TOOL BOX TALK
LOCK OUT/TAG OUT
Roles and Responsibilities
 Approving Authority – Site Supervisor
 Issuing Authority – PTW Coordinator
 Performing Authority – Foreman or Supervisor
 Electrical Isolation Authority
 Mechanical Isolation Authority
The Approving Authority must visit the location where the task is
to take place prior to approving and signing the permit
PROCEDURE
The procedure specifies methods of controlling
hazardous energy sources during construction and
maintenance activities on:
 Electrical services
 Facilities
 Shop equipment
 Pressurized pipe and
 Systems used as
service lines for
construction
 Electrical
 Generated
 Static
 Mechanical
 Transitional
 Rotational
 Thermal
 Machines or Equipment
 Chemical Reactions
 Potential Pressure
 Hydraulic
 Pneumatic
 Vacuum
Procedure (cont’d)
The equipment to be worked is isolated from all
sources of energy:
PROCEDURE (CONT’D)
 A standard “DANGER – DO NOT OPERATE” tag and
individually keyed locks will be used on the Project
 All tags shall be dated, signed and a description of the work
being performed shown on the tag and securely attached to the
equipment / lock
 Tags must never be re-used,
but destroyed immediately
upon removal.
No alterations to a tag are permitted!
DO NOT OPERATE
PROCEDURE (CONT’D)
Tags required beyond one shift shall be replaced by
the oncoming shift.
In no case will locks and tags be permitted to remain
more than 7 days without re-inspection, signed and
Dated
ISOLATION CONFORMATION CERTIFICATE
(ICC)
All sources of energy such as
 pipelines
 valves
 pumps
shall be blanked off and otherwise secured
to prevent charging, energizing or creating
any type of hazards to persons working on
systems or inside a confined space
ELECTRICAL OPERATED SYSTEMS
When work on electrical equipment or services is
scheduled, the power source shall be de-energized using
one or more of the following means:
Main Isolator
Remove Fuses
Local Isolator
ELECTRICAL OPERATED SYSTEMS
(CONT’D)
To lock out electrically powered shop equipment to
ensure maximum employee safety:
A power disconnect switch shall be installed between the
main power supply panel and each piece of electrically driven
equipment which directly connected to the power panel box
The disconnect switch should be located close to the
equipment and properly identified
Pushbuttons or butterfly
controls of equipment should
not be locked out
ELECTRICAL OPERATED SYSTEMS
(CONT’D)
Completed Danger Tag(s) and locks shall be attached to the
controlling device by:
 Person responsible for de-energizing the system
 The foreman in charge of the work on the system
 All craft workers required to work on the system
Where exposed electrical circuits are to be worked on, the de-
energized equipment or systems shall be tested using
a voltmeter on the down stream
side of the tagged our
controlling device to ensure
there is an effective isolation
of the circuit
ELECTRICAL OPERATED SYSTEMS
(CONT’D)
 The lockout log shall list all personnel applying a lock and
tag on any power panel; distribution panel or equipment-
controlling device.
 Each person shall detail in the lockout log the time of day he
applied the lock, the necessity for the lockout, the area or
machine where the work is being performed and
the approximate length of time
that the power panel, distribution
panel or equipment controller will
be de-energized
ELECTRICAL OPERATED SYSTEMS
(CONT’D)
 When the work is completed, the employees will report this
information to the Electrical Superintendent before removing
his lock. The employees will log the time the work was
completed in the lockout log and the time he removed his
lock
 Whenever maintenance of shop equipment is required, such
as changing the blade of a radial arm saw, the craft operator
shall verify that the controlling device (power disconnect) has
been tagged and locked out before maintenance work begins
OPERATING FACILITIES AND
EQUIPMENT
 Electrical Isolation Authority or his designee de-
energizes the system, checks it and places his lock
and tag on the lockout device
 Other employees working on the system places
their locks and tags on the device and complete the
lockout log
 Upon completion of the work, the Electrical
Isolation Authority or his designee is the last
person to remove his lock
and tag
MECHANICAL WORK
Whenever work is scheduled on mechanical
equipment or pressurized systems controlling
devices such as:
 circuit breakers
 switches
 valve handles
 and other operating mechanisms
shall be locked and tagged out to prevent their
manipulation or operation
MECHANICAL WORK (CONT’D)
 Where possible the system shall be disconnected
from all sources of pressure or hazardous
substance
 If appropriate on tanks and pressure vessels, the
system shall be emptied, depressurized and
blanked off before work
starts
 Appropriate gas tests
shall be conducted
TYPES OF LOCKOUT DEVICES
 Plug Locks
 Ball Valve Lockout
 Gate Valve Lockout
 Group Lockout Hasp
 Electrical
 Hydraulic, pneumatic,
and other pressurized
systems
EMERGENCY REMOVAL OF
EMPLOYEES LOCKOUT LOCK
 Each lock-out / tag-out device shall be removed from each
energy-isolating device by the employee who applied the
device
 The supervisor in charge of the work and the Electrical
Isolation Authority shall
complete an “emergency lock-out
Device Removal” form and
present it to the Construction
Manager and the senior
Safety Officer for an
approval to remove the lock
THANK YOU

More Related Content

Similar to Lockout Tagout.ppt

Catalog FR-E700 instruction manual (applied)-Beeteco.com
Catalog FR-E700 instruction manual (applied)-Beeteco.comCatalog FR-E700 instruction manual (applied)-Beeteco.com
Catalog FR-E700 instruction manual (applied)-Beeteco.com
Beeteco
 
Lockout Tagout
Lockout TagoutLockout Tagout
Lockout Tagout
vtsiri
 
Procedure 1
Procedure 1Procedure 1
Procedure 1
Jenifer Loud
 
loto
lotoloto
LOTO 2022 - Energy Isolation Process .pptx
LOTO 2022 - Energy Isolation Process .pptxLOTO 2022 - Energy Isolation Process .pptx
LOTO 2022 - Energy Isolation Process .pptx
Nigel Brown
 
Electrical Safety1
Electrical Safety1Electrical Safety1
Electrical Safety1
jboullemet
 
Safety Tip: Lockout/Tagout (LOTO)
Safety Tip: Lockout/Tagout (LOTO)Safety Tip: Lockout/Tagout (LOTO)
Safety Tip: Lockout/Tagout (LOTO)
ComplianceSigns, LLC
 
Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009
txn4_8
 
Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...
Thorne & Derrick International
 
Lockout Tagout Guidelines
Lockout Tagout GuidelinesLockout Tagout Guidelines
Lockout Tagout Guidelines
krm corporation
 
Loto.pptx
Loto.pptxLoto.pptx
Loto.pptx
ROHITSINGH83692
 
MM Electrical Safety Policy-Procedure draft 2
MM Electrical Safety Policy-Procedure draft 2MM Electrical Safety Policy-Procedure draft 2
MM Electrical Safety Policy-Procedure draft 2
Benjamin Canaday
 
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.pptSVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
ssuser4b097a
 
Nyscma Electrical Safety 11 6 08 Ralph Viola
Nyscma Electrical Safety 11 6 08 Ralph ViolaNyscma Electrical Safety 11 6 08 Ralph Viola
Nyscma Electrical Safety 11 6 08 Ralph Viola
Martin Demarest
 
Loto presentation.pptx
Loto presentation.pptxLoto presentation.pptx
Loto presentation.pptx
naeem41394
 
FX5 Simple Motion(Startup).pdf
FX5 Simple Motion(Startup).pdfFX5 Simple Motion(Startup).pdf
FX5 Simple Motion(Startup).pdf
NguyenTuan295165
 
LOTO
LOTO LOTO
CTSC-200 series PLC User Manual V1.00.pdf
CTSC-200 series PLC User Manual V1.00.pdfCTSC-200 series PLC User Manual V1.00.pdf
CTSC-200 series PLC User Manual V1.00.pdf
HaykelMhadhbi
 
Loto presentation
Loto presentationLoto presentation
Loto presentation
LalitSharma508
 
Iveco workshop manual
Iveco workshop manualIveco workshop manual
Iveco workshop manual
Luiz Antonio da Silva
 

Similar to Lockout Tagout.ppt (20)

Catalog FR-E700 instruction manual (applied)-Beeteco.com
Catalog FR-E700 instruction manual (applied)-Beeteco.comCatalog FR-E700 instruction manual (applied)-Beeteco.com
Catalog FR-E700 instruction manual (applied)-Beeteco.com
 
Lockout Tagout
Lockout TagoutLockout Tagout
Lockout Tagout
 
Procedure 1
Procedure 1Procedure 1
Procedure 1
 
loto
lotoloto
loto
 
LOTO 2022 - Energy Isolation Process .pptx
LOTO 2022 - Energy Isolation Process .pptxLOTO 2022 - Energy Isolation Process .pptx
LOTO 2022 - Energy Isolation Process .pptx
 
Electrical Safety1
Electrical Safety1Electrical Safety1
Electrical Safety1
 
Safety Tip: Lockout/Tagout (LOTO)
Safety Tip: Lockout/Tagout (LOTO)Safety Tip: Lockout/Tagout (LOTO)
Safety Tip: Lockout/Tagout (LOTO)
 
Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009
 
Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...
 
Lockout Tagout Guidelines
Lockout Tagout GuidelinesLockout Tagout Guidelines
Lockout Tagout Guidelines
 
Loto.pptx
Loto.pptxLoto.pptx
Loto.pptx
 
MM Electrical Safety Policy-Procedure draft 2
MM Electrical Safety Policy-Procedure draft 2MM Electrical Safety Policy-Procedure draft 2
MM Electrical Safety Policy-Procedure draft 2
 
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.pptSVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
 
Nyscma Electrical Safety 11 6 08 Ralph Viola
Nyscma Electrical Safety 11 6 08 Ralph ViolaNyscma Electrical Safety 11 6 08 Ralph Viola
Nyscma Electrical Safety 11 6 08 Ralph Viola
 
Loto presentation.pptx
Loto presentation.pptxLoto presentation.pptx
Loto presentation.pptx
 
FX5 Simple Motion(Startup).pdf
FX5 Simple Motion(Startup).pdfFX5 Simple Motion(Startup).pdf
FX5 Simple Motion(Startup).pdf
 
LOTO
LOTO LOTO
LOTO
 
CTSC-200 series PLC User Manual V1.00.pdf
CTSC-200 series PLC User Manual V1.00.pdfCTSC-200 series PLC User Manual V1.00.pdf
CTSC-200 series PLC User Manual V1.00.pdf
 
Loto presentation
Loto presentationLoto presentation
Loto presentation
 
Iveco workshop manual
Iveco workshop manualIveco workshop manual
Iveco workshop manual
 

Recently uploaded

Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
Top Forex Brokers Review
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
DerekIwanaka1
 
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
SEOSMMEARTH
 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
Norma Mushkat Gaffin
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
ssuser567e2d
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
marketing317746
 
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdfHOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
46adnanshahzad
 
How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
MJ Global
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Holger Mueller
 
Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024
FelixPerez547899
 
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
taqyea
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
NZSG
 
The Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb PlatformThe Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb Platform
SabaaSudozai
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel ChartSatta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
hartfordclub1
 
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
my Pandit
 
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Operational Excellence Consulting
 

Recently uploaded (20)

Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
 
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
 
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdfHOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
 
How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
 
Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024
 
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
 
The Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb PlatformThe Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb Platform
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel ChartSatta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
 
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
 
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
 

Lockout Tagout.ppt

  • 1. TOOL BOX TALK LOCK OUT/TAG OUT
  • 2. Roles and Responsibilities  Approving Authority – Site Supervisor  Issuing Authority – PTW Coordinator  Performing Authority – Foreman or Supervisor  Electrical Isolation Authority  Mechanical Isolation Authority The Approving Authority must visit the location where the task is to take place prior to approving and signing the permit
  • 3. PROCEDURE The procedure specifies methods of controlling hazardous energy sources during construction and maintenance activities on:  Electrical services  Facilities  Shop equipment  Pressurized pipe and  Systems used as service lines for construction
  • 4.  Electrical  Generated  Static  Mechanical  Transitional  Rotational  Thermal  Machines or Equipment  Chemical Reactions  Potential Pressure  Hydraulic  Pneumatic  Vacuum Procedure (cont’d) The equipment to be worked is isolated from all sources of energy:
  • 5. PROCEDURE (CONT’D)  A standard “DANGER – DO NOT OPERATE” tag and individually keyed locks will be used on the Project  All tags shall be dated, signed and a description of the work being performed shown on the tag and securely attached to the equipment / lock  Tags must never be re-used, but destroyed immediately upon removal. No alterations to a tag are permitted! DO NOT OPERATE
  • 6. PROCEDURE (CONT’D) Tags required beyond one shift shall be replaced by the oncoming shift. In no case will locks and tags be permitted to remain more than 7 days without re-inspection, signed and Dated
  • 7. ISOLATION CONFORMATION CERTIFICATE (ICC) All sources of energy such as  pipelines  valves  pumps shall be blanked off and otherwise secured to prevent charging, energizing or creating any type of hazards to persons working on systems or inside a confined space
  • 8. ELECTRICAL OPERATED SYSTEMS When work on electrical equipment or services is scheduled, the power source shall be de-energized using one or more of the following means: Main Isolator Remove Fuses Local Isolator
  • 9. ELECTRICAL OPERATED SYSTEMS (CONT’D) To lock out electrically powered shop equipment to ensure maximum employee safety: A power disconnect switch shall be installed between the main power supply panel and each piece of electrically driven equipment which directly connected to the power panel box The disconnect switch should be located close to the equipment and properly identified Pushbuttons or butterfly controls of equipment should not be locked out
  • 10. ELECTRICAL OPERATED SYSTEMS (CONT’D) Completed Danger Tag(s) and locks shall be attached to the controlling device by:  Person responsible for de-energizing the system  The foreman in charge of the work on the system  All craft workers required to work on the system Where exposed electrical circuits are to be worked on, the de- energized equipment or systems shall be tested using a voltmeter on the down stream side of the tagged our controlling device to ensure there is an effective isolation of the circuit
  • 11. ELECTRICAL OPERATED SYSTEMS (CONT’D)  The lockout log shall list all personnel applying a lock and tag on any power panel; distribution panel or equipment- controlling device.  Each person shall detail in the lockout log the time of day he applied the lock, the necessity for the lockout, the area or machine where the work is being performed and the approximate length of time that the power panel, distribution panel or equipment controller will be de-energized
  • 12. ELECTRICAL OPERATED SYSTEMS (CONT’D)  When the work is completed, the employees will report this information to the Electrical Superintendent before removing his lock. The employees will log the time the work was completed in the lockout log and the time he removed his lock  Whenever maintenance of shop equipment is required, such as changing the blade of a radial arm saw, the craft operator shall verify that the controlling device (power disconnect) has been tagged and locked out before maintenance work begins
  • 13. OPERATING FACILITIES AND EQUIPMENT  Electrical Isolation Authority or his designee de- energizes the system, checks it and places his lock and tag on the lockout device  Other employees working on the system places their locks and tags on the device and complete the lockout log  Upon completion of the work, the Electrical Isolation Authority or his designee is the last person to remove his lock and tag
  • 14. MECHANICAL WORK Whenever work is scheduled on mechanical equipment or pressurized systems controlling devices such as:  circuit breakers  switches  valve handles  and other operating mechanisms shall be locked and tagged out to prevent their manipulation or operation
  • 15. MECHANICAL WORK (CONT’D)  Where possible the system shall be disconnected from all sources of pressure or hazardous substance  If appropriate on tanks and pressure vessels, the system shall be emptied, depressurized and blanked off before work starts  Appropriate gas tests shall be conducted
  • 16. TYPES OF LOCKOUT DEVICES  Plug Locks  Ball Valve Lockout  Gate Valve Lockout  Group Lockout Hasp  Electrical  Hydraulic, pneumatic, and other pressurized systems
  • 17. EMERGENCY REMOVAL OF EMPLOYEES LOCKOUT LOCK  Each lock-out / tag-out device shall be removed from each energy-isolating device by the employee who applied the device  The supervisor in charge of the work and the Electrical Isolation Authority shall complete an “emergency lock-out Device Removal” form and present it to the Construction Manager and the senior Safety Officer for an approval to remove the lock