i. The Phuentsholing Township Development Project was conceived in 2003 and aims to mitigate flood risks in Phuentsholing through river training and urban development.
ii. The project will reclaim over 157 acres of land for development, improve infrastructure, and make more land habitable. Funding is provided by the Asian Development Bank and Druk Holding & Investments is the executing agency.
iii. Key works underway include river training through embankments and land reclamation (Package CW-01), and construction of roads, utilities, and other infrastructure (Package CW-02A). Coordination with the Bhutan Power Corporation is also occurring for power infrastructure connections.
- The Works Department in Gilgit-Baltistan oversees infrastructure projects including roads, bridges, buildings, and water supply systems.
- It has a 3 year plan to complete projects on schedule by ensuring timely funding and linking allocations to project phasing.
- A 10 year plan aims to expand clean water access, improve transportation infrastructure through road metaling and bridge conversions.
- Budget and accounts data show funds allocated for maintenance of divisions and challenges around contractor liabilities and audit paras.
- A development profile outlines sector-wise approved and unapproved projects across Gilgit-Baltistan districts.
The document provides a status report for the Hydrology Project-II in Odisha, India. It summarizes that the project strengthened groundwater monitoring infrastructure by upgrading 198 piezometers and installing 28 telemetry systems. It also conducted training programs and implemented two pilot demonstration studies on drought monitoring and conjunctive water use. Challenges in project implementation included delays due to multiple approval procedures and lack of a dedicated project team. The state government is being requested to continue funding activities to sustain improvements from the project.
This presentation proposes converting the existing 136km 4-lane Karachi–Hyderabad Superhighway into a 6-lane motorway (M-9) on a build–operate–transfer basis. Bina Puri Pakistan is the concessionaire that will undertake the design, construction, operation, and maintenance of the motorway for 28 years. The project will cost USD 203 million to widen the highway, add new interchanges, toll plazas, and rest areas. Bina Puri has completed technical studies and is working to finalize financing from banks to reach financial close by July 2012 so construction can begin on schedule.
Cv kanai deb nath, project economist dec- 2021ssuser8943fd
This document provides a curriculum vitae for Kanai Deb Nath, who is applying for the position of Project Economist. It includes details of his education, professional experience, areas of expertise, and past projects. Over his career, Mr. Nath has worked on numerous infrastructure projects in Bangladesh and Afghanistan, conducting economic and financial analysis to evaluate the viability of proposed interventions. His experience includes assessing rural connectivity, urban governance, and climate resilience projects funded by organizations like ADB, World Bank, and others. He has over 40 years of experience working in roles related to project economics, monitoring and evaluation, and financial analysis.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Oswar Mungkasa
The PPP Book aims to provide reliable information to prospective investors
on projects in the PPP pipeline. Its true value lies in the accuracy of the
information. Projects are categorized according to the stage of development
they have reached. A PPP project must be market ready in the true sense of
the word when it is categorized as “ready for offer”. What this implies is that
the basic conditions underlying its business case, such as land availability
and government support (if applicable) are largely met or soon to be met.
The current PPP Book is an update of the 2011 version, incorporating recent
developments. To date, 12 projects have been tendered out. In this 2012
version, there are 3 projects ready for offer, 26 projects under the category
“priority” and 29 projects under “potential”. There are 9 new projects that
are not in the 2011 PPP Book, of which 1 is classified as “priority” and 8
as “potential”. A significant difference from the 2011 version is that the
number of “potential” projects is reduced from 45 to 29 as a result of more
rigorous screening.
1. Alandur is a suburb of Chennai that lacked a sewerage system, and wastewater was collected in septic tanks or holding tanks that were irregularly cleared.
2. In 1997, the Government of Tamil Nadu decided to provide sewerage systems to 12 urban centers, including Alandur, through a World Bank funded project.
3. The Alandur Sewerage Project was implemented between 1997-2003 to provide a sewerage network and sewage treatment plant to improve sanitation for Alandur's growing population.
- The Works Department in Gilgit-Baltistan oversees infrastructure projects including roads, bridges, buildings, and water supply systems.
- It has a 3 year plan to complete projects on schedule by ensuring timely funding and linking allocations to project phasing.
- A 10 year plan aims to expand clean water access, improve transportation infrastructure through road metaling and bridge conversions.
- Budget and accounts data show funds allocated for maintenance of divisions and challenges around contractor liabilities and audit paras.
- A development profile outlines sector-wise approved and unapproved projects across Gilgit-Baltistan districts.
The document provides a status report for the Hydrology Project-II in Odisha, India. It summarizes that the project strengthened groundwater monitoring infrastructure by upgrading 198 piezometers and installing 28 telemetry systems. It also conducted training programs and implemented two pilot demonstration studies on drought monitoring and conjunctive water use. Challenges in project implementation included delays due to multiple approval procedures and lack of a dedicated project team. The state government is being requested to continue funding activities to sustain improvements from the project.
This presentation proposes converting the existing 136km 4-lane Karachi–Hyderabad Superhighway into a 6-lane motorway (M-9) on a build–operate–transfer basis. Bina Puri Pakistan is the concessionaire that will undertake the design, construction, operation, and maintenance of the motorway for 28 years. The project will cost USD 203 million to widen the highway, add new interchanges, toll plazas, and rest areas. Bina Puri has completed technical studies and is working to finalize financing from banks to reach financial close by July 2012 so construction can begin on schedule.
Cv kanai deb nath, project economist dec- 2021ssuser8943fd
This document provides a curriculum vitae for Kanai Deb Nath, who is applying for the position of Project Economist. It includes details of his education, professional experience, areas of expertise, and past projects. Over his career, Mr. Nath has worked on numerous infrastructure projects in Bangladesh and Afghanistan, conducting economic and financial analysis to evaluate the viability of proposed interventions. His experience includes assessing rural connectivity, urban governance, and climate resilience projects funded by organizations like ADB, World Bank, and others. He has over 40 years of experience working in roles related to project economics, monitoring and evaluation, and financial analysis.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Oswar Mungkasa
The PPP Book aims to provide reliable information to prospective investors
on projects in the PPP pipeline. Its true value lies in the accuracy of the
information. Projects are categorized according to the stage of development
they have reached. A PPP project must be market ready in the true sense of
the word when it is categorized as “ready for offer”. What this implies is that
the basic conditions underlying its business case, such as land availability
and government support (if applicable) are largely met or soon to be met.
The current PPP Book is an update of the 2011 version, incorporating recent
developments. To date, 12 projects have been tendered out. In this 2012
version, there are 3 projects ready for offer, 26 projects under the category
“priority” and 29 projects under “potential”. There are 9 new projects that
are not in the 2011 PPP Book, of which 1 is classified as “priority” and 8
as “potential”. A significant difference from the 2011 version is that the
number of “potential” projects is reduced from 45 to 29 as a result of more
rigorous screening.
1. Alandur is a suburb of Chennai that lacked a sewerage system, and wastewater was collected in septic tanks or holding tanks that were irregularly cleared.
2. In 1997, the Government of Tamil Nadu decided to provide sewerage systems to 12 urban centers, including Alandur, through a World Bank funded project.
3. The Alandur Sewerage Project was implemented between 1997-2003 to provide a sewerage network and sewage treatment plant to improve sanitation for Alandur's growing population.
The document provides an overview and updates on the Bangladesh Urban Resilience Project. Key points include:
- The project aims to strengthen disaster resilience in urban areas and is being implemented by several agencies including DNCC, RAJUK, DDM, and PCMU.
- Major achievements so far include construction of emergency facilities, procurement of search and rescue equipment, vulnerability assessments of buildings, and establishment of the Urban Resilience Unit building.
- Challenges include potential delays in training activities, financial settlement issues, tight timelines for some construction works, and ensuring long-term sustainability and O&M after project completion.
- Recommendations focus on critically reviewing essential project components like training
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxhurain5
The presentation summarizes the 128 MW Keyal Khwar hydropower project located in Kohistan, KPK, Pakistan. The project cost is Rs. 26.084 billion with an expected annual energy generation of 418 GWh once completed. Major project components include an underground powerhouse, headrace tunnels, and a concrete gravity dam. The project has faced delays and cost increases due to issues with land acquisition, contractor performance, and damage from recent floods. Lessons learned include securing land and financing earlier in the process to avoid delays in implementation.
The document provides an overview of the progress and readiness for the Saudi Landbridge Railway Network project. It discusses two potential paths (Path 1 and Path 2) for funding and financing the project. Key points include:
- The project involves constructing a 2,500 km railway network and 7 logistics centers to connect major cities.
- Path 1 would involve negotiations with China for financing, while Path 2 would see funding from the Public Investment Fund of Saudi Arabia.
- Several challenges to project readiness were identified, including finalizing designs, securing necessary approvals and budgets, and completing land acquisition.
- A roadmap was proposed to address these challenges over the next 2-3 years through steps like awarding
Civil engineer +MBA . More than 25 years experience in Infrastructure development projects, Development of Industrial corridors and Project Management.
Planning in the region starts with a vision about what we want to be. It is the aspiration of the Filipinos particularly those from SOCCSKSARGEN Region to have a long-term vision for the region and the country as a whole to become a prosperous, predominantly middle class society where no one is poor. The challenge is how every Filipino can afford to have a “matatag, maginhawa at panatag na buhay by 2040.”
This document summarizes the progress and completion of the Odisha Hydrology Project-II. The key points are:
1) The project had a total revised cost of Rs. 13.46 crore and ran from April 2006 to May 2014 to strengthen surface water data collection and decision support systems in Odisha.
2) Financial progress shows that Rs. 891.04 crore was spent out of the total revised cost of Rs. 1346 crore. Major components included installing a real-time data acquisition system and developing decision support systems for drought monitoring and conjunctive surface and groundwater use.
3) Key achievements were establishing the concept for a real-time data acquisition system,
The project completion report summarizes the Northern Area Rural Power Distribution Project in Laos. The project involved constructing 115kV transmission lines, substations, and medium- and low-voltage distribution systems to provide electricity to rural areas in northern Laos. Key outputs included installing 10,464km of transmission lines and completing environmental mitigation works. The project was completed on budget with all funds disbursed. Sustainability is preliminarily assessed as likely due to community support and government commitment to operations and maintenance. The project achieved its objectives of expanding power access in a relevant, effective, and efficient manner.
The document provides terms of reference for conducting feasibility studies and preliminary design for two elevated expressway projects in Dhaka, Bangladesh: 1) The Dhaka-Ashulia Elevated Expressway Project, and 2) The East-West Middle/Outer Ring Road Elevated Expressway Project. The scope of work includes traffic studies, environmental and social assessments, preliminary design, and preparation of a land acquisition plan and resettlement action plan. The studies aim to address traffic congestion in Dhaka through the development of new elevated expressways.
The document provides details about a summer internship with the Central Public Works Department of India from June 13th to July 25th 2016. The internship involves assisting with the construction of an additional office complex for the Supreme Court of India near Pragati Maidan in New Delhi. The Central Public Works Department is a government authority responsible for public construction works across India with over 150 years of experience. The additional office complex will consist of six blocks up to 8 stories tall and provide office, judicial, auditorium and parking spaces. Construction involves excavating three basement levels, installing raft foundations, and erecting the concrete superstructure.
The Hydrology Project Phase II in Puducherry aimed to strengthen water monitoring infrastructure and capacity building. Key achievements include constructing 37 observation wells, 2 weather stations, a level II water testing lab, and a state-of-the-art data center. Over 100 staff were trained. The project also included installing equipment, collecting data, identifying recharge sites, and creating a website to disseminate water resources data. While most targets were met, some equipment is still being installed at the testing lab. A society was formed to maintain assets after project completion.
This document provides biographical and professional details about Ahmad Hazwan Bin Abdul Muaais. It includes his contact information, personal particulars, educational background, skills and proficiencies, achievements, work experience, and current job scope working as a Pipeline Engineer for Petronas Carigali. Some of his current projects include the Angsi Chemical Enhanced Oil Recovery project and Dulang East Development project, where he is involved in conceptual studies, frontend engineering design, and technical evaluation of engineering bids.
Present status of apartment building approval and constructionBinay Shrestha
This document summarizes the findings of a study on the present status of apartment building approval and construction processes in Kathmandu Valley. It was presented by representatives from various organizations. The presentation covered the background of the study, data collection and analysis methodology, key findings, and recommendations. Some of the major findings included the lengthy approval process, weak project management and monitoring, safety issues, and lack of resources at the Department of Urban Development and Building Construction. Recommendations focused on strengthening this department and prioritizing safety.
My specialty is Project Controls. I have 10+ years of intense and diverse experience and training in many facets of project management, financial planning and have excellent communication skills that complement my experience. Some highlights of my career are :
• Project Planning & Scheduling
• Progress Monitoring
• Performance Reporting
• Change Management – Time & Cost
• Bidding and Proposals Management
• Technical Writing- Plans, Method Statements etc.
Detailed presentation of Arch and cable stayed bridge connecting bandra to worli in Mumbai.One of the traffic decongestion efforts by Municipal corporation of Bombay.
Our Future Valley - Developer Session January 28, 2021Allison Zinnick
This document provides an agenda for a meeting on planning in Sturgeon Valley Special Study Areas A and B. Key discussion points included recapping a previous meeting, survey results from developers, planning pathways and responsibilities, and communications. The survey showed mixed feedback from developers. Planning pathways would include an area structure plan with development strategies and detailed plans for identified planning areas. Developers would be responsible for studies and plans within their areas. Clarification was provided on the concept of "demonstrated need." Upcoming engagement sessions in February would explore public expectations on densities and character.
The document discusses the City of Bunbury's long term strategic planning through 2030. It outlines strategies like the Bunbury Integrated Land Use & Transport Vision 2030 and Housing, Commercial, and Industry Strategies to guide development. It also mentions the City's use of its Town Planning Scheme No.7 and Spatial Technology GIS system to implement the strategies and record property data over the next 5-10 years. Developments happening in and around Bunbury are noted.
The Planning and Development Department of Khyber Pakhtunkhwa is proposing the implementation of a new mega project called the Peshawar Uplift Program (PUP) to address civic issues in Peshawar. Rapid population growth and unplanned construction have caused health and infrastructure problems like sewage flowing into irrigation channels and rivers. Only a small percentage of the population is connected to sewer lines or uses solid waste facilities. Past development schemes were fragmented. The PUP aims to improve civic amenities, raise awareness, and coordinate stakeholders at a total cost of Rs. 1000 million over multiple years. The implementation strategy is to house PUP at P&D Department and execute it through program-based flexible coordination of
The document provides details about the Chittagong City Outer Ring Road Project in Bangladesh, which aims to construct a coastal road and strengthen embankments to mitigate flooding during monsoons. It will require acquiring 44.84 hectares of land and will negatively impact over 2,800 households. The project is expected to bring transportation and economic benefits to the city but also entails social impacts that must be addressed. Various organizations like the Chittagong Development Authority, Deputy Commissioner, and consultants are involved in implementing the resettlement action plan to compensate affected people and communities in accordance with guidelines.
Essam Harby has over 26 years of experience in program planning and project controls management across various sectors such as residential, hospitality, commercial, education, and infrastructure. He has worked on large projects in Saudi Arabia and Egypt with budgets totaling billions. His responsibilities have included developing baseline schedules and budgets, analyzing impacts of changes, and reviewing progress reports. He is proficient in Primavera P6 and MS Project and has managed complex program and project controls systems.
The document provides an overview and updates on the Bangladesh Urban Resilience Project. Key points include:
- The project aims to strengthen disaster resilience in urban areas and is being implemented by several agencies including DNCC, RAJUK, DDM, and PCMU.
- Major achievements so far include construction of emergency facilities, procurement of search and rescue equipment, vulnerability assessments of buildings, and establishment of the Urban Resilience Unit building.
- Challenges include potential delays in training activities, financial settlement issues, tight timelines for some construction works, and ensuring long-term sustainability and O&M after project completion.
- Recommendations focus on critically reviewing essential project components like training
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxhurain5
The presentation summarizes the 128 MW Keyal Khwar hydropower project located in Kohistan, KPK, Pakistan. The project cost is Rs. 26.084 billion with an expected annual energy generation of 418 GWh once completed. Major project components include an underground powerhouse, headrace tunnels, and a concrete gravity dam. The project has faced delays and cost increases due to issues with land acquisition, contractor performance, and damage from recent floods. Lessons learned include securing land and financing earlier in the process to avoid delays in implementation.
The document provides an overview of the progress and readiness for the Saudi Landbridge Railway Network project. It discusses two potential paths (Path 1 and Path 2) for funding and financing the project. Key points include:
- The project involves constructing a 2,500 km railway network and 7 logistics centers to connect major cities.
- Path 1 would involve negotiations with China for financing, while Path 2 would see funding from the Public Investment Fund of Saudi Arabia.
- Several challenges to project readiness were identified, including finalizing designs, securing necessary approvals and budgets, and completing land acquisition.
- A roadmap was proposed to address these challenges over the next 2-3 years through steps like awarding
Civil engineer +MBA . More than 25 years experience in Infrastructure development projects, Development of Industrial corridors and Project Management.
Planning in the region starts with a vision about what we want to be. It is the aspiration of the Filipinos particularly those from SOCCSKSARGEN Region to have a long-term vision for the region and the country as a whole to become a prosperous, predominantly middle class society where no one is poor. The challenge is how every Filipino can afford to have a “matatag, maginhawa at panatag na buhay by 2040.”
This document summarizes the progress and completion of the Odisha Hydrology Project-II. The key points are:
1) The project had a total revised cost of Rs. 13.46 crore and ran from April 2006 to May 2014 to strengthen surface water data collection and decision support systems in Odisha.
2) Financial progress shows that Rs. 891.04 crore was spent out of the total revised cost of Rs. 1346 crore. Major components included installing a real-time data acquisition system and developing decision support systems for drought monitoring and conjunctive surface and groundwater use.
3) Key achievements were establishing the concept for a real-time data acquisition system,
The project completion report summarizes the Northern Area Rural Power Distribution Project in Laos. The project involved constructing 115kV transmission lines, substations, and medium- and low-voltage distribution systems to provide electricity to rural areas in northern Laos. Key outputs included installing 10,464km of transmission lines and completing environmental mitigation works. The project was completed on budget with all funds disbursed. Sustainability is preliminarily assessed as likely due to community support and government commitment to operations and maintenance. The project achieved its objectives of expanding power access in a relevant, effective, and efficient manner.
The document provides terms of reference for conducting feasibility studies and preliminary design for two elevated expressway projects in Dhaka, Bangladesh: 1) The Dhaka-Ashulia Elevated Expressway Project, and 2) The East-West Middle/Outer Ring Road Elevated Expressway Project. The scope of work includes traffic studies, environmental and social assessments, preliminary design, and preparation of a land acquisition plan and resettlement action plan. The studies aim to address traffic congestion in Dhaka through the development of new elevated expressways.
The document provides details about a summer internship with the Central Public Works Department of India from June 13th to July 25th 2016. The internship involves assisting with the construction of an additional office complex for the Supreme Court of India near Pragati Maidan in New Delhi. The Central Public Works Department is a government authority responsible for public construction works across India with over 150 years of experience. The additional office complex will consist of six blocks up to 8 stories tall and provide office, judicial, auditorium and parking spaces. Construction involves excavating three basement levels, installing raft foundations, and erecting the concrete superstructure.
The Hydrology Project Phase II in Puducherry aimed to strengthen water monitoring infrastructure and capacity building. Key achievements include constructing 37 observation wells, 2 weather stations, a level II water testing lab, and a state-of-the-art data center. Over 100 staff were trained. The project also included installing equipment, collecting data, identifying recharge sites, and creating a website to disseminate water resources data. While most targets were met, some equipment is still being installed at the testing lab. A society was formed to maintain assets after project completion.
This document provides biographical and professional details about Ahmad Hazwan Bin Abdul Muaais. It includes his contact information, personal particulars, educational background, skills and proficiencies, achievements, work experience, and current job scope working as a Pipeline Engineer for Petronas Carigali. Some of his current projects include the Angsi Chemical Enhanced Oil Recovery project and Dulang East Development project, where he is involved in conceptual studies, frontend engineering design, and technical evaluation of engineering bids.
Present status of apartment building approval and constructionBinay Shrestha
This document summarizes the findings of a study on the present status of apartment building approval and construction processes in Kathmandu Valley. It was presented by representatives from various organizations. The presentation covered the background of the study, data collection and analysis methodology, key findings, and recommendations. Some of the major findings included the lengthy approval process, weak project management and monitoring, safety issues, and lack of resources at the Department of Urban Development and Building Construction. Recommendations focused on strengthening this department and prioritizing safety.
My specialty is Project Controls. I have 10+ years of intense and diverse experience and training in many facets of project management, financial planning and have excellent communication skills that complement my experience. Some highlights of my career are :
• Project Planning & Scheduling
• Progress Monitoring
• Performance Reporting
• Change Management – Time & Cost
• Bidding and Proposals Management
• Technical Writing- Plans, Method Statements etc.
Detailed presentation of Arch and cable stayed bridge connecting bandra to worli in Mumbai.One of the traffic decongestion efforts by Municipal corporation of Bombay.
Our Future Valley - Developer Session January 28, 2021Allison Zinnick
This document provides an agenda for a meeting on planning in Sturgeon Valley Special Study Areas A and B. Key discussion points included recapping a previous meeting, survey results from developers, planning pathways and responsibilities, and communications. The survey showed mixed feedback from developers. Planning pathways would include an area structure plan with development strategies and detailed plans for identified planning areas. Developers would be responsible for studies and plans within their areas. Clarification was provided on the concept of "demonstrated need." Upcoming engagement sessions in February would explore public expectations on densities and character.
The document discusses the City of Bunbury's long term strategic planning through 2030. It outlines strategies like the Bunbury Integrated Land Use & Transport Vision 2030 and Housing, Commercial, and Industry Strategies to guide development. It also mentions the City's use of its Town Planning Scheme No.7 and Spatial Technology GIS system to implement the strategies and record property data over the next 5-10 years. Developments happening in and around Bunbury are noted.
The Planning and Development Department of Khyber Pakhtunkhwa is proposing the implementation of a new mega project called the Peshawar Uplift Program (PUP) to address civic issues in Peshawar. Rapid population growth and unplanned construction have caused health and infrastructure problems like sewage flowing into irrigation channels and rivers. Only a small percentage of the population is connected to sewer lines or uses solid waste facilities. Past development schemes were fragmented. The PUP aims to improve civic amenities, raise awareness, and coordinate stakeholders at a total cost of Rs. 1000 million over multiple years. The implementation strategy is to house PUP at P&D Department and execute it through program-based flexible coordination of
The document provides details about the Chittagong City Outer Ring Road Project in Bangladesh, which aims to construct a coastal road and strengthen embankments to mitigate flooding during monsoons. It will require acquiring 44.84 hectares of land and will negatively impact over 2,800 households. The project is expected to bring transportation and economic benefits to the city but also entails social impacts that must be addressed. Various organizations like the Chittagong Development Authority, Deputy Commissioner, and consultants are involved in implementing the resettlement action plan to compensate affected people and communities in accordance with guidelines.
Essam Harby has over 26 years of experience in program planning and project controls management across various sectors such as residential, hospitality, commercial, education, and infrastructure. He has worked on large projects in Saudi Arabia and Egypt with budgets totaling billions. His responsibilities have included developing baseline schedules and budgets, analyzing impacts of changes, and reviewing progress reports. He is proficient in Primavera P6 and MS Project and has managed complex program and project controls systems.
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka ! Fix Satta Matka ! Matka Result ! Matka Guessing ! Final Matka ! Matka Result ! Dpboss Matka ! Matka Guessing ! Satta Matta Matka 143 ! Kalyan Matka ! Satta Matka Fast Result ! Kalyan Matka Guessing ! Dpboss Matka Guessing ! Satta 143 ! Kalyan Chart ! Kalyan final ! Satta guessing ! Matka tips ! Matka 143 ! India Matka ! Matka 420 ! matka Mumbai ! Satta chart ! Indian Satta ! Satta King ! Satta 143 ! Satta batta ! Satta मटका ! Satta chart ! Matka 143 ! Matka Satta ! India Matka ! Indian Satta Matka ! Final ank
❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart Final Matka Satta Matta Matka 143 Kalyan Chart Satta fix Jodi Kalyan Final ank Matka Boss Satta 143 Matka 420 Golden Matka Final Satta Kalyan Penal Chart Dpboss 143 Guessing Kalyan Night Chart
Heart Touching Romantic Love Shayari In English with ImagesShort Good Quotes
Explore our beautiful collection of Romantic Love Shayari in English to express your love. These heartfelt shayaris are perfect for sharing with your loved one. Get the best words to show your love and care.
KALYAN MATKA | MATKA RESULT | KALYAN MATKA TIPS | SATTA MATKA | MATKA.COM | MATKA PANA JODI TODAY | BATTA SATKA | MATKA PATTI JODI NUMBER | MATKA RESULTS | MATKA CHART | MATKA JODI | SATTA COM | FULL RATE GAME | MATKA GAME | MATKA WAPKA | ALL MATKA RESULT LIVE ONLINE | MATKA RESULT | KALYAN MATKA RESULT | DPBOSS MATKA 143 | MAIN MATKA
The cherry: beauty, softness, its heart-shaped plastic has inspired artists since Antiquity. Cherries and strawberries were considered the fruits of paradise and thus represented the souls of men.
➒➌➎➏➑➐➋➑➐➐KALYAN MATKA | MATKA RESULT | KALYAN MATKA TIPS | SATTA MATKA | MATKA.COM | MATKA PANA JODI TODAY | BATTA SATKA | MATKA PATTI JODI NUMBER | MATKA RESULTS | MATKA CHART | MATKA JODI | SATTA COM | FULL RATE GAME | MATKA GAME | MATKA WAPKA | ALL MATKA RESULT LIVE ONLINE | MATKA RESULT | KALYAN MATKA RESULT | DPBOSS MATKA 143 | MAIN MATKA
This document announces the winners of the 2024 Youth Poster Contest organized by MATFORCE. It lists the grand prize and age category winners for grades K-6, 7-12, and individual age groups from 5 years old to 18 years old.
2. Contents
1. BACKGROUND
2. PROJECT RATIONALE (Vision, Mission & Objectives)
3. PROJECT ORGANIZATION STRUCTURE
4. PROCUREMENT PLAN & PROJECT STATUS (CW-01 & CW-02A)
5. POWER SUPPLY
3. Background: Chronology of Events
Timeline Activity
2003 Initially conceived as “Toorsa River Training & Flood Mitigation Project’
2005 Under a DANIDA financial assistance, the prefeasibility study was carried out by Phuentsholing Thromde
2006 -2007 Detailed feasibility study (Toorsa flood mitigation) was carried out by Danish Hydraulic Institute (DHI), India
May 3, 2010 Project handed over to DHI by MoWHS. DHI then entrusted the work to its subsidiary DHI -INFRA Ltd
Dec 2010 Engaged ILFS, India (Consultant) as so to carry out the Project feasibility studies but was prematurely
terminated in July 2011 for completion of the DPR of Amochhu Hydro Electric Project (AHEP)
Aug 2013 The DPR for AHEP was made available, a revision of the hydrological and hydraulic studies engaging DHI-India,
with AHEP scenario upstream
2014 Around 70 acre of private land which was inside the project area was successfully relocated to the LAP with the
help of Phuentsholing Thromde
Nov 2015 After the international competitive bidding process HCP Design Planning & Management Pvt. Ltd was awarded
the consultancy services for the preparation of Integrated Detailed Project Report (IDPR)
2016 • Asian Development Bank (ADB) indicated their interest to fund the project
• Merger of DHI INFRA and CDCL, Mandate transferred to CDCL (October 2016)
Sept 2017 Completion of IDPR (Integrated Detailed Project Report)
June 5, 2018 Project approved by ADB for financing
July 3, 2018 Project Loan and Grant Agreements with MoF and ADB (AF signed on September 29, 2020)
July 18, 2018 Contract Signed for Package CW-01 & Project implementation Consultant (PIC)
Nov 2018 Implementation of Package-I, (CW-01)
4. i. Conceived as early as 2003
ii. Substantive preparatory works towards implementation started with the issuance of
the Executive Order from the Royal Government of Bhutan on March 02, 2015
iii. Expected Project Impact:
The main purpose of the project is to mitigate the growing risks of flood to the area and to the
existing Phuentsholing City.
While protecting Phuentsholing city from flood threats, around 157 Acre of Land will be retained
(Zone-A), where urban development is proposed.
will ease the demand for space in the commercial hub (80% of country’s trade)
will improve the quality of life for the Phuntsholing residents as a whole
Making habitable about 70 acres of land besides the Project area at LAP, and substantial reduction in
costs of the Phuntsholing-Chamkuna Highway by avoiding protection works.
Background
5. Contents
1. BACKGROUND
2. PROJECT RATIONALE (Vision, Mission & Objectives) & Scope
3. PROJECT FINANCING (ADB & DHI)
4. PROJECT ORGANIZATION STRUCTURE
5. PROCUREMENT PLAN & PROJECT STATUS (CW-01 & CW-02A)
6. ISSUES & CHALLENGES (project implementation)
7. MASTERPLAN & DEVELOPMENT CONTROL REGULATIONS
8. WAY FORWARD:
a. Sustainable Township Management
b. Integration with Existing Township
c. Investment Advisory
6. Rationale – Why this Project?
Mapped Fair Weather Flow after Each Subsequent Flood Over Past 10 Years
Flood Risk along the left bank every year
12. Project Planning & Scope : Site Zoning
PTDP Project Land in acres
Zone A 162.88
Zone B 233.09
Zone C 684.12
Zone E 66.61
Total Developable Land (Acre) 1,146.70
Zone A
Zone B
Zone C
Zone D
Zone E
13. Project Planning & Scope
Boundary of PTDP Project Area – Initial IDPR is prepared inclusive of four Zones (A, B, C & E)
Kaileshwar Hill
Samtse Pling Highway
Phuentsholing
Totapara
Jaigaon
The Project site boundary was fixed based on
the following parameters:
• Northern end is defined by the under
construction Doyagang bridge connecting
Phuentsholing - Samtse Highway.
• North West corner near Toorsa Taar is
demarcated by outer plot boundaries to
exclude private plots.
• Western boundary is defined by base
contour line of Kaileshwar Hill.
• Eastern boundary is bordered by the
existing STP and proposed Phuentsholing
- Samtse Highway.
• Southern end is fixed by the Indo-
Bhutan International border.
Total Project Area – 2076 Acres
14. Funding Agency: Asian Development Bank
&
Druk Holding & Investments (DHI)
Executing Agency: Druk Holding & Investments (DHI)
Implementing Agency : Construction Development Corporation Ltd.
(CDCL)
DHI decided to develop PTDP in a Phased manner, with Zone-A as the start.
Project Planning & Scope:
For Zone-A:
21. Project Output:
# Project Outputs Status
Output 1
Flood and Erosion protection measures installed:
a) construct around 4 kilometers (km) of erosion-resilient river walls to protect
against 100-year probable flood
b) raise ground levels behind the new walls to reclaim at least 66 ha of flood-
protected land for urban development
c) establish and operationalize a flood early warning system and flood
management plan
a) Completed
b) Completed
C) FEWS: under process
by NCHM
(FMC – PIC scope)
Output 2
Municipal infrastructure constructed
a) about 10 km of roads with footpaths, landscaping, and streetlights made
b) modern drinking water supply and distribution systems, and wastewater collection and
treatment systems that service the new township and adjoining areas
c) resource recovery system for managing solid waste in both the new and old townships
established
d) power distribution and telecommunication systems throughout the new township
CW-02A – Contract
Awarded on 4th Nov.
2022
BPC and BT to provide
source connection at the
boundary -Force Account
Output 3
Township management systems installed:
a) establish asset management systems
b) build the capacity of township staff to ensure sustainable and effective urban management
c) initiate investor promotion activities
CS-03: Urban
management Advisor
recruited.
CS-04: Investment
promotion Advisor under
process to recruit
22. Contents
1. BACKGROUND
2. PROJECT RATIONALE (Vision, Mission & Objectives) & Scope
3. PROJECT ORGANIZATION STRUCTURE
4. PROCUREMENT PLAN & PROJECT STATUS (CW-01 & CW-02A)
5. ISSUES & CHALLENGES (project implementation)
6. MASTERPLAN & DEVELOPMENT CONTROL REGULATIONS
7. WAY FORWARD:
a. Sustainable Township Management
b. Integration with Existing Township
c. Investment Advisory
24. Contents
1. BACKGROUND
2. PROJECT RATIONALE (Vision, Mission & Objectives)
3. PROJECT FINANCING (ADB & DHI)
4. PROJECT ORGANIZATION STRUCTURE
5. PROCUREMENT PLAN & PROJECT STATUS (CW-01 & CW-02A)
6. ISSUES & CHALLENGES (project implementation)
7. MASTERPLAN & DEVELOPMENT CONTROL REGULATIONS
8. WAY FORWARD:
a. Sustainable Township Management
b. Integration with Existing Township
c. Investment Advisory
25. Procurement Plan: Works & Goods Packages
Package No Work Package Status
CW-01
River training and land
reclamation
Contractor: M/s AFCONS Infrastructure Ltd.
Project Cost: Nu. 2.935 billion; Duration: 30 months
Project Period: November 2018 – November 2022
CW-02A
Common Urban
Infrastructure
Contractor: Kalika-Rigsar JV
Contract signed on November 4, 2022.
Initial Contract Amount: Nu. 1.748 billion; Duration: 30 months
Project Period: November 2022 – May 2025
CW-02B Landscaping & Greenery works To be awarded in Q1, 2024 (Bid document finalization in 2023)
CW-03
Flood early warning system
(FEWS)
MOU Signed with NCHM on May 2021
Expected Completion – Q2, 2024
Flood Management Plan (FMP) will be prepared by PIC
CW-04
Power transmission
Infrastructure till PTDP boundary
Forced Account – under BPC plan
CW-05 ICT infrastructure outside PTDP
Forced Account – under BT plan
CW-06 Horticulture Re-named as CW-02B (above)
PG-01 Procurement of Goods To be awarded in Q1, 2024 (Document finalization in 2023)
26. Procurement Plan: Consultancy Services
Package No Work Package Status
CS-01
Project implementation Consultant
(PIC)
Contract signed on July 18, 2018.
Input Duration – 79 Months (June 2025)
CS-02
Independent Environment
Monitoring Expert (IEME)
Contract Signed on April 4, 2019
Intermittent inputs until project completion
CS-03 Urban management Advisor
Contract Signed on April 14, 2022
Input Period : 3 months (Intermittent until Q2 2024)
CS-04 Investment Promotion Advisor
Under process; TOR sent to DHI for Approval
Expected Advertisement Date: Q2, 2023
CS-05
Sustainable Township Management
Capacity Development
Expected Advertisement date: Q3, 2023
CS-06
Investor promotion and transaction
advisory services
Expected Advertisement date: Q4, 2023
27. 3) PROMENADE WORKS
4) LANDSCAPE AND
IRRIGATION WORKS
1) RIVER Training WORKS
(4.5km)
2) Backfilling
Works
5) Outfall Integration (13 Nos)
Project Scope & Status: CW-01
28. CW-01 – (Schematic Alignment)
31/10/2022
100% work completed in November 2022
29. Diaphragm Wall
RiverBed Level
Lower Walkway
Upper Walkway
Slope Embankment
Boulders
8.7m
3.4m
2.5m
Diaphragm Wall with Dead Man Anchor and Sloped Embankment
Embankment Concept
Type 1
30. KEYPLAN
Embankment Concept
Type -2
Diaphragm Wall with Anchor Slab and vertical wall Embankment
Diaphragm Wall
Proposed River Bed Level
Lower Walkway
Upper Walkway
RCC Wall
Boulders
42. CW-02A Scope of Works
Road Works
Stormwater Network
Sewage Collection & Conveyance and Sewage Treatment Plant
Water Treatment Plant and Water Distribution Network
Electrical Power Supply Works
Telecommunication Works
Embankment and Street Lighting Works
Solid Waste Treatment Yard
43. Coordination with BPC
Originally, all power supply works were supposed to be carried out by BPC
DHI decided to separate power supply works into:
Within PTDP- to be carried out by PTDP Contractor
Outside PTDP- to be carried out by BPC
First meeting with BPC conducted in June 2020
BPC revised the power supply arrangement within PTDP
44. Electrical Scope of Works
A. Primary Line
3Cx300 SQ.MM XLPE Cable
Runs through Trench
B. Secondary Line (Internal Network Connection)
4Cx630 SQ.MM PVC Cable
Runs through the 300MM DWC Pipe
5 nos of 2.5 MVA USS each
25 nos of Feeder Pillar
C. Promenade Light
365 nos of light pole (45W)
9 nos of sub-feeder pillar
4Cx10 SQ.MM armoured Aluminum Cable
D. Street Light Pole
159 nos of light pole (120W)
4Cx16 SQ.MM armoured Aluminum Cable
45. Discussions
i. USS
Number of ways of RMU in the USS is not specified neither in BoQ nor TS
As per TS 1.3, installed altitude of RMU is 2500m & 3500m above sea level.
Phuentsholing’s maximum altitude is 300m. Is it necessary to follow TS?
Request foundation drawing for USS, as adopted by BPC
ii. Earthing for USS & Feeder Pillar
Resistance of the soil in the project is in between 1400-1500 ohms
Project request BPC for way forward
iii. Cable from USS to Feeder Pillar
As per BoQ is 4Cx630 sq.mm armoured aluminum cable
390A- cable carrying capacity
6- way, 600A feeder pillar
2 or 1 incoming cable to feeder pillar? If 2 then is it advisable to connect two
cable in one outgoing MCCB of 630A at LT side of USS?
46. Discussions continued…
iv. Trench Connection to USS?
v. LV Switchboard (LT side of USS)
MCCBs
• 630A TP MCCB (50KA)- 4 nos
• 300A TP MCCB (50KA)- 4 nos
vi. Final review of USS & Feeder Pillar location by BPC
vii. Review of TS & drawing of Feeder Pillar by BPC
viii.Status of connection from BPC substation