SlideShare a Scribd company logo
1 of 14
POWER
GENERATION
STATION
(PGS)
Project Update / March 23, 2015
Loren Smith
Generation and Transmission Division Manager
History of the SEU
Stillwater is the 2nd largest
municipally owned electric
utility in Oklahoma and the
largest municipal electric
generator in the State.
Stillwater has owned its
Electric Utility since 1901
and began generation of it’s
own electricity in 1903.
Boomer Lake Station
Feasibility Analysis
1. Rebuild Boomer Lake
Station
2. Build a new State of the
Art Generation Facility
3. Get out of the generation
business
Was it economically feasible to build generation
in the City of Stillwater?
GRDA Contract
August 5, 2013 Stillwater Trustees approved the wholesale
purchase power contract. Following signing of contract Stillwater
Trustees authorized staff to:
• Enter into a formal professional
services agreement with Burns &
McDonnell
• Complete the land exchange with
the Commissioners of the Land
Office
• Work with JP Morgan on the bond
underwriting for the project
PGS Project Overview
Final approval received on June 2, 2014
3- 25,000 horse
power natural gas
fired reciprocating
engine/generators
56 MW Output
Control
Room/Admin.
Maintenance
Facilities
New electrical
Transmission and
Distribution
substation.
Procurement Status
• The total project cost is estimated at just under $70 million
• The total project will have 34 procurement packages/bids
– Included: equipment, materials, construction, and services
necessary to construct the facility
• To date 17 of the 34 bids have been released
– Trustees have approved bid recommendations on 9 of them
– Others are still out for bid or are in the evaluation process
• To date we have, or are in the process of finalizing, equipment
and services contracts that total approximately $38.5 million
• We are estimating that for the equipment/services currently
under contract that we are approximately $4.4 million under
budget
Variables out of our control
Construction
Construction scheduled to begin July 2015
Tentative Commercial Operation date June 30, 2016
ODEQ air permit
Weather
ONG pipeline
• Site Prep Design
• Underground Utilities Design
• Final Grading and Drainage Plan
• Site Finishes Design
• Power Generation Building
Foundation Design
• Admin Building Foundation Design
• Major Equipment Foundation Design
• Miscellaneous Foundation Design
• Exhaust Duct Drawings
• Plant Steel Erection Drawings
• Preliminary P&IDs
• Equipment Layouts
• Motor List
• Fire Protection Design
• Under-slab Utilities
Engineering Status
• Engine Hall Piping Design
• Maintenance Area Piping Design
• Plant Electrical One-Lines
• Underground Duct Bank Design
• Underground Grounding Grid
• Electrical Equipment Layouts
• LV and MV Switchgear Schematics
• Wartsila Communications Design
• Control Room Layout
• I/O Design
• Substation Foundation Plan View
• Substation Steel Drawings
• Steel Calculations
• Substation Above Ground
• Substation Switchgear Building Layout
Water Line Project
Natural Gas Line
Project
ODEQ – Title V Air
Permit
Fiber optic
communication to
the New Power
Generation Station
69,000 Volt
transmission
system
improvements
Southwest Power
Pool (SPP)
registration
GRDA
communication
connection to the
new PGS
City of Stillwater
Use By Right permit
application
Off-Site Projects & Permitting
All projects are
expected to be
completed by
the commercial
operation date
of June 30, 2016.
At this time the
PGS project, and
the parallel
projects are on
schedule and
under budget.
Project Completion
Questions

More Related Content

What's hot

Energy used in Burdur Turkey Kaan Peksen
Energy used in Burdur Turkey Kaan PeksenEnergy used in Burdur Turkey Kaan Peksen
Energy used in Burdur Turkey Kaan Peksenberfinim
 
Offshore Wind Power Experiences Potential And Key Issues For Deployment
Offshore Wind Power Experiences Potential And Key Issues For DeploymentOffshore Wind Power Experiences Potential And Key Issues For Deployment
Offshore Wind Power Experiences Potential And Key Issues For DeploymentGlenn Klith Andersen
 
Electricity & Water Demand Forecast 2009 - 2030
Electricity & Water DemandForecast 2009 - 2030Electricity & Water DemandForecast 2009 - 2030
Electricity & Water Demand Forecast 2009 - 2030mubarak2009
 
Eoi – uganda epc assignments for kikagati hydro power project uganda – 12 ...
Eoi – uganda   epc assignments for kikagati hydro power project  uganda – 12 ...Eoi – uganda   epc assignments for kikagati hydro power project  uganda – 12 ...
Eoi – uganda epc assignments for kikagati hydro power project uganda – 12 ...Josue Tandoum Waffo
 
Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )Gurparvesh kaur
 
Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Brittany Maxwell
 
VIETNAM – SOLAR POWER SECTOR NEW MODEL PPA FOR ROOFTOP SOLAR POWER PROJECTS
VIETNAM – SOLAR POWER SECTOR NEW MODEL PPA FOR ROOFTOP SOLAR POWER PROJECTSVIETNAM – SOLAR POWER SECTOR NEW MODEL PPA FOR ROOFTOP SOLAR POWER PROJECTS
VIETNAM – SOLAR POWER SECTOR NEW MODEL PPA FOR ROOFTOP SOLAR POWER PROJECTSDr. Oliver Massmann
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Portfolio (Sunil Basnet )
Portfolio (Sunil Basnet )Portfolio (Sunil Basnet )
Portfolio (Sunil Basnet )tensab_linus419
 
nisource Statistical Summary Book 2007
nisource Statistical Summary Book 2007nisource Statistical Summary Book 2007
nisource Statistical Summary Book 2007finance29
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Crosstown TO
 
Presentation Jacques Vandermeiren at Trends Lunch
Presentation Jacques Vandermeiren at Trends LunchPresentation Jacques Vandermeiren at Trends Lunch
Presentation Jacques Vandermeiren at Trends LunchElia
 

What's hot (20)

BAZYAN CCPP – Phase 1
BAZYAN CCPP – Phase 1BAZYAN CCPP – Phase 1
BAZYAN CCPP – Phase 1
 
Page6 Pembroke
Page6 PembrokePage6 Pembroke
Page6 Pembroke
 
Energy used in Burdur Turkey Kaan Peksen
Energy used in Burdur Turkey Kaan PeksenEnergy used in Burdur Turkey Kaan Peksen
Energy used in Burdur Turkey Kaan Peksen
 
Welcome
WelcomeWelcome
Welcome
 
Offshore Wind Power Experiences Potential And Key Issues For Deployment
Offshore Wind Power Experiences Potential And Key Issues For DeploymentOffshore Wind Power Experiences Potential And Key Issues For Deployment
Offshore Wind Power Experiences Potential And Key Issues For Deployment
 
Gas power-infrastructure
Gas power-infrastructureGas power-infrastructure
Gas power-infrastructure
 
Electricity & Water Demand Forecast 2009 - 2030
Electricity & Water DemandForecast 2009 - 2030Electricity & Water DemandForecast 2009 - 2030
Electricity & Water Demand Forecast 2009 - 2030
 
Eoi – uganda epc assignments for kikagati hydro power project uganda – 12 ...
Eoi – uganda   epc assignments for kikagati hydro power project  uganda – 12 ...Eoi – uganda   epc assignments for kikagati hydro power project  uganda – 12 ...
Eoi – uganda epc assignments for kikagati hydro power project uganda – 12 ...
 
Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )
 
Electromech
Electromech Electromech
Electromech
 
Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018
 
Firepumpdesignintent4.01
Firepumpdesignintent4.01Firepumpdesignintent4.01
Firepumpdesignintent4.01
 
VIETNAM – SOLAR POWER SECTOR NEW MODEL PPA FOR ROOFTOP SOLAR POWER PROJECTS
VIETNAM – SOLAR POWER SECTOR NEW MODEL PPA FOR ROOFTOP SOLAR POWER PROJECTSVIETNAM – SOLAR POWER SECTOR NEW MODEL PPA FOR ROOFTOP SOLAR POWER PROJECTS
VIETNAM – SOLAR POWER SECTOR NEW MODEL PPA FOR ROOFTOP SOLAR POWER PROJECTS
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
 
Portfolio (Sunil Basnet )
Portfolio (Sunil Basnet )Portfolio (Sunil Basnet )
Portfolio (Sunil Basnet )
 
nisource Statistical Summary Book 2007
nisource Statistical Summary Book 2007nisource Statistical Summary Book 2007
nisource Statistical Summary Book 2007
 
WQ-2
WQ-2WQ-2
WQ-2
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
 
Wapda internship report
Wapda internship reportWapda internship report
Wapda internship report
 
Presentation Jacques Vandermeiren at Trends Lunch
Presentation Jacques Vandermeiren at Trends LunchPresentation Jacques Vandermeiren at Trends Lunch
Presentation Jacques Vandermeiren at Trends Lunch
 

Viewers also liked

Shanahan Engineering Presentation
Shanahan Engineering PresentationShanahan Engineering Presentation
Shanahan Engineering Presentationshanahaneng
 
Detailed design of portal frames
Detailed design of portal framesDetailed design of portal frames
Detailed design of portal frameskaran prabhakar
 
Portal Frame Construction & Pre Engineered Building System
Portal Frame Construction & Pre Engineered Building SystemPortal Frame Construction & Pre Engineered Building System
Portal Frame Construction & Pre Engineered Building SystemIan Toisa
 
Piping fundamentals bfl
Piping fundamentals bflPiping fundamentals bfl
Piping fundamentals bflMN Raghu
 
6 portal frames
6 portal frames6 portal frames
6 portal framesPrabhu mk
 
Operation and Maintenance of Diesel Power Generating Plants
Operation and Maintenance of Diesel Power Generating PlantsOperation and Maintenance of Diesel Power Generating Plants
Operation and Maintenance of Diesel Power Generating PlantsLiving Online
 
Valve types and selection
Valve types and selectionValve types and selection
Valve types and selectionMusa Sabri
 

Viewers also liked (10)

Shanahan Engineering Presentation
Shanahan Engineering PresentationShanahan Engineering Presentation
Shanahan Engineering Presentation
 
Pipe rack & rack piping
Pipe rack & rack pipingPipe rack & rack piping
Pipe rack & rack piping
 
Detailed design of portal frames
Detailed design of portal framesDetailed design of portal frames
Detailed design of portal frames
 
Portal Frame Construction & Pre Engineered Building System
Portal Frame Construction & Pre Engineered Building SystemPortal Frame Construction & Pre Engineered Building System
Portal Frame Construction & Pre Engineered Building System
 
Piping fundamentals bfl
Piping fundamentals bflPiping fundamentals bfl
Piping fundamentals bfl
 
6 portal frames
6 portal frames6 portal frames
6 portal frames
 
Operation and Maintenance of Diesel Power Generating Plants
Operation and Maintenance of Diesel Power Generating PlantsOperation and Maintenance of Diesel Power Generating Plants
Operation and Maintenance of Diesel Power Generating Plants
 
Valves ppt
Valves pptValves ppt
Valves ppt
 
Valve types and selection
Valve types and selectionValve types and selection
Valve types and selection
 
ORGANISATION STRUCTURES PPT
ORGANISATION STRUCTURES PPTORGANISATION STRUCTURES PPT
ORGANISATION STRUCTURES PPT
 

Similar to SUA presentation of the Power Generation Station Project

Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01Kiran Singh
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectascemiami-dade
 
Dominion Cove Point LNG Facility May 2016 Status Report
Dominion Cove Point LNG Facility May 2016 Status ReportDominion Cove Point LNG Facility May 2016 Status Report
Dominion Cove Point LNG Facility May 2016 Status ReportMarcellus Drilling News
 
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)Andrew Gelston
 
Tom's Resume 9-1-16
Tom's Resume 9-1-16Tom's Resume 9-1-16
Tom's Resume 9-1-16Tom Coughlin
 
CV_ Sayantan Ghosh_B.Tech_Electrical
CV_ Sayantan Ghosh_B.Tech_ElectricalCV_ Sayantan Ghosh_B.Tech_Electrical
CV_ Sayantan Ghosh_B.Tech_ElectricalSAYANTAN GHOSH
 
CV_ Sayantan Ghosh_B.Tech_Electrical
CV_ Sayantan Ghosh_B.Tech_ElectricalCV_ Sayantan Ghosh_B.Tech_Electrical
CV_ Sayantan Ghosh_B.Tech_ElectricalSAYANTAN GHOSH
 
PVN SOQ Presentation 2016 Final
PVN SOQ Presentation 2016 FinalPVN SOQ Presentation 2016 Final
PVN SOQ Presentation 2016 FinalRobert Potter
 
Copy of BhaskarSarkar_AECOM
Copy of BhaskarSarkar_AECOMCopy of BhaskarSarkar_AECOM
Copy of BhaskarSarkar_AECOMB SARKAR
 
Merrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectMerrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectFairfax County
 
Electric Vehicle Charing Stations
Electric Vehicle Charing StationsElectric Vehicle Charing Stations
Electric Vehicle Charing Stationsfairlingtonmeadows
 
Municipalization Overview
Municipalization OverviewMunicipalization Overview
Municipalization OverviewEmily Sandoval
 
Muhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo - COST OF PROJECTSMuhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo - COST OF PROJECTSMuhammad Faisal Wattoo
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects UpdateTownofAddison
 

Similar to SUA presentation of the Power Generation Station Project (20)

Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01
 
Guide to Solar Project Implementation
Guide to Solar Project ImplementationGuide to Solar Project Implementation
Guide to Solar Project Implementation
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
 
Dominion Cove Point LNG Facility May 2016 Status Report
Dominion Cove Point LNG Facility May 2016 Status ReportDominion Cove Point LNG Facility May 2016 Status Report
Dominion Cove Point LNG Facility May 2016 Status Report
 
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
 
Tom's Resume 9-1-16
Tom's Resume 9-1-16Tom's Resume 9-1-16
Tom's Resume 9-1-16
 
CV_ Sayantan Ghosh_B.Tech_Electrical
CV_ Sayantan Ghosh_B.Tech_ElectricalCV_ Sayantan Ghosh_B.Tech_Electrical
CV_ Sayantan Ghosh_B.Tech_Electrical
 
CV_ Sayantan Ghosh_B.Tech_Electrical
CV_ Sayantan Ghosh_B.Tech_ElectricalCV_ Sayantan Ghosh_B.Tech_Electrical
CV_ Sayantan Ghosh_B.Tech_Electrical
 
PVN SOQ Presentation 2016 Final
PVN SOQ Presentation 2016 FinalPVN SOQ Presentation 2016 Final
PVN SOQ Presentation 2016 Final
 
Copy of BhaskarSarkar_AECOM
Copy of BhaskarSarkar_AECOMCopy of BhaskarSarkar_AECOM
Copy of BhaskarSarkar_AECOM
 
ramakant_23.9.2016 (1)
ramakant_23.9.2016 (1)ramakant_23.9.2016 (1)
ramakant_23.9.2016 (1)
 
Wind Power EPCM
Wind Power EPCMWind Power EPCM
Wind Power EPCM
 
PECL PROJECTS
PECL PROJECTSPECL PROJECTS
PECL PROJECTS
 
 
Merrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectMerrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation Project
 
Electric Vehicle Charing Stations
Electric Vehicle Charing StationsElectric Vehicle Charing Stations
Electric Vehicle Charing Stations
 
Municipalization Overview
Municipalization OverviewMunicipalization Overview
Municipalization Overview
 
Muhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo - COST OF PROJECTSMuhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo - COST OF PROJECTS
 
Resume C Brewer
Resume C BrewerResume C Brewer
Resume C Brewer
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 

More from City of Stillwater

Sales, Use & Hotel/Motel Tax Report | May 2019
Sales, Use & Hotel/Motel Tax Report | May 2019 Sales, Use & Hotel/Motel Tax Report | May 2019
Sales, Use & Hotel/Motel Tax Report | May 2019 City of Stillwater
 
Sales, Use & Hotel/Motel Tax Report | April 2019
Sales, Use & Hotel/Motel Tax Report | April 2019Sales, Use & Hotel/Motel Tax Report | April 2019
Sales, Use & Hotel/Motel Tax Report | April 2019City of Stillwater
 
Sales, Use & Hotel/Motel Tax Report | March 2019
Sales, Use & Hotel/Motel Tax Report | March 2019 Sales, Use & Hotel/Motel Tax Report | March 2019
Sales, Use & Hotel/Motel Tax Report | March 2019 City of Stillwater
 
Form Based Code Warrant: 911 W. 5th Avenue
Form Based Code Warrant: 911 W. 5th AvenueForm Based Code Warrant: 911 W. 5th Avenue
Form Based Code Warrant: 911 W. 5th AvenueCity of Stillwater
 
Specific Use Permit: 115 S. Main Street
Specific Use Permit: 115 S. Main StreetSpecific Use Permit: 115 S. Main Street
Specific Use Permit: 115 S. Main StreetCity of Stillwater
 
Preliminary Plat: Baymere Addition
Preliminary Plat: Baymere AdditionPreliminary Plat: Baymere Addition
Preliminary Plat: Baymere AdditionCity of Stillwater
 
Sales, Use & Hotel/Motel Tax Report | February 2019
Sales, Use & Hotel/Motel Tax Report | February 2019 Sales, Use & Hotel/Motel Tax Report | February 2019
Sales, Use & Hotel/Motel Tax Report | February 2019 City of Stillwater
 
Sales, Use & Hotel/Motel Tax Report | January 2019
Sales, Use & Hotel/Motel Tax Report | January 2019Sales, Use & Hotel/Motel Tax Report | January 2019
Sales, Use & Hotel/Motel Tax Report | January 2019City of Stillwater
 
Sales, Use & Hotel/Motel Tax Report | November 2018
Sales, Use & Hotel/Motel Tax Report | November 2018 Sales, Use & Hotel/Motel Tax Report | November 2018
Sales, Use & Hotel/Motel Tax Report | November 2018 City of Stillwater
 
Sales, Use & Hotel/Motel Tax Report | October 2018
Sales, Use & Hotel/Motel Tax Report | October 2018 Sales, Use & Hotel/Motel Tax Report | October 2018
Sales, Use & Hotel/Motel Tax Report | October 2018 City of Stillwater
 
Sales, Use & Hotel/Motel Tax Report | September 2018
Sales, Use & Hotel/Motel Tax Report | September 2018Sales, Use & Hotel/Motel Tax Report | September 2018
Sales, Use & Hotel/Motel Tax Report | September 2018City of Stillwater
 
Sales, Use & Hotel/Motel Tax Report | August 2018
Sales, Use & Hotel/Motel Tax Report | August 2018  Sales, Use & Hotel/Motel Tax Report | August 2018
Sales, Use & Hotel/Motel Tax Report | August 2018 City of Stillwater
 
City of Stillwater Commercial Projects 2016–2017
City of Stillwater Commercial Projects 2016–2017 City of Stillwater Commercial Projects 2016–2017
City of Stillwater Commercial Projects 2016–2017 City of Stillwater
 
Block 34 Task Force Presentation (Stillwater City Council Meeting / Jan. 9, 2...
Block 34 Task Force Presentation (Stillwater City Council Meeting / Jan. 9, 2...Block 34 Task Force Presentation (Stillwater City Council Meeting / Jan. 9, 2...
Block 34 Task Force Presentation (Stillwater City Council Meeting / Jan. 9, 2...City of Stillwater
 
12th Avenue Land Use Plan Introductory Meeting Presentation
12th Avenue Land Use Plan Introductory Meeting Presentation12th Avenue Land Use Plan Introductory Meeting Presentation
12th Avenue Land Use Plan Introductory Meeting PresentationCity of Stillwater
 
City of Stillwater Commercial Projects 2016
City of Stillwater Commercial Projects 2016City of Stillwater Commercial Projects 2016
City of Stillwater Commercial Projects 2016City of Stillwater
 
City of Stillwater Commercial Projects 2015
City of Stillwater Commercial Projects 2015City of Stillwater Commercial Projects 2015
City of Stillwater Commercial Projects 2015City of Stillwater
 
Commercial projects update, 2010 thru April 2014
Commercial projects update, 2010 thru April 2014Commercial projects update, 2010 thru April 2014
Commercial projects update, 2010 thru April 2014City of Stillwater
 
Bond 2013 - Project Renderings and Sketches
Bond 2013 - Project Renderings and SketchesBond 2013 - Project Renderings and Sketches
Bond 2013 - Project Renderings and SketchesCity of Stillwater
 

More from City of Stillwater (20)

Sales, Use & Hotel/Motel Tax Report | May 2019
Sales, Use & Hotel/Motel Tax Report | May 2019 Sales, Use & Hotel/Motel Tax Report | May 2019
Sales, Use & Hotel/Motel Tax Report | May 2019
 
Sales, Use & Hotel/Motel Tax Report | April 2019
Sales, Use & Hotel/Motel Tax Report | April 2019Sales, Use & Hotel/Motel Tax Report | April 2019
Sales, Use & Hotel/Motel Tax Report | April 2019
 
Sales, Use & Hotel/Motel Tax Report | March 2019
Sales, Use & Hotel/Motel Tax Report | March 2019 Sales, Use & Hotel/Motel Tax Report | March 2019
Sales, Use & Hotel/Motel Tax Report | March 2019
 
Form Based Code Warrant: 911 W. 5th Avenue
Form Based Code Warrant: 911 W. 5th AvenueForm Based Code Warrant: 911 W. 5th Avenue
Form Based Code Warrant: 911 W. 5th Avenue
 
Specific Use Permit: 115 S. Main Street
Specific Use Permit: 115 S. Main StreetSpecific Use Permit: 115 S. Main Street
Specific Use Permit: 115 S. Main Street
 
Preliminary Plat: Baymere Addition
Preliminary Plat: Baymere AdditionPreliminary Plat: Baymere Addition
Preliminary Plat: Baymere Addition
 
Sales, Use & Hotel/Motel Tax Report | February 2019
Sales, Use & Hotel/Motel Tax Report | February 2019 Sales, Use & Hotel/Motel Tax Report | February 2019
Sales, Use & Hotel/Motel Tax Report | February 2019
 
Sales, Use & Hotel/Motel Tax Report | January 2019
Sales, Use & Hotel/Motel Tax Report | January 2019Sales, Use & Hotel/Motel Tax Report | January 2019
Sales, Use & Hotel/Motel Tax Report | January 2019
 
Sales, Use & Hotel/Motel Tax Report | November 2018
Sales, Use & Hotel/Motel Tax Report | November 2018 Sales, Use & Hotel/Motel Tax Report | November 2018
Sales, Use & Hotel/Motel Tax Report | November 2018
 
Sales, Use & Hotel/Motel Tax Report | October 2018
Sales, Use & Hotel/Motel Tax Report | October 2018 Sales, Use & Hotel/Motel Tax Report | October 2018
Sales, Use & Hotel/Motel Tax Report | October 2018
 
Sales, Use & Hotel/Motel Tax Report | September 2018
Sales, Use & Hotel/Motel Tax Report | September 2018Sales, Use & Hotel/Motel Tax Report | September 2018
Sales, Use & Hotel/Motel Tax Report | September 2018
 
Sales, Use & Hotel/Motel Tax Report | August 2018
Sales, Use & Hotel/Motel Tax Report | August 2018  Sales, Use & Hotel/Motel Tax Report | August 2018
Sales, Use & Hotel/Motel Tax Report | August 2018
 
City of Stillwater Commercial Projects 2016–2017
City of Stillwater Commercial Projects 2016–2017 City of Stillwater Commercial Projects 2016–2017
City of Stillwater Commercial Projects 2016–2017
 
Block 34 Task Force Presentation (Stillwater City Council Meeting / Jan. 9, 2...
Block 34 Task Force Presentation (Stillwater City Council Meeting / Jan. 9, 2...Block 34 Task Force Presentation (Stillwater City Council Meeting / Jan. 9, 2...
Block 34 Task Force Presentation (Stillwater City Council Meeting / Jan. 9, 2...
 
12th Avenue Land Use Plan Introductory Meeting Presentation
12th Avenue Land Use Plan Introductory Meeting Presentation12th Avenue Land Use Plan Introductory Meeting Presentation
12th Avenue Land Use Plan Introductory Meeting Presentation
 
City of Stillwater Commercial Projects 2016
City of Stillwater Commercial Projects 2016City of Stillwater Commercial Projects 2016
City of Stillwater Commercial Projects 2016
 
City of Stillwater Commercial Projects 2015
City of Stillwater Commercial Projects 2015City of Stillwater Commercial Projects 2015
City of Stillwater Commercial Projects 2015
 
Complete Streets Presentation
Complete Streets PresentationComplete Streets Presentation
Complete Streets Presentation
 
Commercial projects update, 2010 thru April 2014
Commercial projects update, 2010 thru April 2014Commercial projects update, 2010 thru April 2014
Commercial projects update, 2010 thru April 2014
 
Bond 2013 - Project Renderings and Sketches
Bond 2013 - Project Renderings and SketchesBond 2013 - Project Renderings and Sketches
Bond 2013 - Project Renderings and Sketches
 

Recently uploaded

Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...anilsa9823
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...ResolutionFoundation
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.Christina Parmionova
 
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Roomishabajaj13
 
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...Suhani Kapoor
 
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceHigh Profile Call Girls
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28JSchaus & Associates
 
(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Christina Parmionova
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at workChristina Parmionova
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...Hemant Purohit
 
VIP Call Girls Pune Vani 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Vani 8617697112 Independent Escort Service PuneVIP Call Girls Pune Vani 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Vani 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginningsinfo695895
 
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 

Recently uploaded (20)

Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.
 
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
 
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
 
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
 
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28
 
(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at work
 
How to Save a Place: 12 Tips To Research & Know the Threat
How to Save a Place: 12 Tips To Research & Know the ThreatHow to Save a Place: 12 Tips To Research & Know the Threat
How to Save a Place: 12 Tips To Research & Know the Threat
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
 
VIP Call Girls Pune Vani 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Vani 8617697112 Independent Escort Service PuneVIP Call Girls Pune Vani 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Vani 8617697112 Independent Escort Service Pune
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
 
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
 

SUA presentation of the Power Generation Station Project

  • 1. POWER GENERATION STATION (PGS) Project Update / March 23, 2015 Loren Smith Generation and Transmission Division Manager
  • 2. History of the SEU Stillwater is the 2nd largest municipally owned electric utility in Oklahoma and the largest municipal electric generator in the State. Stillwater has owned its Electric Utility since 1901 and began generation of it’s own electricity in 1903.
  • 4. Feasibility Analysis 1. Rebuild Boomer Lake Station 2. Build a new State of the Art Generation Facility 3. Get out of the generation business Was it economically feasible to build generation in the City of Stillwater?
  • 5. GRDA Contract August 5, 2013 Stillwater Trustees approved the wholesale purchase power contract. Following signing of contract Stillwater Trustees authorized staff to: • Enter into a formal professional services agreement with Burns & McDonnell • Complete the land exchange with the Commissioners of the Land Office • Work with JP Morgan on the bond underwriting for the project
  • 6. PGS Project Overview Final approval received on June 2, 2014 3- 25,000 horse power natural gas fired reciprocating engine/generators 56 MW Output Control Room/Admin. Maintenance Facilities New electrical Transmission and Distribution substation.
  • 7.
  • 8. Procurement Status • The total project cost is estimated at just under $70 million • The total project will have 34 procurement packages/bids – Included: equipment, materials, construction, and services necessary to construct the facility • To date 17 of the 34 bids have been released – Trustees have approved bid recommendations on 9 of them – Others are still out for bid or are in the evaluation process • To date we have, or are in the process of finalizing, equipment and services contracts that total approximately $38.5 million • We are estimating that for the equipment/services currently under contract that we are approximately $4.4 million under budget
  • 9.
  • 10. Variables out of our control Construction Construction scheduled to begin July 2015 Tentative Commercial Operation date June 30, 2016 ODEQ air permit Weather ONG pipeline
  • 11. • Site Prep Design • Underground Utilities Design • Final Grading and Drainage Plan • Site Finishes Design • Power Generation Building Foundation Design • Admin Building Foundation Design • Major Equipment Foundation Design • Miscellaneous Foundation Design • Exhaust Duct Drawings • Plant Steel Erection Drawings • Preliminary P&IDs • Equipment Layouts • Motor List • Fire Protection Design • Under-slab Utilities Engineering Status • Engine Hall Piping Design • Maintenance Area Piping Design • Plant Electrical One-Lines • Underground Duct Bank Design • Underground Grounding Grid • Electrical Equipment Layouts • LV and MV Switchgear Schematics • Wartsila Communications Design • Control Room Layout • I/O Design • Substation Foundation Plan View • Substation Steel Drawings • Steel Calculations • Substation Above Ground • Substation Switchgear Building Layout
  • 12. Water Line Project Natural Gas Line Project ODEQ – Title V Air Permit Fiber optic communication to the New Power Generation Station 69,000 Volt transmission system improvements Southwest Power Pool (SPP) registration GRDA communication connection to the new PGS City of Stillwater Use By Right permit application Off-Site Projects & Permitting
  • 13. All projects are expected to be completed by the commercial operation date of June 30, 2016. At this time the PGS project, and the parallel projects are on schedule and under budget. Project Completion