SlideShare a Scribd company logo
BEEF, Inc. 
Memorandum 
 
 
Date: October 16, 2015 
 
To: Drs. James E. Maneval, Elif E. Miskioglu, and Ryan C. Snyder 
Project Supervisors, Process Engineering Department 
 
From: Andrew J. Fox, Alexander Kempf, and Joel Toro 
CHEG 400 Senior Engineers, Process Engineering Department 
 
Subject: PR3.A9: Project Report 3 Full Draft 
 
 
 
Abstract 
 
Our team has continued in the process design and has determined the complete structure of our 
design. We have developed a series of goals for each separation section and determined the 
necessary separation units to accomplish such a separation. Each unit has been thoroughly 
designed and investigated to ensure the achievement of our overall goals. Using a series of 
heuristics, the size necessary of each unit was determined and the capital investment and 
operating costs of using each unit was calculated. By combining each unit, a complete process 
flow diagram was created and evaluated to confirm the technical feasibility of our design. The 
financial feasibility of our process was then analyzed determined using net present value and 
found to be $18,227,945. Process improvements, mainly energy integration, were evaluated and 
found to improve the profitability potential by raising the net present value to $18,972,634. 
Based on our analysis, we recommended that our design be implemented. 
 
 
 
 
Background 
 
The Marcellus formation, known colloquially as Marcellus shale, is a sedimentary rock                       
formation, running from New York to West Virginia. Over millions of years, organic material                           
trapped in the rock decomposed and, due to the unique conditions within the shale, created an                               
estimated 1 trillion cubic feet of natural gas. The natural gas found within the formation was                               
thought to be unobtainable, until the development of hydraulic fracturing, or “fracking”, made                         
extraction of the gas possible. This natural gas, composed primarily of methane with other trace                             
components, represents a new source of chemical resources that could potentially be used as a                             
raw material. Our team has sought to use this potential chemical resource to create a product that                                 
is economically viable and competitive. 
 
Our team evaluated the technical and economic feasibility of the production of chemicals from 
Marcellus­shale natural gas. Through our previous investigations in PR1 and PR2, we have 
developed an appropriate base for further investigation. We have determined that we would 
produce chloromethane by chlorinating methane using chlorine gas in a continuous method 
operation.  After identifying the destinations of each chemical within our process, an 
input­output structure of our block flow diagram was created with a material balance. Using this, 
the annual profit potential for our process was determined and used to select various operating 
conditions, leading to the development of the recycle structure of our process, including reactors 
and necessary separations sections. 
 
In this memo, our team will complete stages 5 and 6. In Key Finding 1, we develop the specifics 
of the separation section, developing the size and design variables necessary to achieve our 
separation goals. In Key Finding 2, we consider alternative design possibilities and examine an 
energy integration analysis. Finally, we summarize the results and make recommendations for 
completing the project. 
 
 
 
Key Finding I: Separation 
 
We developed a base case design for our system that is based on the results of our PR2 block 
flow diagram. The base case process flow diagram is shown in Figure 1 on the following page. 
Throughout this flow diagram there are many separation units that are necessary. Key Finding 1 
aims to address these separation units throughout our process. These units aim to separate out the 
necessary components that we need either for a relatively pure feed into our reactor, to separate 
out any components that can be recycled, or to separate out our products. We have broken the 
units down into three different sections that each focus on one of these goals. Each section 
contains the individual separator units, their specific goals, and the key data necessary to run 
each section.  
 
Separator Section 1: 
 
Figure 2. Process flow diagram of separation section 1. 
 
S1 Cooler 
The flash drum works by separating a gaseous stream from a liquid stream based on the boiling 
points of the components. The key data for performing this separation is using the boiling points 
of the components of the natural gas stream. As shown below in Table 1, there is a sharp divide 
between the boiling points of carbon dioxide and methane (­60.86 and ­141.2°C respectively). 
Using this information, the separation can be conducted using a flash drum instead of other 
separation methods, where a temperature gradient is not required. The separation will retain a 
small amount of nitrogen in the stream, which is acceptable as the 99% purity of methane can 
still be achieved and the nitrogen does not affect the reaction. 
Component  BP (°C) 
Ethane  ­57.78 
Carbon Dioxide  ­60.86 
Methane  ­141.2 
Nitrogen  ­181.4 
 
Table 1:​ The boiling points of each component in the original natural gas stream at 60 psia. 
 
 
 
 
Figure 1: A process flow diagram showing the initial base case design of the process.  
 
 
In order to obtain the required temperature for this separation, a working fluid must be used that 
can reach these temperatures. We decided to use liquid nitrogen which is able to reach a 
temperature of 195.8°C at 1 atm, allowing it to fully cool our natural gas stream. We would 
implement a refrigeration unit on­site to keep recycling the cryogenic nitrogen for cooling 
throughout not just this cooling, but others throughout our process as well. The refrigeration flow 
diagram is shown below in Figure 3. This is blown­up version of the S1 Cooler unit in our PFD. 
 
 
Figure 3. Process flow diagram for the refrigeration system of S1 Cooler. 
 
Streams 4.1­4.4 contain the liquid nitrogen while streams S1.1 and S1.2 contain our natural gas 
feed. In the evaporator the natural gas stream enters at 25°C and exits at ­139°C while liquid 
nitrogen enters at ­195.8°C to cool the natural gas stream. As the nitrogen goes through its 
refrigeration process, it evaporates into a vapor, compresses to a higher pressure, is cooled with a 
another stream of working fluid which turns it into a liquid, expands to atmospheric pressure to 
its saturation temperature of ­195.8°C and repeats the cycle. In order to determine the cost of 
implementing this we looked at the Carnot efficiency of this mechanical refrigeration system 
which can be expressed by the reversible coefficient of performance. After determining the 
temperatures that we would need for the condenser and evaporator we used HYSYS to model 
this system as best as it could. We were able to get an evaporator heat load from HYSYS and 
calculate the work required for this cycle. Knowing this we were able to take our value of 
$0.07/hr of electricity and calculate an annual cost of $14,216 for this refrigeration unit. The 
detailed calculations for this are located in Appendix D. 
 
S1.2 ­ Flash drum 
We have chosen to use a flash drum as our first separation unit in the process. The natural gas 
stream contains methane, ethane, nitrogen, and carbon dioxide. The drum aims to separate our 
natural gas feed stream into two streams, one with a high purity of methane while the other 
contains the primary unwanted component of ethane that would react in our reactor, creating 
undesirable chloroethanes. A list of the main goals for this separation is below. 
 
 
 
 
 
Goals: 
● Achieve a 99% purity of methane in the methane stream 
● Limit amount of ethane entering the methane stream 
● Minimize the amount of methane in the waste stream 
 
These goals were met by this separation process as shown in the stream table below. All of the 
methane was able to be separated into stream S1.3 from the inlet stream of S1.2 with a limited 
amount of ethane entering that stream. 
 
Stream Table for S1.2 – Flash Drum: ​All values in kg/hr. 
Stream ID:  S1.2  S1.3  S1.4 
Total  225.2000  210.2000  14.9800 
CH4  204.2261  204.2261  0.0000 
C2H6  16.1175  1.9789  14.1386 
N2  1.8769  1.8769  0.0000 
CO2  2.9486  2.1079  0.8408 
 
We found the flash drum to have a volume of 0.4m​3​
 with a base module cost of $30,125. 
Calculations for determining these values is found in Appendix D. The total cost for this 
separation section includes the costs of the flash drum, cooler and operating cost of the 
refrigeration cycle. The capital cost is $38,383 with an operating cost of $14,216 per year. 
 
After this separation unit, the pure methane stream is mixed with chlorine gas and sent to the 
reactor. After the reactor, the product stream exits at a temperature of 440°C and enters 
separation section 2. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Separator Section 2: 
 
 
Figure 4. Process flow diagram of separation section 2. 
 
S2 Cooler  
The product stream exits the reactor at 440°C and needs to be cooled before it enters the first 
distillation column. This is because we need to get the stream to a temperature where we can get 
a separation of our chloromethane products in stream S2.s7 and recycle components in stream 
S2.s3. This cooler uses the same refrigeration cycle system as the S1 Cooler with liquid nitrogen 
as the working fluid. The process flow diagram is depicted below in Figure 5.  
 
Figure 5. Process flow diagram for the refrigeration system of S2 Cooler. 
 
 
Streams 6.1­6.4 contain the liquid nitrogen while streams S2.s1 and S2.s2 contain our post 
reactor products stream. In the evaporator the products stream enters at 440°C and exits at ­50°C 
while liquid nitrogen enters at ­195.8°C to cool the stream. In order to determine the cost of 
implementing this, the Carnot efficiency of this mechanical refrigeration system was again 
calculated from the same equations used in the S1 Cooler section. After determining the 
temperatures that we would need for the condenser and evaporator we used HYSYS to model 
this system as best as it could. We were able to get an evaporator heat load from HYSYS and 
calculate the work required for this cycle. Knowing this we were able to take our value of 
$0.07/hr of electricity and calculate an annual cost of $204,735 for this refrigeration unit.  
 
S2.2 ­ Distillation column 
We chose to use a distillation column for the separation that occurs after our reactor since we 
require a temperature gradient throughout to get pure products in the distillate and bottoms 
streams.  
 
Goals: 
● Separate the chlorinated methane products from the remaining components 
 
As seen in the stream table below the chlorinated methane products are separated from stream 
S2.s2 into S2.s7 while there is some chloromethane that goes into stream S2.s3. This stream is 
recycled back into the reactor which does not go to waste and ends up being part of our final 
products streams.  
 
 
Stream Table for S2.2 – Distillation Column:​ All values in kg/hr. 
Stream ID:  S2.s2  S2.s3  Flare  S2.s7 
Total  1759.6755  1025.1873  1.0465  733.4417 
CH4  413.1240  412.6481  0.4759  0.0000 
C2H6  9.9877  9.9876  0.0000  0.0001 
N2  11.8986  11.3281  0.5705  0.0000 
CO2  2.1079  2.1078  0.0000  0.0001 
Cl2  66.9121  15.8493  0.0000  51.0628 
CH3Cl  349.4269  33.9080  0.0000  315.5189 
CH2Cl2  259.5216  0.0001  0.0000  259.5215 
CHCl3  85.1140  0.0000  0.0000  85.1140 
CCl4  15.6690  0.0000  0.0000  15.9960 
HCl  545.9137  539.3583  0.0001  6.5553 
 
 
 
From our HYSYS simulation we were able to size this distillation column as well as the other 
distillation columns that are present throughout separation section 3. We found this distillation 
column to have a volume of 7.2 m​3​
 with 13 trays. The bare module costing calculations can be 
found in Appendix D, where we calculated a cost of $170,365.  
 
 
 
Additionally, we looked at sizing the condenser and reboiler for the distillation column along 
with calculating the costs for each. We plan on using liquid nitrogen for the condenser and 
saturated steam for the reboiler. We found that the reboiler surface area is 1.2m​2​
, and the 
condenser is 3.55m​2​
. From these values we calculated the cost of each of these and found them to 
be a bare module cost of $7,008 for the condenser, and $4,145 for the reboiler. These 
calculations can be found in Appendix D. 
 
S2.2 ­ Absorption column 
An absorption column is necessary here to watch out as much of the hydrochloric acid in the 
recycle stream as possible. This is simply because we do not want HCl to get into the reactor at 
high concentrations. The goals for this section are listed below. 
 
Goals:  
● Remove as much HCl as reasonably possible from waste stream in order to recycle the 
valuable reactant.  
● Achieve a purity of 37% hydrochloric acid in the outlet stream 
 
As seen in the stream table below for the absorption column we were actually able to 
successfully separate out all of the HCl from stream S2.s4 into stream S2.s5 with stream S2.p1 as 
the recycle stream.  
 
 
 
Stream Table for S2.2 – Absorption Column:​ All values in kg/hr. 
Stream ID:  S2.s4  S2.fH2O  S2.s5  S2.p1 
Total  1025.1874  749.0805  478.7566  1295.5112 
CH4  412.6481  0.0000  412.4831  0.1651 
C2H6  9.9876  0.0000  8.9010  1.0867 
N2  11.3281  0.0000  11.1718  0.1563 
CO2  2.1078  0.0000  0.0000  2.1078 
Cl2  15.8493  0.0000  12.2927  3.5566 
CH3Cl  33.9080  0.0000  33.9080  0.0000 
HCl  539.3583  0.0000  0.0000  539.3583 
H2O  0.0000  749.0805  0.0000  749.0805 
 
 
 
As shown in Table 3, the solubility of hydrochloric acid is much higher than those of the 
remaining components, followed by the chlorinated components and carbon dioxide. Because of 
this we were able to wash the stream with water where the HCl had a higher affinity for and 
would separate out into the water stream instead of the recycle stream. 
 
 
 
 
 
Component 
Solubility 
(g/L) 
Solubility 
(mol/L) 
HCl  720  19.7 
CH2Cl2  17.5  0.21 
CHCl3  8.09  0.07 
Chlorine Gas  7.2  0.1 
CHCl3  5.325  0.11 
Carbon 
Dioxide  1.45  0.033 
CCl4  0.81  0.0053 
Ethane  0.0568  0.0019 
Methane  0.0227  0.0014 
Nitrogen  0.019  0.00068 
 
Table 3. The solubility of each component of the product stream from the reactor in water 
 
 
 
The resulting stream of mainly hydrochloric acid and water is actually a higher concentration of 
37% HCl, so we mixed more water with the stream after separation to achieve this concentration 
so it could be sold. 
 
 
 
In sizing this unit we looked at equilibrium data for hydrochloric acid and water. We were able 
to determine a height of the column to be 4.177m. We also needed to know the diameter in order 
to get the volume of the unit, which was calculated based on the flow of our gas through the 
system and heuristics from Turtin. We calculated a diameter of 0.36m. From this we calculated a 
volume for the absorption column to be 0.4m​3​
. The bare module cost was then calculated to be 
$26,623. Calculations for determining the height, diameter, and cost of the column are found in 
Appendix D. 
 
 
 
From HYSYS we were able to determine a flow of water that we needed for this separation as 
well, which adds to the operating costs of this unit. At a flow rate of 50.58 kgmol/hr of H​2​O with 
a price of $0.5735/100 gallons of H​2​O, we determined an annual cost of $23.84.   
 
 
Separation Section 3 
The third and final separation section of our process includes three distillation columns. We 
chose to use distillation columns because we need to have each stream come out at a high 
enough purity of our products to be able to be sold. A PFD for this section is shown below along 
with the goals for each of the separate distillation columns. 
 
 
S3.1 ­ Distillation column 
The purpose of this distillation column is to further separate out our products form any 
undesirable components. These include Cl​2​ and HCl. This distillation column separates these 
components into stream S3.s1, which is a waste stream. The costing for this waste stream can be 
found in Key Finding 2.  
 
Goals: 
● Further separate out the chlorinated methane products from remaining components, specifically 
chlorine 
 
S3.2 ­ Distillation column 
The purpose of this distillation column is to obtain our primary product, chloromethane, in a pure 
stream while the rest of our products are sent to the S3.3 – Distillation Column. 
 
Goals: 
● Separate out chloromethane from the product stream 
● Achieve a chloromethane purity of 99% 
 
S3.3 ­ Distillation column 
The purpose of this distillation column is to obtain one of our valuable byproducts of 
dichloromethane as a pure stream, while the other stream contains any waste that is leftover from 
our process. The costing for the disposal of this waste stream is found in Key Finding 2.  
 
Goals: 
● Separate out dichloromethane from the product stream 
● Achieve a dichloromethane purity of 99.8% 
 
 
Based on the stream tables for each of the distillation columns shown below, we were able to 
meet our goals of separating out high product purities. In S3.1 – Distillation Column we were 
able to separate out all of the hydrochloric acid (HCl) and most of the chlorine (Cl2) from stream 
S2.s7 into stream S3.s1, where stream S3.s2 contains our valuable products. For S3.2 – 
Distillation Column we were able to separate out most of the chloromethane (CH3Cl), where 
stream S3.s3 has a chloromethane purity of 99.2%, which meets our goal. For S3.3 – Distillation 
Column we were able to separate out most of the dichloromethane (CH2Cl2), where stream 
S3.s5 has a dichloromethane purity of 99.8%, which also meets our goal.  
 
Stream Table for S3.1 – Distillation Column:​ All values in kg/hr. 
Stream ID:  S2.s7  S3.s1  S3.s2 
Total  733.4417  57.2714  676.1703 
Cl2  51.0628  49.8812  1.1815 
CH3Cl  315.5189  0.8347  314.6842 
CH2Cl2  259.5215  0.0000  259.5215 
CHCl3  85.1140  0.0000  85.1140 
CCl4  15.6690  0.0000  15.6690 
HCl  6.5553  6.5553  0.0000 
 
Stream Table for S3.2 – Distillation Column:​ All values in kg/hr. 
Stream ID:  S3.s2  S3.s3  S3.s4 
Total  676.1703  316.8983  359.2720 
Cl2  1.1815  1.1810  0.0005 
CH3Cl  314.6842  314.4740  0.2102 
CH2Cl2  259.5215  1.2432  258.2783 
CHCl3  85.1140  0.0000  85.1140 
CCl4  15.6690  0.0000  15.6690 
 
Stream Table for S3.3 – Distillation Column:​ All values in kg/hr. 
Stream ID:  S3.s4  S3.s5  S3.s6 
Total  359.2720  254.7190  104.5531 
Cl2  0.0005  0.0005  0.0000 
CH3Cl  0.2102  0.2102  0.0000 
CH2Cl2  258.2783  254.2844  3.9940 
CHCl3  85.1140  0.1996  84.9144 
CCl4  15.6690  0.0243  15.6447 
 
The key data to performing this separation in the distillation columns are the boiling points of the 
components of the reactor products, and in the absorption column are the solubility of these 
components in water. As shown below in Table 2, the boiling points of all of the chlorinated 
methane products are higher than those of the remaining components. In addition, the boiling 
points of the chloromethanes increase as the degree of chlorination increases, with 
chloromethane having the lowest boiling point temperature and carbon tetrachloride having the 
highest boiling point temperature.  
 
 
 
Component  BP (°C) 
CCl4  77.08 
CHCl3  62.05 
CH2Cl2  39.95 
CH3Cl  ­24.01 
Chlorine Gas  ­33.15 
HCl  ­84.78 
Carbon Dioxide  ­86.58 
Ethane  ­88.61 
Methane  ­161.6 
Nitrogen  ­195.7 
Table 2. The boiling points of each component in the product stream from the reactor 
 
Additionally, we looked at sizing the condensers and reboilers for the distillation columns along 
with calculating the costs for each. We plan on using liquid nitrogen for the condensers and 
saturated steam for the reboilers. The following table shows the surface area and bare module 
cost for the condensers and reboilers for each of the distillation columns in this section. The 
calculations that achieved these values can be found in Appendix D. 
 
 
  Surface area (m^2)  Bare Module Cost 
S2.3­ Condenser  3.63  $7,166 
S2.3­ Reboiler  2.4058  $7,915 
S2.4­ Condenser  14.89  $5211.5 
S2.4­ Reboiler  14.19  $4966.5 
S2.5­ Condenser  70.16  $17540 
S2.5­ Reboiler  102.2  $30660 
 
 
   
 
 
Key Finding II: Energy Integration and Process Improvements 
 
After completing the base case design (Figure 1), Team 7 carefully examined how we could decrease the                                 
operating costs of the process. Potential areas for cost reduction including energy integration, waste                           
stream management, reduction of capital costs and reduction of operating (utility) costs. 
 
We looked at the temperatures of all streams, especially ones right before and after heaters and coolers.                                 
The goal of this examination is to decrease our annual costs and to increase the net present value of the                                       
project.  
 
In the creation of the base case (Figure 1), unit and operating cost were highly considered at all times. The                                       
smallest and cheapest units were used when possible (for example, flash drums were first installed and if                                 
they didn’t work, then a distillation column was used). Since the creation of our base case design was so                                     
iterative, there is not much cost reduction that would be further possible in terms of capital cost.  
 
In order to meet our goals of decreasing the annual costs and to increase the net present value of the                                       
project, we completed the following: 
 
1. Identify and assess improvements with respect to energy use 
2. Identify and assess improvements with respect to utility costs 
 
Energy Use 
 
Table 1.1: Shows the inlet and outlet temperatures from the heaters and coolers in the base case. 
  Stream  Inlet temp (C) 
Outlet temp 
(C) 
Heat/Cool load 
kJ/hr 
S1 
Cooler  Natural gas feed  25  ­139  ­84000 
S1 
Heater 
HCl and recycle from heat 
exchanger 3  45.6  440  930000 
S2 
Cooler  HCl and recycle  440  ­50  ­1400000 
S2 
Heater 
Reactor feed from heat 
exchanger 1  ­170  25  800000 
   
Net energy 
requirement    246000 
 
 
 
 
 
 
 
 
 
 
 
Table 1.2: Shows the streams that are crossed in heat exchangers and their inlet and outlet temperatures in                                   
the energy integration case.  
  Cold stream 
Cold 
stream 
inlet temp 
(C) 
Cold 
stream 
outlet 
temp (C)  Hot stream 
Hot 
stream 
inlet temp 
(C) 
Hot stream 
outlet temp 
(C) 
Heat 
exchanger 1  Reactor feed  44.4  430  Reactor products  430  68 
Heat 
exchanger 2 
HCl and 
recycle from 
heat 
exchanger 3  ­159  ­81.7 
Reactor products 
from heat 
exchanger 1  68  ­50 
Heat 
exchanger 3 
HCl and 
recycle  ­171  ­159  Natural gas feed  25  ­139 
Fired heater 1 
Reactor feed 
from heat 
exchanger 1  430  440 
Ethane stream 
from natural gas 
purification 
This 
stream is 
burned 
Exhaust is 
vented to 
atmosphere 
 
Table 1.2 shows the inlet and outlet stream temperatures and how the heat exchangers reached their                               
required temperatures. We did not need to use composite curves in this energy integration since there was                                 
enough energy available to eliminate all of the heaters and coolers and replace them with the heat                                 
exchangers. We chose which streams to cross through an iterative process in HYSYS. There are a lot of                                   
very high and very low temperature streams which made crossing them to exchange heat a relatively                               
simple process. There was only one stream that was not able to be fully heated by crossing it with other                                       
streams, so this was dealt with by heating it with a fired heater which burned an ethane waste stream.  
 
Quantitatively, this can be shown by the net energy input required for all of the heaters and coolers in the                                       
base case. The 2.5x10​5
kJ/hr of energy that is needed (assuming perfect energy integration) is more than                                 
covered by the direct fired heater. In the energy integration case, the direct fired heater is able to deliver                                     
1.1x10​6​
 kJ/hr of heat. 
 
All of the heat exchangers and direct fired heaters were added in order to replace heaters and coolers that                                     
were initially in the base case. Making changes in this manner removes the capital cost of the heaters and                                     
coolers, as well as the utility costs of them. However it does add the capital cost of the heat exchanger and                                         
direct fired heater. As shown by the present value of the project in Table 3, this is a profitable                                     
replacement.  
 
 
 
 
 
Figure 1: A process flow diagram showing the initial base case design of the process.  
 
 
 
Figure 2: A process flow diagram showing how streams have been rerouted to cross other streams in an                                   
effort to reduce overall costs.  
 
 
S1.1­ Heat Exchanger 1: 
 
 
Figure 3: A portion of Figure 2 showing the streams involved with heat exchanger 1.   
 
Goals: This heat exchanger serves to cool the natural gas feed stream down while heating up the distillate                                   
(HCl and recycle) stream of the first distillation column after the reactor. 
 
This heat exchanger is replacing a heater that would have heated the HCl and recycle stream, as well as a                                       
cooler that would have cooled the natural gas feed stream.  
 
S1.5­  Heat Exchanger 2:  
 
Figure 4: A portion of Figure 2 showing the streams involved with heat exchanger 2.   
 
 
 
Goals: The goals of this heat exchanger are essentially to heat the reactor feed stream with the product                                   
stream.  
 
Additional required heating of the reactor feed stream is added by a direct fired heater discussed below.                                 
This replaces a heater that would have heated the reactor feed stream and a cooler that would have cooled                                     
the products stream.  
 
S2.1­ Heat Exchanger 3: 
 
Figure 5: A portion of figure 2(from above) showing the streams involved with heat exchanger 3.   
 
Goals: The goals of this heat exchanger are to further cool the reactor products, or first distillation column                                   
feed, with the distillate stream from the first distillation column. 
 
This heat exchanger replaces a cooler that would cool the feed to the first distillation column, as well as a                                       
heater that would have heated the distillate stream. 
 
 
   
 
 
S1.6­ Direct Fired Heater 1: 
 
 
 
Figure 6: A portion of Figure 2 showing the streams involved with direct fired heater 1.   
 
Goals: This fired heater serves to burn a waste stream in order to decrease waste disposal costs. It also                                     
heats the reactor feed stream the additional 10 degrees that heat exchanger S1.5 was unable to                               
accomplish.  
 
This unit partially replaces the heater that was needed to preheat the feed stream. 
 
 
 
 
Utilities 
 
In an effort to reduce utility costs, the breakdown of the utilities was calculated below.  
 
Table 2.1: Utility breakdown and percentage of total utility cost for base case.  
 
Unit  Utility  Cost of utility 
Percentage of 
total 
S1 Cooler 
Nitrogen  $2  0.00011% 
electricity  $14,216  1.03287% 
S1 Heater  Saturated Steam  $2,089  0.15176% 
Reactor  Cooling water  $1  0.00005% 
S2 Cooler 
Nitrogen  $15  0.00111% 
Electricity  $204,735  14.87548% 
S2 Heater  Steam  $101  0.00735% 
Compressor  Electricity  $19,254  1.39898% 
S2.1  nitrogen  $2  0.00014% 
  Saturated Steam  $488  0.03548% 
S2.2  Product water  $24  0.00173% 
S2.3  nitrogen  $2  0.00014% 
  Saturated Steam  $81  0.00586% 
S2.4  nitrogen  $2  0.00014% 
  Saturated Steam  $421  0.03057% 
S2.5  nitrogen  $2  0.00014% 
  Saturated Steam  $2,089  0.15175% 
Water pipe service charge  Water­ general  $38,664  2.80922% 
Waste  Waste disposal  $1,094,138  79.49711% 
       
Net Utilities  $1,376,325   
 
   
 
 
Table 2.2: Utility breakdown and percentage of total utility cost for energy integration. Utilities that are                               
less than 0.5% of the total are not shown here. This includes nitrogen and steam costs.  
Unit  Utility  Annual cost of utility 
Percentage of 
total 
Waste 
Waste 
disposal  $1,094,138  94.96509% 
Water pipe service charge  Water­ general  $38,664  3.35582% 
Compressor  Electricity  $19,254.48  1.67118% 
       
Net Utilities  $1,152,148     
 
 
As shown by Tables 2.1 and 2.2, the energy integration did decrease the net utility cost by approximately                                   
$200,000. However, as shown in Table 2.2, the primary utility cost in this design is the waste disposal. As                                     
discussed above in the Waste Stream Management section, it would be very difficult to separate the waste                                 
stream into valuable byproducts, adding multiple large distillation columns as well as adding the utility                             
costs for those units.  
 
Net Impact of Energy Integration: 
 
The costing information described below only represents the changes that occurred in capital costs and                             
utility costs due to the energy integration, as well as the overall project costs (see appendix C). To see a                                       
detailed breakdown of how the calculations were carried out, please refer to Project Report 2.  
 
Table 3: Cost comparison between the base case and the energy integrated case. This table only shows the                                   
utilities that had a significant change between the base case and energy integration case.  
  Base case  Energy integration 
FCI  $7,299,822  $8,417,570 
Steam  $5,167  $59 
Electricity   $238,205  $19,254 
Water  $38,688  $38,688 
Net Utilities  $1,376,224  $1,152,148 
NPV  $18,227,945  $18,972,634 
 
 
In an effort to increase the overall efficiency of our plant, decrease our utility costs and therefore make the                                     
overall process more profitable, Team 7 has closely examined ways to save energy, decrease the amount                               
of utilities used, decrease waste disposal costs, and decrease the capital cost of the equipment. We have                                 
accomplished this by using different temperature streams to heat or cool each other, rather than paying for                                 
a heater and a cooler. We also utilized direct fired heaters to burn our waste streams and provide further                                     
heating.  
 
As shown by Table 3, the net present value of the project increases the capital cost of the units, but it                                         
decreases the utility costs. Additionally, it decreases electricity consumption which is more                       
environmentally friendly. Overall there is a relatively small change in the net present value of the project,                                 
 
 
and increase of roughly 4%. This means that the project is more profitable after the energy integration, as                                   
well as more environmentally friendly, meeting our goal of becoming more profitable.  
Waste Stream Management 
 
Team 7 also examined our waste streams, and how they can best be dealt with. From the base case design                                       
(Figure 1), there is stream (S1.s4) that will be sent to a flare, and two streams (S3.s1 and S3.s6) that need                                         
to be disposed of as hazardous waste. They could not be burned since they are primarily chloromethane.                                 
The flared streams provide energy to the fired heaters currently in our process. As for the waste streams,                                   
the only alternative option would be to separate them further and sell the products. However, in order to                                   
purify the stream to a high enough purity for sale, two additional distillation columns that were larger than                                   
any other columns in the system would have to be added. Since these products are not our primary                                   
product and since they would have had an enormous capital cost, we chose to simply dispose of the waste.  
 
 
 
 
 
   
 
 
Conclusions 
 
Our team has developed the structure of the separations necessary for the chlorination of methane using 
chlorine gas to produce chloromethane. Our key findings are as follows: 
 
1. Our base case has a net present value of $18,227,945 and total capital investment of $8,077,467 
2. Our energy integrated design has a net present value of $18,972,634 and total capital investment 
of $9,306,990 
 
 
Recommendations 
 
We recommend the following actions to be taken based on these findings:  
 
● Recommendation 1: The series of separations detailed in Key Finding 1 be used to successfully 
separate and purify our primary product and valuable byproducts 
● Recommendation 2: The energy integration detailed in Key Finding 2 be used to reduce the 
overall cost and increase the net present value. 
● Recommendation 3: Our process for the production of chloromethane be implemented 
 
   
 
 
References 
1. Fair, J. Henry. "Natural Gas Drilling in the Marcellus Shale Uncovered: Community, 
Environment, and Law." ​Environmental Studies Capstone ::​. Swarthmore College, n.d. Web. 16 
Sept. 2015. <http://www.swarthmore.edu/environmental­studies­capstone>. 
2. "History and Background ­ What Is Marcellus Shale?" ​Natural Gas Development​. Cornell 
University, n.d. Web. 
<http://www2.cce.cornell.edu/naturalgasdev/documents/pdfs/history%20and%20background1.pd
f>. 
3. "The Marcellus Shale, Explained." ​StateImpact​. NPR, n.d. Web. 16 Sept. 2015. 
<https://stateimpact.npr.org/pennsylvania/tag/marcellus­shale/>. 
4. United States of America. Department of Conservation and Natural Resoruces. ​Marcellus Shale​. 
PA DCNR ­ Geology, n.d. 
<http://www.dcnr.state.pa.us/topogeo/econresource/oilandgas/marcellus/marcellus_faq/marcellus
_shale/index.htm> 
5. United States of America. Ohio Department of Natural Resources. Ohio Geological Study. ​The 
Marcellus Shale Play: Geology, History, and Oil & Gas Potential in Ohio​. By Chris Perry and 
Larry Wickstrom. Ohio Geological Survey, n.d. Web. 
<http://geosurvey.ohiodnr.gov/portals/geosurvey/Energy/Marcellus/The_Marcellus_Shale_Play_
Wickstrom_and_Perry.pdf>. 
 
 
 
 
 
 
Appendix A: Unit Sizing: 
 
Unit  Size  Cp  B1  B2 
F
m  Cbm = Cp*(B1+B2Fm) 
Reactor  10 liters  $128,000  1.49  1.52  9.4  $2,019,584 
S2 Compressor  42.1 hp  $12,800      9.8  $125,440 
 
 
Column 
Diamete
r (m) 
Numbe
r of 
trays 
Colum
n 
height 
(m) 
Colum
n 
volume 
(m^3) 
Base 
price 
Pressur
e factor 
Materi
al 
Factor  B1  B2 
Bare 
module 
cost 
S1­ Flash 
Drum ­ 
Vertical  0.4572  N/A  2.515  0.4  $2,192  0.672  9.4 
2.2
5 
1.8
2  $30,125 
S2.1­ 
Distillatio
n column  1.19  13  6.5  7.2  $9,235  0.947  9.4 
2.2
5 
1.8
2 
$170,36
5 
S2.2­ 
Absorptio
n column  0.360  N/A  4.177  0.4  $2,226  0.568  9.4 
2.2
5 
1.8
2  $26,623 
S2.3­ 
Distillatio
n column  1.193  61  30.5  34.1 
$27,59
8  0.948  9.4 
2.2
5 
1.8
2 
$509,67
0 
S2.4­ 
Distillatio
n column  1.193  33  16.5  18.4 
$17,41
5  0.835  9.4 
2.2
5 
1.8
2 
$287,93
1 
S2.5­ 
Distillatio
n column  1.193  73  36.5  40.8 
$31,78
4  0.806  9.4 
2.2
5 
1.8
2 
$509,67
6 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Surface area 
(m^2) 
Cp (from graph in 
Turtin)  B1  B2 
Bare Module 
Cost 
S1 Natural Gas 
Cooler  5.02  2510  1.74  1.55  $8,258 
S1 Reactor 
Preheater  31.81  11133.5  1.74  1.55  $36,629 
S2 Products Cooler  49.61  17363.5  1.74  1.55  $57,126 
S2 Heater  48.4  16940  1.74  1.55  $55,733 
S2.1­ Condenser  3.55  2130  1.74  1.55  $7,008 
S2.1­ Reboiler  1.2  1260  1.74  1.55  $4,145 
S2.3­ Condenser  3.63  2178  1.74  1.55  $7,166 
S2.3­ Reboiler  2.4058  2405.8  1.74  1.55  $7,915 
S2.4­ Condenser  14.89  5211.5  1.74  1.55  $17,146 
S2.4­ Reboiler  14.19  4966.5  1.74  1.55  $16,340 
S2.5­ Condenser  70.16  17540  1.74  1.55  $57,707 
S2.5­ Reboiler  102.2  30660  1.74  1.55  $100,871 
 
 
Unit Cost Summary   
Reactor  $2,019,584 
S1­ Flash Drum ­ Vertical  $30,125 
S1 Natural Gas Cooler  $170,365 
S1 Reactor Preheater  $26,623 
S1 Products Cooler  $509,670 
S2 Heater  $287,931 
S2 Compressor  $125,440 
S2.1­ Distillation column  $181,518 
S2.2­ Absorption column  $26,623 
S2.3­ Distillation column  $524,751 
S2.4­ Distillation column  $321,416 
S2.5­ Distillation column  $668,254 
Total unit costs  $4,055,457 
 
 
 
 
 
 
Fixed capital investment (FCI)  $7,299,822  =total unit cost * 1.2 * 1.5 
 
Cl2     
kgmol/hr  15.76  from HYSYS 
$/kgmol  $15  from Alibaba.com 
7 day supply  $39,715  =kgmol/hr * $/kgmol * 24hr * 7 days 
 
Natural Gas     
kgmol/hr  13.40  from HYSYS 
$/kgmol  $0.0017  from Alibaba.com 
7 day supply  $4  =kgmol/hr * $/kgmol * 24hr * 7 days 
 
Feed inventories (FI)  $39,719 
=7 day supply Cl2 + 7 day supply natural 
gas 
Working capital (WC)  $777,645  =1.2 * FI + 0.1 * FCI 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Appendix B: Utilities 
Heat 
exchanger 
utilities                 
  Tf C 
kgmol
/hr 
Heat 
flow 
kJ/hr 
Needed 
flow of 
steam(for 
reboilers) 
nitrogen 
(for 
condensers
) g/s 
mol/mont
h H2O 
gal/mont
h H2O 
$/100 gal 
(condenser
) 
$/1000 kg 
(reboiler) 
Annual 
cost 
S1 Natural 
Gas Cooler  ­139  13.4  ­83540  77.7  55944  266  0.5735  $1.53 
S1 Reactor 
Preheater  440  53.26  927900  2033.33  1463998  6962  30 
$2,088.6
6 
S2 Cooler  ­50  53.26 
­14180
00  778  560160  2664  0.5735  $15.28 
S2 Heater  25  42.2  800600  98.53  70942  337  30  $101.21 
S2.1­ 
Condenser  ­170.2  42.2 
­74000
0  100  72000  342  0.5735  $1.96 
S2.1­ 
Reboiler  11.6  11.2  107000  475.4  342288  1628  30  $488 
S2.3­ 
Condenser  ­43.5  0.9 
­63000
0  100  72000  342  0.5735  $2 
S2.3­ 
Reboiler  19.3  10.1  640000  78.55  56556  269  30  $81 
S2.4­ 
Condenser  ­24.1  6.3 
­33000
00  100  72000  342  0.5735  $2 
S2.4­ 
Reboiler  65.8  3.9 
333000
0  409.61  294919  1403  30  $421 
S2.5­ 
Condenser  39.8  2.1 
­20000
0  100  72000  342  0.5735  $2 
S2.5­ 
Reboiler  67.6  1.78  200000  2033.23  1463926  6962  30  $2,089 
 
 
 
 
 
 
 
 
 
S2.2 and HCl utilities  
kgmol/hr H2O  50.58 
mol/month H2O  36418 
gal/month H2O  173 
$/100 gal  0.5735 
Annual cost  $23.84 
 
Waste streams   
  Flow rate­ kgmol/hr 
Waste1­ kgmol/hr  0.9 
Waste2­ kgmol/hr  0.86 
Waste1­ kg/hr  57.27 
Waste2­ kg/hr  104.6 
Annual production­ ton/year  1563 
Disposal cost­ $/ton  700 
Annual disposal cost  $1,094,138 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
     
 
 
Unit Utility Costs 
Unit  Utility 
Cost of 
utility 
S1 Cooler 
Nitrogen  $1.53 
electricity  $14,216 
S1 Heater 
Saturated 
Steam  $2,088.66 
Reactor  Cooling water  $0.65 
S2 Cooler 
Nitrogen  $15.28 
Electricity  $204,735 
Compressor  Electricity  $19,254 
S2.1  nitrogen  $1.96 
 
Saturated 
Steam  $488 
S2.2  Product water  $23.84 
S2.3  nitrogen  $2 
 
Saturated 
Steam  $81 
S2.4  nitrogen  $2 
 
Saturated 
Steam  $421 
S2.5  nitrogen  $2 
 
Saturated 
Steam  $2,089 
Water pipe service charge  Water­ general  $38,664 
 
 
 
 
Appendix C 
 
Table 2­ This table show the total unit costs for the base case.  
Reactor  $2,019,584 
S1­ Flash Drum ­ Vertical  $30,125 
S1 Natural Gas Cooler  $170,365 
S1 Reactor Preheater  $26,623 
S1 Products Cooler  $509,670 
S2 Heater  $287,931 
S2 Compressor  $125,440 
S2.1­ Distillation column  $181,518 
S2.2­ Absorption column  $26,623 
S2.3­ Distillation column  $524,751 
S2.4­ Distillation column  $321,416 
S2.5­ Distillation column  $668,254 
Total unit costs  $4,055,457 
 
Table 3­ This table show the total unit costs for the energy integrated case.  
Reactor  $2,019,584 
Fired_heater1   $740 
Heat_recovery1  $58,957 
Heat_recovery2  $12,015 
Heat_recovery3  $626,913 
Heater  $80,092 
S2 Compressor  $125,440 
S2.1­ Distillation column  $804,285 
S2.2­ Absorption column  $26,623 
S2.3­ Distillation column  $520,981 
S2.4­ Distillation column  $312,991 
S2.5­ Distillation column  $583,723 
Total unit costs  $4,676,428 
 
 
 
 
 
 
Table 4­ This table shows the utility costs of each unit in the base case.  
Unit  Utility  Cost of utility 
S1 Cooler 
Nitrogen  $2 
electricity  $14,216 
S1 Heater  Saturated Steam  $2,089 
Reactor  Cooling water  $1 
S2 Cooler 
Nitrogen  $15 
Electricity  $204,735 
Compressor  Electricity  $19,254 
S2.1  nitrogen  $2 
  Saturated Steam  $488 
S2.2  Product water  $24 
S2.3  nitrogen  $2 
  Saturated Steam  $81 
S2.4  nitrogen  $2 
  Saturated Steam  $421 
S2.5  nitrogen  $2 
  Saturated Steam  $2,089 
Water pipe service charge  Water­ general  $38,664 
Waste  Waste disposal  $1,094,138 
     
Net Utilities  $1,376,224 
 
   
 
 
Table 5­ This table shows the utility costs of each unit in the energy integrated case.  
Unit  Utility  Cost of utility 
Reactor  Cooling water  $0.65 
Compressor  Electricity  $19,254.48 
S2.1  nitrogen  $1.96 
  Saturated Steam  $9.34 
S2.2  Product water  $23.84 
S2.3  nitrogen  $1.96 
  Saturated Steam  $1.54 
S2.4  nitrogen  $1.96 
  Saturated Steam  $8.04 
S2.5  nitrogen  $1.96 
  Saturated Steam  $39.93 
Water pipe service charge  Water­ general  $38,664 
Waste  Waste disposal  $1,094,138 
     
Net Utilities  $1,152,148   
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Appendix D: Unit Sheets 
Project: Chloromethane synthesis from methane 
Unit Name/ID: S1.1 Flash Drum 
Unit Type: Flash Drum (vertical) 
Sizing Basis: Volume, m​3
 
 
 
Unit Diagram 
 
Stream Table: ​All values in kg/hr. 
Stream ID:  S1.2  S1.3  S1.4 
Total  225.2000  210.2000  14.9800 
CH4  204.2261  204.2261  0.0000 
C2H6  16.1175  1.9789  14.1386 
N2  1.8769  1.8769  0.0000 
CO2  2.9486  2.1079  0.8408 
 
Flash Drum Size Summary 
Using the Souders­Brown equation shown below we were able to size our drum. 
  
k)  V = (
√ ρV
ρ −ρL V
 
where: 
V = maximum allowable vapor velocity (m/s) 
 = liquid density, kg/m​3
ρL  
 = vapor density, kg/m​3
ρV  
k = 0.107 m/s  
 
From the vapor velocity and knowing the flow rate of the natural gas stream from our HYSYS 
model we could get the cross sectional area (A) and diameter (D) of the drum with the following 
equations: 
 
A = V
vapor flow rate, in m /s3
 
 
D = [ ]π
4(A) 0.5
 
 
 
The height of the vessel (h) was then calculated with the equation below assuming a liquid 
residence time of 5 minutes and that the liquid level is about the midpoint of the vessel height: 
 
h = A
2 (5 min) (liquid flow rate, in m /min)* *
3
 
 
With the height and diameter of the vessel the volume (V) can be calculated as follows: 
 
( ) hV = π 2
D 2
 
 
We calculated the flash drum to have a volume of 0.4m​3​
. 
 
Flash Drum Cost Summary 
We found the flash drum to have a volume of 0.4m​3​
. Looking in Table A.1 of Turton we 
determined the purchased equipment cost at ambient operating pressure and using carbon steel 
construction with the following equation: 
 
 C   log  (A)  [log  (A) ]log10
0
p = K1 + K2 10 + K3 10
2
 
 
where: 
A = 0.4m​3
 
K​1​ = 3.4974 
K​2​ = 0.4485 
K​3​ = 0.1074 
 
The bare module cost (C​BM​) for this vessel has to account for its material factors (F​M​) and 
pressure factor (F​P​). 
 
(B F F )CBM = C0
p 1 + B2 M P  
 
 
FP,vessel = 0.0063
+0.00315(P+1)D
2[850−0.6(P+1)]
 
 
 
where: 
D = 0.46m 
B​1​ = 2.25 
B​2​ = 1.82 
F​M​ = 9.4 
P = 3.01 barg 
 
The base module cost (C​BM​) was found to be $30,125. 
 
 
 
S1 Cooler Size Summary 
 
 
Using the following set of equations as well as information from HYSYS, we were able to size 
the heat exchanger between liquid nitrogen and our natural gas stream.  
 
A
Q
= dT
+∑
 
 
1
hi k
x
pipe
 
 
hi = D
k Nui
 
 
u .023Re PrN = 0 0.8 0.3
 
 
eR = μ
ρvD
 
 
r p( )P = C k
μ
 
 
Td =  
ln ( ) T −Tsat in
T −Tsat out
(T −T )−(T −T )sat out sat in
 
 
A =   ( )A
Q
Qneeded
 
 
where: 
i = the liquid nitrogen stream and natural gas stream 
k​pipe​ = 400 W/mC 
D = 0.1407m 
x = 0.0021m 
 
Q​needed​, viscosity ( ), thermal conductivity (k), density ( ). T​in​, and T​out​ data was found from ourμ ρ  
HYSYS simulation for each stream. 
 
We calculated a surface area of 5.02m​2​
 for this heat exchanger. 
 
S1 Cooler Cost Summary – Capital Cost 
Knowing the surface area (A) of the heat exchanger, we used Figure A.5 in Appendix A of 
Turtin to find a C​p​
0​
/A($/m​2​
) where: 
C0
p =
C0
p
A( )$
m2
* A  
 
To calculate the bare module cost (C​BM​) of this heat exchanger we used the following equation: 
 
(B F F )CBM = C0
p 1 + B2 M P  
 
 
 
 
where: 
B​1​ = 1.74 
 
 
B​2​ = 1.55 
F​M​ = 1 
F​P​ = 1 
 
We calculated a bare module cost of $8,258 for this heat exchanger. 
 
S1 Cooler Cost Summary – Operating Cost 
The condenser in the refrigeration unit that creates the liquid nitrogen used in the heat exchanger 
requires power. Therefore the cost of the electricity to run it was calculated. We looked at the 
Carnot efficiency of this mechanical refrigeration system which can be expressed by the 
reversible coefficient of performance, COP​REV​: 
 
COPREV =
evaporator temperature (T )1
temperature difference between condenser and evaporator (T −T )2 1
 
 
 
ork requiredw = COP
evaporator heat load
 
 
where: 
T​1​ = ­195.8°C 
T​2​ = 0°C 
evaporator heat load = 83460 kJ/hr 
 
We calculated a value of 23.2 kW of work required, and were able to take our value of $0.07/hr 
of electricity to calculate an annual operating cost of $14,216 for this refrigeration unit. 
 
 
 
Total Capital Cost: $38,383 
Total Operating Cost: $14,216/year 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Project: Chloromethane synthesis from methane 
Unit Name/ID: S2.1 Distillation Column 
 
 
Unit Type: Distillation Column 
Sizing Basis: Volume, m​3
 
 
 
Unit Diagram 
 
Stream Table:​ All values in kg/hr. 
Stream ID:  S2.s2  S2.s3  Flare  S2.s7 
Total  1759.6755  1025.1873  1.0465  733.4417 
CH4  413.1240  412.6481  0.4759  0.0000 
C2H6  9.9877  9.9876  0.0000  0.0001 
N2  11.8986  11.3281  0.5705  0.0000 
CO2  2.1079  2.1078  0.0000  0.0001 
Cl2  66.9121  15.8493  0.0000  51.0628 
CH3Cl  349.4269  33.9080  0.0000  315.5189 
CH2Cl2  259.5216  0.0001  0.0000  259.5215 
CHCl3  85.1140  0.0000  0.0000  85.1140 
CCl4  15.6690  0.0000  0.0000  15.9960 
HCl  545.9137  539.3583  0.0001  6.5553 
 
 
 
S2.2 – Distillation Column Size Summary 
Column Diameter = 1.19m 
Number of Trays = 13 
Column Height = 6.5m (assuming the distance between each tray is 0.5m) 
 
olumn V olume π olumn HeightC =   * ( )2
Column Diameter 2
* C  
 
Column Volume = 7.2m​3 
S2.2 – Distillation Column Cost Summary 
 
 
We found the distillation column to have a volume of 7.2m​3​
. Looking in Table A.1 of Turton we 
determined the purchased equipment cost at ambient operating pressure and using carbon steel 
construction with the following equation: 
 
 C   log  (A)  [log  (A) ]log10
0
p = K1 + K2 10 + K3 10
2
 
 
where: 
A = 7.2m​3
 
K​1​ = 3.4974 
K​2​ = 0.4485 
K​3​ = 0.1074 
 
The bare module cost (C​BM​) for this vessel has to account for its material factors (F​M​) and 
pressure factor (F​P​). 
 
(B F F )CBM = C0
p 1 + B2 M P  
 
 
FP,vessel = 0.0063
+0.00315(P+1)D
2[850−0.6(P+1)]
 
 
 
where 
D = 1.19m 
B​1​ = 2.25 
B​2​ = 1.82 
F​M​ = 9.4 
P = 3.01 barg 
 
The base module cost (C​BM​) was found to be $170,365. 
 
S2.2 Condenser and Reboiler Size Summary 
Using the following set of equations as well as information from HYSYS, we were able to size 
the condensers as well as reboilers in the distillation column. For the condensers we used liquid 
nitrogen and for the reboilers we used saturated steam.  
 
A
Q
= dT
+∑
 
 
1
hi k
x
pipe
 
 
hi = D
k Nui
 
 
u .023Re PrN = 0 0.8 0.3
 
 
eR = μ
ρvD
 
 
r p( )P = C k
μ
 
 
 
 
Td =  
ln ( ) T −Tsat in
T −Tsat out
(T −T )−(T −T )sat out sat in
 
 
A =   ( )A
Q
Qneeded
 
 
where: 
i = each stream in the condenser or reboiler 
k​pipe​ = 400 W/mC 
D = 0.1407m 
x = 0.0021m 
 
Q​needed​, viscosity ( ), thermal conductivity (k), density ( ). T​in​, and T​out​ data was found from ourμ ρ  
HYSYS simulation for each exit stream of either the condenser or reboiler.  
 
From this set of equation we were able to calculate the surface area of the heat exchanger for the 
reboiler and condenser in the distillation column. The reboiler surface area is 1.2m​2​
, and the 
condenser is 3.55m​2​
.  
 
S2.2 Condenser and Reboiler Cost Summary 
Knowing the surface area (A) of the condenser and reboiler, we used Figure A.5 in Appendix A 
of Turtin to find a C​p​
0​
/A($/m​2​
) where: 
C0
p =
C0
p
A( )$
m2
* A  
 
To calculate the bare module cost (C​BM​) of this heat exchanger we used the following equation: 
 
(B F F )CBM = C0
p 1 + B2 M P  
 
where: 
B​1​ = 1.74 
B​2​ = 1.55 
F​M​ = 1 
F​P​ = 1 
 
We calculated a bare module cost of $7,008 for the condenser, and $4,145 for the reboiler. 
 
Total Capital Coat = $181,518 
 
 
 
 
 
Project: Chloromethane synthesis from methane 
Unit Name/ID: S2.2 Absorption Column 
Unit Type: Absorption Column 
 
 
Sizing Basis: Volume, m​3
 
 
 
Unit Diagram 
 
 
Stream Table:​ All values in kg/hr. 
Stream ID:  S2.s4  S2.fH2O  S2.s5  S2.p1 
Total  1025.1874  749.0805  478.7566  1295.5112 
CH4  412.6481  0.0000  412.4831  0.1651 
C2H6  9.9876  0.0000  8.9010  1.0867 
N2  11.3281  0.0000  11.1718  0.1563 
CO2  2.1078  0.0000  0.0000  2.1078 
Cl2  15.8493  0.0000  12.2927  3.5566 
CH3Cl  33.9080  0.0000  33.9080  0.0000 
HCl  539.3583  0.0000  0.0000  539.3583 
H2O  0.0000  749.0805  0.0000  749.0805 
 
 
 
S2.2 ­ Absorption Column Size Summary 
The following set of equation was used in order to determine the height of the absorption 
column. 
 
x )LM( * − x = ln ( ) (x2 −x2)*
(x1 −x1)*
(x1 −x1)−(x2 −x2)* *
 
 
LM(1 )− x *
= ln ( ) (1−x1)
(1−x1 )*
(1−x1)−(1−x1 )*
 
 
.6634Kya = 0 * L0.82
 
 
TUN = (x1−x2)
(x −x)LM*  
 
TUH = L
K (1−x) LMya*
*  
 
 
 
TU TUz = H * N  
 
where: 
x1 = 0.262 
x2 = 0 
x1​*​
 = 0.9693 
x2​*​
 = 0.9693 
L = 41.6 kgmol/hr 
 
We found that the height of the column (z) is 4.177m. 
We then used the following equation to determine the diameter of the column. 
 
 D = √ π
( )3600
gas flow, in kg/hr
average gas density, in 1kg
m3* s
m
* 2 
 
 
The diameter of the column was calculated to be 0.36m. 
We then used the following equation to determine the volume of the absorption column. 
 
πV =   * ( )2
D 2
* z  
 
The column has a volume of 0.4 m​3​
. 
 
S2.2 ­ Absorption Column Capital Cost Summary 
We found the absorption column to have a volume of 0.4m​3​
. Looking in Table A.1 of Turton we 
determined the purchased equipment cost at ambient operating pressure and using carbon steel 
construction with the following equation: 
 
 C   log  (A)  [log  (A) ]log10
0
p = K1 + K2 10 + K3 10
2
 
 
where: 
A = 0.4m​3
 
K​1​ = 3.4974 
K​2​ = 0.4485 
K​3​ = 0.1074 
 
The bare module cost (C​BM​) for this vessel has to account for its material factors (F​M​) and 
pressure factor (F​P​). 
 
(B F F )CBM = C0
p 1 + B2 M P  
 
 
FP,vessel = 0.0063
+0.00315(P+1)D
2[850−0.6(P+1)]
 
 
 
 
 
where 
D = 0.36m 
B​1​ = 2.25 
B​2​ = 1.82 
F​M​ = 9.4 
P = 3.01 barg 
 
The base module cost (C​BM​) was found to be $26,623. 
 
S2.2 Absorption Column Operating Cost Summary 
We require a feed stream of pure water at a rate of 50.58kgmol/hr to obtain the separation that 
we need through the absorption column. This equates to 173gallons of H​2​O per month. With a 
current price of $0.5735/100 gal of water, we found an annual cost of $23.84 for the water 
required to run the absorption column. 
 
 
 
Total Capital Cost = $26,623 
Total Operating Cost = $23.84/year 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Project: Chloromethane synthesis from methane 
Unit Name/ID: S3.1 Distillation Column 
Unit Type: Distillation Column 
Sizing Basis: Volume, m​3
 
 
 
 
 
Unit Diagram 
 
Stream Table:​ All values in kg/hr. 
Stream ID:  S2.s7  S3.s1  S3.s2 
Total  733.4417  57.2714  676.1703 
Cl2  51.0628  49.8812  1.1815 
CH3Cl  315.5189  0.8347  314.6842 
CH2Cl2  259.5215  0.0000  259.5215 
CHCl3  85.1140  0.0000  85.1140 
CCl4  15.6690  0.0000  15.6690 
HCl  6.5553  6.5553  0.0000 
 
 
S3.1 – Distillation Column Size Summary 
Column Diameter = 1.193m 
Number of Trays = 61 
Column Height = 30.5m (assuming the distance between each tray is 0.5m) 
 
olumn V olume π olumn HeightC =   * ( )2
Column Diameter 2
* C  
 
Column Volume = 34.1m​3 
 
 
 
S3.1 – Distillation Column Cost Summary 
We found the distillation column to have a volume of 34.1m​3​
. Looking in Table A.1 of Turton 
we determined the purchased equipment cost at ambient operating pressure and using carbon 
steel construction with the following equation: 
 
 
 
 C   log  (A)  [log  (A) ]log10
0
p = K1 + K2 10 + K3 10
2
 
 
where: 
A = 34.1m​3
 
K​1​ = 3.4974 
K​2​ = 0.4485 
K​3​ = 0.1074 
 
The bare module cost (C​BM​) for this vessel has to account for its material factors (F​M​) and 
pressure factor (F​P​). 
 
(B F F )CBM = C0
p 1 + B2 M P  
 
 
FP,vessel = 0.0063
+0.00315(P+1)D
2[850−0.6(P+1)]
 
 
 
where 
D = 1.193m 
B​1​ = 2.25 
B​2​ = 1.82 
F​M​ = 9.4 
P = 3.01 barg 
 
The base module cost (C​BM​) was found to be $509,670 
 
S3.1 Condenser and Reboiler Size Summary 
Using the following set of equations as well as information from HYSYS, we were able to size 
the condensers as well as reboilers in the distillation column. For the condensers we used liquid 
nitrogen and for the reboilers we used saturated steam.  
 
A
Q
= dT
+∑
 
 
1
hi k
x
pipe
 
 
hi = D
k Nui
 
 
u .023Re PrN = 0 0.8 0.3
 
 
eR = μ
ρvD
 
 
r p( )P = C k
μ
 
 
Td =  
ln ( ) T −Tsat in
T −Tsat out
(T −T )−(T −T )sat out sat in
 
 
 
 
A =   ( )A
Q
Qneeded
 
 
where: 
i = each stream in the condenser or reboiler 
k​pipe​ = 400 W/mC 
D = 0.1407m 
x = 0.0021m 
 
Q​needed​, viscosity ( ), thermal conductivity (k), density ( ). T​in​, and T​out​ data was found from ourμ ρ  
HYSYS simulation for each exit stream of either the condenser or reboiler.  
 
From this set of equation we were able to calculate the surface area of the heat exchanger for the 
reboiler and condenser in the distillation column. The reboiler surface area is 2.4m​2​
, and the 
condenser is 3.63m​2​
.  
 
S3.1 Condenser and Reboiler Cost Summary 
Knowing the surface area (A) of the condenser and reboiler, we used Figure A.5 in Appendix A 
of Turtin to find a C​p​
0​
/A($/m​2​
) where: 
C0
p =
C0
p
A( )$
m2
* A  
 
To calculate the bare module cost (C​BM​) of this heat exchanger we used the following equation: 
 
(B F F )CBM = C0
p 1 + B2 M P  
 
where: 
B​1​ = 1.74 
B​2​ = 1.55 
F​M​ = 1 
F​P​ = 1 
 
We calculated a bare module cost of $7,166 for the condenser, and $7,915 for the reboiler. 
 
Total Capital Coat = $524,751 
 
 
 
 
 
Project: Chloromethane synthesis from methane 
Unit Name/ID: S3.2 Distillation Column 
Unit Type: Distillation Column 
Sizing Basis: Volume, m​3
 
 
 
Unit Diagram 
 
 
 
Stream Table:​ All values in kg/hr. 
Stream ID:  S3.s2  S3.s3  S3.s4 
Total  676.1703  316.8983  359.2720 
Cl2  1.1815  1.1810  0.0005 
CH3Cl  314.6842  314.4740  0.2102 
CH2Cl2  259.5215  1.2432  258.2783 
CHCl3  85.1140  0.0000  85.1140 
CCl4  15.6690  0.0000  15.6690 
 
 
S3.2 – Distillation Column Size Summary 
Column Diameter = 1.193m 
Number of Trays = 33 
Column Height = 16.5m (assuming the distance between each tray is 0.5m) 
 
olumn V olume π olumn HeightC =   * ( )2
Column Diameter 2
* C  
 
Column Volume = 18.4m​3 
 
S3.2 – Distillation Column Cost Summary 
We found the distillation column to have a volume of 18.4m​3​
. Looking in Table A.1 of Turton 
we determined the purchased equipment cost at ambient operating pressure and using carbon 
steel construction with the following equation: 
 
 C   log  (A)  [log  (A) ]log10
0
p = K1 + K2 10 + K3 10
2
 
where: 
A = 18.4m​3
 
K​1​ = 3.4974 
K​2​ = 0.4485 
K​3​ = 0.1074 
 
 
 
The bare module cost (C​BM​) for this vessel has to account for its material factors (F​M​) and 
pressure factor (F​P​). 
 
(B F F )CBM = C0
p 1 + B2 M P  
 
 
FP,vessel = 0.0063
+0.00315(P+1)D
2[850−0.6(P+1)]
 
 
 
where 
D = 1.193m 
B​1​ = 2.25 
B​2​ = 1.82 
F​M​ = 9.4 
P = 3.01 barg 
 
The base module cost (C​BM​) was found to be $287,931 
 
S3.2 Condenser and Reboiler Size Summary 
Using the following set of equations as well as information from HYSYS, we were able to size 
the condensers as well as reboilers in the distillation column. For the condensers we used liquid 
nitrogen and for the reboilers we used saturated steam.  
 
A
Q
= dT
+∑
 
 
1
hi k
x
pipe
 
 
hi = D
k Nui
 
 
u .023Re PrN = 0 0.8 0.3
 
 
eR = μ
ρvD
 
 
r p( )P = C k
μ
 
 
Td =  
ln ( ) T −Tsat in
T −Tsat out
(T −T )−(T −T )sat out sat in
 
 
A =   ( )A
Q
Qneeded
 
where: 
i = each stream in the condenser or reboiler 
k​pipe​ = 400 W/mC 
D = 0.1407m 
x = 0.0021m 
 
 
 
Q​needed​, viscosity ( ), thermal conductivity (k), density ( ). T​in​, and T​out​ data was found from ourμ ρ  
HYSYS simulation for each exit stream of either the condenser or reboiler.  
 
From this set of equation we were able to calculate the surface area of the heat exchanger for the 
reboiler and condenser in the distillation column. The reboiler surface area is 14.19m​2​
, and the 
condenser is 14.89m​2​
.  
 
S3.2 Condenser and Reboiler Cost Summary 
Knowing the surface area (A) of the condenser and reboiler, we used Figure A.5 in Appendix A 
of Turtin to find a C​p​
0​
/A($/m​2​
) where: 
C0
p =
C0
p
A( )$
m2
* A  
 
To calculate the bare module cost (C​BM​) of this heat exchanger we used the following equation: 
 
(B F F )CBM = C0
p 1 + B2 M P  
 
where: 
B​1​ = 1.74 
B​2​ = 1.55 
F​M​ = 1 
F​P​ = 1 
 
We calculated a bare module cost of $17,146 for the condenser, and $16,340 for the reboiler. 
 
Total Capital Coat = $321,417 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Project: Chloromethane synthesis from methane 
Unit Name/ID: S3.3 Distillation Column 
Unit Type: Distillation Column 
Sizing Basis: Volume, m​3
 
 
 
 
 
Unit Diagram 
 
Stream Table:​ All values in kg/hr. 
Stream ID:  S3.s4  S3.s5  S3.s6 
Total  359.2720  254.7190  104.5531 
Cl2  0.0005  0.0005  0.0000 
CH3Cl  0.2102  0.2102  0.0000 
CH2Cl2  258.2783  254.2844  3.9940 
CHCl3  85.1140  0.1996  84.9144 
CCl4  15.6690  0.0243  15.6447 
 
 
S3.3 – Distillation Column Size Summary 
Column Diameter = 1.193m 
Number of Trays = 73 
Column Height = 36.5m (assuming the distance between each tray is 0.5m) 
 
olumn V olume π olumn HeightC =   * ( )2
Column Diameter 2
* C  
 
Column Volume = 40.8m​3 
 
S3.3 – Distillation Column Cost Summary 
We found the distillation column to have a volume of 40.8m​3​
. Looking in Table A.1 of Turton 
we determined the purchased equipment cost at ambient operating pressure and using carbon 
steel construction with the following equation: 
 
 C   log  (A)  [log  (A) ]log10
0
p = K1 + K2 10 + K3 10
2
 
where: 
A = 40.8m​3
 
K​1​ = 3.4974 
K​2​ = 0.4485 
K​3​ = 0.1074 
 
 
 
The bare module cost (C​BM​) for this vessel has to account for its material factors (F​M​) and 
pressure factor (F​P​). 
 
(B F F )CBM = C0
p 1 + B2 M P  
 
 
FP,vessel = 0.0063
+0.00315(P+1)D
2[850−0.6(P+1)]
 
 
 
where 
D = 1.193m 
B​1​ = 2.25 
B​2​ = 1.82 
F​M​ = 9.4 
P = 3.01 barg 
 
The base module cost (C​BM​) was found to be $509,676 
 
S3.3 Condenser and Reboiler Size Summary 
Using the following set of equations as well as information from HYSYS, we were able to size 
the condensers as well as reboilers in the distillation column. For the condensers we used liquid 
nitrogen and for the reboilers we used saturated steam.  
 
A
Q
= dT
+∑
 
 
1
hi k
x
pipe
 
 
hi = D
k Nui
 
 
u .023Re PrN = 0 0.8 0.3
 
 
eR = μ
ρvD
 
 
r p( )P = C k
μ
 
 
Td =  
ln ( ) T −Tsat in
T −Tsat out
(T −T )−(T −T )sat out sat in
 
 
A =   ( )A
Q
Qneeded
 
where: 
i = each stream in the condenser or reboiler 
k​pipe​ = 400 W/mC 
D = 0.1407m 
x = 0.0021m 
 
 
 
Q​needed​, viscosity ( ), thermal conductivity (k), density ( ). T​in​, and T​out​ data was found from ourμ ρ  
HYSYS simulation for each exit stream of either the condenser or reboiler.  
 
From this set of equation we were able to calculate the surface area of the heat exchanger for the 
reboiler and condenser in the distillation column. The reboiler surface area is 102.2m​2​
, and the 
condenser is 70.16m​2​
.  
 
S3.3 Condenser and Reboiler Cost Summary 
Knowing the surface area (A) of the condenser and reboiler, we used Figure A.5 in Appendix A 
of Turtin to find a C​p​
0​
/A($/m​2​
) where: 
C0
p =
C0
p
A( )$
m2
* A  
 
To calculate the bare module cost (C​BM​) of this heat exchanger we used the following equation: 
 
(B F F )CBM = C0
p 1 + B2 M P  
 
where: 
B​1​ = 1.74 
B​2​ = 1.55 
F​M​ = 1 
F​P​ = 1 
 
We calculated a bare module cost of $57,707 for the condenser, and $100,871 for the reboiler. 
 
Total Capital Coat = $668,254 
 
 

More Related Content

What's hot

Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15Bill Rogers
 
Session T6 - Artificial Intelligence Meets Project Controls
Session T6 - Artificial Intelligence Meets Project ControlsSession T6 - Artificial Intelligence Meets Project Controls
Session T6 - Artificial Intelligence Meets Project Controls
Project Controls Expo
 
EPA Presentation - Andy Smith
EPA Presentation - Andy SmithEPA Presentation - Andy Smith
EPA Presentation - Andy Smith
Andy Smith
 
Gyasi Brown Resume 6-8-16
Gyasi Brown Resume 6-8-16Gyasi Brown Resume 6-8-16
Gyasi Brown Resume 6-8-16Gyasi Brown
 
edSe275 ms project-assignment
edSe275 ms project-assignmentedSe275 ms project-assignment
edSe275 ms project-assignment
harinathinfotech
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2
Narayan Mane
 

What's hot (9)

Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15
 
Session T6 - Artificial Intelligence Meets Project Controls
Session T6 - Artificial Intelligence Meets Project ControlsSession T6 - Artificial Intelligence Meets Project Controls
Session T6 - Artificial Intelligence Meets Project Controls
 
Varun Garg_CV
Varun Garg_CVVarun Garg_CV
Varun Garg_CV
 
EPA Presentation - Andy Smith
EPA Presentation - Andy SmithEPA Presentation - Andy Smith
EPA Presentation - Andy Smith
 
Gyasi Brown Resume 6-8-16
Gyasi Brown Resume 6-8-16Gyasi Brown Resume 6-8-16
Gyasi Brown Resume 6-8-16
 
edSe275 ms project-assignment
edSe275 ms project-assignmentedSe275 ms project-assignment
edSe275 ms project-assignment
 
Ragab_Personel CV _Form_Jan_2015
Ragab_Personel CV _Form_Jan_2015Ragab_Personel CV _Form_Jan_2015
Ragab_Personel CV _Form_Jan_2015
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2
 
Resume rahul iyer jan 2014 vietnam
Resume rahul iyer jan 2014 vietnamResume rahul iyer jan 2014 vietnam
Resume rahul iyer jan 2014 vietnam
 

Similar to PR3_final.JCT.AGK.docx

Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Mohammad Lemar ZALMAİ
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
G K, BE,MS,ISTQB Certified Expert
 
E3 NC Summary Report_FINAL
E3 NC Summary Report_FINALE3 NC Summary Report_FINAL
E3 NC Summary Report_FINALaemangum
 
John Stewart CV 2016
John Stewart CV 2016John Stewart CV 2016
John Stewart CV 2016John Stewart
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
KareemBullard1
 
Earned Effort Analysis
Earned Effort AnalysisEarned Effort Analysis
Earned Effort Analysis
Rodrigo Carvalho Pinho, PMP
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET Journal
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec doms
Babasab Patil
 
Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725
Minn Lwin
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
PMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost ManagementPMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost Management
Mohamed ElSaadany, PMP, CCP, PMI-RMP, SCE-PE
 
CYS EN ISO 50001 is Proven to Generate Significant Energy Savings! (Part 2 of...
CYS EN ISO 50001 is Proven to Generate Significant Energy Savings! (Part 2 of...CYS EN ISO 50001 is Proven to Generate Significant Energy Savings! (Part 2 of...
CYS EN ISO 50001 is Proven to Generate Significant Energy Savings! (Part 2 of...
Arantico Ltd
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
priyang2004
 
Six Sigma BB Project Update
Six Sigma BB Project UpdateSix Sigma BB Project Update
Six Sigma BB Project Update
cybermetheus
 
Design of a Prevention, Appraisal and Failure Cost Model
Design of a Prevention, Appraisal and Failure Cost ModelDesign of a Prevention, Appraisal and Failure Cost Model
Design of a Prevention, Appraisal and Failure Cost Model
Tennelli Industries (Pty) Ltd
 
Project performance tracking analysis and reporting
Project performance tracking analysis and reportingProject performance tracking analysis and reporting
Project performance tracking analysis and reporting
Charles Cotter, PhD
 

Similar to PR3_final.JCT.AGK.docx (20)

Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
E3 NC Summary Report_FINAL
E3 NC Summary Report_FINALE3 NC Summary Report_FINAL
E3 NC Summary Report_FINAL
 
Tim Howard
Tim HowardTim Howard
Tim Howard
 
John Stewart CV 2016
John Stewart CV 2016John Stewart CV 2016
John Stewart CV 2016
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
Earned Effort Analysis
Earned Effort AnalysisEarned Effort Analysis
Earned Effort Analysis
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec doms
 
Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
PMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost ManagementPMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost Management
 
CYS EN ISO 50001 is Proven to Generate Significant Energy Savings! (Part 2 of...
CYS EN ISO 50001 is Proven to Generate Significant Energy Savings! (Part 2 of...CYS EN ISO 50001 is Proven to Generate Significant Energy Savings! (Part 2 of...
CYS EN ISO 50001 is Proven to Generate Significant Energy Savings! (Part 2 of...
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
 
LRAFB_Project Profile
LRAFB_Project ProfileLRAFB_Project Profile
LRAFB_Project Profile
 
Six Sigma BB Project Update
Six Sigma BB Project UpdateSix Sigma BB Project Update
Six Sigma BB Project Update
 
Design of a Prevention, Appraisal and Failure Cost Model
Design of a Prevention, Appraisal and Failure Cost ModelDesign of a Prevention, Appraisal and Failure Cost Model
Design of a Prevention, Appraisal and Failure Cost Model
 
JHS resume 10_29_15
JHS resume 10_29_15JHS resume 10_29_15
JHS resume 10_29_15
 
VAWT Report
VAWT ReportVAWT Report
VAWT Report
 
Project performance tracking analysis and reporting
Project performance tracking analysis and reportingProject performance tracking analysis and reporting
Project performance tracking analysis and reporting
 

PR3_final.JCT.AGK.docx