Optimum Solutions Consultants
JetBlue Airways Implementation Project
Project Objective:
This project is to successfully, implement an ERP system (mySAP) powered by the
SAP NetWeaver™ platform for this particular client (JetBlue Airway). The
commissioned date to start was on April 04, 2011, and completed by February 19,
2014. The implementation of this ERP system will help the client achieve the
business agility it needs and eliminate obstacles of technology integration as the
company grows. It will also help with the improvement of Customer Relationships
and a more efficient relationship with their vendors.
Yet more importantly, business operations will show a decrease in time and
expense, while at the same time allow better decision-making process with fewer
errors.
JetBlue Airways Corporation
 JetBlue is one of the nation's leading low-cost airlines and is based out of
New York's JFK Airport.
 JetBlue flies up to 600 flights a day to 63 cities including all three NYC
airports. In five years, the company has become the biggest airline
serving JFK and specializes in non-stop trips from New York to the West
Coast and Florida.
 They established the idea of bringing humanity back to air travel and
strive to make every part of the passengers experience as simple and as
pleasant as possible.
JetBlue’s Situation
 On February 14, 2007, a JetBlue flight from John F. Kennedy
International Airport to Cancun, Mexico was delayed on the ramp in a
snowstorm, keeping passengers on the plane for nearly nine hours.
Throughout that day, at least nine other JetBlue aircraft were also
stranded on the tarmac, keeping the passengers all on board. Four days
later, JetBlue was still not operating normally, canceling nearly all
flights using Embraer 190 aircraft.
 Most of the problems were related to staffing issues. JetBlue, which
books 80% of its tickets online, did not have enough reservations
agents on its toll-free line to handle all of the rescheduling.
 At Kennedy Airport, there was not enough trained staff to work on
rebooking.
 And the unit in charge of locating pilots and flight attendants and
assigning them to their next flight was overwhelmed.
ERP Project Phases
 Initiation
 Project planning
 Analysis and Process design
 Realization
 Transition
 Operations from “go live” to support
Phase 1
Project Preparation (Initiation):
 Team prepares for a kick-off meeting, and undertakes
planning and preparation of Study Development, Testing,
Approval, and Implementation.
Phase 2
Systems Requirement and Specification and
Business Blue Print (Project Planning)
 workshop is conducted with key stakeholders to define
project objective, scope time schedule etc.
Communication plan
Audience Content Event Responsible Medium
Client/Customers
Projectoverview(basic
understanding,highlevel
timeline)
toinclude successes/issues.
Regularly-scheduledteam
meetings(1/mo);
And asneeded
Projectmanager
• Face-to-face;
• Phone;
• Email.
Vendors/suppliers
Anupdateon deliveryof
equipment& service
progress.
Daily/weekly Productmanager • Phone
• Face-to-face
ProjectSteeringTeam
Policy-relatedissues;
Projectprogress.
Regularly-scheduledteam
meetingsandasneeded.
Projectleader& taskleader • Face-to-face;
• Email.
InternalStakeholders
Projectoverview&
progress.
Projectdeliverables
weekly Projectleader • Face-to-face;
• Email.
Risk & Quality Issues
Quality Objectives Quality Planning Quality Control Quality Assurance
Identify the work (tasks,
dependencies, and
deliverables), effort
(hours), schedules (start
and end dates) and
resources (people,
equipment, and funding)
required to meet the
specified objective.
According to
specifications and
standards
Deliverable Reviews and
Acceptance Process
Ensuring the project
methodologies, standards
and controls are
appropriate and
reasonable for the project
environment.
Establish a baseline
against which to measure
progress.
On time/within Budget Project Quality Review. Saphire IV & V
(Independent Verification
and Validation) Plan
Software development SDLC SDLC SDLC
Project Objectives
• Implementation of enterprise software
• Ensure the software meets the needs for each level of user.
• Centralize ERP system.
• Eliminate current (outdated) software.
• Train the 8000 employees for their level of software.
• Determine the best possible solution for sustaining pending
the completion of the project.
Tools & Technology
• SAP ECC 5.0® Human Capital Management;
• SAP NetWeaver Portal;
• Performance Management (Objective Setting and
Appraisals);
• Enterprise Compensation Management;
• E-Recruiting 6.00;
• Worklogix Accelerated Suite for Performance
Management and Enterprise Compensation.
Budget/Cost Structure
• Software licenses for 8000 users $20,000
• Maintenance for the software
• Hardware (server) ---------
• Maintenance on the hardware ---------
• Hardware (workstations) annual cost: $ 15,000
• Infrastructure annual cost: $ 25,000
• Changes to software
• Interfaces to several systems
• Data conversion (from old to new system)
•
Phase 3
Systems Development and Testing :
• Creation of Database, Input and Interface Forms and Queries.
• Programs are written as per business process requirement as
defined in the Business Plan.
• Each module is tested and views of the client are noted.
Phase 4
Project Realization
• Implementation of the entire business process
requirement as per the Business Blue Print.
• Holding of integration test and designing of end
user documentation.
Phase 5
Final Preparation (Transition):
• Covers user and administrator training, system
management, activities to finalized go-live readiness.
Phase 6
“Go-live” and support
• Moving the project from project orientation and pre-production
environment to live production operation.
• Key elements include setting up production support, monitoring
systems transaction and optimization of overall systems
performances as well as the completion of all documentations.
Lessons learned?
“Every wrong decision is in fact a correct
decision but taken at a wrong time so my
friends don't regret... don't stop... keep
walking ahead.”
Thank You for your time…..

More Related Content

What's hot

ResumeMaster2015
ResumeMaster2015ResumeMaster2015
ResumeMaster2015
Rodney Lettman
 
Operational Efficiency Increases by 40% for Multinational Hotel Chain
Operational Efficiency Increases by 40% for Multinational Hotel ChainOperational Efficiency Increases by 40% for Multinational Hotel Chain
Operational Efficiency Increases by 40% for Multinational Hotel Chain
AppViewX
 
Preeti Sharma tech
Preeti Sharma techPreeti Sharma tech
Preeti Sharma tech
Preeti Sharma
 
Resume
ResumeResume
Resume
Sajal Gupta
 
Jian Zhang Resume 2014
Jian Zhang Resume 2014Jian Zhang Resume 2014
Jian Zhang Resume 2014
Jian Zhang
 
Lavanya-Resume 10+
Lavanya-Resume 10+Lavanya-Resume 10+
Lavanya-Resume 10+
Lavanya Sri
 
Nader_Kamal_Farahat_Ibrahim updted-2017
Nader_Kamal_Farahat_Ibrahim updted-2017Nader_Kamal_Farahat_Ibrahim updted-2017
Nader_Kamal_Farahat_Ibrahim updted-2017
nader Kamal
 
Modis Job Openings
Modis Job OpeningsModis Job Openings
Modis Job Openings
Brian Ward
 
Kota_Udayachandrakumar
Kota_UdayachandrakumarKota_Udayachandrakumar
Kota_Udayachandrakumar
udayachandrakumar kota
 
Apoorva_M_Resume
Apoorva_M_ResumeApoorva_M_Resume
Apoorva_M_Resume
Apoorva M
 
sarath_virtusa
sarath_virtusasarath_virtusa
sarath_virtusa
chanda4uonly
 
Resume (MES) Online
Resume (MES) OnlineResume (MES) Online
Resume (MES) Online
Larry Beifeld
 
denise white resume x
denise white resume xdenise white resume x
denise white resume x
Denise White
 
Resume
ResumeResume
Devaraj_SethuMadhavan_CV
Devaraj_SethuMadhavan_CVDevaraj_SethuMadhavan_CV
Devaraj_SethuMadhavan_CV
Devaraj Sethu Madhavan
 
Daniel Csencsits FINAL 1-27-16 (no address)
Daniel Csencsits FINAL 1-27-16 (no address)Daniel Csencsits FINAL 1-27-16 (no address)
Daniel Csencsits FINAL 1-27-16 (no address)
Daniel Csencsits
 
RESUME - Moustafa
RESUME - MoustafaRESUME - Moustafa
RESUME - Moustafa
Moustafa Chitt
 
Kenneth Paulsen Resume 2015-HP-1
Kenneth Paulsen Resume 2015-HP-1Kenneth Paulsen Resume 2015-HP-1
Kenneth Paulsen Resume 2015-HP-1
Kenneth Paulsen
 
Camunda Roadshow 2019, Praxisbericht Wien: Migration von Legacy workflow Syst...
Camunda Roadshow 2019, Praxisbericht Wien: Migration von Legacy workflow Syst...Camunda Roadshow 2019, Praxisbericht Wien: Migration von Legacy workflow Syst...
Camunda Roadshow 2019, Praxisbericht Wien: Migration von Legacy workflow Syst...
camunda services GmbH
 
Saura Jyoti Dhar - Resume
Saura Jyoti Dhar - ResumeSaura Jyoti Dhar - Resume
Saura Jyoti Dhar - Resume
Saura Jyoti Dhar
 

What's hot (20)

ResumeMaster2015
ResumeMaster2015ResumeMaster2015
ResumeMaster2015
 
Operational Efficiency Increases by 40% for Multinational Hotel Chain
Operational Efficiency Increases by 40% for Multinational Hotel ChainOperational Efficiency Increases by 40% for Multinational Hotel Chain
Operational Efficiency Increases by 40% for Multinational Hotel Chain
 
Preeti Sharma tech
Preeti Sharma techPreeti Sharma tech
Preeti Sharma tech
 
Resume
ResumeResume
Resume
 
Jian Zhang Resume 2014
Jian Zhang Resume 2014Jian Zhang Resume 2014
Jian Zhang Resume 2014
 
Lavanya-Resume 10+
Lavanya-Resume 10+Lavanya-Resume 10+
Lavanya-Resume 10+
 
Nader_Kamal_Farahat_Ibrahim updted-2017
Nader_Kamal_Farahat_Ibrahim updted-2017Nader_Kamal_Farahat_Ibrahim updted-2017
Nader_Kamal_Farahat_Ibrahim updted-2017
 
Modis Job Openings
Modis Job OpeningsModis Job Openings
Modis Job Openings
 
Kota_Udayachandrakumar
Kota_UdayachandrakumarKota_Udayachandrakumar
Kota_Udayachandrakumar
 
Apoorva_M_Resume
Apoorva_M_ResumeApoorva_M_Resume
Apoorva_M_Resume
 
sarath_virtusa
sarath_virtusasarath_virtusa
sarath_virtusa
 
Resume (MES) Online
Resume (MES) OnlineResume (MES) Online
Resume (MES) Online
 
denise white resume x
denise white resume xdenise white resume x
denise white resume x
 
Resume
ResumeResume
Resume
 
Devaraj_SethuMadhavan_CV
Devaraj_SethuMadhavan_CVDevaraj_SethuMadhavan_CV
Devaraj_SethuMadhavan_CV
 
Daniel Csencsits FINAL 1-27-16 (no address)
Daniel Csencsits FINAL 1-27-16 (no address)Daniel Csencsits FINAL 1-27-16 (no address)
Daniel Csencsits FINAL 1-27-16 (no address)
 
RESUME - Moustafa
RESUME - MoustafaRESUME - Moustafa
RESUME - Moustafa
 
Kenneth Paulsen Resume 2015-HP-1
Kenneth Paulsen Resume 2015-HP-1Kenneth Paulsen Resume 2015-HP-1
Kenneth Paulsen Resume 2015-HP-1
 
Camunda Roadshow 2019, Praxisbericht Wien: Migration von Legacy workflow Syst...
Camunda Roadshow 2019, Praxisbericht Wien: Migration von Legacy workflow Syst...Camunda Roadshow 2019, Praxisbericht Wien: Migration von Legacy workflow Syst...
Camunda Roadshow 2019, Praxisbericht Wien: Migration von Legacy workflow Syst...
 
Saura Jyoti Dhar - Resume
Saura Jyoti Dhar - ResumeSaura Jyoti Dhar - Resume
Saura Jyoti Dhar - Resume
 

Viewers also liked

JetBlue Airways and social media
JetBlue Airways and social mediaJetBlue Airways and social media
JetBlue Airways and social media
Andi Narvaez
 
JetBlue Airways Corp. - February 2013
JetBlue Airways Corp. - February 2013JetBlue Airways Corp. - February 2013
JetBlue Airways Corp. - February 2013
Nick Poling
 
Gartner 360 Summit - JetBlue Case Study
Gartner 360 Summit - JetBlue Case StudyGartner 360 Summit - JetBlue Case Study
Gartner 360 Summit - JetBlue Case Study
Burke Powers
 
Jet blue airways managing growth
Jet blue airways managing growthJet blue airways managing growth
Jet blue airways managing growth
Abhishek Mishra
 
Strategic analysis of jet blue airlines us
Strategic analysis of jet blue airlines usStrategic analysis of jet blue airlines us
Strategic analysis of jet blue airlines us
Kshitij Shrivastava
 
Four actions framework of blue ocean applied to jet blue
Four actions framework of blue ocean applied to jet blueFour actions framework of blue ocean applied to jet blue
Four actions framework of blue ocean applied to jet blue
Neil Kizhakayil George
 
Jetblue Midterm Project_sgay.Pdf
Jetblue Midterm Project_sgay.PdfJetblue Midterm Project_sgay.Pdf
Jetblue Midterm Project_sgay.Pdf
Sarah Kuntsal
 
jetBlue Media Plan
jetBlue Media PlanjetBlue Media Plan
jetBlue Media Plan
tomburr2
 
Case 3 strategic management
Case 3 strategic managementCase 3 strategic management
Case 3 strategic management
Sharun Dewi Moorthy
 
Jetblue Airways- Intro, SWOT, 5 Generic, Porter's 5, Key Sucess Factors etc
Jetblue Airways- Intro, SWOT, 5 Generic, Porter's 5, Key Sucess Factors etcJetblue Airways- Intro, SWOT, 5 Generic, Porter's 5, Key Sucess Factors etc
Jetblue Airways- Intro, SWOT, 5 Generic, Porter's 5, Key Sucess Factors etc
Arshed Aydrose
 
Jetblue airways ppt presentation
Jetblue airways ppt presentationJetblue airways ppt presentation
Jetblue airways ppt presentation
Monica Ceasar
 
JetBlue case study
JetBlue case studyJetBlue case study
JetBlue case study
Mohamed Zaid
 
Jet Blue case study
Jet Blue case studyJet Blue case study
Jet Blue case study
Joe Brennan, Ph.D.
 
Jet Blue Airways - Strategic Management Case Study
Jet Blue Airways - Strategic Management Case StudyJet Blue Airways - Strategic Management Case Study
Jet Blue Airways - Strategic Management Case Study
salmanchd
 
Organizational development case study
Organizational development case studyOrganizational development case study
Organizational development case study
Najmina Md Isa
 
Why JetBlue Added First Class to its Transcontinental Flights
Why JetBlue Added First Class to its Transcontinental FlightsWhy JetBlue Added First Class to its Transcontinental Flights
Why JetBlue Added First Class to its Transcontinental Flights
Dexter King, MBA
 
Jet Blue
Jet BlueJet Blue
Jet Blue
Meenakshi
 
Service Recovery Jet Blue & Lion Air
Service Recovery Jet Blue & Lion AirService Recovery Jet Blue & Lion Air
Service Recovery Jet Blue & Lion Air
Frisca Listyaningtyas
 
Jet Blue : A Strategic Management Case Study
Jet Blue : A Strategic Management Case StudyJet Blue : A Strategic Management Case Study
Jet Blue : A Strategic Management Case Study
fawadsiddequi
 

Viewers also liked (19)

JetBlue Airways and social media
JetBlue Airways and social mediaJetBlue Airways and social media
JetBlue Airways and social media
 
JetBlue Airways Corp. - February 2013
JetBlue Airways Corp. - February 2013JetBlue Airways Corp. - February 2013
JetBlue Airways Corp. - February 2013
 
Gartner 360 Summit - JetBlue Case Study
Gartner 360 Summit - JetBlue Case StudyGartner 360 Summit - JetBlue Case Study
Gartner 360 Summit - JetBlue Case Study
 
Jet blue airways managing growth
Jet blue airways managing growthJet blue airways managing growth
Jet blue airways managing growth
 
Strategic analysis of jet blue airlines us
Strategic analysis of jet blue airlines usStrategic analysis of jet blue airlines us
Strategic analysis of jet blue airlines us
 
Four actions framework of blue ocean applied to jet blue
Four actions framework of blue ocean applied to jet blueFour actions framework of blue ocean applied to jet blue
Four actions framework of blue ocean applied to jet blue
 
Jetblue Midterm Project_sgay.Pdf
Jetblue Midterm Project_sgay.PdfJetblue Midterm Project_sgay.Pdf
Jetblue Midterm Project_sgay.Pdf
 
jetBlue Media Plan
jetBlue Media PlanjetBlue Media Plan
jetBlue Media Plan
 
Case 3 strategic management
Case 3 strategic managementCase 3 strategic management
Case 3 strategic management
 
Jetblue Airways- Intro, SWOT, 5 Generic, Porter's 5, Key Sucess Factors etc
Jetblue Airways- Intro, SWOT, 5 Generic, Porter's 5, Key Sucess Factors etcJetblue Airways- Intro, SWOT, 5 Generic, Porter's 5, Key Sucess Factors etc
Jetblue Airways- Intro, SWOT, 5 Generic, Porter's 5, Key Sucess Factors etc
 
Jetblue airways ppt presentation
Jetblue airways ppt presentationJetblue airways ppt presentation
Jetblue airways ppt presentation
 
JetBlue case study
JetBlue case studyJetBlue case study
JetBlue case study
 
Jet Blue case study
Jet Blue case studyJet Blue case study
Jet Blue case study
 
Jet Blue Airways - Strategic Management Case Study
Jet Blue Airways - Strategic Management Case StudyJet Blue Airways - Strategic Management Case Study
Jet Blue Airways - Strategic Management Case Study
 
Organizational development case study
Organizational development case studyOrganizational development case study
Organizational development case study
 
Why JetBlue Added First Class to its Transcontinental Flights
Why JetBlue Added First Class to its Transcontinental FlightsWhy JetBlue Added First Class to its Transcontinental Flights
Why JetBlue Added First Class to its Transcontinental Flights
 
Jet Blue
Jet BlueJet Blue
Jet Blue
 
Service Recovery Jet Blue & Lion Air
Service Recovery Jet Blue & Lion AirService Recovery Jet Blue & Lion Air
Service Recovery Jet Blue & Lion Air
 
Jet Blue : A Strategic Management Case Study
Jet Blue : A Strategic Management Case StudyJet Blue : A Strategic Management Case Study
Jet Blue : A Strategic Management Case Study
 

Similar to Optimum Solutions Consultant - JetBlue Airways ERP Project

PraveenResumeF4Miami
PraveenResumeF4MiamiPraveenResumeF4Miami
PraveenResumeF4Miami
Praveen Mathew
 
Resume_New
Resume_NewResume_New
Resume_New
ROSHAN MISHRA
 
Amol Aswar
Amol AswarAmol Aswar
Amol Aswar
Amol Aswar
 
Resume_Atanu_Ganguly
Resume_Atanu_GangulyResume_Atanu_Ganguly
Resume_Atanu_Ganguly
Atanu Ganguly
 
Demiana-Anis-Resume
Demiana-Anis-ResumeDemiana-Anis-Resume
Demiana-Anis-Resume
Demiana Anis
 
Anuradha_Resume_10 Years
Anuradha_Resume_10 YearsAnuradha_Resume_10 Years
Anuradha_Resume_10 Years
Anuradha Appikatla
 
Custom Software Engineering & Business Process Operations
Custom Software Engineering & Business Process OperationsCustom Software Engineering & Business Process Operations
Custom Software Engineering & Business Process Operations
Athens Technology Center
 
Global Squad Leader - Resume
Global Squad Leader - ResumeGlobal Squad Leader - Resume
Global Squad Leader - Resume
Srivathsan (Sri) Rangarajan, PMI-ACP®
 
AyyappaKumar_AutomationTesting
AyyappaKumar_AutomationTestingAyyappaKumar_AutomationTesting
AyyappaKumar_AutomationTesting
Ayyappa Kumar
 
5.10 years Expetience in Asp.net with MVC
5.10 years Expetience in Asp.net with MVC5.10 years Expetience in Asp.net with MVC
5.10 years Expetience in Asp.net with MVC
prashant zope
 
Suchasmita Padhi Resume
Suchasmita Padhi ResumeSuchasmita Padhi Resume
Suchasmita Padhi Resume
Suchasmita Padhi
 
Babus Resume
Babus ResumeBabus Resume
Babus Resume
ram p
 
Abdus Salam
Abdus SalamAbdus Salam
Abdus Salam
abdus salam
 
RajendraLK_13_Years_PeopleSoft
RajendraLK_13_Years_PeopleSoftRajendraLK_13_Years_PeopleSoft
RajendraLK_13_Years_PeopleSoft
Rajendra Kalvikatte
 
ITA2323_Final_SHOWREADY_28April2015
ITA2323_Final_SHOWREADY_28April2015ITA2323_Final_SHOWREADY_28April2015
ITA2323_Final_SHOWREADY_28April2015
Paul Kirch
 
YatinDixit
YatinDixitYatinDixit
YatinDixit
Yatin Dixit
 
K Chandrasekaran
K ChandrasekaranK Chandrasekaran
K Chandrasekaran
Chandru Sekaran
 
LOAY FARAHAT PMP
LOAY FARAHAT PMPLOAY FARAHAT PMP
LOAY FARAHAT PMP
Loay Farahat
 
Ashalatha Nagappa
Ashalatha NagappaAshalatha Nagappa
Ashalatha Nagappa
asha latha
 
technical project manager 12 yrs
technical project manager 12 yrstechnical project manager 12 yrs
technical project manager 12 yrs
Nitin Katlana
 

Similar to Optimum Solutions Consultant - JetBlue Airways ERP Project (20)

PraveenResumeF4Miami
PraveenResumeF4MiamiPraveenResumeF4Miami
PraveenResumeF4Miami
 
Resume_New
Resume_NewResume_New
Resume_New
 
Amol Aswar
Amol AswarAmol Aswar
Amol Aswar
 
Resume_Atanu_Ganguly
Resume_Atanu_GangulyResume_Atanu_Ganguly
Resume_Atanu_Ganguly
 
Demiana-Anis-Resume
Demiana-Anis-ResumeDemiana-Anis-Resume
Demiana-Anis-Resume
 
Anuradha_Resume_10 Years
Anuradha_Resume_10 YearsAnuradha_Resume_10 Years
Anuradha_Resume_10 Years
 
Custom Software Engineering & Business Process Operations
Custom Software Engineering & Business Process OperationsCustom Software Engineering & Business Process Operations
Custom Software Engineering & Business Process Operations
 
Global Squad Leader - Resume
Global Squad Leader - ResumeGlobal Squad Leader - Resume
Global Squad Leader - Resume
 
AyyappaKumar_AutomationTesting
AyyappaKumar_AutomationTestingAyyappaKumar_AutomationTesting
AyyappaKumar_AutomationTesting
 
5.10 years Expetience in Asp.net with MVC
5.10 years Expetience in Asp.net with MVC5.10 years Expetience in Asp.net with MVC
5.10 years Expetience in Asp.net with MVC
 
Suchasmita Padhi Resume
Suchasmita Padhi ResumeSuchasmita Padhi Resume
Suchasmita Padhi Resume
 
Babus Resume
Babus ResumeBabus Resume
Babus Resume
 
Abdus Salam
Abdus SalamAbdus Salam
Abdus Salam
 
RajendraLK_13_Years_PeopleSoft
RajendraLK_13_Years_PeopleSoftRajendraLK_13_Years_PeopleSoft
RajendraLK_13_Years_PeopleSoft
 
ITA2323_Final_SHOWREADY_28April2015
ITA2323_Final_SHOWREADY_28April2015ITA2323_Final_SHOWREADY_28April2015
ITA2323_Final_SHOWREADY_28April2015
 
YatinDixit
YatinDixitYatinDixit
YatinDixit
 
K Chandrasekaran
K ChandrasekaranK Chandrasekaran
K Chandrasekaran
 
LOAY FARAHAT PMP
LOAY FARAHAT PMPLOAY FARAHAT PMP
LOAY FARAHAT PMP
 
Ashalatha Nagappa
Ashalatha NagappaAshalatha Nagappa
Ashalatha Nagappa
 
technical project manager 12 yrs
technical project manager 12 yrstechnical project manager 12 yrs
technical project manager 12 yrs
 

Recently uploaded

Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women MagazineEllen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
CIOWomenMagazine
 
The latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from NewentideThe latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from Newentide
JoeYangGreatMachiner
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
GraceKohler1
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
concepsionchomo153
 
Science Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around UsScience Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around Us
PennapaKeavsiri
 
AI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your BusinessAI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your Business
Arijit Dutta
 
Prescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPTPrescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPT
Freelance
 
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
irhcs
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
ZevinAttisha
 
IMG_20240615_091110.pdf dpboss guessing
IMG_20240615_091110.pdf dpboss  guessingIMG_20240615_091110.pdf dpboss  guessing
Lukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptxLukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptx
pavelborek
 
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
dpbossdpboss69
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
katiejasper96
 
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...
Herman Kienhuis
 
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Niswey
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
State of D2C in India: A Logistics Update
State of D2C in India: A Logistics UpdateState of D2C in India: A Logistics Update
State of D2C in India: A Logistics Update
RedSeer
 
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
taqyea
 
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper PresentationKirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip
 

Recently uploaded (20)

Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women MagazineEllen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
 
The latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from NewentideThe latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from Newentide
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
 
Science Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around UsScience Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around Us
 
AI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your BusinessAI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your Business
 
Prescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPTPrescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPT
 
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
 
IMG_20240615_091110.pdf dpboss guessing
IMG_20240615_091110.pdf dpboss  guessingIMG_20240615_091110.pdf dpboss  guessing
IMG_20240615_091110.pdf dpboss guessing
 
Lukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptxLukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptx
 
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
 
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...
 
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
State of D2C in India: A Logistics Update
State of D2C in India: A Logistics UpdateState of D2C in India: A Logistics Update
State of D2C in India: A Logistics Update
 
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
 
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper PresentationKirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper Presentation
 

Optimum Solutions Consultant - JetBlue Airways ERP Project

  • 1. Optimum Solutions Consultants JetBlue Airways Implementation Project
  • 2. Project Objective: This project is to successfully, implement an ERP system (mySAP) powered by the SAP NetWeaver™ platform for this particular client (JetBlue Airway). The commissioned date to start was on April 04, 2011, and completed by February 19, 2014. The implementation of this ERP system will help the client achieve the business agility it needs and eliminate obstacles of technology integration as the company grows. It will also help with the improvement of Customer Relationships and a more efficient relationship with their vendors. Yet more importantly, business operations will show a decrease in time and expense, while at the same time allow better decision-making process with fewer errors.
  • 3. JetBlue Airways Corporation  JetBlue is one of the nation's leading low-cost airlines and is based out of New York's JFK Airport.  JetBlue flies up to 600 flights a day to 63 cities including all three NYC airports. In five years, the company has become the biggest airline serving JFK and specializes in non-stop trips from New York to the West Coast and Florida.  They established the idea of bringing humanity back to air travel and strive to make every part of the passengers experience as simple and as pleasant as possible.
  • 4. JetBlue’s Situation  On February 14, 2007, a JetBlue flight from John F. Kennedy International Airport to Cancun, Mexico was delayed on the ramp in a snowstorm, keeping passengers on the plane for nearly nine hours. Throughout that day, at least nine other JetBlue aircraft were also stranded on the tarmac, keeping the passengers all on board. Four days later, JetBlue was still not operating normally, canceling nearly all flights using Embraer 190 aircraft.  Most of the problems were related to staffing issues. JetBlue, which books 80% of its tickets online, did not have enough reservations agents on its toll-free line to handle all of the rescheduling.  At Kennedy Airport, there was not enough trained staff to work on rebooking.  And the unit in charge of locating pilots and flight attendants and assigning them to their next flight was overwhelmed.
  • 5. ERP Project Phases  Initiation  Project planning  Analysis and Process design  Realization  Transition  Operations from “go live” to support
  • 6. Phase 1 Project Preparation (Initiation):  Team prepares for a kick-off meeting, and undertakes planning and preparation of Study Development, Testing, Approval, and Implementation.
  • 7. Phase 2 Systems Requirement and Specification and Business Blue Print (Project Planning)  workshop is conducted with key stakeholders to define project objective, scope time schedule etc.
  • 8. Communication plan Audience Content Event Responsible Medium Client/Customers Projectoverview(basic understanding,highlevel timeline) toinclude successes/issues. Regularly-scheduledteam meetings(1/mo); And asneeded Projectmanager • Face-to-face; • Phone; • Email. Vendors/suppliers Anupdateon deliveryof equipment& service progress. Daily/weekly Productmanager • Phone • Face-to-face ProjectSteeringTeam Policy-relatedissues; Projectprogress. Regularly-scheduledteam meetingsandasneeded. Projectleader& taskleader • Face-to-face; • Email. InternalStakeholders Projectoverview& progress. Projectdeliverables weekly Projectleader • Face-to-face; • Email.
  • 9. Risk & Quality Issues Quality Objectives Quality Planning Quality Control Quality Assurance Identify the work (tasks, dependencies, and deliverables), effort (hours), schedules (start and end dates) and resources (people, equipment, and funding) required to meet the specified objective. According to specifications and standards Deliverable Reviews and Acceptance Process Ensuring the project methodologies, standards and controls are appropriate and reasonable for the project environment. Establish a baseline against which to measure progress. On time/within Budget Project Quality Review. Saphire IV & V (Independent Verification and Validation) Plan Software development SDLC SDLC SDLC
  • 10. Project Objectives • Implementation of enterprise software • Ensure the software meets the needs for each level of user. • Centralize ERP system. • Eliminate current (outdated) software. • Train the 8000 employees for their level of software. • Determine the best possible solution for sustaining pending the completion of the project.
  • 11. Tools & Technology • SAP ECC 5.0® Human Capital Management; • SAP NetWeaver Portal; • Performance Management (Objective Setting and Appraisals); • Enterprise Compensation Management; • E-Recruiting 6.00; • Worklogix Accelerated Suite for Performance Management and Enterprise Compensation.
  • 12. Budget/Cost Structure • Software licenses for 8000 users $20,000 • Maintenance for the software • Hardware (server) --------- • Maintenance on the hardware --------- • Hardware (workstations) annual cost: $ 15,000 • Infrastructure annual cost: $ 25,000 • Changes to software • Interfaces to several systems • Data conversion (from old to new system) •
  • 13. Phase 3 Systems Development and Testing : • Creation of Database, Input and Interface Forms and Queries. • Programs are written as per business process requirement as defined in the Business Plan. • Each module is tested and views of the client are noted.
  • 14. Phase 4 Project Realization • Implementation of the entire business process requirement as per the Business Blue Print. • Holding of integration test and designing of end user documentation.
  • 15. Phase 5 Final Preparation (Transition): • Covers user and administrator training, system management, activities to finalized go-live readiness.
  • 16. Phase 6 “Go-live” and support • Moving the project from project orientation and pre-production environment to live production operation. • Key elements include setting up production support, monitoring systems transaction and optimization of overall systems performances as well as the completion of all documentations.
  • 17. Lessons learned? “Every wrong decision is in fact a correct decision but taken at a wrong time so my friends don't regret... don't stop... keep walking ahead.”
  • 18. Thank You for your time…..