SlideShare a Scribd company logo
learning and development - consultancy - research EIPA 2018©
PPPs for Regional Development – Discussion on role of
auditors
OECD Network of Senior PPP and Infrastructure
Officials, 11th Annual Meeting, Paris, 27 March 2018
Michael Burnett, Director, European PPP Forum, European Institute of
Public Administration, Maastricht, the Netherlands @eipappp
EIPA 2018 - www.eipa.eu©
Introduction – Self
 UK Chartered Accountant (20+ years working in
PPP/public procurement/audit)
 Assistant Director, KPMG
 Director, EIPA European PPP Forum since 2005
 Member, Editorial Board, European Procurement
and PPP Law Review since 2007
 Member, European Commission Stakeholder
Expert Group on Public Procurement since 2012
 Author, 3 books on PPP and on Competitive
Dialogue and Negotiated Procedures
EIPA 2018 - www.eipa.eu©
Key challenges for sub-national PPPs
 Not all PPP transactions bear an equal risk of
sub-optimal outcomes (different geographical
risk, awarding entity risk, economic operator
risk, sector risk, transaction risk etc.)
 PPP award processes usually involve
dialogue/negotiation - often different skill levels
of the awarding body and of economic operators
 Value for money (VFM) in PPP contracts is based
both on what is secured in the award phase and
what realised in the execution phase
 Awarding bodies must plan how they will
manage the contract execution phase early in
the contract award process
EIPA 2018 - www.eipa.eu©
Key issues for auditors – 1
 Auditors are a key part of the regulatory
framework for PPP at sub-national level
 Auditors need to prioritise their activities based
on risk assessment of PPP transactions and the
impact if risks materialise
 Procedures involving dialogue/negotiation (as
PPP usually are) should be prioritised by
auditors because they are long-term high value
contracts with risks in the planning and
preparation phase and in the conduct of
dialogue/negotiation which need to be managed
EIPA 2018 - www.eipa.eu©
Key issues for auditors – 2
 As VFM is based both on what is secured by in
the contract award phase and what realised in
the contract execution phase, auditors need to:
- Audit planned contract management
arrangements during the contract award phase
- Undertake ex ante/in progress audit of the likely
impact of decisions made in the contract award
phase on securing VFM for planned outcomes
- Undertake ex post audit of VFM secured in the
contract award phase
- Continue with regular (at least annual) audit of
VFM realised in the contract execution phase
EIPA 2018 - www.eipa.eu©
Questions for discussion
Award stage
 How well understood are the key risks in the
dialogue/negotiation phase of a PPP award?
 How can these risks best be managed?
 How should auditors audit dialogue/negotiation?
Execution phase
 How can auditors assess if awarding bodies are
securing VFM in the contract execution phase?
Reporting
 How and when should auditors report on their
findings re the award or execution phase?
EIPA 2018 - www.eipa.eu©
European PPP Forum
CONTACT DETAILS
Mr. Michael Burnett
Director, European PPP Forum
European Institute of Public Administration
Maastricht, the Netherlands
Tel +31-43-32 96 286 E-mail: m.burnett@eipa.eu
Follow me on Twitter@eipappp

More Related Content

What's hot

5_Procurement, conflict of interest and sub-granting
5_Procurement, conflict of interest and sub-granting5_Procurement, conflict of interest and sub-granting
5_Procurement, conflict of interest and sub-granting
csdialogue
 
EU project management training
EU project management trainingEU project management training
EU project management training
ISAR Ednannia
 
Managing VfM: a project lifecycle approach - Fernando Crespo Diu, Portugal
Managing VfM: a project lifecycle approach - Fernando Crespo Diu, PortugalManaging VfM: a project lifecycle approach - Fernando Crespo Diu, Portugal
Managing VfM: a project lifecycle approach - Fernando Crespo Diu, Portugal
OECD Governance
 
Ensuring affordability, economic viability and fiscal sustainability - Duncan...
Ensuring affordability, economic viability and fiscal sustainability - Duncan...Ensuring affordability, economic viability and fiscal sustainability - Duncan...
Ensuring affordability, economic viability and fiscal sustainability - Duncan...
OECD Governance
 
Performance budgeting: current issues and ambitions - Ronnie Downes, OECD Se...
Performance budgeting:  current issues and ambitions - Ronnie Downes, OECD Se...Performance budgeting:  current issues and ambitions - Ronnie Downes, OECD Se...
Performance budgeting: current issues and ambitions - Ronnie Downes, OECD Se...
OECD Governance
 
15 jan ifc_aimm
15 jan ifc_aimm15 jan ifc_aimm
Use of market-type mechanisms for public service delivery: Outsourcing - Jon ...
Use of market-type mechanisms for public service delivery: Outsourcing - Jon ...Use of market-type mechanisms for public service delivery: Outsourcing - Jon ...
Use of market-type mechanisms for public service delivery: Outsourcing - Jon ...
OECD Governance
 
Impact of COVID-19 on infrastructure investment-edhe cinfra
Impact of COVID-19 on infrastructure investment-edhe cinfraImpact of COVID-19 on infrastructure investment-edhe cinfra
Impact of COVID-19 on infrastructure investment-edhe cinfra
OECD Directorate for Financial and Enterprise Affairs
 
Applying formal Project Management processes to EU-funded R&D projects
Applying formal Project Management processes to EU-funded R&D projectsApplying formal Project Management processes to EU-funded R&D projects
Applying formal Project Management processes to EU-funded R&D projects
Georgios Gardikis
 
Private sector in infrastructure funding/financing models and role of institu...
Private sector in infrastructure funding/financing models and role of institu...Private sector in infrastructure funding/financing models and role of institu...
Private sector in infrastructure funding/financing models and role of institu...
OECD Governance
 
15 jan platform_for_inclusive_growth_and_investment
15 jan platform_for_inclusive_growth_and_investment15 jan platform_for_inclusive_growth_and_investment
15 jan platform_for_inclusive_growth_and_investment
Development Co-operation Directorate (DCD-DAC)
 
Ensuring affordability, economic viability and fiscal sustainability - Andrew...
Ensuring affordability, economic viability and fiscal sustainability - Andrew...Ensuring affordability, economic viability and fiscal sustainability - Andrew...
Ensuring affordability, economic viability and fiscal sustainability - Andrew...
OECD Governance
 
Capacity building for PPP projects
Capacity building for PPP projectsCapacity building for PPP projects
Capacity building for PPP projects
geoffrey-cip
 
Capacity Building for PPP projects
Capacity Building for PPP projects Capacity Building for PPP projects
Capacity Building for PPP projects
admin-cip
 
54 Seibert Eib Experience
54 Seibert Eib Experience54 Seibert Eib Experience
54 Seibert Eib Experience
Odisus
 
Maintaining and enhancing value from existing PPPs - Jo Fox, United Kingdom
Maintaining and enhancing value from existing PPPs  - Jo Fox, United KingdomMaintaining and enhancing value from existing PPPs  - Jo Fox, United Kingdom
Maintaining and enhancing value from existing PPPs - Jo Fox, United Kingdom
OECD Governance
 
Kazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECD
Kazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECDKazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECD
Kazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECD
OECD Governance
 
Alan Watt - APM Assurance SIG Conference 2018
Alan Watt - APM Assurance SIG Conference 2018Alan Watt - APM Assurance SIG Conference 2018
Alan Watt - APM Assurance SIG Conference 2018
Association for Project Management
 
Regulating it projects in public and state administration in the Republic of ...
Regulating it projects in public and state administration in the Republic of ...Regulating it projects in public and state administration in the Republic of ...
Regulating it projects in public and state administration in the Republic of ...
Goran Vojkovic, Ph.D.
 

What's hot (20)

5_Procurement, conflict of interest and sub-granting
5_Procurement, conflict of interest and sub-granting5_Procurement, conflict of interest and sub-granting
5_Procurement, conflict of interest and sub-granting
 
EU project management training
EU project management trainingEU project management training
EU project management training
 
Managing VfM: a project lifecycle approach - Fernando Crespo Diu, Portugal
Managing VfM: a project lifecycle approach - Fernando Crespo Diu, PortugalManaging VfM: a project lifecycle approach - Fernando Crespo Diu, Portugal
Managing VfM: a project lifecycle approach - Fernando Crespo Diu, Portugal
 
Ensuring affordability, economic viability and fiscal sustainability - Duncan...
Ensuring affordability, economic viability and fiscal sustainability - Duncan...Ensuring affordability, economic viability and fiscal sustainability - Duncan...
Ensuring affordability, economic viability and fiscal sustainability - Duncan...
 
Performance budgeting: current issues and ambitions - Ronnie Downes, OECD Se...
Performance budgeting:  current issues and ambitions - Ronnie Downes, OECD Se...Performance budgeting:  current issues and ambitions - Ronnie Downes, OECD Se...
Performance budgeting: current issues and ambitions - Ronnie Downes, OECD Se...
 
15 jan ifc_aimm
15 jan ifc_aimm15 jan ifc_aimm
15 jan ifc_aimm
 
Use of market-type mechanisms for public service delivery: Outsourcing - Jon ...
Use of market-type mechanisms for public service delivery: Outsourcing - Jon ...Use of market-type mechanisms for public service delivery: Outsourcing - Jon ...
Use of market-type mechanisms for public service delivery: Outsourcing - Jon ...
 
Impact of COVID-19 on infrastructure investment-edhe cinfra
Impact of COVID-19 on infrastructure investment-edhe cinfraImpact of COVID-19 on infrastructure investment-edhe cinfra
Impact of COVID-19 on infrastructure investment-edhe cinfra
 
Applying formal Project Management processes to EU-funded R&D projects
Applying formal Project Management processes to EU-funded R&D projectsApplying formal Project Management processes to EU-funded R&D projects
Applying formal Project Management processes to EU-funded R&D projects
 
Private sector in infrastructure funding/financing models and role of institu...
Private sector in infrastructure funding/financing models and role of institu...Private sector in infrastructure funding/financing models and role of institu...
Private sector in infrastructure funding/financing models and role of institu...
 
15 jan platform_for_inclusive_growth_and_investment
15 jan platform_for_inclusive_growth_and_investment15 jan platform_for_inclusive_growth_and_investment
15 jan platform_for_inclusive_growth_and_investment
 
Ensuring affordability, economic viability and fiscal sustainability - Andrew...
Ensuring affordability, economic viability and fiscal sustainability - Andrew...Ensuring affordability, economic viability and fiscal sustainability - Andrew...
Ensuring affordability, economic viability and fiscal sustainability - Andrew...
 
Capacity building for PPP projects
Capacity building for PPP projectsCapacity building for PPP projects
Capacity building for PPP projects
 
Capacity Building for PPP projects
Capacity Building for PPP projects Capacity Building for PPP projects
Capacity Building for PPP projects
 
54 Seibert Eib Experience
54 Seibert Eib Experience54 Seibert Eib Experience
54 Seibert Eib Experience
 
Maintaining and enhancing value from existing PPPs - Jo Fox, United Kingdom
Maintaining and enhancing value from existing PPPs  - Jo Fox, United KingdomMaintaining and enhancing value from existing PPPs  - Jo Fox, United Kingdom
Maintaining and enhancing value from existing PPPs - Jo Fox, United Kingdom
 
Kazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECD
Kazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECDKazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECD
Kazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECD
 
Alan Watt - APM Assurance SIG Conference 2018
Alan Watt - APM Assurance SIG Conference 2018Alan Watt - APM Assurance SIG Conference 2018
Alan Watt - APM Assurance SIG Conference 2018
 
Regulating it projects in public and state administration in the Republic of ...
Regulating it projects in public and state administration in the Republic of ...Regulating it projects in public and state administration in the Republic of ...
Regulating it projects in public and state administration in the Republic of ...
 
Facts on Public Finance Management
Facts on Public Finance ManagementFacts on Public Finance Management
Facts on Public Finance Management
 

Similar to PPP for regional development - Michael BURNETT, EIPA

Presentation "PPPs in the EU- Widespread shortcomings and limited benefits"
Presentation "PPPs in the EU- Widespread shortcomings and limited benefits"Presentation "PPPs in the EU- Widespread shortcomings and limited benefits"
Presentation "PPPs in the EU- Widespread shortcomings and limited benefits"
Support for Improvement in Governance and Management SIGMA
 
Startup Grind Bucharest April 2019 Gyorgy Bodo
Startup Grind Bucharest April 2019 Gyorgy BodoStartup Grind Bucharest April 2019 Gyorgy Bodo
Startup Grind Bucharest April 2019 Gyorgy Bodo
Daniel-Ioan Dumitrescu, PhD.
 
Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...
Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...
Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...
NALED Serbia
 
the European Innovation Council in Horizon2020
the European Innovation Council in Horizon2020the European Innovation Council in Horizon2020
the European Innovation Council in Horizon2020
Emile Dupont
 
Agenda-Workshop on Auditing Public Private Partnerships and Concessions. Anka...
Agenda-Workshop on Auditing Public Private Partnerships and Concessions. Anka...Agenda-Workshop on Auditing Public Private Partnerships and Concessions. Anka...
Agenda-Workshop on Auditing Public Private Partnerships and Concessions. Anka...
Support for Improvement in Governance and Management SIGMA
 
Presentation “Auditing PPP- Lessons learned from the French experience”. Anka...
Presentation “Auditing PPP- Lessons learned from the French experience”. Anka...Presentation “Auditing PPP- Lessons learned from the French experience”. Anka...
Presentation “Auditing PPP- Lessons learned from the French experience”. Anka...
Support for Improvement in Governance and Management SIGMA
 
Proprietà intellettuale (IP) nei progetti finanziati dalla UE - Seminario Ast...
Proprietà intellettuale (IP) nei progetti finanziati dalla UE - Seminario Ast...Proprietà intellettuale (IP) nei progetti finanziati dalla UE - Seminario Ast...
Proprietà intellettuale (IP) nei progetti finanziati dalla UE - Seminario Ast...
Parma Couture
 
Bassel Shoirah's CV 2017
Bassel Shoirah's CV 2017Bassel Shoirah's CV 2017
Bassel Shoirah's CV 2017Bassel Shoirah
 
Gestione della proprietà intellettuale nei progetti di ricerca Horizon 2020
Gestione della proprietà intellettuale nei progetti di ricerca Horizon 2020 Gestione della proprietà intellettuale nei progetti di ricerca Horizon 2020
Gestione della proprietà intellettuale nei progetti di ricerca Horizon 2020
AREA Science Park
 
3rd EPP Aftermarket and Manufacturing Forum
3rd EPP Aftermarket and Manufacturing Forum3rd EPP Aftermarket and Manufacturing Forum
3rd EPP Aftermarket and Manufacturing Forum
European Pricing Platform
 
Pm process matrix v 1.1
Pm process matrix v 1.1Pm process matrix v 1.1
Pm process matrix v 1.1
Dave Fourie [PMP PRINCE2]
 
Uwe Flach, Austria, third regional conference on public procurement for ENP E...
Uwe Flach, Austria, third regional conference on public procurement for ENP E...Uwe Flach, Austria, third regional conference on public procurement for ENP E...
Uwe Flach, Austria, third regional conference on public procurement for ENP E...
Support for Improvement in Governance and Management SIGMA
 
1_Introduction to Full Application preparation
1_Introduction to Full Application preparation1_Introduction to Full Application preparation
1_Introduction to Full Application preparation
csdialogue
 
AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon
 
FP7 project negotiation, management and financial rules
FP7 project  negotiation, management and financial rulesFP7 project  negotiation, management and financial rules
FP7 project negotiation, management and financial rules
Europa Media Trainings
 
Startup Europe: EU funding for start-ups
Startup Europe: EU funding for start-upsStartup Europe: EU funding for start-ups
Startup Europe: EU funding for start-ups
Iraklis Agiovlasitis
 
Homeday - NOAH18 Berlin
Homeday - NOAH18 BerlinHomeday - NOAH18 Berlin
Homeday - NOAH18 Berlin
NOAH Advisors
 

Similar to PPP for regional development - Michael BURNETT, EIPA (20)

Presentation "PPPs in the EU- Widespread shortcomings and limited benefits"
Presentation "PPPs in the EU- Widespread shortcomings and limited benefits"Presentation "PPPs in the EU- Widespread shortcomings and limited benefits"
Presentation "PPPs in the EU- Widespread shortcomings and limited benefits"
 
GCCV 2016
GCCV 2016GCCV 2016
GCCV 2016
 
Startup Grind Bucharest April 2019 Gyorgy Bodo
Startup Grind Bucharest April 2019 Gyorgy BodoStartup Grind Bucharest April 2019 Gyorgy Bodo
Startup Grind Bucharest April 2019 Gyorgy Bodo
 
Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...
Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...
Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...
 
the European Innovation Council in Horizon2020
the European Innovation Council in Horizon2020the European Innovation Council in Horizon2020
the European Innovation Council in Horizon2020
 
Agenda-Workshop on Auditing Public Private Partnerships and Concessions. Anka...
Agenda-Workshop on Auditing Public Private Partnerships and Concessions. Anka...Agenda-Workshop on Auditing Public Private Partnerships and Concessions. Anka...
Agenda-Workshop on Auditing Public Private Partnerships and Concessions. Anka...
 
Presentation “Auditing PPP- Lessons learned from the French experience”. Anka...
Presentation “Auditing PPP- Lessons learned from the French experience”. Anka...Presentation “Auditing PPP- Lessons learned from the French experience”. Anka...
Presentation “Auditing PPP- Lessons learned from the French experience”. Anka...
 
Proprietà intellettuale (IP) nei progetti finanziati dalla UE - Seminario Ast...
Proprietà intellettuale (IP) nei progetti finanziati dalla UE - Seminario Ast...Proprietà intellettuale (IP) nei progetti finanziati dalla UE - Seminario Ast...
Proprietà intellettuale (IP) nei progetti finanziati dalla UE - Seminario Ast...
 
Bassel Shoirah's CV 2017
Bassel Shoirah's CV 2017Bassel Shoirah's CV 2017
Bassel Shoirah's CV 2017
 
Gestione della proprietà intellettuale nei progetti di ricerca Horizon 2020
Gestione della proprietà intellettuale nei progetti di ricerca Horizon 2020 Gestione della proprietà intellettuale nei progetti di ricerca Horizon 2020
Gestione della proprietà intellettuale nei progetti di ricerca Horizon 2020
 
3rd EPP Aftermarket and Manufacturing Forum
3rd EPP Aftermarket and Manufacturing Forum3rd EPP Aftermarket and Manufacturing Forum
3rd EPP Aftermarket and Manufacturing Forum
 
Pm process matrix v 1.1
Pm process matrix v 1.1Pm process matrix v 1.1
Pm process matrix v 1.1
 
Uwe Flach, Austria, third regional conference on public procurement for ENP E...
Uwe Flach, Austria, third regional conference on public procurement for ENP E...Uwe Flach, Austria, third regional conference on public procurement for ENP E...
Uwe Flach, Austria, third regional conference on public procurement for ENP E...
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project risk management
Project risk managementProject risk management
Project risk management
 
1_Introduction to Full Application preparation
1_Introduction to Full Application preparation1_Introduction to Full Application preparation
1_Introduction to Full Application preparation
 
AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016
 
FP7 project negotiation, management and financial rules
FP7 project  negotiation, management and financial rulesFP7 project  negotiation, management and financial rules
FP7 project negotiation, management and financial rules
 
Startup Europe: EU funding for start-ups
Startup Europe: EU funding for start-upsStartup Europe: EU funding for start-ups
Startup Europe: EU funding for start-ups
 
Homeday - NOAH18 Berlin
Homeday - NOAH18 BerlinHomeday - NOAH18 Berlin
Homeday - NOAH18 Berlin
 

More from OECD Governance

Public Integrity Indicators Slides
Public Integrity Indicators SlidesPublic Integrity Indicators Slides
Public Integrity Indicators Slides
OECD Governance
 
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
OECD Governance
 
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
OECD Governance
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
OECD Governance
 
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
OECD Governance
 
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
OECD Governance
 
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
OECD Governance
 
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
OECD Governance
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
OECD Governance
 
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
OECD Governance
 
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
OECD Governance
 
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
OECD Governance
 
Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023
OECD Governance
 
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
OECD Governance
 
Digital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and RecommendationsDigital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and Recommendations
OECD Governance
 
Buliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdfBuliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdf
OECD Governance
 
Session-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptxSession-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptx
OECD Governance
 
Session-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptxSession-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptx
OECD Governance
 
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptxSession-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
OECD Governance
 
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptxSession-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
OECD Governance
 

More from OECD Governance (20)

Public Integrity Indicators Slides
Public Integrity Indicators SlidesPublic Integrity Indicators Slides
Public Integrity Indicators Slides
 
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
 
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
 
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
 
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
 
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
 
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
 
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
 
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
 
Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023
 
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
 
Digital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and RecommendationsDigital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and Recommendations
 
Buliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdfBuliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdf
 
Session-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptxSession-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptx
 
Session-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptxSession-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptx
 
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptxSession-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
 
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptxSession-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
 

Recently uploaded

PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
ahcitycouncil
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
Saeed Al Dhaheri
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
Mohammed325561
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
JSchaus & Associates
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
ahcitycouncil
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
Paul Smith
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
ehbuaw
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
ClaudioTebaldi2
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
SERUDS INDIA
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Congressional Budget Office
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
ahcitycouncil
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
RIDPRO11
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
ukyewh
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
850fcj96
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
Antti Rautiainen
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
AjayVejendla3
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
ahcitycouncil
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
GrantManagementInsti
 

Recently uploaded (20)

PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
 

PPP for regional development - Michael BURNETT, EIPA

  • 1. learning and development - consultancy - research EIPA 2018© PPPs for Regional Development – Discussion on role of auditors OECD Network of Senior PPP and Infrastructure Officials, 11th Annual Meeting, Paris, 27 March 2018 Michael Burnett, Director, European PPP Forum, European Institute of Public Administration, Maastricht, the Netherlands @eipappp
  • 2. EIPA 2018 - www.eipa.eu© Introduction – Self  UK Chartered Accountant (20+ years working in PPP/public procurement/audit)  Assistant Director, KPMG  Director, EIPA European PPP Forum since 2005  Member, Editorial Board, European Procurement and PPP Law Review since 2007  Member, European Commission Stakeholder Expert Group on Public Procurement since 2012  Author, 3 books on PPP and on Competitive Dialogue and Negotiated Procedures
  • 3. EIPA 2018 - www.eipa.eu© Key challenges for sub-national PPPs  Not all PPP transactions bear an equal risk of sub-optimal outcomes (different geographical risk, awarding entity risk, economic operator risk, sector risk, transaction risk etc.)  PPP award processes usually involve dialogue/negotiation - often different skill levels of the awarding body and of economic operators  Value for money (VFM) in PPP contracts is based both on what is secured in the award phase and what realised in the execution phase  Awarding bodies must plan how they will manage the contract execution phase early in the contract award process
  • 4. EIPA 2018 - www.eipa.eu© Key issues for auditors – 1  Auditors are a key part of the regulatory framework for PPP at sub-national level  Auditors need to prioritise their activities based on risk assessment of PPP transactions and the impact if risks materialise  Procedures involving dialogue/negotiation (as PPP usually are) should be prioritised by auditors because they are long-term high value contracts with risks in the planning and preparation phase and in the conduct of dialogue/negotiation which need to be managed
  • 5. EIPA 2018 - www.eipa.eu© Key issues for auditors – 2  As VFM is based both on what is secured by in the contract award phase and what realised in the contract execution phase, auditors need to: - Audit planned contract management arrangements during the contract award phase - Undertake ex ante/in progress audit of the likely impact of decisions made in the contract award phase on securing VFM for planned outcomes - Undertake ex post audit of VFM secured in the contract award phase - Continue with regular (at least annual) audit of VFM realised in the contract execution phase
  • 6. EIPA 2018 - www.eipa.eu© Questions for discussion Award stage  How well understood are the key risks in the dialogue/negotiation phase of a PPP award?  How can these risks best be managed?  How should auditors audit dialogue/negotiation? Execution phase  How can auditors assess if awarding bodies are securing VFM in the contract execution phase? Reporting  How and when should auditors report on their findings re the award or execution phase?
  • 7. EIPA 2018 - www.eipa.eu© European PPP Forum CONTACT DETAILS Mr. Michael Burnett Director, European PPP Forum European Institute of Public Administration Maastricht, the Netherlands Tel +31-43-32 96 286 E-mail: m.burnett@eipa.eu Follow me on Twitter@eipappp