Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
Most of the construction projects are exposed to time and cost overruns due to various factors and this is a major problem. As a solution to this, the Earned Value Management (EVM) method is considered. EVM is a powerful and well-known method used in monitoring and controlling the project. EVM gives an early indication that either project is delayed or not and the project is either over budget or under budget at any particular day by tracking it. Thus, it helps to improve the management control system of a construction project, to detect and control the problems in potential risk areas and to suggest the importance and purpose of monitoring the construction work.
This paper explains the main parameters of the EVM system involved in the calculation of time and cost for construction projects. In this study, the Primavera P6 software is used to deals with the project monitoring process of a seven-storeyed (G+6) faculty building whose construction is in progress at Istanbul, Turkey. A comparison between the planned progress of construction activities and actual progress is performed and the analysis results are interpreted. This case study justifies the benefits of using EVM for project cash flow analysis and forecasting.
Abstract— Execution of engineering projects are tracked against critical metrics such as safety, quality,
delivery cost and inventory. Earned value is a key parameter that helps in assessing delivery (schedule) and cost.
Static shows that 70% of projects are over budget behind schedule, 52% of all projects finish at 189% of their
initial budget and some, after huge investments of time and money, are simply never completed. The rest of this
paper gives a perspective on monitoring project health by Earned value analysis.
This paper presents concepts and explanations about how to apply the Earned Effort Analysis in Projects, showing how the use of this technique should contribute to the project controls management and predictability of the project results. It describes the elements, formulas, indicators, results obtained by method and also presents examples of how the Earned Effort can be implemented.
لمشاهدة ملفات الفيديو
https://www.youtube.com/watch?v=gKbK6kCp7G0&list=PL0CTRdzzWSMuvJ9nKHzyxGAYCapJMQ8_Y&index=15
للمتابعة في جروب المذاكرة
https://www.facebook.com/groups/PMP.SG
CYS EN ISO 50001 is Proven to Generate Significant Energy Savings! (Part 2 of...Arantico Ltd
This presentation, the second in a three part series was presented by Dr. Mike Brogan, COO of Enerit (www.enerit.com) at a seminar entitled CYS EN ISO 50001 in Cyrpus in April 2014.
The presentation covers the following areas;
*What is Systematic Energy Management?
Proven Benefits
*Main Requirements of CYS EN ISO 50001
*Implementation of CYS EN ISO 50001 Energy Management System
*Case Studies
*How ICT Helps
*How do I get started?
*Where am I now?
*And what do I do next?
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
Most of the construction projects are exposed to time and cost overruns due to various factors and this is a major problem. As a solution to this, the Earned Value Management (EVM) method is considered. EVM is a powerful and well-known method used in monitoring and controlling the project. EVM gives an early indication that either project is delayed or not and the project is either over budget or under budget at any particular day by tracking it. Thus, it helps to improve the management control system of a construction project, to detect and control the problems in potential risk areas and to suggest the importance and purpose of monitoring the construction work.
This paper explains the main parameters of the EVM system involved in the calculation of time and cost for construction projects. In this study, the Primavera P6 software is used to deals with the project monitoring process of a seven-storeyed (G+6) faculty building whose construction is in progress at Istanbul, Turkey. A comparison between the planned progress of construction activities and actual progress is performed and the analysis results are interpreted. This case study justifies the benefits of using EVM for project cash flow analysis and forecasting.
Abstract— Execution of engineering projects are tracked against critical metrics such as safety, quality,
delivery cost and inventory. Earned value is a key parameter that helps in assessing delivery (schedule) and cost.
Static shows that 70% of projects are over budget behind schedule, 52% of all projects finish at 189% of their
initial budget and some, after huge investments of time and money, are simply never completed. The rest of this
paper gives a perspective on monitoring project health by Earned value analysis.
This paper presents concepts and explanations about how to apply the Earned Effort Analysis in Projects, showing how the use of this technique should contribute to the project controls management and predictability of the project results. It describes the elements, formulas, indicators, results obtained by method and also presents examples of how the Earned Effort can be implemented.
لمشاهدة ملفات الفيديو
https://www.youtube.com/watch?v=gKbK6kCp7G0&list=PL0CTRdzzWSMuvJ9nKHzyxGAYCapJMQ8_Y&index=15
للمتابعة في جروب المذاكرة
https://www.facebook.com/groups/PMP.SG
CYS EN ISO 50001 is Proven to Generate Significant Energy Savings! (Part 2 of...Arantico Ltd
This presentation, the second in a three part series was presented by Dr. Mike Brogan, COO of Enerit (www.enerit.com) at a seminar entitled CYS EN ISO 50001 in Cyrpus in April 2014.
The presentation covers the following areas;
*What is Systematic Energy Management?
Proven Benefits
*Main Requirements of CYS EN ISO 50001
*Implementation of CYS EN ISO 50001 Energy Management System
*Case Studies
*How ICT Helps
*How do I get started?
*Where am I now?
*And what do I do next?
Project performance tracking analysis and reporting
PR3_final.JCT.AGK.docx
1. BEEF, Inc.
Memorandum
Date: October 16, 2015
To: Drs. James E. Maneval, Elif E. Miskioglu, and Ryan C. Snyder
Project Supervisors, Process Engineering Department
From: Andrew J. Fox, Alexander Kempf, and Joel Toro
CHEG 400 Senior Engineers, Process Engineering Department
Subject: PR3.A9: Project Report 3 Full Draft
Abstract
Our team has continued in the process design and has determined the complete structure of our
design. We have developed a series of goals for each separation section and determined the
necessary separation units to accomplish such a separation. Each unit has been thoroughly
designed and investigated to ensure the achievement of our overall goals. Using a series of
heuristics, the size necessary of each unit was determined and the capital investment and
operating costs of using each unit was calculated. By combining each unit, a complete process
flow diagram was created and evaluated to confirm the technical feasibility of our design. The
financial feasibility of our process was then analyzed determined using net present value and
found to be $18,227,945. Process improvements, mainly energy integration, were evaluated and
found to improve the profitability potential by raising the net present value to $18,972,634.
Based on our analysis, we recommended that our design be implemented.
2.
Background
The Marcellus formation, known colloquially as Marcellus shale, is a sedimentary rock
formation, running from New York to West Virginia. Over millions of years, organic material
trapped in the rock decomposed and, due to the unique conditions within the shale, created an
estimated 1 trillion cubic feet of natural gas. The natural gas found within the formation was
thought to be unobtainable, until the development of hydraulic fracturing, or “fracking”, made
extraction of the gas possible. This natural gas, composed primarily of methane with other trace
components, represents a new source of chemical resources that could potentially be used as a
raw material. Our team has sought to use this potential chemical resource to create a product that
is economically viable and competitive.
Our team evaluated the technical and economic feasibility of the production of chemicals from
Marcellusshale natural gas. Through our previous investigations in PR1 and PR2, we have
developed an appropriate base for further investigation. We have determined that we would
produce chloromethane by chlorinating methane using chlorine gas in a continuous method
operation. After identifying the destinations of each chemical within our process, an
inputoutput structure of our block flow diagram was created with a material balance. Using this,
the annual profit potential for our process was determined and used to select various operating
conditions, leading to the development of the recycle structure of our process, including reactors
and necessary separations sections.
In this memo, our team will complete stages 5 and 6. In Key Finding 1, we develop the specifics
of the separation section, developing the size and design variables necessary to achieve our
separation goals. In Key Finding 2, we consider alternative design possibilities and examine an
energy integration analysis. Finally, we summarize the results and make recommendations for
completing the project.
6.
Goals:
● Achieve a 99% purity of methane in the methane stream
● Limit amount of ethane entering the methane stream
● Minimize the amount of methane in the waste stream
These goals were met by this separation process as shown in the stream table below. All of the
methane was able to be separated into stream S1.3 from the inlet stream of S1.2 with a limited
amount of ethane entering that stream.
Stream Table for S1.2 – Flash Drum: All values in kg/hr.
Stream ID: S1.2 S1.3 S1.4
Total 225.2000 210.2000 14.9800
CH4 204.2261 204.2261 0.0000
C2H6 16.1175 1.9789 14.1386
N2 1.8769 1.8769 0.0000
CO2 2.9486 2.1079 0.8408
We found the flash drum to have a volume of 0.4m3
with a base module cost of $30,125.
Calculations for determining these values is found in Appendix D. The total cost for this
separation section includes the costs of the flash drum, cooler and operating cost of the
refrigeration cycle. The capital cost is $38,383 with an operating cost of $14,216 per year.
After this separation unit, the pure methane stream is mixed with chlorine gas and sent to the
reactor. After the reactor, the product stream exits at a temperature of 440°C and enters
separation section 2.
10.
Component
Solubility
(g/L)
Solubility
(mol/L)
HCl 720 19.7
CH2Cl2 17.5 0.21
CHCl3 8.09 0.07
Chlorine Gas 7.2 0.1
CHCl3 5.325 0.11
Carbon
Dioxide 1.45 0.033
CCl4 0.81 0.0053
Ethane 0.0568 0.0019
Methane 0.0227 0.0014
Nitrogen 0.019 0.00068
Table 3. The solubility of each component of the product stream from the reactor in water
The resulting stream of mainly hydrochloric acid and water is actually a higher concentration of
37% HCl, so we mixed more water with the stream after separation to achieve this concentration
so it could be sold.
In sizing this unit we looked at equilibrium data for hydrochloric acid and water. We were able
to determine a height of the column to be 4.177m. We also needed to know the diameter in order
to get the volume of the unit, which was calculated based on the flow of our gas through the
system and heuristics from Turtin. We calculated a diameter of 0.36m. From this we calculated a
volume for the absorption column to be 0.4m3
. The bare module cost was then calculated to be
$26,623. Calculations for determining the height, diameter, and cost of the column are found in
Appendix D.
From HYSYS we were able to determine a flow of water that we needed for this separation as
well, which adds to the operating costs of this unit. At a flow rate of 50.58 kgmol/hr of H2O with
a price of $0.5735/100 gallons of H2O, we determined an annual cost of $23.84.
13.
Component BP (°C)
CCl4 77.08
CHCl3 62.05
CH2Cl2 39.95
CH3Cl 24.01
Chlorine Gas 33.15
HCl 84.78
Carbon Dioxide 86.58
Ethane 88.61
Methane 161.6
Nitrogen 195.7
Table 2. The boiling points of each component in the product stream from the reactor
Additionally, we looked at sizing the condensers and reboilers for the distillation columns along
with calculating the costs for each. We plan on using liquid nitrogen for the condensers and
saturated steam for the reboilers. The following table shows the surface area and bare module
cost for the condensers and reboilers for each of the distillation columns in this section. The
calculations that achieved these values can be found in Appendix D.
Surface area (m^2) Bare Module Cost
S2.3 Condenser 3.63 $7,166
S2.3 Reboiler 2.4058 $7,915
S2.4 Condenser 14.89 $5211.5
S2.4 Reboiler 14.19 $4966.5
S2.5 Condenser 70.16 $17540
S2.5 Reboiler 102.2 $30660
14.
Key Finding II: Energy Integration and Process Improvements
After completing the base case design (Figure 1), Team 7 carefully examined how we could decrease the
operating costs of the process. Potential areas for cost reduction including energy integration, waste
stream management, reduction of capital costs and reduction of operating (utility) costs.
We looked at the temperatures of all streams, especially ones right before and after heaters and coolers.
The goal of this examination is to decrease our annual costs and to increase the net present value of the
project.
In the creation of the base case (Figure 1), unit and operating cost were highly considered at all times. The
smallest and cheapest units were used when possible (for example, flash drums were first installed and if
they didn’t work, then a distillation column was used). Since the creation of our base case design was so
iterative, there is not much cost reduction that would be further possible in terms of capital cost.
In order to meet our goals of decreasing the annual costs and to increase the net present value of the
project, we completed the following:
1. Identify and assess improvements with respect to energy use
2. Identify and assess improvements with respect to utility costs
Energy Use
Table 1.1: Shows the inlet and outlet temperatures from the heaters and coolers in the base case.
Stream Inlet temp (C)
Outlet temp
(C)
Heat/Cool load
kJ/hr
S1
Cooler Natural gas feed 25 139 84000
S1
Heater
HCl and recycle from heat
exchanger 3 45.6 440 930000
S2
Cooler HCl and recycle 440 50 1400000
S2
Heater
Reactor feed from heat
exchanger 1 170 25 800000
Net energy
requirement 246000
15.
Table 1.2: Shows the streams that are crossed in heat exchangers and their inlet and outlet temperatures in
the energy integration case.
Cold stream
Cold
stream
inlet temp
(C)
Cold
stream
outlet
temp (C) Hot stream
Hot
stream
inlet temp
(C)
Hot stream
outlet temp
(C)
Heat
exchanger 1 Reactor feed 44.4 430 Reactor products 430 68
Heat
exchanger 2
HCl and
recycle from
heat
exchanger 3 159 81.7
Reactor products
from heat
exchanger 1 68 50
Heat
exchanger 3
HCl and
recycle 171 159 Natural gas feed 25 139
Fired heater 1
Reactor feed
from heat
exchanger 1 430 440
Ethane stream
from natural gas
purification
This
stream is
burned
Exhaust is
vented to
atmosphere
Table 1.2 shows the inlet and outlet stream temperatures and how the heat exchangers reached their
required temperatures. We did not need to use composite curves in this energy integration since there was
enough energy available to eliminate all of the heaters and coolers and replace them with the heat
exchangers. We chose which streams to cross through an iterative process in HYSYS. There are a lot of
very high and very low temperature streams which made crossing them to exchange heat a relatively
simple process. There was only one stream that was not able to be fully heated by crossing it with other
streams, so this was dealt with by heating it with a fired heater which burned an ethane waste stream.
Quantitatively, this can be shown by the net energy input required for all of the heaters and coolers in the
base case. The 2.5x105
kJ/hr of energy that is needed (assuming perfect energy integration) is more than
covered by the direct fired heater. In the energy integration case, the direct fired heater is able to deliver
1.1x106
kJ/hr of heat.
All of the heat exchangers and direct fired heaters were added in order to replace heaters and coolers that
were initially in the base case. Making changes in this manner removes the capital cost of the heaters and
coolers, as well as the utility costs of them. However it does add the capital cost of the heat exchanger and
direct fired heater. As shown by the present value of the project in Table 3, this is a profitable
replacement.
17.
Figure 2: A process flow diagram showing how streams have been rerouted to cross other streams in an
effort to reduce overall costs.
18.
S1.1 Heat Exchanger 1:
Figure 3: A portion of Figure 2 showing the streams involved with heat exchanger 1.
Goals: This heat exchanger serves to cool the natural gas feed stream down while heating up the distillate
(HCl and recycle) stream of the first distillation column after the reactor.
This heat exchanger is replacing a heater that would have heated the HCl and recycle stream, as well as a
cooler that would have cooled the natural gas feed stream.
S1.5 Heat Exchanger 2:
Figure 4: A portion of Figure 2 showing the streams involved with heat exchanger 2.
19.
Goals: The goals of this heat exchanger are essentially to heat the reactor feed stream with the product
stream.
Additional required heating of the reactor feed stream is added by a direct fired heater discussed below.
This replaces a heater that would have heated the reactor feed stream and a cooler that would have cooled
the products stream.
S2.1 Heat Exchanger 3:
Figure 5: A portion of figure 2(from above) showing the streams involved with heat exchanger 3.
Goals: The goals of this heat exchanger are to further cool the reactor products, or first distillation column
feed, with the distillate stream from the first distillation column.
This heat exchanger replaces a cooler that would cool the feed to the first distillation column, as well as a
heater that would have heated the distillate stream.
22.
Table 2.2: Utility breakdown and percentage of total utility cost for energy integration. Utilities that are
less than 0.5% of the total are not shown here. This includes nitrogen and steam costs.
Unit Utility Annual cost of utility
Percentage of
total
Waste
Waste
disposal $1,094,138 94.96509%
Water pipe service charge Water general $38,664 3.35582%
Compressor Electricity $19,254.48 1.67118%
Net Utilities $1,152,148
As shown by Tables 2.1 and 2.2, the energy integration did decrease the net utility cost by approximately
$200,000. However, as shown in Table 2.2, the primary utility cost in this design is the waste disposal. As
discussed above in the Waste Stream Management section, it would be very difficult to separate the waste
stream into valuable byproducts, adding multiple large distillation columns as well as adding the utility
costs for those units.
Net Impact of Energy Integration:
The costing information described below only represents the changes that occurred in capital costs and
utility costs due to the energy integration, as well as the overall project costs (see appendix C). To see a
detailed breakdown of how the calculations were carried out, please refer to Project Report 2.
Table 3: Cost comparison between the base case and the energy integrated case. This table only shows the
utilities that had a significant change between the base case and energy integration case.
Base case Energy integration
FCI $7,299,822 $8,417,570
Steam $5,167 $59
Electricity $238,205 $19,254
Water $38,688 $38,688
Net Utilities $1,376,224 $1,152,148
NPV $18,227,945 $18,972,634
In an effort to increase the overall efficiency of our plant, decrease our utility costs and therefore make the
overall process more profitable, Team 7 has closely examined ways to save energy, decrease the amount
of utilities used, decrease waste disposal costs, and decrease the capital cost of the equipment. We have
accomplished this by using different temperature streams to heat or cool each other, rather than paying for
a heater and a cooler. We also utilized direct fired heaters to burn our waste streams and provide further
heating.
As shown by Table 3, the net present value of the project increases the capital cost of the units, but it
decreases the utility costs. Additionally, it decreases electricity consumption which is more
environmentally friendly. Overall there is a relatively small change in the net present value of the project,
23.
and increase of roughly 4%. This means that the project is more profitable after the energy integration, as
well as more environmentally friendly, meeting our goal of becoming more profitable.
Waste Stream Management
Team 7 also examined our waste streams, and how they can best be dealt with. From the base case design
(Figure 1), there is stream (S1.s4) that will be sent to a flare, and two streams (S3.s1 and S3.s6) that need
to be disposed of as hazardous waste. They could not be burned since they are primarily chloromethane.
The flared streams provide energy to the fired heaters currently in our process. As for the waste streams,
the only alternative option would be to separate them further and sell the products. However, in order to
purify the stream to a high enough purity for sale, two additional distillation columns that were larger than
any other columns in the system would have to be added. Since these products are not our primary
product and since they would have had an enormous capital cost, we chose to simply dispose of the waste.
28.
Fixed capital investment (FCI) $7,299,822 =total unit cost * 1.2 * 1.5
Cl2
kgmol/hr 15.76 from HYSYS
$/kgmol $15 from Alibaba.com
7 day supply $39,715 =kgmol/hr * $/kgmol * 24hr * 7 days
Natural Gas
kgmol/hr 13.40 from HYSYS
$/kgmol $0.0017 from Alibaba.com
7 day supply $4 =kgmol/hr * $/kgmol * 24hr * 7 days
Feed inventories (FI) $39,719
=7 day supply Cl2 + 7 day supply natural
gas
Working capital (WC) $777,645 =1.2 * FI + 0.1 * FCI
36.
The height of the vessel (h) was then calculated with the equation below assuming a liquid
residence time of 5 minutes and that the liquid level is about the midpoint of the vessel height:
h = A
2 (5 min) (liquid flow rate, in m /min)* *
3
With the height and diameter of the vessel the volume (V) can be calculated as follows:
( ) hV = π 2
D 2
We calculated the flash drum to have a volume of 0.4m3
.
Flash Drum Cost Summary
We found the flash drum to have a volume of 0.4m3
. Looking in Table A.1 of Turton we
determined the purchased equipment cost at ambient operating pressure and using carbon steel
construction with the following equation:
C log (A) [log (A) ]log10
0
p = K1 + K2 10 + K3 10
2
where:
A = 0.4m3
K1 = 3.4974
K2 = 0.4485
K3 = 0.1074
The bare module cost (CBM) for this vessel has to account for its material factors (FM) and
pressure factor (FP).
(B F F )CBM = C0
p 1 + B2 M P
FP,vessel = 0.0063
+0.00315(P+1)D
2[850−0.6(P+1)]
where:
D = 0.46m
B1 = 2.25
B2 = 1.82
FM = 9.4
P = 3.01 barg
The base module cost (CBM) was found to be $30,125.
S1 Cooler Size Summary
37.
Using the following set of equations as well as information from HYSYS, we were able to size
the heat exchanger between liquid nitrogen and our natural gas stream.
A
Q
= dT
+∑
1
hi k
x
pipe
hi = D
k Nui
u .023Re PrN = 0 0.8 0.3
eR = μ
ρvD
r p( )P = C k
μ
Td =
ln ( ) T −Tsat in
T −Tsat out
(T −T )−(T −T )sat out sat in
A = ( )A
Q
Qneeded
where:
i = the liquid nitrogen stream and natural gas stream
kpipe = 400 W/mC
D = 0.1407m
x = 0.0021m
Qneeded, viscosity ( ), thermal conductivity (k), density ( ). Tin, and Tout data was found from ourμ ρ
HYSYS simulation for each stream.
We calculated a surface area of 5.02m2
for this heat exchanger.
S1 Cooler Cost Summary – Capital Cost
Knowing the surface area (A) of the heat exchanger, we used Figure A.5 in Appendix A of
Turtin to find a Cp
0
/A($/m2
) where:
C0
p =
C0
p
A( )$
m2
* A
To calculate the bare module cost (CBM) of this heat exchanger we used the following equation:
(B F F )CBM = C0
p 1 + B2 M P
where:
B1 = 1.74
39.
Unit Type: Distillation Column
Sizing Basis: Volume, m3
Unit Diagram
Stream Table: All values in kg/hr.
Stream ID: S2.s2 S2.s3 Flare S2.s7
Total 1759.6755 1025.1873 1.0465 733.4417
CH4 413.1240 412.6481 0.4759 0.0000
C2H6 9.9877 9.9876 0.0000 0.0001
N2 11.8986 11.3281 0.5705 0.0000
CO2 2.1079 2.1078 0.0000 0.0001
Cl2 66.9121 15.8493 0.0000 51.0628
CH3Cl 349.4269 33.9080 0.0000 315.5189
CH2Cl2 259.5216 0.0001 0.0000 259.5215
CHCl3 85.1140 0.0000 0.0000 85.1140
CCl4 15.6690 0.0000 0.0000 15.9960
HCl 545.9137 539.3583 0.0001 6.5553
S2.2 – Distillation Column Size Summary
Column Diameter = 1.19m
Number of Trays = 13
Column Height = 6.5m (assuming the distance between each tray is 0.5m)
olumn V olume π olumn HeightC = * ( )2
Column Diameter 2
* C
Column Volume = 7.2m3
S2.2 – Distillation Column Cost Summary
40.
We found the distillation column to have a volume of 7.2m3
. Looking in Table A.1 of Turton we
determined the purchased equipment cost at ambient operating pressure and using carbon steel
construction with the following equation:
C log (A) [log (A) ]log10
0
p = K1 + K2 10 + K3 10
2
where:
A = 7.2m3
K1 = 3.4974
K2 = 0.4485
K3 = 0.1074
The bare module cost (CBM) for this vessel has to account for its material factors (FM) and
pressure factor (FP).
(B F F )CBM = C0
p 1 + B2 M P
FP,vessel = 0.0063
+0.00315(P+1)D
2[850−0.6(P+1)]
where
D = 1.19m
B1 = 2.25
B2 = 1.82
FM = 9.4
P = 3.01 barg
The base module cost (CBM) was found to be $170,365.
S2.2 Condenser and Reboiler Size Summary
Using the following set of equations as well as information from HYSYS, we were able to size
the condensers as well as reboilers in the distillation column. For the condensers we used liquid
nitrogen and for the reboilers we used saturated steam.
A
Q
= dT
+∑
1
hi k
x
pipe
hi = D
k Nui
u .023Re PrN = 0 0.8 0.3
eR = μ
ρvD
r p( )P = C k
μ
41.
Td =
ln ( ) T −Tsat in
T −Tsat out
(T −T )−(T −T )sat out sat in
A = ( )A
Q
Qneeded
where:
i = each stream in the condenser or reboiler
kpipe = 400 W/mC
D = 0.1407m
x = 0.0021m
Qneeded, viscosity ( ), thermal conductivity (k), density ( ). Tin, and Tout data was found from ourμ ρ
HYSYS simulation for each exit stream of either the condenser or reboiler.
From this set of equation we were able to calculate the surface area of the heat exchanger for the
reboiler and condenser in the distillation column. The reboiler surface area is 1.2m2
, and the
condenser is 3.55m2
.
S2.2 Condenser and Reboiler Cost Summary
Knowing the surface area (A) of the condenser and reboiler, we used Figure A.5 in Appendix A
of Turtin to find a Cp
0
/A($/m2
) where:
C0
p =
C0
p
A( )$
m2
* A
To calculate the bare module cost (CBM) of this heat exchanger we used the following equation:
(B F F )CBM = C0
p 1 + B2 M P
where:
B1 = 1.74
B2 = 1.55
FM = 1
FP = 1
We calculated a bare module cost of $7,008 for the condenser, and $4,145 for the reboiler.
Total Capital Coat = $181,518
Project: Chloromethane synthesis from methane
Unit Name/ID: S2.2 Absorption Column
Unit Type: Absorption Column
42.
Sizing Basis: Volume, m3
Unit Diagram
Stream Table: All values in kg/hr.
Stream ID: S2.s4 S2.fH2O S2.s5 S2.p1
Total 1025.1874 749.0805 478.7566 1295.5112
CH4 412.6481 0.0000 412.4831 0.1651
C2H6 9.9876 0.0000 8.9010 1.0867
N2 11.3281 0.0000 11.1718 0.1563
CO2 2.1078 0.0000 0.0000 2.1078
Cl2 15.8493 0.0000 12.2927 3.5566
CH3Cl 33.9080 0.0000 33.9080 0.0000
HCl 539.3583 0.0000 0.0000 539.3583
H2O 0.0000 749.0805 0.0000 749.0805
S2.2 Absorption Column Size Summary
The following set of equation was used in order to determine the height of the absorption
column.
x )LM( * − x = ln ( ) (x2 −x2)*
(x1 −x1)*
(x1 −x1)−(x2 −x2)* *
LM(1 )− x *
= ln ( ) (1−x1)
(1−x1 )*
(1−x1)−(1−x1 )*
.6634Kya = 0 * L0.82
TUN = (x1−x2)
(x −x)LM*
TUH = L
K (1−x) LMya*
*
43.
TU TUz = H * N
where:
x1 = 0.262
x2 = 0
x1*
= 0.9693
x2*
= 0.9693
L = 41.6 kgmol/hr
We found that the height of the column (z) is 4.177m.
We then used the following equation to determine the diameter of the column.
D = √ π
( )3600
gas flow, in kg/hr
average gas density, in 1kg
m3* s
m
* 2
The diameter of the column was calculated to be 0.36m.
We then used the following equation to determine the volume of the absorption column.
πV = * ( )2
D 2
* z
The column has a volume of 0.4 m3
.
S2.2 Absorption Column Capital Cost Summary
We found the absorption column to have a volume of 0.4m3
. Looking in Table A.1 of Turton we
determined the purchased equipment cost at ambient operating pressure and using carbon steel
construction with the following equation:
C log (A) [log (A) ]log10
0
p = K1 + K2 10 + K3 10
2
where:
A = 0.4m3
K1 = 3.4974
K2 = 0.4485
K3 = 0.1074
The bare module cost (CBM) for this vessel has to account for its material factors (FM) and
pressure factor (FP).
(B F F )CBM = C0
p 1 + B2 M P
FP,vessel = 0.0063
+0.00315(P+1)D
2[850−0.6(P+1)]
45.
Unit Diagram
Stream Table: All values in kg/hr.
Stream ID: S2.s7 S3.s1 S3.s2
Total 733.4417 57.2714 676.1703
Cl2 51.0628 49.8812 1.1815
CH3Cl 315.5189 0.8347 314.6842
CH2Cl2 259.5215 0.0000 259.5215
CHCl3 85.1140 0.0000 85.1140
CCl4 15.6690 0.0000 15.6690
HCl 6.5553 6.5553 0.0000
S3.1 – Distillation Column Size Summary
Column Diameter = 1.193m
Number of Trays = 61
Column Height = 30.5m (assuming the distance between each tray is 0.5m)
olumn V olume π olumn HeightC = * ( )2
Column Diameter 2
* C
Column Volume = 34.1m3
S3.1 – Distillation Column Cost Summary
We found the distillation column to have a volume of 34.1m3
. Looking in Table A.1 of Turton
we determined the purchased equipment cost at ambient operating pressure and using carbon
steel construction with the following equation:
46.
C log (A) [log (A) ]log10
0
p = K1 + K2 10 + K3 10
2
where:
A = 34.1m3
K1 = 3.4974
K2 = 0.4485
K3 = 0.1074
The bare module cost (CBM) for this vessel has to account for its material factors (FM) and
pressure factor (FP).
(B F F )CBM = C0
p 1 + B2 M P
FP,vessel = 0.0063
+0.00315(P+1)D
2[850−0.6(P+1)]
where
D = 1.193m
B1 = 2.25
B2 = 1.82
FM = 9.4
P = 3.01 barg
The base module cost (CBM) was found to be $509,670
S3.1 Condenser and Reboiler Size Summary
Using the following set of equations as well as information from HYSYS, we were able to size
the condensers as well as reboilers in the distillation column. For the condensers we used liquid
nitrogen and for the reboilers we used saturated steam.
A
Q
= dT
+∑
1
hi k
x
pipe
hi = D
k Nui
u .023Re PrN = 0 0.8 0.3
eR = μ
ρvD
r p( )P = C k
μ
Td =
ln ( ) T −Tsat in
T −Tsat out
(T −T )−(T −T )sat out sat in
47.
A = ( )A
Q
Qneeded
where:
i = each stream in the condenser or reboiler
kpipe = 400 W/mC
D = 0.1407m
x = 0.0021m
Qneeded, viscosity ( ), thermal conductivity (k), density ( ). Tin, and Tout data was found from ourμ ρ
HYSYS simulation for each exit stream of either the condenser or reboiler.
From this set of equation we were able to calculate the surface area of the heat exchanger for the
reboiler and condenser in the distillation column. The reboiler surface area is 2.4m2
, and the
condenser is 3.63m2
.
S3.1 Condenser and Reboiler Cost Summary
Knowing the surface area (A) of the condenser and reboiler, we used Figure A.5 in Appendix A
of Turtin to find a Cp
0
/A($/m2
) where:
C0
p =
C0
p
A( )$
m2
* A
To calculate the bare module cost (CBM) of this heat exchanger we used the following equation:
(B F F )CBM = C0
p 1 + B2 M P
where:
B1 = 1.74
B2 = 1.55
FM = 1
FP = 1
We calculated a bare module cost of $7,166 for the condenser, and $7,915 for the reboiler.
Total Capital Coat = $524,751
Project: Chloromethane synthesis from methane
Unit Name/ID: S3.2 Distillation Column
Unit Type: Distillation Column
Sizing Basis: Volume, m3
Unit Diagram
48.
Stream Table: All values in kg/hr.
Stream ID: S3.s2 S3.s3 S3.s4
Total 676.1703 316.8983 359.2720
Cl2 1.1815 1.1810 0.0005
CH3Cl 314.6842 314.4740 0.2102
CH2Cl2 259.5215 1.2432 258.2783
CHCl3 85.1140 0.0000 85.1140
CCl4 15.6690 0.0000 15.6690
S3.2 – Distillation Column Size Summary
Column Diameter = 1.193m
Number of Trays = 33
Column Height = 16.5m (assuming the distance between each tray is 0.5m)
olumn V olume π olumn HeightC = * ( )2
Column Diameter 2
* C
Column Volume = 18.4m3
S3.2 – Distillation Column Cost Summary
We found the distillation column to have a volume of 18.4m3
. Looking in Table A.1 of Turton
we determined the purchased equipment cost at ambient operating pressure and using carbon
steel construction with the following equation:
C log (A) [log (A) ]log10
0
p = K1 + K2 10 + K3 10
2
where:
A = 18.4m3
K1 = 3.4974
K2 = 0.4485
K3 = 0.1074
49.
The bare module cost (CBM) for this vessel has to account for its material factors (FM) and
pressure factor (FP).
(B F F )CBM = C0
p 1 + B2 M P
FP,vessel = 0.0063
+0.00315(P+1)D
2[850−0.6(P+1)]
where
D = 1.193m
B1 = 2.25
B2 = 1.82
FM = 9.4
P = 3.01 barg
The base module cost (CBM) was found to be $287,931
S3.2 Condenser and Reboiler Size Summary
Using the following set of equations as well as information from HYSYS, we were able to size
the condensers as well as reboilers in the distillation column. For the condensers we used liquid
nitrogen and for the reboilers we used saturated steam.
A
Q
= dT
+∑
1
hi k
x
pipe
hi = D
k Nui
u .023Re PrN = 0 0.8 0.3
eR = μ
ρvD
r p( )P = C k
μ
Td =
ln ( ) T −Tsat in
T −Tsat out
(T −T )−(T −T )sat out sat in
A = ( )A
Q
Qneeded
where:
i = each stream in the condenser or reboiler
kpipe = 400 W/mC
D = 0.1407m
x = 0.0021m
50.
Qneeded, viscosity ( ), thermal conductivity (k), density ( ). Tin, and Tout data was found from ourμ ρ
HYSYS simulation for each exit stream of either the condenser or reboiler.
From this set of equation we were able to calculate the surface area of the heat exchanger for the
reboiler and condenser in the distillation column. The reboiler surface area is 14.19m2
, and the
condenser is 14.89m2
.
S3.2 Condenser and Reboiler Cost Summary
Knowing the surface area (A) of the condenser and reboiler, we used Figure A.5 in Appendix A
of Turtin to find a Cp
0
/A($/m2
) where:
C0
p =
C0
p
A( )$
m2
* A
To calculate the bare module cost (CBM) of this heat exchanger we used the following equation:
(B F F )CBM = C0
p 1 + B2 M P
where:
B1 = 1.74
B2 = 1.55
FM = 1
FP = 1
We calculated a bare module cost of $17,146 for the condenser, and $16,340 for the reboiler.
Total Capital Coat = $321,417
Project: Chloromethane synthesis from methane
Unit Name/ID: S3.3 Distillation Column
Unit Type: Distillation Column
Sizing Basis: Volume, m3
51.
Unit Diagram
Stream Table: All values in kg/hr.
Stream ID: S3.s4 S3.s5 S3.s6
Total 359.2720 254.7190 104.5531
Cl2 0.0005 0.0005 0.0000
CH3Cl 0.2102 0.2102 0.0000
CH2Cl2 258.2783 254.2844 3.9940
CHCl3 85.1140 0.1996 84.9144
CCl4 15.6690 0.0243 15.6447
S3.3 – Distillation Column Size Summary
Column Diameter = 1.193m
Number of Trays = 73
Column Height = 36.5m (assuming the distance between each tray is 0.5m)
olumn V olume π olumn HeightC = * ( )2
Column Diameter 2
* C
Column Volume = 40.8m3
S3.3 – Distillation Column Cost Summary
We found the distillation column to have a volume of 40.8m3
. Looking in Table A.1 of Turton
we determined the purchased equipment cost at ambient operating pressure and using carbon
steel construction with the following equation:
C log (A) [log (A) ]log10
0
p = K1 + K2 10 + K3 10
2
where:
A = 40.8m3
K1 = 3.4974
K2 = 0.4485
K3 = 0.1074
52.
The bare module cost (CBM) for this vessel has to account for its material factors (FM) and
pressure factor (FP).
(B F F )CBM = C0
p 1 + B2 M P
FP,vessel = 0.0063
+0.00315(P+1)D
2[850−0.6(P+1)]
where
D = 1.193m
B1 = 2.25
B2 = 1.82
FM = 9.4
P = 3.01 barg
The base module cost (CBM) was found to be $509,676
S3.3 Condenser and Reboiler Size Summary
Using the following set of equations as well as information from HYSYS, we were able to size
the condensers as well as reboilers in the distillation column. For the condensers we used liquid
nitrogen and for the reboilers we used saturated steam.
A
Q
= dT
+∑
1
hi k
x
pipe
hi = D
k Nui
u .023Re PrN = 0 0.8 0.3
eR = μ
ρvD
r p( )P = C k
μ
Td =
ln ( ) T −Tsat in
T −Tsat out
(T −T )−(T −T )sat out sat in
A = ( )A
Q
Qneeded
where:
i = each stream in the condenser or reboiler
kpipe = 400 W/mC
D = 0.1407m
x = 0.0021m
53.
Qneeded, viscosity ( ), thermal conductivity (k), density ( ). Tin, and Tout data was found from ourμ ρ
HYSYS simulation for each exit stream of either the condenser or reboiler.
From this set of equation we were able to calculate the surface area of the heat exchanger for the
reboiler and condenser in the distillation column. The reboiler surface area is 102.2m2
, and the
condenser is 70.16m2
.
S3.3 Condenser and Reboiler Cost Summary
Knowing the surface area (A) of the condenser and reboiler, we used Figure A.5 in Appendix A
of Turtin to find a Cp
0
/A($/m2
) where:
C0
p =
C0
p
A( )$
m2
* A
To calculate the bare module cost (CBM) of this heat exchanger we used the following equation:
(B F F )CBM = C0
p 1 + B2 M P
where:
B1 = 1.74
B2 = 1.55
FM = 1
FP = 1
We calculated a bare module cost of $57,707 for the condenser, and $100,871 for the reboiler.
Total Capital Coat = $668,254