MS Project
Overview
Prepared By
Dr.S.Deepika
maher.almohamad@outlook.co
m
Objectives
• Projects management Basics
• Getting started with MS Project
• Creating a project ( Tasks, Resources, …)
• Views and Reports
Projects Management
Introduction
maher.almohamad@outlook.co
m
A temporary endeavor
undertaken to create a unique
product, service, or
result.
A Project is
maher.almohamad@outlook.co
m
Project Life Cycle (Phases)
• Initiation
• Planning
• Execution
• Closure
Initiation Closure
Planning
Execution
maher.almohamad@outlook.co
m
The application of knowledge, skills, tools, and
techniques to project activities, in order to meet or
exceed stakeholder needs and expectations from a
defined project - balancing the following:
• Scope, time, cost, and quality
• Stakeholders’ expectations
• Requirements (needs) vs. unidentified requirements
Projects Management is
maher.almohamad@outlook.co
m
Monitoring and Controlling
PM Process Groups
• Initiating
• Planning
• Executing
• Monitoring and Controlling
• Closing
Initiating Closing
Planning
Executing
Project Life Cycle with PM
maher.almohamad@outlook.co
m
Project Manager
A project manager is a professional in the
field of project management.
Project managers can have
the responsibility of the
planning, execution, and
closing of any project.
maher.almohamad@outlook.co
m
MS Project
Microsoft Project is a project management
software program, which is designed to assist
a project manager in developing a plan,
assigning resources to tasks, tracking
progress, managing the budget, and
analysing workloads.
maher.almohamad@outlook.co
m
Note
Microsoft project expert isn’t a replacement
for the project manager.
Microsoft Project doesn’t ensure a successful
project if a person doesn’t understand project
management. However, Microsoft Project can
assist a project manager in becoming more
effective.
MS Project
Getting Started
Start a new project
The MS Project interface
Toolbar
Ribbon
Main Screen
components
Schedule a Project from a Start or Finish
Dates
Setting working Days
maher.almohamad@outlook.co
m
Gantt Chart
Task Spreadsheet Gantt Diagram
Working with Tasks List
Adding the essential data of
tasks :
Task name
Duration (D, W, H, M, Mo)
Predecessors
Task Information
Task Mode, Milestones, Summary, Sub Task, …
Task Relationships
Creating Tasks Relationships
Note:
MS project will calculate dates
based on the durations of the
tasks, their relationships and
the start date set for the
project, however it is possible to
change the starting date of a
task (if necessary) By double
clicking on a Task or milestone,
and using the fields related to
the dates (Start or Finish).
maher.almohamad@outlook.co
m
FS Finish-to-Start Relationship
Task/Resources
Successors
Duration
Predecessors
FS
maher.almohamad@outlook.co
m
SS Start-to-Start Relationship
Task/Resources
Successors
Predecessors
SS
maher.almohamad@outlook.co
m
FF Finish-to-Finish Relationship
Task/Resources
Successors
Predecessors
FF
maher.almohamad@outlook.co
m
SF Start-to-Finish Relationship
Task/Resources
Successors
Predecessors
SF
maher.almohamad@outlook.co
m
Overlap
Task/Resources
Successors
Predecessors
Overlap
maher.almohamad@outlook.co
m
Lag
Task/Resources
Successors
Predecessors
Lag
maher.almohamad@outlook.co
m
The Critical Path
CP is the flow of tasks, of which, a delay in any
one of these tasks will cause a delay to the
project.
It is the longest path through the project
network diagram and the shortest possible time
to complete the project.
Showing Critical Path
Project Statistics
Working with Resources List
You can use the Resource Sheet to create a
list of the people, equipment, and
material resources.
Assigning Resources to Tasks
1. Assign Resources Using Task List Resources Name Column
Assigning Resources to Tasks
2. Assign Resources Using Task Information, Resources Tab
Assigning Resources to Tasks
3. Assign Resources Using Resource Tab
Over allocated Task Resource
Complete adding Task Resources
Project Statistics – Cost Updated
Task Usage View
Network Diagram View
Task Form
Resources Form
Resources Using View
Team Planner View
Calendar View
Resource Overview Report
Cost Overruns Report
Printing the Project Map
Thank You

ms-project-2016-overview-160216021349.pptx

Editor's Notes

  • #4 A project is a temporary effort of sequential activities designed to accomplish a unique purpose. a temporary endeavor that helps to accomplish some specific objective by utilizing definite interconnected tasks and the effective utilization of resources. To achieve an objective One Time (Start and finish dates) Constraints of time, cost and resources Performed by People – Single or Group Coordinated and controlled activities Specific Deliverables Progressive Elaboration
  • #7 Initiating •Set the project goal •Identify the necessary start or finish date limitations •Identify the project manager •Identify budget and quality considerations Planning •Enter project tasks, duration and relationships •Identify project milestones •Define available resources and costs •Assign resources to tasks Monitoring and Controlling  •Producing work results •Requesting changes •Recommending improvements •Creating project records, reports, and presentations •Updating project •Managing resources and tasks •Meet management timing, resource, and cost objectives •Identify budget and quality considerations Closing •Review and analyze performance of the project •Create a Closure Report •Archive records
  • #13 File> New> blank project.
  • #14  The Quick Access Toolbar (File, Task, Resource, Reports, Project, View, Format) The Ribbon (tabs, buttons and drop-down list) Main Screen components
  • #15 By default, the new project file is scheduled from a Project Start Date All tasks are scheduled to begin as soon as possible MS Project calculates the project’s Finish date based on Tasks, Durations, Dependencies. When a project is scheduled from a Finish date, such as a conference, all tasks are scheduled to begin as late as possible
  • #16 The project calendar defines the general working and nonworking days and time for tasks. By default, the entire project, each task, and each resource is scheduled according to the Standard calendar The Standard calendar specifies that Monday through Friday are working days with 8 hours of work completed each day. Saturday and Sunday are designated as nonworking days. The Calendar can be modified to identify holidays or other nonworking days or times in which work should not be scheduled.
  • #17 Select Gantt Chart view from the view menu. You’ll have a spreadsheet where you can now enter information of all the activities i.e. task name, duration, start date, end date, and various other fields. You can enter required information in two ways, in spreadsheet or when you double click on cell you get pop up window in which you can enter all the information of that particular activity.
  • #28 CPA helps you to identify the minimum length of time needed to complete a project. For finding CP list all the activities and enter early start, late start, early finish and late finish info of all the activities. Project automatically calculates ES, EF, LS and LF based on the starting/ending dates you have provided to find CP.
  • #31  1. On the View menu, click Resource Sheet. 2. On the View menu, point to Table, and then click Entry. 3. In the Resource Name field, type a resource name. 4. You can go through the fields in the sheet, but for the simplicity of the example just focus on the name and initials of the Resource 5. Below is an example of some Human resources added to the Resource Sheet (We could add also other type of resources such as Equipments, Consumables, etc.)