This document provides quantities of materials required for various construction items. It lists 34 items of work and the quantity of materials needed per 100 cubic feet or 100 cubic meters. Key materials included are bricks, mortar, stone, ballast, sand, cement and reinforcement bars. Reinforcement quantities are provided for items like footings, beams, lintels, slabs and columns. The document also specifies materials for items like flooring, plastering, painting, doors, windows and roofing.
Effect of Waste Foundry Sand on Durability Properties of ConcreteIEI GSC
Presentation on Effect of Waste Foundry Sand on Durability Properties of Concrete by Tirth Doshi guided by Dr Urmil Dave & Prof Tejas Joshi at #33NCCE 33rd National Convention of Civil Engineers at #IEIGSC
Information on the slides is found on the internet. Any incorrect information is not intended. All credit is given to the source of information, not to the author of this slide.
Effect of Waste Foundry Sand on Durability Properties of ConcreteIEI GSC
Presentation on Effect of Waste Foundry Sand on Durability Properties of Concrete by Tirth Doshi guided by Dr Urmil Dave & Prof Tejas Joshi at #33NCCE 33rd National Convention of Civil Engineers at #IEIGSC
Information on the slides is found on the internet. Any incorrect information is not intended. All credit is given to the source of information, not to the author of this slide.
Khai giảng khóa Huấn luyện An toàn lao động theo thông tư 27 tại Hà Nội,HCM,Đ...Vienquocte
Chứng chỉ An toàn lao động,lớp học An toàn lao động, học an toàn lao động ở đâu,học an toàn vệ sinh lao động,chứng nhận an toàn lao động,học an toàn lao động hà nội,lớp an toàn lao động ở hồ chí minh,
Chứng chỉ An toàn lao động,lớp học An toàn lao động, học an toàn lao động ở đâu,học an toàn vệ sinh lao động,chứng nhận an toàn lao động,học an toàn lao động hà nội,lớp an toàn lao động ở hồ chí minh,
Chứng chỉ An toàn lao động,lớp học An toàn lao động, học an toàn lao động ở đâu,học an toàn vệ sinh lao động,chứng nhận an toàn lao động,học an toàn lao động hà nội,lớp an toàn lao động ở hồ chí minh,
The capacity of doing work by an artisan or skilled labour in the form of quantity of work per day is known as the task work or out turn of the labour.
The out-turn of work per artisan varies to some extent according to the nature, size, height, situation, location, etc., In bigger cities where specialized and experienced labour is available the out-turn is greater than small towns and country sides. In well organized work less labour is required.
Khai giảng khóa Huấn luyện An toàn lao động theo thông tư 27 tại Hà Nội,HCM,Đ...Vienquocte
Chứng chỉ An toàn lao động,lớp học An toàn lao động, học an toàn lao động ở đâu,học an toàn vệ sinh lao động,chứng nhận an toàn lao động,học an toàn lao động hà nội,lớp an toàn lao động ở hồ chí minh,
Chứng chỉ An toàn lao động,lớp học An toàn lao động, học an toàn lao động ở đâu,học an toàn vệ sinh lao động,chứng nhận an toàn lao động,học an toàn lao động hà nội,lớp an toàn lao động ở hồ chí minh,
Chứng chỉ An toàn lao động,lớp học An toàn lao động, học an toàn lao động ở đâu,học an toàn vệ sinh lao động,chứng nhận an toàn lao động,học an toàn lao động hà nội,lớp an toàn lao động ở hồ chí minh,
The capacity of doing work by an artisan or skilled labour in the form of quantity of work per day is known as the task work or out turn of the labour.
The out-turn of work per artisan varies to some extent according to the nature, size, height, situation, location, etc., In bigger cities where specialized and experienced labour is available the out-turn is greater than small towns and country sides. In well organized work less labour is required.
BHADANIS Construction Material Estimation Guide - Estimation of Civil Works Material Consumption Statement Sheet - Concrete Work Material Estimation Concrete Work Estimation Shuttering Work Estimation Road Work Estimation
BHADANIS Construction Material Estimation Guide - Estimation of Civil Works Material Consumption Statement Sheet - Concrete Work Material Estimation Concrete Work Estimation Shuttering Work Estimation Road Work Estimation
BHADANIS - BRICK WORK ESTIMATION GUIDE CIVIL WORKS CONSTRUCTION ESTIMATION BHADANIS Construction Material Estimation Guide - Estimation of Civil Works Material Consumption Statement Sheet - Concrete Work Material Estimation Concrete Work Estimation Shuttering Work Estimation Road Work Estimation
Bhadanis RCC WORK ESTIMATION GUIDE PCC WORK ESTIMATION BHADANIS Construction Material Estimation Guide - Estimation of Civil Works Material Consumption Statement Sheet - Concrete Work Material Estimation Concrete Work Estimation Shuttering Work Estimation Road Work Estimation
ROAD WORK ESTIMATION GUIDE MATERIAL BHADANIS BHADANIS Construction Material Estimation Guide - Estimation of Civil Works Material Consumption Statement Sheet - Concrete Work Material Estimation Concrete Work Estimation Shuttering Work Estimation Road Work Estimation
BHADANIS - PLASTER WORK ESTIMATION GUIDE BHADANIS Construction Material Estimation Guide - Estimation of Civil Works Material Consumption Statement Sheet - Concrete Work Material Estimation Concrete Work Estimation Shuttering Work Estimation Road Work Estimation
Structural Properties of Laterite - Quarry Dust Cement BlocksQUESTJOURNAL
ABSTRACT: The study investigated the compressive strength and static modulus of elasticity of building blocks with full replacement of river sand with a blend of laterite – quarry. Values of compressive strength and static modulus are very helpful in the analyses and design of structures as they help in avoiding unrealistic assumptions which may be misleading in design. The maximum value of compressive strength obtained from a blend of 70% quarry dust and 30% laterite was 2.56N/mm2 at water cement ratio of 0.58 while a static modulus of elasticity of 8.86 was obtained from a combination of 75% quarry dust and 25% laterite.
Similar to Materials%20required%20for%20different%20items%20of%20work (20)
1. MATERIALS REQUIRED FOR DIFFERENT ITEMS OF WORK
Quantity
Sr. per 100
no. Particulars Cft per 100 Cu m
1 Bricks
9"x47"x3" or 200 x 100x 100 mm) 1350 nos 50,000 nos
2 Dry mortar for Brick work 30 % 30 Cft 30 Cu m
3 Stone for rubble masonry 125 % 125 Cft 125 Cu m
4 Dry mortar for Brick work 42 % 42 Cft 42 m3
5 Bricks for brick ballast for Lime Concrete 1050 nos 37000 nos
6 Brick bats for brick ballast 105 Cft 105 Cu m
7 Brick ballast for lime Concrete 100 Cft 100 Cu m
8 Dry mortar for lime concrete in foundations 35 Cft 35 Cu m
9 Do for roof terracing 45 % 45 Cft 45 Cu m
10 Materials for cement concrete 1:2:4
Ballast of grit 88 % 88 Cft 83 Cu m
Sand 44% 44 Cft 44 Cu m
Cement 22 % 22 Cft 22 Cu m
17.5
bags 630 bags
11 Bricks for R B Work 1200 nos 42000 nos
12 Dry mortar for R. B. Work 45 % 45 Cft 45 Cu m
No. Particulars Lot/Unit Lot / Unit
13 Reinforcement Quantity
a) Footing 4 Ib/Cft 64 kg/Cu m
b) R. C. C. Steps 4 ft long 15 Ib/Cft 7 Kg/ Cu m
130.00 Kg/Cu
c) Beams 8 Ib/Cft m
115.00 Kg/ Cu
d) Lintel 7 Ib/Cft m
1.6 Ib/
e) Roof Slab 4 1/2" Sft 8.00 kg/ sq m
2.0 Ib/
f) Roof Slab 5 1/2" Sft 10.00 Kg/ sq m
2.75
g) Balcony Slab 5 1/2" Ib/Sft 14.00 Kg/ sq m
1.60
h) Chajjas Ib/Sft 8 Kg/sqft
8.00
i) Column Ib/Cft 130 kg/ Cu m
Reinforcement quantities are only approximate and vary
as per design
14 Material for 25 mm (1") C.C. 1:2:4 floor
a) Stone grit 8 Cft 2.4 Cu m
b) Sand 4 Cft 1.2 Cu m
c) Cement 2.5 Cft 0.8m3
(2 bags) for % Sq.M)
15 Dry mortar for 12 mm plaster 6 Cft 6 Cu m
16 Dry mortar for pointing Brick work 2 Cft 2 Cu m
17 Lime for white washing 1 coat 0.65 kg 6.5 kg
2. 18 Dry Distemper 1st coat 0.65 kg 6.5 kg
19 Dry distemper 2nd coat 0.5 kg 5 kg
20 Snowcem 1st coat 3 kg 30 kg
21 Snowcem 2nd coat 2 kg 20 kg
22 Readymade paint for 1 coat 1/2 gal 10 ltrs
23 Paint (stiff) for painting 1 coat 1 kg 10 kgs
24 Bricks for half brick wall 500 nos 5000 nos
25 Dry mortar for above 12 Cft 3.2 Cu m
26 Bricks (9" x 4 1/2" x 3") for brick on edge floor 350 nos 3500 nos
27 Dry mortar for above 8 Cft 2.25 cu m
28 Bricks (9" x 4 1/2" x 3")for honeycomb wall 350 nos 3500 nos
29 Dry mortar for above 8 Cft 2.25 cu m
30 Materials for 3/4" (20 mm) D.P.C. in 1:2 cm
a) Sand 6 Cft 1.80 Cu m
b) Cement 2.5 bags 27 bags
c) Composeal or Impermo 1 kg per bag of cement 2.5 kg 27 kg
31 Materials for 1" (25 mm) D. P. C. in
Cement concrete 1:1 1/2:3
a) Stone grit 8 Cft 2.25 cu m
b) Sand coarse 4 Cft 1.12 cu m
c) cement 27 Cft 0.75 cu m
2 1/4
bags 22 1/2 bags
Composeal or impermo 1 kg/ bag of cement 2 2/3 kg 22 1/2 kg
32 Bitumen or Asphalt for painting on DPC on roof
1st coat 15 kg 150 kg
2nd coat 10 kg 100 kg
33 C.G. I sheet for roof 128 stf 128 sq m
34 A.C. Sheet corrugated for roof 115 stf 115 sq m
35 Timber for panelled door shutter 40 mm 15 cft 4.5 cu.m
36 Timber for battoned door shutter 40 mm 13 cft 4.0 cu.m
Timber for partly panelled and glazed shutter 40 mm
37 thick 11 cft 3.0 cu.m
38 Timber for fully glazed shutter 40 mm thick 8 cft 2.0 cu.m
39 Binding Wire 15 kg/ton 15 per kg ton