1) A contractor needs to complete a canal that is 12 km long in 350 days. After working for 200 days with 45 men, only 4.5 km has been dug.
2) To finish the remaining work in the allotted time, the contractor needs to hire 55 additional men.
3) The problem involves using proportions to determine the number of additional men needed given the original work rate over 200 days and the remaining time and distance to be completed.