This document provides details of a 2166 MW turnkey EPC power plant project in Wales, United Kingdom. The project consists of 5 x 420 MW single-shaft power plants utilizing 5 gas turbines, 5 heat recovery steam generators, 5 steam turbines, and 5 generators. Major subcontractors are listed for civil, steel, mechanical, electrical, and piping works. The notice to proceed date is February 18, 2009 with a scheduled start of April 18, 2009 and a completion date of 31 months later in November 2011.