The document is a proposal from PTS Data Center Solutions, Inc. to the Ministry of Information & Communication of Bangladesh for designing a new 5,000 sq ft data center. The proposal includes:
1) An overview of the project background and objectives
2) A description of PTS' proposed approach and scope of services which includes conceptual design, modeling, cost estimating and reporting
3) Clarification that additional services like detailed design or construction management are not included in the proposed fees
When it comes to designing, building, and operating mission-critical data centers, simple is better. Data centers are faster and cheaper to build, and more reliable with lower total cost of ownership (TCO), when they start with a dramatically simplified design and build process that incorporates these elements: reference designs, pre-fabricated/modular architecture, partners that bring comprehensive capabilities into play, and coordinated planning around software, operations, and service. What you will learn: The top 5 weaknesses of today’s design/bid/build approach A simplified approach using reference designs and pre-fab products can preserve Day 1 capital and improve speed to market An integrated solution provider (Design, Build, Hardware and Operations) can optimize CapEx, OpEx and TCO.
Data Center Energy Efficiency Best Practices – Insights Into The ROI On Best Practices
Electricity expense has become an increasingly important factor of the total cost of ownership (TCO) for data centers. Energy consumption of typical data centers can be substantially reduced through design of the physical infrastructure and IT architecture.
To view the recorded webinar presentation, please visit http://www.42u.com/energy-efficiency-webinar.htm
When it comes to designing, building, and operating mission-critical data centers, simple is better. Data centers are faster and cheaper to build, and more reliable with lower total cost of ownership (TCO), when they start with a dramatically simplified design and build process that incorporates these elements: reference designs, pre-fabricated/modular architecture, partners that bring comprehensive capabilities into play, and coordinated planning around software, operations, and service. What you will learn: The top 5 weaknesses of today’s design/bid/build approach A simplified approach using reference designs and pre-fab products can preserve Day 1 capital and improve speed to market An integrated solution provider (Design, Build, Hardware and Operations) can optimize CapEx, OpEx and TCO.
Data Center Energy Efficiency Best Practices – Insights Into The ROI On Best Practices
Electricity expense has become an increasingly important factor of the total cost of ownership (TCO) for data centers. Energy consumption of typical data centers can be substantially reduced through design of the physical infrastructure and IT architecture.
To view the recorded webinar presentation, please visit http://www.42u.com/energy-efficiency-webinar.htm
Enclosure Strategies for Efficiency – Data Center Efficiency Best-Practice Starts with Your Racks
Historically, Data Center managers didn't invest much thought in their deployment of server racks beyond basic functionality, air flow, and the initial cost of the rack itself. Today, the widespread deployment of high-density configurations is causing major hot spot concerns and capacity issues. These factors, along with the high cost of power, require a sound understanding of how your server rack deployment plan relates to your overall efficiency strategy.
To view the recorded webinar presentation, please visit http://www.42u.com/enclosure-strategies-webinar.htm
MetaFabric™ Architecture Virtualized Data Center: Design and Implementation G...Juniper Networks
The benefits of virtualization are driving data center operators to rethink their legacy data center networks and look for new ways to reduce costs and improve efficiency in the data center. Moving from a legacy network to a state-of-the-art solution allows you to deploy new applications in seconds rather than days, weeks, or months. If you want to harness the power of virtualization in your data center network, this guide will help you to achieve your goal.
Thirteen (13) years of experience in piping engineering work for oil and gas, chemical, petrochemical and power plant industries. The experience covers both onshore and offshore works for feasibility study, conceptual design, basic engineering, and detail design and administration of 3D CAD tools (PDMS, E3D, SP3D, PDS).
I have been involved and worked in overseas such as: Japan, Brazil and Malaysia.
Positions of Responsibility are Piping Engineer / PDMS Administrator in TechnipFMC. Experience in various position including: Piping Engineer, Piping Designer, PDMS administrator, E3D Administrator, SP3D Administrator.
Knowledge in international codes and standards like ASME, API, ASTM, Shell DEP.
Enclosure Strategies for Efficiency – Data Center Efficiency Best-Practice Starts with Your Racks
Historically, Data Center managers didn't invest much thought in their deployment of server racks beyond basic functionality, air flow, and the initial cost of the rack itself. Today, the widespread deployment of high-density configurations is causing major hot spot concerns and capacity issues. These factors, along with the high cost of power, require a sound understanding of how your server rack deployment plan relates to your overall efficiency strategy.
To view the recorded webinar presentation, please visit http://www.42u.com/enclosure-strategies-webinar.htm
MetaFabric™ Architecture Virtualized Data Center: Design and Implementation G...Juniper Networks
The benefits of virtualization are driving data center operators to rethink their legacy data center networks and look for new ways to reduce costs and improve efficiency in the data center. Moving from a legacy network to a state-of-the-art solution allows you to deploy new applications in seconds rather than days, weeks, or months. If you want to harness the power of virtualization in your data center network, this guide will help you to achieve your goal.
Thirteen (13) years of experience in piping engineering work for oil and gas, chemical, petrochemical and power plant industries. The experience covers both onshore and offshore works for feasibility study, conceptual design, basic engineering, and detail design and administration of 3D CAD tools (PDMS, E3D, SP3D, PDS).
I have been involved and worked in overseas such as: Japan, Brazil and Malaysia.
Positions of Responsibility are Piping Engineer / PDMS Administrator in TechnipFMC. Experience in various position including: Piping Engineer, Piping Designer, PDMS administrator, E3D Administrator, SP3D Administrator.
Knowledge in international codes and standards like ASME, API, ASTM, Shell DEP.
Presentation on DataGuard: Data Transmission & Error Detection SystemMOHAMMADSAJJADHOSSAI5
Ensure the integrity of your data transmission with DataGuard – the robust error detection system designed to safeguard against data corruption and ensure seamless communication. In this presentation, we delve into four key components of DataGuard that contribute to its effectiveness:
1️⃣ Parity Check: Learn how DataGuard employs the simple yet powerful technique of parity checking to detect errors in transmitted data. Understand how parity bits are strategically used to verify the accuracy of information, enhancing the reliability of your data transfer processes.
2️⃣ Hamming Distance: Explore the advanced error detection capabilities of DataGuard through Hamming distance calculations. Discover how this mathematical concept plays a crucial role in identifying and correcting errors in transmitted data, ensuring the accuracy and integrity of your information.
3️⃣ Bit Stuffing and De-stuffing: Uncover the intricacies of bit stuffing and de-stuffing techniques implemented by DataGuard. Dive into the world of efficient data encapsulation, where redundant bits are strategically inserted and removed to prevent data misinterpretation and enhance the overall reliability of your communication channels.
4️⃣ Character Stuffing and De-stuffing: Explore how DataGuard takes error detection to the next level with character stuffing and de-stuffing mechanisms. Delve into the details of how characters are strategically added and removed, bolstering the system's ability to identify and rectify errors in the transmitted data stream.
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...Mansi Shah
This study examines cattle rearing in urban and rural settings, focusing on milk production and consumption. By exploring a case in Ahmedabad, it highlights the challenges and processes in dairy farming across different environments, emphasising the need for sustainable practices and the essential role of milk in daily consumption.
Connect Conference 2022: Passive House - Economic and Environmental Solution...TE Studio
Passive House: The Economic and Environmental Solution for Sustainable Real Estate. Lecture by Tim Eian of TE Studio Passive House Design in November 2022 in Minneapolis.
- The Built Environment
- Let's imagine the perfect building
- The Passive House standard
- Why Passive House targets
- Clean Energy Plans?!
- How does Passive House compare and fit in?
- The business case for Passive House real estate
- Tools to quantify the value of Passive House
- What can I do?
- Resources
Storytelling For The Web: Integrate Storytelling in your Design ProcessChiara Aliotta
In this slides I explain how I have used storytelling techniques to elevate websites and brands and create memorable user experiences. You can discover practical tips as I showcase the elements of good storytelling and its applied to some examples of diverse brands/projects..
Book Formatting: Quality Control Checks for DesignersConfidence Ago
This presentation was made to help designers who work in publishing houses or format books for printing ensure quality.
Quality control is vital to every industry. This is why every department in a company need create a method they use in ensuring quality. This, perhaps, will not only improve the quality of products and bring errors to the barest minimum, but take it to a near perfect finish.
It is beyond a moot point that a good book will somewhat be judged by its cover, but the content of the book remains king. No matter how beautiful the cover, if the quality of writing or presentation is off, that will be a reason for readers not to come back to the book or recommend it.
So, this presentation points designers to some important things that may be missed by an editor that they could eventually discover and call the attention of the editor.
Can AI do good? at 'offtheCanvas' India HCI preludeAlan Dix
Invited talk at 'offtheCanvas' IndiaHCI prelude, 29th June 2024.
https://www.alandix.com/academic/talks/offtheCanvas-IndiaHCI2024/
The world is being changed fundamentally by AI and we are constantly faced with newspaper headlines about its harmful effects. However, there is also the potential to both ameliorate theses harms and use the new abilities of AI to transform society for the good. Can you make the difference?
Mo ict 2013 new data center design proposal - pts-0813-004006 - ptsp-c-13-009431-01
1. A Cons
2013 Ne
Submitte
Ministr
BANSDO
Agargao
Attn: Mr
Submitte
Submitte
Project n
Proposa
sulting S
ew Data Ce
ed to:
ry of Info
OC Bhaban
on, Sher-E-
r. Nazrul Is
ed by:
ed on:
number:
al number:
ervices P
enter Desig
ormation &
n, E-141/Y
Bangla Nag
slam Khan
Augus
PTS-0
PTSP
Proposal
n
& Commu
gar, Dhaka
, Secretary
st 27, 2013
0813-00400
-C-13-0094
PTS
Expe
568
Fran
(201
www
unication
a-1207
y
06
431-00
S Data C
erts for Yo
Commerce
nklin Lakes,
) 337-3833
w.PTSdcs.c
n Techno
Center S
our Always
e Street
, NJ 07417
3
com
ology
Solution
s Available
7
s, Inc.
e Data Centter
2. 2013 Ne
Ministry
Project n
Proposa
Table
A. P
B. P
C. S
D. C
E. P
F. A
ew Data Ce
of Informat
number: PT
al number: P
e of Con
PROJECT U
PROJECT A
SCOPE OF
CLARIFICA
PROFESSIO
AGREEMEN
enter Desig
tion & Com
TS-0813-00
PTSP-C-13
ntents
UNDERSTA
APPROAC
SERVICES
ATIONS .....
ONAL FEE
NT.............
n
mmunication
04006
3-009431-0
ANDING ...
H ..............
S...............
.................
S AND EX
.................
n Technolog
0
.................
.................
.................
.................
PENSES..
.................
gy
.................
.................
.................
.................
.................
.................
.................
.................
.................
.................
.................
.................
Pa
.................
.................
.................
.................
.................
.................
age 2
..... 3
..... 4
..... 4
..... 6
..... 7
..... 8
3. 2013 Ne
Ministry
Project n
Proposa
A. PRO
a. P
(a
(b
(c
b. P
(a
(b
(c
(d
c. T
Act
Pro
Sta
Pro
Con
Pre
App
Com
Pro
Com
Clo
Pro
ew Data Ce
of Informat
number: PT
al number: P
OJECT UND
Project Back
a) The gove
Center in
b) PTS prop
Center.
c) The Data
Project Team
a) PTS: Mic
b) PTS: Ma
c) PTS: Sur
d) PTS: Tan
Tentative Pr
tivity
oject Award
aging Phase
oject Preparat
nceptual Des
eliminary Con
prove Prelimin
mplete Conce
oject Budget
mplete Projec
oseout Phase
oject Review M
enter Desig
tion & Com
TS-0813-00
PTSP-C-13
DERSTAND
kground
ernment of
n their capit
poses to pa
a Center sh
m
chael Petrin
atthew Blake
resh Sound
nya Niesse
roject Timel
tion & Plannin
sign Phase
ceptual Desig
nary Concept
eptual Design
t Phase
ct Budget Rep
e
Meeting via W
n
mmunication
04006
3-009431-0
DING
Banglades
tal city, Dha
artner with s
hall be Tier
no, Project
e, P.E., LE
dararaj, C.E
n, Project A
line
ng
gn
tual Designs
n Drawings
port
Web
n Technolog
0
sh seeks to
aka.
sBIT, Inc. (s
3 or Tier 4
Lead
ED AP, Eng
E.M., Projec
Accounting
gy
build a new
sBIT) to de
by design
gineering M
ct Mechanic
w, high-cap
esign a 5,00
Manager
cal and CF
2
Pa
pacity Data
00 sq foot D
D Engineer
Duration
TBD
1 Week
2 Weeks
TBD
2-3 Weeks
1 Week
1 Day
age 3
Data
r
4. 2013 Ne
Ministry
Project n
Proposa
B. PRO
a. P
C. SCO
a. K
(a
(b
(c
(d
(e
(f
(g
(h
b. P
(a
(b
(c
ew Data Ce
of Informat
number: PT
al number: P
OJECT APP
PTS will act
OPE OF SE
Key Design
a) Identify a
b) Client to
c) Client to
applicabl
d) Gather e
e) Interview
well as e
and max
by contra
f) Identify t
by under
them to p
g) Interview
deploym
h) Utilize PT
identify h
scope &
Program Re
a) Deliver a
guideline
support i
architect
control, a
specific n
Design C
b) Meet with
and requ
c) Meet with
concepts
enter Desig
tion & Com
TS-0813-00
PTSP-C-13
PROACH
as the lead
RVICES
Criteria De
all project s
complete t
complete t
le
existing con
w project sta
establish a l
ximum oper
asting past
he IT equip
rstanding th
potential tec
w project sta
ent strategy
TS’ proprie
how load, a
budget
equirements
a program r
e of all the d
nfrastructu
ure, electric
access, and
needs of th
Criteria
h designate
uirements fo
h the appro
s for the fac
n
mmunication
04006
3-009431-0
d consultan
efinition
takeholders
he Prelimin
he Comput
ditions data
akeholders
oad growth
ating load c
experience
pment deplo
he technolo
chnology re
akeholders
y with futur
tary compu
vailability, a
s Developm
requirement
design requ
re as well a
cal, mecha
d security. T
e project ba
ed personn
or the proje
opriate pers
cility and de
n Technolog
0
nt for this pr
s
nary Informa
ter Room E
a including
to understa
h model sui
condition Id
es with futu
oyment den
ogies that ar
efreshes
to compare
re load depl
uter room p
and density
ment Service
ts documen
uirements fo
as the natur
nical, fire p
The progra
ased upon
el to review
ect
sonnel to es
etermine the
gy
roject repor
ation works
Existing Con
documents
and the pre
table to est
dentify site a
re requirem
nsity strateg
re presently
e the existin
loyment co
roject cost
y decisions
e
nt that will s
or the proje
re of the co
protection, p
m requirem
the previou
w and estab
stablish the
e requireme
rting directly
sheet
nditions Su
s, drawings
esent load c
tablish both
availability
ments
gy for the c
y in use an
ng IT equip
nsideration
modeling a
impact the
serve as a w
ect, includin
onfiguration
plumbing, s
ments will be
usly establis
blish the go
e preliminar
ents for exi
Pa
y to sBIT.
rvey, if
s, etc.
condition as
h the day on
requiremen
computer ro
d comparin
pment
ns
application t
e overall pro
written
ng the size o
n of
structural,
e tailored to
shed Key
oals, objecti
ry phasing
sting and
age 4
s
ne
nts
oom
ng
to
oject
of all
o the
ves,
5. 2013 Ne
Ministry
Project n
Proposa
(d
c. C
(a
(b
(c
(d
d. P
(a
(b
(c
(d
ew Data Ce
of Informat
number: PT
al number: P
projected
interface
d) Investiga
drawings
Computer R
a) Based on
floor plan
b) Use the l
verify the
c) Prepare
use by th
1. Comp
condi
2. Comp
secur
3. Comp
infras
(1) Th
se
ce
d) Compute
sizing an
Project Cost
a) Estimate
major sit
systems
b) Estimate
elements
c) Estimate
consultin
d) Provide a
project’s
enter Desig
tion & Com
TS-0813-00
PTSP-C-13
d support in
relationshi
ate the exis
s and/or all
Room Conce
n the appro
ns showing
latest comp
e cooling sy
schematic
he A/E firms
puter Room
ition analys
puter Room
rity, and sur
puter Room
structure siz
he electrica
ervice switc
enter and n
er Room Me
nd locations
t Estimating
e the cost of
e, facility, p
for the spe
e the cost of
s as configu
e the fees in
ng, & gener
a line item d
KDC and C
n
mmunication
04006
3-009431-0
nfrastructure
ips
ting conditi
other pertin
eptual Desi
oved projec
the genera
putational fl
ystems des
design doc
s, or for rev
m CFD Mod
sis of the co
m Floor Plan
rveillance lo
m Electrical
zing and loc
al one-line c
chgear, gen
ot just the e
echanical O
s and airflow
g Service
f the suppo
power, cool
ecific Conce
f the labor t
ured in the
ncluding site
al condition
detailed Pro
Conceptual
n Technolog
0
e, operating
ons that ma
nent inform
ign with CF
t requireme
al design in
uid dynami
ign approac
cuments of
view by loca
el Results
ooling strate
n (support i
ocations an
One-Line (
cations)
conceptual
nerator, ATS
expansion a
One-Line (c
w elevation
orting infras
ing, fire pro
eptual Desig
to install or
specific Co
e, architect
ns for the sp
roject Cost E
l Design
gy
g procedure
ay impact t
mation that is
FD Analysis
ents, PTS w
tent and lay
ic (CFD) so
ch
the propos
al authoritie
(CFD mode
egy)
nfrastructu
nd details)
(power prot
design will
S, and distr
area(s)
computer ro
details)
structure inc
otection, arc
gn
construct t
onceptual D
tural, engine
pecific Con
Estimate R
es, security
the project a
s available
s
will prepare
yout of all c
oftware mod
ed project a
es, including
el load and
re, IT equip
tection and
encompas
ribution for
oom cooling
cluding iden
chitecture,
the support
Design
eering, tech
nceptual De
Report, spec
Pa
y criteria, an
and will rev
preliminary
critical spac
deling tools
available fo
g the follow
failure
pment, acce
distribution
ss the utility
the entire d
g infrastruct
ntifying all
& security
t infrastruct
hnology
esign
cific to this
age 5
nd
view
y
ces
s to
or
wing:
ess
n
y
data
ture
ure
6. 2013 Ne
Ministry
Project n
Proposa
D. CLA
a. T
fo
(a
(b
(c
(d
(e
ew Data Ce
of Informat
number: PT
al number: P
ARIFICATIO
The follow s
or an additio
a) Detailed
b) Equipme
and/or pr
c) Construc
d) Commiss
e) Maintena
enter Desig
tion & Com
TS-0813-00
PTSP-C-13
ONS
ervices are
onal fee:
design and
ent procurem
rocess man
ction and/or
sioning
ance and/or
n
mmunication
04006
3-009431-0
e not include
d engineerin
ment and/o
nagement
r constructio
r monitoring
n Technolog
0
ed as part o
ng including
or request fo
on manage
g
gy
of this prop
g written eq
or proposal
ement
posal, but ca
quipment s
l (RFP) dev
Pa
an be provi
pecification
velopment
age 6
ided
ns
7. 2013 Ne
Ministry
Project n
Proposa
E. PRO
a. C
b. R
R
b
in
e
c. P
ew Data Ce
of Informat
number: PT
al number: P
OFESSIONA
Cost of Serv
Reimbursab
Reimbursab
illed at cos
nclude (1) t
xpress and
Payment Sc
Phase
Initial Invoic
Final Invoice
* All in
enter Desig
tion & Com
TS-0813-00
PTSP-C-13
AL FEES A
vices
TOT
ble Expense
ble expense
t plus 10%
ravel and o
d overnight
chedule
e
ce 5
e 5
nvoices are d
n
mmunication
04006
3-009431-0
AND EXPEN
Key Design
Program Req
Conceptu
Projec
TAL: $60,0
es
es incurred
above-and
out-of-town
deliveries.
Am
50%
50% + Expe
due upon re
n Technolog
0
NSES
Item
n Criteria Deve
quirements Dev
al Design with
ct Cost Estimat
000.00 (Incl
d in conne
d-beyond th
living expe
mount
enses
eceipt.
gy
elopment Servic
velopment Serv
CFD Modeling
ting Service
luding Exp
ction with
he professio
enses (2) p
Contra
Delive
ce
vice
g
penses)
profession
onal fees. T
lotting and
Timi
act Signing
ry of Final D
Pa
al services
These expe
blueprintin
ing
Documents
age 7
s will
nses
g (3)
8. 2013 Ne
Ministry
Project n
Proposa
F. AGR
1. In
P
pr
2. P
P
in
le
fe
3. D
P
fu
ot
re
sp
4. D
A
pe
to
th
sh
pa
In
of
se
5. C
S
el
al
no
no
re
ou
6. L
P
N
h
vi
co
7. H
A
T
ew Data Ce
of Informat
number: PT
al number: P
REEMENT
nvoicing
TS will invoic
roject's perce
ayments
ayments due
nvoice at the r
egal fees and
ees hereunde
Delays
TS will sched
ulfilling the se
ther unforese
elated to circu
pecific service
Disputes
Any controvers
erformance o
o be conducte
he event that t
hall be submi
arties consen
n the event of
ff any paymen
ervices.
Contract Term
hould the pro
lect to termina
ll services pe
otice. PTS ha
otice to the cl
eceived when
ur compensat
imitation of L
TS engineers
Notwithstandin
idden conditio
isible for visua
ompensation
Hourly Rates
Additional serv
echnology, w
Principal
Business Con
enter Desig
tion & Com
TS-0813-00
PTSP-C-13
ce fees month
entage of com
PTS and wh
rate of eightee
any other cos
r.
dule services
rvice caused
een conditions
umstances ou
e performanc
sy, claim, or d
of this agreem
ed by a mutua
the matter ca
tted for deter
nt to the jurisd
f a dispute pu
nts due or ow
mination
oject be suspe
ate our servic
rformed and r
as the option t
lient, where p
n due. If the pr
tion shall be e
Liability
s shall utilize
ng the foregoi
ons, or any ot
al examinatio
for efforts rel
vices, if requir
will be billed u
nsultant
n
mmunication
04006
3-009431-0
hly for work pe
mpletion. Paym
ich remain un
en percent (1
sts expended
as quickly as
by labor disp
s may affect t
utside of its co
ce dates due t
dispute arising
ment, or the br
ally acceptabl
annot be resol
mination to th
diction of the S
rsuant to serv
wing to PTS, a
ended for mor
ces prior to ou
reimbursable
to suspend se
payment of an
roject is resum
equitably adju
best efforts to
ng, PTS shal
ther discrepan
on from a grou
ated to such
red and appro
utilizing the fo
n Technolog
0
erformed duri
ments are due
npaid shall be
8%) per annu
d if it becomes
possible at th
putes of third p
he schedule.
ontrol. PTS do
to the variabil
g out of or rel
reach thereof
e mediator pr
lved through
he Supreme C
Supreme Cou
vices rendere
and shall be o
re than three
ur completion
expenses ex
ervices five (5
ny invoiced am
med after bei
usted.
o ascertain th
l not be held
ncies that ma
und level obse
deviations, co
oved by the M
ollowing preva
$ 2
$ 2
gy
ing the previo
e upon receip
ear interest 30
um. PTS is en
s necessary t
he convenien
parties, custo
PTS will not
oes not contra
lity in each un
lating to the in
f shall be refe
rior to resortin
mediation an
Court of the S
urt of the Stat
ed, the client d
obligated to re
(3) months o
n of the work,
xpended up to
5) business d
mount, not rea
ng suspende
he existing con
responsible f
ay arise during
ervation. PTS
onditions, and
Ministry of In
ailing hourly r
285.00
235.00
ous month on
pt.
0 days from th
ntitled to reco
to pursue lega
nce of the cus
omer contract
be responsib
actually guara
nique project.
nterpretation,
rred to non-b
ng to judicial
y controversy
State of New J
te of Jersey.
does not have
emit all payme
or abandoned
PTS shall be
o the date of r
ays after givi
asonably in d
ed for more th
nditions of the
for any deviat
g the project,
S shall be ent
d discrepanci
formation &
ates:
Pa
a basis of the
he date of the
over any and
al actions to c
stomer. Delay
ted services, o
ble for delays
antee actual a
construction
inding mediat
intervention.
y, claim, or dis
Jersey. The
e the right to s
ents for comp
, or should yo
e compensate
receipt of writ
ng prior writte
dispute is not
an six (6) mo
e project site.
tions, concea
which were n
titled to additio
es.
Communica
age 8
e
e
all
collect
ys in
or
and
, or
tion
In
spute
set
pleted
ou
ed for
tten
en
onths,
.
led or
not
onal
ation
9. 2013 Ne
Ministry
Project n
Proposa
T
W
(a
no
no
*N
8. E
T
su
bo
ag
ou
M
C
B
S
T
D
ew Data Ce
of Informat
number: PT
al number: P
Project Leade
Project Mana
Professional
Construction
Staff Enginee
Facility Servic
Project Coord
CAD / Draftin
Project Admin
hese rates wi
Work performe
also referred t
ormal rate. W
ormal rate.
Normal busin
xtent of Agre
his agreemen
upersedes all
oth parties. T
greeable, kind
ur files. Than
Ministry of Inf
Communicati
y: _____
ign: _____
itle: _____
Date: _____
enter Desig
tion & Com
TS-0813-00
PTSP-C-13
er
ager
Engineer / Lic
Supervisor
er
ce Technician
dinator
ng
nistration
ill remain fixe
ed, at the proj
to as overtime
Work performe
ness hours a
eement
nt will constitu
l prior negotia
This proposal
dly signify you
nk you for you
formation &
on Technolo
____________
____________
____________
____________
n
mmunication
04006
3-009431-0
censed Archit
n
d through De
ject site or in
e or OT) shal
ed on a Sunda
are Monday
ute the entire
ations. This ag
is valid for a p
ur acceptance
ur considerati
ogy
__________
__________
__________
__________
n Technolog
0
$ 1
$ 1
tect $ 1
$ 1
$ 1
$ 1
$ 1
$ 1
$ 9
ecember 31, 2
PTS’s office,
l be compute
ay or Holiday
y thru Friday,
agreement of
greement ma
period of sixty
e in the space
on.
gy
180.00
180.00
180.00
145.00
145.00
130.00
130.00
100.00
90.00
2013.
at times othe
d at one and
will be comp
, 9:00am to
f the parties c
ay be modified
y (60) days. If
e provided be
PTS Data
By: Micha
Sign: M
Title: Vice
Date: Aug
er than norma
one half (1-1
puted at two (2
5:00pm
concerning th
d only in writin
f you find this
elow and retu
a Center Sol
ael Petrino
Michael Pet
e President
gust 27, 2013
Pa
al business ho
/2) times the
2) times the
he project and
ng, if agreed t
s proposal
rn a copy to u
utions, Inc.
trino
3
age 9
ours*
d
to by
us for