1. BIM FOR ALL STAGES OF THE
PROJECT LIFECYCLE
Krzysztof Nowosiński –BIM Champion
2. VSU PROJECT
Best deployment of BIM on a
Project, 2012
AWARD WINNING BIM PROJECTS
CASEMENT PARK STADIUM
2013 BIM Project of the Year
2014 Fiatech CETI Automated
Design Award
2014 BIM Initiative of the Year
“The real clincher was the
development of a 5D BIM
process with an object
based naming convention
as a blueprint for future
projects – both delivering
and learning on the job!
Judging panel comments
3. To champion lean
solutions, including BIM
and off-site construction,
to minimise carbon
emissions, resource use
and waste on all our
projects
OUR COMMITMENT TO DfMA
“
”
15. CENTRAL BIM
4D PROGRAMME 6D ASSET
MANAGEMENT
5D COST PLANCLASH DETECTION
BUILDING SERVICES
MODEL
ENGINEERING
ANALYSIS
THERMAL,
BREEAM
FIRE
LIGHTING
DESIGN
ENGINEERING
DESIGN
CIVIL INFRASTRUCTURE
CUT & FILL
MODELS
DRAINAGE
TRAFFIC
MODELS
WASTE
STUDIES
DELIVERY &
LOADING
ACCESS
STRUCTURAL
MODEL
WIND
ANALYSIS
BOWL
DESIGN
ROOF
DESIGN
BUILD
SEQUENCE
CONCEPTUAL
STUDIES
DAYLIGHT
STUDIES
SIGHT LINES
VISUALISATION
ARCHITECTURAL
MODEL
PEOPLE
FLOW
3D FLY-
THROUGH
‘RIGHT TO
LIGHT’
16. Generative model with input parameters
Revit model exported
into CSC Fastrak
Exported to Robot
for dynamics
calculation
Models exported to Robot
Optimised for
minimum steel
weight avoiding
value engineering
Linked via Geometry
Gym and IFC link
17. Intelligent
properties added to
rooms and spaces
3D modelling of plant
areas and main
distribution routes
Energy modelling
Truss feature
lighting
Sports lighting
analysis
18. BIM used for elemental
quantification
Clash detection
between disciplines
4D construction
studies
Multidisciplinary reviews
19. 5D PROCESS IMPROVEMENTS
Benefits
- Consistent approach to naming conventions
- Quantification accuracy within 1%
- Real time cost reports
- Delivery of better value buildings for our clients
5D Publishing Guide now being used on multiple projects
80%
Time saving to
prepare cost plan
25. Construction Phase
Water Level
Drill Rods left in-situ
Level of assumed clay
Revised level of clay from
recent boreholes
Known gap between jet grout
columns
REDUCING RISK USING BIM
Extracts from 3d models used
in daily site review meetings
27. Design for manufacture and assembly
ANGLIAN WATER PRODUCT BASED DELIVERY
BIM hugely facilitates offsite manufacture
28. Design for manufacture and assembly
ANGLIAN WATER PRODUCT BASED DELIVERY
20%
Less Carbon
90%
Time saving
29. Design for manufacture and assembly
M inimum
Asset
Standard
3D M odel
Drawings
Integration
Guide
Health & Safety
Risk Assessment
Calculations
Specification
Procurement
Guide
Framework
Agreement
BOM
Cost data
Acceptance
Criteria
Installation
Guide
Commissioning
Data
Functional
Design Spec
Software Block
M aintenance
Schedule
Spares
Schedule
O&M
data
SAP ALM
data
JoE
Carbon
Footprint
Telemetry
Standards
Asset M onitoring
Frameworks (IRIS)
STANDARD
PRODUCTS
34. Asset management
INTEGRATED ASSET INFORMATION
Asset data GIS data
Middleware
Data
Users
Performance data
Delivery partners Operators Asset Managers
Survey data
35. Asset management
As-Built Owner
Model
As-Maintained
Owner Model
Changes in Maximo
updated in
Owner Model
Navisworks for
visualization
Links between
geometry and data
Empty Maximo
Database
Populated Maximo
Database
Publish key Revit
Data for O&M
EMERGING ASSET MANAGEMENT