SlideShare a Scribd company logo
1 of 30
Feasibility study of setting up a 10 MW solar farm in Luzon
Submitted By
Siddharth Kundu
MBA 2012 Candidate
Asian Institute of Management
Proponent
Shrinivas Polishetty
American orient Capital Partners
Philippines
Mentors
Prof. G Ortigas
Prof. F Roxas
Asian Institute of Management
MANAGEMENT RESEARCH REPORT
FLOW OF PRESENTATION
Industry Analysis
Internal Analysis
PEST Analysis
Five forces Framework
Demand & supply
Key success Factors
Opportunities & Threat
American Orient Capital Partners
Stakeholder Analysis
Revenue Model/sources
Operations strategy
Marketing strategy
Financials
Risk
Recommendation
The Company
• Government is supporting and attracting investment in Renewable energy sector
Political
• Continuous growth of GDP ,Industry Power requirements are increasing
Economic
• Total per capita of consumption of electricity is continuously increasing
Social
• Solar technology is getting affordable and non- conventional energy cost is
increasing
Technology
MACRO ENVIRONMENT ANALYSIS - PEST
Threat of
New Entrants
LOW
Bargaining Power
of Suppliers
Low
Bargaining Power
of Buyers
Medium
Competitive
Rivalry
HIGH
Threat of
Substitutes
MEDIUM
Capital Requirement – High
Economies of Scale – High
Product Differentiation – Low
First mover Advantage - High
Government and Legal Barriers - High
Buyer Propensity to Substitutes – LOW
Relative Price of the Substitutes - Medium
Buyers Sensitivity to Price – High
RPS mandate- Low
Buyers Sensitivity to Price – High
Relative Bargaining Power – High
Industry Concentration – Low
Diversity of Competitors – low
Product Differentiation – LOW
Exit Barriers - High
The Industry is attractive for New Players
PORTER’S FIVE FORCES – SOLAR DEVELOPER
Supply Side Demand Factors
CURRENT DEMAND AND SUPPLY OF ELECTRICITY - Philippines
Solar Energy (<0.01%)
Dependable Capacity 2011
13902 MW
Renewable Energy 44%
6117 MW
Locally
Produced
55%
Imported
Sources
45%
Total Peak Demand 2011
11226 MW
11226
14311
24434
0
5000
10000
15000
20000
25000
30000
2011 2018 2030
Demand (MW)
Is there Opportunity for solar farming in Pangasinan, Luzon?
Distribution Companies
 4 distribution companies in
vicinity to have bilateral contracts
 2 of them do not have renewable
sourcing of electricity
Consumption
 Luzon till 2030 – 11,9000 MW
 Pangasinan currently
consumes more than 1310 MW
First Mover Advantage
No proposed or approved
solar projects in the
Pangasinan
Strategic Land site for setting up project
Distance from substation or main transmission line
Cost of land
Solar generation capacity of land- Pvsyst analysis
Initial setup cost( sourcing capability)
Cost and quality of RE components
Cost and quality of project engineering
Initial project startup registration cost and fees
Capital structure
Interest rate of debt
Principal and Interest Payback period for debt
Bilateral contracts & CDM rate
Bilateral contract rate
CDM Rate
Price escalation clause
Minimum off take Agreement
Approvals & registration
DOE and NREB of Approval for the project
CDM registration with UNFCCC to trade Carbon credits
Registry with European Union Emission Trading System (EUETS)
Capital Funding
Price
Place
Suppliers and
components
Political Factors
KEY SUCCESS FACTORS
Threat
 Approved Solar projects in Luzon
 Lack of trust on the legal and judicial system
and previously rigid laws on venturing in
Philippines reduced the entry of foreign
investment.
 Costly power transmission capacity may
affect the demand and supply of electricity.
 Natural calamities
Opportunities
 All electric power industry participants (
distributors) are mandated to comply with
the RPS
 No operating solar player in Region-
1, Luzon
 Potential Demand and supply gap of
electricity
 Four Distribution companies in the vicinity
of the project.
 Solar is given top most priority among all
other sources of RE
OPPORTUNITIES AND THREATS
The Company
Who are we?
 AOCP is an investment and financial advisory services company.
 Over 100 major transactions valued in excess of US$10 billion in Asia
 They have acquired an unmatched blend of exposure and experience with international
financial and industrial sectors.
Objective of American Orient capital Partners
Why are AOCP interested in Solar ?
To check the feasibility of Solar energy Development in Philippines.
To produce and sell electricity and CDM generated from project.
To benefit by supply RE for the Renewable portfolio Standard set by NREB to meet
demand of renewable source of energy.
Internal Analysis
STAKEHOLDERS Analysis
10 MW
SOLAR
FARM
WSEM
GOVERNMENT
Approvals/Sanctions
Regulatory Compliances
Electricity Trading
SUPPLIERS Better deals in procuring
RE components
UNFCCC
Approvals and sanction
Carbon credit Trading
Electricity
Distributors
 Bilateral Contracts
BANKS
Financing
Options
Power
Interest
Hi
Mid
Lo HiMid
G
S
B
D
W
G
Manage closelyKeep satisfied
Monitor Keep Informed
B Bank D Distributor S Component
supplier
W wsemGovernment
Stakeholder Power grid Matrix
Bilateral contract
- For fixed cash flow to meet to long term
debt principal and interest amount
CDM certificates
- To benefit by registering for sale of CDM
certificate from the green renewable energy
project
Trading energy in WESM
- By selling at the spot market to enjoy the
benefit of spot market rate with a guarded floor
price of 9.68
Revenue Model / Sources of Revenue
1st degree potential
customers
• PANELCO 3
• CENPALCO
• DECORP
• PANELCO 1
2nd degree potential
customers
• INEC
• ISESCO
• LUELCO
• Meralco
3rd degree potential
customers
• Nor feeds
• B Meg
• SYGENTA
• University of Eastern
Philippines
Potential Bilateral Contract Customers
• Total Purchase of electricity in a year ?
• What are the source generation companies
for buying electricity and detailed breakup
of energy purchase?
• Are you ready for Minimum off take in
bilateral contract ?
• Is your cooperative ready to buy electricity
from solar energy producers ? If yes then
at what rate?
Factors considered while deciding Bilateral contract Rate
 The price goes high as up to 60
Peso/ KwH
 The amount electricity traded at
more than 10 Peso is almost to an
little less than 10 % of total
transactions happening of WSEM.
 The average trading rate 6.9 Peso
in peak hours is 9am -4 PM.
 The floor price for solar energy set
by FIT rate is Peso 9.68
 Solar energy will be given first
Priority among all sources of energy
on the trade floor.
Picture: Average trading rate Graph of WSEM
Electricity trading at WSEM
 Company has to be registered to European Union
Emission Trading System (EUETS)
 Receiving UNFCCC approval for emissions reduction
projects in order to yield carbon credits
 Average trading rate is 3 Euro/Ton for CDM
CERTIFICATE
 52 week high was around 13.5 euro / ton for CDM
CERTIFICATE
 It is forecasted to be around 20 euro/ ton on average
by Year 2020 by big trading houses in CDM trading
houses in Europe.
 Risk mitigation of fluctuating CDM rate can done by
having carbon exchange contracts
CDM Trading
• Major task of operation will be keep the
site running to its maximum potential.
• To look after the regular technical
maintainace and cleaning of the plant.
• Approval & Permits – 4 weeks
• Construction of Site – 3 weeks
• Component installation-3 weeks
OPERATION STRATEGY
Timeline for Project
Site operation Employees and Cost
We need to have good relationship with the suppliers to get a attractive
rate , good quality RE components and after sales service.
 Solar panels are the costliest
Component for this project. The
rate charged is .69$ per Wp with 10
year warranty and CIS.
 Around 38000,265 Wp modules will
be required to make 10 MW plant
 Land & structure cost are second
costliest component and make 25
% of total Capex
RE Components/Suppliers
Looking at the study on solar
projects, our marketing approach will
be showing the value proposition of the
solar project and promote the
affordability to strengthen our
possibility of favourable bilateral
contract
Ways of Promoting
• Public Relations
• B2B Presentation & seminar
• Website
Marketing strategy
Project Director/ CEO
American Orient capital Partners , Philippines
Project Manager , HR manager ,Costing & audit
Manager, Sales & Marketing Manager, Operations &
Panel Engineer- Experienced Industry Professionals
1-Field engineer, 4-Field operator
6-daily labor, 4- security guard
ORGANISATION STRUCTURE - PROJECTS
 This will be a P 560 Million Project
 Capital Expenditure is P 498 million
 Operating expense is around P 8 million
per year.
 Contingency Amount-P 158,17,581 3%
of total Capital expenditure to factor in
any unexpected cost. DEBT – EQUITY Ratio 70:30
Funding structure
( All figures in Peso unless mentioned )
Scenario Pessimistic Base Optimistic
Long term interest rate(%) PA 12% 10% 7.45%
Bilateral contract rate (peso) 6.4 6.9 9
Generation / Production(KwH) 10,000,000 14,410,000 17,520,000
CDM Credit Certificate(Euro) 0 3 9
FIT rate -WSEM 9.68 9.68 9.68-3 years/ 17 -
4th year onward
OPEX escalation (%) 4 4 4
Depreciation Accelerated Depreciation
Bilateral Rate escalation Every 5 years
Financial Assumptions
Base case scenario
Pessimistic Case Scenario
Optimistic case
PERCENTAGE OF REVENUE SHARE FOR DIFFERENT SCENARIOS
Year 2012 2013 2014 2015 2016 2017 2018 2019 2020
All figures in Peso unless mentioned
Units Generated (kWh) 1,44,10,000 1,42,65,900 1,41,23,241 1,39,82,009 1,38,42,189 1,37,03,767 1,35,66,729 1,34,31,062
Tariff 6.90 6.90 6.90 6.90 6.90 8.28 8.28 8.28
Units decided to sold on bilateral
contract 79,74,176 79,74,176 79,74,176 79,74,176 79,74,176 79,74,176 79,74,176 79,74,176
Revenue from Bilateral Tariff 5,50,21,815 5,50,21,815 5,50,21,815 5,50,21,815 5,50,21,815 6,60,26,178 6,60,26,178 6,60,26,178
Units to sold WSEM 64,35,824 62,91,724 61,49,065 60,07,832 58,68,012 57,29,591 55,92,553 54,56,886
WSEM ** Tairff 9.68 9.68 9.68 9.68 9.68 9.68 9.68 9.68
Revenue from wsem Tariff 6,22,98,775 6,09,03,887 5,95,22,948 5,81,55,818 5,68,02,360 5,54,62,436 5,41,35,912 5,28,22,652
CDM benefit 2,03,75,812 1,81,54,849 1,59,76,267 1,38,39,441 1,17,43,754 96,88,597 95,91,711 94,95,794
Total Revenues 13,76,96,402 13,40,80,551 13,05,21,030 12,70,17,075 12,35,67,929 13,11,77,212 12,97,53,801 12,83,44,625
Opex 83,31,253 86,64,503 90,11,083 93,71,526 97,46,387 1,01,36,243 1,05,41,692 1,09,63,360
Working Capital 1,14,74,700 1,11,73,379 1,08,76,753 1,05,84,756 1,02,97,327 1,09,31,434 1,08,12,817 1,06,95,385
Outstanding debt 39 30 12 966 37,72,92,446.90 36,15,71,928 34,58,51,410 33,01,30,891 31,44,10,372 29,86,89,854 28,29,69,335 26,72,48,817
Annual debt repayment 1,57,20,519 1,57,20,519 1,57,20,519 1,57,20,519 1,57,20,519 1,57,20,519 1,57,20,519 1,57,20,519
Interest component 3,93,01,297 3,77,29,245 3,61,57,193 3,45,85,141 3,30,13,089 3,14,41,037 2,98,68,985 2,82,96,934
Depreciation 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257
Taxable Income 4,37,93,078 4,14,16,028 3,90,81,979 3,67,89,632 3,45,37,678 4,33,29,156 4,30,72,348 4,28,13,555
Taxes 42 81 356
NET INCOME 4 37 93 078 4 14 16 028 3 90 81 979 3 67 89 632 3 45 37 678 4 33 29 156 4 30 72 348 3 85 32 200
BASE CASE INCOME STATEMENT
year 0 1.00 2.00 3.00 4.00 5.00 6.00 7.00
Cash in Flow from Operating Activities
Cash flow from sales of unit 11,73,20,590 11,59,25,702 11,45,44,763 11,31,77,634 11,18,24,175 12,14,88,614 12,01,62,090
Cash flow from CDM units 2,03,75,812 2,44,46,572 1,59,76,267 1,38,39,441 1,17,43,754 96,88,597 95,91,711
Total Revenue 13,76,96,412 13,40,80,561 13,05,21,030 12,70,17,075 12,35,67,929 13,11,77,212 12,97,53,801
Cash Out flow from Operating activities
Operating Expenditure 83,31,253 86,64,503 90,11,083 93,71,526 97,46,387 1,01,36,243 1,05,41,692
Total OPEX 83,31,253 86,64,503 90,11,083 93,71,526 97,46,387 1,01,36,243 1,05,41,692
EBIT 12,93,65,160 12,54,16,058 12,15,09,947 11,76,45,549 11,38,21,542 12,10,40,969 11,92,12,109
Taxes - - - - - - -
NOPAT 12,93,65,160 12,54,16,058 12,15,09,947 11,76,45,549 11,38,21,542 12,10,40,969 11,92,12,109
Depreciation 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257
Change in Working Capital (3,01,320.96) (2,96,626.75) (2,91,996.28) (2,87,428.77) 6,34,106.85 (1,18,617.55) (1,17,431.37)
Capital expenditure 49,89,32,243.90
salvage value (After Tax)
Cash Flow (49,89,32,244) 16,02,16,738 15,62,62,942 15,23,52,201 14,84,83,234 14,37,37,693 15,17,09,844 14,98,79,797
Cumulative Cash Flow (49,89,32,244) (33,87,15,506) (18,24,52,564) (3,01,00,364) 11,83,82,871 26,21,20,563 41,38,30,407 56,37,10,204
IRR 29.86%
NPV 67,26,28,437
IRR -29.89%
NPV - 672,628,437 PHP
Payback Period -3.20 years
BASE CASE CASH FLOW
Scenario Analysis
Scenario Pessimistic Base Optimistic
IRR 16.91% 29.86% 54.07%
NPV 155,778,382 672,628,437 2070,395,676
PAYBACK 5.78 years 3.20 years 1.92 years
SCENARIO ANALYSIS
Risk analysis
RISK CATEGORY Reason Risk Mitigation
Project Finance Risk High leveraged Bilateral contracts
Cost overrun Contingency Fund, Advance Contract
Bad Quality Product Service & warranty contract with reputed Companies
Labour Risk Third Party Employment
Low Electricity Generation Minimum Off take contract
Market Risk Low Demand- High Price RPS Mandate of RE Act 2008, FIT RATE
Political Risk Subsidies and Law First Mover Advantage to have Bilateral contract for long term
Operations Risk
Construction Risk
RISK ANALYSIS
• Get the Registration and Approval from DOE basis of Project
Plan.
• Be the First Mover to secure Bilateral contracts.
• Take advantage of bilateral contract to get the Long term
loan.
• Utilize economies of scale to Procure RE components to
procure RE components at the cheaper price.
Go Ahead with Plan!
RECOMMENDATION

More Related Content

What's hot

1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and TrackingATUL RAJ
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenanceLeonardo ENERGY
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsGensol Engineering Limited
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesPuneet Jaggi
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderGensol Engineering Limited
 
Pre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power PlantPre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power PlantGensol Engineering Limited
 
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...OECD Environment
 
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuideUtility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuidePrivate Consultants
 
POWER PURCHASE AGREEMENT.pptx
POWER PURCHASE AGREEMENT.pptxPOWER PURCHASE AGREEMENT.pptx
POWER PURCHASE AGREEMENT.pptxmohammedmarzook1
 
Biomass Power Plants
Biomass Power PlantsBiomass Power Plants
Biomass Power PlantsDaniel Campos
 
Solar Project Management
Solar Project ManagementSolar Project Management
Solar Project Managementfirstgreen
 
Photovoltaic Devices: Life Cycle Considerations
Photovoltaic Devices: Life Cycle ConsiderationsPhotovoltaic Devices: Life Cycle Considerations
Photovoltaic Devices: Life Cycle ConsiderationsGavin Harper
 

What's hot (20)

1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant Maintenance
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar Projects
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best Practices
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
 
Phases of Construction - Solar Project
Phases of Construction - Solar ProjectPhases of Construction - Solar Project
Phases of Construction - Solar Project
 
Pre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power PlantPre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power Plant
 
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
 
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuideUtility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
 
the economics of electricity in the Philippines
the economics of electricity in the Philippinesthe economics of electricity in the Philippines
the economics of electricity in the Philippines
 
POWER PURCHASE AGREEMENT.pptx
POWER PURCHASE AGREEMENT.pptxPOWER PURCHASE AGREEMENT.pptx
POWER PURCHASE AGREEMENT.pptx
 
MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation Schedule
 
Biomass Power Plants
Biomass Power PlantsBiomass Power Plants
Biomass Power Plants
 
EIA World Energy Outlook - 2023
EIA World Energy Outlook - 2023EIA World Energy Outlook - 2023
EIA World Energy Outlook - 2023
 
Solar Power Purchase Agreement Contracts
Solar Power Purchase Agreement ContractsSolar Power Purchase Agreement Contracts
Solar Power Purchase Agreement Contracts
 
Solar Project Management
Solar Project ManagementSolar Project Management
Solar Project Management
 
Solar Power Plant Design and PV Syst
Solar Power Plant Design and PV SystSolar Power Plant Design and PV Syst
Solar Power Plant Design and PV Syst
 
Photovoltaic Devices: Life Cycle Considerations
Photovoltaic Devices: Life Cycle ConsiderationsPhotovoltaic Devices: Life Cycle Considerations
Photovoltaic Devices: Life Cycle Considerations
 
Gensol Permits Procurement Services
Gensol Permits Procurement ServicesGensol Permits Procurement Services
Gensol Permits Procurement Services
 
Gensol - EPC Services
Gensol - EPC ServicesGensol - EPC Services
Gensol - EPC Services
 

Viewers also liked

DOE Philippine Power Situationer, S.Almendras 2012
DOE Philippine Power Situationer, S.Almendras 2012DOE Philippine Power Situationer, S.Almendras 2012
DOE Philippine Power Situationer, S.Almendras 2012noelgamboaylopez
 
150528 oca tenerrdis hydro en fr ra savoie ecosystème innovation
150528 oca tenerrdis hydro en fr ra savoie ecosystème innovation150528 oca tenerrdis hydro en fr ra savoie ecosystème innovation
150528 oca tenerrdis hydro en fr ra savoie ecosystème innovationOlivier CATEURA, PhD
 
Solar energy proposal by MGE
Solar energy proposal by MGESolar energy proposal by MGE
Solar energy proposal by MGEViet Ngo Thanh
 
Vegetables (krizel mae s. salangsang)
Vegetables (krizel mae s. salangsang)Vegetables (krizel mae s. salangsang)
Vegetables (krizel mae s. salangsang)bsed3a
 
Ymca of Metro Chicago Facebook Case Study
Ymca of Metro Chicago Facebook Case StudyYmca of Metro Chicago Facebook Case Study
Ymca of Metro Chicago Facebook Case StudyYMCA of Metro Chicago
 
Feasibility of residential grid connected pv system under the jordanian net m...
Feasibility of residential grid connected pv system under the jordanian net m...Feasibility of residential grid connected pv system under the jordanian net m...
Feasibility of residential grid connected pv system under the jordanian net m...Alexander Decker
 
Feasibility Study of Low Carbon Energy Investments in Jordan. By Bashar Zagha
Feasibility Study of Low Carbon Energy Investments in Jordan. By Bashar ZaghaFeasibility Study of Low Carbon Energy Investments in Jordan. By Bashar Zagha
Feasibility Study of Low Carbon Energy Investments in Jordan. By Bashar Zaghabasharzagha
 
Feasibility of PE investment in African Telecom : SPJCM
Feasibility of PE investment in African Telecom : SPJCMFeasibility of PE investment in African Telecom : SPJCM
Feasibility of PE investment in African Telecom : SPJCMApurva Chiranewala
 
Feasibility study of metro transport case study madurai
Feasibility study of metro transport case study maduraiFeasibility study of metro transport case study madurai
Feasibility study of metro transport case study maduraiIAEME Publication
 
Feasibility Study on Implementing Dry Fermentation Tech - Spencer
Feasibility Study on Implementing Dry Fermentation Tech - SpencerFeasibility Study on Implementing Dry Fermentation Tech - Spencer
Feasibility Study on Implementing Dry Fermentation Tech - SpencerMassRecycle .
 
World's Largest Solar Project
World's Largest Solar ProjectWorld's Largest Solar Project
World's Largest Solar ProjectMitchellDong
 
Feasibility studies for construction of railway
Feasibility studies for construction of railwayFeasibility studies for construction of railway
Feasibility studies for construction of railwayNawid Qasemy
 
“EFFECTIVENESS OF MAKABUHAY (Tinospora rumphii Boerl) STEM EXTRACT IN ELIMINA...
“EFFECTIVENESS OF MAKABUHAY (Tinospora rumphii Boerl) STEM EXTRACT IN ELIMINA...“EFFECTIVENESS OF MAKABUHAY (Tinospora rumphii Boerl) STEM EXTRACT IN ELIMINA...
“EFFECTIVENESS OF MAKABUHAY (Tinospora rumphii Boerl) STEM EXTRACT IN ELIMINA...Manong Inday
 
10 mw solar power plant
10 mw solar power plant10 mw solar power plant
10 mw solar power plantRusiru Sanjaya
 
Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]Fahad Mahmud Mirza
 
India solar power_plant_vpc
India solar power_plant_vpcIndia solar power_plant_vpc
India solar power_plant_vpcPasu Kumar
 
Solar Power Presentation
Solar Power PresentationSolar Power Presentation
Solar Power Presentationthatpho
 
Feasibility study of setting up a computer store chapter 1-5
Feasibility study of setting up a computer store chapter 1-5Feasibility study of setting up a computer store chapter 1-5
Feasibility study of setting up a computer store chapter 1-5Christofer De Los Reyes
 

Viewers also liked (20)

UCLA - Solar Canal Feasibility Study
UCLA - Solar Canal Feasibility StudyUCLA - Solar Canal Feasibility Study
UCLA - Solar Canal Feasibility Study
 
DOE Philippine Power Situationer, S.Almendras 2012
DOE Philippine Power Situationer, S.Almendras 2012DOE Philippine Power Situationer, S.Almendras 2012
DOE Philippine Power Situationer, S.Almendras 2012
 
150528 oca tenerrdis hydro en fr ra savoie ecosystème innovation
150528 oca tenerrdis hydro en fr ra savoie ecosystème innovation150528 oca tenerrdis hydro en fr ra savoie ecosystème innovation
150528 oca tenerrdis hydro en fr ra savoie ecosystème innovation
 
Solar energy proposal by MGE
Solar energy proposal by MGESolar energy proposal by MGE
Solar energy proposal by MGE
 
Vegetables (krizel mae s. salangsang)
Vegetables (krizel mae s. salangsang)Vegetables (krizel mae s. salangsang)
Vegetables (krizel mae s. salangsang)
 
Ymca of Metro Chicago Facebook Case Study
Ymca of Metro Chicago Facebook Case StudyYmca of Metro Chicago Facebook Case Study
Ymca of Metro Chicago Facebook Case Study
 
Feasibility of residential grid connected pv system under the jordanian net m...
Feasibility of residential grid connected pv system under the jordanian net m...Feasibility of residential grid connected pv system under the jordanian net m...
Feasibility of residential grid connected pv system under the jordanian net m...
 
Feasibility Study of Low Carbon Energy Investments in Jordan. By Bashar Zagha
Feasibility Study of Low Carbon Energy Investments in Jordan. By Bashar ZaghaFeasibility Study of Low Carbon Energy Investments in Jordan. By Bashar Zagha
Feasibility Study of Low Carbon Energy Investments in Jordan. By Bashar Zagha
 
Feasibility of PE investment in African Telecom : SPJCM
Feasibility of PE investment in African Telecom : SPJCMFeasibility of PE investment in African Telecom : SPJCM
Feasibility of PE investment in African Telecom : SPJCM
 
Feasibility study of metro transport case study madurai
Feasibility study of metro transport case study maduraiFeasibility study of metro transport case study madurai
Feasibility study of metro transport case study madurai
 
Feasibility Study on Implementing Dry Fermentation Tech - Spencer
Feasibility Study on Implementing Dry Fermentation Tech - SpencerFeasibility Study on Implementing Dry Fermentation Tech - Spencer
Feasibility Study on Implementing Dry Fermentation Tech - Spencer
 
World's Largest Solar Project
World's Largest Solar ProjectWorld's Largest Solar Project
World's Largest Solar Project
 
Feasibility studies for construction of railway
Feasibility studies for construction of railwayFeasibility studies for construction of railway
Feasibility studies for construction of railway
 
“EFFECTIVENESS OF MAKABUHAY (Tinospora rumphii Boerl) STEM EXTRACT IN ELIMINA...
“EFFECTIVENESS OF MAKABUHAY (Tinospora rumphii Boerl) STEM EXTRACT IN ELIMINA...“EFFECTIVENESS OF MAKABUHAY (Tinospora rumphii Boerl) STEM EXTRACT IN ELIMINA...
“EFFECTIVENESS OF MAKABUHAY (Tinospora rumphii Boerl) STEM EXTRACT IN ELIMINA...
 
10 mw solar power plant
10 mw solar power plant10 mw solar power plant
10 mw solar power plant
 
Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]
 
Proposal
ProposalProposal
Proposal
 
India solar power_plant_vpc
India solar power_plant_vpcIndia solar power_plant_vpc
India solar power_plant_vpc
 
Solar Power Presentation
Solar Power PresentationSolar Power Presentation
Solar Power Presentation
 
Feasibility study of setting up a computer store chapter 1-5
Feasibility study of setting up a computer store chapter 1-5Feasibility study of setting up a computer store chapter 1-5
Feasibility study of setting up a computer store chapter 1-5
 

Similar to Feasibility study of setting of solar plant in Philippines

Fuelcell Investor Presentation March 2014
Fuelcell Investor Presentation March 2014Fuelcell Investor Presentation March 2014
Fuelcell Investor Presentation March 2014Company Spotlight
 
Fuelcell investor presentation_14
Fuelcell investor presentation_14Fuelcell investor presentation_14
Fuelcell investor presentation_14Company Spotlight
 
Implementing Net Metering in the Developing World
Implementing Net Metering in the Developing WorldImplementing Net Metering in the Developing World
Implementing Net Metering in the Developing WorldRuchir Punjabi
 
Project Finance Conference Feb 2016
Project Finance Conference Feb 2016Project Finance Conference Feb 2016
Project Finance Conference Feb 2016Niamh McGrath
 
Five myths of Renewable Energy 2013 Bangkok Prabaljit Sarkar
Five myths of Renewable Energy 2013 Bangkok  Prabaljit SarkarFive myths of Renewable Energy 2013 Bangkok  Prabaljit Sarkar
Five myths of Renewable Energy 2013 Bangkok Prabaljit SarkarPrabaljit Sarkar
 
Peter Hobson, SDCL - Introductory Presentation: Sustainable Development Capit...
Peter Hobson, SDCL - Introductory Presentation: Sustainable Development Capit...Peter Hobson, SDCL - Introductory Presentation: Sustainable Development Capit...
Peter Hobson, SDCL - Introductory Presentation: Sustainable Development Capit...OECD Environment
 
RENEWABLE ENERGY SECTOR CONSTRAINTS,SOLUTIONS AND FINANCING
RENEWABLE ENERGY  SECTOR CONSTRAINTS,SOLUTIONS AND FINANCINGRENEWABLE ENERGY  SECTOR CONSTRAINTS,SOLUTIONS AND FINANCING
RENEWABLE ENERGY SECTOR CONSTRAINTS,SOLUTIONS AND FINANCINGNigeria Alternative Energy Expo
 
Regulation's role in demand management and renewables: reflections from the e...
Regulation's role in demand management and renewables: reflections from the e...Regulation's role in demand management and renewables: reflections from the e...
Regulation's role in demand management and renewables: reflections from the e...electricitygovernance
 
Financing energy storage - Masterclass By MACQUARIE
Financing energy storage - Masterclass By MACQUARIEFinancing energy storage - Masterclass By MACQUARIE
Financing energy storage - Masterclass By MACQUARIEDavide Bonomi
 
Scaling up renewable energies
Scaling up renewable energiesScaling up renewable energies
Scaling up renewable energiesRCREEE
 
Presensation For IARU Climate Change Congress
Presensation For IARU Climate Change CongressPresensation For IARU Climate Change Congress
Presensation For IARU Climate Change Congressbrendanwhelan24
 
Building the Energy Efficiency Financing Market
Building the Energy Efficiency Financing MarketBuilding the Energy Efficiency Financing Market
Building the Energy Efficiency Financing MarketSteven Fawkes
 
Evaluation of United Power Generation & Development – Financial & Strategic ...
Evaluation of United Power Generation & Development  – Financial & Strategic ...Evaluation of United Power Generation & Development  – Financial & Strategic ...
Evaluation of United Power Generation & Development – Financial & Strategic ...rubahihs namhar
 
Evaluation of United Power – Financial and Strategic Perspective
Evaluation of United Power  – Financial and Strategic PerspectiveEvaluation of United Power  – Financial and Strategic Perspective
Evaluation of United Power – Financial and Strategic PerspectiveShihabur Rahman
 
The case for net metering in Country 'X'
The case for net metering in Country 'X'The case for net metering in Country 'X'
The case for net metering in Country 'X'Joseph Saviour
 

Similar to Feasibility study of setting of solar plant in Philippines (20)

Andrew Tipping - Green Growth Diagnostics for Africa
Andrew Tipping - Green Growth Diagnostics for AfricaAndrew Tipping - Green Growth Diagnostics for Africa
Andrew Tipping - Green Growth Diagnostics for Africa
 
Fuelcell Investor Presentation March 2014
Fuelcell Investor Presentation March 2014Fuelcell Investor Presentation March 2014
Fuelcell Investor Presentation March 2014
 
Fuelcell investor presentation_14
Fuelcell investor presentation_14Fuelcell investor presentation_14
Fuelcell investor presentation_14
 
Implementing Net Metering in the Developing World
Implementing Net Metering in the Developing WorldImplementing Net Metering in the Developing World
Implementing Net Metering in the Developing World
 
Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
 
Project Finance Conference Feb 2016
Project Finance Conference Feb 2016Project Finance Conference Feb 2016
Project Finance Conference Feb 2016
 
Five myths of Renewable Energy 2013 Bangkok Prabaljit Sarkar
Five myths of Renewable Energy 2013 Bangkok  Prabaljit SarkarFive myths of Renewable Energy 2013 Bangkok  Prabaljit Sarkar
Five myths of Renewable Energy 2013 Bangkok Prabaljit Sarkar
 
Jim barry presentation
Jim barry presentationJim barry presentation
Jim barry presentation
 
Peter Hobson, SDCL - Introductory Presentation: Sustainable Development Capit...
Peter Hobson, SDCL - Introductory Presentation: Sustainable Development Capit...Peter Hobson, SDCL - Introductory Presentation: Sustainable Development Capit...
Peter Hobson, SDCL - Introductory Presentation: Sustainable Development Capit...
 
RENEWABLE ENERGY SECTOR CONSTRAINTS,SOLUTIONS AND FINANCING
RENEWABLE ENERGY  SECTOR CONSTRAINTS,SOLUTIONS AND FINANCINGRENEWABLE ENERGY  SECTOR CONSTRAINTS,SOLUTIONS AND FINANCING
RENEWABLE ENERGY SECTOR CONSTRAINTS,SOLUTIONS AND FINANCING
 
Regulation's role in demand management and renewables: reflections from the e...
Regulation's role in demand management and renewables: reflections from the e...Regulation's role in demand management and renewables: reflections from the e...
Regulation's role in demand management and renewables: reflections from the e...
 
Financing energy storage - Masterclass By MACQUARIE
Financing energy storage - Masterclass By MACQUARIEFinancing energy storage - Masterclass By MACQUARIE
Financing energy storage - Masterclass By MACQUARIE
 
Scaling up renewable energies
Scaling up renewable energiesScaling up renewable energies
Scaling up renewable energies
 
10 pv o&amp;m budgeting - pricing &amp; practices - epri v1
10   pv o&amp;m budgeting - pricing &amp; practices - epri v110   pv o&amp;m budgeting - pricing &amp; practices - epri v1
10 pv o&amp;m budgeting - pricing &amp; practices - epri v1
 
Vietnam _Green Growth
Vietnam _Green GrowthVietnam _Green Growth
Vietnam _Green Growth
 
Presensation For IARU Climate Change Congress
Presensation For IARU Climate Change CongressPresensation For IARU Climate Change Congress
Presensation For IARU Climate Change Congress
 
Building the Energy Efficiency Financing Market
Building the Energy Efficiency Financing MarketBuilding the Energy Efficiency Financing Market
Building the Energy Efficiency Financing Market
 
Evaluation of United Power Generation & Development – Financial & Strategic ...
Evaluation of United Power Generation & Development  – Financial & Strategic ...Evaluation of United Power Generation & Development  – Financial & Strategic ...
Evaluation of United Power Generation & Development – Financial & Strategic ...
 
Evaluation of United Power – Financial and Strategic Perspective
Evaluation of United Power  – Financial and Strategic PerspectiveEvaluation of United Power  – Financial and Strategic Perspective
Evaluation of United Power – Financial and Strategic Perspective
 
The case for net metering in Country 'X'
The case for net metering in Country 'X'The case for net metering in Country 'X'
The case for net metering in Country 'X'
 

Recently uploaded

8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creationsnakalysalcedo61
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 

Recently uploaded (20)

8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 

Feasibility study of setting of solar plant in Philippines

  • 1. Feasibility study of setting up a 10 MW solar farm in Luzon Submitted By Siddharth Kundu MBA 2012 Candidate Asian Institute of Management Proponent Shrinivas Polishetty American orient Capital Partners Philippines Mentors Prof. G Ortigas Prof. F Roxas Asian Institute of Management MANAGEMENT RESEARCH REPORT
  • 2. FLOW OF PRESENTATION Industry Analysis Internal Analysis PEST Analysis Five forces Framework Demand & supply Key success Factors Opportunities & Threat American Orient Capital Partners Stakeholder Analysis Revenue Model/sources Operations strategy Marketing strategy Financials Risk Recommendation The Company
  • 3. • Government is supporting and attracting investment in Renewable energy sector Political • Continuous growth of GDP ,Industry Power requirements are increasing Economic • Total per capita of consumption of electricity is continuously increasing Social • Solar technology is getting affordable and non- conventional energy cost is increasing Technology MACRO ENVIRONMENT ANALYSIS - PEST
  • 4. Threat of New Entrants LOW Bargaining Power of Suppliers Low Bargaining Power of Buyers Medium Competitive Rivalry HIGH Threat of Substitutes MEDIUM Capital Requirement – High Economies of Scale – High Product Differentiation – Low First mover Advantage - High Government and Legal Barriers - High Buyer Propensity to Substitutes – LOW Relative Price of the Substitutes - Medium Buyers Sensitivity to Price – High RPS mandate- Low Buyers Sensitivity to Price – High Relative Bargaining Power – High Industry Concentration – Low Diversity of Competitors – low Product Differentiation – LOW Exit Barriers - High The Industry is attractive for New Players PORTER’S FIVE FORCES – SOLAR DEVELOPER
  • 5. Supply Side Demand Factors CURRENT DEMAND AND SUPPLY OF ELECTRICITY - Philippines Solar Energy (<0.01%) Dependable Capacity 2011 13902 MW Renewable Energy 44% 6117 MW Locally Produced 55% Imported Sources 45% Total Peak Demand 2011 11226 MW 11226 14311 24434 0 5000 10000 15000 20000 25000 30000 2011 2018 2030 Demand (MW)
  • 6. Is there Opportunity for solar farming in Pangasinan, Luzon? Distribution Companies  4 distribution companies in vicinity to have bilateral contracts  2 of them do not have renewable sourcing of electricity Consumption  Luzon till 2030 – 11,9000 MW  Pangasinan currently consumes more than 1310 MW First Mover Advantage No proposed or approved solar projects in the Pangasinan
  • 7. Strategic Land site for setting up project Distance from substation or main transmission line Cost of land Solar generation capacity of land- Pvsyst analysis Initial setup cost( sourcing capability) Cost and quality of RE components Cost and quality of project engineering Initial project startup registration cost and fees Capital structure Interest rate of debt Principal and Interest Payback period for debt Bilateral contracts & CDM rate Bilateral contract rate CDM Rate Price escalation clause Minimum off take Agreement Approvals & registration DOE and NREB of Approval for the project CDM registration with UNFCCC to trade Carbon credits Registry with European Union Emission Trading System (EUETS) Capital Funding Price Place Suppliers and components Political Factors KEY SUCCESS FACTORS
  • 8. Threat  Approved Solar projects in Luzon  Lack of trust on the legal and judicial system and previously rigid laws on venturing in Philippines reduced the entry of foreign investment.  Costly power transmission capacity may affect the demand and supply of electricity.  Natural calamities Opportunities  All electric power industry participants ( distributors) are mandated to comply with the RPS  No operating solar player in Region- 1, Luzon  Potential Demand and supply gap of electricity  Four Distribution companies in the vicinity of the project.  Solar is given top most priority among all other sources of RE OPPORTUNITIES AND THREATS
  • 10. Who are we?  AOCP is an investment and financial advisory services company.  Over 100 major transactions valued in excess of US$10 billion in Asia  They have acquired an unmatched blend of exposure and experience with international financial and industrial sectors. Objective of American Orient capital Partners Why are AOCP interested in Solar ? To check the feasibility of Solar energy Development in Philippines. To produce and sell electricity and CDM generated from project. To benefit by supply RE for the Renewable portfolio Standard set by NREB to meet demand of renewable source of energy.
  • 12. STAKEHOLDERS Analysis 10 MW SOLAR FARM WSEM GOVERNMENT Approvals/Sanctions Regulatory Compliances Electricity Trading SUPPLIERS Better deals in procuring RE components UNFCCC Approvals and sanction Carbon credit Trading Electricity Distributors  Bilateral Contracts BANKS Financing Options
  • 13. Power Interest Hi Mid Lo HiMid G S B D W G Manage closelyKeep satisfied Monitor Keep Informed B Bank D Distributor S Component supplier W wsemGovernment Stakeholder Power grid Matrix
  • 14. Bilateral contract - For fixed cash flow to meet to long term debt principal and interest amount CDM certificates - To benefit by registering for sale of CDM certificate from the green renewable energy project Trading energy in WESM - By selling at the spot market to enjoy the benefit of spot market rate with a guarded floor price of 9.68 Revenue Model / Sources of Revenue
  • 15. 1st degree potential customers • PANELCO 3 • CENPALCO • DECORP • PANELCO 1 2nd degree potential customers • INEC • ISESCO • LUELCO • Meralco 3rd degree potential customers • Nor feeds • B Meg • SYGENTA • University of Eastern Philippines Potential Bilateral Contract Customers
  • 16. • Total Purchase of electricity in a year ? • What are the source generation companies for buying electricity and detailed breakup of energy purchase? • Are you ready for Minimum off take in bilateral contract ? • Is your cooperative ready to buy electricity from solar energy producers ? If yes then at what rate? Factors considered while deciding Bilateral contract Rate
  • 17.  The price goes high as up to 60 Peso/ KwH  The amount electricity traded at more than 10 Peso is almost to an little less than 10 % of total transactions happening of WSEM.  The average trading rate 6.9 Peso in peak hours is 9am -4 PM.  The floor price for solar energy set by FIT rate is Peso 9.68  Solar energy will be given first Priority among all sources of energy on the trade floor. Picture: Average trading rate Graph of WSEM Electricity trading at WSEM
  • 18.  Company has to be registered to European Union Emission Trading System (EUETS)  Receiving UNFCCC approval for emissions reduction projects in order to yield carbon credits  Average trading rate is 3 Euro/Ton for CDM CERTIFICATE  52 week high was around 13.5 euro / ton for CDM CERTIFICATE  It is forecasted to be around 20 euro/ ton on average by Year 2020 by big trading houses in CDM trading houses in Europe.  Risk mitigation of fluctuating CDM rate can done by having carbon exchange contracts CDM Trading
  • 19. • Major task of operation will be keep the site running to its maximum potential. • To look after the regular technical maintainace and cleaning of the plant. • Approval & Permits – 4 weeks • Construction of Site – 3 weeks • Component installation-3 weeks OPERATION STRATEGY Timeline for Project Site operation Employees and Cost
  • 20. We need to have good relationship with the suppliers to get a attractive rate , good quality RE components and after sales service.  Solar panels are the costliest Component for this project. The rate charged is .69$ per Wp with 10 year warranty and CIS.  Around 38000,265 Wp modules will be required to make 10 MW plant  Land & structure cost are second costliest component and make 25 % of total Capex RE Components/Suppliers
  • 21. Looking at the study on solar projects, our marketing approach will be showing the value proposition of the solar project and promote the affordability to strengthen our possibility of favourable bilateral contract Ways of Promoting • Public Relations • B2B Presentation & seminar • Website Marketing strategy
  • 22. Project Director/ CEO American Orient capital Partners , Philippines Project Manager , HR manager ,Costing & audit Manager, Sales & Marketing Manager, Operations & Panel Engineer- Experienced Industry Professionals 1-Field engineer, 4-Field operator 6-daily labor, 4- security guard ORGANISATION STRUCTURE - PROJECTS
  • 23.  This will be a P 560 Million Project  Capital Expenditure is P 498 million  Operating expense is around P 8 million per year.  Contingency Amount-P 158,17,581 3% of total Capital expenditure to factor in any unexpected cost. DEBT – EQUITY Ratio 70:30 Funding structure ( All figures in Peso unless mentioned )
  • 24. Scenario Pessimistic Base Optimistic Long term interest rate(%) PA 12% 10% 7.45% Bilateral contract rate (peso) 6.4 6.9 9 Generation / Production(KwH) 10,000,000 14,410,000 17,520,000 CDM Credit Certificate(Euro) 0 3 9 FIT rate -WSEM 9.68 9.68 9.68-3 years/ 17 - 4th year onward OPEX escalation (%) 4 4 4 Depreciation Accelerated Depreciation Bilateral Rate escalation Every 5 years Financial Assumptions
  • 25. Base case scenario Pessimistic Case Scenario Optimistic case PERCENTAGE OF REVENUE SHARE FOR DIFFERENT SCENARIOS
  • 26. Year 2012 2013 2014 2015 2016 2017 2018 2019 2020 All figures in Peso unless mentioned Units Generated (kWh) 1,44,10,000 1,42,65,900 1,41,23,241 1,39,82,009 1,38,42,189 1,37,03,767 1,35,66,729 1,34,31,062 Tariff 6.90 6.90 6.90 6.90 6.90 8.28 8.28 8.28 Units decided to sold on bilateral contract 79,74,176 79,74,176 79,74,176 79,74,176 79,74,176 79,74,176 79,74,176 79,74,176 Revenue from Bilateral Tariff 5,50,21,815 5,50,21,815 5,50,21,815 5,50,21,815 5,50,21,815 6,60,26,178 6,60,26,178 6,60,26,178 Units to sold WSEM 64,35,824 62,91,724 61,49,065 60,07,832 58,68,012 57,29,591 55,92,553 54,56,886 WSEM ** Tairff 9.68 9.68 9.68 9.68 9.68 9.68 9.68 9.68 Revenue from wsem Tariff 6,22,98,775 6,09,03,887 5,95,22,948 5,81,55,818 5,68,02,360 5,54,62,436 5,41,35,912 5,28,22,652 CDM benefit 2,03,75,812 1,81,54,849 1,59,76,267 1,38,39,441 1,17,43,754 96,88,597 95,91,711 94,95,794 Total Revenues 13,76,96,402 13,40,80,551 13,05,21,030 12,70,17,075 12,35,67,929 13,11,77,212 12,97,53,801 12,83,44,625 Opex 83,31,253 86,64,503 90,11,083 93,71,526 97,46,387 1,01,36,243 1,05,41,692 1,09,63,360 Working Capital 1,14,74,700 1,11,73,379 1,08,76,753 1,05,84,756 1,02,97,327 1,09,31,434 1,08,12,817 1,06,95,385 Outstanding debt 39 30 12 966 37,72,92,446.90 36,15,71,928 34,58,51,410 33,01,30,891 31,44,10,372 29,86,89,854 28,29,69,335 26,72,48,817 Annual debt repayment 1,57,20,519 1,57,20,519 1,57,20,519 1,57,20,519 1,57,20,519 1,57,20,519 1,57,20,519 1,57,20,519 Interest component 3,93,01,297 3,77,29,245 3,61,57,193 3,45,85,141 3,30,13,089 3,14,41,037 2,98,68,985 2,82,96,934 Depreciation 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 Taxable Income 4,37,93,078 4,14,16,028 3,90,81,979 3,67,89,632 3,45,37,678 4,33,29,156 4,30,72,348 4,28,13,555 Taxes 42 81 356 NET INCOME 4 37 93 078 4 14 16 028 3 90 81 979 3 67 89 632 3 45 37 678 4 33 29 156 4 30 72 348 3 85 32 200 BASE CASE INCOME STATEMENT
  • 27. year 0 1.00 2.00 3.00 4.00 5.00 6.00 7.00 Cash in Flow from Operating Activities Cash flow from sales of unit 11,73,20,590 11,59,25,702 11,45,44,763 11,31,77,634 11,18,24,175 12,14,88,614 12,01,62,090 Cash flow from CDM units 2,03,75,812 2,44,46,572 1,59,76,267 1,38,39,441 1,17,43,754 96,88,597 95,91,711 Total Revenue 13,76,96,412 13,40,80,561 13,05,21,030 12,70,17,075 12,35,67,929 13,11,77,212 12,97,53,801 Cash Out flow from Operating activities Operating Expenditure 83,31,253 86,64,503 90,11,083 93,71,526 97,46,387 1,01,36,243 1,05,41,692 Total OPEX 83,31,253 86,64,503 90,11,083 93,71,526 97,46,387 1,01,36,243 1,05,41,692 EBIT 12,93,65,160 12,54,16,058 12,15,09,947 11,76,45,549 11,38,21,542 12,10,40,969 11,92,12,109 Taxes - - - - - - - NOPAT 12,93,65,160 12,54,16,058 12,15,09,947 11,76,45,549 11,38,21,542 12,10,40,969 11,92,12,109 Depreciation 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 3,05,50,257 Change in Working Capital (3,01,320.96) (2,96,626.75) (2,91,996.28) (2,87,428.77) 6,34,106.85 (1,18,617.55) (1,17,431.37) Capital expenditure 49,89,32,243.90 salvage value (After Tax) Cash Flow (49,89,32,244) 16,02,16,738 15,62,62,942 15,23,52,201 14,84,83,234 14,37,37,693 15,17,09,844 14,98,79,797 Cumulative Cash Flow (49,89,32,244) (33,87,15,506) (18,24,52,564) (3,01,00,364) 11,83,82,871 26,21,20,563 41,38,30,407 56,37,10,204 IRR 29.86% NPV 67,26,28,437 IRR -29.89% NPV - 672,628,437 PHP Payback Period -3.20 years BASE CASE CASH FLOW
  • 28. Scenario Analysis Scenario Pessimistic Base Optimistic IRR 16.91% 29.86% 54.07% NPV 155,778,382 672,628,437 2070,395,676 PAYBACK 5.78 years 3.20 years 1.92 years SCENARIO ANALYSIS
  • 29. Risk analysis RISK CATEGORY Reason Risk Mitigation Project Finance Risk High leveraged Bilateral contracts Cost overrun Contingency Fund, Advance Contract Bad Quality Product Service & warranty contract with reputed Companies Labour Risk Third Party Employment Low Electricity Generation Minimum Off take contract Market Risk Low Demand- High Price RPS Mandate of RE Act 2008, FIT RATE Political Risk Subsidies and Law First Mover Advantage to have Bilateral contract for long term Operations Risk Construction Risk RISK ANALYSIS
  • 30. • Get the Registration and Approval from DOE basis of Project Plan. • Be the First Mover to secure Bilateral contracts. • Take advantage of bilateral contract to get the Long term loan. • Utilize economies of scale to Procure RE components to procure RE components at the cheaper price. Go Ahead with Plan! RECOMMENDATION

Editor's Notes

  1. How do u suggest the continuously growing?
  2. Talk about existing technologies .Solar technology availability and how does it benefit.
  3. 211 mw project approved but not running.
  4. RPS standard
  5. United Nations Framework Convention on Climate Change
  6. which if not produced can be bought from wholesale spot electricity market(WESM) following the regulations of Electricity Regulation Market (ERC) or can have direct contracts with RE producersshall be required to maintain a minimum share of renewable energy in their portfolio consistent with the level set by the NREB in Philippines
  7. Remove useless data.to make it big
  8. This has been analysed by studying over the monthly reports of WESM 10 months of last 10 months.
  9. Receiving UNFCCC approval for emissions reduction projects in order to yield carbon credits is a complex procedure.  At both national and international levels, approvals, validations &amp; verifications must be received.  This system separates the opportunist voluntary carbon projects from the true business of developing sustainability whilst reducing pollution in the developing world.