SlideShare a Scribd company logo
Prepared By:
Paras Agarwal
Summer Intern,
DoMS IIT Madras
Project Mentors:
Mr. G Rajendran
Mr. Rahul Yadav
Titan Company Ltd. 1
Incoming
Load
from
Factory
Metal
Setting
S1
Mould
Setting
S5
Hand
Work
S4
Benchworking
Benchworking
Benchworking Prepolishing Stone Setting Final Polishing
Waxing
BezelChannelPavePressureProng
Quality Control
Rhodium
Polishing
Soap
Cleaning
Steam
Cleaning
Gluing
Third
Party
Casting
Final Polishing
Prepolishing Stone Setting Final Polishing
Bangle
2
Shop floor workers
• Better Communication
• Standard Operating procedures
• Clarity about the color priority logic
Supervisor & KP owner
• Real time info about the process
• Easy Identification of source of problem
• Low dependency on physical availability of Supervisor
• Output should be maintained while following color priority
Titan Management
• Accurate info about the process
• High Quality output
• Color priority based output
• Skill level improvement of KP
SituationalUser
• Quick understanding of the process
• Clear mapping to find a particular person/ workstation
3
al Mgmt : Customer Identification
and Need Analysis
 Production according to color (TOC)
priority
 Process flow & WIP synchronized with
skill set of employees.
 Increasing overall Output rate in terms of
(increased capacity, increased efficiency)
 Faster Delivery (Reduction in Lead time)
 Improved Quality (Reduction in Rework
and other redundant activities)
 Better Communication mechanism at Shop
floor
 Better visibility of process
AS-IS Process To-Be Process
* No Skill Capacity dedicated input * Low output
* Low TOC dedicated output * High rework
* Skill Capacity dedicated input * High output
* High TOC dedicated output * Less rework
4
LG shop floor
 Output not in accordance with the expectation
As-Is : Black o/p: <30% (of total o/p) Expected : Black o/p: >80%
 Lower Black Conversion: Black output consisted of a very small portion of daily morning
Black WIP ( only 13% on a average).
0
50
100
150
200
250
5-Jun
6-Jun
7-Jun
8-Jun
9-Jun
10-Jun
11-Jun
12-Jun
13-Jun
14-Jun
15-Jun
16-Jun
17-Jun
Opening Black WIP vs Total Black output
Closing Black O/P
Opening Black WIP
Noofcards
5
 Lead time of Black cards was observed higher than non Black cards for all
productroutes.
6
 The most consistent reason for these high lead times of Black
cards is due to time spent by them as Inactive cards.
 But the point of concern is most of the causes for cards entering
into inactive zone are associated with Karigar park only.
Flag Cause
Input
Issues
Weight Mismatch,
Part Missing
Casting
Replace
ment
Melting of gold,
Over etching,
Prong broken, Bad
input casting
Stone
Replace
ment
Stone Breakage
Bath
Plating
with
Mask
Operation not
available
13% 4%
48%
30%
0% 4%
Different flags raised
for Inactive cards
Input
Issues
Laser
Welding
Casting
Replace
ment
Stone
Replace
ment
Polishing Workstation
Stone Setting Workstation
Bench Work Workstation
7
0
2
4
6
8
10
12
14
16
18
20
Instantaneous Black
WIP
Instantaneous Non
Black WIP
Output per 2 hrs
The solution part consists of two fold approach:
1) Increasing flow by working on identified and yet to emerge bottlenecks.
2) Implementing solutions using the visual means to aid the increased flow.
8
Single Piece Flow (Critical)
 Work allocated to Karigars according to the skill sets.
 Karigar works on a single product at a time, and puts it
in a collection bin in front of him.
 Time difference problem between jobs controlled by
having a buffer maintained before each job in the bins
of precedent jobs.
 Transfer of some load from Time based batching bins
to Karigars of single piece flow in case of no inventory
in buffer bins.
Time Based Batching (Non Critical)
 Work allocated to Karigars according to their skill and
capacity for 1 hour.
 For BW, PP, FP work allocated according to number of
cards possible in 1 hour.
 In SE, on the basis of number of stones, ideally around
20-24 stones of work.
 TOC priority followed at the time of allocation.
 Work gap between different jobs managed by
deploying excess cards from precedent job to TOC rack
and considering them again after 1 hour following TOC
color priority.
Trial run of Hybrid Model of U-cell and Job bay implemented :
U-cell-> Non critical (Single flow)
Job bays-> Both critical & Non Critical (SF & Time based)
Ultimate target of converting all Bays into U-cell, with
1 Bay-> Critical (Single flow) and
2 Bays-> Non Critical (only Time Based Batching)
9
Active WIPInactive cardsTotalWIP
Non CriticalHandworkCritical
Loading
logic
Lead Time
Output Ratio
5 days3 days
x
3 days
3x
New Load Target Load Active WIP
• Bangles
• Neckwear
• 2 Set Products
• Non Mould
Setting Products
with Stones >24
• Products for
which waxing
and casting
done outside
Titan
• All Other productsSpecial Cases
1) No/Less Handwork Load ??
2) No/Less Critical Load ??
3) No/Less Non Critical Load ??
4) Excess Black cards in Critical
than loading requirement, major
chunk of Non Critical load in
yellow/green and vice versa ??
10
11
AS-IS Process To-Be Process
• Reading and analyzing the
color guide- tedious and
cumbersome for many Karigars
• Plugging in the current color
clip on the cards being issued
to the workstations
Average
29%
Average
83%
12
Average Daily O/P 97
Conversion Rate wrt
Opening Active WIP 27%
Average Daily O/P 81
Conversion Rate wrt
Opening Active WIP 23%
13
Expected Lead Time <3 days PASS/FAIL
Expected Lead Time <3 days PASS
Expected Lead Time
Critical <3 days
Handwork <6 days FAIL
PASSTotal O/P 659
Total O/P 125
Total O/P 76
14
Burr Plate at Stone Setting WS Wheel Board at Polishing WS Load Tower at every WS

More Related Content

What's hot

Minimization of the Casting Defects Using Taguchi’s Method
Minimization of the Casting Defects Using Taguchi’s MethodMinimization of the Casting Defects Using Taguchi’s Method
Minimization of the Casting Defects Using Taguchi’s Method
inventionjournals
 
2012 deep research report on global and china sapphire ingot industry
2012 deep research report on global and china sapphire ingot industry2012 deep research report on global and china sapphire ingot industry
2012 deep research report on global and china sapphire ingot industrysmarter2011
 
Great Design in Steel - Gestamp 2016
Great Design in Steel - Gestamp 2016Great Design in Steel - Gestamp 2016
Great Design in Steel - Gestamp 2016Christophe Cazes
 
RoHs report
RoHs reportRoHs report
RoHs reportLeo Lyu
 
IRJET- Artificial Intelligence ARM- Review
IRJET- Artificial Intelligence ARM- ReviewIRJET- Artificial Intelligence ARM- Review
IRJET- Artificial Intelligence ARM- Review
IRJET Journal
 
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear box
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear boxDesign and Analysis of fluid flow in AISI 1008 Steel reduction gear box
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear box
IRJET Journal
 
Fill The Void Presentation
Fill The Void PresentationFill The Void Presentation
Fill The Void Presentation
FCT Solder
 
Automating Leak Testing
Automating Leak TestingAutomating Leak Testing
Automating Leak Testing
Elizabeth (Lisa) Gardner
 
IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...
IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...
IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...
IRJET Journal
 
spec 525 grade
spec 525 gradespec 525 grade
spec 525 gradeMaggie XU
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous Flow
Julian Kalac P.Eng
 
Enigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in indiaEnigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in india
Dr. Bikram Jit Singh
 
SIX SIGMA GB CERTIFICATION@Dinesh
SIX SIGMA GB CERTIFICATION@DineshSIX SIGMA GB CERTIFICATION@Dinesh
SIX SIGMA GB CERTIFICATION@DineshDinesh Goonarathne
 

What's hot (15)

Minimization of the Casting Defects Using Taguchi’s Method
Minimization of the Casting Defects Using Taguchi’s MethodMinimization of the Casting Defects Using Taguchi’s Method
Minimization of the Casting Defects Using Taguchi’s Method
 
2012 deep research report on global and china sapphire ingot industry
2012 deep research report on global and china sapphire ingot industry2012 deep research report on global and china sapphire ingot industry
2012 deep research report on global and china sapphire ingot industry
 
Great Design in Steel - Gestamp 2016
Great Design in Steel - Gestamp 2016Great Design in Steel - Gestamp 2016
Great Design in Steel - Gestamp 2016
 
RoHs report
RoHs reportRoHs report
RoHs report
 
Ts industries overview ver 5
Ts industries overview ver 5Ts industries overview ver 5
Ts industries overview ver 5
 
IRJET- Artificial Intelligence ARM- Review
IRJET- Artificial Intelligence ARM- ReviewIRJET- Artificial Intelligence ARM- Review
IRJET- Artificial Intelligence ARM- Review
 
BigSys_Quickparts
BigSys_QuickpartsBigSys_Quickparts
BigSys_Quickparts
 
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear box
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear boxDesign and Analysis of fluid flow in AISI 1008 Steel reduction gear box
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear box
 
Fill The Void Presentation
Fill The Void PresentationFill The Void Presentation
Fill The Void Presentation
 
Automating Leak Testing
Automating Leak TestingAutomating Leak Testing
Automating Leak Testing
 
IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...
IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...
IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...
 
spec 525 grade
spec 525 gradespec 525 grade
spec 525 grade
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous Flow
 
Enigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in indiaEnigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in india
 
SIX SIGMA GB CERTIFICATION@Dinesh
SIX SIGMA GB CERTIFICATION@DineshSIX SIGMA GB CERTIFICATION@Dinesh
SIX SIGMA GB CERTIFICATION@Dinesh
 

Viewers also liked

Presentación2
Presentación2Presentación2
Presentación2
josef marin marcano
 
20160517092516437
2016051709251643720160517092516437
20160517092516437LYLE BROWN
 
Identidade visual e UX
Identidade visual e UXIdentidade visual e UX
Identidade visual e UX
B&R Consultoria Empresarial
 
Contaminacion jose.
Contaminacion jose.Contaminacion jose.
Contaminacion jose.
josef marin marcano
 
No hay vida sin internet
No hay vida sin internetNo hay vida sin internet
No hay vida sin internet
Merche Diez
 
Calentamiento global
Calentamiento globalCalentamiento global
Calentamiento global
Efrain Cruz
 
Conhecendo o Wordpress
Conhecendo o WordpressConhecendo o Wordpress
Conhecendo o Wordpress
B&R Consultoria Empresarial
 
Matemaniacos Genios
Matemaniacos GeniosMatemaniacos Genios
Matemaniacos Genios
Benjamin Paulo
 
NewsPlan Edition 2 May-August 2016
NewsPlan Edition 2 May-August 2016NewsPlan Edition 2 May-August 2016
NewsPlan Edition 2 May-August 2016Fiza Naseer
 
Tarea5.carlos camacho
Tarea5.carlos camachoTarea5.carlos camacho
Component-Based Entity System과 Data-oriented Design
Component-Based Entity System과 Data-oriented DesignComponent-Based Entity System과 Data-oriented Design
Component-Based Entity System과 Data-oriented Design
Sukwoo Lee
 
The Application of Next Generation Sequencing (NGS) in cancer treatment
The Application of Next Generation Sequencing (NGS) in cancer treatmentThe Application of Next Generation Sequencing (NGS) in cancer treatment
The Application of Next Generation Sequencing (NGS) in cancer treatment
Premadarshini Sai
 

Viewers also liked (13)

Presentación2
Presentación2Presentación2
Presentación2
 
20160517092516437
2016051709251643720160517092516437
20160517092516437
 
Identidade visual e UX
Identidade visual e UXIdentidade visual e UX
Identidade visual e UX
 
Contaminacion jose.
Contaminacion jose.Contaminacion jose.
Contaminacion jose.
 
No hay vida sin internet
No hay vida sin internetNo hay vida sin internet
No hay vida sin internet
 
Calentamiento global
Calentamiento globalCalentamiento global
Calentamiento global
 
Conhecendo o Wordpress
Conhecendo o WordpressConhecendo o Wordpress
Conhecendo o Wordpress
 
CV
CVCV
CV
 
Matemaniacos Genios
Matemaniacos GeniosMatemaniacos Genios
Matemaniacos Genios
 
NewsPlan Edition 2 May-August 2016
NewsPlan Edition 2 May-August 2016NewsPlan Edition 2 May-August 2016
NewsPlan Edition 2 May-August 2016
 
Tarea5.carlos camacho
Tarea5.carlos camachoTarea5.carlos camacho
Tarea5.carlos camacho
 
Component-Based Entity System과 Data-oriented Design
Component-Based Entity System과 Data-oriented DesignComponent-Based Entity System과 Data-oriented Design
Component-Based Entity System과 Data-oriented Design
 
The Application of Next Generation Sequencing (NGS) in cancer treatment
The Application of Next Generation Sequencing (NGS) in cancer treatmentThe Application of Next Generation Sequencing (NGS) in cancer treatment
The Application of Next Generation Sequencing (NGS) in cancer treatment
 

Similar to Paras Agarwal_Titan_Summer Internship_brief

North American PCB Manufacturer
North American PCB ManufacturerNorth American PCB Manufacturer
North American PCB Manufacturer
Domestic PCB Fabrication
 
Casting manufacturing process improvement
Casting manufacturing process improvementCasting manufacturing process improvement
Casting manufacturing process improvement
Abdullah Ansari
 
q-Maxim’s approach to waste reduction in foundry application using Taguchi ...
q-Maxim’s approach to waste reduction in  foundry application  using Taguchi ...q-Maxim’s approach to waste reduction in  foundry application  using Taguchi ...
q-Maxim’s approach to waste reduction in foundry application using Taguchi ...
q-Maxim
 
WIP Flow: A Card system for Production Planning and Control
WIP Flow: A Card system for Production Planning and ControlWIP Flow: A Card system for Production Planning and Control
WIP Flow: A Card system for Production Planning and Control
IBRAHIM MOHAMMED, PMP
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Chris Baichoo
 
Saivs Sand Casting &amp; Machining
Saivs Sand Casting &amp; MachiningSaivs Sand Casting &amp; Machining
Saivs Sand Casting &amp; Machining
huhangcheng
 
Electronic manufacturing v3.0 - Fab Academy 2016
Electronic manufacturing v3.0 - Fab Academy 2016Electronic manufacturing v3.0 - Fab Academy 2016
Electronic manufacturing v3.0 - Fab Academy 2016
seeedstudio
 
Presntation (MNIT).pptx
Presntation (MNIT).pptxPresntation (MNIT).pptx
Presntation (MNIT).pptx
rajtashee725
 
Job Shop Scheduling with Setup Times Release times and Deadlines
Job Shop Scheduling with Setup Times  Release times and DeadlinesJob Shop Scheduling with Setup Times  Release times and Deadlines
Job Shop Scheduling with Setup Times Release times and DeadlinesAlkis Vazacopoulos
 
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.EngVOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
Julian Kalac P.Eng
 
Corporate presentation 2014
Corporate presentation 2014Corporate presentation 2014
Corporate presentation 2014
bmacforever
 
Supply chain design and operation
Supply chain design and operationSupply chain design and operation
Supply chain design and operation
AngelainBay
 
Failure Analysis, benefits, logistics and limitations
Failure Analysis, benefits, logistics and limitationsFailure Analysis, benefits, logistics and limitations
Failure Analysis, benefits, logistics and limitations
Accendo Reliability
 
Deterministic Polishing from Theory to Practice (Optifab 2015)
Deterministic Polishing from Theory to Practice (Optifab 2015)Deterministic Polishing from Theory to Practice (Optifab 2015)
Deterministic Polishing from Theory to Practice (Optifab 2015)
Nanophase Technologies
 
Tru design coatings
Tru design coatingsTru design coatings
Tru design coatings
Courtney Herda
 
mid sem report.pptx
mid sem report.pptxmid sem report.pptx
mid sem report.pptx
ShubhamPareta8
 
Wind Turbine Components Case Study - Dragon Sourcing
Wind Turbine Components Case Study - Dragon SourcingWind Turbine Components Case Study - Dragon Sourcing
Wind Turbine Components Case Study - Dragon Sourcing
Dragon Sourcing
 
Quick circuit prototyping systems,pcba prototype,prototyping pcb boards,mcpcb...
Quick circuit prototyping systems,pcba prototype,prototyping pcb boards,mcpcb...Quick circuit prototyping systems,pcba prototype,prototyping pcb boards,mcpcb...
Quick circuit prototyping systems,pcba prototype,prototyping pcb boards,mcpcb...raymingpcb
 
Rapid pcb prototyping,fast pcb.com,goldphoenixpcb,pcb board manufacturing,pcb...
Rapid pcb prototyping,fast pcb.com,goldphoenixpcb,pcb board manufacturing,pcb...Rapid pcb prototyping,fast pcb.com,goldphoenixpcb,pcb board manufacturing,pcb...
Rapid pcb prototyping,fast pcb.com,goldphoenixpcb,pcb board manufacturing,pcb...raymingpcb
 
Printed circuit board assembly,wholesale pcb prototype board,rapid prototypin...
Printed circuit board assembly,wholesale pcb prototype board,rapid prototypin...Printed circuit board assembly,wholesale pcb prototype board,rapid prototypin...
Printed circuit board assembly,wholesale pcb prototype board,rapid prototypin...raymingpcb
 

Similar to Paras Agarwal_Titan_Summer Internship_brief (20)

North American PCB Manufacturer
North American PCB ManufacturerNorth American PCB Manufacturer
North American PCB Manufacturer
 
Casting manufacturing process improvement
Casting manufacturing process improvementCasting manufacturing process improvement
Casting manufacturing process improvement
 
q-Maxim’s approach to waste reduction in foundry application using Taguchi ...
q-Maxim’s approach to waste reduction in  foundry application  using Taguchi ...q-Maxim’s approach to waste reduction in  foundry application  using Taguchi ...
q-Maxim’s approach to waste reduction in foundry application using Taguchi ...
 
WIP Flow: A Card system for Production Planning and Control
WIP Flow: A Card system for Production Planning and ControlWIP Flow: A Card system for Production Planning and Control
WIP Flow: A Card system for Production Planning and Control
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
 
Saivs Sand Casting &amp; Machining
Saivs Sand Casting &amp; MachiningSaivs Sand Casting &amp; Machining
Saivs Sand Casting &amp; Machining
 
Electronic manufacturing v3.0 - Fab Academy 2016
Electronic manufacturing v3.0 - Fab Academy 2016Electronic manufacturing v3.0 - Fab Academy 2016
Electronic manufacturing v3.0 - Fab Academy 2016
 
Presntation (MNIT).pptx
Presntation (MNIT).pptxPresntation (MNIT).pptx
Presntation (MNIT).pptx
 
Job Shop Scheduling with Setup Times Release times and Deadlines
Job Shop Scheduling with Setup Times  Release times and DeadlinesJob Shop Scheduling with Setup Times  Release times and Deadlines
Job Shop Scheduling with Setup Times Release times and Deadlines
 
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.EngVOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
 
Corporate presentation 2014
Corporate presentation 2014Corporate presentation 2014
Corporate presentation 2014
 
Supply chain design and operation
Supply chain design and operationSupply chain design and operation
Supply chain design and operation
 
Failure Analysis, benefits, logistics and limitations
Failure Analysis, benefits, logistics and limitationsFailure Analysis, benefits, logistics and limitations
Failure Analysis, benefits, logistics and limitations
 
Deterministic Polishing from Theory to Practice (Optifab 2015)
Deterministic Polishing from Theory to Practice (Optifab 2015)Deterministic Polishing from Theory to Practice (Optifab 2015)
Deterministic Polishing from Theory to Practice (Optifab 2015)
 
Tru design coatings
Tru design coatingsTru design coatings
Tru design coatings
 
mid sem report.pptx
mid sem report.pptxmid sem report.pptx
mid sem report.pptx
 
Wind Turbine Components Case Study - Dragon Sourcing
Wind Turbine Components Case Study - Dragon SourcingWind Turbine Components Case Study - Dragon Sourcing
Wind Turbine Components Case Study - Dragon Sourcing
 
Quick circuit prototyping systems,pcba prototype,prototyping pcb boards,mcpcb...
Quick circuit prototyping systems,pcba prototype,prototyping pcb boards,mcpcb...Quick circuit prototyping systems,pcba prototype,prototyping pcb boards,mcpcb...
Quick circuit prototyping systems,pcba prototype,prototyping pcb boards,mcpcb...
 
Rapid pcb prototyping,fast pcb.com,goldphoenixpcb,pcb board manufacturing,pcb...
Rapid pcb prototyping,fast pcb.com,goldphoenixpcb,pcb board manufacturing,pcb...Rapid pcb prototyping,fast pcb.com,goldphoenixpcb,pcb board manufacturing,pcb...
Rapid pcb prototyping,fast pcb.com,goldphoenixpcb,pcb board manufacturing,pcb...
 
Printed circuit board assembly,wholesale pcb prototype board,rapid prototypin...
Printed circuit board assembly,wholesale pcb prototype board,rapid prototypin...Printed circuit board assembly,wholesale pcb prototype board,rapid prototypin...
Printed circuit board assembly,wholesale pcb prototype board,rapid prototypin...
 

Paras Agarwal_Titan_Summer Internship_brief

  • 1. Prepared By: Paras Agarwal Summer Intern, DoMS IIT Madras Project Mentors: Mr. G Rajendran Mr. Rahul Yadav Titan Company Ltd. 1
  • 2. Incoming Load from Factory Metal Setting S1 Mould Setting S5 Hand Work S4 Benchworking Benchworking Benchworking Prepolishing Stone Setting Final Polishing Waxing BezelChannelPavePressureProng Quality Control Rhodium Polishing Soap Cleaning Steam Cleaning Gluing Third Party Casting Final Polishing Prepolishing Stone Setting Final Polishing Bangle 2
  • 3. Shop floor workers • Better Communication • Standard Operating procedures • Clarity about the color priority logic Supervisor & KP owner • Real time info about the process • Easy Identification of source of problem • Low dependency on physical availability of Supervisor • Output should be maintained while following color priority Titan Management • Accurate info about the process • High Quality output • Color priority based output • Skill level improvement of KP SituationalUser • Quick understanding of the process • Clear mapping to find a particular person/ workstation 3 al Mgmt : Customer Identification and Need Analysis  Production according to color (TOC) priority  Process flow & WIP synchronized with skill set of employees.  Increasing overall Output rate in terms of (increased capacity, increased efficiency)  Faster Delivery (Reduction in Lead time)  Improved Quality (Reduction in Rework and other redundant activities)  Better Communication mechanism at Shop floor  Better visibility of process
  • 4. AS-IS Process To-Be Process * No Skill Capacity dedicated input * Low output * Low TOC dedicated output * High rework * Skill Capacity dedicated input * High output * High TOC dedicated output * Less rework 4 LG shop floor
  • 5.  Output not in accordance with the expectation As-Is : Black o/p: <30% (of total o/p) Expected : Black o/p: >80%  Lower Black Conversion: Black output consisted of a very small portion of daily morning Black WIP ( only 13% on a average). 0 50 100 150 200 250 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun Opening Black WIP vs Total Black output Closing Black O/P Opening Black WIP Noofcards 5
  • 6.  Lead time of Black cards was observed higher than non Black cards for all productroutes. 6  The most consistent reason for these high lead times of Black cards is due to time spent by them as Inactive cards.  But the point of concern is most of the causes for cards entering into inactive zone are associated with Karigar park only. Flag Cause Input Issues Weight Mismatch, Part Missing Casting Replace ment Melting of gold, Over etching, Prong broken, Bad input casting Stone Replace ment Stone Breakage Bath Plating with Mask Operation not available 13% 4% 48% 30% 0% 4% Different flags raised for Inactive cards Input Issues Laser Welding Casting Replace ment Stone Replace ment
  • 7. Polishing Workstation Stone Setting Workstation Bench Work Workstation 7 0 2 4 6 8 10 12 14 16 18 20 Instantaneous Black WIP Instantaneous Non Black WIP Output per 2 hrs
  • 8. The solution part consists of two fold approach: 1) Increasing flow by working on identified and yet to emerge bottlenecks. 2) Implementing solutions using the visual means to aid the increased flow. 8 Single Piece Flow (Critical)  Work allocated to Karigars according to the skill sets.  Karigar works on a single product at a time, and puts it in a collection bin in front of him.  Time difference problem between jobs controlled by having a buffer maintained before each job in the bins of precedent jobs.  Transfer of some load from Time based batching bins to Karigars of single piece flow in case of no inventory in buffer bins. Time Based Batching (Non Critical)  Work allocated to Karigars according to their skill and capacity for 1 hour.  For BW, PP, FP work allocated according to number of cards possible in 1 hour.  In SE, on the basis of number of stones, ideally around 20-24 stones of work.  TOC priority followed at the time of allocation.  Work gap between different jobs managed by deploying excess cards from precedent job to TOC rack and considering them again after 1 hour following TOC color priority.
  • 9. Trial run of Hybrid Model of U-cell and Job bay implemented : U-cell-> Non critical (Single flow) Job bays-> Both critical & Non Critical (SF & Time based) Ultimate target of converting all Bays into U-cell, with 1 Bay-> Critical (Single flow) and 2 Bays-> Non Critical (only Time Based Batching) 9
  • 10. Active WIPInactive cardsTotalWIP Non CriticalHandworkCritical Loading logic Lead Time Output Ratio 5 days3 days x 3 days 3x New Load Target Load Active WIP • Bangles • Neckwear • 2 Set Products • Non Mould Setting Products with Stones >24 • Products for which waxing and casting done outside Titan • All Other productsSpecial Cases 1) No/Less Handwork Load ?? 2) No/Less Critical Load ?? 3) No/Less Non Critical Load ?? 4) Excess Black cards in Critical than loading requirement, major chunk of Non Critical load in yellow/green and vice versa ?? 10
  • 11. 11 AS-IS Process To-Be Process • Reading and analyzing the color guide- tedious and cumbersome for many Karigars • Plugging in the current color clip on the cards being issued to the workstations
  • 12. Average 29% Average 83% 12 Average Daily O/P 97 Conversion Rate wrt Opening Active WIP 27% Average Daily O/P 81 Conversion Rate wrt Opening Active WIP 23%
  • 13. 13 Expected Lead Time <3 days PASS/FAIL Expected Lead Time <3 days PASS Expected Lead Time Critical <3 days Handwork <6 days FAIL PASSTotal O/P 659 Total O/P 125 Total O/P 76
  • 14. 14 Burr Plate at Stone Setting WS Wheel Board at Polishing WS Load Tower at every WS