1
LOCAL PROJECT
UPDATES
NELSON D. NELSON, P.E.
PUBLIC WORKS DIRECTOR
July 6, 2016
City Council Meeting
2
Traffic Signal Cabinet and TMC Communication Cabinet
Knocked Down at Sixth Street and Main Street
on June 22nd
3
TMC Communication Cabinet
still being restored at Sixth Street and Main Street
4
Foothill Parkway between I-15 and Teddy Bear Lane
Paving complete: Concrete, Striping, and Traffic Signal Modifications
through July 14th
5
6
SR-91 CLOSURES
2-WEEK LOOK AHEAD AT A GLANCE
7
SR-91 EB On-Ramp from Main Street
Open to Eastbound 91 Only
On-Ramp to I-15 anticipated in August
Westbound SR-91: 2-Week Look Ahead
Eastbound SR-91: 2-Week Look Ahead
10
LOCAL PROJECT UPDATES
CITY COUNCIL MEETING
July 6, 2016

Local projects update,

Editor's Notes

  • #3 A collision with the Traffic Control Cabinet and TMC Communication Cabinet disabled a significant portion of the City’s traffic signal communication network. This affected the traffic signal coordination and communication with the Animal Shelter.
  • #4 The signal cabinet has been fully repaired. The communication cabinet has been replaced, but the internal equipment still needs work and could be down for another 2 weeks. This will have minor impacts with signal coordination along Main Street and Sixth Street in the area. Staff is monitoring these locations until repairs are completed.
  • #5 The developer is completing the concrete, asphalt, striping and traffic signal modifications for this length of road over the next two weeks. The next phase of work from Teddy Bear Lane to California is being finalized to advertise for construction soon. The project is anticipated to be complete by November.
  • #6 Harrison Sewer Trunk Line starting next week. All work in roadway is scheduled for night work. Sidewalks and ramps during the day. Project scheduled to be complete the first part of September.
  • #8 Eastbound On-Ramp from Main Street open to EB 91 Only for now. Anticipate EB On-Ramp to I-15 to be open in August.
  • #9 The WB Off-Ramp to Main Street is scheduled to open on July 14th. Night closures of the WB On-Ramp from Main are scheduled through Saturday. The WB Off-Ramp to Lincoln is scheduled for short-term closures for the next several weeks. Sherman and Enterprise are closed nightly. The WB On-Ramp from Maple will be closed nightly this week along with the Maple Bridge. The WB Off-Ramp to Serfas Club will be closed until September. The WB On-Ramp from Green River is scheduled for nightly closures this week.
  • #10 The SB 71 to EB 91 Connector is closed nightly this week. The EB On-Ramp from Main Street will be closed nightly. Closure of the EB 91 at the 15 will continue to be closed nightly for the next several weeks. Ontario under the I-15 is also scheduled for nightly closures the next several weeks.