ACHIEVEMENTS:
 Worked on the proposal of Prequalification 132 kV Substations for our company and got the approval
from National Grid Saudi Arabia (NGSA).
PROJECTS ACHIEVED:
 Replacement of (02) nos. A.K-2 188 MVA Generator Transformer costing SAR. 14.438 million - Saline
Water Corporation Co. (SWCC) Al Khobar.
 Reinforcement of 33/13.8 kV SS 7814 in Buraidah costing SAR. 29.743 million – Saudi Electricity Company
SEC- COA.
 Installation of AMR System in 63 nos. of Substations in Aramco at Eastern Region costing SAR. 96.908
million - National Grid Saudi Arabia (NGSA).
 Replacement of over Current & Earth Fault Relays Type RACID /RACIB at Several 33/13.8 kV Substations
in Oassim and Riyadh Area costing SAR 5.582 million - Saudi Electricity Company (SEC-COA).
 Construction of new 132/13.8 kV Substation # 8138 Al Manfoha in Riyadh Costing SAR 81.354 million -
National Grid Saudi Arabia (NGSA).
 Construction of new 132/13.8 kV Substation # 8231 Al Marooj in Riyadh Costing SAR 96.629 million -
National Grid Saudi Arabia (NGSA).
 Construction of new 132/13.8 kV Substation # 8281 Al Hayer in Riyadh Costing SAR 81.893 million -
National Grid Saudi Arabia (NGSA).

More Related Content

What's hot

Power control for vast north sea offshore wind farm - Case Study
Power control for vast north sea offshore wind farm - Case StudyPower control for vast north sea offshore wind farm - Case Study
Power control for vast north sea offshore wind farm - Case Study
Sollatek
 
BMW ReGenX Test Protocol
BMW ReGenX Test ProtocolBMW ReGenX Test Protocol
BMW ReGenX Test ProtocolThane Heins
 
Grid Station Construction (GSC) NTDCL
Grid Station Construction (GSC) NTDCL Grid Station Construction (GSC) NTDCL
Grid Station Construction (GSC) NTDCL
MUDASSAR AFZAL
 
EESS 2018 Day 2 - Mark Mills
EESS 2018 Day 2 - Mark MillsEESS 2018 Day 2 - Mark Mills
EESS 2018 Day 2 - Mark Mills
NSW Environment and Planning
 
Electric fault at forsmark nuclear power plant
Electric fault at forsmark nuclear power plantElectric fault at forsmark nuclear power plant
Electric fault at forsmark nuclear power plant
Abdul Soomro
 
Sami Abu Louz, Curriculum Vitae
Sami Abu Louz, Curriculum VitaeSami Abu Louz, Curriculum Vitae
Sami Abu Louz, Curriculum Vitaesami abulouz
 
Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...
Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...
Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...
Torben Haagh
 
Philadelphia Project Overview09
Philadelphia Project Overview09Philadelphia Project Overview09
Philadelphia Project Overview09
PECO Energy Company
 
Siemens 2 Report Signed Data Sheets Mark Hamilton
Siemens 2 Report Signed Data Sheets Mark HamiltonSiemens 2 Report Signed Data Sheets Mark Hamilton
Siemens 2 Report Signed Data Sheets Mark Hamilton
Thane Heins
 
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilotMike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
james hamilton
 
NOTABLE PROJECTS
NOTABLE PROJECTSNOTABLE PROJECTS
NOTABLE PROJECTSM.Essa Khan
 
DPL Transmission And Distribution
DPL Transmission And DistributionDPL Transmission And Distribution
DPL Transmission And Distribution
Subhojeet Sinha ☁
 
121 MW Allai Khwar Hydel Power Station Presentation
121 MW Allai Khwar Hydel Power Station Presentation121 MW Allai Khwar Hydel Power Station Presentation
121 MW Allai Khwar Hydel Power Station Presentation
EngrAsimRaza2
 
power sector &ehv
power sector &ehvpower sector &ehv
power sector &ehv
Ajay Kishor
 
Steven-Nethery-Technical-Sales-Manager-Goldwind-Australia
Steven-Nethery-Technical-Sales-Manager-Goldwind-AustraliaSteven-Nethery-Technical-Sales-Manager-Goldwind-Australia
Steven-Nethery-Technical-Sales-Manager-Goldwind-Australiagoldwindaus
 

What's hot (19)

CESC-TGS REPORT
CESC-TGS REPORTCESC-TGS REPORT
CESC-TGS REPORT
 
Power control for vast north sea offshore wind farm - Case Study
Power control for vast north sea offshore wind farm - Case StudyPower control for vast north sea offshore wind farm - Case Study
Power control for vast north sea offshore wind farm - Case Study
 
RENEW
RENEWRENEW
RENEW
 
BMW ReGenX Test Protocol
BMW ReGenX Test ProtocolBMW ReGenX Test Protocol
BMW ReGenX Test Protocol
 
Grid Station Construction (GSC) NTDCL
Grid Station Construction (GSC) NTDCL Grid Station Construction (GSC) NTDCL
Grid Station Construction (GSC) NTDCL
 
EESS 2018 Day 2 - Mark Mills
EESS 2018 Day 2 - Mark MillsEESS 2018 Day 2 - Mark Mills
EESS 2018 Day 2 - Mark Mills
 
Electric fault at forsmark nuclear power plant
Electric fault at forsmark nuclear power plantElectric fault at forsmark nuclear power plant
Electric fault at forsmark nuclear power plant
 
Sami Abu Louz, Curriculum Vitae
Sami Abu Louz, Curriculum VitaeSami Abu Louz, Curriculum Vitae
Sami Abu Louz, Curriculum Vitae
 
CESC PROJECT
CESC PROJECTCESC PROJECT
CESC PROJECT
 
Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...
Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...
Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...
 
CESC Report
CESC ReportCESC Report
CESC Report
 
Philadelphia Project Overview09
Philadelphia Project Overview09Philadelphia Project Overview09
Philadelphia Project Overview09
 
Siemens 2 Report Signed Data Sheets Mark Hamilton
Siemens 2 Report Signed Data Sheets Mark HamiltonSiemens 2 Report Signed Data Sheets Mark Hamilton
Siemens 2 Report Signed Data Sheets Mark Hamilton
 
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilotMike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
 
NOTABLE PROJECTS
NOTABLE PROJECTSNOTABLE PROJECTS
NOTABLE PROJECTS
 
DPL Transmission And Distribution
DPL Transmission And DistributionDPL Transmission And Distribution
DPL Transmission And Distribution
 
121 MW Allai Khwar Hydel Power Station Presentation
121 MW Allai Khwar Hydel Power Station Presentation121 MW Allai Khwar Hydel Power Station Presentation
121 MW Allai Khwar Hydel Power Station Presentation
 
power sector &ehv
power sector &ehvpower sector &ehv
power sector &ehv
 
Steven-Nethery-Technical-Sales-Manager-Goldwind-Australia
Steven-Nethery-Technical-Sales-Manager-Goldwind-AustraliaSteven-Nethery-Technical-Sales-Manager-Goldwind-Australia
Steven-Nethery-Technical-Sales-Manager-Goldwind-Australia
 

Similar to ACHIEVEMENTS

Wajid Ali Shah
Wajid Ali ShahWajid Ali Shah
Wajid Ali Shah
Wajid Ali Shah
 
O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid india
Vaibhav Jain
 
Project List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerProject List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerReza Shah Abadi
 
ahmad alhajj-2 with photo
ahmad alhajj-2 with photoahmad alhajj-2 with photo
ahmad alhajj-2 with photoAhmed Alhaj
 
Ibrahim makki saudi cable company
Ibrahim makki  saudi cable companyIbrahim makki  saudi cable company
Ibrahim makki saudi cable companysarah7887
 
resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986sheik syedali
 
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
Prannay Kumar Giri
 
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
Power System Operation
 
NUML PRESENTATION.pptx
NUML PRESENTATION.pptxNUML PRESENTATION.pptx
NUML PRESENTATION.pptx
AsfandyarAliKhan
 
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
Power System Operation
 
wael_issa_CV_updated
wael_issa_CV_updatedwael_issa_CV_updated
wael_issa_CV_updatedwael issa
 
Ultra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVACUltra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVAC
Aravind Panasa
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Abdul Alim Dewan
 
Status of hvdc links
Status of hvdc linksStatus of hvdc links
Status of hvdc links
abhishek pratap singh
 
Electrical Engineer
Electrical EngineerElectrical Engineer
Electrical Engineer
Dhiraj kumar Nishad
 

Similar to ACHIEVEMENTS (20)

Wajid Ali Shah
Wajid Ali ShahWajid Ali Shah
Wajid Ali Shah
 
O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid india
 
Project List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerProject List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical Enginner
 
ahmad alhajj-2 with photo
ahmad alhajj-2 with photoahmad alhajj-2 with photo
ahmad alhajj-2 with photo
 
Ibrahim makki saudi cable company
Ibrahim makki  saudi cable companyIbrahim makki  saudi cable company
Ibrahim makki saudi cable company
 
resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986
 
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
 
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
 
osama dwedar ..
osama dwedar ..osama dwedar ..
osama dwedar ..
 
NUML PRESENTATION.pptx
NUML PRESENTATION.pptxNUML PRESENTATION.pptx
NUML PRESENTATION.pptx
 
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
 
E&I Farukh
E&I FarukhE&I Farukh
E&I Farukh
 
wael_issa_CV_updated
wael_issa_CV_updatedwael_issa_CV_updated
wael_issa_CV_updated
 
Ultra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVACUltra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVAC
 
Nazh cv rev.2
Nazh cv  rev.2Nazh cv  rev.2
Nazh cv rev.2
 
Paulpandy CV.
Paulpandy  CV.Paulpandy  CV.
Paulpandy CV.
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017
 
Status of hvdc links
Status of hvdc linksStatus of hvdc links
Status of hvdc links
 
Electrical Engineer
Electrical EngineerElectrical Engineer
Electrical Engineer
 
CURRICULUM VITAE - Asif
CURRICULUM VITAE - AsifCURRICULUM VITAE - Asif
CURRICULUM VITAE - Asif
 

ACHIEVEMENTS

  • 1. ACHIEVEMENTS:  Worked on the proposal of Prequalification 132 kV Substations for our company and got the approval from National Grid Saudi Arabia (NGSA). PROJECTS ACHIEVED:  Replacement of (02) nos. A.K-2 188 MVA Generator Transformer costing SAR. 14.438 million - Saline Water Corporation Co. (SWCC) Al Khobar.  Reinforcement of 33/13.8 kV SS 7814 in Buraidah costing SAR. 29.743 million – Saudi Electricity Company SEC- COA.  Installation of AMR System in 63 nos. of Substations in Aramco at Eastern Region costing SAR. 96.908 million - National Grid Saudi Arabia (NGSA).  Replacement of over Current & Earth Fault Relays Type RACID /RACIB at Several 33/13.8 kV Substations in Oassim and Riyadh Area costing SAR 5.582 million - Saudi Electricity Company (SEC-COA).  Construction of new 132/13.8 kV Substation # 8138 Al Manfoha in Riyadh Costing SAR 81.354 million - National Grid Saudi Arabia (NGSA).  Construction of new 132/13.8 kV Substation # 8231 Al Marooj in Riyadh Costing SAR 96.629 million - National Grid Saudi Arabia (NGSA).  Construction of new 132/13.8 kV Substation # 8281 Al Hayer in Riyadh Costing SAR 81.893 million - National Grid Saudi Arabia (NGSA).