10 MW Solar PV power Plant - CPM & PERT, Design

8,904 views

Published on

This presentation includes the information of CPM, PERT Pathways of Solar PV Plants and its Design.

Published in: Engineering

10 MW Solar PV power Plant - CPM & PERT, Design

  1. 1. 10 MW Solar PV Power plant Project Team | Nandhini | Nithya | Sowparanika | Ragul | Vignesh
  2. 2. Design & CPM, PERT November 27 - Friday Program Evaluation & Review Technique (PERT) Network Model Critical Path Method (CPM) Mode of activities Grid Connected PV Design
  3. 3. SPV GRID TIE – Without Battery
  4. 4. Design Calculation Total Plant Size - 10 MW Individual Sections - 500 kW * 20 Sets No.of DC Cabinet - 560 V * 20 Sets No.of AC Cabinet - 380 V * 20 Sets No.of Inverters - 500 kVA * 20 Sets No.of Junction Boxes - 560 W * 320 Sets Monitoring Devices - 1 Set Protection Devices - 1 Set Infrastructure - As required
  5. 5. Each 500 kW Set PV Arrays - 16 Sets Mounting Structure - 16 Sets DC Junction Box (560 W) - 16 Sets DC Cabinet (560 V) - 1 Set Inverter (500 kVA) - 1 Set AC Distribution Cabinet - 1 Set 15 PV Arrays - Has 8 Rows Last PV Array - Has 5 Rows Each Row - Has 16 Modules Net Panels (500 kW) - (8*16) + (5*16) = 2000 Panels Like 20 Sets (10 MW) - 20*2000 = 40000 Panels PV Array – 16
  6. 6. 250 Wp Si-Mono Panel
  7. 7. 500 kW - Design layout PV Array 1 DCDistributionBox ACDistributionBox Inverter Junction Box 1PV Array 1 Junction Box 2PV Array 2 Junction Box 3PV Array 3 Junction Box 4PV Array 4 Junction Box 5PV Array 5 Junction Box 6PV Array 6 Junction Box 7PV Array 7 Junction Box 8PV Array 8 Junction Box 9PV Array 9 Junction Box 10PV Array 10 Junction Box 11PV Array 11 Junction Box 12PV Array 12 Junction Box 13PV Array 13 Junction Box 14PV Array 14 Junction Box 15PV Array 15 Junction Box 16PV Array 16
  8. 8. 10 MW Design layout DISTRIBUTION BOARD
  9. 9. CPM & PERT ACTIVITY DESCRIPTION PRECEEDING ACTIVITY DURATION (WEEKS) A SITE ASSESSMENT - 1 B DESIGNING A 1 C LABOUR AND MACHINERY PLANNING B 1 D PROCUREMENT B 6 E MOUNTING STRUCTURE (ERECTION) C,D 2 F PANEL ERECTION E 3 G JUNCTION BOX F 1 H CABLING G 2 I INVERTER G 1 J TRANSFORMER H,I 2 K COMMISSIONING J 1
  10. 10. 1 2 3 A B 5 4 6 D C E 7 F G 8 9 10 H I 11 J K 12
  11. 11. CPM Possible pathways: A-B-C-E-F-G-H-J-K =14 weeks A-B-D-E-F-G-I-J-K =18 weeks

×