 Transformer – 1 x 1600kVA 11kV/433V Oil Type Transformer
 It is in working condition, only servicing is required.
 Manufacturing Year: 2004
 Make: Voltamp
 DG – 2 x 625KVA & 1 x 500kVA DG Sets
 Out of 3 DG sets 500kVA is not in working condition. Remaining 2 DG sets need to be replaced
considering the DG health & life span.
 Electrical room & DG room should be shifted to basement-1 or ground floor.
 3 x 800A Raising Mains are available with reducer at 2 floor, it can retained with/ without modification &
service. Floor power distribution to be checked before using the same.
 Fire hydrant & sprinkler system are at good condition, minor modification required to meet our
requirement. Fire Pump room modification required and fire panel needs to replaced.
 New Fire Alarm & Public Address System need to proposed.
MEP
 Basement-2 ventilation system to be considered new.
 New PHE piping to be considered as per our toilet requirement.
 Storm water system needs cleaning with new rain water downcomers from terrace.
 HVAC: New system to be proposed as per IndiQube requirement.
EXTERNAL -YARD HYDRANT AND FIRE HOSE CABINET
Existing External Yard hydrant, Hose Reels and Other accessories shall be retain as it is.
However the system to be checked and testing to be carried out. Wherever accessories are
missing, same to be restored .
FIRE PUMP ROOM
Existing Pump,Piping arrangement,Valves and
Other accessories shall be retain same. However
the system to be checked and testing to be carried
out. Wherever the valves, fittings or any other
accessories are damaged/Missed out, the same to
be replaced by new .
FIRE PUMP ROOM-EXHAUST PIPE
 DG Operated Pump Set
Exhaust pipe is not
Insulated. The same has
to be insulated to avoid
the following:
 Personnel injury due to
contact with exposed
exhaust pipe.
 Generation of high
temperature
 Damage to cables and
sensors.
 Exhaust Pipe shall be
supported properly with
rigid structural support.
FIRE PUMP PANEL
Existing Panel is in working condition. However
Performance of Panel, Condition of cabling & size of
the breakers to be checked and if required it may be
changed as per the latest fire & safety norms.
Existing Sprinkler Alarm valve is in good shape .Minor
servicing is required. The arrangement shall be retain as it is.
SPRINKLER ALARM VALVE
TERMINATION OF RISER & DRAIN PIPE
Fire Drain Pipe is Terminated at Upper Basement level inside the shaft without any connection with PHE
Drain line .
MEP SHAFT
In a common shaft ,all the services along the fire riser are there. As per Standard Fire shaft should
not be used for any other services.
EXTERNAL STORM WATER DRAINAGE SYSTEM
 External Storm water drainage system is in good condition .However the following actions to be made
 Cleaning and Servicing of the manhole, Inspection Chamber,Gutter
 Proper Alignment of the covers
 Sloping of paver tiles towards storm water drain properly.
PHE SHAFT
Existing Vertical Pipes /Riser are very old and GI pipes are used for
Water Supply system .New pipes with proper support to be provided for
vertical piping inside shaft .
LIGHTNING PROTECTION SYSTEM & EARTHING
 Proper Support for Rain water Down take
and Balcony Drain Pipe is required .
 Proper Water Proofing around the pipe is
required.
RAIN WATER PIPING SYSTEM
Most of the places Rain Water Pipes are in good
condition. Since the Basement pipes are fully
painted,so the Condition of Horizontal lines to be
checked properly and Minor modification has to be
done at some places. Addition to this Pipe joint and
support to be redo as per requirement.
PHE PUMP ROOM
Existing Water Lifting Pumps are in Working Condition.
Minor Servicing is required.
NEW PROPOSALS
 STP : In Existing System the Toilet soil and waste is connected with Municipal Drain directly.
 Basement Drainage
THANK YOU!!!!

More Related Content

Similar to MEP JUGAADS.pptx

Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
Radha Krishna Sahoo
 
Dry Back Scotch Marine Boiler
Dry Back Scotch Marine BoilerDry Back Scotch Marine Boiler
Dry Back Scotch Marine Boiler
CTi Controltech
 
DEBORA PPT.pptx
DEBORA PPT.pptxDEBORA PPT.pptx
DEBORA PPT.pptx
AgohaChinonso
 
Boiler ppt
Boiler pptBoiler ppt
Boiler ppt
Er Ramgarhia
 
Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.ppt
ssuser8006c7
 
Overview of Automatic Fire Sprinkler Systems.pptx
Overview of Automatic Fire Sprinkler Systems.pptxOverview of Automatic Fire Sprinkler Systems.pptx
Overview of Automatic Fire Sprinkler Systems.pptx
M&E Engineer
 
IJ Presentation, Slide 01 to 30.pptx
IJ Presentation, Slide 01 to 30.pptxIJ Presentation, Slide 01 to 30.pptx
IJ Presentation, Slide 01 to 30.pptx
AGNELVVARKEY
 
Condensate system
Condensate systemCondensate system
Condensate system
RAVI PAL SINGH
 
INTRODUCING AQUAFAN
INTRODUCING AQUAFANINTRODUCING AQUAFAN
INTRODUCING AQUAFAN
Bertus Bolknak
 
2011 inspector notes
2011 inspector notes2011 inspector notes
2011 inspector notes
brucecarmichael
 
Eenovators - Solar Hot Water Systems and challenges
Eenovators - Solar Hot Water Systems and challengesEenovators - Solar Hot Water Systems and challenges
Eenovators - Solar Hot Water Systems and challenges
Eenovators Limited
 
odunlami prese_033552.pptx
odunlami prese_033552.pptxodunlami prese_033552.pptx
odunlami prese_033552.pptx
AgohaChinonso
 
Bs presentation slides
Bs presentation slidesBs presentation slides
Bs presentation slides
Syafiq Zariful
 
Sanitary Pump Station Rehabilitation
Sanitary Pump Station RehabilitationSanitary Pump Station Rehabilitation
Sanitary Pump Station Rehabilitation
David E. Mizell, P.E., BCEE
 
ADR PRV Presentation.pptx
ADR PRV Presentation.pptxADR PRV Presentation.pptx
ADR PRV Presentation.pptx
Raja Sv
 
Projects alrawan
Projects alrawanProjects alrawan
Projects alrawan
Mahmoud Farran
 
vdocument.in_660-mw-turbine.ppt
vdocument.in_660-mw-turbine.pptvdocument.in_660-mw-turbine.ppt
vdocument.in_660-mw-turbine.ppt
SVV Surya Narayana Raju
 
Residential manual (9)
Residential manual (9)Residential manual (9)
Residential manual (9)
Maria S
 
Mppkvv company ltd
Mppkvv company ltdMppkvv company ltd
Mppkvv company ltd
DEEPAK PATEL
 
STEAM POWER PLANT
STEAM POWER PLANTSTEAM POWER PLANT
STEAM POWER PLANT
Umang Parmar
 

Similar to MEP JUGAADS.pptx (20)

Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
 
Dry Back Scotch Marine Boiler
Dry Back Scotch Marine BoilerDry Back Scotch Marine Boiler
Dry Back Scotch Marine Boiler
 
DEBORA PPT.pptx
DEBORA PPT.pptxDEBORA PPT.pptx
DEBORA PPT.pptx
 
Boiler ppt
Boiler pptBoiler ppt
Boiler ppt
 
Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.ppt
 
Overview of Automatic Fire Sprinkler Systems.pptx
Overview of Automatic Fire Sprinkler Systems.pptxOverview of Automatic Fire Sprinkler Systems.pptx
Overview of Automatic Fire Sprinkler Systems.pptx
 
IJ Presentation, Slide 01 to 30.pptx
IJ Presentation, Slide 01 to 30.pptxIJ Presentation, Slide 01 to 30.pptx
IJ Presentation, Slide 01 to 30.pptx
 
Condensate system
Condensate systemCondensate system
Condensate system
 
INTRODUCING AQUAFAN
INTRODUCING AQUAFANINTRODUCING AQUAFAN
INTRODUCING AQUAFAN
 
2011 inspector notes
2011 inspector notes2011 inspector notes
2011 inspector notes
 
Eenovators - Solar Hot Water Systems and challenges
Eenovators - Solar Hot Water Systems and challengesEenovators - Solar Hot Water Systems and challenges
Eenovators - Solar Hot Water Systems and challenges
 
odunlami prese_033552.pptx
odunlami prese_033552.pptxodunlami prese_033552.pptx
odunlami prese_033552.pptx
 
Bs presentation slides
Bs presentation slidesBs presentation slides
Bs presentation slides
 
Sanitary Pump Station Rehabilitation
Sanitary Pump Station RehabilitationSanitary Pump Station Rehabilitation
Sanitary Pump Station Rehabilitation
 
ADR PRV Presentation.pptx
ADR PRV Presentation.pptxADR PRV Presentation.pptx
ADR PRV Presentation.pptx
 
Projects alrawan
Projects alrawanProjects alrawan
Projects alrawan
 
vdocument.in_660-mw-turbine.ppt
vdocument.in_660-mw-turbine.pptvdocument.in_660-mw-turbine.ppt
vdocument.in_660-mw-turbine.ppt
 
Residential manual (9)
Residential manual (9)Residential manual (9)
Residential manual (9)
 
Mppkvv company ltd
Mppkvv company ltdMppkvv company ltd
Mppkvv company ltd
 
STEAM POWER PLANT
STEAM POWER PLANTSTEAM POWER PLANT
STEAM POWER PLANT
 

Recently uploaded

Zener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and ApplicationsZener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and Applications
Shiny Christobel
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 
smart pill dispenser is designed to improve medication adherence and safety f...
smart pill dispenser is designed to improve medication adherence and safety f...smart pill dispenser is designed to improve medication adherence and safety f...
smart pill dispenser is designed to improve medication adherence and safety f...
um7474492
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
nedcocy
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
AI-Based Home Security System : Home security
AI-Based Home Security System : Home securityAI-Based Home Security System : Home security
AI-Based Home Security System : Home security
AIRCC Publishing Corporation
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
upoux
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
NATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENT
NATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENTNATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENT
NATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENT
Addu25809
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptxSENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
b0754201
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
Kamal Acharya
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
MadhavJungKarki
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Introduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.pptIntroduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.ppt
Dwarkadas J Sanghvi College of Engineering
 
Height and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdfHeight and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdf
q30122000
 
5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf
AlvianRamadhani5
 
Mechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineeringMechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineering
sachin chaurasia
 

Recently uploaded (20)

Zener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and ApplicationsZener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and Applications
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 
smart pill dispenser is designed to improve medication adherence and safety f...
smart pill dispenser is designed to improve medication adherence and safety f...smart pill dispenser is designed to improve medication adherence and safety f...
smart pill dispenser is designed to improve medication adherence and safety f...
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
AI-Based Home Security System : Home security
AI-Based Home Security System : Home securityAI-Based Home Security System : Home security
AI-Based Home Security System : Home security
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
NATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENT
NATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENTNATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENT
NATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENT
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptxSENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Introduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.pptIntroduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.ppt
 
Height and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdfHeight and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdf
 
5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf
 
Mechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineeringMechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineering
 

MEP JUGAADS.pptx

  • 2. CONTENTS • Services • As per site condition Pictures • Load Details
  • 3. MEP  Transformer – 1 x 1600kVA 11kV/433V Oil Type Transformer  It is in working condition, only servicing is required.  Manufacturing Year: 2004  Make: Voltamp  DG – 2 x 625KVA & 1 x 500kVA DG Sets  Out of 3 DG sets 500kVA is not in working condition. Remaining 2 DG sets need to be replaced considering the DG health & life span.  Electrical room & DG room should be shifted to basement-1 or ground floor.  3 x 800A Raising Mains are available with reducer at 2 floor, it can retained with/ without modification & service. Floor power distribution to be checked before using the same.  Fire hydrant & sprinkler system are at good condition, minor modification required to meet our requirement. Fire Pump room modification required and fire panel needs to replaced.  New Fire Alarm & Public Address System need to proposed.
  • 4. MEP  Basement-2 ventilation system to be considered new.  New PHE piping to be considered as per our toilet requirement.  Storm water system needs cleaning with new rain water downcomers from terrace.  HVAC: New system to be proposed as per IndiQube requirement.
  • 5. EXTERNAL -YARD HYDRANT AND FIRE HOSE CABINET Existing External Yard hydrant, Hose Reels and Other accessories shall be retain as it is. However the system to be checked and testing to be carried out. Wherever accessories are missing, same to be restored .
  • 6. FIRE PUMP ROOM Existing Pump,Piping arrangement,Valves and Other accessories shall be retain same. However the system to be checked and testing to be carried out. Wherever the valves, fittings or any other accessories are damaged/Missed out, the same to be replaced by new .
  • 7. FIRE PUMP ROOM-EXHAUST PIPE  DG Operated Pump Set Exhaust pipe is not Insulated. The same has to be insulated to avoid the following:  Personnel injury due to contact with exposed exhaust pipe.  Generation of high temperature  Damage to cables and sensors.  Exhaust Pipe shall be supported properly with rigid structural support.
  • 8. FIRE PUMP PANEL Existing Panel is in working condition. However Performance of Panel, Condition of cabling & size of the breakers to be checked and if required it may be changed as per the latest fire & safety norms.
  • 9. Existing Sprinkler Alarm valve is in good shape .Minor servicing is required. The arrangement shall be retain as it is. SPRINKLER ALARM VALVE
  • 10. TERMINATION OF RISER & DRAIN PIPE Fire Drain Pipe is Terminated at Upper Basement level inside the shaft without any connection with PHE Drain line .
  • 11. MEP SHAFT In a common shaft ,all the services along the fire riser are there. As per Standard Fire shaft should not be used for any other services.
  • 12. EXTERNAL STORM WATER DRAINAGE SYSTEM  External Storm water drainage system is in good condition .However the following actions to be made  Cleaning and Servicing of the manhole, Inspection Chamber,Gutter  Proper Alignment of the covers  Sloping of paver tiles towards storm water drain properly.
  • 13. PHE SHAFT Existing Vertical Pipes /Riser are very old and GI pipes are used for Water Supply system .New pipes with proper support to be provided for vertical piping inside shaft .
  • 14. LIGHTNING PROTECTION SYSTEM & EARTHING  Proper Support for Rain water Down take and Balcony Drain Pipe is required .  Proper Water Proofing around the pipe is required.
  • 15. RAIN WATER PIPING SYSTEM Most of the places Rain Water Pipes are in good condition. Since the Basement pipes are fully painted,so the Condition of Horizontal lines to be checked properly and Minor modification has to be done at some places. Addition to this Pipe joint and support to be redo as per requirement.
  • 16. PHE PUMP ROOM Existing Water Lifting Pumps are in Working Condition. Minor Servicing is required.
  • 17. NEW PROPOSALS  STP : In Existing System the Toilet soil and waste is connected with Municipal Drain directly.  Basement Drainage