SlideShare a Scribd company logo
Caledonia Clean Energy Project
Update
Stephen Kerr
CCEP Project Director
UKCCSRC Autumn Biannual Meeting
University of Strathclyde • 8-9 September 2015
• Over 25 years experience on renewable energy, oil & gas
and construction projects - UK and international
• 15 years working in renewable energy sector
• Most recently led Inch Cape Offshore Wind Farm
development (up to 780MW east coast of Scotland)
through concept, EIA, S36 consent and CfD application;
2009 - 2015
• Based in Edinburgh
1
Stephen Kerr - Introduction
• 25-year old U.S. developer of clean-energy power plants
• Founded by Donald Paul Hodel (former Secretary of
Energy & Secretary of the Interior) and Earl Gjelde (No. 2
official at Energy & Interior)
• Traditional focus: wind, solar, and state-of-the-art
combined cycle natural gas-fired power plants
• Focus now: power plants w/ CO2 capture & sequestration
• Our new CEO Jason Crew headed GE’s gasification unit
• Currently working on (1) two large gasification projects
with 90+% CO2 pre-combustion capture, and (2) retrofits
of coal & gas-fired plants for post-combustion CO2 capture
2
Summit Power Group
• Texas Clean Energy Project (TCEP) is in the financing stage
and ready to start construction, once contracts are final
• Caledonia Clean Energy Project (CCEP): much earlier stage
• CCEP is a sister project to TCEP; this has many advantages
• These two gasification power projects have in common:
– Commercial-scale power plants with 90+ percent CO2 capture
– No new technology – what’s new is integrating proven systems
– Siemens gasifiers & Siemens high-hydrogen combustion turbines
– Lead EPC contractor is Chinese company with key experience
– Export-Import Bank of China is the expected project lender
– Both projects should be attractive to equity investors
3
Two Summit CCS Projects:
Texas & Scotland
• 400+ MW “polygen” gasification plant to produce power,
urea (fertilizer), and captured CO2 (90+% from coal) for EOR
• Located atop Permian Basin oilfields: CO2 pipeline will be
~1 km long, connecting to Kinder-Morgan pipeline system
• Largest award ($450M) in U.S. DOE’s Clean Coal Power
Initiative, plus $100s of millions in special tax credits
• China Huanqiu Contracting & Engineering Corp. (HQC) is
lead EPC contractor; China Ex-Im Bank will be lead lender
• Challenge through 2014/15 was to optimize plant / reduce
cost
• Finalizing EPC contracts this month; financing commencing
4
TCEP Overview
TCEP Schematic Diagram
Coal Coal Gasification,
Gas Cleanup, and
Gas Separation
Water
Syngas
Syngas
Main Outputs “High
Hydrogen” Syngas
(~95% H2 / 5% CO) &
Pure CO2
CO2
CO2
Ammonia / Urea
Complex
CO2 Delivered to Oil
Fields via Pipeline
~195 MW ultra low
carbon power
to San Antonio
from high-hydrogen
combustion turbine
in combined cycle
~750,000
tons/yr of urea
delivered to
major fertilizer
company
~2 mm tons per
year delivered
to Oil Producers
Brackish Water
Purified via Reverse
Osmosis
Oxygen
Air Separation Unit
* Additional revenue from sales of sulfuric acid, argon gas, & minor
products
5
• 570MW gasification plant w ~ 94% CO2 capture from coal
• Different balance to TCEP, optimized for power output
• Site is at Grangemouth, on Firth of Forth, near Edinburgh
• On- & off-shore CO2 transport infrastructure largely exists
• One of four (4) finalist projects in UK’s CCS Competition,
but not one of the two (2) Competition projects chosen
• CCEP is a “Phase 2” project (per DECC Policy Scoping
Document, Aug 2014) seeking clustered projects to help
initiate CO2/EOR sector
• With our debt structure, CCEP doesn’t need a capital grant
from DECC: just a Contract for Difference (CfD)
6
CCEP - Overview
CCEP CO2 Chain
7
St Fergus CO2 Hub
Caledonia
IGCC
UK
coal
Atlantic pipeline
• Second of a kind IGCC Plant following Texas Clean Energy Project (TCEP)
• 570MW low carbon electricity for a million UK homes
• 3.8 Mt/yr CO2 Captured – Over 90%
• Re-use of existing pipeline systems
• Linking Central Scotland with the Central North Sea
• Storage in proven offshore saline formation
• High security: subsea development (no platform)
• EOR Ready: Independent of Oil Company decision
• Emitter Cluster and Sink Cluster
• Development of St Fergus as a CO2 Hub
78km offshore
Northern UK
Emissions Cluster
Future CO2 Import to
Peterhead Harbour
Injection into proven
saline formation
under a depleted gas
field
IGCC Plant Grangemouth
8
Raw Coal Storage
Coal Milling
and Drying
Siemens Gasification
Island
AirSeparation
Unit
Low Temp Gas
Cooling,
Water/Gas Shift
& Hg Removal
SourWater
Stripper
Sulphuric
AcidPlant
Rectisol
WashUnit
CO2
Compression
Waste Water
Treatment
Flare
Black
Water
Plant
Power Plant
Gas and Steam
Siemens
SST5-5000
Steam
Turbine
Siemens
SGT5-
8000H Gas
Turbine
Heat Recovery Steam
Generator
Parking
Office
Rail Head Coal Delivery
Onshore Transportion
9
• Onshore transport through connection to existing
Feeder 10 Pipeline is planned (in talks w Nat’l Grid)
• Existing natural gas pipeline can be repurposed for CO2
transport
• A FEED study was completed during DEMO 1
(Longannet) process
• Excess capacity may be used to transport other CO2
eventually
34
Tunnel or HDD
Tunnel or HDD
Tunnel
HDD or Cofferdam
(open cut)
Tunnel or HDD
OPTION 1 (exit West)
OPTION 2 (exit South)
Planned Work Programme
• Currently finalising Grant Agreement, organisation and resources;
– Work Package 1: Industrial research and development, resulting in the
preliminary design and notional pricing of CCEP.
– Work Package 2: Feasibility study of requirements, constraints and
mitigation including grid connection, planning and regulatory requirements,
and financing considerations.
– Work Package 3: Obtain required site options and/or exclusivity
agreement(s) as project enablers
• 18 month programme, budget ≈ £6.0M, grant ≈ £4.2M
• Front loading important to de-risk project
10
Onshore
Transportation
Permitting
Technical
Economics
Finance
Commercial
Offshore
11
CCEP – What We Need
• Policy stability, Development Risk, Phase
1 projects moving into Phase 2 projects,
Investor Confidence
• CO2 chain physical interfaces, electrical
grid connection, knowledge sharing, cost
reduction, shared infrastructure,
complex commercial interfaces
• Political, public & local community
support, dedicated CfD budget and
mechanism
Continuity
Collaboration
Support
Long Term - Opportunity
• CCEP as anchor for sustained effort to develop an entire
integrated system, consisting of:
– Clustered CO2 capture projects (not just one project),
– Sharing a common CO2 pipeline and offshore infrastructure,
– To produce low-carbon electric power to replace the UK’s coal
plants (which are slated for closure within 15 years), and
– To store carbon in depleted North Sea gas fields and saline
formations, while also
– Creating a CO2 for enhanced oil recovery (EOR) sector in the
North Sea, with its own secure geological storage of CO2
12
• Sources of captured CO2:
– Peterhead Project: capture from natural gas, for 10 years or more
– Caledonia #1 (a/k/a Grangemouth A): capture from gasified coal
– Caledonia #2 (power plant) and/or capture from industrial sources
– Possible marine terminal to receive added CO2 from Europe by ship
• Onshore CO2 transport: National Grid’s Feeder No. 10 line
– Caledonia #1 & #2 would leave room for industrial CCS sources as
well, all using common infrastructure
• Offshore CO2 transport: existing + some new pipelines
• Offshore CO2 stores (providing the needed multiple sinks):
– Goldeneye (depleted gas field, existing platform & infrastructure)
– Suitable oilfields (with existing & new infrastructure for CO2/EOR)
– Saline formation underlying Goldeneye, if needed
13
Long Term : Physical Components
• “Single source, single sink” should be avoided; multiple
sources & sinks is the right way to do CCS where possible
• Use of a common CO2 transport & storage infrastructure
will significantly reduce costs of CCS (including from
industrial sources)
• Environmental benefits: ~ 10 million tons/year of CO2
sequestered, plus ≈ 1,500 MW of ultra low-carbon power
if Central Scotland opportunity is fully developed
• Major employment & economic development benefits
• UK leadership potential in CCUS & cooperation with China
14
Long Term - Benefits
15
Thank you
Contact information:
• Stephen Kerr, CCEP Project Director:
skerr@caledoniacleanenergyproject.com
• Jason Crew, CEO:
jcrew@summitpower.com
• Eric Redman, Co-Chairman:
eredman@summitpower.com
www.summitpower.com

More Related Content

What's hot

Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...
Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...
Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...
Global CCS Institute
 
CCS for Gas-Fired Power Plants presented at the MIT Carbon Sequestration Foru...
CCS for Gas-Fired Power Plants presented at the MIT Carbon Sequestration Foru...CCS for Gas-Fired Power Plants presented at the MIT Carbon Sequestration Foru...
CCS for Gas-Fired Power Plants presented at the MIT Carbon Sequestration Foru...
UK Carbon Capture and Storage Research Centre
 
TOGS2012-RiversideEnergy
TOGS2012-RiversideEnergyTOGS2012-RiversideEnergy
TOGS2012-RiversideEnergyDawn Hendrick
 
Development of Carbon Capture, Utilization, and Storage (CCUS) in the United ...
Development of Carbon Capture, Utilization, and Storage (CCUS) in the United ...Development of Carbon Capture, Utilization, and Storage (CCUS) in the United ...
Development of Carbon Capture, Utilization, and Storage (CCUS) in the United ...
Economic Research Institute for ASEAN and East Asia
 
CCS learnings from the LNG sector
CCS learnings from the LNG sectorCCS learnings from the LNG sector
CCS learnings from the LNG sector
Global CCS Institute
 
7th study meeting Tokyo - Holger Bietz
7th study meeting Tokyo - Holger Bietz7th study meeting Tokyo - Holger Bietz
7th study meeting Tokyo - Holger Bietz
Global CCS Institute
 
ION Engineering Presentation
ION Engineering PresentationION Engineering Presentation
ION Engineering Presentation
Global CCS Institute
 
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCSDecarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Global CCS Institute
 
Poyry - UK Shale Gas - where are we now? - Point of View
Poyry - UK Shale Gas - where are we now? - Point of ViewPoyry - UK Shale Gas - where are we now? - Point of View
Poyry - UK Shale Gas - where are we now? - Point of View
Pöyry
 
2 co making the business case for ccs
2 co   making the business case for ccs2 co   making the business case for ccs
2 co making the business case for ccsGlobal CCS Institute
 
Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project
Global CCS Institute
 
Séminaire: Wind energy | Technifutur - 22 juin 2017
Séminaire: Wind energy | Technifutur - 22 juin 2017Séminaire: Wind energy | Technifutur - 22 juin 2017
Séminaire: Wind energy | Technifutur - 22 juin 2017
Cluster TWEED
 
Working On Australias Largest CSG to LNG Project
Working On Australias Largest CSG to LNG ProjectWorking On Australias Largest CSG to LNG Project
Working On Australias Largest CSG to LNG Project
bwlogue
 
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Global CCS Institute
 
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Global CCS Institute
 
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage ProjectPaul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Global CCS Institute
 
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Global CCS Institute
 
Research Coordination Network on Carbon Capture, Utilization and Storage Fund...
Research Coordination Network on Carbon Capture, Utilization and Storage Fund...Research Coordination Network on Carbon Capture, Utilization and Storage Fund...
Research Coordination Network on Carbon Capture, Utilization and Storage Fund...
UK Carbon Capture and Storage Research Centre
 
White Rose CCS Project - plenary presentation by Don Reid at the UKCCSRC Card...
White Rose CCS Project - plenary presentation by Don Reid at the UKCCSRC Card...White Rose CCS Project - plenary presentation by Don Reid at the UKCCSRC Card...
White Rose CCS Project - plenary presentation by Don Reid at the UKCCSRC Card...
UK Carbon Capture and Storage Research Centre
 

What's hot (20)

Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...
Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...
Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...
 
CCS for Gas-Fired Power Plants presented at the MIT Carbon Sequestration Foru...
CCS for Gas-Fired Power Plants presented at the MIT Carbon Sequestration Foru...CCS for Gas-Fired Power Plants presented at the MIT Carbon Sequestration Foru...
CCS for Gas-Fired Power Plants presented at the MIT Carbon Sequestration Foru...
 
TOGS2012-RiversideEnergy
TOGS2012-RiversideEnergyTOGS2012-RiversideEnergy
TOGS2012-RiversideEnergy
 
Development of Carbon Capture, Utilization, and Storage (CCUS) in the United ...
Development of Carbon Capture, Utilization, and Storage (CCUS) in the United ...Development of Carbon Capture, Utilization, and Storage (CCUS) in the United ...
Development of Carbon Capture, Utilization, and Storage (CCUS) in the United ...
 
CCS learnings from the LNG sector
CCS learnings from the LNG sectorCCS learnings from the LNG sector
CCS learnings from the LNG sector
 
7th study meeting Tokyo - Holger Bietz
7th study meeting Tokyo - Holger Bietz7th study meeting Tokyo - Holger Bietz
7th study meeting Tokyo - Holger Bietz
 
ION Engineering Presentation
ION Engineering PresentationION Engineering Presentation
ION Engineering Presentation
 
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCSDecarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
 
Adnoc and masdar project may 2013
Adnoc and masdar project   may 2013Adnoc and masdar project   may 2013
Adnoc and masdar project may 2013
 
Poyry - UK Shale Gas - where are we now? - Point of View
Poyry - UK Shale Gas - where are we now? - Point of ViewPoyry - UK Shale Gas - where are we now? - Point of View
Poyry - UK Shale Gas - where are we now? - Point of View
 
2 co making the business case for ccs
2 co   making the business case for ccs2 co   making the business case for ccs
2 co making the business case for ccs
 
Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project
 
Séminaire: Wind energy | Technifutur - 22 juin 2017
Séminaire: Wind energy | Technifutur - 22 juin 2017Séminaire: Wind energy | Technifutur - 22 juin 2017
Séminaire: Wind energy | Technifutur - 22 juin 2017
 
Working On Australias Largest CSG to LNG Project
Working On Australias Largest CSG to LNG ProjectWorking On Australias Largest CSG to LNG Project
Working On Australias Largest CSG to LNG Project
 
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
 
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
 
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage ProjectPaul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
 
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
 
Research Coordination Network on Carbon Capture, Utilization and Storage Fund...
Research Coordination Network on Carbon Capture, Utilization and Storage Fund...Research Coordination Network on Carbon Capture, Utilization and Storage Fund...
Research Coordination Network on Carbon Capture, Utilization and Storage Fund...
 
White Rose CCS Project - plenary presentation by Don Reid at the UKCCSRC Card...
White Rose CCS Project - plenary presentation by Don Reid at the UKCCSRC Card...White Rose CCS Project - plenary presentation by Don Reid at the UKCCSRC Card...
White Rose CCS Project - plenary presentation by Don Reid at the UKCCSRC Card...
 

Similar to Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Biannual 8-9 September 2015

An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
UK Carbon Capture and Storage Research Centre
 
White Rose Carbon Capture and Storage Project
White Rose Carbon Capture and Storage ProjectWhite Rose Carbon Capture and Storage Project
White Rose Carbon Capture and Storage Project
Global CCS Institute
 
Update on CCS Activities in Canada and Possible Topics for European Collabora...
Update on CCS Activities in Canada and Possible Topics for European Collabora...Update on CCS Activities in Canada and Possible Topics for European Collabora...
Update on CCS Activities in Canada and Possible Topics for European Collabora...
UK Carbon Capture and Storage Research Centre
 
OLADE-Slide-Deck-compressed para ver.pdf
OLADE-Slide-Deck-compressed para ver.pdfOLADE-Slide-Deck-compressed para ver.pdf
OLADE-Slide-Deck-compressed para ver.pdf
HenryApaza12
 
Progressing CCS - Engineers Without Borders
Progressing CCS - Engineers Without BordersProgressing CCS - Engineers Without Borders
Progressing CCS - Engineers Without Borders
UK Carbon Capture and Storage Research Centre
 
Ccsstatusandopportunitiesdohanov12 121202220106-phpapp01
Ccsstatusandopportunitiesdohanov12 121202220106-phpapp01Ccsstatusandopportunitiesdohanov12 121202220106-phpapp01
Ccsstatusandopportunitiesdohanov12 121202220106-phpapp01
Sarim Dastgir
 
Gccsi japan members'_meeting_200613_tom-connor_aust_gov
Gccsi japan members'_meeting_200613_tom-connor_aust_govGccsi japan members'_meeting_200613_tom-connor_aust_gov
Gccsi japan members'_meeting_200613_tom-connor_aust_gov
Global CCS Institute
 
AN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTURE
AN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTUREAN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTURE
AN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTURE
iQHub
 
ELEMENTS OF A ROBUST CARBON CAPTURE, UTILIZATION, AND STORAGE BUSINESS MODEL
ELEMENTS OF A ROBUST CARBON CAPTURE, UTILIZATION, AND STORAGE BUSINESS MODELELEMENTS OF A ROBUST CARBON CAPTURE, UTILIZATION, AND STORAGE BUSINESS MODEL
ELEMENTS OF A ROBUST CARBON CAPTURE, UTILIZATION, AND STORAGE BUSINESS MODEL
iQHub
 
Carbon Capture and storage technologies around the world
Carbon Capture and storage technologies around the worldCarbon Capture and storage technologies around the world
Carbon Capture and storage technologies around the world
Ahmed Mohamed Khedr
 
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
atlanticcouncil
 
Economics of promotions_of_r&d_of_carbon_capture
Economics of promotions_of_r&d_of_carbon_captureEconomics of promotions_of_r&d_of_carbon_capture
Economics of promotions_of_r&d_of_carbon_captureSuresh Malluswamy
 
Atlantic Council - Darren Mollot
Atlantic Council - Darren MollotAtlantic Council - Darren Mollot
Atlantic Council - Darren Mollot
Global CCS Institute
 
The role of CCS/CCUS in the Climate Action Plan - Dr S. Julio Friedmann
The role of CCS/CCUS in the Climate Action Plan - Dr S. Julio FriedmannThe role of CCS/CCUS in the Climate Action Plan - Dr S. Julio Friedmann
The role of CCS/CCUS in the Climate Action Plan - Dr S. Julio Friedmann
Global CCS Institute
 
Supporting CCS deployment – an update from the UK Department of Energy and Cl...
Supporting CCS deployment – an update from the UK Department of Energy and Cl...Supporting CCS deployment – an update from the UK Department of Energy and Cl...
Supporting CCS deployment – an update from the UK Department of Energy and Cl...
Global CCS Institute
 
UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...
UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...
UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...
UK Carbon Capture and Storage Research Centre
 
Wayne Calder – Department of Resources, Energy and Tourism – CCS and carbon p...
Wayne Calder – Department of Resources, Energy and Tourism – CCS and carbon p...Wayne Calder – Department of Resources, Energy and Tourism – CCS and carbon p...
Wayne Calder – Department of Resources, Energy and Tourism – CCS and carbon p...
Global CCS Institute
 
Show and Tell - Heat.pdf
Show and Tell - Heat.pdfShow and Tell - Heat.pdf
Show and Tell - Heat.pdf
SIFOfgem
 

Similar to Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Biannual 8-9 September 2015 (20)

An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
 
White Rose Carbon Capture and Storage Project
White Rose Carbon Capture and Storage ProjectWhite Rose Carbon Capture and Storage Project
White Rose Carbon Capture and Storage Project
 
Update on CCS Activities in Canada and Possible Topics for European Collabora...
Update on CCS Activities in Canada and Possible Topics for European Collabora...Update on CCS Activities in Canada and Possible Topics for European Collabora...
Update on CCS Activities in Canada and Possible Topics for European Collabora...
 
OLADE-Slide-Deck-compressed para ver.pdf
OLADE-Slide-Deck-compressed para ver.pdfOLADE-Slide-Deck-compressed para ver.pdf
OLADE-Slide-Deck-compressed para ver.pdf
 
Progressing CCS - Engineers Without Borders
Progressing CCS - Engineers Without BordersProgressing CCS - Engineers Without Borders
Progressing CCS - Engineers Without Borders
 
Ccsstatusandopportunitiesdohanov12 121202220106-phpapp01
Ccsstatusandopportunitiesdohanov12 121202220106-phpapp01Ccsstatusandopportunitiesdohanov12 121202220106-phpapp01
Ccsstatusandopportunitiesdohanov12 121202220106-phpapp01
 
Gccsi japan members'_meeting_200613_tom-connor_aust_gov
Gccsi japan members'_meeting_200613_tom-connor_aust_govGccsi japan members'_meeting_200613_tom-connor_aust_gov
Gccsi japan members'_meeting_200613_tom-connor_aust_gov
 
AN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTURE
AN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTUREAN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTURE
AN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTURE
 
ELEMENTS OF A ROBUST CARBON CAPTURE, UTILIZATION, AND STORAGE BUSINESS MODEL
ELEMENTS OF A ROBUST CARBON CAPTURE, UTILIZATION, AND STORAGE BUSINESS MODELELEMENTS OF A ROBUST CARBON CAPTURE, UTILIZATION, AND STORAGE BUSINESS MODEL
ELEMENTS OF A ROBUST CARBON CAPTURE, UTILIZATION, AND STORAGE BUSINESS MODEL
 
Carbon Capture and storage technologies around the world
Carbon Capture and storage technologies around the worldCarbon Capture and storage technologies around the world
Carbon Capture and storage technologies around the world
 
Olivia Errey - FEED Secondments - Annual ECR Meeting London 23rd June 2015
Olivia Errey - FEED Secondments - Annual ECR Meeting London 23rd June 2015Olivia Errey - FEED Secondments - Annual ECR Meeting London 23rd June 2015
Olivia Errey - FEED Secondments - Annual ECR Meeting London 23rd June 2015
 
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
 
Economics of promotions_of_r&d_of_carbon_capture
Economics of promotions_of_r&d_of_carbon_captureEconomics of promotions_of_r&d_of_carbon_capture
Economics of promotions_of_r&d_of_carbon_capture
 
Atlantic Council - Darren Mollot
Atlantic Council - Darren MollotAtlantic Council - Darren Mollot
Atlantic Council - Darren Mollot
 
The role of CCS/CCUS in the Climate Action Plan - Dr S. Julio Friedmann
The role of CCS/CCUS in the Climate Action Plan - Dr S. Julio FriedmannThe role of CCS/CCUS in the Climate Action Plan - Dr S. Julio Friedmann
The role of CCS/CCUS in the Climate Action Plan - Dr S. Julio Friedmann
 
Supporting CCS deployment – an update from the UK Department of Energy and Cl...
Supporting CCS deployment – an update from the UK Department of Energy and Cl...Supporting CCS deployment – an update from the UK Department of Energy and Cl...
Supporting CCS deployment – an update from the UK Department of Energy and Cl...
 
UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...
UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...
UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...
 
Khursaniyah Project Brochure
Khursaniyah Project BrochureKhursaniyah Project Brochure
Khursaniyah Project Brochure
 
Wayne Calder – Department of Resources, Energy and Tourism – CCS and carbon p...
Wayne Calder – Department of Resources, Energy and Tourism – CCS and carbon p...Wayne Calder – Department of Resources, Energy and Tourism – CCS and carbon p...
Wayne Calder – Department of Resources, Energy and Tourism – CCS and carbon p...
 
Show and Tell - Heat.pdf
Show and Tell - Heat.pdfShow and Tell - Heat.pdf
Show and Tell - Heat.pdf
 

More from UK Carbon Capture and Storage Research Centre

CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
UK Carbon Capture and Storage Research Centre
 
Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...
Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...
Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...
UK Carbon Capture and Storage Research Centre
 
Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...
Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...
Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...
UK Carbon Capture and Storage Research Centre
 
Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...
Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...
Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...
UK Carbon Capture and Storage Research Centre
 
20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...
20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...
20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...
UK Carbon Capture and Storage Research Centre
 
Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...
Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...
Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...
UK Carbon Capture and Storage Research Centre
 
Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...
Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...
Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...
UK Carbon Capture and Storage Research Centre
 
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
UK Carbon Capture and Storage Research Centre
 
Multiphase flow modelling of calcite dissolution patterns from core scale to ...
Multiphase flow modelling of calcite dissolution patterns from core scale to ...Multiphase flow modelling of calcite dissolution patterns from core scale to ...
Multiphase flow modelling of calcite dissolution patterns from core scale to ...
UK Carbon Capture and Storage Research Centre
 
Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...
Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...
Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...
UK Carbon Capture and Storage Research Centre
 
Challenges in the chemical industry, jay brookes (boc) industry ccs worksho...
Challenges in the chemical industry, jay brookes (boc)   industry ccs worksho...Challenges in the chemical industry, jay brookes (boc)   industry ccs worksho...
Challenges in the chemical industry, jay brookes (boc) industry ccs worksho...
UK Carbon Capture and Storage Research Centre
 
Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...
Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...
Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...
UK Carbon Capture and Storage Research Centre
 
Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...
Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...
Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...
UK Carbon Capture and Storage Research Centre
 
Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...
Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...
Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...
UK Carbon Capture and Storage Research Centre
 
Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...
Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...
Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...
UK Carbon Capture and Storage Research Centre
 
Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...
Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...
Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...
UK Carbon Capture and Storage Research Centre
 
Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...
Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...
Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...
UK Carbon Capture and Storage Research Centre
 
Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...
Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...
Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...
UK Carbon Capture and Storage Research Centre
 
Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...
Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...
Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...
UK Carbon Capture and Storage Research Centre
 
Adsorption Materials and Processes for Carbon Capture from Gas-Fired Power Pl...
Adsorption Materials and Processes for Carbon Capture from Gas-Fired Power Pl...Adsorption Materials and Processes for Carbon Capture from Gas-Fired Power Pl...
Adsorption Materials and Processes for Carbon Capture from Gas-Fired Power Pl...
UK Carbon Capture and Storage Research Centre
 

More from UK Carbon Capture and Storage Research Centre (20)

CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
 
Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...
Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...
Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...
 
Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...
Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...
Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...
 
Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...
Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...
Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...
 
20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...
20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...
20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...
 
Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...
Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...
Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...
 
Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...
Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...
Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...
 
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
 
Multiphase flow modelling of calcite dissolution patterns from core scale to ...
Multiphase flow modelling of calcite dissolution patterns from core scale to ...Multiphase flow modelling of calcite dissolution patterns from core scale to ...
Multiphase flow modelling of calcite dissolution patterns from core scale to ...
 
Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...
Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...
Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...
 
Challenges in the chemical industry, jay brookes (boc) industry ccs worksho...
Challenges in the chemical industry, jay brookes (boc)   industry ccs worksho...Challenges in the chemical industry, jay brookes (boc)   industry ccs worksho...
Challenges in the chemical industry, jay brookes (boc) industry ccs worksho...
 
Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...
Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...
Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...
 
Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...
Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...
Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...
 
Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...
Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...
Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...
 
Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...
Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...
Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...
 
Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...
Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...
Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...
 
Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...
Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...
Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...
 
Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...
Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...
Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...
 
Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...
Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...
Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...
 
Adsorption Materials and Processes for Carbon Capture from Gas-Fired Power Pl...
Adsorption Materials and Processes for Carbon Capture from Gas-Fired Power Pl...Adsorption Materials and Processes for Carbon Capture from Gas-Fired Power Pl...
Adsorption Materials and Processes for Carbon Capture from Gas-Fired Power Pl...
 

Recently uploaded

MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 

Recently uploaded (20)

MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 

Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Biannual 8-9 September 2015

  • 1. Caledonia Clean Energy Project Update Stephen Kerr CCEP Project Director UKCCSRC Autumn Biannual Meeting University of Strathclyde • 8-9 September 2015
  • 2. • Over 25 years experience on renewable energy, oil & gas and construction projects - UK and international • 15 years working in renewable energy sector • Most recently led Inch Cape Offshore Wind Farm development (up to 780MW east coast of Scotland) through concept, EIA, S36 consent and CfD application; 2009 - 2015 • Based in Edinburgh 1 Stephen Kerr - Introduction
  • 3. • 25-year old U.S. developer of clean-energy power plants • Founded by Donald Paul Hodel (former Secretary of Energy & Secretary of the Interior) and Earl Gjelde (No. 2 official at Energy & Interior) • Traditional focus: wind, solar, and state-of-the-art combined cycle natural gas-fired power plants • Focus now: power plants w/ CO2 capture & sequestration • Our new CEO Jason Crew headed GE’s gasification unit • Currently working on (1) two large gasification projects with 90+% CO2 pre-combustion capture, and (2) retrofits of coal & gas-fired plants for post-combustion CO2 capture 2 Summit Power Group
  • 4. • Texas Clean Energy Project (TCEP) is in the financing stage and ready to start construction, once contracts are final • Caledonia Clean Energy Project (CCEP): much earlier stage • CCEP is a sister project to TCEP; this has many advantages • These two gasification power projects have in common: – Commercial-scale power plants with 90+ percent CO2 capture – No new technology – what’s new is integrating proven systems – Siemens gasifiers & Siemens high-hydrogen combustion turbines – Lead EPC contractor is Chinese company with key experience – Export-Import Bank of China is the expected project lender – Both projects should be attractive to equity investors 3 Two Summit CCS Projects: Texas & Scotland
  • 5. • 400+ MW “polygen” gasification plant to produce power, urea (fertilizer), and captured CO2 (90+% from coal) for EOR • Located atop Permian Basin oilfields: CO2 pipeline will be ~1 km long, connecting to Kinder-Morgan pipeline system • Largest award ($450M) in U.S. DOE’s Clean Coal Power Initiative, plus $100s of millions in special tax credits • China Huanqiu Contracting & Engineering Corp. (HQC) is lead EPC contractor; China Ex-Im Bank will be lead lender • Challenge through 2014/15 was to optimize plant / reduce cost • Finalizing EPC contracts this month; financing commencing 4 TCEP Overview
  • 6. TCEP Schematic Diagram Coal Coal Gasification, Gas Cleanup, and Gas Separation Water Syngas Syngas Main Outputs “High Hydrogen” Syngas (~95% H2 / 5% CO) & Pure CO2 CO2 CO2 Ammonia / Urea Complex CO2 Delivered to Oil Fields via Pipeline ~195 MW ultra low carbon power to San Antonio from high-hydrogen combustion turbine in combined cycle ~750,000 tons/yr of urea delivered to major fertilizer company ~2 mm tons per year delivered to Oil Producers Brackish Water Purified via Reverse Osmosis Oxygen Air Separation Unit * Additional revenue from sales of sulfuric acid, argon gas, & minor products 5
  • 7. • 570MW gasification plant w ~ 94% CO2 capture from coal • Different balance to TCEP, optimized for power output • Site is at Grangemouth, on Firth of Forth, near Edinburgh • On- & off-shore CO2 transport infrastructure largely exists • One of four (4) finalist projects in UK’s CCS Competition, but not one of the two (2) Competition projects chosen • CCEP is a “Phase 2” project (per DECC Policy Scoping Document, Aug 2014) seeking clustered projects to help initiate CO2/EOR sector • With our debt structure, CCEP doesn’t need a capital grant from DECC: just a Contract for Difference (CfD) 6 CCEP - Overview
  • 8. CCEP CO2 Chain 7 St Fergus CO2 Hub Caledonia IGCC UK coal Atlantic pipeline • Second of a kind IGCC Plant following Texas Clean Energy Project (TCEP) • 570MW low carbon electricity for a million UK homes • 3.8 Mt/yr CO2 Captured – Over 90% • Re-use of existing pipeline systems • Linking Central Scotland with the Central North Sea • Storage in proven offshore saline formation • High security: subsea development (no platform) • EOR Ready: Independent of Oil Company decision • Emitter Cluster and Sink Cluster • Development of St Fergus as a CO2 Hub 78km offshore Northern UK Emissions Cluster Future CO2 Import to Peterhead Harbour Injection into proven saline formation under a depleted gas field
  • 9. IGCC Plant Grangemouth 8 Raw Coal Storage Coal Milling and Drying Siemens Gasification Island AirSeparation Unit Low Temp Gas Cooling, Water/Gas Shift & Hg Removal SourWater Stripper Sulphuric AcidPlant Rectisol WashUnit CO2 Compression Waste Water Treatment Flare Black Water Plant Power Plant Gas and Steam Siemens SST5-5000 Steam Turbine Siemens SGT5- 8000H Gas Turbine Heat Recovery Steam Generator Parking Office Rail Head Coal Delivery
  • 10. Onshore Transportion 9 • Onshore transport through connection to existing Feeder 10 Pipeline is planned (in talks w Nat’l Grid) • Existing natural gas pipeline can be repurposed for CO2 transport • A FEED study was completed during DEMO 1 (Longannet) process • Excess capacity may be used to transport other CO2 eventually 34 Tunnel or HDD Tunnel or HDD Tunnel HDD or Cofferdam (open cut) Tunnel or HDD OPTION 1 (exit West) OPTION 2 (exit South)
  • 11. Planned Work Programme • Currently finalising Grant Agreement, organisation and resources; – Work Package 1: Industrial research and development, resulting in the preliminary design and notional pricing of CCEP. – Work Package 2: Feasibility study of requirements, constraints and mitigation including grid connection, planning and regulatory requirements, and financing considerations. – Work Package 3: Obtain required site options and/or exclusivity agreement(s) as project enablers • 18 month programme, budget ≈ £6.0M, grant ≈ £4.2M • Front loading important to de-risk project 10 Onshore Transportation Permitting Technical Economics Finance Commercial Offshore
  • 12. 11 CCEP – What We Need • Policy stability, Development Risk, Phase 1 projects moving into Phase 2 projects, Investor Confidence • CO2 chain physical interfaces, electrical grid connection, knowledge sharing, cost reduction, shared infrastructure, complex commercial interfaces • Political, public & local community support, dedicated CfD budget and mechanism Continuity Collaboration Support
  • 13. Long Term - Opportunity • CCEP as anchor for sustained effort to develop an entire integrated system, consisting of: – Clustered CO2 capture projects (not just one project), – Sharing a common CO2 pipeline and offshore infrastructure, – To produce low-carbon electric power to replace the UK’s coal plants (which are slated for closure within 15 years), and – To store carbon in depleted North Sea gas fields and saline formations, while also – Creating a CO2 for enhanced oil recovery (EOR) sector in the North Sea, with its own secure geological storage of CO2 12
  • 14. • Sources of captured CO2: – Peterhead Project: capture from natural gas, for 10 years or more – Caledonia #1 (a/k/a Grangemouth A): capture from gasified coal – Caledonia #2 (power plant) and/or capture from industrial sources – Possible marine terminal to receive added CO2 from Europe by ship • Onshore CO2 transport: National Grid’s Feeder No. 10 line – Caledonia #1 & #2 would leave room for industrial CCS sources as well, all using common infrastructure • Offshore CO2 transport: existing + some new pipelines • Offshore CO2 stores (providing the needed multiple sinks): – Goldeneye (depleted gas field, existing platform & infrastructure) – Suitable oilfields (with existing & new infrastructure for CO2/EOR) – Saline formation underlying Goldeneye, if needed 13 Long Term : Physical Components
  • 15. • “Single source, single sink” should be avoided; multiple sources & sinks is the right way to do CCS where possible • Use of a common CO2 transport & storage infrastructure will significantly reduce costs of CCS (including from industrial sources) • Environmental benefits: ~ 10 million tons/year of CO2 sequestered, plus ≈ 1,500 MW of ultra low-carbon power if Central Scotland opportunity is fully developed • Major employment & economic development benefits • UK leadership potential in CCUS & cooperation with China 14 Long Term - Benefits
  • 16. 15 Thank you Contact information: • Stephen Kerr, CCEP Project Director: skerr@caledoniacleanenergyproject.com • Jason Crew, CEO: jcrew@summitpower.com • Eric Redman, Co-Chairman: eredman@summitpower.com www.summitpower.com