The document provides a sample question and answer from the PMP exam. The question asks for the best course of action for a project manager to address unexpected issues threatening the project's schedule and budget. The correct answer is to use management reserves, which are withheld for unforeseen risks rather than the contingency reserves allocated for identified risks or the other options provided. The explanation notes the discrepancy between "issues" in the question and "risks" in the explanation.