Summary of experience:
Design, engineering, construction, operation, maintenance and integrity of onshore/offshore pipeline systems (crude oil, refinery products, natural gas and water) and their components (stations, terminals and tank farms) within the scope of different projects (see details below) including Feasibility and Conceptual Design, FEED (Front End Engineering Design), EPC (Engineering, Procurement and Construction), PMC (Project Management Consultancy) and O&M (Operation and Maintenance) services.
Skills (Pipelines):
- Feasibility Studies;
- Conceptual Engineering Design & Management Support;
- Basic Engineering Design & Management Support;
- Front End Engineering Design (FEED) & Management Support;
- Detailed Engineering Design & Management Support;
- Engineering & Management Support for Procurement;
- Engineering & Management Support for Construction & Mechanical Completion
- Engineering & Management Support for Pre-commissioning, Commissioning and Operational Start-up (Project Completion);
- Engineering & Management Support for Performance Testing, Operation and Maintenance;
- Project Management;
- Project Controlling;
- Project Engineering;
- Project Tendering;
- Tender (ITT) Preparation and Tender Evaluation.
Summary of experience:
Design, engineering, construction, operation, maintenance and integrity of onshore/offshore pipeline systems (crude oil, refinery products, natural gas and water) and their components (stations, terminals and tank farms) within the scope of different projects (see details below) including Feasibility and Conceptual Design, FEED (Front End Engineering Design), EPC (Engineering, Procurement and Construction), PMC (Project Management Consultancy) and O&M (Operation and Maintenance) services.
Skills (Pipelines):
- Feasibility Studies;
- Conceptual Engineering Design & Management Support;
- Basic Engineering Design & Management Support;
- Front End Engineering Design (FEED) & Management Support;
- Detailed Engineering Design & Management Support;
- Engineering & Management Support for Procurement;
- Engineering & Management Support for Construction & Mechanical Completion;
- Engineering & Management Support for Pre-commissioning, Commissioning and Operational Start-up (Project Completion);
- Engineering & Management Support for Performance Testing, Operation and Maintenance;
- Project Management;
- Project Controlling;
- Project Engineering;
- Project Tendering;
- Tender (ITT) Preparation and Tender Evaluation.
Summary of experience:
Design, engineering, construction, operation, maintenance and integrity of onshore/offshore pipeline systems (crude oil, refinery products, natural gas and water) and their components (stations, terminals and tank farms) within the scope of different projects (see details below) including Feasibility and Conceptual Design, FEED (Front End Engineering Design), EPC (Engineering, Procurement and Construction), PMC (Project Management Consultancy) and O&M (Operation and Maintenance) services.
Skills (Pipelines):
- Feasibility Studies;
- Conceptual Engineering Design & Management Support;
- Basic Engineering Design & Management Support;
- Front End Engineering Design (FEED) & Management Support;
- Detailed Engineering Design & Management Support;
- Engineering & Management Support for Procurement;
- Engineering & Management Support for Construction & Mechanical Completion;
- Engineering & Management Support for Pre-commissioning, Commissioning and Operational Start-up (Project Completion);
- Engineering & Management Support for Performance Testing, Operation and Maintenance;
- Project Management;
- Project Controlling;
- Project Engineering;
- Project Tendering;
- Tender (ITT) Preparation and Tender Evaluation.
As a Land Surveyor With 22 years of experience in the Oil Gas industries in Various countries . Very good knowledge to handle latest Survey instruments in the Industries
Briefly, I am Ashish Shrivastava (self employed), Piping stress engineer with 15+ years of experience. I have done wide range of stress analysis in different sectors like Offshore/onshore, Marine, LNG/LPG, Petrochemical, Solar/ Thermal powerplants. Please find my profiles attached here for your reference.
I would be grateful if you can consider my profile for Autocad plant 3D/ pipe stress analysis work that would like to outsource.
I also provide corporate trainings online/offline.
As a Land Surveyor With 22 years of experience in the Oil Gas industries in Various countries . Very good knowledge to handle latest Survey instruments in the Industries
Briefly, I am Ashish Shrivastava (self employed), Piping stress engineer with 15+ years of experience. I have done wide range of stress analysis in different sectors like Offshore/onshore, Marine, LNG/LPG, Petrochemical, Solar/ Thermal powerplants. Please find my profiles attached here for your reference.
I would be grateful if you can consider my profile for Autocad plant 3D/ pipe stress analysis work that would like to outsource.
I also provide corporate trainings online/offline.
Senior Supervisor Piping & Mechanical
Piping &Pipe Line Fabrication/Erection&/ Hydro test /Mechanical Completion Pre-Commissioning
I have around17+, years ‘work experience I have done three years diploma inMechanical engineering,
I have worked as a Piping supervisor in Oil, Gas, power plant & Petro-chemical.
Similar to Lead Pipeline Engineer (with 25+ years of relevant job experience in FEED, EPC and PMC pipeline projects) (20)
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
Lead Pipeline Engineer (with 25+ years of relevant job experience in FEED, EPC and PMC pipeline projects)
1. February 2, 2016 Page 1 of 13
Orhan Degermenci, PhD
Lead Pipeline Engineer
Qualification Profile
Orhan Degermenci (PhD) with his full-time of 25 years total relevant job
experience is involved worldwide in designing, engineering (FEED),
construction (EPC) as well as operation of many oil & gas pipelines with
a total length of more than 15,000 km and a nominal diameter range
between 6 to 56 inches. He has been responsible as project manager also
for engineering, construction and operation of underground natural gas
storage plants with a total storage capacity of 4 billion standard cubic
meters. During these activities he has applied all relevant international
pipeline codes and standards such as API 5L/ISO 3183, API 6D, ISO
13623, EN 10208-2, ASME B31.4, ASME B31.8, BS 8010, EN 1594 and EN
14161 so that he is very familiar with all technical aspects of planning,
designing, engineering, procurement, construction, pre-commissioning,
commissioning, start-up and operation of pipeline systems for both
crude oil and natural gas transportation as well as of underground gas
storage plants.
While working in oil & gas industry he has been teaching for 4 years of
his professional career at the Middle East Technical University (METU)
in Ankara to petroleum engineering students of advanced semester in
PIPELINE ENGINEERING. Occasionally he has published and
introduced his project experiences and work results of scientific and/or
public importance in several international bulletins, oil & gas magazines
as well as on many international oil & gas conferences. For all the details
on his relevant experience and job history he would like to refer you to
the details in his CV which have been highlighted below as per project
of his involvement.
Furthermore, he has a very rich electronic knowledge archive or
database which contains all technical project documents (incl. codes,
standards, feasibility studies, technical reports, construction drawings,
pipeline route maps and alignment drawings, manuals, guidelines,
procedures, calculation spreadsheets, design calculation validation
reports, technical specifications, engineering work instructions, etc.)
gathered over the long period of his professional life. All these
knowledge documents can be made available for utilization in diverse
pipeline projects, where he would be in charge to take on the role of
Lead Pipeline Engineer or the responsibility of Discipline Manager.
Email Address:
orhandegermenci1961@gmail.com
Nationality: Turkish
Citizenship: Turkish
Date of Birth
Nov 10, 1961
Education
M.E. & PhD – Petroleum Engineering
Clausthal Zellerfeld, Germany
University of Clausthal
Year of Passing - 1992
License & Membership:
N.A.
Languages Spoken
English, German, Turkish
Computer Skills
MS Office 2007, PowerPoint, MS
Projects, WRENCH (EDMS)
2. Orhan Degermenci (continued)
February 2, 2016 Page 2 of 13
Level of Experience
25 years of experience in Pipeline Engineering
Fields of Experience
Designing and engineering of pipeline systems including design
calculations, project engineering, project management, project control,
pipeline routing and authority engineering, tender documentation (FEED
+ EPC)
Functional Areas of Work
Pipeline Systems (for Water, Oil, Gas and Refinery Products) including
System Components such as Pump or Compressor Stations and Storage
Tank Farms, Loading and Unloading Facilities
The engineering capabilities on these work areas cover the following:
1. Feasibility Study
2. Conceptual Engineering Design
3. Basic Engineering Design
4. Front End Engineering Design (FEED)
5. Detailed Engineering Design
6. Engineering Support for Procurement
7. Engineering Support for Construction Management
8. Engineering Support for Pre-commissioning and
Commissioning
9. Engineering Support for Operational Start-up, Operation and
Maintenance
Employment/Career History
CH2MHILL, Abu Dhabi, UAE
Current Designation: Lead Pipeline Engineer
(From 18-July-2013 to till date)
Tacaamol Aromatics Project (FEED):
• Design Basis Memorandums (DBM) for FEED of Propane Pipeline
(12 inch x 15 km x 0.7 MTA) and Naphtha Pipeline (32 inch x 15
km x 3,300 m3/h
• Pipelines Mechanical Design Reports (Design Calculation Books)
for Naphtha & Propane Pipelines (incl. Line Pipe Wall Thickness
Calculations, Equivalent Combined Stress Calculations, Elastic
Bend Radius Calculations, Anchor Force Calculations, Upheaval
Buckling Calculations, Free End Expansion Calculations,
Crossing Calculations for Minor Road or Track, Highway and
Railway as well as Paved and Rig Road Crossings, Proximity or
Safety Separation Distance Calculations, and Flexibility
Calculations)
3. Orhan Degermenci (continued)
February 2, 2016 Page 3 of 13
• Sectionalizing Valve Evaluation and Location Class Selection
Reports for Naphtha and Propane Pipelines
• Scraping (Pigging) Evaluation Study & Scraping Philosophy
Reports for Naphtha and Propane Pipelines
• Line Pipe Steel Grade and External Coating Materials Selection
Reports for Naphtha and Propane Pipelines
• Technical Specifications and Datasheets for Naphtha and Propane
Pipelines (covering Scraper Launchers & Receivers,
Barred/Scraping Tees, Bends, Anchor Flanges, Scraper/Pig
Signalers, Sectionalizing and Isolating Valves, SAW/HFW/SMS
Line Pipes, and Isolating Joints)
• Technical Specifications for Naphtha and Propane Pipelines
(covering Construction, Welding and Weld Inspection,
Hydrostatic Pressure Testing, Anti-Corrosion External & Internal
Coatings incl. Line Pipe & Field Joint Coatings, Anti-Buoyancy
Concrete Coating, Corrosion Monitoring Equipment, and
Topographic Survey)
• Typical Drawings for Construction of Naphtha and Propane
Pipelines (covering Layout – SV Station, Piping General
Arrangement at Valve Station, Details of Cased & Uncased Track
Crossings and Safety Barriers, Details of Steel Cased & Uncased
Major Road Crossings, Details of Safety Barrier for Metaled Road
Crossings, Details for Safety Barrier for Pipeline Crossing Tracks
and Un-metaled Roads, Details of Underground Cable Crossings,
Details for Crossings Below Existing Underground Pipeline,
Details for Crossings Above Existing Buried Pipeline in Sabkha
Areas, Details for Crossings Above Existing Pipelines installed in
Berms through Sabkha Areas, Details of Overhead Power Line
Crossings, Pipeline and Cable Crossings in Sabkha Areas, Details
of Pipeline Construction at Sabkha Areas, Details of Pipeline
ROW + Trench + Backfill in General, Details for Pipeline ROW +
Trench + Backfill in High Water Areas & Sand Dune Areas,
Details for Construction in High Water Areas & Sand Dune Areas,
Details of Pipeline Identification Slabs & Cable Tiles, Details of
Casing Vent & Drain-Off, Details of Pipeline Warning Signboard
and KM Markers, Details of Warning Signboard in Populated
Areas, Details of Sign Board Direction at Valve Stations, Details of
Warning Signboard at Valve Stations, Details of Danger
Signboard at Valve Stations, and Typical Details of Signboard
Fixing Posts).
ASAB Natural Gas Field Facilities Upgrade Project (FEED):
• Design Basis Memorandums (DBM) for Pipelines (incl. Gas
Production & Injection Flow Lines, and Gas Gathering & Injection
Trunk Lines)
• Pipelines Routing Desktop Study Reports (incl. Routing Maps
and Plans)
• Optimized Pipeline Route Selection Reports (incl. Routing Maps
and Plans)
• Pipeline and Piping Material Selection Reports
• New Wellhead Location Layout Maps & Field Layout Drawings;
4. Orhan Degermenci (continued)
February 2, 2016 Page 4 of 13
• Request for Quotation (RFQ) and Scope of Work (SOW) for
Topographical Pipeline Route Survey and Detection of
Underground Gas Pipelines
• Technical and Commercial Bid Evaluation Reports for
Topographical Pipeline Route Survey & Detection of
Underground Gas Pipelines
Khalifa Port and Industrial Zone (KPIZ) Project (FEED):
• Pipeline Route Design Report incl. Route Maps and Routing Plans
• SOW (Scope of Work) and RFQ (Request for Quotation)
Documents for Topographical Route Survey
• Specifications and Datasheets for Line Pipes, Pumps, Valves and
Tanks
• Pipeline Hydraulic Design Report incl. Flow Assurance
Calculations
Common Seawater Supply Pipelines Project (FEED & PMC):
• Project Execution Plan & Procedures
• Engineering Management Plan & Procedures
• Design Basis Memorandum
• ITT for Pipelines EPC including Technical & Commercial Tender
Requirements and Scope of Work
• EPC Implementation Schedule
• EPC Cost Estimation Report
• Hydrostatic Pressure Test & Pre-commissioning Plan
• Specification for Pipelines Operation
• Pipeline System Engineering Management Plan
• Regulatory Compliance Plan
• Pipeline System Selection Execution Plan
• Pipeline Stations Layout Design Philosophy & Plan
• Pipeline Pumps & Drivers Selection Study Report
• Pipeline Valves Selection Study Report
• Pipelines Stress Analysis Report
• Pipeline System Safety Design Philosophy
• Logistics and Transport Strategy
• P&IDs, PFDs, SFDs and General Plot Plans of Pipeline System
Components (Stations and Terminals)
• Pipeline System Waste Management Philosophy & Study Report
• Pipeline System Flow Assurance Philosophy & Study Report
• Line Pipe Internal Lining Selection Philosophy & Study Report
• Pipeline System Configuration Selection Execution Plan &
Selection Report
• Pipeline System Aboveground Facilities Optimization Study
Report
• Leak Detection System Selection Report
• Pipeline System Material Selection & Corrosion Control
Philosophy & Study Report
• Wall Thickness & Steel Grade Distribution Study Report
• Waste Management Philosophy & Study Report
• Maintenance Road Study Report
• Pipeline System Basic Data Report
5. Orhan Degermenci (continued)
February 2, 2016 Page 5 of 13
• Datasheets and Specifications for Line Pipes, Hot Induction
Bends, Field Cold Bends, Barred Tees, Pig Traps, Pig Signalers,
Pipeline Valve Actuators, Pipeline Internal Lining and External
Coating, Pipeline Field Joint Coating, Pipeline Cathodic
Protection, Pipeline Welding, Handling & Transportation &
Storage of Line Pipes
• Pipeline System Construction Execution Philosophy & Plan
• Pipeline System Operation & Control Philosophy
• Pipeline Route Maps & Typical Pipeline Construction Drawings
• Material Requisitions for Line Pipes and Pipeline Valves
• HAZOP, HAZID & ENVID Study and Workshop Reports for
Pipelines Systems
• 3D Modelling of Pipeline Stations and Terminals
• MTOs for diverse Pipeline System Components, Materials &
Equipment
Haliba Field Development Project (FEED):
• Project Pipeline Specifications for Line Pipes, Valves, Pig Traps,
Barred Tees, Hot Induction Bends, Isolating Joints, Fittings and
Flanges, Hydrostatic Pressure Testing, Construction, Welding,
Stress Analysis, Corrosion Monitoring
• Pipeline Route Selection Report
• Plant Location Study Report
• Pipeline Design Basis
• Pipeline Alignment Sheets
• PIDs and PFDs
• Pipeline Construction Typical Drawings
• Overall Plant Layouts and Plot Plans
• Project Execution Plan
• Project Procedures for Change Management, Document Control,
Document Numbering, HAZOP, Invoicing, Coordination,
Estimation, Project Planning
• Equipment & Material Lists
• Isolation, Vent & Drain Philosophies
• Material Selection & Corrosion Control Philosophies
CH2M HILL Quality Management Improvement (Internal Project):
• Pipeline Upheaval Buckling (UHB) Calculations
• Pipeline Maximum Cold Bend Angle & Minimum Elastic Bend
Radius Calculations
• Pipeline Road (Highway) Crossing Calculations as per API RP
1102
• Pipeline Railroad Crossing Calculations as per API RP 1102
• Pipeline Combined Stress Calculations
• Pipeline Anchor Load & Free End Expansion Calculations
• Line Pipe Wall Thickness Calculations as per ASME B31.8 (Gas
Pipelines)
• Line Pipe Wall Thickness Calculations as per ASME B31.4 (Liquid
Pipelines)
• Pipeline Hydrostatic Test Pressure Calculations
• Calculations of Line Pipe Wall Thinning During Bending
6. Orhan Degermenci (continued)
February 2, 2016 Page 6 of 13
• Pipeline Induction Bend Centerline Offset Calculations
• Calculations of Soil Stiffness as per ALA-2005 (American Lifelines
Alliance)
• Line Pipe Stacking Calculations as per API 5LW and API 5L1
• Pipeline Lifting and Lowering Calculations
• Pipeline Pulling Force and Stress Calculations
• Pipeline Bending Moment and Stress (Free Span) Calculations
• Pipeline Deflection Calculations
• Pipeline Free Span Calculations
• Pipeline Filling (Oil and Gas Line Pack) Calculations
• Pipeline Pump Sizing Calculations (Liquid Pipelines)
• Pipeline Compressor Sizing Calculations (Gas Pipelines)
• Pipeline System Dimensioning Calculations (Liquid Pipelines)
• CH2M HILL Pipelines Capability Statement
PETROFAC, Sharjah, UAE
Designation: Technical Specialist Pipelines
July 2011 to June 2013
Project execution plans, and logistics & supply chain management
plans needed for PMC (Project Management Consultancy) services
during construction of cross-country pipelines
Internal guidelines and/or procedures:
• Pipeline Buckling Analysis
• Pipeline Stress Analysis
• Pipeline Concrete Anchor Block Design
• Buoyancy Safe Design and Installation of Pipelines Crossing High
Groundwater and Intermittent Flood Plains
• Cost-Optimized Spacing of Sidebooms during Pipeline
Construction (Lifting & Lowering Operation)
• Anti-Buoyancy Pipeline Saddle Weight Design
• Mechanical Safety Interlocking and Sequencing of Pig Trap
Valves during Pig Launching and Receiving Activities
Standardized typical drawings needed for construction of oil and gas
pipeline systems
Tender documentation incl. Specifications, Datasheets, Supplier
Documentation Requirement Lists (SDRL), Material Requisitions,
Scope of Work and Deliveries:
• Pipeline Launcher / Receiver Pig Traps incl. Pig Handling
Facilities (JIB Cranes)
• Mechanical Interlocks and Pig Signalers as well as Quick-Opening
End Closures
• Pipeline Valves (Ball / Gate / Globe / Plug / Check)
• Line Pipes (Non-Sour and Sour Services) as per API 5L and ISO
3183
• CRA (Corrosion Resistant Alloy) Cladded or Lined Steel Pipes
Based on standards API 5LC and API 5LD
• Handling, Transportation and Stockpiling of Line Pipes and Hot
7. Orhan Degermenci (continued)
February 2, 2016 Page 7 of 13
Bends
• Topographical Pipeline Route Survey and Geotechnical Soil
Investigation
• Concrete Weight Coatings
• External and Internal Anti-Corrosion Pipeline Coatings (PE, PP,
PU and FBE)
• Line Pipe Joint Coatings (PU and PP)
• Painting Systems for Pipelines and Related Equipment as well as
Piping Components
• HDD (Horizontal Directional Drilling)
• Pipeline Anchor Flanges
• Pipeline Barred and Non-Barred Tees, Pipeline Flanges; and
• Pipeline Construction including Crossings
Pipeline design engineering calculations:
• Lifting and Lowering During Construction
• Rail/Road/Water Crossing
• Buoyancy
• Hydrostatic Testing
• Elastic Bend Radius
• Upheaval Buckling
• Pipeline Pulling during Construction of Pipeline Crossings;
• Soil Stiffness
• Anchor Load
• Pipe Stacking
• Wall Thickness
Projects Lessons Learned (LL) Reporting for Quality Management
System (QMS)
Diverse engineering roles for the company’s midterm strategic and
business goals in frame of the “Fit For 2015” Program
In-house workshops, seminars and presentations covering personally
prepared and developed in-house guidelines, procedures, manuals
and calculation spreadsheets
Quality control and quality assurance of engineering design
deliverables
BOTAS Turkish Pipeline Corporation, Ankara, TURKEY
Designation: Lead Pipeline Engineer & Advisor to Board of Directors
July 2005 to June 2011
NABUCCO Natural Gas Pipeline Project (FEED):
• Project development, project tendering, tender documentation for
FEED services and QA/QC checking / commenting of pipeline
FEED deliverables produced by the Owner’s Engineer Company
BOTAS Technical Commission Membership (Internal Project):
• Guidelines and manuals on technical integrity of crude oil and
natural gas pipelines as well as LNG and natural gas
8. Orhan Degermenci (continued)
February 2, 2016 Page 8 of 13
underground storage plants in Turkey for engineering design,
construction, operation and abandonment according to Turkish
and/or European industrial standards and technical rules
TPAO Turkish Petroleum Corporation, Ankara, TURKEY
Designation: Project Manager
February 2005 to June 2005
Underground Natural Gas Storage Plant Project (EPC):
• Planning, engineering, construction and operation of
underground gas storage plants located in depleted onshore and
offshore gas fields, QA/QC of project documents and project
management (EPIC contract)
ILF Consulting Engineers, Munich, GERMANY
Designation: Department Head and Project Manager
January 1993 to January 2005
Middle European Crude Oil Pipeline Project (EPC):
• Design engineering and construction, preparation, development
and implementation of project network, structural plan and time
schedule as well as site inspections during pipeline construction
phase.
Iraq to Turkey Crude Oil Pipelines (Turkish Section) Project
(Operation):
• Study of pipeline conservation covering investigation of mainly
possible methods as well as development of a combined concept
for corrosion protection measures.
Schwedt to Seefeld Multiproduct Pipeline Project (EPC):
• Feasibility study for increasing transport capacity and system
improvements, investigation of both current and required
conditions for mechanical and hydraulic as well as control and
automation systems, and related solution concept for their
improvements, cost estimation and time schedule for realization
of mitigating measures
Rostock to Schwedt Crude Oil Pipeline Project (EPC):
• Study on technical upgrading measures covering investigation of
compliance with the German laws and technical rules or
standards, determination of measures for safe operation and
increase of overall transport capacity by improvement of
operating procedures
Project for Natural Gas Flow Stations (Central Node, Jones Creek,
Makaraba, Odidi, Escravos Node) Project (EPC):
• Technical concept and feasibility study for repair of defect (gas
leaking) insulation joints installed on flow stations, site visit and
9. Orhan Degermenci (continued)
February 2, 2016 Page 9 of 13
inspection, defect analysis, repair method, construction concept
and cost estimation for implementation
Buschhaus to Alversdorf Liquid Sulphur Pipeline Project (EPC):
• Technical concept, tender and construction documents for re-
laying of the existing pipeline, conceptual design and preparation
of documents, project specifications and bill of quantities
Project for Trans-Ecuador and Ecuador to Columbia Crude Oil
Pipelines (EPC):
• Verification and investigation of construction tender design
covering system operations, hydraulics, relief philosophy and
block valve sections, alternatives for investment, operation costs
for peak sharing, blending pipeline and slick line operation, and
project specifications
Project for Pipelines Integrity Management Manual / PIMM
(Operation):
• Review and consideration of Shell (SPDC) applicable documents
(policies, procedures and standards) for integrity management of
oil and gas pipelines, interviews with engineering and
management personnel and consideration of information from
Shell departments for design, construction, operation and
maintenance of oil and gas pipelines.
Project for European Natural Gas Pipeline Metering Stations and
Receiving Facilities (Operation):
• Material handling studies covering handling methods for plant
equipment considering major removal or access routes and
procedures for using handling or lifting devices
Middle German Multiproduct Pipelines (MIDER) Project (EPC):
• Application documents and design manuals for pipelines
construction and operation taking into account the German
legislation, technical rules and standards to obtain all necessary
authority permits or approvals for construction and operation of
pipelines
Project for High Pressure 3-Phase (O/W/G) Separator at Awoba Crude
Oil Flow Station (Detailed Engineering):
• Conceptual and detailed design of modifications for separator
installation covering complete design documentation required for
construction and modified flow station operations
Project for LNG Upstream Gathering System (Flow Lines, Test and
Bulk Lines), Inter Field and Gas Supply Pipelines (Detailed
Engineering):
• Technical and commercial bid documents to apply for
engineering project contracts
Bonny Terminal Integrated Projects (EPC):
• Technical and commercial bid documents project contracts
10. Orhan Degermenci (continued)
February 2, 2016 Page 10 of 13
Diverse Gas, Water and Oil Pipeline Projects:
• Workshop testing and inspection of mechanical equipment (line
valves and control valves) incl. visits to manufacturer workshops
in Italy and Netherlands, attendance on testing and inspection
works, preparation of test and inspection reports
Project for Gas Distribution Scheme for Natural Gas Supply to NNPC
Housing Estate (EPC):
• Vetting of detailed pipeline design engineering and construction
documents covering co-ordination of interdisciplinary vetting
works and reporting of comments to the design engineering and
construction teams on site for their implementation
Project for diverse oil fields as well as related gathering lines and
transport pipelines (QRA Study):
• Risk assessment study covering site visits to Russian pipeline
operation companies in Usinsk (Komi Republic) and inspection of
their plants for data collection and preparation of study report
Quo Ibo Terminal Project (EPC):
• Preparation of complete material requisition documents to get
vendors` bids for cost estimation of terminal expansion works and
equipment
Project for new and long-distance pipelines to transport crude oil and
natural gas from the Caspian Region to Europe (Feasibility Study &
Conceptual Design):
• Route investigation and engineering works in Caucasus
(Azerbaijan, Georgia and Armenia) as well as in Turkey and
Greece covering route visits and preparation of route selection
reports in consideration of possible interconnecting routes
westward from the Caspian Sea towards European market
Business development (BD) in countries of Caucasus / CIS (Azerbaijan,
Georgia and Armenia):
• Introduction of company to foreign international as well as local
oil and gas companies and getting the company registered for
bidding process
Nembe Creek to Ekulama Associated Gas Gathering Pipelines Project
(EPC):
• Preparation of tender documents covering complete material
requisitions needed for cost estimation of pipeline construction
works
Fiber Optic Cables Project (EPC):
• Design engineering and construction covering identification and
documentation of crossing objects (pipelines, public roads, rivers
and railways) located along the route of fiber optic cables for
telecommunication purposes, and obtaining of authority/owner
11. Orhan Degermenci (continued)
February 2, 2016 Page 11 of 13
approvals for crossing of these objects during cable laying works
Project for Oil and Gas Transportation via Pipelines from the Caspian
Region to Europe (Feasibility Study & Conceptual Design):
• Feasibility studies covering assessment of main oil and gas supply
/ demand parameters, identification of main transit and export
routes, technical, environmental and commercial feasibility
studies, alternative project development plans, conclusions and
recommendations, project management activities, site visits for
data collection and route investigations in countries such as
Azerbaijan, Georgia, Armenia, Turkey and Greece, organization
of international workshops, publication and presentation of
project results in international oil & gas bulletins, magazines and
workshop seminars
Project for Assessment (Due Diligence) of the Egyptian Petroleum
Pipeline Company (PPC) Assets for Transportation of Crude Oil and
Refinery Products (Study):
• Site visits to pipeline assets, pipelines inspection and data
collection, data evaluation and preparation of due diligence study
report
Crude Oil Main Pumps for the Baku-Tbilisi-Ceyhan Crude Oil Pipeline
(Turkish Section) Project (Detailed Engineering):
• Functionality witness and workshop test as well as preparation of
test reports
Knowledge & Technology Management (Head of Department / HoD):
• As head of knowledge and technology department responsibility
for implementation of company`s own technology and
knowledge management objectives covering both preparation
and execution of knowledge management concepts, professional
competency catalogues, knowledge data bases, knowledge
archives, knowledge libraries, standardization of engineering and
administrative works by numerous company internal documents
such as standard specifications, recommended practices, work
instructions and sample project documents
Institute for Drilling, Crude Oil & Natural Gas Production
Technical University of Causthal, Clausthal Zellerfeld, GERMANY
Designation: Scientist (Doctorate)
July 1989 to October 1992
Science & Research & Development:
• Cuttings (slurry) transportation during drilling operation in
vertical, horizontal and inclined deep bore holes, reporting and
presentation of results from research works, preparation of
doctoral thesis (dissertation) and passing through examination to
obtain degree of doctor-engineer (Dr.-Eng. or PhD)
12. Orhan Degermenci (continued)
February 2, 2016 Page 12 of 13
FAGRO GmbH, Hanover, GERMANY
Designation: Marketing Engineer
September 1988 to June 1989
Sales & Marketing:
• Responsibility for worldwide sales and marketing of equipment
and facilities manufactured by diverse companies in Europe and
USA for exploration, production and transportation of
hydrocarbons covering tendering, procurement and supervision
of installation works as well as consulting services for clients
Institute for Drilling, Crude Oil & Natural Gas Production
Technical University of Causthal, Clausthal Zellerfeld, GERMANY
Designation: Scientist
January 1988 to July 1988
Science & Research & Development:
• Cuttings transportation in inclined and horizontal bore holes
during drilling operation, design and dimensioning of horizontal
bore holes, reporting and presentation of project results, support
and coordination of lectures for navigation and control during
horizontal drilling, and literature study on horizontal drilling and
drain-hole technology)
Summary of Country Experiences
• Germany (12 years), Turkey (6.5 years), United Arab Emirates (4.5
years), Nigeria (1 year), Azerbaijan (6 months), Russia (3 months),
Georgia (1 month), Armenia (1 month), Egypt (1 month) and
Greece (1 month)
Publications and Presentations
• Feasibility of Crude Oil and Natural Gas Transport via Long
Distance Pipelines or Routes Through the Caspian Sea and Their
Further Continuation Links Westward. Oil Gas European
Magazine, Germany, 3/2001
• Trasporto Dal Caspio - Rotte E Costi A Confronto. ENERGIA Rivista
Trimestrale Sui Problem, Dell’Energia, Italy, 1/2002
• European Union Study of Caspian Area Oil, Gas Pipelines
Compares Routes and Costs. Oil & Gas Journal, USA, November 5,
2001
• European Union Study of the Caspian Area Oil and Gas Pipelines,
Comparing Routes and Costs. Pipes & Pipelines International, UK,
Vol. 46, No. 6, November-December 2001
13. Orhan Degermenci (continued)
February 2, 2016 Page 13 of 13
• Highlights of the Caspian Study Results. Black Sea Trend Review of
the Black Sea Economic Cooperation, Turkey, Vol. 1, No. 1, Summer
2002
• Design Engineering of Crude Oil and Natural Gas Pipelines, and
Knowledge Management – An Overview on Technical and Practical
Aspects. IPETGAS 2005 – 15th International Petroleum and Natural
Gas Congress and Exhibition of Turkey, Ankara, 11-13 May 2005
• Commercial Importance of Pipelines as Element of Infrastructure.
IPETGAS 2007 – 16th International Petroleum and Natural Gas
Congress and Exhibition of Turkey, Ankara, 29-31 May 2007
• Status and Challenges of the NABUCCO Natural Gas Pipeline. 63rd
Annual Assembly & International Conference of the International
Institute of Welding, Istanbul, Turkey, 15-16 July 2010
• Transportation Tasks and Dimensioning of Crude Oil and Natural
Gas Pipelines. Workshop & Seminar of PETROFAC International
Limited, Sharjah, United Arab Emirates, 28 December 2011
• Upheaval Buckling (UHB) of Crude Oil and Natural Gas Pipelines.
Workshop & Seminar of PETROFAC International Limited, Sharjah,
United Arab Emirates, 28 March 2012