The document summarizes the preliminary results of an OECD review of the UK's PPP governance framework. It finds that the UK has a comprehensive institutional framework for PPPs that aligns with OECD principles on transparency, value for money, and budgeting. Key aspects include the National Infrastructure Plan for prioritizing projects, guidance in the Green Book for evaluating delivery options, and transparency tools like the Whole of Government Accounts. The framework has evolved over time, with reforms through the PF2 model, but continues to provide integrity in the procurement process.
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
5_Procurement, conflict of interest and sub-grantingcsdialogue
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
1_Introduction to Full Application preparationcsdialogue
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
5_Procurement, conflict of interest and sub-grantingcsdialogue
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
1_Introduction to Full Application preparationcsdialogue
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
PPP for regional development - Michael BURNETT, EIPAOECD Governance
This presentation was made by Michael BURNETT, EIPA, at the 11th Annual Meeting of the OECD Network of Senior PPP and Infrastructure Officials held at the OECD, Paris, on 27 March 2018
3_Logframe, problem and objectives, indicators, assumptionscsdialogue
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
Presentation titled, 'Improving Public Investment Management in the Caribbean,' delivered by Dr. Wendell Samuel, CARTAC Center Coordinator at the Conference, 'Project Cycle Management Conference - A Cornerstone of Implementation and Delivery,' September 2019 in St. George's Grenada.
Session 3 focuses on the regulatory treatment of investments and incentives for investments. Finding an adequate balance between efficient and sufficient investments is one of the major tasks for regulators. They can use various approaches to assess and encourage investments necessary to provide reliable and efficient services. In this session we explain the types of investments and their integration in the regulatory price control. We also present different regulatory incentive schemes to encourage investments. Finally, we provide examples from international regulatory practice.
How to write the full application to the EU_info session on 23 july 2014 in kievISAR Ednannia
The informational session devoted to preparing full application form for the call for proposals " Neighbourhood Civil Society Facility 2013 – Ukraine " (EuropeAid/134433/L/ACT/UA).
The event held on July 23, 2014, from 10.00 to 17.30 in the premises of the Delegation of the European Union to Ukraine (Kyiv, Volodymyrska Street, 101).
The main speakers of the InfoSession are:
- Natasa Gospodjinacki
- Volodymyr Sheyhus
- Andriy Donets
- Natalia Shamray
The Info session is conducted by ISAR "Ednannia" in the framework of the Civil Society. Dialogue for progress Project, funded by EU.
Developing successful, bankable pp ps through a common languageMark Constable
Public-Private Partnerships (PPPs) play a key role in delivering major projects and services. Particularly in developing countries, PPPs are critical to major development and infrastructure projects as government budgets alone cannot support them. As is the case in any project environment, effective stakeholder communication and engagement is crucial to an initiative's success.
The PPP Certification Program Guide (referred to as the PPP Guide) is the Body of Knowledge (BoK) on PPPs. An innovation of the World Bank Group and various multi-lateral development banks (MDBs), it’s designed to support public officials and their advisors in implementing efficient, sustainable PPPs.
In this webinar - delivered with our partners at Training ByteSize - we’ll look at how the Guide offers clear guidance and a common language for effective stakeholder communication, supporting successful PPP initiatives and capacity building. The webinar will be relevant to professionals from both public and private sectors involved in PPP projects and initiatives, in particular those with a role in managing and/or communicating with stakeholders.
Watch the recording here: https://apmg-international.com/events/developing-successful-bankable-ppps-through-common-language
Investment planning and public investment plans: Inssues and Best PracticesJean-Marc Lepain
This presentation goes through the issues in investment appraisal that result in poor outcomes. It introduces Public Investment Plans as a systematic methodology to address these issues.
Towards an effective governance framework for infrastructure - Ronnie Downes,...OECD Governance
This presentation was made by Ronnie Downes, OECD, at the 11th Annual Meeting of Central, Eastern and South-Eastern Senior Budget Officials (CESEE SBO) held in Warsaw, Poland, on 21-22 May 2015.
We look forward to discussing your needs and interests in IPSAS in the coming months. You can contact me email Mark at m.neal67@ahoo.com Or +1 780-297-9569
Presented at the Project Steering Committee Meeting, jointly organised by the OECD-MENA Investment Programme and Libya Entreprise. Tripoli, Libya, 9 September 2013
Burness NHS Procurement Seminar - 30 March 2010Elaine Creamer
How does the NHS ensure that it obtains best value when procuring its construction needs? No doubt this will be a question that will increasingly concern the NHS should they be called upon to bear a share of the widely anticipated cuts in public spending.
Over the last 18 months, the NHS has sought to achieve best value through the application of Frameworks Scotland. HFS Frameworks Scotland operates on a design and build basis along with a target cost payment mechanism. Will HFS Frameworks Scotland always be the most appropriate way to procure the construction needs of the
NHS? Can local frameworks be used to procure projects for which Frameworks Scotland is not suitable? Burness, with the assistance of procurement specialists within the NHS and the private sector, will be offering answers to these questions.
Frameworks are no longer the only option for the NHS and a new era of the hub is now dawning. How will hub operate and how will it interact with national and local frameworks? Burness, as legal advisors to the hub South East Territory, is ideally placed to offer views of these important issues.
PPP for regional development - Michael BURNETT, EIPAOECD Governance
This presentation was made by Michael BURNETT, EIPA, at the 11th Annual Meeting of the OECD Network of Senior PPP and Infrastructure Officials held at the OECD, Paris, on 27 March 2018
3_Logframe, problem and objectives, indicators, assumptionscsdialogue
How to write effective EU project proposals: Introduction to Full application preparation. Application Package for Applicants. Common mistakes.
Natasa Gospodjinacki
Kiev, 3-4 September 2015
Presentation titled, 'Improving Public Investment Management in the Caribbean,' delivered by Dr. Wendell Samuel, CARTAC Center Coordinator at the Conference, 'Project Cycle Management Conference - A Cornerstone of Implementation and Delivery,' September 2019 in St. George's Grenada.
Session 3 focuses on the regulatory treatment of investments and incentives for investments. Finding an adequate balance between efficient and sufficient investments is one of the major tasks for regulators. They can use various approaches to assess and encourage investments necessary to provide reliable and efficient services. In this session we explain the types of investments and their integration in the regulatory price control. We also present different regulatory incentive schemes to encourage investments. Finally, we provide examples from international regulatory practice.
How to write the full application to the EU_info session on 23 july 2014 in kievISAR Ednannia
The informational session devoted to preparing full application form for the call for proposals " Neighbourhood Civil Society Facility 2013 – Ukraine " (EuropeAid/134433/L/ACT/UA).
The event held on July 23, 2014, from 10.00 to 17.30 in the premises of the Delegation of the European Union to Ukraine (Kyiv, Volodymyrska Street, 101).
The main speakers of the InfoSession are:
- Natasa Gospodjinacki
- Volodymyr Sheyhus
- Andriy Donets
- Natalia Shamray
The Info session is conducted by ISAR "Ednannia" in the framework of the Civil Society. Dialogue for progress Project, funded by EU.
Developing successful, bankable pp ps through a common languageMark Constable
Public-Private Partnerships (PPPs) play a key role in delivering major projects and services. Particularly in developing countries, PPPs are critical to major development and infrastructure projects as government budgets alone cannot support them. As is the case in any project environment, effective stakeholder communication and engagement is crucial to an initiative's success.
The PPP Certification Program Guide (referred to as the PPP Guide) is the Body of Knowledge (BoK) on PPPs. An innovation of the World Bank Group and various multi-lateral development banks (MDBs), it’s designed to support public officials and their advisors in implementing efficient, sustainable PPPs.
In this webinar - delivered with our partners at Training ByteSize - we’ll look at how the Guide offers clear guidance and a common language for effective stakeholder communication, supporting successful PPP initiatives and capacity building. The webinar will be relevant to professionals from both public and private sectors involved in PPP projects and initiatives, in particular those with a role in managing and/or communicating with stakeholders.
Watch the recording here: https://apmg-international.com/events/developing-successful-bankable-ppps-through-common-language
Investment planning and public investment plans: Inssues and Best PracticesJean-Marc Lepain
This presentation goes through the issues in investment appraisal that result in poor outcomes. It introduces Public Investment Plans as a systematic methodology to address these issues.
Towards an effective governance framework for infrastructure - Ronnie Downes,...OECD Governance
This presentation was made by Ronnie Downes, OECD, at the 11th Annual Meeting of Central, Eastern and South-Eastern Senior Budget Officials (CESEE SBO) held in Warsaw, Poland, on 21-22 May 2015.
We look forward to discussing your needs and interests in IPSAS in the coming months. You can contact me email Mark at m.neal67@ahoo.com Or +1 780-297-9569
Presented at the Project Steering Committee Meeting, jointly organised by the OECD-MENA Investment Programme and Libya Entreprise. Tripoli, Libya, 9 September 2013
Burness NHS Procurement Seminar - 30 March 2010Elaine Creamer
How does the NHS ensure that it obtains best value when procuring its construction needs? No doubt this will be a question that will increasingly concern the NHS should they be called upon to bear a share of the widely anticipated cuts in public spending.
Over the last 18 months, the NHS has sought to achieve best value through the application of Frameworks Scotland. HFS Frameworks Scotland operates on a design and build basis along with a target cost payment mechanism. Will HFS Frameworks Scotland always be the most appropriate way to procure the construction needs of the
NHS? Can local frameworks be used to procure projects for which Frameworks Scotland is not suitable? Burness, with the assistance of procurement specialists within the NHS and the private sector, will be offering answers to these questions.
Frameworks are no longer the only option for the NHS and a new era of the hub is now dawning. How will hub operate and how will it interact with national and local frameworks? Burness, as legal advisors to the hub South East Territory, is ideally placed to offer views of these important issues.
This presentation was made by Ana-Maria Ruiz Rivadeneira, OECD, at the 12th Annual Meeting of the OECD Network of Senior PPP and Infrastructure Officials, held in Paris on 16 April 2019.
Presentation "Auditing PPP- Lessons learned from the French experience" made during the SIGMA workshop on Auditing Public Private Partnerships and Concessions. Ankara, 2-3 May 2018. Presentation made by Frederic Angermann, SIGMA.
Join senior members from the OECD's Centre for Tax Policy and Administration (CTPA) as they give the latest update on the OECD/G20 BEPS Project.
Topics covered:
- Progress report on the BEPS deliverables
- Discussion drafts and public consultations (consult the updated calendar)
- Developing countries’ engagement and input
- Schedule for release of finalised BEPS package
Towards and Integrated Governance Framework for Infrastructure by Ian Hawkesw...OECD Governance
Presentation by Ian Hawkesworth at the 7th annual meeting of the MENA Senior Budget Officials held on 10-11 December 2014. Find more information at http://www.oecd.org/gov/budgeting
Prioritisation and selection of public investment projects - James BALLINGALL...OECD Governance
This presentation was made by James BALLINGALL, United Kingdom, at the 11th Annual Meeting of the OECD Network of Senior PPP and Infrastructure Officials held at the OECD, Paris, on 27 March 2018
PPP disclosure - A view from the UK audit office - Daniel Fairhead, United Ki...OECD Governance
Presentation made by Daniel Fairhead, National Audit Office, United Kingdom, at the 9th annual network meeting of Senior Infrastructure & PPP Officials held at the OECD, Paris, on 1 March 2016
Join senior members from the OECD's Centre for Tax Policy and Administration (CTPA) for a webcast as they give the latest update on the OECD/G20 BEPS Project.
View the webcast: www.oecd.org/ctp/beps-webcasts.htm
Smart Republic - Multi Partner Platform for Collaborative Development of Smart Cities and Smart Villages.
Smart Republic 2018 is envisaged as a Multi Partner global forum to deliberate on the collaboration framework between government and multiple agencies like the World Bank, UN Habitat, UN Global Compact, Asian Development Bank, Industry and academia for achieving shared goal of making India a Smart Republic by 2022. Smart republic forum will focus on innovative ICT and New Media platforms and deployment of best practices to catalyse effective, coordinated and results-based implementation of 100 Smart Cities Program, AMRUT, HRIDAY and RURBAN missions to achieve the Sustainable Development Goals (SDGs).
AVEVA ProCon FPSO Europe Congress 2016AVEVA ProCon
Rock, Paper, Scissors
A Case Study on complementing cost-savings with strong governance and capital discipline
A recent survey* of 9 FPSO projects identified a combined 38% cost overrun totaling $2.5bn in wasted capital. One of the identified causal factors behind this dead-weight additional capital was “a lack of clarity regarding contract responsibilities”.
8over8 presented a case study where efficiency gains were generated in the world’s first FLNG project by implementing a proven system of strong governance and commercial discipline. The result was connected decision making and reduced incidence of conflict and claims amongst stakeholders in the world’s first FLNG project.
*Source: Douglas Westwood“ FPSO Industry at a Crossroads”- An Industry Whitepaper
To request a free audit visit http://info.8over8.com/contact-us/capital-savings-review/
For more information, visit http://www.8over8.com/procon-overview/
Towards an integrated governance framework for infrastructure - Ian Hawkeswor...OECD Governance
This presentation was made by Ian Hawkesworth, OECD, Thailand, at the 10th OECD-Asian Senior Budget Officials Annual Meeting held in Bangkok, Thailand, on 18-19 December 2014.
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...OECD Governance
Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
Using AI led assurance to deliver projects on time and on budget - D. Amratia...OECD Governance
Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)OECD Governance
Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...OECD Governance
Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...OECD Governance
Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...OECD Governance
Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...OECD Governance
Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmOECD Governance
Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...OECD Governance
Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...OECD Governance
Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...OECD Governance
Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
Presentation of OECD Government at a Glance 2023OECD Governance
Paris, 30 June, 2023
Presentation by Elsa Pilichowski, Director for Public Governance, OECD.
The 2023 edition of Government at a Glance provides a comprehensive overview of public governance and public administration practices in OECD Member and partner countries. It includes indicators on trust in public institutions and satisfaction with public services, as well as evidence on good governance practices in areas such as the policy cycle, budgeting, procurement, infrastructure planning and delivery, regulatory governance, digital government and open government data. Finally, it provides information on what resources public institutions use and how they are managed, including public finances, public employment, and human resources management. Government at a Glance allows for cross-country comparisons and helps identify trends, best practices, and areas for improvement in the public sector.
See: https://www.oecd.org/publication/government-at-a-glance/2023/
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...OECD Governance
Infographics from the OECD report "The Protection and Promotion of Civic Space Strengthening Alignment with International Standards and Guidance".
See: https://www.oecd.org/gov/the-protection-and-promotion-of-civic-space-d234e975-en.htm
OECD Publication "Building Financial Resilience
to Climate Impacts. A Framework for Governments to manage the risks of Losses and Damages.
Governments are facing significant climate-related risks from the expected increase in frequency and intensity of cyclones, floods, fires, and other climate-related extreme events. The report Building Financial Resilience to Climate Impacts: A Framework for Governments to Manage the Risks of Losses and Damages provides a strategic framework to help governments, particularly those in emerging market and developing economies, strengthen their capacity to manage the financial implications of climate-related risks. Published in December 2022.
OECD presentation "Strengthening climate and environmental considerations in infrastructure and budget appraisal tools"
by Margaux Lelong and Ana Maria Ruiz during the 9th Meeting of the OECD Paris Collaborative on Green Budgeting held on 17 and 18 of April 2023 in Paris.
OECD presentation "Building Financial Resilience to Climate Impacts. A Framework to Manage the Risks of Losses and Damages" by Andrew Blazey, Stéphane Jacobzone and Titouan Chassagne. Presented during the 9th Meeting of the OECD Paris Collaborative on Green Budgeting held on 17 and 18 of April 2023 in Paris
OECD Presentation "Financial reporting, sustainability information and assurance" by Peter Welch during the 5th Session during the 9th Meeting of the OECD Paris Collaborative on Green Budgeting held on 17 and 18 of April 2023 in Paris
Presentation "Developments in sovereign green bond markets" by Ms. Fatos Koc during the 4th Session of 9th Meeting of the OECD Paris Collaborative on Green Budgeting held on 17 and 18 of April 2023 in Paris.
OECD review of the PPP governance framework in the United-Kingdom: preliminary results
1. OECD REVIEW OF THE PPP
GOVERNANCE FRAMEWORK
IN THE UNITED KINGDOM:
PRELIMINARY RESULTS
Annual Meeting of Senior PPP and
Infrastructure Officials
23-24 MARCH, 2015
Paris, France
Ian Hawkesworth
Head, Capital Budgeting and PPPs
Budgeting and Public Expenditures Division
Public Governance and Territorial Development
Directorate, OECD
1
2. The OECD’s PPP Principles (2012) fall under three
main headings:
1. Establishing a clear, predictable and legitimate
institutional framework.
2. Grounding the selection of Public-Private
Partnerships in Value for Money.
3. Using the budgetary process transparently to
minimize fiscal risks.
2
Framework for analysis
3. In 2012, the UK introduced a new
private finance scheme : PF2
3
Some key characteristics of PF2 :
• Strengthened partnership through public equity stake in SPVs
• Greater flexibility through the exclusion of ‘soft’ services from contracts
• Faster and cheaper procurement through a new ambitious timetable (18
months)
• Improved VfM through more appropriate risk retention by the public sector
• Greater transparency through:
– New control total for PFI/PF2 commitments (GBP 70 billion until 2020)
– Private sector equity return information to be published
– New business case approval tracker available
• Introduction of funding competitions for a part of private sector equity to
attract long term investors
5. The UK possesses a comprehensive institutional
suite to manage capital investments
- Treasury approvals Points (TAPs)
for PPP appraisals
- Spending/budget department
- Public policy
- Planning, prioritisation and
enabling of infrastructure investment
in the UK
- Includes the PPP policy team (PPP
unit), strategy team (NIP), etc.
-Supreme audit institution
- ex-post reporting on PPP projects
and processes
- Include sub-national governments,
line Departments, and executive
agencies (ex Highways Authority)
- Responsible of PPP from planning
to exit
- Part of ERG
- Assurance process (incl. Gateway
Review)
- Commercial and operational
support to Departments
- Department for Communities
and Local Government
- Scottish Futures Trust
- Local Partnerships
5
HM Treasury
Contracting
Authorities
Infrastructure
UK (IUK)
National Audit
Office
Major Projects
Authority
Others
6. Principle 1: Ensure public awareness of the relative costs,
benefits and risks of PPPs as part of an integrated public-sector
infrastructure investment framework.
• The UK National Infrastructure Plan and the Top 40 is
a process and document well designed to ensure prioritisation,
transparency and linkages (see principle 4).
• Several mechanisms are in place to disclose commitment and
potential liabilities from PFI/PF2 contracts such as the Whole of
Government Accounts (WGA) and the Office of Budget
Responsibility (OBR)
• Broad public and private consultation about the limits of PFI
leading up to PF2 adoption
• The National Audit Office (NAO) plays a key role in informing the
public debate about PFIs
Transparency and open communication about the relative costs,
benefits and risks of PFIs is evident in the UK
6
7. Principle 2: Key institutional roles and responsibilities should
be maintained, and there are clear mandates and sufficient
resources to ensure a prudent procurement process.
• HM Treasury’s Infrastructure UK (IUK) is well capacitated and its
different units regularly advise the public sector with regards to the
appropriateness of PFIs
– Strengthened commercial capacity of IUK and other institutions
• A wide range of institutional support is available to contracting
authorities at the central level (IUK, MPA) and at the devolved
level (ex: SFT, LP).
• Public sector capacities are well established,
complementary, and roles clearly defined.
• Capacity to prepare, procure, and manage projects at the local level
can still be enhanced.
The institutional set up and public sector capabilities for PFIs and
capital projects generally are clear and coherent.
7
8. Principle 3: Ensure that all significant regulation affecting the
operation of Public-Private Partnerships is clear, transparent
and enforced.
• A constantly evolving framework of gradual adjustment and
refinement e.g. refinancing gains.
• There is no specific PPP law in the UK, but the government follows
contract law and EU procurement directives.
• No issues raised with regards to the regulatory framework of PPP
contracts (legal issues, enforcement, or other aspects).
• Steps have been taken to further strengthen the regulation of
PFI/Pf2 contracts
– more centralized procurement is emphasized under PF2
– new standardized suite of documentation issued
Rules affecting contracts are clear and enforced in the UK.
8
10. Principle 4: All investment projects should be prioritised at senior
political level.
• The UK National Infrastructure Plan (NIP) was put in place
since 2010 and
– presents a global government vision with respect to infrastructure
development in the UK.
– lays out the strategic need for investment in the UK.
– creates transparency about the project pipeline and priority
investments in order to show that there is an ongoing market.
– ensures delivery progress by measuring and publishing reports on
developments.
• The ‘Top 40’ list of projects on the NIP has been developed in an
iterative process with the line Departments, HM Treasury and the
Cabinet office.
The NIP and its ‘Top 40’is a good example of a cabinet
sanctioned priority process for projects. 10
11. Principle 5: Carefully investigate which investment method is
likely to yield most value for money.
• The UK Green Book provides comprehensive guidance for the appraisal of all
projects receiving central funding.
• The business case is structured around 5 aspects to ensure that projects are:
– supported by a robust argument for change – the Strategic Case;
– optimise Value for Money – the Economic Case;
– commercially viable (where relevant) – the Commercial Case;
– is financially affordable – the Financial Case; and,
– can be delivered successfully – the Management Case.
• The centrally developed value for money test (PSC) was removed in favor of
contracting authorities developing their own quantitative evaluation of projects as
an integral part of the business case
– The PSC tool was never intended as a “pass-or-fail” test, but it created a
tendency to over-focus attention on the numerical result of the exercise
• Three stages of business case approval by HM Treasury: Strategic Outline
Business Case, Outline Business Case, and Full Business Case (see table)
A level playing field exists for the appraisal, comparison, and selection of the
delivery mode of projects in the UK via the Green Book. 11
12. The appraisal and evaluation of projects is
complemented by an independent gateway
review process
12
Source: Cabinet Office & HM Treasury (2011), Major Project approval and assurance guidance, April 2011
Table: Stages of Treasury Approval Points
Treasury Approval Point
(TAP)
Scope and timing How does the TAP relate to
MPA approval
Strategic Outline Business
Case (SOBC) - Project
initiation stage
- All new Major Projects to ensure
strategic fit, value for money and
deliverability.
- Approval required before any public
commitment is made.
Preceded by at least one of
the following:
● Starting Gate
● Gateway Review 1
● Project Assessment Review
(PAR)
Outline Business Case (OBC)
- Pre-market stage
- All Major Projects to assess all
options in detail.
- Approval required before going to
the market
Preceded by at least one of
the following:
● Gateway Review 2
● PAR
Full Business Case (FBC) -
Pre-final negotiation
stage
- All Major Projects pre-spending
commitments
Approval required before finalising
commercial contracts.
- For projects using competitive
dialogue as a procurement route,
approval required before close of
dialogue.
Preceded by at least one of
the following:
● Gateway Review 3
● PAR
13. Principle 6: Define, identify, measure and transfer the risks to
those that manage them best (at the least cost).
• Standardised contracts in the UK provide a sound basis
for the allocation of generic risk in a PFI project.
• An evolutionary process.
• The PF2 consultation process highlighted that a greater
retention of risk by the public sector (ex: utility
consumption risk) could further improve the VfM of
contracts
Greater risk retention by the public sector might improve
VfM.
13
14. Principle 7: The procuring authorities should be prepared for
the operational phase of the Public-Private Partnerships.
• Ongoing initiatives (ex. MPLA) to strengthen the capacity of
project managers to maintain the performance of projects over
time
• Ongoing operational savings program to implement savings
measures in ongoing projects (in 2013, 118 projects reported savings
of GBP 1.6 billion)
• The NAO reviews individual PFI projects, draws useful lessons,
and offers suggestions on how to cut cost and improve efficiency
• Ex-post evaluation of projects and systematic data collection for
comparison purposes might be enhanced.
Preliminary evidence suggests that performance has been good in
terms of on-time and on-budget delivery of PFI assets
14
15. Principle 8: Value for money should be maintained when
renegotiating.
• A 2008 study found that the monetary impact of
changes to contracts was minimal for projects that were
renegotiated (1.1 % increase in unitary charges)
• Infrequent cases of high impact renegotiations of
infrastructure PFIs (ex: Channel Tunnel Rail Link)
• Some renegotiations shown to have brought significant
savings to projects (NAO 2013)
On balance, contract renegotiations do not appear to be
an issue in the UK
15
16. Principle 9: Government should ensure there is sufficient
competition in the market.
• Decades-long pipeline and substantial industry has
developed the relevant expertise and skills to furnish
sufficient bids to ensure the basis for a competitive
market process
• General issue that may also affect PFI projects:
sometimes, complex and mega projects may not have
enough bidders (e.g. nuclear energy)
The UK market is open and vigorous in term of
engineering, construction and financial companies
16
17. • The argument for pursuing the PFI the UK is
premised on increasing value for money
• In addition, developing a viable private sector
delivery modality to challenge then
prevailing public sector approaches may
have played a role
• As may the then off budget accounting
treatment.
17
19. Principle 10: The Central Budget Authority should ensure that the
project is affordable and the overall investment envelope is
sustainable.
• Spending Reviews set a medium term expenditure framework, with
firm spending limits for line Departments
• Specific approval procedures for major investment decisions such
as PFI/PF2 contracts (HMT TAPs)
• The Office of Budget Responsibility helps the government keep
track of the fiscal sustainability of its expenditures
• Control caps: new control total of GBP 70 billion for PFI/PF2
projects up to 2020; limit in place for capital expenditures in
Scotland.
HM Treasury spending teams work closely with IUK, the Office of
Budget Responsibility, contracting authorities, and other institutions to
ensure the affordability and fiscal sustainability of projects within the
overall budgeting framework.
19
20. Principle 11: The project should be treated transparently in the
budget process. The budget documentation should disclose all
costs and contingent liabilities.
• The Whole of Government Accounts (WGA) provides a comprehensive
overview of PFI commitments over the long term, as well as quantifiable
and non-quantifiable information on contingent liabilities.
• Practically all PFIs are on balance sheet in the WGA under IFRS
standards (based on the “control” criterion; also followed by departmental
accounts).
• Individual Departments also required to report contingent liabilities to
Parliament
• Despite the WGA, there can still be an accounting incentive to use PFI,
but this stems mainly from compliance with Eurostat rules (“risk and
rewards” criterion).
There is a strong suite of tools to transparently account for PFI
commitments and contingent liabilities in the UK, regardless of classification
20
21. The WGA provides a comprehensive
overview of future PFI payments
21
Source: Office for Budget Responsibility (2014), Fiscal Sustainability Report 2014.
Table: Whole of Government Accounts data for
total future costs of PFI deals
22. Principle 12: Government should guard against waste and
corruption by ensuring the integrity of the procurement process.
• Potential conflict of interest from PF2 mitigated by creation of the
public equity team in IUK, but too early to judge
• Procurement identified by government as an area of improvement:
new tools for simplified, more streamlined procurement procedures
(ex: Procurement Routemap)
• PFI/PF2 Tracker newly in place to provide more transparency on
the business case process
• Procurement skills sometimes limited at the sub-national level
• Capacity building to strengthen procurement skills of public
officials (ex: training on Lean Sourcing principles)
Public procurement displays integrity and discipline, and can
further be strengthened.
22
23. CONCLUSIONS
• More than 20 years of experience with PFI have brought the
government lessons and improvements with respect to all forms of
infrastructure procurement and life-cycle management, such as
discipline in cost control.
• The framework for private finance is still evolving in the UK, but
important lessons have been learned and reforms introduced as
part of PF2.
• There is a positive outlook from both the public and private sectors
about the new model, but …
23
24. In the end, it all depends on deals being
done
24
Source: HM Treasury (2014 b), Private Finance Initiative projects: 2014 summary data, December 2014
Number of PFI/PF2 projects having reached
financial close* in the UK, with total capital values