MONITORING OF PROJECT IMPLEMENTATION
A MANUAL
Office of External Relations
Pan American Health Organization
Pan American Sanitary Bureau, Regional Office of the
World Health Organization
www.paho.org
February 1999
Monitoring of Project Implem.3 11/3/00 10:40 AM Page i
Foreword
The introduction of the Logical Framework Approach (LFA) in PAHO a few years ago
has resulted in important improvements in the area of project design.Technical units and
Representations have improved their capacity to prepare better projects, incorporating all
the elements that will provide a greater chance for the attainment of the goals and that
will make a project appealing to the international community. Externally funded projects
are critical in the delivery of PAHO’s technical cooperation to countries, enhancing our
capacity to respond to demands beyond our regular resources.
We have a manual known as the “Standardized Format for PAHO Project Documents
and Profiles”, guiding our personnel, providing them with what are considered the mini-
mum requirements for a good project.This manual is intended to guide a project designer
step by step, securing that all basic elements of good project design are present, including:
involvement of all stakeholders, establishment of clear goals and purpose, identification of
assumptions and risks, and definition of expected results, manageable interest, necessary
activities, indicators of progress and means of verification, etc.
In addition,PAHO has created the necessary internal mechanisms for project review
through the establishment of the Project Review Process (PRP) and Project Review Group
(PRG). Both have allowed the Organization to have a clear view of the projects prepared by
different organizational structures,their degree of development,their priority within Divisions
and the Organization as a whole,and their status in obtaining support from the international
community. The PRG has been an excellent opportunity for peer review,personnel develop-
ment in project design,and identification of opportunities for inter-programmatic work.
To get a project funded is not enough. It is also necessary to execute it well, timely
and in accordance with agreed upon commitments with donors and beneficiaries.
Monitoring is critical to project execution. It is a management tool for tracking progress of
on-going projects and is an integral part of project execution. Accordingly, project man-
agers must develop a monitoring plan to enable them to perform this function with dili-
gence, overseeing integral project implementation, including technical and financial
aspects. Project management is an area within the Organization that needs strengthening.
The purpose of this manual, prepared by the Office of External Relations (DEC), is to cre-
ate some standard procedures, as was done with project design, for managing the imple-
mentation of technical cooperation projects. It provides guidance on how to monitor proj-
ects in a way that will make project management more effective, and facilitate follow up.
Once in place, monitoring will save time and effort for the project manager and will facili-
tate project reporting on achievements and obstacles to our counterparts. Good reporting
provides the basis for continued support from the international community.
Irene Klinger
Chief, Office of External Relations
Monitoring of Project Implem.3 11/3/00 10:40 AM Page ii
TABLE OF CONTENTS
1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
1.1. What is monitoring and why is it useful? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
1.2. Purpose of the manual . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
1.3. How the monitoring manual relates to other PAHO documents . . . . . . . . . . . . . . . . . . . . . . . . . . .2
2. The project cycle and the use of evaluation tools . . . . . . . . . . . . . . . . . . . . . . . . . .2
2.1. The planning process in PAHO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3
2.2. The project cycle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3
2.3. Spanish – English terminology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4
2.4. Purpose of appraisal, monitoring and evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
3. Project management during the implementation phase . . . . . . . . . . . . . . . . . . .5
3.1. The project document . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
3.2. Preparing annual work plans and budgets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
3.3. Responsibilities of the project manager . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6
3.4. The logical framework approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6
3.5. How far does the project manager’s responsibility extend? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7
4. The monitoring procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7
4.1. Reviewing the agreement with the donor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7
4.2. Making an operational plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8
4.3. Making annual work plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9
4.4. Breaking down the project budget . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9
4.5. Preparing a monitoring plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .10
4.5.1. Performance indicators and their definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11
4.5.2. Baseline data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11
4.5.3. Performance targets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12
4.5.4. Means of verification and data source . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13
4.5.5. Method of data collection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13
4.5.6. Frequency and schedule of data collection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14
4.5.7. Responsibilities for acquiring data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14
4.5.8. Data analysis plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14
4.5.9. Identifying needs for complementary evaluations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14
4.5.10. Plans for communicating and using monitoring information . . . . . . . . . . . . . . . . . . . . . . .14
5. Analyzing results of monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15
6. Suggesting correcting measures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15
7. Editing progress reports/annual reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15
8. Concluding remarks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .16
8.1. A participatory approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .16
8.2. Results Oriented Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .17
ANNEX I
CONDENSED GUIDE FOR PAHO MONITORING PROCEDURE . . . . . . . . . . . . . . . . . . . . . . . . . . . .19
ANNEX II
FORMAT FOR ANNUAL PROGRESS REPORT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22
LIST OF ABBREVIATIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .24
Monitoring of Project Implem.3 11/3/00 10:40 AM Page iii
1
1. Introduction
1.1. What is monitoring and why is it useful?
Monitoring is a management tool for tracking progress of ongoing projects.
The basic idea is to compare actual performance with plans and to measure
actual results against expected results.
The monitoring function is an integral part of project execution. It is simply
a way of making efficient project follow-up and to provide systematic, consis-
tent and reliable information on project progress.
Once in place, monitoring will save time and effort for the project manager
and facilitate project follow-up and reporting. It does not make a project more
complex – instead, it makes it more systematically manageable.
Monitoring serves the project manager in several ways:
• It provides information to be presented to national counterparts, PAHO and
external financing partners at periodic meetings and in progress reports.
• It provides a basis for decisions on necessary modifications of the project:
Resource utilization may be adjusted, priorities shifted and new activities
introduced. Flexibility and agility in project management is enhanced.
• It helps the manager:
- to show results,
- to understand and explain to others what is happening in the project
and why expected results are or are not achieved,
- to provide arguments for needed changes, and
- to build confidence with top management in PAHO, national counter-
parts and financing partner agencies.
• It improves the chances of serving the target population well, because the
effect on the target population is analyzed reiteratively.
1.2. Purpose of the manual
Project management is an area within the organization that needs strength-
ening.The purpose of this manual is to create some standard procedure for man-
aging the implementation of technical cooperation projects and to provide guid-
ance on how to perform monitoring in a way that will make project manage-
ment more effective, facilitate follow-up and make reporting more consistent.
The manual is organized in such a way that it should be easy to use for ref-
erence.After the introductory chapters which define monitoring and its place
in the project cycle, as well as its use as a management tool during project
implementation, the monitoring procedure is explained step by step (Chapter
4).Annex I contains a Condensed guide to the PAHO monitoring procedure
and annex II a format for annual progress reports.
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 1
2
1.3. How the monitoring manual relates to other PAHO documents
This manual builds on and is closely linked to a number of other PAHO doc-
uments and systems in use.
AMPES, the system through which PAHO establishes managerial procedures
for planning, programming, monitoring and evaluation provides the framework
for this new manual.The basic document explaining the application of AMPES:
Technical Cooperation Planning, Programming and Evaluation System AMPES
(1998) should be familiar to all readers.
Already in use in PAHO is also the manual Standardized Format for PAHO
Project Documents and Profiles (1994), relating to the Design Phase of the proj-
ect cycle.The new manual should be seen as a complement elaborated to sup-
port the Implementation Phase in the life of a project.
The two manuals, as well as AMPES, are based on the Logical Framework
Approach (LFA) to Project Management. A review of the document The
Logical Approach to Project Management in PAHO is recommended
(PAHO/AD-DAP/96.01).
2. The project cycle and the use of evaluation tools
2.1. The planning process in PAHO
The planning process in PAHO called AMPES includes five levels of objectives
linked by hierarchy and encompasses the following three stages of planning:
1 Policy Planning,
2 Strategic Planning, and
3 Operational Planning.
This manual is related only to the Operational Planning.The figure below
illustrates the hierarchy and the planning levels.
AMPES
Policy Planning General Program of Work (GPW)
Strategic and Programmatic Orientations (SPO)
Strategic Planning Biennial Program Budget (BPB)
Operational Programming Semiannual Program of Work (SPW)
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 2
3
2.2. The project cycle
Project management in PAHO encompasses responsibility for the three
phases of the project cycle:
The project manager will need different analytical tools to assess and evalu-
ate the project in each phase of the cycle:
• Appraisal for the Design phase.
• Monitoring for the Implementation phase.
• Ex-post evaluation for the Evaluation phase.
The concepts of appraisal, monitoring and ex-post evaluation must be clear-
ly separated.Their respective places in the project cycle are illustrated in the
figure above.
2.3. Spanish – English terminology
In Spanish, the term “evaluación” is often used for all three activities:
appraisal, monitoring and ex-post evaluation. In order to establish a clear and
unambiguous terminology, the following terms should be used in English and
Spanish, respectively:
LOGICAL
APPROACH
EVALUATION
Ex-post evaluation
DESIGN
Appraisal
IMPLEMENTATION
Monitoring
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 3
4
2.4. Purpose of appraisal, monitoring and evaluation
The purpose of an appraisal is to assess the viability of a proposed project
before a decision is taken.The project design is scrutinized and alternative
approaches and designs are compared.As a result, it will be recommended that
the project be implemented as proposed, be modified or not be executed at all.
Appraisal is sometimes called ex-ante evaluation.
The purpose of monitoring is to steer a project towards its purpose and to
detect any problems that makes it probable that the project will not achieve
expected results.This is done through periodic follow up of technical progress
and financial expenditure, whereby actual performance and results are com-
pared to plans.
The purpose of ex-post evaluation is to improve the design, strategy and
processes of development cooperation by learning lessons of experience.
Evaluation addresses the higher levels of the project hierarchy,i.e. the project
purpose and the project goal.
Monitoring and evaluation share some of the same objectives:
• To improve the management of projects and ensure the optimum use of
funds.
• To foster accountability and transparency in the management process.
• To ensure that the technical cooperation is pertinent, effective and efficient.
• To provide well substantiated information on project progress and results
to be reported to higher levels in the organization, stakeholders and finan-
cial partners.
• To learn lessons of experience with the aim of improving the design, formu-
lation and management of projects (organizational learning).
Monitoring and evaluation are however different with respect to their tim-
ing and the aspects that they address. Evaluation is more occasional than moni-
toring and is typically undertaken “after the fact” analyzing the long-term
English Spanish
Design phase Appraisal Evaluación ex ante
Implementation phase Monitoring Monitoreo
Evaluation phase Ex-post evaluation Evaluación ex post
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 4
5
impact of an intervention. Monitoring, on the other hand, is done periodically
during project implementation assessing project progress.
From now on this manual will address the concept and tool of monitoring
only, i.e. tracking project progress during the implementation of a project.
3. Project management during the implementation phase
3.1. The project document
The project document, which is elaborated at the final stage of project
preparation, is a systematic description of the project including a budget and a
chronogram. It is intended to guide the implementation phase. It is also the
basis for the formal agreements between PAHO and the national counterparts
and between PAHO and external financing partners.
3.2. Preparing annual work plans and budgets
The project document covers the entire project period. In order to translate
the document into operational programming, it is necessary to break it down
into annual work plans and budgets.Tasks, activities and expenditure are pro-
grammed on a yearly basis (or any other chosen period).The work plan is in
fact a calendar of activities to be performed in a given period and the estimated
financial expenditure related to these activities, as well as an identification of
the responsible party for its execution.
The annual work plan and budget will then form a basis for monitoring of
project progress.They should be elaborated in collaboration with designated
(international, national, and local) counterparts and be presented to higher lev-
els of management in PAHO and to external financing partners.
3.3. Responsibilities of the project manager
Successful project implementation requires that managers assume the fol-
lowing responsibilities:
• Manage all the resources.
• Produce outputs (the expected results) of the project.
• Perform technical as well as financial monitoring.
• Alert top management when
- The achievement of expected results is uncertain.
- Problems within the project appear to threaten achievement of the
project purpose.
- Changes in the project environment have a negative impact on the project.
• Recommend adjustments and corrective action.
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 5
6
3.4. The logical framework approach
The logical approach (LFA) to project management provides the basic ele-
ments needed for designing complex projects and assisting in their execution,
monitoring and evaluation. LFA is a management tool that facilitates project
management.
It is expected that projects designed with LFA have well-formulated objec-
tives and measurable targets to make it possible to monitor progress and assess
results. Indicators need to be established, means of verification determined and
assumptions explicitly stated.
3.5. How far does the project manager’s responsibility extend?
The LFA matrix also defines the responsibilities for a project.
The lower levels of the LFA hierarchy, up to and including expected results,
are under management control.The project manager will therefore be responsi-
ble and held accountable for achieving the expected results.This is sometimes
called the management contract.
Achievement of the project purpose, on the other hand, depends partly on
factors beyond the project manager’s control; hence he or she cannot assume
responsibility or be held accountable for achieving the project purpose and
even less for attaining the goal. Nevertheless, the project manager is committed
to working towards the purpose and the goal of the project and to alert his/her
superiors, if there is evidence or probability that the project purpose will not
be achieved.
LFA MATRIX FOR PROJECT DESIGN
HIERARCHY OF INDICATORS MEANS OF ASSUMPTIONS
OBJECTIVES VERIFICATION AND RISKS
GOAL
PURPOSE
EXPECTED RESULTS
ACTIVITIES Resources
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 6
7
As shown in this figure, monitoring is to be focused on the activities and
expected results levels, while evaluations should address the project purpose
level, and possibly also the goal level.
4. The monitoring procedure
In this section the reader will be guided through a typical monitoring pro-
cedure, step by step.
4.1. Reviewing the agreement with the donor
For every new project funded by the international community, there will be
either a project specific agreement, or an umbrella agreement that rules the
relations with that specific donor and covers more than one project.
The project manager should familiarize him/herself with that agreement in
order to ensure compliance with all its specifications, which have been
approved and signed by PAHO’s Director or his designate. Project agreements
have specific clauses regarding transfers of funds, structures for project imple-
mentation, project personnel, procurement issues, relations with national coun-
terparts, involvement of the donor at different stages, reporting requirements,
etc. These are all crucial elements to be considered by the project manager
when defining plans of action and when monitoring execution.
Not under management control:
E V A L U A T I O N
Under management control
and responsibility:
M O N I T OR I N G
GOAL
PURPOSE
EXPECTED
RESULTS
ACTIVITIES
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 7
8
4.2. Making an operational plan
Once the project document is approved, an operational plan for the entire project
period must be elaborated. By this is meant that activities necessary for achieving
expected results are outlined indicating the sequence and timing of and defining
dates when stated results are to be achieved.A simplified and condensed operational
plan may be organized as follows:
OPERATIONAL PLAN FOR PROJECT CONTRIBUTING TO THE ELIM-
INATION OF ILLNESSES CAUSED BY DRINKING IMPURE WATER
Project purpose: Hygienic practices adopted
by rural population in the NW region
J
A
N
F
E
B
M
A
R
A
P
R
M
A
Y
J
U
N
J
U
L
A
U
G
S
E
P
O
C
T
N
O
V
D
E
CExpected Results
01 Clean water provided to villages in NW region
02 Health workers trained
03 Community informed about water treatment
techniques
Activities
01 Consultations with regional and local
representatives
Choose sites for wells
Determine techniques
Invitation to tender
Contract firm
02 Develop curriculum
Develop training material
Train trainers
Select participants
Conduct training courses
Evaluate results of training
03 Assess hygienic practices to create baseline
Organize local workshops
Hire trainers
Recruit local representatives
Conduct workshops
Evaluate hygienic practices after training
Chronogram
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 8
9
4.3. Making annual work plans
Based on the operational plan annual work plans should be elaborated
specifying in greater detail the timing of technical execution and related finan-
cial expenditure.A calendar of activities and a budget related to planned activi-
ties and expected results should be established. For the first year the plan must
be detailed and specific.Towards the end of the first year a more specific work
plan for the following year will be elaborated and so on.
For a specific year in the work plan the following will be defined:
• expected results to be achieved based on the project document
• activities to be performed
• tasks to be undertaken
• costs,i.e.a budget specifying funds needed to carry out the annual work plan.
The work plan forms the basis for the technical monitoring.
4.4. Breaking down the project budget
The project budget included in the project document indicates the finan-
cial resources needed for the entire project period.The costing of the project is
calculated on the basis of tasks, activities and expected results.This budget now
needs to be broken down by year or shorter periods to show what resources
will be needed to accomplish the work plan.
The annual work plan outlining the technical execution should be accom-
panied by a break down of expected costs related to tasks, activities and the
expected results.
A simplified project budget may look like this:
YEAR 1 YEAR 2 YEAR 3 TOTAL BUDGET
Result 01
Activity 1
Task 1
Task 2
Activity 2
Cost per year
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 9
10
The project manager will need a budget with a considerable level of detail.
Superiors and financing partners, however, will be better served with budgets
where items have been aggregated up to the activities level or even to results
level.This way they get a better overview.
The budget constitutes the basis for the financial monitoring.
4.5. Preparing a monitoring plan
Once the work plan is elaborated, a monitoring plan should be prepared. It
should address the expected results level, i.e. when, whether or to what extent
expected results are being achieved.
At the task and the activity levels, performance will be checked against the
calendar of activities and the budget. No other indicators are needed.This is a
straightforward and relatively uncomplicated exercise and will not be dealt
with further here.
A monitoring plan is used to plan, manage and document the data collec-
tion process. It ensures that comparable data will be collected on a regular and
timely basis. It identifies the indicators to be tracked, specifies the source,
method and schedule of data collection and assigns responsibilities.The plan
will help keeping the monitoring system on track and ensure that data are
reported regularly to project management.
The elaboration of such plan should preferably be undertaken with partici-
pation of all the stakeholders of the project, specially a representative of the
beneficiary party, as well as the financing partner.A multiparty project steering
or technical committee, with representatives of all stakeholders, is usually a
good participatory mechanism to monitor progress. It allows for a shared view
on planning and on monitoring indicators. It also offers opportunity for
exchange of views among all involved on obstacles and potential solutions.
The following elements should be included in the monitoring plan:
Plans for data collection:
• Performance indicators and their definitions
• Baseline data
• Performance targets
• Data Source
• Method of data collection
• Frequency and Schedule of data collection
• Responsibilities for acquiring data
Plans for data analysis, reporting and use of information:
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 10
11
• Data analysis plans
• Identifying needs for complementary evaluation
• Plans for communication and using monitoring information
Each one of these elements is explained below and some advice offered.
4.5.1. Performance indicators and their definitions
For monitoring purposes, indicators need only to be defined for the
expected results level. In the work plan some preliminary indicators may
have been identified. In that case, they should be revised and, if necessary,
complemented.
Example:
Good indicators start with a clear statement of objectives or expected
results. Each indicator needs a detailed definition specifying quantity, quality
and time.When selecting indicators the most important characteristics are
the following:
• Validity – that the indicator actually measures what is purported to
measure,
• Reliability – that repeated measurements will give the same results,
• Sensibility – that the indicator will be responsive to changes, and
• Specificity – that the indicator measures only those changes related to
the project intervention in question.
4.5.2. Baseline data
It is hardly possible to establish targets or measure progress without
knowing what the situation is like at the commencement of a project.That
is why baseline data have to be established before the project starts.They
should reflect, as near as possible, the value of each indicator at the outset
of a project and they will be the value against which changes will be meas-
ured throughout the project period.
1.Patients´ waiting period
reduced by 30%
Waiting time
measurement
2.Medical staff receives 10%
more patients per day
Number of
patients
3.User satisfaction level
remains the same
Patients
opinions
PROJECT PURPOSE EXPECTED RESULT INDICATORS
Management of health
services improved
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 11
12
Example:
In a project aimed at increased wheat production of small farmers establishing
the baseline is easy, at least in theory:The level of production of wheat at the
outset of a project specifying the quality of wheat.
In cases where expected results are of a more qualitative nature, e.g.“increased
awareness of hygienic practices related to use of water”, it takes a bit more
imagination to establish the baseline.
4.5.3. Performance targets
Targets represent the exact level and timing of expected results to be
achieved by a project.Whereas the indicator defines how performance will
be measured along a scale or dimension, the target identifies the specific
planned level of result to be achieved within an explicit time frame.
Example:
If the expected result is “patients' waiting period reduced by 30% in a two year
period”, interim targets may be set as follows:
“10% reduction of average waiting time by July Year 1; further 10% reduction by
January Year 2 and finally an additional 10% reduction by July Year 2.”
A final target is the planned value of an indicator by the end of the proj-
ect or the planning period. If this time frame is very long, it is advisable to
set interim targets or, as they are often called, milestones.
Example:
Expected result:“Access to clean drinking water to 80% of the rural population
in the province of Santa Clara”.
When the project starts only 50% of the population has access to clean water
(baseline value).The project is planned for a seven-year period.The final target
is 80% to be achieved by the end of 7 years. In this case it may be wise to
establish intermediate targets, e.g. 60% after two years, 70% after four years
and 80% after seven years.
It is a good idea to use a cumulative curve to illustrate the intermediate
targets and the final target.This will be a good basis for comparison with
actual achievements.
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 12
13
4.5.4. Means of verification and data source
The means of verification make it possible to verify the status of the
indicators.They should be defined in the LFA-matrix of the project docu-
ment. If this has not been done or if new indicators have been selected,
project management has to establish means of verification.
The data source is where the data to verify the status of the indicator
are to be found. It can be an institution that conducts the data collection or
a system for data collection set up by the project. It is important that the
same source can be used routinely, as switching data sources for the same
indicator over time can lead to inconsistencies and misinterpretations. For
example switching from estimates of infant mortality rates based on nation-
al sample surveys to estimates based on hospital registration statistics can
lead to false impressions of change.
Two examples:
4.5.5. Method of data collection
The method or approach to data collection for each indicator should be
specified. It should be noted whether it is primary data collection or is
based on secondary data.
For primary data collection, consider
• The unit of analysis
• Data segregation needs (by gender, age, ethnic group, location)
• Sampling techniques
• Techniques or instruments for acquiring data.
EXPECTED
RESULTS
Reduced mortality of
pre-school children by
20% in three years
Management of health
services more respon-
sive to client demands
INDICATORS
U5MR
Patients’ waiting time
reduced.
More patients
received.
Client satisfaction
increased.
MEANS OF
VERIFICATION
Mortality statistics
Waiting time
monitoring sheet
Satisfaction levels
DATA SOURCE
Bureau of National
Statistics
Statistics of 10 select-
ed health centers on
number of patients
and waiting time.
Exit questionnaires to
clients
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 13
14
For indicators based on secondary data,give the method of calculating the
specific indicator data point and the sources of data.Provide sufficient detail
on the data collection or calculation method to enable it to be replicated.
4.5.6. Frequency and schedule of data collection
Monitoring systems must gather comparable data periodically to meas-
ure progress. How often should data be collected? There is no general
answer. Depending on the indicator, it may make sense to collect data on a
quarterly, annual or less frequent basis. For example, because changes are
slow, fertility data may be collected every few years whereas data on contra-
ceptive distribution and sales may be gathered quarterly.
When planning the frequency and the scheduling for data collection,
important factors to consider are the management’ s needs for timely deci-
sion making and the decision points in the project cycle.
4.5.7. Responsibilities for acquiring data
In terms of each indicator, the responsibility for the timely acquisition
of data from their source should be clearly assigned to a particular individ-
ual, team or office.The mode of registration of data should be determined.
4.5.8. Data analysis plan
To the extent possible, it is advisable to plan in advance not only for the
collection of data, but also for data analysis, reporting, review and use, to
identify data analysis techniques and data presentation formats to be used.
4.5.9. Identifying needs for complementary evaluations
Evaluations of ongoing projects should be undertaken only when moni-
toring results show that there are serious problems or obstacles that make
it less probable that the project purpose be achieved. For example, if rea-
sons for not meeting targets are not clearly understood, planning evalua-
tions to investigate and analyze the project makes sense.
4.5.10. Plans for communicating and using monitoring information
Planning how monitoring information will be used is critical for effec-
tive management.There are basically three ways of using the information:
1. Influencing management decisions
2. Writing progress/semiannual or annual reports directed to superiors,
national counterparts and financing partners.
3. Sharing the information with stakeholders for discussion and analysis.
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 14
15
5. Analyzing results of monitoring
Analysis of monitoring results is basically a matter of comparing actual per-
formance with plans, and actual expenditure with budget and analyzing devia-
tions and discrepancies.This can be expressed in words, as well as in tables and
diagrams. Figures usually are easier and faster to interpret illustrating clearly the
comparison between plans and outcome.
Example:
In this case the technical execution, i.e. the number of health workers
trained, is only 90% of the expected, while the cost amounts to 16% more than
budgeted.There may be good reasons for this cost overrun that need to be
explained. Or there may be problems that motivate a change in the organiza-
tion of the training.
Discrepancies and shortfalls may be due to problems or conditions within
the project, such as the project organization, administrative systems, change of
project directors or shortage of staff.
But there is also the possibility that disappointing results, delays or cost
overruns are due to situations or changes in the project environment, such as
political disturbances, natural disasters, new legislation or increasing inflation.
The latter factors are related to the assumptions and assessment of risks that
should be considered at the project design stage.
6. Suggesting correcting measures
Depending on the results of the analysis the project manager may want to
propose corrective measures, improve the project design or adjust resource
allocation.The operational frame or the assigning of responsibilities may need
adjustment. Monitoring results will help justify such measures.
7. Editing progress reports/annual reports
Monitoring results should be incorporated into periodic reports and taken into
account when new work plans are drawn up.The reports should always relate to
the project document and to the LFA matrix presented in that document.
TRAINING OF HEALTH WORKERS
No. planned Actual no. % Budgeted cost. Actual cost. %
trained US$ US$
180 162 90% 8,600 10,100 116%
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 15
16
There are two main issues that should be addressed in the reports:
• Technical execution – as related to the annual plan. Focus should be on the
Expected Results level more than on the Activity and Task levels.
• Financial execution – as related to budget and specifically to expected cost
for producing Expected Results and to carrying out Activities.
The reporting on the two issues must be synchronized comparing the
degree of technical execution with the utilization of funds. It is the responsibili-
ty of the project manager to ensure that this match exists.
The monitoring of the technical execution provides the Project Manager with
elements for the technical reporting, while the financial system in PAHO (Budget
and Finance Division) supplies him or her with the financial information.
The reporting requirements of external financing partners are defined in the
respective agreements between PAHO and the contracting partner. Requirements
vary to some extent in terms of frequency, content and level of detail.
It is important that reports are well structured, concise and to the point.
The aim should be to give an overview of project progress, of the extent to
which expected results have been achieved, of problems encountered in proj-
ect execution and in the project environment, and of perspectives for the next
reporting period. It is wise to avoid getting involved in great detail.
The structure of the reports should remain the same throughout the life of
the project and the level and categories of reporting should be maintained in
order to facilitate comparison.
8. Concluding remarks
8.1. A participatory approach
Experience shows that people centered approaches to design, monitoring
and evaluation enhance ownership and promote the sustainability of interven-
tions. Participatory approaches will lead to greater involvement, better and
more lasting results, and shared commitment and responsibilities.
As convenient and pertinent, counterparts, staff and the representatives for
the target group should therefore be involved in planning and conducting mon-
itoring activities, interpreting data, analyzing results and discussing the reasons
for results being achieved or not achieved. Besides the instant advantages of
such an approach, it also has the benefit of building national capacity in the
area of monitoring.
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 16
17
8.2. Results Oriented Management
Monitoring for project progress is an integral part of project management. It
is a useful tool that does not make project management more difficult or more
complicated. On the contrary, it pays in the long run to establish an effective
system of monitoring. It is a way of managing projects better and smarter.
Monitoring will save time and effort for the project manager and make proj-
ect follow-up and reporting more effective.
Monitoring is a way of knowing and understanding what is going on in the
project and of being in control.The results serve as the basis for decisions with
regard to the need for reprogramming and/or reassigning human and financial
resources. It will provide relevant and timely information to top management
on the progress and any difficulties encountered in the project.
Monitoring is to be focused on the Expected Results level of the LFA hier-
archy, a level that is under management control.The project document, and
more particularly the annual work plans, constitutes the basis for monitoring
project progress.
Monitoring means comparing actual performance with plans. It includes
two distinct but interrelated types of follow-up: technical execution of the proj-
ect and financial expenditure related to the project.The two aspects of moni-
toring and reporting should be performed in a synchronized manner.
Monitoring results are valuable inputs in future evaluations of the project.
Effective monitoring will enhance the quality of project management.This is a
logical step in the institutional development of the organization and will make
PAHO more accountable and attractive as a partner of external financing agencies.
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 17
ANNEXES
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 18
19
Annex I
CONDENSED GUIDE FOR PAHO MONITORING PROCEDURE
1. PREPARING THE MONITORING PLAN
1.1. Review project agreement
Internalize all aspects related to project execution and reporting that
appear in the project agreement signed with the donor.What are the commit-
ments? Which procurement procedures? How often will transfers of funds be
made? Which implementation structure needs to be in place? How often are
reports due? How will donor be involved or not during the life of the project?
1.2. Review LFA matrix for project.
What are the “expected results” to be achieved?
1.3. Review work plan for current year.
What activities are to take place during the year?
What is the expected expenditure (budget) for the year?
What should be achieved by the end of the year?
1.4. Review/develop indicators for tracking progress at the “expected
results” level
Which are the indicators whereby progress can be tracked?
Which targets have been set (expected results level):
• To be achieved by the end of the project?
• To be achieved by the end of the year (intermediate targets or milestones)?
Expected End of project TargetYear 1 ResultYear 1 % of year
results target target
01
02
03
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 19
20
1.5. What are the means of verification of the selected indicators?
1.6. What data sources should be used?
1.7. Who is responsible for the data collection?
2. DATA COLLECTION IN ACCORDANCE WITH
MONITORING PLAN
3. ANALYSIS OF MONITORING RESULTS
3.1. Rate of technical execution?
3.2. Rate of financial execution?
3.3. Consolidating and comparing technical and financial execution
3.4. Technical execution: Deviations and discrepancies from planned
results?
• At the level of “expected results”
• At the level of activities
3.5. Technical execution:Analysis of deviations and shortfalls
• Problems within the project (project design, organization, counterparts,
staffing etc)?
TRAINING OF HEALTH WORKERS
No. planned Actual no. % Budgeted cost. Actual cost. %
trained US$ US$
180 162 90% 8,600 10,100 116%
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 20
21
• Problems in the project environment – outside the control of project man-
agement?
• Any unexpected results – positive or negative?
3.6. Financial execution: Deviations from budget
• At the level of expected results
• At the level of activities
3.7. Financial execution:Analysis of over-spending or under-spending
4. PROPOSED ACTION
• Immediate action?
• Adjustments in work plan of the following year
• Adjustments in budget for the following year
5. CONCLUSIONS AND LESSONS LEARNED
Budget Actual Expenditure as
Year 1 expenditure % of budget
Expected
result 01: 100 90 90
Activity 1 25 25 100
Activity 2 40 36 90
Activity 3 35 29 83
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 21
22
ANNEX II
FORMAT FOR ANNUAL PROGRESS REPORT
The report should preferably be limited to 10 pages, and should in no case
exceed 15 pages. If more information is deemed pertinent and necessary it
should be presented in annexes to the report.
1. EXECUTIVE SUMMARY
Principal project achievements, problems, summary, financial execution and
future proposals
(one page).
2. INTRODUCTION-CONTEXT
Brief history of the project. Political, social and economic context in which
the project is carried out.
This section should not exceed one page unless there were changes affecting
the development of the project (such as elections, natural disasters, and war).
3. PERTINENT NATIONAL POLICIES AND THEIR IMPACT ON
THE PROJECT
RELATIONS TO NATIONAL AND LOCAL COUNTERPARTS
Maximum one page.
4. PROJECT PROGRESS
This section must be based on the LFA matrix. Explanatory notes should
not exceed three pages.
4.1 Describe to what extent the expected results have been achieved using the
data emerging from the project monitoring. Refer to good indicators.
Explain and comment delays, deviations and differences of actual perform-
ance as compared to plans. Indicate and discuss problems, deficiencies,
errors etc and propose corrective action.
4.2 Indicate to what extent expected results are actually contributing to the
project purpose. Comment on whether or to what extent the project envi-
ronment – what is outside the control of the project – has affected the proj-
ect positively or negatively.Are there any unexpected results, positive or
negative?
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 22
23
4.3 Assess progress from the point of view of project management, e.g. com-
ment on project organization, operational framework, administrative sys-
tems, adequacy of staffing – both in PAHO and the counterpart institution.
5. FINANCIAL EXECUTION ANALYSIS
This section should not exceed two pages.
5.1 Analyze expenditure as percentage of budget by activity corresponding to
the work plan. If requested by donor, also include PAHO’s budget compo-
nents. In case of multi-country projects, include tables for each country, as
well as a consolidated table.
5.2 Utilizing the ABF/ABU official report prepared by the Budget and Report
Section of PAHO, show the rate of technical and financial execution by con-
solidating technical and financial data. Explain and comment on any devia-
tion. Suggest corrective measures, as necessary.This is not an auditing exer-
cise, but rather a review of project progress in relation to the utilization of
funds.The purpose is to determine whether it is necessary to reassign allot-
ments or adjust calendar of activities.
5.3 Introduce a financial chart showing
a) PAHO’s contribution,including resources from external financing partners
b) National counterpart contribution
5.4 All the data mentioned should be presented for the year for which the
report is made, and accumulated during life of the project and also be relat-
ed to the original project document and budget.
6. FUTURE PROGRAMMING
Propose the work plan for the following year. In the case of multi-country
projects, include one for each country.
Comments are necessary only if new activities are introduced or if changes
are proposed in terms of activities or the budget contained in the original proj-
ect document.
7. ADDITIONAL COMMENTS
Further comments should be included only if there are relevant or impor-
tant issues that have not already been covered in the report.
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 23
24
LIST OF ABBREVIATIONS
ABF/ABU Office of Budget and Reports
AMPES Technical Cooperation Planning, Programming and
Evaluation System
BPB Biennial Program Budget
DEC Office of External Relations
GPW General Program of Work
LFA Logical Framework Approach
PAHO Pan American Health Organization
PRG Project Review Group
PRP Project Review Process
SPO Strategic and Programmatic Orientations
SPW Semiannual Program of Work
U5MR Under 5 Mortality Rate
Monitoring of Project Implem.3 11/3/00 10:40 AM Page 24
Office of External Relations
Pan American Health Organization
Pan American Sanitary Bureau, Regional Office of the
World Health Organization
525 Twenty-third Street, N.W. 20037, U.S.A.
February 1999 P a n A m e r i c a n H e a l t h O r g a n i z a t i o n
o 10 20 30 40 50 60 70 80 90 100
PROJECT IMPLEMENTATION
a manual
MONITORING of
Monitoring Cover Final.qxd 11/3/00 10:42 AM Page 1

More Related Content

What's hot

Presentation project management
Presentation project managementPresentation project management
Presentation project managementFlobz Caloy
 
Introduction to monitoring and evaluation
Introduction to monitoring and evaluationIntroduction to monitoring and evaluation
Introduction to monitoring and evaluation
Meshack Lomoywara
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycleAndrei Crăciun
 
LEADERSHIP AND PROJECT MANAGEMENT
LEADERSHIP AND PROJECT MANAGEMENTLEADERSHIP AND PROJECT MANAGEMENT
LEADERSHIP AND PROJECT MANAGEMENT
RDC ZP
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
Nishant Munjal
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
Waleed Elnaggar
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
Anand Bobade
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
BhuWan Khadka
 
Project m&e & logframe
Project m&e & logframeProject m&e & logframe
Project m&e & logframeWesley Opaki
 
Monitoring and evaluation frameworks logical framework
Monitoring and evaluation frameworks logical frameworkMonitoring and evaluation frameworks logical framework
Monitoring and evaluation frameworks logical framework
Preston Healthcare Consulting
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
Institute of Rural Management
 
Sponsorship presentation
Sponsorship presentationSponsorship presentation
Sponsorship presentation
Association for Project Management
 
Project integration management
Project integration managementProject integration management
Project integration management
Saad Al Jabri
 
Project Management
Project ManagementProject Management
Project Management
ahmad bassiouny
 
Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
megat zainurul anuar
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
S. Sathishkumar
 
Project Closing
Project ClosingProject Closing
Project Closing
Martin Sillaots
 
TTIPEC: Monitoring and Evaluation (Session 2)
TTIPEC: Monitoring and Evaluation (Session 2)TTIPEC: Monitoring and Evaluation (Session 2)
TTIPEC: Monitoring and Evaluation (Session 2)
Research to Action
 
Project management
Project managementProject management
Project management
meena velmurugan
 

What's hot (20)

Presentation project management
Presentation project managementPresentation project management
Presentation project management
 
Introduction to monitoring and evaluation
Introduction to monitoring and evaluationIntroduction to monitoring and evaluation
Introduction to monitoring and evaluation
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
LEADERSHIP AND PROJECT MANAGEMENT
LEADERSHIP AND PROJECT MANAGEMENTLEADERSHIP AND PROJECT MANAGEMENT
LEADERSHIP AND PROJECT MANAGEMENT
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
Project m&e & logframe
Project m&e & logframeProject m&e & logframe
Project m&e & logframe
 
Monitoring and evaluation frameworks logical framework
Monitoring and evaluation frameworks logical frameworkMonitoring and evaluation frameworks logical framework
Monitoring and evaluation frameworks logical framework
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 
Sponsorship presentation
Sponsorship presentationSponsorship presentation
Sponsorship presentation
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Project Management
Project ManagementProject Management
Project Management
 
Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
Project cycle
Project cycleProject cycle
Project cycle
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
Project Closing
Project ClosingProject Closing
Project Closing
 
TTIPEC: Monitoring and Evaluation (Session 2)
TTIPEC: Monitoring and Evaluation (Session 2)TTIPEC: Monitoring and Evaluation (Session 2)
TTIPEC: Monitoring and Evaluation (Session 2)
 
Project management
Project managementProject management
Project management
 

Similar to Monitoring of project implementation

English version dec 24 final 1
English version dec 24 final 1English version dec 24 final 1
English version dec 24 final 1
wondimg
 
International innovators business plan
International innovators business planInternational innovators business plan
International innovators business plan
jitharadharmesh
 
Mbg spmp project_management
Mbg spmp project_managementMbg spmp project_management
Mbg spmp project_management
University of Colombo School of Computing
 
Comprehensive Multi-year Plan - Universal Immunization Program Reaching Every...
Comprehensive Multi-year Plan - Universal Immunization Program Reaching Every...Comprehensive Multi-year Plan - Universal Immunization Program Reaching Every...
Comprehensive Multi-year Plan - Universal Immunization Program Reaching Every...
ITSU - Immunization Technical Support Unit
 
RDGB Corporate Profile
RDGB Corporate ProfileRDGB Corporate Profile
RDGB Corporate Profile
Rejaul Islam
 
IT Project Planning Standards V 1.2
IT Project Planning Standards V 1.2IT Project Planning Standards V 1.2
IT Project Planning Standards V 1.2
Ahmed303
 
Comunis Project report
 Comunis Project report  Comunis Project report
GAD-harmonized-gad-guidelines-2nd_ed_0 (1).pdf
GAD-harmonized-gad-guidelines-2nd_ed_0 (1).pdfGAD-harmonized-gad-guidelines-2nd_ed_0 (1).pdf
GAD-harmonized-gad-guidelines-2nd_ed_0 (1).pdf
JzaninnaSolBagtas
 
Conducting BIAs for UASC in Cairo (RefugePoint 2012)
Conducting BIAs for UASC in Cairo (RefugePoint 2012)Conducting BIAs for UASC in Cairo (RefugePoint 2012)
Conducting BIAs for UASC in Cairo (RefugePoint 2012)Devon Cone
 
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnershipInterim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnershipEd Dodds
 
Where tonight mobile application.pdf
Where tonight  mobile application.pdfWhere tonight  mobile application.pdf
Where tonight mobile application.pdf
okorisolo
 
Chat Application [Full Documentation]
Chat Application [Full Documentation]Chat Application [Full Documentation]
Chat Application [Full Documentation]
Rajon
 
Us gsa (1992) value engineering program guide for design and construction -...
Us gsa (1992)   value engineering program guide for design and construction -...Us gsa (1992)   value engineering program guide for design and construction -...
Us gsa (1992) value engineering program guide for design and construction -...
Wan Yusoff Wan Mahmood
 
Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...
Chris Delepierre
 
Report iatc-final
Report iatc-finalReport iatc-final
Report iatc-finalagjinopulli
 
AU-NEPAD African Action Plan 2010-2015
AU-NEPAD African Action Plan 2010-2015AU-NEPAD African Action Plan 2010-2015
AU-NEPAD African Action Plan 2010-2015
Dr Lendy Spires
 
Watershed Development in India An Approach Evolving through Experience_0.pdf
Watershed Development in India An Approach Evolving through Experience_0.pdfWatershed Development in India An Approach Evolving through Experience_0.pdf
Watershed Development in India An Approach Evolving through Experience_0.pdf
ravi936752
 

Similar to Monitoring of project implementation (20)

English version dec 24 final 1
English version dec 24 final 1English version dec 24 final 1
English version dec 24 final 1
 
J4769e06
J4769e06J4769e06
J4769e06
 
International innovators business plan
International innovators business planInternational innovators business plan
International innovators business plan
 
Mbg spmp project_management
Mbg spmp project_managementMbg spmp project_management
Mbg spmp project_management
 
Comprehensive Multi-year Plan - Universal Immunization Program Reaching Every...
Comprehensive Multi-year Plan - Universal Immunization Program Reaching Every...Comprehensive Multi-year Plan - Universal Immunization Program Reaching Every...
Comprehensive Multi-year Plan - Universal Immunization Program Reaching Every...
 
RDGB Corporate Profile
RDGB Corporate ProfileRDGB Corporate Profile
RDGB Corporate Profile
 
IT Project Planning Standards V 1.2
IT Project Planning Standards V 1.2IT Project Planning Standards V 1.2
IT Project Planning Standards V 1.2
 
Comunis Project report
 Comunis Project report  Comunis Project report
Comunis Project report
 
GAD-harmonized-gad-guidelines-2nd_ed_0 (1).pdf
GAD-harmonized-gad-guidelines-2nd_ed_0 (1).pdfGAD-harmonized-gad-guidelines-2nd_ed_0 (1).pdf
GAD-harmonized-gad-guidelines-2nd_ed_0 (1).pdf
 
Conducting BIAs for UASC in Cairo (RefugePoint 2012)
Conducting BIAs for UASC in Cairo (RefugePoint 2012)Conducting BIAs for UASC in Cairo (RefugePoint 2012)
Conducting BIAs for UASC in Cairo (RefugePoint 2012)
 
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnershipInterim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
 
Where tonight mobile application.pdf
Where tonight  mobile application.pdfWhere tonight  mobile application.pdf
Where tonight mobile application.pdf
 
PM Trends
PM TrendsPM Trends
PM Trends
 
Chat Application [Full Documentation]
Chat Application [Full Documentation]Chat Application [Full Documentation]
Chat Application [Full Documentation]
 
Us gsa (1992) value engineering program guide for design and construction -...
Us gsa (1992)   value engineering program guide for design and construction -...Us gsa (1992)   value engineering program guide for design and construction -...
Us gsa (1992) value engineering program guide for design and construction -...
 
Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...
 
Report iatc-final
Report iatc-finalReport iatc-final
Report iatc-final
 
AU-NEPAD African Action Plan 2010-2015
AU-NEPAD African Action Plan 2010-2015AU-NEPAD African Action Plan 2010-2015
AU-NEPAD African Action Plan 2010-2015
 
M&E Report SEAL 2012
M&E Report SEAL 2012M&E Report SEAL 2012
M&E Report SEAL 2012
 
Watershed Development in India An Approach Evolving through Experience_0.pdf
Watershed Development in India An Approach Evolving through Experience_0.pdfWatershed Development in India An Approach Evolving through Experience_0.pdf
Watershed Development in India An Approach Evolving through Experience_0.pdf
 

Recently uploaded

The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
balatucanapplelovely
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
agatadrynko
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Avirahi City Dholera
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
Lital Barkan
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
fisherameliaisabella
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
zechu97
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
Adam Smith
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 

Recently uploaded (20)

The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 

Monitoring of project implementation

  • 1. Office of External Relations Pan American Health Organization Pan American Sanitary Bureau, Regional Office of the World Health Organization 525 Twenty-third Street, N.W. 20037, U.S.A. February 1999 P a n A m e r i c a n H e a l t h O r g a n i z a t i o n o 10 20 30 40 50 60 70 80 90 100 PROJECT IMPLEMENTATION a manual MONITORING of Monitoring Cover Final.qxd 11/3/00 10:42 AM Page 1
  • 2. MONITORING OF PROJECT IMPLEMENTATION A MANUAL Office of External Relations Pan American Health Organization Pan American Sanitary Bureau, Regional Office of the World Health Organization www.paho.org February 1999 Monitoring of Project Implem.3 11/3/00 10:40 AM Page i
  • 3. Foreword The introduction of the Logical Framework Approach (LFA) in PAHO a few years ago has resulted in important improvements in the area of project design.Technical units and Representations have improved their capacity to prepare better projects, incorporating all the elements that will provide a greater chance for the attainment of the goals and that will make a project appealing to the international community. Externally funded projects are critical in the delivery of PAHO’s technical cooperation to countries, enhancing our capacity to respond to demands beyond our regular resources. We have a manual known as the “Standardized Format for PAHO Project Documents and Profiles”, guiding our personnel, providing them with what are considered the mini- mum requirements for a good project.This manual is intended to guide a project designer step by step, securing that all basic elements of good project design are present, including: involvement of all stakeholders, establishment of clear goals and purpose, identification of assumptions and risks, and definition of expected results, manageable interest, necessary activities, indicators of progress and means of verification, etc. In addition,PAHO has created the necessary internal mechanisms for project review through the establishment of the Project Review Process (PRP) and Project Review Group (PRG). Both have allowed the Organization to have a clear view of the projects prepared by different organizational structures,their degree of development,their priority within Divisions and the Organization as a whole,and their status in obtaining support from the international community. The PRG has been an excellent opportunity for peer review,personnel develop- ment in project design,and identification of opportunities for inter-programmatic work. To get a project funded is not enough. It is also necessary to execute it well, timely and in accordance with agreed upon commitments with donors and beneficiaries. Monitoring is critical to project execution. It is a management tool for tracking progress of on-going projects and is an integral part of project execution. Accordingly, project man- agers must develop a monitoring plan to enable them to perform this function with dili- gence, overseeing integral project implementation, including technical and financial aspects. Project management is an area within the Organization that needs strengthening. The purpose of this manual, prepared by the Office of External Relations (DEC), is to cre- ate some standard procedures, as was done with project design, for managing the imple- mentation of technical cooperation projects. It provides guidance on how to monitor proj- ects in a way that will make project management more effective, and facilitate follow up. Once in place, monitoring will save time and effort for the project manager and will facili- tate project reporting on achievements and obstacles to our counterparts. Good reporting provides the basis for continued support from the international community. Irene Klinger Chief, Office of External Relations Monitoring of Project Implem.3 11/3/00 10:40 AM Page ii
  • 4. TABLE OF CONTENTS 1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1 1.1. What is monitoring and why is it useful? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1 1.2. Purpose of the manual . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1 1.3. How the monitoring manual relates to other PAHO documents . . . . . . . . . . . . . . . . . . . . . . . . . . .2 2. The project cycle and the use of evaluation tools . . . . . . . . . . . . . . . . . . . . . . . . . .2 2.1. The planning process in PAHO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 2.2. The project cycle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 2.3. Spanish – English terminology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 2.4. Purpose of appraisal, monitoring and evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5 3. Project management during the implementation phase . . . . . . . . . . . . . . . . . . .5 3.1. The project document . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5 3.2. Preparing annual work plans and budgets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5 3.3. Responsibilities of the project manager . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6 3.4. The logical framework approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6 3.5. How far does the project manager’s responsibility extend? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 4. The monitoring procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 4.1. Reviewing the agreement with the donor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 4.2. Making an operational plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8 4.3. Making annual work plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9 4.4. Breaking down the project budget . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9 4.5. Preparing a monitoring plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .10 4.5.1. Performance indicators and their definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11 4.5.2. Baseline data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11 4.5.3. Performance targets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12 4.5.4. Means of verification and data source . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13 4.5.5. Method of data collection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13 4.5.6. Frequency and schedule of data collection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14 4.5.7. Responsibilities for acquiring data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14 4.5.8. Data analysis plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14 4.5.9. Identifying needs for complementary evaluations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14 4.5.10. Plans for communicating and using monitoring information . . . . . . . . . . . . . . . . . . . . . . .14 5. Analyzing results of monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15 6. Suggesting correcting measures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15 7. Editing progress reports/annual reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15 8. Concluding remarks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .16 8.1. A participatory approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .16 8.2. Results Oriented Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .17 ANNEX I CONDENSED GUIDE FOR PAHO MONITORING PROCEDURE . . . . . . . . . . . . . . . . . . . . . . . . . . . .19 ANNEX II FORMAT FOR ANNUAL PROGRESS REPORT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22 LIST OF ABBREVIATIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .24 Monitoring of Project Implem.3 11/3/00 10:40 AM Page iii
  • 5. 1 1. Introduction 1.1. What is monitoring and why is it useful? Monitoring is a management tool for tracking progress of ongoing projects. The basic idea is to compare actual performance with plans and to measure actual results against expected results. The monitoring function is an integral part of project execution. It is simply a way of making efficient project follow-up and to provide systematic, consis- tent and reliable information on project progress. Once in place, monitoring will save time and effort for the project manager and facilitate project follow-up and reporting. It does not make a project more complex – instead, it makes it more systematically manageable. Monitoring serves the project manager in several ways: • It provides information to be presented to national counterparts, PAHO and external financing partners at periodic meetings and in progress reports. • It provides a basis for decisions on necessary modifications of the project: Resource utilization may be adjusted, priorities shifted and new activities introduced. Flexibility and agility in project management is enhanced. • It helps the manager: - to show results, - to understand and explain to others what is happening in the project and why expected results are or are not achieved, - to provide arguments for needed changes, and - to build confidence with top management in PAHO, national counter- parts and financing partner agencies. • It improves the chances of serving the target population well, because the effect on the target population is analyzed reiteratively. 1.2. Purpose of the manual Project management is an area within the organization that needs strength- ening.The purpose of this manual is to create some standard procedure for man- aging the implementation of technical cooperation projects and to provide guid- ance on how to perform monitoring in a way that will make project manage- ment more effective, facilitate follow-up and make reporting more consistent. The manual is organized in such a way that it should be easy to use for ref- erence.After the introductory chapters which define monitoring and its place in the project cycle, as well as its use as a management tool during project implementation, the monitoring procedure is explained step by step (Chapter 4).Annex I contains a Condensed guide to the PAHO monitoring procedure and annex II a format for annual progress reports. Monitoring of Project Implem.3 11/3/00 10:40 AM Page 1
  • 6. 2 1.3. How the monitoring manual relates to other PAHO documents This manual builds on and is closely linked to a number of other PAHO doc- uments and systems in use. AMPES, the system through which PAHO establishes managerial procedures for planning, programming, monitoring and evaluation provides the framework for this new manual.The basic document explaining the application of AMPES: Technical Cooperation Planning, Programming and Evaluation System AMPES (1998) should be familiar to all readers. Already in use in PAHO is also the manual Standardized Format for PAHO Project Documents and Profiles (1994), relating to the Design Phase of the proj- ect cycle.The new manual should be seen as a complement elaborated to sup- port the Implementation Phase in the life of a project. The two manuals, as well as AMPES, are based on the Logical Framework Approach (LFA) to Project Management. A review of the document The Logical Approach to Project Management in PAHO is recommended (PAHO/AD-DAP/96.01). 2. The project cycle and the use of evaluation tools 2.1. The planning process in PAHO The planning process in PAHO called AMPES includes five levels of objectives linked by hierarchy and encompasses the following three stages of planning: 1 Policy Planning, 2 Strategic Planning, and 3 Operational Planning. This manual is related only to the Operational Planning.The figure below illustrates the hierarchy and the planning levels. AMPES Policy Planning General Program of Work (GPW) Strategic and Programmatic Orientations (SPO) Strategic Planning Biennial Program Budget (BPB) Operational Programming Semiannual Program of Work (SPW) Monitoring of Project Implem.3 11/3/00 10:40 AM Page 2
  • 7. 3 2.2. The project cycle Project management in PAHO encompasses responsibility for the three phases of the project cycle: The project manager will need different analytical tools to assess and evalu- ate the project in each phase of the cycle: • Appraisal for the Design phase. • Monitoring for the Implementation phase. • Ex-post evaluation for the Evaluation phase. The concepts of appraisal, monitoring and ex-post evaluation must be clear- ly separated.Their respective places in the project cycle are illustrated in the figure above. 2.3. Spanish – English terminology In Spanish, the term “evaluación” is often used for all three activities: appraisal, monitoring and ex-post evaluation. In order to establish a clear and unambiguous terminology, the following terms should be used in English and Spanish, respectively: LOGICAL APPROACH EVALUATION Ex-post evaluation DESIGN Appraisal IMPLEMENTATION Monitoring Monitoring of Project Implem.3 11/3/00 10:40 AM Page 3
  • 8. 4 2.4. Purpose of appraisal, monitoring and evaluation The purpose of an appraisal is to assess the viability of a proposed project before a decision is taken.The project design is scrutinized and alternative approaches and designs are compared.As a result, it will be recommended that the project be implemented as proposed, be modified or not be executed at all. Appraisal is sometimes called ex-ante evaluation. The purpose of monitoring is to steer a project towards its purpose and to detect any problems that makes it probable that the project will not achieve expected results.This is done through periodic follow up of technical progress and financial expenditure, whereby actual performance and results are com- pared to plans. The purpose of ex-post evaluation is to improve the design, strategy and processes of development cooperation by learning lessons of experience. Evaluation addresses the higher levels of the project hierarchy,i.e. the project purpose and the project goal. Monitoring and evaluation share some of the same objectives: • To improve the management of projects and ensure the optimum use of funds. • To foster accountability and transparency in the management process. • To ensure that the technical cooperation is pertinent, effective and efficient. • To provide well substantiated information on project progress and results to be reported to higher levels in the organization, stakeholders and finan- cial partners. • To learn lessons of experience with the aim of improving the design, formu- lation and management of projects (organizational learning). Monitoring and evaluation are however different with respect to their tim- ing and the aspects that they address. Evaluation is more occasional than moni- toring and is typically undertaken “after the fact” analyzing the long-term English Spanish Design phase Appraisal Evaluación ex ante Implementation phase Monitoring Monitoreo Evaluation phase Ex-post evaluation Evaluación ex post Monitoring of Project Implem.3 11/3/00 10:40 AM Page 4
  • 9. 5 impact of an intervention. Monitoring, on the other hand, is done periodically during project implementation assessing project progress. From now on this manual will address the concept and tool of monitoring only, i.e. tracking project progress during the implementation of a project. 3. Project management during the implementation phase 3.1. The project document The project document, which is elaborated at the final stage of project preparation, is a systematic description of the project including a budget and a chronogram. It is intended to guide the implementation phase. It is also the basis for the formal agreements between PAHO and the national counterparts and between PAHO and external financing partners. 3.2. Preparing annual work plans and budgets The project document covers the entire project period. In order to translate the document into operational programming, it is necessary to break it down into annual work plans and budgets.Tasks, activities and expenditure are pro- grammed on a yearly basis (or any other chosen period).The work plan is in fact a calendar of activities to be performed in a given period and the estimated financial expenditure related to these activities, as well as an identification of the responsible party for its execution. The annual work plan and budget will then form a basis for monitoring of project progress.They should be elaborated in collaboration with designated (international, national, and local) counterparts and be presented to higher lev- els of management in PAHO and to external financing partners. 3.3. Responsibilities of the project manager Successful project implementation requires that managers assume the fol- lowing responsibilities: • Manage all the resources. • Produce outputs (the expected results) of the project. • Perform technical as well as financial monitoring. • Alert top management when - The achievement of expected results is uncertain. - Problems within the project appear to threaten achievement of the project purpose. - Changes in the project environment have a negative impact on the project. • Recommend adjustments and corrective action. Monitoring of Project Implem.3 11/3/00 10:40 AM Page 5
  • 10. 6 3.4. The logical framework approach The logical approach (LFA) to project management provides the basic ele- ments needed for designing complex projects and assisting in their execution, monitoring and evaluation. LFA is a management tool that facilitates project management. It is expected that projects designed with LFA have well-formulated objec- tives and measurable targets to make it possible to monitor progress and assess results. Indicators need to be established, means of verification determined and assumptions explicitly stated. 3.5. How far does the project manager’s responsibility extend? The LFA matrix also defines the responsibilities for a project. The lower levels of the LFA hierarchy, up to and including expected results, are under management control.The project manager will therefore be responsi- ble and held accountable for achieving the expected results.This is sometimes called the management contract. Achievement of the project purpose, on the other hand, depends partly on factors beyond the project manager’s control; hence he or she cannot assume responsibility or be held accountable for achieving the project purpose and even less for attaining the goal. Nevertheless, the project manager is committed to working towards the purpose and the goal of the project and to alert his/her superiors, if there is evidence or probability that the project purpose will not be achieved. LFA MATRIX FOR PROJECT DESIGN HIERARCHY OF INDICATORS MEANS OF ASSUMPTIONS OBJECTIVES VERIFICATION AND RISKS GOAL PURPOSE EXPECTED RESULTS ACTIVITIES Resources Monitoring of Project Implem.3 11/3/00 10:40 AM Page 6
  • 11. 7 As shown in this figure, monitoring is to be focused on the activities and expected results levels, while evaluations should address the project purpose level, and possibly also the goal level. 4. The monitoring procedure In this section the reader will be guided through a typical monitoring pro- cedure, step by step. 4.1. Reviewing the agreement with the donor For every new project funded by the international community, there will be either a project specific agreement, or an umbrella agreement that rules the relations with that specific donor and covers more than one project. The project manager should familiarize him/herself with that agreement in order to ensure compliance with all its specifications, which have been approved and signed by PAHO’s Director or his designate. Project agreements have specific clauses regarding transfers of funds, structures for project imple- mentation, project personnel, procurement issues, relations with national coun- terparts, involvement of the donor at different stages, reporting requirements, etc. These are all crucial elements to be considered by the project manager when defining plans of action and when monitoring execution. Not under management control: E V A L U A T I O N Under management control and responsibility: M O N I T OR I N G GOAL PURPOSE EXPECTED RESULTS ACTIVITIES Monitoring of Project Implem.3 11/3/00 10:40 AM Page 7
  • 12. 8 4.2. Making an operational plan Once the project document is approved, an operational plan for the entire project period must be elaborated. By this is meant that activities necessary for achieving expected results are outlined indicating the sequence and timing of and defining dates when stated results are to be achieved.A simplified and condensed operational plan may be organized as follows: OPERATIONAL PLAN FOR PROJECT CONTRIBUTING TO THE ELIM- INATION OF ILLNESSES CAUSED BY DRINKING IMPURE WATER Project purpose: Hygienic practices adopted by rural population in the NW region J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E CExpected Results 01 Clean water provided to villages in NW region 02 Health workers trained 03 Community informed about water treatment techniques Activities 01 Consultations with regional and local representatives Choose sites for wells Determine techniques Invitation to tender Contract firm 02 Develop curriculum Develop training material Train trainers Select participants Conduct training courses Evaluate results of training 03 Assess hygienic practices to create baseline Organize local workshops Hire trainers Recruit local representatives Conduct workshops Evaluate hygienic practices after training Chronogram Monitoring of Project Implem.3 11/3/00 10:40 AM Page 8
  • 13. 9 4.3. Making annual work plans Based on the operational plan annual work plans should be elaborated specifying in greater detail the timing of technical execution and related finan- cial expenditure.A calendar of activities and a budget related to planned activi- ties and expected results should be established. For the first year the plan must be detailed and specific.Towards the end of the first year a more specific work plan for the following year will be elaborated and so on. For a specific year in the work plan the following will be defined: • expected results to be achieved based on the project document • activities to be performed • tasks to be undertaken • costs,i.e.a budget specifying funds needed to carry out the annual work plan. The work plan forms the basis for the technical monitoring. 4.4. Breaking down the project budget The project budget included in the project document indicates the finan- cial resources needed for the entire project period.The costing of the project is calculated on the basis of tasks, activities and expected results.This budget now needs to be broken down by year or shorter periods to show what resources will be needed to accomplish the work plan. The annual work plan outlining the technical execution should be accom- panied by a break down of expected costs related to tasks, activities and the expected results. A simplified project budget may look like this: YEAR 1 YEAR 2 YEAR 3 TOTAL BUDGET Result 01 Activity 1 Task 1 Task 2 Activity 2 Cost per year Monitoring of Project Implem.3 11/3/00 10:40 AM Page 9
  • 14. 10 The project manager will need a budget with a considerable level of detail. Superiors and financing partners, however, will be better served with budgets where items have been aggregated up to the activities level or even to results level.This way they get a better overview. The budget constitutes the basis for the financial monitoring. 4.5. Preparing a monitoring plan Once the work plan is elaborated, a monitoring plan should be prepared. It should address the expected results level, i.e. when, whether or to what extent expected results are being achieved. At the task and the activity levels, performance will be checked against the calendar of activities and the budget. No other indicators are needed.This is a straightforward and relatively uncomplicated exercise and will not be dealt with further here. A monitoring plan is used to plan, manage and document the data collec- tion process. It ensures that comparable data will be collected on a regular and timely basis. It identifies the indicators to be tracked, specifies the source, method and schedule of data collection and assigns responsibilities.The plan will help keeping the monitoring system on track and ensure that data are reported regularly to project management. The elaboration of such plan should preferably be undertaken with partici- pation of all the stakeholders of the project, specially a representative of the beneficiary party, as well as the financing partner.A multiparty project steering or technical committee, with representatives of all stakeholders, is usually a good participatory mechanism to monitor progress. It allows for a shared view on planning and on monitoring indicators. It also offers opportunity for exchange of views among all involved on obstacles and potential solutions. The following elements should be included in the monitoring plan: Plans for data collection: • Performance indicators and their definitions • Baseline data • Performance targets • Data Source • Method of data collection • Frequency and Schedule of data collection • Responsibilities for acquiring data Plans for data analysis, reporting and use of information: Monitoring of Project Implem.3 11/3/00 10:40 AM Page 10
  • 15. 11 • Data analysis plans • Identifying needs for complementary evaluation • Plans for communication and using monitoring information Each one of these elements is explained below and some advice offered. 4.5.1. Performance indicators and their definitions For monitoring purposes, indicators need only to be defined for the expected results level. In the work plan some preliminary indicators may have been identified. In that case, they should be revised and, if necessary, complemented. Example: Good indicators start with a clear statement of objectives or expected results. Each indicator needs a detailed definition specifying quantity, quality and time.When selecting indicators the most important characteristics are the following: • Validity – that the indicator actually measures what is purported to measure, • Reliability – that repeated measurements will give the same results, • Sensibility – that the indicator will be responsive to changes, and • Specificity – that the indicator measures only those changes related to the project intervention in question. 4.5.2. Baseline data It is hardly possible to establish targets or measure progress without knowing what the situation is like at the commencement of a project.That is why baseline data have to be established before the project starts.They should reflect, as near as possible, the value of each indicator at the outset of a project and they will be the value against which changes will be meas- ured throughout the project period. 1.Patients´ waiting period reduced by 30% Waiting time measurement 2.Medical staff receives 10% more patients per day Number of patients 3.User satisfaction level remains the same Patients opinions PROJECT PURPOSE EXPECTED RESULT INDICATORS Management of health services improved Monitoring of Project Implem.3 11/3/00 10:40 AM Page 11
  • 16. 12 Example: In a project aimed at increased wheat production of small farmers establishing the baseline is easy, at least in theory:The level of production of wheat at the outset of a project specifying the quality of wheat. In cases where expected results are of a more qualitative nature, e.g.“increased awareness of hygienic practices related to use of water”, it takes a bit more imagination to establish the baseline. 4.5.3. Performance targets Targets represent the exact level and timing of expected results to be achieved by a project.Whereas the indicator defines how performance will be measured along a scale or dimension, the target identifies the specific planned level of result to be achieved within an explicit time frame. Example: If the expected result is “patients' waiting period reduced by 30% in a two year period”, interim targets may be set as follows: “10% reduction of average waiting time by July Year 1; further 10% reduction by January Year 2 and finally an additional 10% reduction by July Year 2.” A final target is the planned value of an indicator by the end of the proj- ect or the planning period. If this time frame is very long, it is advisable to set interim targets or, as they are often called, milestones. Example: Expected result:“Access to clean drinking water to 80% of the rural population in the province of Santa Clara”. When the project starts only 50% of the population has access to clean water (baseline value).The project is planned for a seven-year period.The final target is 80% to be achieved by the end of 7 years. In this case it may be wise to establish intermediate targets, e.g. 60% after two years, 70% after four years and 80% after seven years. It is a good idea to use a cumulative curve to illustrate the intermediate targets and the final target.This will be a good basis for comparison with actual achievements. Monitoring of Project Implem.3 11/3/00 10:40 AM Page 12
  • 17. 13 4.5.4. Means of verification and data source The means of verification make it possible to verify the status of the indicators.They should be defined in the LFA-matrix of the project docu- ment. If this has not been done or if new indicators have been selected, project management has to establish means of verification. The data source is where the data to verify the status of the indicator are to be found. It can be an institution that conducts the data collection or a system for data collection set up by the project. It is important that the same source can be used routinely, as switching data sources for the same indicator over time can lead to inconsistencies and misinterpretations. For example switching from estimates of infant mortality rates based on nation- al sample surveys to estimates based on hospital registration statistics can lead to false impressions of change. Two examples: 4.5.5. Method of data collection The method or approach to data collection for each indicator should be specified. It should be noted whether it is primary data collection or is based on secondary data. For primary data collection, consider • The unit of analysis • Data segregation needs (by gender, age, ethnic group, location) • Sampling techniques • Techniques or instruments for acquiring data. EXPECTED RESULTS Reduced mortality of pre-school children by 20% in three years Management of health services more respon- sive to client demands INDICATORS U5MR Patients’ waiting time reduced. More patients received. Client satisfaction increased. MEANS OF VERIFICATION Mortality statistics Waiting time monitoring sheet Satisfaction levels DATA SOURCE Bureau of National Statistics Statistics of 10 select- ed health centers on number of patients and waiting time. Exit questionnaires to clients Monitoring of Project Implem.3 11/3/00 10:40 AM Page 13
  • 18. 14 For indicators based on secondary data,give the method of calculating the specific indicator data point and the sources of data.Provide sufficient detail on the data collection or calculation method to enable it to be replicated. 4.5.6. Frequency and schedule of data collection Monitoring systems must gather comparable data periodically to meas- ure progress. How often should data be collected? There is no general answer. Depending on the indicator, it may make sense to collect data on a quarterly, annual or less frequent basis. For example, because changes are slow, fertility data may be collected every few years whereas data on contra- ceptive distribution and sales may be gathered quarterly. When planning the frequency and the scheduling for data collection, important factors to consider are the management’ s needs for timely deci- sion making and the decision points in the project cycle. 4.5.7. Responsibilities for acquiring data In terms of each indicator, the responsibility for the timely acquisition of data from their source should be clearly assigned to a particular individ- ual, team or office.The mode of registration of data should be determined. 4.5.8. Data analysis plan To the extent possible, it is advisable to plan in advance not only for the collection of data, but also for data analysis, reporting, review and use, to identify data analysis techniques and data presentation formats to be used. 4.5.9. Identifying needs for complementary evaluations Evaluations of ongoing projects should be undertaken only when moni- toring results show that there are serious problems or obstacles that make it less probable that the project purpose be achieved. For example, if rea- sons for not meeting targets are not clearly understood, planning evalua- tions to investigate and analyze the project makes sense. 4.5.10. Plans for communicating and using monitoring information Planning how monitoring information will be used is critical for effec- tive management.There are basically three ways of using the information: 1. Influencing management decisions 2. Writing progress/semiannual or annual reports directed to superiors, national counterparts and financing partners. 3. Sharing the information with stakeholders for discussion and analysis. Monitoring of Project Implem.3 11/3/00 10:40 AM Page 14
  • 19. 15 5. Analyzing results of monitoring Analysis of monitoring results is basically a matter of comparing actual per- formance with plans, and actual expenditure with budget and analyzing devia- tions and discrepancies.This can be expressed in words, as well as in tables and diagrams. Figures usually are easier and faster to interpret illustrating clearly the comparison between plans and outcome. Example: In this case the technical execution, i.e. the number of health workers trained, is only 90% of the expected, while the cost amounts to 16% more than budgeted.There may be good reasons for this cost overrun that need to be explained. Or there may be problems that motivate a change in the organiza- tion of the training. Discrepancies and shortfalls may be due to problems or conditions within the project, such as the project organization, administrative systems, change of project directors or shortage of staff. But there is also the possibility that disappointing results, delays or cost overruns are due to situations or changes in the project environment, such as political disturbances, natural disasters, new legislation or increasing inflation. The latter factors are related to the assumptions and assessment of risks that should be considered at the project design stage. 6. Suggesting correcting measures Depending on the results of the analysis the project manager may want to propose corrective measures, improve the project design or adjust resource allocation.The operational frame or the assigning of responsibilities may need adjustment. Monitoring results will help justify such measures. 7. Editing progress reports/annual reports Monitoring results should be incorporated into periodic reports and taken into account when new work plans are drawn up.The reports should always relate to the project document and to the LFA matrix presented in that document. TRAINING OF HEALTH WORKERS No. planned Actual no. % Budgeted cost. Actual cost. % trained US$ US$ 180 162 90% 8,600 10,100 116% Monitoring of Project Implem.3 11/3/00 10:40 AM Page 15
  • 20. 16 There are two main issues that should be addressed in the reports: • Technical execution – as related to the annual plan. Focus should be on the Expected Results level more than on the Activity and Task levels. • Financial execution – as related to budget and specifically to expected cost for producing Expected Results and to carrying out Activities. The reporting on the two issues must be synchronized comparing the degree of technical execution with the utilization of funds. It is the responsibili- ty of the project manager to ensure that this match exists. The monitoring of the technical execution provides the Project Manager with elements for the technical reporting, while the financial system in PAHO (Budget and Finance Division) supplies him or her with the financial information. The reporting requirements of external financing partners are defined in the respective agreements between PAHO and the contracting partner. Requirements vary to some extent in terms of frequency, content and level of detail. It is important that reports are well structured, concise and to the point. The aim should be to give an overview of project progress, of the extent to which expected results have been achieved, of problems encountered in proj- ect execution and in the project environment, and of perspectives for the next reporting period. It is wise to avoid getting involved in great detail. The structure of the reports should remain the same throughout the life of the project and the level and categories of reporting should be maintained in order to facilitate comparison. 8. Concluding remarks 8.1. A participatory approach Experience shows that people centered approaches to design, monitoring and evaluation enhance ownership and promote the sustainability of interven- tions. Participatory approaches will lead to greater involvement, better and more lasting results, and shared commitment and responsibilities. As convenient and pertinent, counterparts, staff and the representatives for the target group should therefore be involved in planning and conducting mon- itoring activities, interpreting data, analyzing results and discussing the reasons for results being achieved or not achieved. Besides the instant advantages of such an approach, it also has the benefit of building national capacity in the area of monitoring. Monitoring of Project Implem.3 11/3/00 10:40 AM Page 16
  • 21. 17 8.2. Results Oriented Management Monitoring for project progress is an integral part of project management. It is a useful tool that does not make project management more difficult or more complicated. On the contrary, it pays in the long run to establish an effective system of monitoring. It is a way of managing projects better and smarter. Monitoring will save time and effort for the project manager and make proj- ect follow-up and reporting more effective. Monitoring is a way of knowing and understanding what is going on in the project and of being in control.The results serve as the basis for decisions with regard to the need for reprogramming and/or reassigning human and financial resources. It will provide relevant and timely information to top management on the progress and any difficulties encountered in the project. Monitoring is to be focused on the Expected Results level of the LFA hier- archy, a level that is under management control.The project document, and more particularly the annual work plans, constitutes the basis for monitoring project progress. Monitoring means comparing actual performance with plans. It includes two distinct but interrelated types of follow-up: technical execution of the proj- ect and financial expenditure related to the project.The two aspects of moni- toring and reporting should be performed in a synchronized manner. Monitoring results are valuable inputs in future evaluations of the project. Effective monitoring will enhance the quality of project management.This is a logical step in the institutional development of the organization and will make PAHO more accountable and attractive as a partner of external financing agencies. Monitoring of Project Implem.3 11/3/00 10:40 AM Page 17
  • 22. ANNEXES Monitoring of Project Implem.3 11/3/00 10:40 AM Page 18
  • 23. 19 Annex I CONDENSED GUIDE FOR PAHO MONITORING PROCEDURE 1. PREPARING THE MONITORING PLAN 1.1. Review project agreement Internalize all aspects related to project execution and reporting that appear in the project agreement signed with the donor.What are the commit- ments? Which procurement procedures? How often will transfers of funds be made? Which implementation structure needs to be in place? How often are reports due? How will donor be involved or not during the life of the project? 1.2. Review LFA matrix for project. What are the “expected results” to be achieved? 1.3. Review work plan for current year. What activities are to take place during the year? What is the expected expenditure (budget) for the year? What should be achieved by the end of the year? 1.4. Review/develop indicators for tracking progress at the “expected results” level Which are the indicators whereby progress can be tracked? Which targets have been set (expected results level): • To be achieved by the end of the project? • To be achieved by the end of the year (intermediate targets or milestones)? Expected End of project TargetYear 1 ResultYear 1 % of year results target target 01 02 03 Monitoring of Project Implem.3 11/3/00 10:40 AM Page 19
  • 24. 20 1.5. What are the means of verification of the selected indicators? 1.6. What data sources should be used? 1.7. Who is responsible for the data collection? 2. DATA COLLECTION IN ACCORDANCE WITH MONITORING PLAN 3. ANALYSIS OF MONITORING RESULTS 3.1. Rate of technical execution? 3.2. Rate of financial execution? 3.3. Consolidating and comparing technical and financial execution 3.4. Technical execution: Deviations and discrepancies from planned results? • At the level of “expected results” • At the level of activities 3.5. Technical execution:Analysis of deviations and shortfalls • Problems within the project (project design, organization, counterparts, staffing etc)? TRAINING OF HEALTH WORKERS No. planned Actual no. % Budgeted cost. Actual cost. % trained US$ US$ 180 162 90% 8,600 10,100 116% Monitoring of Project Implem.3 11/3/00 10:40 AM Page 20
  • 25. 21 • Problems in the project environment – outside the control of project man- agement? • Any unexpected results – positive or negative? 3.6. Financial execution: Deviations from budget • At the level of expected results • At the level of activities 3.7. Financial execution:Analysis of over-spending or under-spending 4. PROPOSED ACTION • Immediate action? • Adjustments in work plan of the following year • Adjustments in budget for the following year 5. CONCLUSIONS AND LESSONS LEARNED Budget Actual Expenditure as Year 1 expenditure % of budget Expected result 01: 100 90 90 Activity 1 25 25 100 Activity 2 40 36 90 Activity 3 35 29 83 Monitoring of Project Implem.3 11/3/00 10:40 AM Page 21
  • 26. 22 ANNEX II FORMAT FOR ANNUAL PROGRESS REPORT The report should preferably be limited to 10 pages, and should in no case exceed 15 pages. If more information is deemed pertinent and necessary it should be presented in annexes to the report. 1. EXECUTIVE SUMMARY Principal project achievements, problems, summary, financial execution and future proposals (one page). 2. INTRODUCTION-CONTEXT Brief history of the project. Political, social and economic context in which the project is carried out. This section should not exceed one page unless there were changes affecting the development of the project (such as elections, natural disasters, and war). 3. PERTINENT NATIONAL POLICIES AND THEIR IMPACT ON THE PROJECT RELATIONS TO NATIONAL AND LOCAL COUNTERPARTS Maximum one page. 4. PROJECT PROGRESS This section must be based on the LFA matrix. Explanatory notes should not exceed three pages. 4.1 Describe to what extent the expected results have been achieved using the data emerging from the project monitoring. Refer to good indicators. Explain and comment delays, deviations and differences of actual perform- ance as compared to plans. Indicate and discuss problems, deficiencies, errors etc and propose corrective action. 4.2 Indicate to what extent expected results are actually contributing to the project purpose. Comment on whether or to what extent the project envi- ronment – what is outside the control of the project – has affected the proj- ect positively or negatively.Are there any unexpected results, positive or negative? Monitoring of Project Implem.3 11/3/00 10:40 AM Page 22
  • 27. 23 4.3 Assess progress from the point of view of project management, e.g. com- ment on project organization, operational framework, administrative sys- tems, adequacy of staffing – both in PAHO and the counterpart institution. 5. FINANCIAL EXECUTION ANALYSIS This section should not exceed two pages. 5.1 Analyze expenditure as percentage of budget by activity corresponding to the work plan. If requested by donor, also include PAHO’s budget compo- nents. In case of multi-country projects, include tables for each country, as well as a consolidated table. 5.2 Utilizing the ABF/ABU official report prepared by the Budget and Report Section of PAHO, show the rate of technical and financial execution by con- solidating technical and financial data. Explain and comment on any devia- tion. Suggest corrective measures, as necessary.This is not an auditing exer- cise, but rather a review of project progress in relation to the utilization of funds.The purpose is to determine whether it is necessary to reassign allot- ments or adjust calendar of activities. 5.3 Introduce a financial chart showing a) PAHO’s contribution,including resources from external financing partners b) National counterpart contribution 5.4 All the data mentioned should be presented for the year for which the report is made, and accumulated during life of the project and also be relat- ed to the original project document and budget. 6. FUTURE PROGRAMMING Propose the work plan for the following year. In the case of multi-country projects, include one for each country. Comments are necessary only if new activities are introduced or if changes are proposed in terms of activities or the budget contained in the original proj- ect document. 7. ADDITIONAL COMMENTS Further comments should be included only if there are relevant or impor- tant issues that have not already been covered in the report. Monitoring of Project Implem.3 11/3/00 10:40 AM Page 23
  • 28. 24 LIST OF ABBREVIATIONS ABF/ABU Office of Budget and Reports AMPES Technical Cooperation Planning, Programming and Evaluation System BPB Biennial Program Budget DEC Office of External Relations GPW General Program of Work LFA Logical Framework Approach PAHO Pan American Health Organization PRG Project Review Group PRP Project Review Process SPO Strategic and Programmatic Orientations SPW Semiannual Program of Work U5MR Under 5 Mortality Rate Monitoring of Project Implem.3 11/3/00 10:40 AM Page 24
  • 29. Office of External Relations Pan American Health Organization Pan American Sanitary Bureau, Regional Office of the World Health Organization 525 Twenty-third Street, N.W. 20037, U.S.A. February 1999 P a n A m e r i c a n H e a l t h O r g a n i z a t i o n o 10 20 30 40 50 60 70 80 90 100 PROJECT IMPLEMENTATION a manual MONITORING of Monitoring Cover Final.qxd 11/3/00 10:42 AM Page 1