wastage of material and man hours.
9. Bad weather
Cause – Due to heavy rain work may suspend for a day or two.
Effect – Suspend work for a day to weeks which will delay the construction work and may
damage the material exposed to weather.
10. Dispute Between Labor Union and management
Cause – Improper behavior of management, could happen related to wage or could be
regarding safety.
Effect – Unknown delays in construction schedule, which may affect the cost.
11. Cash Flow Interruptions
Cause- The government is known for its radical behavior in terms of creating new laws, that can
create panic and stop investment.
Effect - Cash flow could be affected; therefore, the initiation of the construction could be
delayed or construction could be paralyzed. It can also make stakeholders to doubt the extent
of the project, the investment, etc.
8
12. Accessibility
Cause – The street to access the site of construction is always congested due to a vehicular
revision that is located next to the project. This place has a queue of cars waiting to be checked
out.
Effect – Trucks with materials, machinery, big trucks and other vehicles accessing the site can
be obstructed because of these phenomena, delaying the delivery of materials and or services
needed to proceed with the project.
13. Community protests
Cause – Since the location of the project is in a industrial/residential zone, the resident
neighbors could have complaints about noise, contamination, traffic, road blocks, etc.
Effect – There could be complaints from the residents of the area regarding the issues that a
construction of that extent can cause. At the end the project can be delayed or even stopped.
14. Permits
Cause – Construction and environmental permits need to be obtained.
Effect- Permits don’t have an specific time of processing. Sometime they can take weeks or
even months. Bureaucracy and a fast personnel shift in the office that give the permits often
causes delays and time uncertainty. Delays in the construction can be serious.
15. Insecurity
Cause – The area is catalogued as a dangerous area where a lot of robberies occur. Expensive
equipment and material can be targeted by thieves.
Effect – The construction can be delayed because even if the materials or machinery have
insurance the reposition will take time and money. The cost of the project could go up. Workers
can feel threatened and the community surrounding the area.
16. Corruption
Cause – Corruption is a common practice in the construction area of Ecuador's market.
Effect – Obtaining permits and keeping them can be affected by corruption. In many cases a
payment is requested by local authorities that can threaten to close the project.
9
17. Environment (DUST)
Cause – Since the location of the project is close to the Ecuador, sun is strong and makes the
land to be dry. Wind can spread dust in the early stages (excavation and soil movement,
replacement, etc.).
Effect – Dust can affect the families and overall community that live close by, making people
uncomfortable, affecting local businesses and the environment.
18. Quality of Construction Materials
Cause – There is a market of materials of low quality that often lie about strength of materials
or other properties.
Effect – The quality of the material defines the overall quality of the project as well. So if the
quality does not match with the design, financial loss and delays can happen.
19. Leadership
Cause – Lack of a proper management skills (PM) during design and construction
Effect – Delays, a faulty schedule, cost increase and lack of coordination can be the result of a
bad project management.
20. Material Shortage
Cause – Lack of material in the market.
Effect – A shortage in materials can stop the project completely or delay some phases of it. That
can produce losses, increase the cost of the project and overrule the project schedule.
21. Natural disaster
Cause - Some natural disaster such as flood and earthquake. Effect - They may destroy the
construction and equipment. In addition, it may cause huge finical loss and make workers
injured.
22. Traffic accident
Cause - When transfer some supplies or equipment, some traffic accidents may happen.
Effect - Financial loss, loss of life and personal injury.
10
23. Cost increase
Cause - rising price, economic crisis.
Effect - budget increase, lack of enough money.
24. Policies change
Cause - Industry laws and regulation revise.
Effect - Influence the design and actions, may cause schedule delay.
25. Lack of workers
Cause - Working prospect and salary are lack of attraction, during festivals and holidays.
Effect - Schedule delay.
26. Personal safety
Cause - Incorrect operation process, poor equipment, poor security.
Effect - Financial loss, loss of life and personal injury, compensation, schedule delay, bad
reputation.
27. Equipment malfunctions
Cause - Being used for long time, lack of maintenance, operate incorrectly.
Effect - Schedule delay, financial loss, personal injury.
28. Currency and exchange rate
Cause - Economic crisis.
Effect - Budget is not enough.
29. Inexperience
Cause - Green hands.
Effect - Schedule delay, unnecessary financial loss.
30. Fire
Cause - Smoking, equipment overheats.
Effect - Schedule delay, financial loss, personal injury, bad reputation.
11
Part 3: Risk Categories and Organization
Project Termik
Figure 3. Project Termik Summary
Risk Categories and Preliminary Analysis
There are many ways in which we can categorize risk. Different disciplines use terms like
hazards or risk exposures. Categorization can be done by analyzing the causes of a risk or its
nature of consequence and in some cases of both.
The losses can be ultimately measured in economic terms that can affect a determined project.
In most situation before measuring the risk in terms of loss, we can categorize them in five
broad categories of risks: health, safety, security, financial and environmental. There are often
interrelations between those categories, but its prime nature should be reflected in only one.
For example, a health risk may later lead to financial loss but that doesn't mean it should be
considered as financial risk.
12
For this project, we have developed our own categories for risk. To organize them better we
have divided risks considering their nature and causes, in the following categories: project
management, supply, legal, environment, construction & design, safety and financial (Figure 4).
Most of the risks of Project Termik are in the project management category and it makes sense
because that discipline will rule in the success of the project, being present in all the project
lifecycle, we could see that in table 2.
Figure 4. Risk Categories of Project Termik
13
# Risk
RISK CATEGORIES
C&D Safety PM Enviro. Legal Supply Financial
1 Contamination of soil x
2 Rock bed found after certain depth x
3 Delay in water and electricity supply x
4 Delay in Supply of Materials x
5 Fail of Formwork during casting of concrete x
6 Mismatch of steel structure during erection x
7 Slips, Trips and Falls x
8 Misconception of Design x
9 Bad weather x
10 Dispute Between Labor Union and management x
11 Political Instability x
12 Accessibility x
13 Community protests x
14 Permits x
15 Insecurity x
16 Corruption x x
17 Environment (DUST) x
18 Quality of Construction Materials x
19 Leadership x
20 Material Shortage x
21 Natural disaster x
22 Traffic accidents x
23 Cost increase x
24 Policy Change x
25 Lack of workers x
26 Personnel Safety x
27 Equipment Malfunction x
28 Currency and Exchange Rate x
29 Inexperience x
30 Fire Hazards x
Table 2. Risk Categorization of Project Termik
After separating the risk in categories, we also grade them according to their likelihood and
impact in the project in a qualitative and quantitative way.
14
Table 3. Risk Categories & Qualitative and Quantitative Analysis
Once we established the categories and know the potential likelihood/impact of each risk, we
proceed to put this information into Primavera for further analysis, like we see in table 4 and 5.
Table 4. Probability scale, Impact and scale types, PID from Primavera
15
Table 5. Risk influence in the project
As a result of the primavera analysis, we can see that some risks are not so influential in our
project, like traffic accidents or dust formations during the project (table 4). Many other risks in
the yellow area could influence the project in a medium way and most of the risks have a great
influence in the project. This could be explained by the fact that most of the project activities
are extensive and expensive, so any alteration in cost or schedule will have a high or very high
influence in the project.
Influence Diagrams
For further analysis, we have created influence diagrams so we can see each risk in all seven
categories and their area of influence. The objective of creating these influence diagrams is to
give the viewer a clear idea of the risks inside a category and the area of influence this risk may
have. We achieve that through a dynamic graphic that proposes inputs and outputs.
The influence diagram can help us see how a group of risks will affect more or less areas than
other groups. In the red circles we have the inputs (risks) then in green we have the area of
focus in which those risks will take place, and finally in a blue diamond the possible outcomes
16
that the risks may cause or the variables of the project that can be impacted. So, for this part
we will have 7 influence diagrams since we have categorized our risk into 7 categories.
For example, legal risks in influence diagram 5 have influence in only one area as an output, the
schedule. Other categories like in influence diagram 7 were we can see safety risks, can result
affecting several areas like quality of construction, cost and schedule and project success.
Other factors could also intervene in determining which risk would we rather have in our
project than only the areas of influence. Priorities of each project are different and can alter the
way we interpret the results and view risks.
Construction and Design Risks:
Influence Diagram 1. Construction and Design Influence Diagram
17
Environmental Risks:
Influence Diagram 2. Environmental Risk Influence Diagram
Financial Risks:
Influence Diagram 3. Financial Risks Influence Diagram
18
Supply Risks:
Influence Diagram 4. Supply Risks Influence Diagram
Legal Risks:
Influence Diagram 5. Legal Risks Influence Diagram
19
Project Management Risks:
Influence Diagram 6. PM Risks Influence Diagram
Safety Risks:
Influence Diagram 7. Safety Risks Influence Diagram
20
Part 4. Qualitative and Quantitative Analysis
So far, we have we have found 30 possible risks that could affect our project. We categorized
those risks into seven categories: Supply, Financial, Construction & Design Risks, Environmental
Project Management, Legal and Safety. We performed already a qualitative analysis by putting
the likelihood and the impacts of each risk (Tables 4,5). Then we analyzed the influence of each
risk in the project.
For part 4, the qualitative analysis will include a link between each risk to the activities that it
influences in the primavera schedule (figure 5). This will help us to relate each risk with the
possible activities it may affect. So, results of the qualitative analysis could change and also, we
can get out a quantitative analysis as well.
Example:
Figure 5. Link between a risk and the affected activities
The probability of each risk will be taken from the qualitative analysis that we entered in
primavera (figure 5). We will run the risk analysis with a complete schedule for the project,
entering parameters of cost and duration for each activity (figure 6). The schedule this time will
have to include every single activity in the project, its duration and follow a sequence (figure 7).
Example:
Figure 6. Parameters of cost and duration for each activity on the schedule
21
Figure 7. Schedule with activities, cost, duration, sequence and start/finish dates
It's important to say that after completing the sequence of every activity of the project in
Primavera, the schedule of the project changed to 18 months approximately, more than
speculated at the beginning (14-16 months).
After running the risk analysis with the new linked activities/risk we can obtain results that will
tell us how the risks will affect the project. We will do the analysis by comparing results of the
duration, cost and finish date that the analysis will give us. One set of results will include the
risks linked to the activities and the other will not (Figure 8).
Figure 8. Objective of the quantitative risk analysis
First, having performed a qualitative analysis that can be seen in table 4 and 5, we get a
probability scale, Impact and scale types and the risk influence in the project. That probability
22
scale shown also in table 6, tells us the ID for each risk, the description a score based on the
inputs we put before, those are likelihood and impact. The probability of each risk now will be
used in the qualitative analysis once que link the risks to each activity.
Table 6. Qualitative analysis with probability of occurrence of risks
In table 7 we can see the same risks we introduced in primavera before, but now we have
linked each risk to every activity or task in the schedule that will be influenced by it. The
probability of occurrence is also there and we have chosen a pre-mitigated phase, since we
have not yet taken actions over the risks.
23
Table 7. Quantitative analysis with probability of risks/activities
After we do this, the next step in Primavera is to run the risk analysis again, and see how this
new results (pre-mitigated) vary from the ones we got before the risks were a variable. In
figures 9 and 10 we can see results for duration of the project with and without risk. According
to the statistics, the mean or expected value of duration for the project is 643 days. The range
in which the project could finish goes from 564 and 698 days, leaving a window of 134 days.
When we input the risks, the mean is 673 days, 30 days or a month more than the results we
got before.
24
Figure 9. Distribution Graph of Duration (Without Risk)
Figure 10. Distribution Graph of Duration (With Risk)
The range goes from 590 to 769 days, so the window has increased with risks from 134 to 179
days. We can say confidently by watching this results, that there is more uncertainty in the
25
duration now that we put the risks in the mix. Figures 11 and 12 are the results for finish date,
they vary in the same proportion of duration since they are directly related, an increased
duration will change the finish date. The mean will vary a month from 26/07/18 to 26/08/18.
Figure 11. Distribution Graph of Finish Date (Without Risk)
Figure 12. Distribution Graph of Finish Date (With Risk)
26
If we see the analysis graph in figure 13 and we choose 90% of probability of results, we get
that end date with risks will be most likely 28/09/18 and without risks 31/08/18, a month apart.
That will gave the project a duration of almost two years with risk.
Figure 13. Distribution Analysis of Finish Date
As for the cost, we can see in figures 14 and 16 the results for the plan cost without and with
risks respectively. The mean cost without risk is USD 5,900,260.00 and with risk USD
8,425,570.00. The variation between both is of USD 2,525,310.00, almost 43% more than the
initial budget without risk input. Range from figure 14 is from minimum amount to maximum
goes from USD 5,365,198.00 to USD 6,254,651.00, having a window of almost a million dollars.
In figure 15 we can see that the range goes from USD 6,441,676.00 to USD 11,564,521.00,
having a huge window of 5,092,345.00.
In this variable, cost, we can see how influential risk could be if no actions are taken to reduce
it, prevent it, control it or mitigate it. Like we see in the analysis in table 16 the difference of
cost with and without risks is much more defined than in the other variables.
27
Figure 14. Distribution Graph of Cost (Without Risk)
Figure 15. Distribution Graph of Cost (With Risk)
28
Figure 16. Distribution Analysis Graph of Cost
If we see the analysis graph in figure 16 and we choose 90% of probability of results, we get
that end cost with risks will be most likely USD 9,601,560.00 and without risks USD
6,074,766.00, almost 3 million dollars apart.
The costs that are most influential to the project now that the risks have been inserted in
Primavera are shown in figure 17, with a percental value.
Figure 17. Tornado Cost Sensitivity
29
A summary of all the results can be seen in figure 18, for calculations of before and after risk
has been added to the risk analysis calculations in Primavera.
Figure 18. Distribution Analysis Graph of Cost before and after risk
The numbers and variations of finish dates, durations and mostly cost, only confirm that risks
cannot be taken lightly because they have a major influence in the project. If the risks are not
monitored and controlled or mitigated; they could not only delay the finish date, but increase
the cost in a dramatic way. The project has to consider risks in overall planning or further down
the road the worst-case scenario could be catastrophic. The objective now is to elaborate a
mitigation strategy for each risk to prevent these developments to take place.
30
Part 5. Risk monitoring, Controlling and Reporting
So far, we have identified risks for project Termik, we have assessed those risks and ranked
them in a qualitative and quantitative way. Like we mentioned after the quantitative analysis,
the project has to consider risks in overall planning or further down the road the worst-case
scenario could be catastrophic. In this part, we will talk about monitoring those risks and
managing them with mitigation, control and reporting strategies (figure 19). Also, we will
identify stakeholders involved in the process.
We will propose these strategies to manage 9 of the 30 risks we identified before, these nine
risks are:
1. Traffic accident
2. Cost increase
3. Policy changes
4. Accessibility
5. Leadership
6. Quality of construction materials
7. Rock bed found after certain depth
8. Contamination of Soil
9. Delay in water and electricity supply Figure 19. Risk Mgmt. Process
For these nine risks, we will be explaining the way we can monitor them, control them and how
this risks should be communicated and reported. The objective is to elaborate a mitigation
strategy to prevent these developments to take place. The mitigation and controlling strategies
should cost less or have benefits that represent more than the possible impact of that risk. Also,
after these control and mitigation strategies will be implemented, they will diminish project
vulnerabilities.
31
1. Traffic accident
In our project, during the transportation of some materials, accidents may happen. Accidents
can be caused by many kinds of reasons, such as bad traffic condition, bad weather and
irresponsible driving. Once an accident has happened, it will increase our cost and it will be a
cause of delay. Therefore, we should do the preparation and mitigation.
Risk Monitoring
a. Surrounding traffic condition: On some special type of highway such as curve highway
sections, traffic accidents are easier to happen. Drivers should pay attention to these
accident black spots.
b. Driver management: Fatigue driving, drunk driving, new drivers are the possible reasons
leading to traffic accidents. Therefore, we should improve the management of drivers.
c. Bad weather: Traffic accidents are easier to happen with bad weather. So, we should
decrease the transportation in bad weather.
d. Breaking traffic regulations: Breaking traffic regulations such as overloading may lead to
traffic accidents. Therefore, we should strengthen the management of drivers.
Risk Controlling / Mitigation
a. Hire experienced drivers.
b. Strengthen management of drivers, improve the safety consciousness of drivers.
c. Pay attention to traffic and weather condition. Try to avoid transportation in bad
weather.
d. Provide accidents insurance.
Risk reporting / Communication
a. Provide road and traffic condition to drivers.
b. Provide weather condition to drivers.
c. Safety training.
d. Accidents insurance.
32
Stakeholders
a. Driver
b. Insurance Company
c. Project Administration
d. Project manager
2. Cost increase
Because of the changing financial condition, cost may be increasing. Wrong decision making,
changing of the relationship between supply and demand, economic crisis can also lead to cost
increasing. It will influence the project investment and even cause the schedule delay.
Therefore, we should pay attention to the marketing situation and do the adjustment of project
cost in time.
Risk monitoring
a. Schedule delay: Schedule delay may cause the cost increasing. So, management of
schedule is important.
b. Supply and demand in market: Changes of the relationship between supply and demand
in market may influence the price of materials in the project. Purchasing materials in
time or in advance can lower this risk.
c. Financial crisis: The risk of financial crisis is very low.
d. Decision making: Before purchasing materials and concluding a contract, decision maker
should do the research and comparison.
Risk Controlling / Mitigation
a. Pay attention to international and domestic finance situation.
b. Purchasing materials in advance, with a contract that establishes cost.
c. Management of schedule. Complete the schedule on time.
33
Risk Reporting / Communication
a. Do the marketing research before making decisions.
b. Provide report of increasing cost if schedule was delay.
Stakeholders
a. Supply manager
b. Project manager
c. Customer
3. Policy change
Policy change is not easy to happen, but once it does, it will have big impacts on the process of
the project. We should do the preview and prepare alternatives.
Risk Monitoring
a. Industry laws and regulation revise: Some industry laws and regulation revising may
influence the completion of the project. Therefore, we should pay attention to the
regulation situation and do the preparation.
Risk Controlling / Mitigation
a. Pay attention the policy and possible changes.
b. Preview of policy changing.
c. Prepare alternatives in advance to face the policy change.
d. Adjust the project in time according to the new policy.
Risk Reporting / Communication
a. Provide report of domestic policy and possible changing during project.
b. Provide emergency plan.
c. Provide the report of loss leading by policy changing.
34
Stakeholders
a. Construction manager
b. Project manager
4. Accessibility
After evaluating possible vulnerabilities of Project Termik, Accessibility showed possible results
for risk. Due to a high volume of vehicles that park and wait for revision in a center that it's next
to project Termik, congestion and delays may be created, making accessibility difficult for
vehicles to the project's location. Also, it's worth to mention that the street which provides
access to project Termik is a two-way street, so transit of bigger vehicles like trucks may be
more difficult than expected. For this reason, constant monitoring of the accessibility situation
must be provided, so that vehicles that wait for the revision next to the project may be
relocated or leave a certain amount of distance to make easier the circulation of vehicles,
especially during construction. Controlling this risk can also avoid complaints that could, in a
worst-case scenario, stop the activities of construction.
Risk Monitoring
a. Provide personnel to monitor parked vehicles outside and manage them in an organized
matter. These personnel may also help pedestrians to circulate safely and provide any
assistance or information necessary.
b. Talk to possible stakeholders and open a channel of communication to keep everybody
informed about any situation (Neighbors, residents, police, traffic management
authorities, project management).
c. Provide a journal so that activities are monitored by personnel at the entrance, to check
all vehicles in and out the premises with information about their activity. Also, they can
monitor delays, schedules, etc.
Risk Controlling / Mitigation
a. The entrance to project Termik must have correct signalization. No parking signals, red
cones if necessary or any signalization preventing for delays to happen. These signals
35
will also sum organization and safety to personnel and people in the surrounding area.
b. Getting to certain agreements with stakeholders will be another way to control
unnecessary complaints, traffic jams and delays at the access point. For example: a
schedule of incoming and going vehicles can be created.
c. Journals kept by personnel in the entrance will be a good tool to control the existence of
delays or problems with accessibility. This reports will be analyzed by the administration
of the project, so any decision can be taken.
d. A fine or penalty system may be created with material providers and contractor so they
follow a certain schedule. This will maintain the order of coming and going vehicles
towards the project's location.
e. Constant reunions and communication with stakeholders involved in the topic may be
necessary. Creating an agreement to organize traffic flow in the street of access is a
priority.
Risk Reporting / Communication
a. Journals and reports of the access activity must be kept by personnel in charge.
b. Schedule noncompliance by any contractor or material provider must be properly
documented and notify to management of the project. This way the administration can
inform each company about fines.
Stakeholders
a. Personnel in charge
b. Project Management
c. Neighbors
d. Transit Authorities
e. Residents
36
5. Leadership
A risk in leadership is a tricky business. It’s hard to point the exact flaws in leadership and in
many cases, it's easy to identify by performance. Even though it's not a concrete science, there
are ways to manage the risk leaving uncertainty aside. A thorough hiring process for the right
candidates is often the way to go.
Risk Monitoring
a. The project Manager will oversee monitoring and assessing the leadership and decision
making skills of his/her team.
b. A proper report of complaints from personnel towards a member of the projects
administration, management or towards any problem within the project shall be kept.
This will help monitor areas that need more control and identify the person that is in
charge of that area.
c. Change orders with justifications must be provided. Monitoring compliance of the
construction rules and procedures must be done.
d. Weekly meetings between all management staff to monitor compliance with schedule,
cost and performance, will help to identify areas in trouble with possible lack of
leadership.
e. Weekly meetings with management and stakeholders for feedback, organizing work and
taking decisions.
Risk Controlling / Mitigation
a. Evaluate performance of each member of the management team and communicate to
them the areas that need improvement. All monitoring techniques will help in
developing an evaluation on performance.
b. Create daily journals so that any member of management can write important events of
the day, possible change orders with justification, weather situation, or any decision
taken during that day.
c. Create a good channel of communication or a system in which all members of the
management team can be informed of current information.
37
d. Prepare the personnel for different work scenarios with trainings and courses that
encourage a best practice of leadership
e. Hire personnel with experience and knowledge in the area, that have skills desired in a
good leader (always thru a HR office or external HR party).
Risk Reports / Communication
a. All the reports of complaints towards management personnel or in certain areas of work
shall be provided weekly.
b. A summary of every meeting should be prepared weekly so that record of any decision
or action can be evaluated.
c. The PM will oversee communicating with his/her personnel weekly to report any risk in
management.
d. Documentation of any change order shall be provided with a responsible signature.
Stakeholders
a. Project Management
b. Project Administration
c. Human Resources
d. Customer
6. Quality of construction materials
Quality of materials determine the quality of the end product. In this case, we want to make
sure that every material used to build Project Termik complies with specifications provided in
the design. It’s best to hire a third party that has expertise in the area, and share the
responsibility with them. This action will also facilitate the work of project management,
because they will have one less thing to worry about. Nonetheless, they will still be involved in
important decision making.
Risk Monitoring
a. Before hiring any material supplier, the evaluation of credential and compliance with
38
regulations must be in order.
b. Product quality reassured by an international regulator or certified laboratory. It
depends on the quality that the customer wants.
c. Regular reports of the material entering the project with documentation.
d. For some materials, the need to hire a laboratory to test materials will be needed. For
example, for concrete, a cylinder testing must be done to monitor the quality of the
materials. Also, record of the origin of other materials used (water, sand, rocks,
additives, etc.).
e. Supervision that shall provide a quality check (Quality Management)
Risk Controlling / Mitigation
a. Compare quality between at least three providers of the material, and choose one with
desired quality that has more benefits over cost. It will help if the provider was also
close to the site.
b. Contracts with suppliers that have specifications of desired quality of materials must be
established before the construction.
c. Contract with a third party that can guide in assuring to keep the quality of materials on
site (adequate storage) and that can perform a quality check of the materials is
necessary.
d. Follow manufacturer's suggested procedures on handling materials. Or follow standards
of construction for different activities. For example, in Ecuador there is a Norm for
Construction (NEC).
e. Buy only materials that comply with specifications from the design.
f. Any additional test result obtain from material testing should be approved or rejected
with justification by supervision and project management.
Risk Reports / Communication
a. Quality management should have a daily journal with activities and documentation
related to quality of materials that arrive to the site and also for materials stored.
b. Proper channel of communication and reporting should be implied between project
39
management and the quality management or supervision.
c. Test results obtain from material testing with approval should be available for all
management personnel to read. Risks can be reported in them.
Stakeholders
a. Suppliers
b. Supply manager
c. Project management
d. Transportation company
e. Supervision Personnel and/or Quality manager
7. Contamination of Soil
Soil is the most important for designing foundation and it needs to well compacted. Excavation
is the first most important step in the construction. If the soil is contaminated then we have to
perform test, hire 3rd party environmental agency to make remove the top soil till we get the
natural compact soil and we have to take other measures to provide solid base to the structure.
Risk Monitoring
a. Potential Areas of Soil Contamination: Usually contamination of soil takes place at the
potential areas like Industrial sites, Near Oil Refineries, Petrol Station, and where there
is Spill of chemicals.
b. Percentage of the chemicals in the soil: If there is any industry situated nearby the site
then there is a high probability the soil can contain high number of chemicals.
c. Site survey: Site survey should be done at certain period because it will help to
understand the structure of the soil and if there are any Large cracks formation found at
the site, it may result into soil contamination. Data Analysis methods could be used by
Hierarchical cluster analysis (HCA) and principal components analysis (PCA), and can
interpret the Quality of the soil.
d. Settlement of soil: We can track the rate of settlement of the soil which could happen if
the soil is loose. Settlement might be the result of soil contamination
40
e. Soil strength/ soil bearing capacity: Examination of soil strength would help us to
understand the soil compaction and soil bearing capacity and it will also help to design
the foundation as well.
Risk Controlling / Mitigation
a. Soil testing should be done prior to the excavation.
b. Hire 3rd party environmental agency for site remediation as it regulates the procedures.
c. If soil is too loose then provide change order in the design for the use of piles and
foundation.
d. We can rent machineries and increase the number of labors to remove the
contaminated soil within time period.
e. Rent pumps to remove water from the excavation area if the water table is high at the
construction site.
f. At the same time we can order the supply of material of the backfill to make the base
more compacted for the foundation
Risk Reports / Communication
a. We have to Make proper soil testing reports well before designing of the foundation.
b. Site Survey and reports should be done properly
c. Sufficient supply of materials and machineries should be provided to the construction
site.
Stakeholders
a. Project Manager
b. 3rd Party Environmental Agency
c. Site Surveyors
d. Site Engineer
e. Soil Testing Laboratories
41
8. Rock bed found after certain depth
Rock beds are usually good for the foundation, and it’s usually found in the hilly areas.
However, it’s very hard to excavate and time consuming. Rock bed can be found by performing
geotechnical survey. If there is any error or if the rock bed is not even, then we have to perform
excavation work with heavy machineries which will consume time and require money.
Risk Monitoring
a. Geotechnical tracking or electromagnetic / Ultrasonic testing of the site.
b. To monitor this risk, we can perform the geotechnical report and Electromagnetic
testing/ ultrasonic testing of the site for the rock structures. If there is any, we can find
out the depth of the rock and the locations of the rock bed at the construction site.
Risk Controlling / Mitigation
a. Geotechnical report should be taken well in advance; accordingly, we can ask for more
labor and rock cutting machinery.
b. If there is any error in geotechnical report and we find any unexpected rock bed then, to
Control this risk we can rent rock cutting machineries and can increase the number of
laborers, which will accelerate the excavation at the site and would help the get work
done within the scheduled period. Also it may affect the design of the building, so If it is
required, we can ask for change order with in the design as soon as we find the rock
bed.
Reports / Communication
a. Geotechnical report should be done properly and Details should be given properly to
the Project manager.
b. Reports should be provided to the designers and change orders should be given with the
updated report of the site.
Stakeholders
a. Geotechnical Surveyors
b. Geotechnical Engineers
42
c. Equipment operator
d. Project Manager
e. Designers
9. Delay in water and electricity supply
Water and electricity is the most important and is required right from the beginning of the
construction. We require water for curing, preparing concrete etc and Electricity to operate
heavy electric machineries. If we don’t get supply within time then we have to arrange from
external sources like private companies.
Risk Monitoring
a. We must keep the track of permission of supply of water and electricity.
b. Make proper coordination and communication regularly with the supplier. And we have
to Make sure the supply to be provided to construction site take place well before
construction work starts, for ex. 2-3 weeks before
c. Make Proper check of the pipelines, if there is any problem there could be delay in work
Risk Controlling / Mitigation
a. We can ask for electricity from private company or use commercial generators and
invertors, if there is any delay in electricity supply. Order for filled tankers prior to the
construction work. Also Project Manager has arranged for Water storage by preparing
reservoir well in advance near construction site. Make proper contact the supplier or
the govt if they are supplying the water and electricity.
Reports / Communication
a. Make sure the supply to be take place well before construction work, for ex. 2-3 weeks
before.
b. Make proper contact the supplier or the govt if they are supplying the water and
electricity.
43
Stakeholders
a. Government Agencies
b. Private Suppliers
c. Project Managers
d. Contractors
e. Machinery suppliers
Recommendations:
A deeper analysis should be done for all the risks found in Project Termik. Controlling
techniques that can be implemented from the beginning of the project could save money and
prevent delays. Constant monitoring of the project will allow to find deviations from cost,
schedule, risks and quality, allowing management the chance to control and mitigate them in
an early base. Report and communication techniques are very important to help project
management to be informed about any relevant situation in the project that requires to
manage risk with established procedures or by new decisions. Project management will be in
charge of dealing with stakeholders to lower risks and keep the expected performance in
schedule, cost, quality and risk management.
All the information of the risk analysis and procedures needed to handle risks should be written
down in a Risk Management Plan, that will contain information on procedures, assumptions,
examples of reports and techniques used throughout project development, and every
document, guide or procedure related to monitoring, controlling, mitigating, reporting and
communicating risk.

More Related Content

Viewers also liked

What's trending? The Latest Trends in Social For Hospitality
What's trending? The Latest Trends in Social For HospitalityWhat's trending? The Latest Trends in Social For Hospitality
What's trending? The Latest Trends in Social For HospitalityElizabeth Harvey
 
Application Integration with XProc
Application Integration with XProcApplication Integration with XProc
Application Integration with XProcVojtech Toman
 
[학생발표]십자성마을_2020에너지자립비전및계획_2014SEL포럼
[학생발표]십자성마을_2020에너지자립비전및계획_2014SEL포럼[학생발표]십자성마을_2020에너지자립비전및계획_2014SEL포럼
[학생발표]십자성마을_2020에너지자립비전및계획_2014SEL포럼STUDENT ENERGY LAB
 
JaSST'13 Kansai 継続的フィードバックによる品質運営
JaSST'13 Kansai 継続的フィードバックによる品質運営JaSST'13 Kansai 継続的フィードバックによる品質運営
JaSST'13 Kansai 継続的フィードバックによる品質運営智治 長沢
 
How Summer Camp Builds Self-Confidence
How Summer Camp Builds Self-ConfidenceHow Summer Camp Builds Self-Confidence
How Summer Camp Builds Self-ConfidenceBuzz Marketing Pros
 
U.S. Department of Agriculture - Regulatory Reform - January 2012 Update
U.S. Department of Agriculture - Regulatory Reform - January 2012 UpdateU.S. Department of Agriculture - Regulatory Reform - January 2012 Update
U.S. Department of Agriculture - Regulatory Reform - January 2012 UpdateObama White House
 
LibreOfficeの最近の動向とDebianでのLibreOfficeパッケージについて
LibreOfficeの最近の動向とDebianでのLibreOfficeパッケージについてLibreOfficeの最近の動向とDebianでのLibreOfficeパッケージについて
LibreOfficeの最近の動向とDebianでのLibreOfficeパッケージについてShinji Enoki
 
Vidcon Thumbnail Best Practices - Vidcon Presentation - Jeremy Vest
Vidcon Thumbnail Best Practices - Vidcon Presentation - Jeremy VestVidcon Thumbnail Best Practices - Vidcon Presentation - Jeremy Vest
Vidcon Thumbnail Best Practices - Vidcon Presentation - Jeremy Vestjeremy vest
 
Crew, Foia, Documents 011726 - 011863
Crew, Foia, Documents 011726 - 011863Crew, Foia, Documents 011726 - 011863
Crew, Foia, Documents 011726 - 011863Obama White House
 
Quality Control for Translations-The Best in Process, Plans and People
Quality Control for Translations-The Best in Process, Plans and PeopleQuality Control for Translations-The Best in Process, Plans and People
Quality Control for Translations-The Best in Process, Plans and PeopleStacey Brown-Sommers
 
Rinconcompskillz2.doc
Rinconcompskillz2.docRinconcompskillz2.doc
Rinconcompskillz2.docMRINCON002
 

Viewers also liked (20)

What's trending? The Latest Trends in Social For Hospitality
What's trending? The Latest Trends in Social For HospitalityWhat's trending? The Latest Trends in Social For Hospitality
What's trending? The Latest Trends in Social For Hospitality
 
Unit 2 Power Point
Unit 2 Power PointUnit 2 Power Point
Unit 2 Power Point
 
EPA CAA Email 8.29.03 (b)
EPA CAA Email 8.29.03 (b)EPA CAA Email 8.29.03 (b)
EPA CAA Email 8.29.03 (b)
 
TV Quiz Long Connect
TV Quiz Long ConnectTV Quiz Long Connect
TV Quiz Long Connect
 
Application Integration with XProc
Application Integration with XProcApplication Integration with XProc
Application Integration with XProc
 
[학생발표]십자성마을_2020에너지자립비전및계획_2014SEL포럼
[학생발표]십자성마을_2020에너지자립비전및계획_2014SEL포럼[학생발표]십자성마을_2020에너지자립비전및계획_2014SEL포럼
[학생발표]십자성마을_2020에너지자립비전및계획_2014SEL포럼
 
JaSST'13 Kansai 継続的フィードバックによる品質運営
JaSST'13 Kansai 継続的フィードバックによる品質運営JaSST'13 Kansai 継続的フィードバックによる品質運営
JaSST'13 Kansai 継続的フィードバックによる品質運営
 
FOTOinformator 06/2015
FOTOinformator 06/2015FOTOinformator 06/2015
FOTOinformator 06/2015
 
How Summer Camp Builds Self-Confidence
How Summer Camp Builds Self-ConfidenceHow Summer Camp Builds Self-Confidence
How Summer Camp Builds Self-Confidence
 
Selami Macit
Selami MacitSelami Macit
Selami Macit
 
Welcome to flanders
Welcome to flandersWelcome to flanders
Welcome to flanders
 
EPA DROE Email 6.23.03 (a)
EPA DROE Email 6.23.03 (a)EPA DROE Email 6.23.03 (a)
EPA DROE Email 6.23.03 (a)
 
Excerto damiao góis_mooclisboa
Excerto damiao góis_mooclisboaExcerto damiao góis_mooclisboa
Excerto damiao góis_mooclisboa
 
SERA Email 12.23.02
SERA Email 12.23.02SERA Email 12.23.02
SERA Email 12.23.02
 
U.S. Department of Agriculture - Regulatory Reform - January 2012 Update
U.S. Department of Agriculture - Regulatory Reform - January 2012 UpdateU.S. Department of Agriculture - Regulatory Reform - January 2012 Update
U.S. Department of Agriculture - Regulatory Reform - January 2012 Update
 
LibreOfficeの最近の動向とDebianでのLibreOfficeパッケージについて
LibreOfficeの最近の動向とDebianでのLibreOfficeパッケージについてLibreOfficeの最近の動向とDebianでのLibreOfficeパッケージについて
LibreOfficeの最近の動向とDebianでのLibreOfficeパッケージについて
 
Vidcon Thumbnail Best Practices - Vidcon Presentation - Jeremy Vest
Vidcon Thumbnail Best Practices - Vidcon Presentation - Jeremy VestVidcon Thumbnail Best Practices - Vidcon Presentation - Jeremy Vest
Vidcon Thumbnail Best Practices - Vidcon Presentation - Jeremy Vest
 
Crew, Foia, Documents 011726 - 011863
Crew, Foia, Documents 011726 - 011863Crew, Foia, Documents 011726 - 011863
Crew, Foia, Documents 011726 - 011863
 
Quality Control for Translations-The Best in Process, Plans and People
Quality Control for Translations-The Best in Process, Plans and PeopleQuality Control for Translations-The Best in Process, Plans and People
Quality Control for Translations-The Best in Process, Plans and People
 
Rinconcompskillz2.doc
Rinconcompskillz2.docRinconcompskillz2.doc
Rinconcompskillz2.doc
 

Similar to Prakhar gupta risk analysis report

Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacPMA Consultants
 
1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx
1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx
1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docxvickeryr87
 
Seismic mitigation final
Seismic mitigation finalSeismic mitigation final
Seismic mitigation finalSiDdu GowTham
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projectsPALLA NARASIMHUDU
 
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...IJCMESJOURNAL
 
IRJET- A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET-  	  A case Study on Risk Identification and Risk Assessment in Real Es...IRJET-  	  A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET- A case Study on Risk Identification and Risk Assessment in Real Es...IRJET Journal
 
Final presentation
Final presentationFinal presentation
Final presentationjai vinayak
 
Project Management C7 -risk_management
Project Management C7  -risk_managementProject Management C7  -risk_management
Project Management C7 -risk_managementIzah Asmadi
 
A Case Study On Risk Identification And Risk Assessment In Real Estate Projects
A Case Study On Risk Identification And Risk Assessment In Real Estate ProjectsA Case Study On Risk Identification And Risk Assessment In Real Estate Projects
A Case Study On Risk Identification And Risk Assessment In Real Estate ProjectsNancy Rinehart
 
RM_audit_overview_w_voice.pptx (2).mp4 Interoperability.docx
RM_audit_overview_w_voice.pptx (2).mp4  Interoperability.docxRM_audit_overview_w_voice.pptx (2).mp4  Interoperability.docx
RM_audit_overview_w_voice.pptx (2).mp4 Interoperability.docxSUBHI7
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...Dr. Amarjeet Singh
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfmohamed Ismail
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET Journal
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsIRJET Journal
 
B0363010015
B0363010015B0363010015
B0363010015theijes
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET Journal
 

Similar to Prakhar gupta risk analysis report (20)

QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
 
IJET-V2I6P23
IJET-V2I6P23IJET-V2I6P23
IJET-V2I6P23
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
 
1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx
1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx
1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx
 
Seismic mitigation final
Seismic mitigation finalSeismic mitigation final
Seismic mitigation final
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projects
 
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
 
IRJET- A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET-  	  A case Study on Risk Identification and Risk Assessment in Real Es...IRJET-  	  A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET- A case Study on Risk Identification and Risk Assessment in Real Es...
 
Final presentation
Final presentationFinal presentation
Final presentation
 
Project Management C7 -risk_management
Project Management C7  -risk_managementProject Management C7  -risk_management
Project Management C7 -risk_management
 
A Case Study On Risk Identification And Risk Assessment In Real Estate Projects
A Case Study On Risk Identification And Risk Assessment In Real Estate ProjectsA Case Study On Risk Identification And Risk Assessment In Real Estate Projects
A Case Study On Risk Identification And Risk Assessment In Real Estate Projects
 
RM_audit_overview_w_voice.pptx (2).mp4 Interoperability.docx
RM_audit_overview_w_voice.pptx (2).mp4  Interoperability.docxRM_audit_overview_w_voice.pptx (2).mp4  Interoperability.docx
RM_audit_overview_w_voice.pptx (2).mp4 Interoperability.docx
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdf
 
112 risk management
112 risk management112 risk management
112 risk management
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction Projects
 
B0363010015
B0363010015B0363010015
B0363010015
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction Projects
 

Recently uploaded

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 

Recently uploaded (20)

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 

Prakhar gupta risk analysis report

  • 1. WAREHOUSES - PROJECT TERMIK Quito, Ecuador By : BGH Group Prakhar Gupta Pia Emilia Bertero Ziwei Hu CE 8283 Risk Analysis New York University Fall 2016
  • 2. 2 Table of Contents Part 1. Project Proposal Introduction Scope of Work Design Quality Cost Estimation Schedule Purpose of Risk Management Plan Part 2. Risk Identification Procedures Risk Identification Part 3: Risk Categories and Organization Risk Categories and Preliminary Analysis Influence Diagrams Part 4. Qualitative and Quantitative Analysis Part 5. Risk monitoring, Controlling and Reporting 1. Traffic accident 2. Cost increase 3. Policy changes 4. Accessibility 5. Leadership 6. Quality of construction materials 7. Rock bed found after certain depth 8. Contamination of Soil 9. Delay in water and electricity supply Recommendations Page 1 1 2 2 3 3 3 4 4 6 11 11 15 20 30 31 32 33 34 36 37 39 41 42 43
  • 3. Figures Figure 1. Photograph of the project location Figure 2. Project Termik referential graph, and chart of areas Figure 3. Project Termik Summary Figure 4. Risk Categories of Project Termik Figure 5. Link between a risk and the affected activities. Figure 6. Parameters of cost/duration for activities on the schedule Figure 7. Schedule with activities, cost, duration, start/finish dates Figure 8. Objective of the quantitative risk analysis. Figure 9. Distribution Graph of Duration (Without Risk) Figure 10. Distribution Graph of Duration (With Risk) Figure 11. Distribution Graph of Finish Date (Without Risk) Figure 12. Distribution Graph of Finish Date (With Risk) Figure 13. Distribution Analysis of Finish Date Figure 14. Distribution Graph of Cost (Without Risk) Figure 15. Distribution Graph of Cost (With Risk) Figure 16. Distribution Analysis Graph of Cost Figure 17. Tornado Cost Sensitivity Figure 18. Distribution Analysis Graph of Cost before and after risk Figure 19. Risk Mgmt. Process Tables Table 1. Risk Matrix with likelihood and impact Table 2. Risk Categorization of Project Termik Table 3. Risk Categories & Qualitative and Quantitative Analysis Table 4. Probability scale, Impact and scale types, PID from Primavera Table 5. Risk influence in the project Table 6. Qualitative analysis with probability of occurrence of risks Table 7. Quantitative analysis with probability/activities Influence Diagrams Influence Diagram 1. Construction and Design Influence Diagram Influence Diagram 2. Environmental Risk Influence Diagram Influence Diagram 3. Financial Risks Influence Diagram Influence Diagram 4. Supply Risks Influence Diagram Influence Diagram 5. Legal Risks Influence Diagram Influence Diagram 6. PM Risks Influence Diagram Influence Diagram 7. Safety Risks Influence Diagram Page 1 2 11 12 20 20 21 21 24 24 25 25 26 27 27 28 28 29 30 5 13 14 14 15 22 33 16 17 17 18 18 19 19
  • 4. 1 Part 1. Project Proposal Introduction Ecuador is a country that uses US dollars and because of it, it's expensive to produce finished goods. Consequently, commerce is a practiced activity. Importing goods, storage and selling those products consist an important part of the economy. The project is located within a residential/industrial zone of the northeast part of Quito, Ecuador. By being so close to the city and having many different routes to the center and southern part of Quito, this piece of land is well located for its purpose. The project is connected to Quito international airport by a recently built highway (dist. 9km approx.) and many other highways that allow an easy transportation of goods, not only to the entire city but to smaller cities and the countryside surrounding it. Site Location Figure 1. Photograph of the project location Lat: -0.102784 Lon: -78.443866, Google Maps
  • 5. 2 Scope of Work This project is intended to satisfy storage needs for small and medium businesses. The idea is to build 14 warehouses in the northeast of the capital, Quito. The space is designed to store goods of different nature until they reach a final destination. Construction will be broken down into consecutive phases like: site preparations and permits, land movement and excavation for foundations, construction of metallic superstructure, Mechanical Electrical and Plumbing (MEP) Rough-in and interior finishes. Design Quality The Project is designed to satisfy the requirement to store finish products for small and medium businesses until they are delivered to other locations. Figure 2. Project Termik referential graph, and chart of areas
  • 6. 3 Cost Estimation We have estimated that the total cost would be around 5.1 million USD, divided into this phases: ● Preliminary work - $138,351 ● Excavation - $485,110 ● Walls and sub structural works – $1,500,000 ● Metallic Structure – $1,090,000 ● Finishing Work – $950,000 ● Exterior Work, Other Utilities, Water and Electricity supply – $1,170,000 Schedule We anticipate the construction will take 14 – 16 months. This estimated schedule will depend upon the anticipated risk within the projected. We have allocated 6 months for the excavation and substructure. The other 6 months for the superstructure and the rest of the work is allocated for 3 months. Purpose of Risk Management Plan Understanding all potential risks before the construction starts will help the project team better prepare itself to go forward successfully. If one of those risk scenarios threatens the project execution, the team will be prepared and have some mitigation plan to deal with all possible outcomes. Our goal is to identify those risks and understand the magnitude they could have and calculate or determine possible losses. Also, to develop a plan or strategies to deal with them. We are going to use both quantitative and qualitative analysis techniques to develop an understanding of the effects of those risks to our project success. Also with the help of Primavera, a software that will allow us to better plan the project schedule, manage risks and their influence in the project, we could check if the duration of the project, the cost and the end date will change once we enter the risks.
  • 7. 4 Part 2. Risk Identification Procedures: 1. Risk Identification: Through analyzing the concept of operations we can identify possible risks in every stage of the project by simulating realistic undesirable scenarios. And we can understand things that can possibly go wrong and how could it effect in the project. 2. Impact and likelihood: Once we have identified the risks, we can predict how likely is that risk going to happen. The impact will be calculated by the severity of the losses or consequences each risk may cause. The likelihood will make us understand the probability or frequency of that scenario. 3. Risk Assessment: The combination of both impact and likelihood of each risk will help to understand the project vulnerabilities through Qualitative and Quantitative analysis. It will also help to decide which risks should be prioritized. 4. Mitigation: For every risk, we can develop a plan to prevent and mitigate every situation that has been formulated, so we are prepared for the best and worst case scenarios. 5. Identification of Hazards: Physical situations with a potential of an undesirable loss or consequence will be analyzed. In this case the proper personal protection equipment will be taken into consideration for hazards and will be inside the risk of personnel safety. For the construction of the warehouses, it's expected to have mechanical, thermal, chemical, electrical and information hazards. 6. Risk Management: It's a continuously asses of risk related to uncertainties. It's a constant practice to prevent, control and minimize losses due to risk exposure. We can make a plan of action towards management this risks. But risk management will occur during construction.
  • 8. 5 7. Risk Communication: Communicate possible hazards and ways of procedure against diverse risks would be a perfect way to prevent losses or consequences. Stakeholders must be aware of all possible risks and uncertainties, so the process it's inclusive and has different points of view. Risk Matrix # Risk Consequences or Losses Likelihood Impact Environmental Social Budget Schedule Quality 1 Contamination of soil x x x Medium High 2 Rock bed found after certain depth x x Low High 3 Delay in water and electricity supply x x x Medium Medium 4 Delay in Supply of Materials x x High Medium 5 Fail of Formwork during the casting of the concrete x x x x Low High 6 Mismatch of steel structure during erection x x x Low High 7 Slips, Trips and Falls x x x Medium Low 8 Fail of the Object x x x x Low Low 9 Bad weather x x x x Medium Medium 10 Dispute Between Labor Union and management x x x Medium High 11 Political Instability (Change of LAW) x x Medium High 12 Accessibility x x Medium Medium 13 Community protests x Low High 14 Permits x Medium High 15 Insecurity x x x High Medium 16 Corruption x x x Medium Low 17 Environment (DUST) x x High Low 18 Quality of Construction Materials x Medium Medium 19 Leadership x x x x Medium High 20 Material Shortage x x Medium Medium 21 Natural disaster x x Low High 22 Traffic accidents x x Low Low 23 Cost increase x Medium High 24 Policy Change x x High High 25 Lack of workers x x High Medium 26 Personnel Safety x Medium High 27 Equipment Malfunction x Low Medium 28 Currency and Exchange Rate x x x Medium High 29 Inexperience x x x x Medium High 30 Fire Hazards x x x Low High Table 1. Risk Matrix with likelihood and impact
  • 9. 6 Risk Identification 1. Contamination of soil Cause – Site located at an industrial area there is a high probability of contamination of soil. Effect – May have to dig deeper than it is designed for the construction of foundation or will require to backfill compact soil to provide strong base to the foundation 2. Rock bed found after certain depth Cause – Possibility of rock bed after certain depth Effect – It will require rock cutting machine and other Machineries. It will also require extra labors and man hours which will affect the cost and will delay the schedule estimated for the excavation of the site 3. Delay in water and electricity supply Cause – As supply is been given by the government, it has possibility we may not get supply in time . Effect – It will delay concrete construction work, as the concrete requires high amount of curing at initial stage. 4. Delay in supply of materials Cause – Due to bottlenecks and congestion in the traffic it has high possibility of delay in the supply if the materials. Effect – It can affect other work and increase the labor and machinery cost as well. 5. Fail of Formwork During the Casting of the concrete Cause – Formwork could fail to carry the load of the concrete due week support and tie with each other. Effect – May cause serious damage to the worker and laborers. It will also lead to wastage of material and ultimately to the cost. In a very serious case it may suspend the work for few days.
  • 10. 7 6. Mismatch of Steel Structure During Erection Cause – Since it is steel structure, fabrication is being done at specific are and then it is brought to the site. Which may lead to a mismatch during erection. Effect – Wastage of the material and will suspend work for few hours or a day. And will require to redesign the parts. 7. Slips, Trips and Falls Cause – Since it is a steel structure and labors will be working at some heights. Effect – Fatal accident of labors. 8. Fail of the Object Cause - Improper designing of the structural if not take properly, Cheap quality used for construction. Effect - Serious accident and wastage of material and man hours. 9. Bad weather Cause – Due to heavy rain work may suspend for a day or two. Effect – Suspend work for a day to weeks which will delay the construction work and may damage the material exposed to weather. 10. Dispute Between Labor Union and management Cause – Improper behavior of management, could happen related to wage or could be regarding safety. Effect – Unknown delays in construction schedule, which may affect the cost. 11. Cash Flow Interruptions Cause- The government is known for its radical behavior in terms of creating new laws, that can create panic and stop investment. Effect - Cash flow could be affected; therefore, the initiation of the construction could be delayed or construction could be paralyzed. It can also make stakeholders to doubt the extent of the project, the investment, etc.
  • 11. 8 12. Accessibility Cause – The street to access the site of construction is always congested due to a vehicular revision that is located next to the project. This place has a queue of cars waiting to be checked out. Effect – Trucks with materials, machinery, big trucks and other vehicles accessing the site can be obstructed because of these phenomena, delaying the delivery of materials and or services needed to proceed with the project. 13. Community protests Cause – Since the location of the project is in a industrial/residential zone, the resident neighbors could have complaints about noise, contamination, traffic, road blocks, etc. Effect – There could be complaints from the residents of the area regarding the issues that a construction of that extent can cause. At the end the project can be delayed or even stopped. 14. Permits Cause – Construction and environmental permits need to be obtained. Effect- Permits don’t have an specific time of processing. Sometime they can take weeks or even months. Bureaucracy and a fast personnel shift in the office that give the permits often causes delays and time uncertainty. Delays in the construction can be serious. 15. Insecurity Cause – The area is catalogued as a dangerous area where a lot of robberies occur. Expensive equipment and material can be targeted by thieves. Effect – The construction can be delayed because even if the materials or machinery have insurance the reposition will take time and money. The cost of the project could go up. Workers can feel threatened and the community surrounding the area. 16. Corruption Cause – Corruption is a common practice in the construction area of Ecuador's market. Effect – Obtaining permits and keeping them can be affected by corruption. In many cases a payment is requested by local authorities that can threaten to close the project.
  • 12. 9 17. Environment (DUST) Cause – Since the location of the project is close to the Ecuador, sun is strong and makes the land to be dry. Wind can spread dust in the early stages (excavation and soil movement, replacement, etc.). Effect – Dust can affect the families and overall community that live close by, making people uncomfortable, affecting local businesses and the environment. 18. Quality of Construction Materials Cause – There is a market of materials of low quality that often lie about strength of materials or other properties. Effect – The quality of the material defines the overall quality of the project as well. So if the quality does not match with the design, financial loss and delays can happen. 19. Leadership Cause – Lack of a proper management skills (PM) during design and construction Effect – Delays, a faulty schedule, cost increase and lack of coordination can be the result of a bad project management. 20. Material Shortage Cause – Lack of material in the market. Effect – A shortage in materials can stop the project completely or delay some phases of it. That can produce losses, increase the cost of the project and overrule the project schedule. 21. Natural disaster Cause - Some natural disaster such as flood and earthquake. Effect - They may destroy the construction and equipment. In addition, it may cause huge finical loss and make workers injured. 22. Traffic accident Cause - When transfer some supplies or equipment, some traffic accidents may happen. Effect - Financial loss, loss of life and personal injury.
  • 13. 10 23. Cost increase Cause - rising price, economic crisis. Effect - budget increase, lack of enough money. 24. Policies change Cause - Industry laws and regulation revise. Effect - Influence the design and actions, may cause schedule delay. 25. Lack of workers Cause - Working prospect and salary are lack of attraction, during festivals and holidays. Effect - Schedule delay. 26. Personal safety Cause - Incorrect operation process, poor equipment, poor security. Effect - Financial loss, loss of life and personal injury, compensation, schedule delay, bad reputation. 27. Equipment malfunctions Cause - Being used for long time, lack of maintenance, operate incorrectly. Effect - Schedule delay, financial loss, personal injury. 28. Currency and exchange rate Cause - Economic crisis. Effect - Budget is not enough. 29. Inexperience Cause - Green hands. Effect - Schedule delay, unnecessary financial loss. 30. Fire Cause - Smoking, equipment overheats. Effect - Schedule delay, financial loss, personal injury, bad reputation.
  • 14. 11 Part 3: Risk Categories and Organization Project Termik Figure 3. Project Termik Summary Risk Categories and Preliminary Analysis There are many ways in which we can categorize risk. Different disciplines use terms like hazards or risk exposures. Categorization can be done by analyzing the causes of a risk or its nature of consequence and in some cases of both. The losses can be ultimately measured in economic terms that can affect a determined project. In most situation before measuring the risk in terms of loss, we can categorize them in five broad categories of risks: health, safety, security, financial and environmental. There are often interrelations between those categories, but its prime nature should be reflected in only one. For example, a health risk may later lead to financial loss but that doesn't mean it should be considered as financial risk.
  • 15. 12 For this project, we have developed our own categories for risk. To organize them better we have divided risks considering their nature and causes, in the following categories: project management, supply, legal, environment, construction & design, safety and financial (Figure 4). Most of the risks of Project Termik are in the project management category and it makes sense because that discipline will rule in the success of the project, being present in all the project lifecycle, we could see that in table 2. Figure 4. Risk Categories of Project Termik
  • 16. 13 # Risk RISK CATEGORIES C&D Safety PM Enviro. Legal Supply Financial 1 Contamination of soil x 2 Rock bed found after certain depth x 3 Delay in water and electricity supply x 4 Delay in Supply of Materials x 5 Fail of Formwork during casting of concrete x 6 Mismatch of steel structure during erection x 7 Slips, Trips and Falls x 8 Misconception of Design x 9 Bad weather x 10 Dispute Between Labor Union and management x 11 Political Instability x 12 Accessibility x 13 Community protests x 14 Permits x 15 Insecurity x 16 Corruption x x 17 Environment (DUST) x 18 Quality of Construction Materials x 19 Leadership x 20 Material Shortage x 21 Natural disaster x 22 Traffic accidents x 23 Cost increase x 24 Policy Change x 25 Lack of workers x 26 Personnel Safety x 27 Equipment Malfunction x 28 Currency and Exchange Rate x 29 Inexperience x 30 Fire Hazards x Table 2. Risk Categorization of Project Termik After separating the risk in categories, we also grade them according to their likelihood and impact in the project in a qualitative and quantitative way.
  • 17. 14 Table 3. Risk Categories & Qualitative and Quantitative Analysis Once we established the categories and know the potential likelihood/impact of each risk, we proceed to put this information into Primavera for further analysis, like we see in table 4 and 5. Table 4. Probability scale, Impact and scale types, PID from Primavera
  • 18. 15 Table 5. Risk influence in the project As a result of the primavera analysis, we can see that some risks are not so influential in our project, like traffic accidents or dust formations during the project (table 4). Many other risks in the yellow area could influence the project in a medium way and most of the risks have a great influence in the project. This could be explained by the fact that most of the project activities are extensive and expensive, so any alteration in cost or schedule will have a high or very high influence in the project. Influence Diagrams For further analysis, we have created influence diagrams so we can see each risk in all seven categories and their area of influence. The objective of creating these influence diagrams is to give the viewer a clear idea of the risks inside a category and the area of influence this risk may have. We achieve that through a dynamic graphic that proposes inputs and outputs. The influence diagram can help us see how a group of risks will affect more or less areas than other groups. In the red circles we have the inputs (risks) then in green we have the area of focus in which those risks will take place, and finally in a blue diamond the possible outcomes
  • 19. 16 that the risks may cause or the variables of the project that can be impacted. So, for this part we will have 7 influence diagrams since we have categorized our risk into 7 categories. For example, legal risks in influence diagram 5 have influence in only one area as an output, the schedule. Other categories like in influence diagram 7 were we can see safety risks, can result affecting several areas like quality of construction, cost and schedule and project success. Other factors could also intervene in determining which risk would we rather have in our project than only the areas of influence. Priorities of each project are different and can alter the way we interpret the results and view risks. Construction and Design Risks: Influence Diagram 1. Construction and Design Influence Diagram
  • 20. 17 Environmental Risks: Influence Diagram 2. Environmental Risk Influence Diagram Financial Risks: Influence Diagram 3. Financial Risks Influence Diagram
  • 21. 18 Supply Risks: Influence Diagram 4. Supply Risks Influence Diagram Legal Risks: Influence Diagram 5. Legal Risks Influence Diagram
  • 22. 19 Project Management Risks: Influence Diagram 6. PM Risks Influence Diagram Safety Risks: Influence Diagram 7. Safety Risks Influence Diagram
  • 23. 20 Part 4. Qualitative and Quantitative Analysis So far, we have we have found 30 possible risks that could affect our project. We categorized those risks into seven categories: Supply, Financial, Construction & Design Risks, Environmental Project Management, Legal and Safety. We performed already a qualitative analysis by putting the likelihood and the impacts of each risk (Tables 4,5). Then we analyzed the influence of each risk in the project. For part 4, the qualitative analysis will include a link between each risk to the activities that it influences in the primavera schedule (figure 5). This will help us to relate each risk with the possible activities it may affect. So, results of the qualitative analysis could change and also, we can get out a quantitative analysis as well. Example: Figure 5. Link between a risk and the affected activities The probability of each risk will be taken from the qualitative analysis that we entered in primavera (figure 5). We will run the risk analysis with a complete schedule for the project, entering parameters of cost and duration for each activity (figure 6). The schedule this time will have to include every single activity in the project, its duration and follow a sequence (figure 7). Example: Figure 6. Parameters of cost and duration for each activity on the schedule
  • 24. 21 Figure 7. Schedule with activities, cost, duration, sequence and start/finish dates It's important to say that after completing the sequence of every activity of the project in Primavera, the schedule of the project changed to 18 months approximately, more than speculated at the beginning (14-16 months). After running the risk analysis with the new linked activities/risk we can obtain results that will tell us how the risks will affect the project. We will do the analysis by comparing results of the duration, cost and finish date that the analysis will give us. One set of results will include the risks linked to the activities and the other will not (Figure 8). Figure 8. Objective of the quantitative risk analysis First, having performed a qualitative analysis that can be seen in table 4 and 5, we get a probability scale, Impact and scale types and the risk influence in the project. That probability
  • 25. 22 scale shown also in table 6, tells us the ID for each risk, the description a score based on the inputs we put before, those are likelihood and impact. The probability of each risk now will be used in the qualitative analysis once que link the risks to each activity. Table 6. Qualitative analysis with probability of occurrence of risks In table 7 we can see the same risks we introduced in primavera before, but now we have linked each risk to every activity or task in the schedule that will be influenced by it. The probability of occurrence is also there and we have chosen a pre-mitigated phase, since we have not yet taken actions over the risks.
  • 26. 23 Table 7. Quantitative analysis with probability of risks/activities After we do this, the next step in Primavera is to run the risk analysis again, and see how this new results (pre-mitigated) vary from the ones we got before the risks were a variable. In figures 9 and 10 we can see results for duration of the project with and without risk. According to the statistics, the mean or expected value of duration for the project is 643 days. The range in which the project could finish goes from 564 and 698 days, leaving a window of 134 days. When we input the risks, the mean is 673 days, 30 days or a month more than the results we got before.
  • 27. 24 Figure 9. Distribution Graph of Duration (Without Risk) Figure 10. Distribution Graph of Duration (With Risk) The range goes from 590 to 769 days, so the window has increased with risks from 134 to 179 days. We can say confidently by watching this results, that there is more uncertainty in the
  • 28. 25 duration now that we put the risks in the mix. Figures 11 and 12 are the results for finish date, they vary in the same proportion of duration since they are directly related, an increased duration will change the finish date. The mean will vary a month from 26/07/18 to 26/08/18. Figure 11. Distribution Graph of Finish Date (Without Risk) Figure 12. Distribution Graph of Finish Date (With Risk)
  • 29. 26 If we see the analysis graph in figure 13 and we choose 90% of probability of results, we get that end date with risks will be most likely 28/09/18 and without risks 31/08/18, a month apart. That will gave the project a duration of almost two years with risk. Figure 13. Distribution Analysis of Finish Date As for the cost, we can see in figures 14 and 16 the results for the plan cost without and with risks respectively. The mean cost without risk is USD 5,900,260.00 and with risk USD 8,425,570.00. The variation between both is of USD 2,525,310.00, almost 43% more than the initial budget without risk input. Range from figure 14 is from minimum amount to maximum goes from USD 5,365,198.00 to USD 6,254,651.00, having a window of almost a million dollars. In figure 15 we can see that the range goes from USD 6,441,676.00 to USD 11,564,521.00, having a huge window of 5,092,345.00. In this variable, cost, we can see how influential risk could be if no actions are taken to reduce it, prevent it, control it or mitigate it. Like we see in the analysis in table 16 the difference of cost with and without risks is much more defined than in the other variables.
  • 30. 27 Figure 14. Distribution Graph of Cost (Without Risk) Figure 15. Distribution Graph of Cost (With Risk)
  • 31. 28 Figure 16. Distribution Analysis Graph of Cost If we see the analysis graph in figure 16 and we choose 90% of probability of results, we get that end cost with risks will be most likely USD 9,601,560.00 and without risks USD 6,074,766.00, almost 3 million dollars apart. The costs that are most influential to the project now that the risks have been inserted in Primavera are shown in figure 17, with a percental value. Figure 17. Tornado Cost Sensitivity
  • 32. 29 A summary of all the results can be seen in figure 18, for calculations of before and after risk has been added to the risk analysis calculations in Primavera. Figure 18. Distribution Analysis Graph of Cost before and after risk The numbers and variations of finish dates, durations and mostly cost, only confirm that risks cannot be taken lightly because they have a major influence in the project. If the risks are not monitored and controlled or mitigated; they could not only delay the finish date, but increase the cost in a dramatic way. The project has to consider risks in overall planning or further down the road the worst-case scenario could be catastrophic. The objective now is to elaborate a mitigation strategy for each risk to prevent these developments to take place.
  • 33. 30 Part 5. Risk monitoring, Controlling and Reporting So far, we have identified risks for project Termik, we have assessed those risks and ranked them in a qualitative and quantitative way. Like we mentioned after the quantitative analysis, the project has to consider risks in overall planning or further down the road the worst-case scenario could be catastrophic. In this part, we will talk about monitoring those risks and managing them with mitigation, control and reporting strategies (figure 19). Also, we will identify stakeholders involved in the process. We will propose these strategies to manage 9 of the 30 risks we identified before, these nine risks are: 1. Traffic accident 2. Cost increase 3. Policy changes 4. Accessibility 5. Leadership 6. Quality of construction materials 7. Rock bed found after certain depth 8. Contamination of Soil 9. Delay in water and electricity supply Figure 19. Risk Mgmt. Process For these nine risks, we will be explaining the way we can monitor them, control them and how this risks should be communicated and reported. The objective is to elaborate a mitigation strategy to prevent these developments to take place. The mitigation and controlling strategies should cost less or have benefits that represent more than the possible impact of that risk. Also, after these control and mitigation strategies will be implemented, they will diminish project vulnerabilities.
  • 34. 31 1. Traffic accident In our project, during the transportation of some materials, accidents may happen. Accidents can be caused by many kinds of reasons, such as bad traffic condition, bad weather and irresponsible driving. Once an accident has happened, it will increase our cost and it will be a cause of delay. Therefore, we should do the preparation and mitigation. Risk Monitoring a. Surrounding traffic condition: On some special type of highway such as curve highway sections, traffic accidents are easier to happen. Drivers should pay attention to these accident black spots. b. Driver management: Fatigue driving, drunk driving, new drivers are the possible reasons leading to traffic accidents. Therefore, we should improve the management of drivers. c. Bad weather: Traffic accidents are easier to happen with bad weather. So, we should decrease the transportation in bad weather. d. Breaking traffic regulations: Breaking traffic regulations such as overloading may lead to traffic accidents. Therefore, we should strengthen the management of drivers. Risk Controlling / Mitigation a. Hire experienced drivers. b. Strengthen management of drivers, improve the safety consciousness of drivers. c. Pay attention to traffic and weather condition. Try to avoid transportation in bad weather. d. Provide accidents insurance. Risk reporting / Communication a. Provide road and traffic condition to drivers. b. Provide weather condition to drivers. c. Safety training. d. Accidents insurance.
  • 35. 32 Stakeholders a. Driver b. Insurance Company c. Project Administration d. Project manager 2. Cost increase Because of the changing financial condition, cost may be increasing. Wrong decision making, changing of the relationship between supply and demand, economic crisis can also lead to cost increasing. It will influence the project investment and even cause the schedule delay. Therefore, we should pay attention to the marketing situation and do the adjustment of project cost in time. Risk monitoring a. Schedule delay: Schedule delay may cause the cost increasing. So, management of schedule is important. b. Supply and demand in market: Changes of the relationship between supply and demand in market may influence the price of materials in the project. Purchasing materials in time or in advance can lower this risk. c. Financial crisis: The risk of financial crisis is very low. d. Decision making: Before purchasing materials and concluding a contract, decision maker should do the research and comparison. Risk Controlling / Mitigation a. Pay attention to international and domestic finance situation. b. Purchasing materials in advance, with a contract that establishes cost. c. Management of schedule. Complete the schedule on time.
  • 36. 33 Risk Reporting / Communication a. Do the marketing research before making decisions. b. Provide report of increasing cost if schedule was delay. Stakeholders a. Supply manager b. Project manager c. Customer 3. Policy change Policy change is not easy to happen, but once it does, it will have big impacts on the process of the project. We should do the preview and prepare alternatives. Risk Monitoring a. Industry laws and regulation revise: Some industry laws and regulation revising may influence the completion of the project. Therefore, we should pay attention to the regulation situation and do the preparation. Risk Controlling / Mitigation a. Pay attention the policy and possible changes. b. Preview of policy changing. c. Prepare alternatives in advance to face the policy change. d. Adjust the project in time according to the new policy. Risk Reporting / Communication a. Provide report of domestic policy and possible changing during project. b. Provide emergency plan. c. Provide the report of loss leading by policy changing.
  • 37. 34 Stakeholders a. Construction manager b. Project manager 4. Accessibility After evaluating possible vulnerabilities of Project Termik, Accessibility showed possible results for risk. Due to a high volume of vehicles that park and wait for revision in a center that it's next to project Termik, congestion and delays may be created, making accessibility difficult for vehicles to the project's location. Also, it's worth to mention that the street which provides access to project Termik is a two-way street, so transit of bigger vehicles like trucks may be more difficult than expected. For this reason, constant monitoring of the accessibility situation must be provided, so that vehicles that wait for the revision next to the project may be relocated or leave a certain amount of distance to make easier the circulation of vehicles, especially during construction. Controlling this risk can also avoid complaints that could, in a worst-case scenario, stop the activities of construction. Risk Monitoring a. Provide personnel to monitor parked vehicles outside and manage them in an organized matter. These personnel may also help pedestrians to circulate safely and provide any assistance or information necessary. b. Talk to possible stakeholders and open a channel of communication to keep everybody informed about any situation (Neighbors, residents, police, traffic management authorities, project management). c. Provide a journal so that activities are monitored by personnel at the entrance, to check all vehicles in and out the premises with information about their activity. Also, they can monitor delays, schedules, etc. Risk Controlling / Mitigation a. The entrance to project Termik must have correct signalization. No parking signals, red cones if necessary or any signalization preventing for delays to happen. These signals
  • 38. 35 will also sum organization and safety to personnel and people in the surrounding area. b. Getting to certain agreements with stakeholders will be another way to control unnecessary complaints, traffic jams and delays at the access point. For example: a schedule of incoming and going vehicles can be created. c. Journals kept by personnel in the entrance will be a good tool to control the existence of delays or problems with accessibility. This reports will be analyzed by the administration of the project, so any decision can be taken. d. A fine or penalty system may be created with material providers and contractor so they follow a certain schedule. This will maintain the order of coming and going vehicles towards the project's location. e. Constant reunions and communication with stakeholders involved in the topic may be necessary. Creating an agreement to organize traffic flow in the street of access is a priority. Risk Reporting / Communication a. Journals and reports of the access activity must be kept by personnel in charge. b. Schedule noncompliance by any contractor or material provider must be properly documented and notify to management of the project. This way the administration can inform each company about fines. Stakeholders a. Personnel in charge b. Project Management c. Neighbors d. Transit Authorities e. Residents
  • 39. 36 5. Leadership A risk in leadership is a tricky business. It’s hard to point the exact flaws in leadership and in many cases, it's easy to identify by performance. Even though it's not a concrete science, there are ways to manage the risk leaving uncertainty aside. A thorough hiring process for the right candidates is often the way to go. Risk Monitoring a. The project Manager will oversee monitoring and assessing the leadership and decision making skills of his/her team. b. A proper report of complaints from personnel towards a member of the projects administration, management or towards any problem within the project shall be kept. This will help monitor areas that need more control and identify the person that is in charge of that area. c. Change orders with justifications must be provided. Monitoring compliance of the construction rules and procedures must be done. d. Weekly meetings between all management staff to monitor compliance with schedule, cost and performance, will help to identify areas in trouble with possible lack of leadership. e. Weekly meetings with management and stakeholders for feedback, organizing work and taking decisions. Risk Controlling / Mitigation a. Evaluate performance of each member of the management team and communicate to them the areas that need improvement. All monitoring techniques will help in developing an evaluation on performance. b. Create daily journals so that any member of management can write important events of the day, possible change orders with justification, weather situation, or any decision taken during that day. c. Create a good channel of communication or a system in which all members of the management team can be informed of current information.
  • 40. 37 d. Prepare the personnel for different work scenarios with trainings and courses that encourage a best practice of leadership e. Hire personnel with experience and knowledge in the area, that have skills desired in a good leader (always thru a HR office or external HR party). Risk Reports / Communication a. All the reports of complaints towards management personnel or in certain areas of work shall be provided weekly. b. A summary of every meeting should be prepared weekly so that record of any decision or action can be evaluated. c. The PM will oversee communicating with his/her personnel weekly to report any risk in management. d. Documentation of any change order shall be provided with a responsible signature. Stakeholders a. Project Management b. Project Administration c. Human Resources d. Customer 6. Quality of construction materials Quality of materials determine the quality of the end product. In this case, we want to make sure that every material used to build Project Termik complies with specifications provided in the design. It’s best to hire a third party that has expertise in the area, and share the responsibility with them. This action will also facilitate the work of project management, because they will have one less thing to worry about. Nonetheless, they will still be involved in important decision making. Risk Monitoring a. Before hiring any material supplier, the evaluation of credential and compliance with
  • 41. 38 regulations must be in order. b. Product quality reassured by an international regulator or certified laboratory. It depends on the quality that the customer wants. c. Regular reports of the material entering the project with documentation. d. For some materials, the need to hire a laboratory to test materials will be needed. For example, for concrete, a cylinder testing must be done to monitor the quality of the materials. Also, record of the origin of other materials used (water, sand, rocks, additives, etc.). e. Supervision that shall provide a quality check (Quality Management) Risk Controlling / Mitigation a. Compare quality between at least three providers of the material, and choose one with desired quality that has more benefits over cost. It will help if the provider was also close to the site. b. Contracts with suppliers that have specifications of desired quality of materials must be established before the construction. c. Contract with a third party that can guide in assuring to keep the quality of materials on site (adequate storage) and that can perform a quality check of the materials is necessary. d. Follow manufacturer's suggested procedures on handling materials. Or follow standards of construction for different activities. For example, in Ecuador there is a Norm for Construction (NEC). e. Buy only materials that comply with specifications from the design. f. Any additional test result obtain from material testing should be approved or rejected with justification by supervision and project management. Risk Reports / Communication a. Quality management should have a daily journal with activities and documentation related to quality of materials that arrive to the site and also for materials stored. b. Proper channel of communication and reporting should be implied between project
  • 42. 39 management and the quality management or supervision. c. Test results obtain from material testing with approval should be available for all management personnel to read. Risks can be reported in them. Stakeholders a. Suppliers b. Supply manager c. Project management d. Transportation company e. Supervision Personnel and/or Quality manager 7. Contamination of Soil Soil is the most important for designing foundation and it needs to well compacted. Excavation is the first most important step in the construction. If the soil is contaminated then we have to perform test, hire 3rd party environmental agency to make remove the top soil till we get the natural compact soil and we have to take other measures to provide solid base to the structure. Risk Monitoring a. Potential Areas of Soil Contamination: Usually contamination of soil takes place at the potential areas like Industrial sites, Near Oil Refineries, Petrol Station, and where there is Spill of chemicals. b. Percentage of the chemicals in the soil: If there is any industry situated nearby the site then there is a high probability the soil can contain high number of chemicals. c. Site survey: Site survey should be done at certain period because it will help to understand the structure of the soil and if there are any Large cracks formation found at the site, it may result into soil contamination. Data Analysis methods could be used by Hierarchical cluster analysis (HCA) and principal components analysis (PCA), and can interpret the Quality of the soil. d. Settlement of soil: We can track the rate of settlement of the soil which could happen if the soil is loose. Settlement might be the result of soil contamination
  • 43. 40 e. Soil strength/ soil bearing capacity: Examination of soil strength would help us to understand the soil compaction and soil bearing capacity and it will also help to design the foundation as well. Risk Controlling / Mitigation a. Soil testing should be done prior to the excavation. b. Hire 3rd party environmental agency for site remediation as it regulates the procedures. c. If soil is too loose then provide change order in the design for the use of piles and foundation. d. We can rent machineries and increase the number of labors to remove the contaminated soil within time period. e. Rent pumps to remove water from the excavation area if the water table is high at the construction site. f. At the same time we can order the supply of material of the backfill to make the base more compacted for the foundation Risk Reports / Communication a. We have to Make proper soil testing reports well before designing of the foundation. b. Site Survey and reports should be done properly c. Sufficient supply of materials and machineries should be provided to the construction site. Stakeholders a. Project Manager b. 3rd Party Environmental Agency c. Site Surveyors d. Site Engineer e. Soil Testing Laboratories
  • 44. 41 8. Rock bed found after certain depth Rock beds are usually good for the foundation, and it’s usually found in the hilly areas. However, it’s very hard to excavate and time consuming. Rock bed can be found by performing geotechnical survey. If there is any error or if the rock bed is not even, then we have to perform excavation work with heavy machineries which will consume time and require money. Risk Monitoring a. Geotechnical tracking or electromagnetic / Ultrasonic testing of the site. b. To monitor this risk, we can perform the geotechnical report and Electromagnetic testing/ ultrasonic testing of the site for the rock structures. If there is any, we can find out the depth of the rock and the locations of the rock bed at the construction site. Risk Controlling / Mitigation a. Geotechnical report should be taken well in advance; accordingly, we can ask for more labor and rock cutting machinery. b. If there is any error in geotechnical report and we find any unexpected rock bed then, to Control this risk we can rent rock cutting machineries and can increase the number of laborers, which will accelerate the excavation at the site and would help the get work done within the scheduled period. Also it may affect the design of the building, so If it is required, we can ask for change order with in the design as soon as we find the rock bed. Reports / Communication a. Geotechnical report should be done properly and Details should be given properly to the Project manager. b. Reports should be provided to the designers and change orders should be given with the updated report of the site. Stakeholders a. Geotechnical Surveyors b. Geotechnical Engineers
  • 45. 42 c. Equipment operator d. Project Manager e. Designers 9. Delay in water and electricity supply Water and electricity is the most important and is required right from the beginning of the construction. We require water for curing, preparing concrete etc and Electricity to operate heavy electric machineries. If we don’t get supply within time then we have to arrange from external sources like private companies. Risk Monitoring a. We must keep the track of permission of supply of water and electricity. b. Make proper coordination and communication regularly with the supplier. And we have to Make sure the supply to be provided to construction site take place well before construction work starts, for ex. 2-3 weeks before c. Make Proper check of the pipelines, if there is any problem there could be delay in work Risk Controlling / Mitigation a. We can ask for electricity from private company or use commercial generators and invertors, if there is any delay in electricity supply. Order for filled tankers prior to the construction work. Also Project Manager has arranged for Water storage by preparing reservoir well in advance near construction site. Make proper contact the supplier or the govt if they are supplying the water and electricity. Reports / Communication a. Make sure the supply to be take place well before construction work, for ex. 2-3 weeks before. b. Make proper contact the supplier or the govt if they are supplying the water and electricity.
  • 46. 43 Stakeholders a. Government Agencies b. Private Suppliers c. Project Managers d. Contractors e. Machinery suppliers Recommendations: A deeper analysis should be done for all the risks found in Project Termik. Controlling techniques that can be implemented from the beginning of the project could save money and prevent delays. Constant monitoring of the project will allow to find deviations from cost, schedule, risks and quality, allowing management the chance to control and mitigate them in an early base. Report and communication techniques are very important to help project management to be informed about any relevant situation in the project that requires to manage risk with established procedures or by new decisions. Project management will be in charge of dealing with stakeholders to lower risks and keep the expected performance in schedule, cost, quality and risk management. All the information of the risk analysis and procedures needed to handle risks should be written down in a Risk Management Plan, that will contain information on procedures, assumptions, examples of reports and techniques used throughout project development, and every document, guide or procedure related to monitoring, controlling, mitigating, reporting and communicating risk.