SlideShare a Scribd company logo
Phuentsholing Township Development Project (PTDP)
March XX, 2023
Venue: XXXXX
Contents
1. BACKGROUND
2. PROJECT RATIONALE (Vision, Mission & Objectives)
3. PROJECT ORGANIZATION STRUCTURE
4. PROCUREMENT PLAN & PROJECT STATUS (CW-01 & CW-02A)
5. POWER SUPPLY
Background: Chronology of Events
Timeline Activity
2003 Initially conceived as “Toorsa River Training & Flood Mitigation Project’
2005 Under a DANIDA financial assistance, the prefeasibility study was carried out by Phuentsholing Thromde
2006 -2007 Detailed feasibility study (Toorsa flood mitigation) was carried out by Danish Hydraulic Institute (DHI), India
May 3, 2010 Project handed over to DHI by MoWHS. DHI then entrusted the work to its subsidiary DHI -INFRA Ltd
Dec 2010 Engaged ILFS, India (Consultant) as so to carry out the Project feasibility studies but was prematurely
terminated in July 2011 for completion of the DPR of Amochhu Hydro Electric Project (AHEP)
Aug 2013 The DPR for AHEP was made available, a revision of the hydrological and hydraulic studies engaging DHI-India,
with AHEP scenario upstream
2014 Around 70 acre of private land which was inside the project area was successfully relocated to the LAP with the
help of Phuentsholing Thromde
Nov 2015 After the international competitive bidding process HCP Design Planning & Management Pvt. Ltd was awarded
the consultancy services for the preparation of Integrated Detailed Project Report (IDPR)
2016 • Asian Development Bank (ADB) indicated their interest to fund the project
• Merger of DHI INFRA and CDCL, Mandate transferred to CDCL (October 2016)
Sept 2017 Completion of IDPR (Integrated Detailed Project Report)
June 5, 2018 Project approved by ADB for financing
July 3, 2018 Project Loan and Grant Agreements with MoF and ADB (AF signed on September 29, 2020)
July 18, 2018 Contract Signed for Package CW-01 & Project implementation Consultant (PIC)
Nov 2018 Implementation of Package-I, (CW-01)
i. Conceived as early as 2003
ii. Substantive preparatory works towards implementation started with the issuance of
the Executive Order from the Royal Government of Bhutan on March 02, 2015
iii. Expected Project Impact:
 The main purpose of the project is to mitigate the growing risks of flood to the area and to the
existing Phuentsholing City.
 While protecting Phuentsholing city from flood threats, around 157 Acre of Land will be retained
(Zone-A), where urban development is proposed.
 will ease the demand for space in the commercial hub (80% of country’s trade)
 will improve the quality of life for the Phuntsholing residents as a whole
 Making habitable about 70 acres of land besides the Project area at LAP, and substantial reduction in
costs of the Phuntsholing-Chamkuna Highway by avoiding protection works.
Background
Contents
1. BACKGROUND
2. PROJECT RATIONALE (Vision, Mission & Objectives) & Scope
3. PROJECT FINANCING (ADB & DHI)
4. PROJECT ORGANIZATION STRUCTURE
5. PROCUREMENT PLAN & PROJECT STATUS (CW-01 & CW-02A)
6. ISSUES & CHALLENGES (project implementation)
7. MASTERPLAN & DEVELOPMENT CONTROL REGULATIONS
8. WAY FORWARD:
a. Sustainable Township Management
b. Integration with Existing Township
c. Investment Advisory
Rationale – Why this Project?
Mapped Fair Weather Flow after Each Subsequent Flood Over Past 10 Years
Flood Risk along the left bank every year
Flood Condition - 2016
Flood Condition - 2016
Flood Condition - 2016
Flood Condition - 2016
Flood Condition - 2016
Project Planning & Scope : Site Zoning
PTDP Project Land in acres
Zone A 162.88
Zone B 233.09
Zone C 684.12
Zone E 66.61
Total Developable Land (Acre) 1,146.70
Zone A
Zone B
Zone C
Zone D
Zone E
Project Planning & Scope
Boundary of PTDP Project Area – Initial IDPR is prepared inclusive of four Zones (A, B, C & E)
Kaileshwar Hill
Samtse Pling Highway
Phuentsholing
Totapara
Jaigaon
The Project site boundary was fixed based on
the following parameters:
• Northern end is defined by the under
construction Doyagang bridge connecting
Phuentsholing - Samtse Highway.
• North West corner near Toorsa Taar is
demarcated by outer plot boundaries to
exclude private plots.
• Western boundary is defined by base
contour line of Kaileshwar Hill.
• Eastern boundary is bordered by the
existing STP and proposed Phuentsholing
- Samtse Highway.
• Southern end is fixed by the Indo-
Bhutan International border.
Total Project Area – 2076 Acres
Funding Agency: Asian Development Bank
&
Druk Holding & Investments (DHI)
Executing Agency: Druk Holding & Investments (DHI)
Implementing Agency : Construction Development Corporation Ltd.
(CDCL)
DHI decided to develop PTDP in a Phased manner, with Zone-A as the start.
Project Planning & Scope:
For Zone-A:
Concept - Sabarmati Riverfront, Gujrat
Before After
© CDCL 2017, All Rights Reserved
PTDP: 2014
© CDCL 2017, All Rights Reserved
(2017)
PTDP
(2021)
Future
Visualizations of PTDP
OVERALL
ZONE A
Zone A
Project Output:
# Project Outputs Status
Output 1
Flood and Erosion protection measures installed:
a) construct around 4 kilometers (km) of erosion-resilient river walls to protect
against 100-year probable flood
b) raise ground levels behind the new walls to reclaim at least 66 ha of flood-
protected land for urban development
c) establish and operationalize a flood early warning system and flood
management plan
a) Completed
b) Completed
C) FEWS: under process
by NCHM
(FMC – PIC scope)
Output 2
Municipal infrastructure constructed
a) about 10 km of roads with footpaths, landscaping, and streetlights made
b) modern drinking water supply and distribution systems, and wastewater collection and
treatment systems that service the new township and adjoining areas
c) resource recovery system for managing solid waste in both the new and old townships
established
d) power distribution and telecommunication systems throughout the new township
CW-02A – Contract
Awarded on 4th Nov.
2022
BPC and BT to provide
source connection at the
boundary -Force Account
Output 3
Township management systems installed:
a) establish asset management systems
b) build the capacity of township staff to ensure sustainable and effective urban management
c) initiate investor promotion activities
CS-03: Urban
management Advisor
recruited.
CS-04: Investment
promotion Advisor under
process to recruit
Contents
1. BACKGROUND
2. PROJECT RATIONALE (Vision, Mission & Objectives) & Scope
3. PROJECT ORGANIZATION STRUCTURE
4. PROCUREMENT PLAN & PROJECT STATUS (CW-01 & CW-02A)
5. ISSUES & CHALLENGES (project implementation)
6. MASTERPLAN & DEVELOPMENT CONTROL REGULATIONS
7. WAY FORWARD:
a. Sustainable Township Management
b. Integration with Existing Township
c. Investment Advisory
Project Organization Structure
Contents
1. BACKGROUND
2. PROJECT RATIONALE (Vision, Mission & Objectives)
3. PROJECT FINANCING (ADB & DHI)
4. PROJECT ORGANIZATION STRUCTURE
5. PROCUREMENT PLAN & PROJECT STATUS (CW-01 & CW-02A)
6. ISSUES & CHALLENGES (project implementation)
7. MASTERPLAN & DEVELOPMENT CONTROL REGULATIONS
8. WAY FORWARD:
a. Sustainable Township Management
b. Integration with Existing Township
c. Investment Advisory
Procurement Plan: Works & Goods Packages
Package No Work Package Status
CW-01
River training and land
reclamation
Contractor: M/s AFCONS Infrastructure Ltd.
Project Cost: Nu. 2.935 billion; Duration: 30 months
Project Period: November 2018 – November 2022
CW-02A
Common Urban
Infrastructure
Contractor: Kalika-Rigsar JV
Contract signed on November 4, 2022.
Initial Contract Amount: Nu. 1.748 billion; Duration: 30 months
Project Period: November 2022 – May 2025
CW-02B Landscaping & Greenery works To be awarded in Q1, 2024 (Bid document finalization in 2023)
CW-03
Flood early warning system
(FEWS)
MOU Signed with NCHM on May 2021
Expected Completion – Q2, 2024
Flood Management Plan (FMP) will be prepared by PIC
CW-04
Power transmission
Infrastructure till PTDP boundary
Forced Account – under BPC plan
CW-05 ICT infrastructure outside PTDP
Forced Account – under BT plan
CW-06 Horticulture Re-named as CW-02B (above)
PG-01 Procurement of Goods To be awarded in Q1, 2024 (Document finalization in 2023)
Procurement Plan: Consultancy Services
Package No Work Package Status
CS-01
Project implementation Consultant
(PIC)
Contract signed on July 18, 2018.
Input Duration – 79 Months (June 2025)
CS-02
Independent Environment
Monitoring Expert (IEME)
Contract Signed on April 4, 2019
Intermittent inputs until project completion
CS-03 Urban management Advisor
Contract Signed on April 14, 2022
Input Period : 3 months (Intermittent until Q2 2024)
CS-04 Investment Promotion Advisor
Under process; TOR sent to DHI for Approval
Expected Advertisement Date: Q2, 2023
CS-05
Sustainable Township Management
Capacity Development
Expected Advertisement date: Q3, 2023
CS-06
Investor promotion and transaction
advisory services
Expected Advertisement date: Q4, 2023
3) PROMENADE WORKS
4) LANDSCAPE AND
IRRIGATION WORKS
1) RIVER Training WORKS
(4.5km)
2) Backfilling
Works
5) Outfall Integration (13 Nos)
Project Scope & Status: CW-01
CW-01 – (Schematic Alignment)
31/10/2022
100% work completed in November 2022
Diaphragm Wall
RiverBed Level
Lower Walkway
Upper Walkway
Slope Embankment
Boulders
8.7m
3.4m
2.5m
Diaphragm Wall with Dead Man Anchor and Sloped Embankment
Embankment Concept
Type 1
KEYPLAN
Embankment Concept
Type -2
Diaphragm Wall with Anchor Slab and vertical wall Embankment
Diaphragm Wall
Proposed River Bed Level
Lower Walkway
Upper Walkway
RCC Wall
Boulders
CW-01 : Pictorial Views (completed works)
AMPITHEATRE
Completed Section at Part 2 & 3
Paver Block Walkway at Part 1
ACCESS AT OUTFALL 3
ACCESS TYPE 3B
International Border
Open Outfall 3 – Downstream View from PCR Bridge
Open Outfall 4 – Downstream View from PCR Bridge
Overall PTDPArea
© CDCL 2017, All Rights Reserved 45
June 2020
May 2021
CW-02A Scope of Works
Road Works
Stormwater Network
Sewage Collection & Conveyance and Sewage Treatment Plant
Water Treatment Plant and Water Distribution Network
Electrical Power Supply Works
Telecommunication Works
Embankment and Street Lighting Works
Solid Waste Treatment Yard
Coordination with BPC
Originally, all power supply works were supposed to be carried out by BPC
DHI decided to separate power supply works into:
 Within PTDP- to be carried out by PTDP Contractor
 Outside PTDP- to be carried out by BPC
First meeting with BPC conducted in June 2020
BPC revised the power supply arrangement within PTDP
Electrical Scope of Works
A. Primary Line
 3Cx300 SQ.MM XLPE Cable
 Runs through Trench
B. Secondary Line (Internal Network Connection)
 4Cx630 SQ.MM PVC Cable
 Runs through the 300MM DWC Pipe
 5 nos of 2.5 MVA USS each
 25 nos of Feeder Pillar
C. Promenade Light
 365 nos of light pole (45W)
 9 nos of sub-feeder pillar
 4Cx10 SQ.MM armoured Aluminum Cable
D. Street Light Pole
 159 nos of light pole (120W)
 4Cx16 SQ.MM armoured Aluminum Cable
Discussions
i. USS
 Number of ways of RMU in the USS is not specified neither in BoQ nor TS
 As per TS 1.3, installed altitude of RMU is 2500m & 3500m above sea level.
Phuentsholing’s maximum altitude is 300m. Is it necessary to follow TS?
 Request foundation drawing for USS, as adopted by BPC
ii. Earthing for USS & Feeder Pillar
 Resistance of the soil in the project is in between 1400-1500 ohms
 Project request BPC for way forward
iii. Cable from USS to Feeder Pillar
 As per BoQ is 4Cx630 sq.mm armoured aluminum cable
 390A- cable carrying capacity
 6- way, 600A feeder pillar
 2 or 1 incoming cable to feeder pillar? If 2 then is it advisable to connect two
cable in one outgoing MCCB of 630A at LT side of USS?
Discussions continued…
iv. Trench Connection to USS?
v. LV Switchboard (LT side of USS)
 MCCBs
• 630A TP MCCB (50KA)- 4 nos
• 300A TP MCCB (50KA)- 4 nos
vi. Final review of USS & Feeder Pillar location by BPC
vii. Review of TS & drawing of Feeder Pillar by BPC
viii.Status of connection from BPC substation
Thank You

More Related Content

Similar to PPT to BPC.pptx

TC Presentation_M&E Team_May25.pptx
TC Presentation_M&E Team_May25.pptxTC Presentation_M&E Team_May25.pptx
TC Presentation_M&E Team_May25.pptx
Morshed Denar Alam Manna
 
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxFinal Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
hurain5
 
SAR Readiness - v10 - 4-06-2023.pptx
SAR Readiness - v10 - 4-06-2023.pptxSAR Readiness - v10 - 4-06-2023.pptx
SAR Readiness - v10 - 4-06-2023.pptx
RakanAlAnazi10
 
Vijay banga
Vijay banga Vijay banga
Vijay banga
VIJAY BANGA
 
RDP Chapter 19
RDP Chapter 19RDP Chapter 19
Vijay banga
Vijay banga Vijay banga
Vijay banga
VIJAY BANGA
 
Odisha sw wb mission-may14
Odisha sw wb mission-may14Odisha sw wb mission-may14
Odisha sw wb mission-may14
hydrologywebsite1
 
Norhtern Power Distribution Project
Norhtern Power Distribution ProjectNorhtern Power Distribution Project
Norhtern Power Distribution Project
Damrong Charles Phomdouangsy(Laos)
 
ToR
ToRToR
supreme court additonal complex project
supreme court additonal complex projectsupreme court additonal complex project
supreme court additonal complex project
Abhishek singh
 
Puducherry
Puducherry Puducherry
Puducherry
hydrologyproject0
 
CV_Hazwan Updated
CV_Hazwan UpdatedCV_Hazwan Updated
CV_Hazwan Updated
Ahmad Hazwan
 
Present status of apartment building approval and construction
Present status of apartment building approval and constructionPresent status of apartment building approval and construction
Present status of apartment building approval and construction
Binay Shrestha
 
CV- Project Control Manager PMP
CV- Project Control Manager PMPCV- Project Control Manager PMP
CV- Project Control Manager PMP
Faheem Ijaz Janjua, PMP
 
Bandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,IndiaBandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,India
oyepuneeta
 
Our Future Valley - Developer Session January 28, 2021
Our Future Valley - Developer Session January 28, 2021Our Future Valley - Developer Session January 28, 2021
Our Future Valley - Developer Session January 28, 2021
Allison Zinnick
 
Tony Brun Geographical Association Of Western Australia Conference Presen...
Tony Brun   Geographical Association Of Western Australia   Conference Presen...Tony Brun   Geographical Association Of Western Australia   Conference Presen...
Tony Brun Geographical Association Of Western Australia Conference Presen...
Curtin University Sustainability Policy (CUSP) Institute
 
Note sheet
Note sheetNote sheet
Note sheet
hosting guests
 
Monthly progress report , Resettlement ,Rehabilitation , Livelihood and Rest...
Monthly progress report , Resettlement  ,Rehabilitation , Livelihood and Rest...Monthly progress report , Resettlement  ,Rehabilitation , Livelihood and Rest...
Monthly progress report , Resettlement ,Rehabilitation , Livelihood and Rest...
Bangladesh Economic Zones Authority under prime minister's office funded by world bank
 
2017 Updated CV - Essam Harby
2017 Updated  CV - Essam Harby2017 Updated  CV - Essam Harby
2017 Updated CV - Essam Harby
Essam Harby
 

Similar to PPT to BPC.pptx (20)

TC Presentation_M&E Team_May25.pptx
TC Presentation_M&E Team_May25.pptxTC Presentation_M&E Team_May25.pptx
TC Presentation_M&E Team_May25.pptx
 
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxFinal Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
 
SAR Readiness - v10 - 4-06-2023.pptx
SAR Readiness - v10 - 4-06-2023.pptxSAR Readiness - v10 - 4-06-2023.pptx
SAR Readiness - v10 - 4-06-2023.pptx
 
Vijay banga
Vijay banga Vijay banga
Vijay banga
 
RDP Chapter 19
RDP Chapter 19RDP Chapter 19
RDP Chapter 19
 
Vijay banga
Vijay banga Vijay banga
Vijay banga
 
Odisha sw wb mission-may14
Odisha sw wb mission-may14Odisha sw wb mission-may14
Odisha sw wb mission-may14
 
Norhtern Power Distribution Project
Norhtern Power Distribution ProjectNorhtern Power Distribution Project
Norhtern Power Distribution Project
 
ToR
ToRToR
ToR
 
supreme court additonal complex project
supreme court additonal complex projectsupreme court additonal complex project
supreme court additonal complex project
 
Puducherry
Puducherry Puducherry
Puducherry
 
CV_Hazwan Updated
CV_Hazwan UpdatedCV_Hazwan Updated
CV_Hazwan Updated
 
Present status of apartment building approval and construction
Present status of apartment building approval and constructionPresent status of apartment building approval and construction
Present status of apartment building approval and construction
 
CV- Project Control Manager PMP
CV- Project Control Manager PMPCV- Project Control Manager PMP
CV- Project Control Manager PMP
 
Bandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,IndiaBandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,India
 
Our Future Valley - Developer Session January 28, 2021
Our Future Valley - Developer Session January 28, 2021Our Future Valley - Developer Session January 28, 2021
Our Future Valley - Developer Session January 28, 2021
 
Tony Brun Geographical Association Of Western Australia Conference Presen...
Tony Brun   Geographical Association Of Western Australia   Conference Presen...Tony Brun   Geographical Association Of Western Australia   Conference Presen...
Tony Brun Geographical Association Of Western Australia Conference Presen...
 
Note sheet
Note sheetNote sheet
Note sheet
 
Monthly progress report , Resettlement ,Rehabilitation , Livelihood and Rest...
Monthly progress report , Resettlement  ,Rehabilitation , Livelihood and Rest...Monthly progress report , Resettlement  ,Rehabilitation , Livelihood and Rest...
Monthly progress report , Resettlement ,Rehabilitation , Livelihood and Rest...
 
2017 Updated CV - Essam Harby
2017 Updated  CV - Essam Harby2017 Updated  CV - Essam Harby
2017 Updated CV - Essam Harby
 

Recently uploaded

一比一原版加拿大多伦多大学毕业证(uoft毕业证书)如何办理
一比一原版加拿大多伦多大学毕业证(uoft毕业证书)如何办理一比一原版加拿大多伦多大学毕业证(uoft毕业证书)如何办理
一比一原版加拿大多伦多大学毕业证(uoft毕业证书)如何办理
taqyea
 
FinalLessonPlanResponding.docxnknknknknknk
FinalLessonPlanResponding.docxnknknknknknkFinalLessonPlanResponding.docxnknknknknknk
FinalLessonPlanResponding.docxnknknknknknk
abbieharman
 
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka ! Fix Satta Matka ! Matka Result ! Matka Guessing ! ...
❼❷⓿❺❻❷❽❷❼❽  Dpboss Matka ! Fix Satta Matka ! Matka Result ! Matka Guessing ! ...❼❷⓿❺❻❷❽❷❼❽  Dpboss Matka ! Fix Satta Matka ! Matka Result ! Matka Guessing ! ...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka ! Fix Satta Matka ! Matka Result ! Matka Guessing ! ...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart
 
❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart
❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart
❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart
❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart
 
This is a test powerpoint!!!!!!!!!!!!!!!
This is a test powerpoint!!!!!!!!!!!!!!!This is a test powerpoint!!!!!!!!!!!!!!!
This is a test powerpoint!!!!!!!!!!!!!!!
briannedpegg
 
Heart Touching Romantic Love Shayari In English with Images
Heart Touching Romantic Love Shayari In English with ImagesHeart Touching Romantic Love Shayari In English with Images
Heart Touching Romantic Love Shayari In English with Images
Short Good Quotes
 
➒➌➎➏➑➐➋➑➐➐ Dpboss Matka Guessing Satta Matka Kalyan panel Chart Indian Matka ...
➒➌➎➏➑➐➋➑➐➐ Dpboss Matka Guessing Satta Matka Kalyan panel Chart Indian Matka ...➒➌➎➏➑➐➋➑➐➐ Dpboss Matka Guessing Satta Matka Kalyan panel Chart Indian Matka ...
➒➌➎➏➑➐➋➑➐➐ Dpboss Matka Guessing Satta Matka Kalyan panel Chart Indian Matka ...
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Cherries 32 collection of colorful paintings
Cherries 32 collection of colorful paintingsCherries 32 collection of colorful paintings
Cherries 32 collection of colorful paintings
sandamichaela *
 
➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
一比一原版美国加州大学圣地亚哥分校毕业证(ucsd毕业证书)如何办理
一比一原版美国加州大学圣地亚哥分校毕业证(ucsd毕业证书)如何办理一比一原版美国加州大学圣地亚哥分校毕业证(ucsd毕业证书)如何办理
一比一原版美国加州大学圣地亚哥分校毕业证(ucsd毕业证书)如何办理
taqyea
 
My storyboard for a sword fight scene with lightsabers
My storyboard for a sword fight scene with lightsabersMy storyboard for a sword fight scene with lightsabers
My storyboard for a sword fight scene with lightsabers
AlejandroGuarnGutirr
 
Colour Theory for Painting - Fine Artist.pdf
Colour Theory for Painting - Fine Artist.pdfColour Theory for Painting - Fine Artist.pdf
Colour Theory for Painting - Fine Artist.pdf
Ketan Naik
 
➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
2024 MATFORCE Youth Poster Contest Winners
2024 MATFORCE Youth Poster Contest Winners2024 MATFORCE Youth Poster Contest Winners
2024 MATFORCE Youth Poster Contest Winners
matforce
 
Full CAD Project Cardiovascuwhore Debut PDF CAD Meena Pittman
Full CAD Project Cardiovascuwhore Debut PDF CAD Meena PittmanFull CAD Project Cardiovascuwhore Debut PDF CAD Meena Pittman
Full CAD Project Cardiovascuwhore Debut PDF CAD Meena Pittman
meenap32
 
哪里购买美国乔治城大学毕业证硕士学位证书原版一模一样
哪里购买美国乔治城大学毕业证硕士学位证书原版一模一样哪里购买美国乔治城大学毕业证硕士学位证书原版一模一样
哪里购买美国乔治城大学毕业证硕士学位证书原版一模一样
tc73868
 
一比一原版美国亚利桑那大学毕业证(ua毕业证书)如何办理
一比一原版美国亚利桑那大学毕业证(ua毕业证书)如何办理一比一原版美国亚利桑那大学毕业证(ua毕业证书)如何办理
一比一原版美国亚利桑那大学毕业证(ua毕业证书)如何办理
homgo
 
原版制作(UNITO毕业证书)都灵大学毕业证Offer一模一样
原版制作(UNITO毕业证书)都灵大学毕业证Offer一模一样原版制作(UNITO毕业证书)都灵大学毕业证Offer一模一样
原版制作(UNITO毕业证书)都灵大学毕业证Offer一模一样
dxtmnb3y
 
Domino Express Storyboard - TV Adv Toys 30"
Domino Express Storyboard - TV Adv Toys 30"Domino Express Storyboard - TV Adv Toys 30"
Domino Express Storyboard - TV Adv Toys 30"
Alessandro Occhipinti
 
Jennifer Murillo's Storyboard: Bardic Sandbag
Jennifer Murillo's Storyboard: Bardic SandbagJennifer Murillo's Storyboard: Bardic Sandbag
Jennifer Murillo's Storyboard: Bardic Sandbag
mariajennifermurillo
 

Recently uploaded (20)

一比一原版加拿大多伦多大学毕业证(uoft毕业证书)如何办理
一比一原版加拿大多伦多大学毕业证(uoft毕业证书)如何办理一比一原版加拿大多伦多大学毕业证(uoft毕业证书)如何办理
一比一原版加拿大多伦多大学毕业证(uoft毕业证书)如何办理
 
FinalLessonPlanResponding.docxnknknknknknk
FinalLessonPlanResponding.docxnknknknknknkFinalLessonPlanResponding.docxnknknknknknk
FinalLessonPlanResponding.docxnknknknknknk
 
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka ! Fix Satta Matka ! Matka Result ! Matka Guessing ! ...
❼❷⓿❺❻❷❽❷❼❽  Dpboss Matka ! Fix Satta Matka ! Matka Result ! Matka Guessing ! ...❼❷⓿❺❻❷❽❷❼❽  Dpboss Matka ! Fix Satta Matka ! Matka Result ! Matka Guessing ! ...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka ! Fix Satta Matka ! Matka Result ! Matka Guessing ! ...
 
❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart
❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart
❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart
 
This is a test powerpoint!!!!!!!!!!!!!!!
This is a test powerpoint!!!!!!!!!!!!!!!This is a test powerpoint!!!!!!!!!!!!!!!
This is a test powerpoint!!!!!!!!!!!!!!!
 
Heart Touching Romantic Love Shayari In English with Images
Heart Touching Romantic Love Shayari In English with ImagesHeart Touching Romantic Love Shayari In English with Images
Heart Touching Romantic Love Shayari In English with Images
 
➒➌➎➏➑➐➋➑➐➐ Dpboss Matka Guessing Satta Matka Kalyan panel Chart Indian Matka ...
➒➌➎➏➑➐➋➑➐➐ Dpboss Matka Guessing Satta Matka Kalyan panel Chart Indian Matka ...➒➌➎➏➑➐➋➑➐➐ Dpboss Matka Guessing Satta Matka Kalyan panel Chart Indian Matka ...
➒➌➎➏➑➐➋➑➐➐ Dpboss Matka Guessing Satta Matka Kalyan panel Chart Indian Matka ...
 
Cherries 32 collection of colorful paintings
Cherries 32 collection of colorful paintingsCherries 32 collection of colorful paintings
Cherries 32 collection of colorful paintings
 
➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka
 
一比一原版美国加州大学圣地亚哥分校毕业证(ucsd毕业证书)如何办理
一比一原版美国加州大学圣地亚哥分校毕业证(ucsd毕业证书)如何办理一比一原版美国加州大学圣地亚哥分校毕业证(ucsd毕业证书)如何办理
一比一原版美国加州大学圣地亚哥分校毕业证(ucsd毕业证书)如何办理
 
My storyboard for a sword fight scene with lightsabers
My storyboard for a sword fight scene with lightsabersMy storyboard for a sword fight scene with lightsabers
My storyboard for a sword fight scene with lightsabers
 
Colour Theory for Painting - Fine Artist.pdf
Colour Theory for Painting - Fine Artist.pdfColour Theory for Painting - Fine Artist.pdf
Colour Theory for Painting - Fine Artist.pdf
 
➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Kalyan Matka Satta Matka Dpboss Matka Guessing Indian Matka
 
2024 MATFORCE Youth Poster Contest Winners
2024 MATFORCE Youth Poster Contest Winners2024 MATFORCE Youth Poster Contest Winners
2024 MATFORCE Youth Poster Contest Winners
 
Full CAD Project Cardiovascuwhore Debut PDF CAD Meena Pittman
Full CAD Project Cardiovascuwhore Debut PDF CAD Meena PittmanFull CAD Project Cardiovascuwhore Debut PDF CAD Meena Pittman
Full CAD Project Cardiovascuwhore Debut PDF CAD Meena Pittman
 
哪里购买美国乔治城大学毕业证硕士学位证书原版一模一样
哪里购买美国乔治城大学毕业证硕士学位证书原版一模一样哪里购买美国乔治城大学毕业证硕士学位证书原版一模一样
哪里购买美国乔治城大学毕业证硕士学位证书原版一模一样
 
一比一原版美国亚利桑那大学毕业证(ua毕业证书)如何办理
一比一原版美国亚利桑那大学毕业证(ua毕业证书)如何办理一比一原版美国亚利桑那大学毕业证(ua毕业证书)如何办理
一比一原版美国亚利桑那大学毕业证(ua毕业证书)如何办理
 
原版制作(UNITO毕业证书)都灵大学毕业证Offer一模一样
原版制作(UNITO毕业证书)都灵大学毕业证Offer一模一样原版制作(UNITO毕业证书)都灵大学毕业证Offer一模一样
原版制作(UNITO毕业证书)都灵大学毕业证Offer一模一样
 
Domino Express Storyboard - TV Adv Toys 30"
Domino Express Storyboard - TV Adv Toys 30"Domino Express Storyboard - TV Adv Toys 30"
Domino Express Storyboard - TV Adv Toys 30"
 
Jennifer Murillo's Storyboard: Bardic Sandbag
Jennifer Murillo's Storyboard: Bardic SandbagJennifer Murillo's Storyboard: Bardic Sandbag
Jennifer Murillo's Storyboard: Bardic Sandbag
 

PPT to BPC.pptx

  • 1. Phuentsholing Township Development Project (PTDP) March XX, 2023 Venue: XXXXX
  • 2. Contents 1. BACKGROUND 2. PROJECT RATIONALE (Vision, Mission & Objectives) 3. PROJECT ORGANIZATION STRUCTURE 4. PROCUREMENT PLAN & PROJECT STATUS (CW-01 & CW-02A) 5. POWER SUPPLY
  • 3. Background: Chronology of Events Timeline Activity 2003 Initially conceived as “Toorsa River Training & Flood Mitigation Project’ 2005 Under a DANIDA financial assistance, the prefeasibility study was carried out by Phuentsholing Thromde 2006 -2007 Detailed feasibility study (Toorsa flood mitigation) was carried out by Danish Hydraulic Institute (DHI), India May 3, 2010 Project handed over to DHI by MoWHS. DHI then entrusted the work to its subsidiary DHI -INFRA Ltd Dec 2010 Engaged ILFS, India (Consultant) as so to carry out the Project feasibility studies but was prematurely terminated in July 2011 for completion of the DPR of Amochhu Hydro Electric Project (AHEP) Aug 2013 The DPR for AHEP was made available, a revision of the hydrological and hydraulic studies engaging DHI-India, with AHEP scenario upstream 2014 Around 70 acre of private land which was inside the project area was successfully relocated to the LAP with the help of Phuentsholing Thromde Nov 2015 After the international competitive bidding process HCP Design Planning & Management Pvt. Ltd was awarded the consultancy services for the preparation of Integrated Detailed Project Report (IDPR) 2016 • Asian Development Bank (ADB) indicated their interest to fund the project • Merger of DHI INFRA and CDCL, Mandate transferred to CDCL (October 2016) Sept 2017 Completion of IDPR (Integrated Detailed Project Report) June 5, 2018 Project approved by ADB for financing July 3, 2018 Project Loan and Grant Agreements with MoF and ADB (AF signed on September 29, 2020) July 18, 2018 Contract Signed for Package CW-01 & Project implementation Consultant (PIC) Nov 2018 Implementation of Package-I, (CW-01)
  • 4. i. Conceived as early as 2003 ii. Substantive preparatory works towards implementation started with the issuance of the Executive Order from the Royal Government of Bhutan on March 02, 2015 iii. Expected Project Impact:  The main purpose of the project is to mitigate the growing risks of flood to the area and to the existing Phuentsholing City.  While protecting Phuentsholing city from flood threats, around 157 Acre of Land will be retained (Zone-A), where urban development is proposed.  will ease the demand for space in the commercial hub (80% of country’s trade)  will improve the quality of life for the Phuntsholing residents as a whole  Making habitable about 70 acres of land besides the Project area at LAP, and substantial reduction in costs of the Phuntsholing-Chamkuna Highway by avoiding protection works. Background
  • 5. Contents 1. BACKGROUND 2. PROJECT RATIONALE (Vision, Mission & Objectives) & Scope 3. PROJECT FINANCING (ADB & DHI) 4. PROJECT ORGANIZATION STRUCTURE 5. PROCUREMENT PLAN & PROJECT STATUS (CW-01 & CW-02A) 6. ISSUES & CHALLENGES (project implementation) 7. MASTERPLAN & DEVELOPMENT CONTROL REGULATIONS 8. WAY FORWARD: a. Sustainable Township Management b. Integration with Existing Township c. Investment Advisory
  • 6. Rationale – Why this Project? Mapped Fair Weather Flow after Each Subsequent Flood Over Past 10 Years Flood Risk along the left bank every year
  • 12. Project Planning & Scope : Site Zoning PTDP Project Land in acres Zone A 162.88 Zone B 233.09 Zone C 684.12 Zone E 66.61 Total Developable Land (Acre) 1,146.70 Zone A Zone B Zone C Zone D Zone E
  • 13. Project Planning & Scope Boundary of PTDP Project Area – Initial IDPR is prepared inclusive of four Zones (A, B, C & E) Kaileshwar Hill Samtse Pling Highway Phuentsholing Totapara Jaigaon The Project site boundary was fixed based on the following parameters: • Northern end is defined by the under construction Doyagang bridge connecting Phuentsholing - Samtse Highway. • North West corner near Toorsa Taar is demarcated by outer plot boundaries to exclude private plots. • Western boundary is defined by base contour line of Kaileshwar Hill. • Eastern boundary is bordered by the existing STP and proposed Phuentsholing - Samtse Highway. • Southern end is fixed by the Indo- Bhutan International border. Total Project Area – 2076 Acres
  • 14. Funding Agency: Asian Development Bank & Druk Holding & Investments (DHI) Executing Agency: Druk Holding & Investments (DHI) Implementing Agency : Construction Development Corporation Ltd. (CDCL) DHI decided to develop PTDP in a Phased manner, with Zone-A as the start. Project Planning & Scope: For Zone-A:
  • 15. Concept - Sabarmati Riverfront, Gujrat Before After
  • 16. © CDCL 2017, All Rights Reserved PTDP: 2014
  • 17. © CDCL 2017, All Rights Reserved (2017) PTDP (2021) Future
  • 20.
  • 21. Project Output: # Project Outputs Status Output 1 Flood and Erosion protection measures installed: a) construct around 4 kilometers (km) of erosion-resilient river walls to protect against 100-year probable flood b) raise ground levels behind the new walls to reclaim at least 66 ha of flood- protected land for urban development c) establish and operationalize a flood early warning system and flood management plan a) Completed b) Completed C) FEWS: under process by NCHM (FMC – PIC scope) Output 2 Municipal infrastructure constructed a) about 10 km of roads with footpaths, landscaping, and streetlights made b) modern drinking water supply and distribution systems, and wastewater collection and treatment systems that service the new township and adjoining areas c) resource recovery system for managing solid waste in both the new and old townships established d) power distribution and telecommunication systems throughout the new township CW-02A – Contract Awarded on 4th Nov. 2022 BPC and BT to provide source connection at the boundary -Force Account Output 3 Township management systems installed: a) establish asset management systems b) build the capacity of township staff to ensure sustainable and effective urban management c) initiate investor promotion activities CS-03: Urban management Advisor recruited. CS-04: Investment promotion Advisor under process to recruit
  • 22. Contents 1. BACKGROUND 2. PROJECT RATIONALE (Vision, Mission & Objectives) & Scope 3. PROJECT ORGANIZATION STRUCTURE 4. PROCUREMENT PLAN & PROJECT STATUS (CW-01 & CW-02A) 5. ISSUES & CHALLENGES (project implementation) 6. MASTERPLAN & DEVELOPMENT CONTROL REGULATIONS 7. WAY FORWARD: a. Sustainable Township Management b. Integration with Existing Township c. Investment Advisory
  • 24. Contents 1. BACKGROUND 2. PROJECT RATIONALE (Vision, Mission & Objectives) 3. PROJECT FINANCING (ADB & DHI) 4. PROJECT ORGANIZATION STRUCTURE 5. PROCUREMENT PLAN & PROJECT STATUS (CW-01 & CW-02A) 6. ISSUES & CHALLENGES (project implementation) 7. MASTERPLAN & DEVELOPMENT CONTROL REGULATIONS 8. WAY FORWARD: a. Sustainable Township Management b. Integration with Existing Township c. Investment Advisory
  • 25. Procurement Plan: Works & Goods Packages Package No Work Package Status CW-01 River training and land reclamation Contractor: M/s AFCONS Infrastructure Ltd. Project Cost: Nu. 2.935 billion; Duration: 30 months Project Period: November 2018 – November 2022 CW-02A Common Urban Infrastructure Contractor: Kalika-Rigsar JV Contract signed on November 4, 2022. Initial Contract Amount: Nu. 1.748 billion; Duration: 30 months Project Period: November 2022 – May 2025 CW-02B Landscaping & Greenery works To be awarded in Q1, 2024 (Bid document finalization in 2023) CW-03 Flood early warning system (FEWS) MOU Signed with NCHM on May 2021 Expected Completion – Q2, 2024 Flood Management Plan (FMP) will be prepared by PIC CW-04 Power transmission Infrastructure till PTDP boundary Forced Account – under BPC plan CW-05 ICT infrastructure outside PTDP Forced Account – under BT plan CW-06 Horticulture Re-named as CW-02B (above) PG-01 Procurement of Goods To be awarded in Q1, 2024 (Document finalization in 2023)
  • 26. Procurement Plan: Consultancy Services Package No Work Package Status CS-01 Project implementation Consultant (PIC) Contract signed on July 18, 2018. Input Duration – 79 Months (June 2025) CS-02 Independent Environment Monitoring Expert (IEME) Contract Signed on April 4, 2019 Intermittent inputs until project completion CS-03 Urban management Advisor Contract Signed on April 14, 2022 Input Period : 3 months (Intermittent until Q2 2024) CS-04 Investment Promotion Advisor Under process; TOR sent to DHI for Approval Expected Advertisement Date: Q2, 2023 CS-05 Sustainable Township Management Capacity Development Expected Advertisement date: Q3, 2023 CS-06 Investor promotion and transaction advisory services Expected Advertisement date: Q4, 2023
  • 27. 3) PROMENADE WORKS 4) LANDSCAPE AND IRRIGATION WORKS 1) RIVER Training WORKS (4.5km) 2) Backfilling Works 5) Outfall Integration (13 Nos) Project Scope & Status: CW-01
  • 28. CW-01 – (Schematic Alignment) 31/10/2022 100% work completed in November 2022
  • 29. Diaphragm Wall RiverBed Level Lower Walkway Upper Walkway Slope Embankment Boulders 8.7m 3.4m 2.5m Diaphragm Wall with Dead Man Anchor and Sloped Embankment Embankment Concept Type 1
  • 30. KEYPLAN Embankment Concept Type -2 Diaphragm Wall with Anchor Slab and vertical wall Embankment Diaphragm Wall Proposed River Bed Level Lower Walkway Upper Walkway RCC Wall Boulders
  • 31. CW-01 : Pictorial Views (completed works)
  • 33. Completed Section at Part 2 & 3
  • 34. Paver Block Walkway at Part 1
  • 38. Open Outfall 3 – Downstream View from PCR Bridge
  • 39. Open Outfall 4 – Downstream View from PCR Bridge
  • 41. © CDCL 2017, All Rights Reserved 45 June 2020 May 2021
  • 42. CW-02A Scope of Works Road Works Stormwater Network Sewage Collection & Conveyance and Sewage Treatment Plant Water Treatment Plant and Water Distribution Network Electrical Power Supply Works Telecommunication Works Embankment and Street Lighting Works Solid Waste Treatment Yard
  • 43. Coordination with BPC Originally, all power supply works were supposed to be carried out by BPC DHI decided to separate power supply works into:  Within PTDP- to be carried out by PTDP Contractor  Outside PTDP- to be carried out by BPC First meeting with BPC conducted in June 2020 BPC revised the power supply arrangement within PTDP
  • 44. Electrical Scope of Works A. Primary Line  3Cx300 SQ.MM XLPE Cable  Runs through Trench B. Secondary Line (Internal Network Connection)  4Cx630 SQ.MM PVC Cable  Runs through the 300MM DWC Pipe  5 nos of 2.5 MVA USS each  25 nos of Feeder Pillar C. Promenade Light  365 nos of light pole (45W)  9 nos of sub-feeder pillar  4Cx10 SQ.MM armoured Aluminum Cable D. Street Light Pole  159 nos of light pole (120W)  4Cx16 SQ.MM armoured Aluminum Cable
  • 45. Discussions i. USS  Number of ways of RMU in the USS is not specified neither in BoQ nor TS  As per TS 1.3, installed altitude of RMU is 2500m & 3500m above sea level. Phuentsholing’s maximum altitude is 300m. Is it necessary to follow TS?  Request foundation drawing for USS, as adopted by BPC ii. Earthing for USS & Feeder Pillar  Resistance of the soil in the project is in between 1400-1500 ohms  Project request BPC for way forward iii. Cable from USS to Feeder Pillar  As per BoQ is 4Cx630 sq.mm armoured aluminum cable  390A- cable carrying capacity  6- way, 600A feeder pillar  2 or 1 incoming cable to feeder pillar? If 2 then is it advisable to connect two cable in one outgoing MCCB of 630A at LT side of USS?
  • 46. Discussions continued… iv. Trench Connection to USS? v. LV Switchboard (LT side of USS)  MCCBs • 630A TP MCCB (50KA)- 4 nos • 300A TP MCCB (50KA)- 4 nos vi. Final review of USS & Feeder Pillar location by BPC vii. Review of TS & drawing of Feeder Pillar by BPC viii.Status of connection from BPC substation

Editor's Notes

  1. Payment to Consultant (PTDP) - CDCL 5201900001 4,683,505.35 Payment to Contractor (PTDP) - CDCL 5201900002 121,056,567.93