This Executive Summary of the final environmental
impact statement (final EIS) summarizes the
proposed Project, including the purpose of and need
for the Project, and the major conclusions and areas
of concern raised by agencies and the public.
The first of three installments of a report to the Maryland governor and legislature from an appointed committee of 13 members on the feasibility of Marcellus Shale gas drilling in the state. This first report covers revenue opportunities and liability issues--that is, ways to tax the industry, and ways to sue them.
Formal submission to the review of the draft Single State Planning Policy, the 7 sustainability principles and existing 12 sustainability policies. Innovative tools and co-design with community.
The Keystone XL Pipeline: What You Should KnowPeter Getty
Peter Getty provides a few facts about The Keystone XL Pipeline. Earlier today, President Obama vetoed a bill to continue work on the keystone pipeline. Getty includes information on the existing keystone pipeline as well as updates on what the future construction may look like if the bill does get passed.
Will the 9th U.N. secretary-general be a woman?Devex
In its 70 years of existence, the U.N. has never been led by a woman. But in 2016, as current Secretary-General Ban Ki-moon enters his last year in office, there’s clamor for change. Here are seven women to consider for secretary-general.
The first of three installments of a report to the Maryland governor and legislature from an appointed committee of 13 members on the feasibility of Marcellus Shale gas drilling in the state. This first report covers revenue opportunities and liability issues--that is, ways to tax the industry, and ways to sue them.
Formal submission to the review of the draft Single State Planning Policy, the 7 sustainability principles and existing 12 sustainability policies. Innovative tools and co-design with community.
The Keystone XL Pipeline: What You Should KnowPeter Getty
Peter Getty provides a few facts about The Keystone XL Pipeline. Earlier today, President Obama vetoed a bill to continue work on the keystone pipeline. Getty includes information on the existing keystone pipeline as well as updates on what the future construction may look like if the bill does get passed.
Will the 9th U.N. secretary-general be a woman?Devex
In its 70 years of existence, the U.N. has never been led by a woman. But in 2016, as current Secretary-General Ban Ki-moon enters his last year in office, there’s clamor for change. Here are seven women to consider for secretary-general.
The ScottMadden Energy Industry Update, the twice-per-year report issued by energy consulting firm ScottMadden. This particular edition takes a close look at the natural gas industry--in particular how ever-increasing gas resources can find adequate infrastructure to make their way to market.
Wind Energy Siting Guidelines presented by RI Statewide Planning at the kick-off meeting of the Renewable Energy Siting Partnership (RESP) on September 15, 2011.
Geoengineering has been defined as: “the deliberate large-scale manipulation of the
planetary environment to counteract anthropogenic climate change.1” As Lord Rees,
chair of The Royal Society, wrote in the forward to the Society's 2009 report on geoengineering,
"The continuing rise in the atmospheric concentration of greenhouse gases, mainly caused by the burning of
fossil fuels, is driving changes in the Earth’s climate. The long-term consequences will be exceedingly
threatening, especially if nations continue ‘business as usual’ in the coming decades. Most nations now recognize
the need to shift to a low-carbon economy, and nothing should divert us from the main priority of reducing
global greenhouse gas emissions. But if such reductions achieve too little, too late, there will surely
be pressure to consider a ‘plan B’—to seek ways to counteract the climatic effects of greenhouse gas emissions
by ‘geoengineering’ … Far more detailed study would be needed before any method could even be
seriously considered for deployment on the requisite international scale. Moreover, it is already clear than
Fact-Based Regulation for Environmental Protection in Shale Gas DevelopmentMarcellus Drilling News
Study released in Feb 2012 by the Energy Institute at the University of Texas which looks at the science of hydraulic fracturing and a potential link between fracking and groundwater contamination. The study's conclusion: there is no link. Fracking itself does not contaminate groundwater. There are legitimate concerns about drilling, but those issues exist in conventional drilling--they are not specific to fracking.
THE NETL CARBON SEQUESTRATION NEWSLETTER: ANNUAL INDEX Cláudio Carneiro
SEPTEMBER 2010 – AUGUST 2011
This is a compilation of the past year’s monthly National Energy Technology Laboratory Carbon
Sequestration Newsletter. The newsletter is produced by the NETL to provide information on
activities and publications related to carbon sequestration. It covers domestic, international,
public sector, and private sector news. This compilation covers newsletters issued from
September 2010 to August 2011. It highlights the primary news and events that have taken
place in the carbon sequestration arena over the past year. Information that has become
outdated (e.g. conference dates, paper submittals, etc.) was removed.
To navigate this document please use the Bookmarks tab or the Acrobat search tool (Ctrl+F).
To subscribe to this newsletter, please visit:
http://www.netl.doe.gov/technologies/carbon_seq/refshelf/subscribe.html.
The Executive Summary of the draft Environmental Impact Statement (EIS) from the Federal Energy Regulatory Commission. It is a review of the potential impacts from building a 125-mile natural gas pipeline from Susquehanna County, PA north into central New York where it will connect with two interstate natural gas transmission pipelines, delivering up to 650,000 dekatherms of natural gas per day to New York and New England--something badly needed. The EIS says there will be negative effects on the environment--but that those effects can be mitigated to "less than significant levels" if certain things are done.
The ScottMadden Energy Industry Update, the twice-per-year report issued by energy consulting firm ScottMadden. This particular edition takes a close look at the natural gas industry--in particular how ever-increasing gas resources can find adequate infrastructure to make their way to market.
Wind Energy Siting Guidelines presented by RI Statewide Planning at the kick-off meeting of the Renewable Energy Siting Partnership (RESP) on September 15, 2011.
Geoengineering has been defined as: “the deliberate large-scale manipulation of the
planetary environment to counteract anthropogenic climate change.1” As Lord Rees,
chair of The Royal Society, wrote in the forward to the Society's 2009 report on geoengineering,
"The continuing rise in the atmospheric concentration of greenhouse gases, mainly caused by the burning of
fossil fuels, is driving changes in the Earth’s climate. The long-term consequences will be exceedingly
threatening, especially if nations continue ‘business as usual’ in the coming decades. Most nations now recognize
the need to shift to a low-carbon economy, and nothing should divert us from the main priority of reducing
global greenhouse gas emissions. But if such reductions achieve too little, too late, there will surely
be pressure to consider a ‘plan B’—to seek ways to counteract the climatic effects of greenhouse gas emissions
by ‘geoengineering’ … Far more detailed study would be needed before any method could even be
seriously considered for deployment on the requisite international scale. Moreover, it is already clear than
Fact-Based Regulation for Environmental Protection in Shale Gas DevelopmentMarcellus Drilling News
Study released in Feb 2012 by the Energy Institute at the University of Texas which looks at the science of hydraulic fracturing and a potential link between fracking and groundwater contamination. The study's conclusion: there is no link. Fracking itself does not contaminate groundwater. There are legitimate concerns about drilling, but those issues exist in conventional drilling--they are not specific to fracking.
THE NETL CARBON SEQUESTRATION NEWSLETTER: ANNUAL INDEX Cláudio Carneiro
SEPTEMBER 2010 – AUGUST 2011
This is a compilation of the past year’s monthly National Energy Technology Laboratory Carbon
Sequestration Newsletter. The newsletter is produced by the NETL to provide information on
activities and publications related to carbon sequestration. It covers domestic, international,
public sector, and private sector news. This compilation covers newsletters issued from
September 2010 to August 2011. It highlights the primary news and events that have taken
place in the carbon sequestration arena over the past year. Information that has become
outdated (e.g. conference dates, paper submittals, etc.) was removed.
To navigate this document please use the Bookmarks tab or the Acrobat search tool (Ctrl+F).
To subscribe to this newsletter, please visit:
http://www.netl.doe.gov/technologies/carbon_seq/refshelf/subscribe.html.
The Executive Summary of the draft Environmental Impact Statement (EIS) from the Federal Energy Regulatory Commission. It is a review of the potential impacts from building a 125-mile natural gas pipeline from Susquehanna County, PA north into central New York where it will connect with two interstate natural gas transmission pipelines, delivering up to 650,000 dekatherms of natural gas per day to New York and New England--something badly needed. The EIS says there will be negative effects on the environment--but that those effects can be mitigated to "less than significant levels" if certain things are done.
Presentation by Joe Kiely, Vice President of Operations at Ports-to-Plains Alliance at Northern Ports-to-Plains Work Group Meeting in Wainwright, AB on June 21, 2013
Energy Development Impact on Transportation Infrastructure presented by TxDOT at Ports-to-Plains Alliance Annual Meeting in Washington DC on April 26, 2013.
Wind Energy's Future and the Impact on U.S. Manufacturing presentation at Ports-to-Plains Alliance Energy Conference in Washington DC on April 26, 2013.
Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...Ports-To-Plains Blog
Fuels Policy, Ethanol and RFS Reform
Political and Policy Implications on Gasoline Prices.
Presented at Ports-to-Plains Alliance Energy Conference, Washington Dc on April 26, 2013
Dear Governor Heineman:
Thank you for approving the new route for the Keystone XL Pipeline. The project will allow America to gain independence from Middle East and Venezuelan oil by increasing supplies from our loyal, stable and secure ally in Canada. It will also be a major economic development booster for our country and region, not only in the construction of the pipeline, but in further development of Alberta’s oil resources. For every two Canadian jobs created by the oil sands, a third is created in the US. Alberta oil sands development is projected to generate more than $500 billion in US economic impact over the next 25 years.
Letter supporting the Findings of nebraska Department of Environmental Quality for the Keystone XL Pipeline Evaluation by 125 elected officials and community leaders in the Ports-to-Plains region.
Jack Schenendorf, Ports-to-Plains Alliance Transportation Consultant, in Washington will address the following topics:
The 2012 elections, the politics of 113th Congress, and the new leaders handling transportation.
Fiscal cliff: how bad is it and what is likely to happen?
Transportation's fiscal cliff: what are we going to do about it?
MAP-21 implementation and reauthorization in 113th Congress.
Jack Schenendorf’s practice concentrates on transportation and legislation with a particular focus on legislative strategy, legislative procedure, and the federal budget process. For nearly 25 years, Mr. Schenendorf served on the staff of the Committee on Transportation and Infrastructure of the U.S. House of Representatives. He was Chief of Staff from 1995 to 2001.
Jack represents the Ports-to-Plains Alliance in Washington, DC. In addition he has represented Associated General Contractors, American Association of State Highway and Transportation Officials, Association of Equipment Manufactures, United Airlines and others
The international trade data comes from Bureau of Transportation Statistics North American Transborder Freight Data (http://www.bts.gov/programs/international/transborder/TBDR_QA.html). domestic data is from the Freight Analysis Framework by Center for Transportation Analysis in the Oak Ridge National Laboratory under funding from the Federal Highway Administration (http://faf.ornl.gov/fafweb/Extraction2.aspx).
Comments on Interim Guidance on State Freight Plans and State Advisory Commit...Ports-To-Plains Blog
The U.S. Department of Transportation (DOT) requested comments related to the interim guidance on state freight plans and state advisory committees. In response to the Notice, the Ports-to-Plains Alliance respectfully submitted these comments.
Interim Guidance on State Freight Plans and State Freight Advisory CommitteesPorts-To-Plains Blog
DEPARTMENT OF TRANSPORTATION
Office of the Secretary of Transportation
Interim Guidance on State Freight Plans and State Freight Advisory Committees
Federal Register / Vol. 77, No. 199 / Monday, October 15, 2012 / Notices
Statement on TBD Colorado Recommendations on Transportation
Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012Ports-To-Plains Blog
Members of the Ports-to-Plains Alliance, organizations and individuals from North Dakota, Montana, Alberta and Saskatchewan met in Regina on October 10 and 11, 2012 to develop a northern plan to enhance the Ports-to-Plains Corridor.
The international trade data comes from Bureau of Transportation Statistics North American Transborder Freight Data (http://www.bts.gov/programs/international/transborder/TBDR_QA.html). domestic data is from the Freight Analysis Framework by Center for Transportation Analysis in the Oak Ridge National Laboratory under funding from the Federal Highway Administration (http://faf.ornl.gov/fafweb/Extraction2.aspx).
Welocme to ViralQR, your best QR code generator.ViralQR
Welcome to ViralQR, your best QR code generator available on the market!
At ViralQR, we design static and dynamic QR codes. Our mission is to make business operations easier and customer engagement more powerful through the use of QR technology. Be it a small-scale business or a huge enterprise, our easy-to-use platform provides multiple choices that can be tailored according to your company's branding and marketing strategies.
Our Vision
We are here to make the process of creating QR codes easy and smooth, thus enhancing customer interaction and making business more fluid. We very strongly believe in the ability of QR codes to change the world for businesses in their interaction with customers and are set on making that technology accessible and usable far and wide.
Our Achievements
Ever since its inception, we have successfully served many clients by offering QR codes in their marketing, service delivery, and collection of feedback across various industries. Our platform has been recognized for its ease of use and amazing features, which helped a business to make QR codes.
Our Services
At ViralQR, here is a comprehensive suite of services that caters to your very needs:
Static QR Codes: Create free static QR codes. These QR codes are able to store significant information such as URLs, vCards, plain text, emails and SMS, Wi-Fi credentials, and Bitcoin addresses.
Dynamic QR codes: These also have all the advanced features but are subscription-based. They can directly link to PDF files, images, micro-landing pages, social accounts, review forms, business pages, and applications. In addition, they can be branded with CTAs, frames, patterns, colors, and logos to enhance your branding.
Pricing and Packages
Additionally, there is a 14-day free offer to ViralQR, which is an exceptional opportunity for new users to take a feel of this platform. One can easily subscribe from there and experience the full dynamic of using QR codes. The subscription plans are not only meant for business; they are priced very flexibly so that literally every business could afford to benefit from our service.
Why choose us?
ViralQR will provide services for marketing, advertising, catering, retail, and the like. The QR codes can be posted on fliers, packaging, merchandise, and banners, as well as to substitute for cash and cards in a restaurant or coffee shop. With QR codes integrated into your business, improve customer engagement and streamline operations.
Comprehensive Analytics
Subscribers of ViralQR receive detailed analytics and tracking tools in light of having a view of the core values of QR code performance. Our analytics dashboard shows aggregate views and unique views, as well as detailed information about each impression, including time, device, browser, and estimated location by city and country.
So, thank you for choosing ViralQR; we have an offer of nothing but the best in terms of QR code services to meet business diversity!
Elevating Tactical DDD Patterns Through Object CalisthenicsDorra BARTAGUIZ
After immersing yourself in the blue book and its red counterpart, attending DDD-focused conferences, and applying tactical patterns, you're left with a crucial question: How do I ensure my design is effective? Tactical patterns within Domain-Driven Design (DDD) serve as guiding principles for creating clear and manageable domain models. However, achieving success with these patterns requires additional guidance. Interestingly, we've observed that a set of constraints initially designed for training purposes remarkably aligns with effective pattern implementation, offering a more ‘mechanical’ approach. Let's explore together how Object Calisthenics can elevate the design of your tactical DDD patterns, offering concrete help for those venturing into DDD for the first time!
PHP Frameworks: I want to break free (IPC Berlin 2024)Ralf Eggert
In this presentation, we examine the challenges and limitations of relying too heavily on PHP frameworks in web development. We discuss the history of PHP and its frameworks to understand how this dependence has evolved. The focus will be on providing concrete tips and strategies to reduce reliance on these frameworks, based on real-world examples and practical considerations. The goal is to equip developers with the skills and knowledge to create more flexible and future-proof web applications. We'll explore the importance of maintaining autonomy in a rapidly changing tech landscape and how to make informed decisions in PHP development.
This talk is aimed at encouraging a more independent approach to using PHP frameworks, moving towards a more flexible and future-proof approach to PHP development.
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...UiPathCommunity
💥 Speed, accuracy, and scaling – discover the superpowers of GenAI in action with UiPath Document Understanding and Communications Mining™:
See how to accelerate model training and optimize model performance with active learning
Learn about the latest enhancements to out-of-the-box document processing – with little to no training required
Get an exclusive demo of the new family of UiPath LLMs – GenAI models specialized for processing different types of documents and messages
This is a hands-on session specifically designed for automation developers and AI enthusiasts seeking to enhance their knowledge in leveraging the latest intelligent document processing capabilities offered by UiPath.
Speakers:
👨🏫 Andras Palfi, Senior Product Manager, UiPath
👩🏫 Lenka Dulovicova, Product Program Manager, UiPath
UiPath Test Automation using UiPath Test Suite series, part 3DianaGray10
Welcome to UiPath Test Automation using UiPath Test Suite series part 3. In this session, we will cover desktop automation along with UI automation.
Topics covered:
UI automation Introduction,
UI automation Sample
Desktop automation flow
Pradeep Chinnala, Senior Consultant Automation Developer @WonderBotz and UiPath MVP
Deepak Rai, Automation Practice Lead, Boundaryless Group and UiPath MVP
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionAggregage
Join Maher Hanafi, VP of Engineering at Betterworks, in this new session where he'll share a practical framework to transform Gen AI prototypes into impactful products! He'll delve into the complexities of data collection and management, model selection and optimization, and ensuring security, scalability, and responsible use.
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfPaige Cruz
Monitoring and observability aren’t traditionally found in software curriculums and many of us cobble this knowledge together from whatever vendor or ecosystem we were first introduced to and whatever is a part of your current company’s observability stack.
While the dev and ops silo continues to crumble….many organizations still relegate monitoring & observability as the purview of ops, infra and SRE teams. This is a mistake - achieving a highly observable system requires collaboration up and down the stack.
I, a former op, would like to extend an invitation to all application developers to join the observability party will share these foundational concepts to build on:
Epistemic Interaction - tuning interfaces to provide information for AI supportAlan Dix
Paper presented at SYNERGY workshop at AVI 2024, Genoa, Italy. 3rd June 2024
https://alandix.com/academic/papers/synergy2024-epistemic/
As machine learning integrates deeper into human-computer interactions, the concept of epistemic interaction emerges, aiming to refine these interactions to enhance system adaptability. This approach encourages minor, intentional adjustments in user behaviour to enrich the data available for system learning. This paper introduces epistemic interaction within the context of human-system communication, illustrating how deliberate interaction design can improve system understanding and adaptation. Through concrete examples, we demonstrate the potential of epistemic interaction to significantly advance human-computer interaction by leveraging intuitive human communication strategies to inform system design and functionality, offering a novel pathway for enriching user-system engagements.
State of ICS and IoT Cyber Threat Landscape Report 2024 previewPrayukth K V
The IoT and OT threat landscape report has been prepared by the Threat Research Team at Sectrio using data from Sectrio, cyber threat intelligence farming facilities spread across over 85 cities around the world. In addition, Sectrio also runs AI-based advanced threat and payload engagement facilities that serve as sinks to attract and engage sophisticated threat actors, and newer malware including new variants and latent threats that are at an earlier stage of development.
The latest edition of the OT/ICS and IoT security Threat Landscape Report 2024 also covers:
State of global ICS asset and network exposure
Sectoral targets and attacks as well as the cost of ransom
Global APT activity, AI usage, actor and tactic profiles, and implications
Rise in volumes of AI-powered cyberattacks
Major cyber events in 2024
Malware and malicious payload trends
Cyberattack types and targets
Vulnerability exploit attempts on CVEs
Attacks on counties – USA
Expansion of bot farms – how, where, and why
In-depth analysis of the cyber threat landscape across North America, South America, Europe, APAC, and the Middle East
Why are attacks on smart factories rising?
Cyber risk predictions
Axis of attacks – Europe
Systemic attacks in the Middle East
Download the full report from here:
https://sectrio.com/resources/ot-threat-landscape-reports/sectrio-releases-ot-ics-and-iot-security-threat-landscape-report-2024/
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
Keystone XL Pipeline Final EIS Executive Summary
1. EXECUTIVE SUMMARY
Final Environmental Impact Statement
for the Proposed Keystone XL Project
August 26, 2011
g
United States Department of State
Bureau of Oceans and International
Environmental and Scientific Affairs
2. Keystone XL Project Executive Summary − Final EIS
Table of Contents
INTRODUCTION.................................................................................................................................................. ES-1
PRESIDENTIAL PERMITTING PROCESS .......................................................................................................... ES-1
SUMMARY OF THE KEYSTONE XL PROJECT .................................................................................................. ES-1
Transport of Canadian Oil Sands Crude Oil ..................................................................................................... ES-2
Transport of U.S. Crude Oil .............................................................................................................................. ES-3
Other Connected Actions ................................................................................................................................. ES-3
PURPOSE OF AND NEED FOR THE KEYSTONE XL PROJECT ........................................................................ ES-5
PROJECT DESIGN AND SAFETY .......................................................................................................................ES-6
Pipe Design and Manufacturing ....................................................................................................................... ES-7
System Design, Construction and Testing ....................................................................................................... ES-7
Operations, Maintenance, and Monitoring........................................................................................................ ES-7
Reporting, Record Keeping, and Certification .................................................................................................. ES-7
SPILL POTENTIAL AND RESPONSE .................................................................................................................. ES-8
Estimated Frequency of Spills .......................................................................................................................... ES-8
Spills from the Existing Keystone Oil Pipeline System ..................................................................................... ES-8
Maximum Spill Volume ..................................................................................................................................... ES-9
Emergency Planning ........................................................................................................................................ ES-9
Local Emergency Planning Committees (LEPCs) ............................................................................................ ES-9
POTENTIAL ENVIRONMENTAL IMPACTS OF OIL SPILLS ................................................................................ ES-9
General Types of Potential Impacts ................................................................................................................. ES-9
Potential Impacts to the Ogallala Aquifer and other Groundwater Areas ....................................................... ES-10
Potential Environmental Justice Concerns ..................................................................................................... ES-10
ALTERNATIVES CONSIDERED........................................................................................................................ ES-10
No Action Alternative ...................................................................................................................................... ES-11
System Alternatives ....................................................................................................................................... ES-11
Major Route Alternatives ................................................................................................................................ ES-12
Route Variations and Minor Realignments ..................................................................................................... ES-12
Other Alternatives Considered ....................................................................................................................... ES-14
Agency Preferred Alternative ......................................................................................................................... ES-14
ENVIRONMENTAL ANALYSES......................................................................................................................... ES-14
Environmental Justice .................................................................................................................................... ES-14
Greenhouse Gas Emissions........................................................................................................................... ES-15
Geology and Soils .......................................................................................................................................... ES-15
Water Resources ........................................................................................................................................... ES-16
Wetlands ........................................................................................................................................................ ES-16
Terrestrial Vegetation ..................................................................................................................................... ES-18
Wildlife............................................................................................................................................................ ES-18
Fisheries Resources ...................................................................................................................................... ES-19
Threatened and Endangered Species ............................................................................................................ ES-20
Cultural Resources ......................................................................................................................................... ES-20
Air Quality and Noise ..................................................................................................................................... ES-21
Land Use, Recreation, and Visual Resources ................................................................................................ ES-21
Socioeconomics ............................................................................................................................................. ES-22
Cumulative Impacts ........................................................................................................................................ ES-22
Environmental Impacts in Canada ................................................................................................................. ES-22
EIS CONTENTS..................................................................................................................................................... ES-24
ES-i
3. Keystone XL Project Executive Summary − Final EIS
This page intentionally left blank.
4. Keystone XL Project Executive Summary − Final EIS
INTRODUCTION with expertise in key areas of concern related to the
proposed Project.
In September 2008, TransCanada Keystone Pipeline,
LP (Keystone) filed an application for a Presidential The determination of national interest involves
Permit with the U.S. Department of State (DOS) to consideration of many factors, including energy
build and operate the Keystone XL Project. The security; environmental, cultural, and economic
proposed Project would have the capacity to transport impacts; foreign policy; and compliance with relevant
700,000 barrels per day (bpd) of crude oil to delivery federal regulations. Before making a decision, DOS
points in Oklahoma and southeastern Texas. will consult with the eight federal agencies identified
in Executive Order 13337: the Departments of
This Executive Summary of the final environmental Energy, Defense, Transportation, Homeland Security,
impact statement (final EIS) summarizes the Justice, Interior, and Commerce, and the
proposed Project, including the purpose of and need
Environmental Protection Agency (EPA). DOS will
for the Project, and the major conclusions and areas also solicit public input on the national interest
of concern raised by agencies and the public. More determination by accepting written comments and
detailed information on the proposed Project,
holding comment meetings in the six
alternatives to the proposed Project, states traversed by the proposed
Aboveground Facilities
and the associated potential route and in Washington, D.C.
environmental impacts is presented in 30 pump stations on 5- to15-acre
the final EIS that is provided in the CD sites Figure ES-1 lists the major events,
Delivery facilities at Cushing, public outreach activities, and other
in the sleeve on the back page. Oklahoma and Nederland and
Moore Junction, Texas details of the environmental review
PRESIDENTIAL PERMITTING Densitometer sites located at all and national interest determination
PROCESS injection points and at all delivery processes.
points
All facilities which cross the 112 mainline valves along pipeline SUMMARY OF THE KEYSTONE
international borders of the United and 2 mainline valves at each
pump station XL PROJECT
States require a Presidential Permit.
Tank farm at Cushing, Oklahoma
For liquid hydrocarbon pipelines, the on a 74-acre site
The proposed Keystone XL Project
President, through Executive Order consists of a crude oil pipeline and
See Section 2.2 for further related facilities that would primarily
13337, directs the Secretary of State to information on aboveground facilities.
decide whether a project is in the be used to transport Western
national interest before granting a Presidential Permit. Canadian Sedimentary Basin crude
oil from an oil supply hub near Hardisty, Alberta,
As part of the Presidential Permit review process, Canada to delivery points in Oklahoma and Texas.
DOS determined that it should prepare an EIS The proposed Project would also be capable of
consistent with the National Environmental Policy Act
transporting U.S. crude oil to those delivery points.
(NEPA). DOS is the lead federal agency for the The U.S. portion of the pipeline would begin near
NEPA environmental review of the Proposed Project Morgan, Montana at the international border of the
because the need for a Presidential Permit is the
United States and extend to delivery points in
most substantial federal decision related to the Nederland and Moore Junction, Texas. There would
Proposed Project. To assist in preparing the EIS, also be a delivery point at Cushing, Oklahoma.
DOS retained an environmental consulting firm,
These three delivery points would provide access to
Cardno ENTRIX, following DOS guidelines on third- many other U.S. pipeline systems and terminals,
party contracts. The DOS environmental and safety including pipelines to refineries in the U.S. Gulf Coast
review of the proposed Project that lead to the final region. Market conditions, not the operator of the
EIS was conducted for nearly 3 years and included pipeline, would determine the refining locations of the
consultations with the third-party contractor,
crude oil.
cooperating agencies, and scientists and engineers
ES-1
5. Keystone XL Project Executive Summary − Final EIS
Figure ES-1
U.S. Department of State Environmental and National Interest Determination Review Processes
The proposed Keystone XL pipeline would consist of the bitumen to a point where it liquefies and can be
approximately 1,711 miles of new 36-inch-diameter pumped to the surface.
pipeline, with approximately 327 miles of pipeline in
Bitumen is treated in several ways to create crude oil
Canada and 1,384 miles in the U.S. Figure ES-3
suitable for transport by pipeline and refining. The
depicts the three segments of the proposed Project in
types of Canadian crude oil that would be transported
the U.S. As noted in that illustration, the proposed
by the proposed Project would primarily consist of
Project would connect to the northern and southern
synthetic crude oil and diluted bitumen.
ends of the existing Cushing Extension of the
Keystone Oil Pipeline System. Synthetic crude oil is produced from bitumen using
refining methods – a process termed upgrading – that
Figure ES-4 illustrates the construction sequence that
in general converts bitumen into lighter liquid
would be followed for the proposed Project. The
hydrocarbons. In other words, the bitumen is
proposed Project would also include 30 electrically
converted into a crude oil similar to conventional
operated pump stations, 112 mainline valves, 50
crude oil.
permanent access roads, and a new oil storage
facility in Cushing, Oklahoma. If market conditions Figure ES-2
change, the capacity of the proposed Project could be 36-Inch-Diameter Crude Oil Pipe
increased to 830,000 bpd by increasing pumping
capacity at the proposed pump stations.
The overall proposed Keystone XL Project is
estimated to cost $7 billion. If permitted, it would
begin operation in 2013, with the actual date
dependant on the necessary permits, approvals, and
authorizations.
Transport of Canadian Oil Sands Crude Oil
The proposed Keystone XL Project would primarily
transport crude oil extracted from the oil sands areas
in Alberta, Canada. Oil sands (which are also
referred to as tar sands) are a combination of clay,
sand, water, and bitumen, which is a material similar
to soft asphalt. Bitumen is extracted from the ground
by mining or by injecting steam underground to heat
ES-2
6. Keystone XL Project Executive Summary − Final EIS
Figure ES-1 (Cont.)
U.S. Department of State Environmental and National Interest Determination Review Processes
Diluted bitumen – often termed dilbit – consists of These fields have experienced high growth in the last
bitumen mixed with a diluent, which is a light few years as new technology has allowed the oil to be
hydrocarbon liquid such as natural gas condensate or profitably extracted. Keystone currently has long-
refinery naphtha. The bitumen is diluted to reduce its term commitments for transporting 65,000 bpd of
viscosity so that it is in a more liquid form that can be crude oil in the proposed Keystone XL Project from
transported via pipeline. Dilbit is also processed to the Bakken Marketlink Project.
remove sand, water, and other impurities. The
The Cushing Marketlink Project would allow transport
diluents in dilbit are integrally combined with the
of up to 150,000 bpd on the proposed Project from
bitumen to form a crude oil that is a homogenous
the Cushing, Oklahoma area to the proposed
mixture that does not physically separate when
Keystone XL Project delivery points in Texas.
released.
Both synthetic crude oil and dilbit are Pipe Specifications Other Connected Actions
similar in composition and quality to the • Material: High-strength X70 In addition to the Marketlink projects,
crude oils currently transported in steel pipe, API 5L
there are two other types of connected
pipelines in the U.S. and being refined • Outside diameter: 36 inches
• Operating Pressure: 1,308 psig actions associated with the proposed
in Gulf Coast refineries. Neither type of Project: electrical distribution lines and
• External Coating: fusion-bonded
crude oil requires heating for transport epoxy substations that would provide power
in pipelines. for the pump stations, and an electrical
See Section 2.3.1 for further
information on pipe specifications. transmission line that would be required
Transport of U.S. Crude Oil
to ensure transmission system reliability
In late 2010, Keystone Marketlink, LLC announced when the proposed Project is operating at maximum
plans for two separate projects that would enable capacity. Those projects would not be built or
crude oil from domestic sources to be transported in operated by Keystone, and the permit applications for
the proposed Keystone XL Project. Those two those projects would be reviewed and acted on by
projects, the Bakken Marketlink Project and the other agencies. Although only limited information was
Cushing Marketlink Project, are considered available on the design, construction, and operation
“connected actions” under NEPA. The Bakken of the projects, DOS assessed the potential impacts
Marketlink Project would allow transport of up to of the projects based on currently available
100,000 bpd of crude oil from the Bakken formation in information.
the Williston Basin in Montana and North Dakota.
ES-3
7. Keystone XL Project Executive Summary − Final EIS
Figure ES-3
Proposed Pipeline Route
ES-4
8. Keystone XL Project Executive Summary − Final EIS
Figure ES-4
Typical Pipeline Construction Sequence
PURPOSE OF AND NEED FOR THE Cushing, Oklahoma in the existing Keystone Oil
KEYSTONE XL PROJECT Pipeline Project. If the proposed Project is approved
and implemented, Keystone would transfer shipment
The primary purpose of the proposed Project is to of crude oil under those contracts to the proposed
provide the infrastructure necessary to transport Project. Although there is sufficient pipeline capacity
Western Canadian Sedimentary Basin heavy crude from Canada to the U.S. in general to accommodate
oil from the U.S. border with Canada to delivery projected additional imports of Canadian crude in the
points in Texas in response to the market demand of short to medium term, there is extremely limited
Gulf Coast refineries for heavy crude oil. This market pipeline transport capacity to move such crude oils to
demand is driven by the need of the refiners to Gulf Coast refineries.
replace declining feed stocks of heavy crude oil
obtained from other foreign sources with crude oil The 58 refineries in the Gulf Coast District provide a
from a more stable and reliable source. Keystone total refining capacity of approximately 8.4 million
currently has firm, long-term contracts to transport bpd, or nearly half of U.S. refining capacity. These
380,000 bpd of Canadian crude oil to the Texas refineries provide substantial volumes of refined
delivery points. petroleum product, such as gasoline and jet fuel, via
pipeline to the Gulf Coast region as well as the East
An additional purpose of the proposed Project is to Coast and the Midwest.
transport Canadian heavy crude oil to the proposed
Cushing tank farm in response to the market demand In 2009, Gulf Coast refineries imported approximately
of refineries in the central and Midwest U.S. for heavy 5.1 million bpd of crude oil from more than 40
crude oil. Keystone also has firm contracts to countries. The top four suppliers were Mexico,
transport 155,000 bpd of Canadian crude oil to Venezuela, Saudi Arabia, and Nigeria. Of the total
ES-5
9. Keystone XL Project Executive Summary − Final EIS
volume imported, approximately 2.9 million bpd was been incorporated into the Special Permit. However,
heavy crude oil similar to the crude oil that would be in August 2010, Keystone withdrew its application to
transported by the proposed Project; Mexico and PHMSA for a Special Permit. However, to enhance
Venezuela were the major suppliers. However, the overall safety of the proposed Project, DOS and
imports of heavy crude oil from these two countries PHMSA continued working on Special Conditions
have been in steady decline while Gulf Coast refining specific to the proposed Project and ultimately
capacity is projected to grow by at least 500,000 bpd established 57 Project-specific Special Conditions.
by 2020, with or without the proposed Project. As a result, Keystone agreed to design, construct,
operate, maintain, and monitor the proposed Project
PROJECT DESIGN AND SAFETY in accordance with the more stringent 57 Project-
specific Special Conditions in addition to complying
The Pipeline and Hazardous Materials Safety
with the existing PHMSA regulatory requirements.
Administration (PHMSA), a federal agency within the
U.S. Department of Transportation, is the primary In consultation with PHMSA, DOS determined that
federal regulatory agency responsible for ensuring the incorporation of the Special Conditions would result in
safety of America's energy pipelines, including crude a Project that would have a degree of safety greater
oil pipeline systems. As a part of that responsibility, than any typically constructed domestic oil pipeline
PHMSA established regulatory requirements for the system under current regulations and a degree of
construction, operation, maintenance, monitoring, safety along the entire length of the pipeline system
inspection, and repair of hazardous liquid pipeline that would be similar to that required in high
systems. consequence areas as defined in the regulations.
Key aspects of the Special Conditions are
In 2009, Keystone applied to PHMSA for a Special
summarized below. Appendix U of the EIS presents
Permit to operate the proposed Project at a slightly
the Special Conditions and a comparison of the
higher pressure than allowed under the existing
conditions with the existing regulatory requirements.
regulations. DOS worked with PHMSA to develop
Project-specific Special Conditions that would have
Figure ES-5
Pipeline Cross-section
ES-6
10. Keystone XL Project Executive Summary − Final EIS
Pipe Design and Manufacturing Figure ES-6
Smart Pig
The first nine Special Conditions present design
standards to be used in manufacturing the pipe and
requirements for pipe materials, pipe inspections at
the mill and in the field, performance tests, and quality
control procedures.
System Design, Construction and Testing
Conditions 10 through 23 address design and
construction of the proposed Project, including testing
of Project components. Those Conditions present
requirements for aspects of the proposed Project
such as field coatings, depth of cover over the
pipeline, temperature and overpressure control,
welding procedures, and testing prior to operations.
Testing requirements include hydrostatic testing, a Pipeline pressure is the primary indicator used by the
process which involves filling the line with water and SCADA system to detect an oil spill. If the monitoring
increasing the pressure within the pipeline to test the system identifies a pressure change in the pipeline,
pipeline’s ability to withstand pressure. If the test the controller would evaluate the data to determine if
water pressure drops, further testing must be it is a false alarm or an actual spill. Using pipeline
conducted and reported to PHMSA, and faulty pressure allows the operator to detect leaks down to
pipeline sections must be repaired or replaced. approximately 1.5 to 2 percent of pipeline flow rate.
Operations could not begin until the entire system has
passed the required hydrostatic testing. The proposed Project would also include a computer-
based system that does not rely on pipeline pressure
Operations, Maintenance, and Monitoring to assist in identifying leaks below the 1.5 to 2 percent
detection thresholds.
Conditions 24 through 49 present the requirements
for the Supervisory Control and Data Acquisition In addition to computer monitoring, there would be
(SCADA) system that would be used to remotely scheduled patrols of the pipeline right-of-way as well
monitor and control the pipeline, as well as as public and landowner awareness programs.
requirements for internal corrosion inspection, Communities along the pipeline would be given
cathodic protection, identification of the location of the information to facilitate the reporting of suspected
pipeline with aboveground markers, internal pipeline leaks and events that could suggest a threat to
inspections using electronic sensing devices termed pipeline safety.
“smart pigs,” visual monitoring of the pipeline corridor,
and repair procedures. The SCADA system would Reporting, Record Keeping, and Certification
alert the Operations Control Center of an abnormal The final eight conditions present requirements for
operating condition, indicating a possible release of maintaining detailed records, development a right-of-
oil. The system would include automatic features that way management plan, reporting to PHMSA, and
would ensure operation within prescribed pressure providing PHMSA with certification from a senior
limits. There would also be a complete backup officer of Keystone that it has complied with the
system. Special Conditions.
ES-7
11. Keystone XL Project Executive Summary − Final EIS
SPILL POTENTIAL AND RESPONSE Center (NRC) database for releases and spills of
hazardous substances and oil.
Spills could result from many causes, including
corrosion (external or internal), excavation equipment, Based on those data, DOS calculated that there could
defects in materials or in construction, over- be from 1.18 to 1.83 spills greater than 2,100 gallons
pressuring the pipeline, and geologic hazards, such per year for the entire Project. The estimated
as ground movement, washouts, and flooding. frequency of spills of any size ranged from 1.78 to
Although the leak detection system would be in place, 2.51 spills per year.
some leaks might not be detected by the system. For
example, a pinhole leak could be undetected for days Keystone submitted a risk analysis that also included
or a few weeks if the release volume rate were small an estimate of the frequency of spills over the life of
and in a remote area. the proposed Project. Keystone’s analysis was for
the pipeline only and did not include releases from
In most cases the oil from a small leak would likely pump stations, valve stations, or the tank farm.
remain within or near the pipeline trench where it
could be contained and cleaned up after discovery. Keystone initially calculated a spill frequency of 1.38
As a result, for most small leaks it is likely that the oil spills per year based only on the historical PHMSA
would be detected before a substantial volume of oil spill incident database available in 2008 when the
reaches the surface and affects the environment. application was submitted. Keystone also calculated
Spills may be identified during regular pipeline aerial a Project-specific spill frequency for the pipeline that
inspections, by ground patrols and maintenance staff, considered the specific terrain and environmental
or by landowners or passersby in the vicinity of the conditions along the proposed Project corridor,
spill. required regulatory controls, depth of cover, strength
of materials, and technological advances in the
For larger spills, the released oil would likely migrate design of the proposed Project. Using those factors,
from the release site. However, DOS analysis of Keystone estimated that there could be 0.22 spills per
previous large pipeline oil spills suggests that the year from the pipeline.
depth and distance that the oil would migrate would
likely be limited unless it reaches an active river, Spills from the Existing Keystone Oil Pipeline
stream, a steeply sloped area, or another migration System
pathway such as a drainage ditch.
The existing Keystone Oil Pipeline System has
Estimated Frequency of Spills experienced 14 spills since it began operation in June
2010. The spills occurred at fittings and seals at
In spite of the safety measures included in the design, pump or valve stations and did not involve the actual
construction, and operation of the proposed Project, pipeline. Twelve of the spills remained entirely within
spills are likely to occur during operation over the the confines of the pump and valve stations. Of
lifetime of the proposed Project. Crude oil could be those spills, 7 were 10 gallons or less, 4 were 100
released from the pipeline, pump stations, or valve gallons or less, 2 were between 400 and 500 gallons,
stations. and 1 was 21,000 gallons.
Although a large spill could occur at the proposed The spill of 21,000 gallons occurred when a fitting
Cushing tank farm, each of the three 350,000-barrel failed at the Ludden, North Dakota pump station. As
tanks would be surrounded by a secondary a result, PHMSA issued a Corrective Action Order,
containment berm that would hold 110 percent of the halting pipeline operation. Keystone was required to
contents of the tank plus freeboard for precipitation. consult with PHMSA before returning the pipeline to
Therefore, there would have to be a concurrent failure operation. In that incident, most of the oil was
of the secondary containment berm for a tank-farm contained within the pump station, but 210 gallons
spill to reach the area outside of the tank. Such an discharged from the pump station to adjacent land.
event is considered unlikely. The land affected was treated in place in compliance
DOS calculated estimates of spill frequency and spill with North Dakota Department of Health land
volumes. Those estimates included potential spills treatment guidelines.
from the pipeline, pump stations, and valve stations.
The calculations used data from the PHMSA spill
incident database for hazardous liquid pipelines and
crude oil pipelines, and from the National Response
ES-8
12. Keystone XL Project Executive Summary − Final EIS
Maximum Spill Volume planning for low income and minority populations.
The LEPCs would participate in emergency response
Keystone conducted an assessment of the maximum
consistent with their authority under the Right-to-
potential pipeline spill volume from a complete
Know Act and as required by their local emergency
pipeline structural failure. Keystone estimated that
response plans.
the maximum spill volume would be approximately
2.8 million gallons, which would be possible along
less than 1.7 miles of the proposed pipeline route due
POTENTIAL ENVIRONMENTAL IMPACTS OF
to topographic conditions. For approximately 50 OIL SPILLS
percent of the proposed pipeline route (approximately Impacts from an oil spill would be affected by
842 miles), the maximum spill volume would be variables such as the weather, time of year, water
approximately 672,000 gallons. level, soil, local wildlife, and human activity. The
Figure ES-7 extent of impact would also depend on the response
Pump Station on the Existing Keystone Oil time and capabilities of the emergency response
Pipeline System team.
The greatest concern would be a spill in
environmentally sensitive areas, such as wetlands,
flowing streams and rivers, shallow groundwater
areas, areas near water intakes for drinking water or
for commercial/industrial uses, and areas with
populations of sensitive wildlife or plant species.
General Types of Potential Impacts
There are two primary types of impacts that occur
with a spill of crude oil – physical impacts and
toxicological impacts. Physical impacts typically
consist of the coating of soils, sediments, plants, and
animals. The coating of organisms can result in
effects such as preventing them from feeding or
Emergency Planning obtaining oxygen, reducing the insulating ability of fur
or feathers, and adding weight to the organism so that
As required by PHMSA regulations, Keystone must it cannot move naturally or maintain balance. In
submit an Emergency Response Plan and a Pipeline addition, oil may coat beaches along rivers or lakes
Spill Response Plan to PHMSA for review prior to and foul other human-use resources.
initiation of operation of the proposed Project. These
plans would not be completed until the final details of Toxicological impacts of an oil spill are a function of
the proposed Project are established in all applicable the chemical composition of the oil, the solubility of
permits. each class of compounds in the oil, and the sensitivity
of the area or organism exposed. Crude oil may be
If a leak is suspected, the Emergency Response Plan toxic when ingested. Ingestion typically occurs when
and Pipeline Spill Response Plan would be initiated. an oiled animal attempts to clean its fur or feathers.
After confirmation that a spill occurred, the operator Some of the possible toxic effects include direct
would shut down pumps and close the isolation mortality, interference with feeding or reproductive
valves, actions that would require approximately 12 capacity, disorientation, reduced resistance to
minutes. disease, tumors, reduction or loss of various sensory
perceptions, and interference with metabolic,
Local Emergency Planning Committees (LEPCs) biochemical, and genetic processes.
LEPCs were established as a part of the Emergency Birds typically are the most affected wildlife due to an
Planning and Community Right-to-Know Act. oil spill. Oil on feathers causes hypothermia or
Keystone has committed to a communication program drowning due to the loss of flotation, and birds may
to reach out to LEPCs along the proposed pipeline suffer both acute and chronic toxicological effects. In
corridor during development of the Emergency addition, dead oiled birds may be scavenged by other
Response Plan and the Pipeline Spill Response Plan, animals.
with particular consideration given to emergency
ES-9
13. Keystone XL Project Executive Summary − Final EIS
Fish and aquatic invertebrates could also experience impacts are typically limited to several hundred feet or
toxic impacts of spilled oil. The potential impacts less from a spill site. An example of a crude oil
would generally be greater in standing water habitats release from a pipeline system into an environment
− such as wetlands, lakes and ponds − than in flowing similar to the Northern High Plains Aquifer system
rivers and creeks. occurred in 1979 near Bemidji, Minnesota.
Crude oil spills are not likely to have toxic effects on While the conditions at Bemidji are not fully
the general public because of the many restrictions analogous to the Sand Hills region, extensive studies
that local, state and federal agencies impose to avoid of the Bemidji spill suggest that impacts to shallow
environmental exposure after a spill. groundwater from a spill of a similar volume in the
Sand Hills region would affect a limited area of the
Potential Impacts to the Ogallala Aquifer and aquifer around the spill site. In no spill incident
other Groundwater Areas scenario would the entire Northern High Plains
DOS recognizes the public’s concern for the Northern Aquifer system be adversely affected.
High Plains Aquifer System, which includes the In addition to the Northern High Plains Aquifer
Ogallala aquifer formation and the Sand Hills aquifer system, there are other groundwater areas along the
unit. proposed route, including shallow or near-surface
The Northern High Plains Aquifer system supplies 78 aquifers. DOS in consultation with PHMSA and EPA
percent of the public water supply and 83 percent of determined that Keystone should commission an
irrigation water in Nebraska and approximately 30 independent consultant to review the Keystone risk
percent of water used in the U.S. for irrigation and assessment. The independent review will be
agriculture. Of particular concern is the part of the conducted by a firm approved by DOS in concurrence
aquifer which lies below the Sand Hills region. In that with PHMSA and EPA, and would focus on a review
region, the aquifer is at or near the surface. of valve placement and the possibility of deploying
external leak detection systems in areas of
DOS assessed the potential impacts of the proposed particularly sensitive environmental resources, but
Project on many aquifer systems. The aquifer would not be limited to those issues. The specific
analysis included the identification of potable scope of the analysis will be approved by DOS,
groundwater in water wells within 1 mile of the PHMSA, and EPA. DOS, with concurrence from
proposed centerline of the pipeline. More than 200 PHMSA and EPA, will determine the need for any
Public Water Supply wells, most of which are in additional mitigation measures resulting from the
Texas, are within 1 mile of the proposed centerline, analysis.
and 40 private water wells are within 100 feet of the
centerline. No sole-source aquifers, or aquifers Potential Environmental Justice Concerns
serving as the principal source of drinking water for
Low income and minority communities could be more
an area, are crossed by the proposed pipeline route.
vulnerable to health impacts than other communities
The potential for a crude oil spill to reach groundwater in the event of a spill, particularly if access to health
is related to the spill volume, the viscosity and density care is less available in the release area. Exposure
of the crude oil, the characteristics of the environment pathways could include direct contact with the crude
into which the crude oil is released (particularly the oil, inhalation of airborne contaminants, or
characteristics of the underlying soils), and the depth consumption of food or water contaminated by either
to groundwater. The depth to groundwater is less the crude oil or components of the crude oil.
than 10 feet for about 65 miles of the proposed route Keystone agreed to remediate spills, restore the
in Nebraska and there are other areas of shallow affected areas, and provide alternative water supplies
groundwater in each state along the proposed route. if a spill contaminates groundwater or surface water.
Diluted bitumen and synthetic crude oil, the two types Keystone also agreed to develop communications
of crude oil that would be transported by the proposed directed at bilingual communities, such as signage in
Project, would both initially float on water if spilled. both English and Spanish languages, and emergency
Over time, the lighter aromatic fractions of the crude communications in both languages.
oil would evaporate, and water-soluble components
could enter the groundwater. ALTERNATIVES CONSIDERED
Studies of oil spills from underground storage tanks DOS considered the following three major alternative
indicate that potential surface and groundwater scenarios:
ES-10
14. Keystone XL Project Executive Summary − Final EIS
No Action Alternative – potential scenarios that and reliable sources of crude oil, including the Middle
could occur if the proposed Project is not built and East, Africa, Mexico, and South America.
operated;
As a result of these considerations, DOS does not
System Alternatives − the use of other pipeline regard the No Action Alternative to be preferable to
systems or other methods of providing Canadian the proposed Project.
crude oil to the Cushing tank farm and the Gulf
Coast market; If the proposed Project is not implemented, Canadian
Major Route Alternatives − other potential pipeline producers would seek alternative transportation
routes for transporting heavy crude oil from the systems to move oil to markets other than the U.S.
U.S./Canada border to Cushing, Oklahoma and Several projects have been proposed to transport
the Gulf Coast market. crude oil out of using pipelines to Canadian ports.
Whether or not the proposed Project is implemented,
No Action Alternative
Canadian producers would seek alternative
Under the No Action Alternative, the potential adverse transportation systems to move oil to markets other
and positive impacts associated with building and than the U.S. Several projects have been proposed
operating the proposed Project would not occur. to transport crude oil out of the oil sands area of
However, there is an existing market demand for Alberta using pipelines to Canadian ports.
heavy crude oil in the Gulf Coast area. The demand
for crude oil in the Gulf Coast area is projected to System Alternatives
increase and refinery runs are projected to grow over
System alternatives would use combinations of
the next 10 years, even under a low demand outlook.
existing or expanded pipeline systems, pipeline
A report commissioned by the Department of Energy systems that have been proposed or announced, and
(DOE) indicated that whether the proposed Project is non-pipeline systems such as tank trucks, railroad
built or not is unlikely to impact the demand for heavy tank cars, and barges and marine tankers to transport
crude oil by the Gulf Coast refineries. Even if Canadian heavy crude oil to Gulf Coast refineries.
improved fuel efficiency and broader adoption of None of the pipeline systems considered would be
alternative fuels reduced overall demand for oil, capable of transporting Canadian crude oil to Gulf
demand for Canadian heavy crude oil at Gulf Coast Coast delivery points in the volumes required to meet
refineries would not be substantially affected. Keystone’s commitments for transporting 380,000
At the same time, three of the four countries that are bpd to delivery points in Texas. Therefore they would
major crude oil suppliers to Gulf Coast refineries not meet the purpose of the proposed Project. A
currently face declining or uncertain production combination of the pipeline systems considered
horizons. As a result, those refineries are expected to could, over time, deliver volumes of Canadian oil
obtain increased volumes of heavy crude oil from sands crude oil in volumes similar to the volumes that
alternative sources in both the near term and further would be transported by the proposed Project.
into the future. Implementation of the No Action However, that would not meet the near-term need for
Alternative would not meet this need. heavy crude oil at the Gulf Coast refineries.
Expanding the pipeline systems that were considered
If the proposed Project is not built and operated, Gulf to meet the purpose of the proposed Project or
Coast refineries could obtain Canadian crude oil construction of new components or a combination of
transported through other new pipelines or by rail or those systems would result in impacts similar to those
truck transport. Other pipeline projects have been of the proposed Project.
proposed to transport Canadian crude oil to the Gulf
Coast area, and both rail transport and barge The trucking alternative would add substantial
transport could be used to meet a portion of the need. congestion to highways in all states along the route
In addition, the Gulf Coast refineries could obtain selected, particularly at and near the border crossing
crude oil transported by marine tanker from areas and in the vicinity of the delivery points. At those
outside of North America. Many of the sources locations it is likely that there would be significant
outside of North America are in regions that are impacts to the existing transportation systems.
experiencing declining production or are not secure Trucking would also result in substantially higher
greenhouse gas emissions and a higher risk of
accidents than transport by pipeline.
ES-11
15. Keystone XL Project Executive Summary − Final EIS
Development of a rail system to transport the volume The Western Alternative was eliminated since it was
of crude oil that would be transported by the proposed financially impracticable. Although the other four
Project would likely produce less impact from route alternatives could have been eliminated based
construction than would the proposed Project on consideration of economical and technical
because it could be done using existing tracks. practicability and feasibility without further evaluation,
However, there would be greater safety concerns and they were nonetheless examined further with an
greater impacts during operation, including higher emphasis on groundwater resources. The I-90
energy use and greenhouse emissions, greater noise Corridor and Keystone Corridor alternatives would all
impacts, and greater direct and indirect effects on avoid the Sand Hills; however, they would not avoid
many more communities than the proposed Project. the Northern High Plains Aquifer system, and they
would not avoid areas of shallow groundwater.
As a result of these considerations as described in Instead, these routes would shift risks to other areas
Section 4.2 of the EIS, system alternatives were of the Northern High Plains Aquifer system and to
considered either not reasonable or not other aquifers.
environmentally preferable.
In addition, these alternatives would be longer than
Major Route Alternatives the proposed route and would disturb more land and
The analysis of route alternatives considered 14 cross more water bodies than the proposed route. In
major route alternatives. Figure ES-8 depicts the addition, I-90 Corridor Alternatives A and B require
alternative routes considered. The analysis of crossing Lake Francis Case on the Missouri River
alternatives routes was conducted following the which would pose technical challenges due to the
approach to assessments of alternative pipeline width of the reservoir and the slope of the western
routes used by the Federal Energy Regulatory side of the crossing area.
Commission. As a result, the analysis began with a
Keystone Corridor Alternatives 1 and 2 would cost
screening process that first established criteria for
about 25 percent more than the proposed Project
screening alternatives, then identified potential
(about $1.7 billion more) and implementation of either
alternatives that met the criteria, and determined
of those alternatives would compromise the Bakken
whether or not they would (1) meet the purpose of
Marketlink Project and the opportunity to transport
and need for the proposed Project, and (2) be
crude oil from the producers in the Bakken formation
technically and economically practicable or feasible.
to markets in Cushing and the Gulf Coast.
For those alternatives meeting the criteria, DOS
assessed whether or not the alternative offered an Based on the above considerations and as described
overall environmental advantage over the proposed in Section 4.3 of the EIS, DOS eliminated the major
route. potential route alternatives from further consideration.
Due to public concern regarding the Ogallala Aquifer
(Northern High Plains Aquifer system) and the Sand Route Variations and Minor Realignments
Hills region, 5 of the alternative routes were A route variation is a relatively short deviation from a
developed to either minimize the pipeline length over proposed route that replaces a segment of the
those areas or avoid the areas entirely. These proposed route. Variations are developed to resolve
alternative routes consisted of I-90 Corridor landowner concerns and impacts to cultural resource
Alternatives A and B, Keystone Corridor Alternatives sites, wetlands, recreational lands, and terrain.
1 and 2 (which are parallel to all or part of the route of
the existing Keystone Oil Pipeline System), and the DOS consulted with the Bureau of Land Management
Western Alternative. and state agencies to negotiate route variations and
minor realignments, including nearly 100 in Montana
The assessment considered the environmental and about 240 minor realignments in other states
characteristics of the areas that these alternatives along the proposed route. Additional route variations
would cross, including the presence of aquifers, the and minor realignments may be added in response to
depth of wells, developed land, forested areas, specific conditions that may arise throughout the
wetlands, and streams and rivers. construction process.
ES-12
16. Keystone XL Project Executive Summary − Final EIS
Figure ES-8
Major Route Alternatives
ES-13
17. Keystone XL Project Executive Summary − Final EIS
The variations and minor realignments would replace Keystone would comply with all applicable laws
short segments of the proposed Project, are relatively and regulations;
close to the proposed route, and would be
implemented in accordance with applicable regulatory The proposed Project would be constructed,
requirements of federal, state, or local permitting operated, and maintained as described in the
agencies. DOS considers the variations and minor EIS;
realignments selected to have been evaluated Keystone has agreed to incorporate the 57
sufficiently to meet the environmental review Project-specific Special Conditions developed by
requirements of the National Environmental PHMSA into the proposed Project;
Protection Act.
Keystone has agreed to implement the measures
Other Alternatives Considered designed to avoid or reduce impacts described in
its application for a Presidential Permit and
DOS also considered several other scenarios in supplemental filings with DOS, the measures in
response to comments on the draft EIS. The its Construction, Mitigation, and Reclamation
alternative pipeline designs considered consisted of (CMR) Plan presented in Appendix B of the EIS,
an aboveground pipeline and a smaller diameter pipe and the construction methods for the Sand Hills
to decrease the volume of oil released from a spill. region described in Appendix H to the EIS; and
DOS also considered alternative sites for the major
aboveground facilities of the proposed Project, Keystone would incorporate the mitigation
including pump stations, mainline valves, and the measures required in permits issued by
Cushing tank farm. None of the alternative designs or environmental permitting agencies into the
facility locations were considered safer or construction, operation, and maintenance of the
environmentally preferable to the proposed Project proposed Project.
design.
Environmental Justice
Agency Preferred Alternative Executive Order 12898 requires federal agencies to
DOS did not find any of the major alternatives to be address and mitigate potential adverse impacts to
preferable to the proposed Project for the reasons minority and low income populations. In consultation
presented in the final EIS and summarized above. As with EPA, DOS identified these communities within a
a result, the agency-preferred alternative is the 4-mile-wide corridor centered on the pipeline using
proposed Project route with the variations and minor census and county level data.
route realignments described in the EIS, and the Potential Construction Impacts: The assessment
proposed location of the Cushing tank farm. suggested that potential impacts to minority and low
income populations could occur primarily in Harris,
ENVIRONMENTAL ANALYSES Jefferson, and Angelina Counties in Texas and in
Four levels of impact duration were considered in the Lincoln County, Oklahoma. During construction,
analysis of potential environmental impacts due to potential impacts include exposure to increased dust
construction and normal operation of the proposed and noise, disruption of traffic patterns, and increased
Project: temporary, short-term, long-term, and competition for social services in underserved
permanent. Temporary impacts generally occur populations. At any given location along the
during construction, with the resources returning to proposed pipeline route, the duration of the
pre-construction conditions almost immediately construction period would typically range from 20 to
afterward. Short-term impacts could continue for 30 working days. As a result, the impacts to minority
approximately 3 years after construction, and impacts and low-income populations due to construction
were considered long term if the resources would would be temporary and minor.
require more than 3 years to recover. Permanent Medical Services: Areas along the pipeline route that
impacts would occur if the resources would not return are medically underserved may be more vulnerable
to pre-construction conditions during the life of the during construction periods. These communities have
proposed Project, such as impacts to land use due to been identified as Health Professional Shortage
installation of pump stations. Areas or Medically Underserved Areas/Populations.
Conclusions in the EIS are based on the analysis of However, construction-related disruptions in those
environmental impacts and the understanding that: areas would be temporary and minor. In areas in
ES-14
18. Keystone XL Project Executive Summary − Final EIS
Montana and South Dakota, minor medical needs of the proposed Project and is currently refined in large
workers would be handled in construction camps to quantities by Gulf Coast refineries.
avoid or minimize the need for medical services from
The proposed Project is not likely to impact the
the surrounding communities.
amount of crude oil produced from the oil sands.
Air Emissions Related to Environmental Justice However, for illustrative purposes, the DOS-
Issues: The refineries that are likely to receive oil commissioned study estimated that incremental life-
transported by the pipeline are already configured to cycle U.S. greenhouse gas emissions from displacing
process heavy crude oil, and in the future would seek reference crude oils with Canadian oil sands crude
to continue processing heavy crude oil whether or not oils imported through the proposed Project would be
the proposed pipeline is constructed. The analysis in between 3 and 21 million metric tons of carbon
the EIS, including a DOE-commissioned study, dioxide emissions annually. This range is equivalent
indicates that the proposed Project would not likely to annual greenhouse gas emissions from the
affect the overall quality or quantity of crude oil combustion of fuels in 588,000 to 4,061,000
refined in the Gulf Coast region, and, as a result, passenger vehicles.
would not likely effect refinery emissions.
In addition, current projections suggest that the
amount of energy required to extract all crude oils is
Greenhouse Gas Emissions
projected to increase over time due to the need to
DOS commissioned a detailed study of greenhouse extract oil from ever deeper reservoirs using more
gas life-cycle emissions that compared Canadian oil energy intensive techniques. However, while the
sands crude with other selected reference crudes. greenhouse gas intensity of reference crude oils may
This study was a thorough review of recent scientific trend upward, the projections for the greenhouse gas
literature on greenhouse gas life-cycle emissions for intensity of Canadian oil sands crude oils suggests
Canadian oil sands crude including extraction, that they may stay relatively constant. Although there
upgrading, transportation, refining, and combustion. is some uncertainty in the trends for both reference
The study’s major conclusion was that, throughout its crude oils and oil sands derived crude oils, on
life cycle, oil sands crude is, on average, more balance it appears that the gap in greenhouse gas
greenhouse gas intensive than the crude oil it would intensity may decrease over time.
replace in the U.S. However, the relative greenhouse
Geology and Soils
gas intensity varies depending on (1) study design
factors, such as the reference crudes selected for Geologic Hazards: Potential geologic hazards
comparison with Canadian oil sands crudes (e.g., assessed in the EIS include seismic hazards
2005 U.S. average crude oil, Venezuelan (earthquakes), landslides, or subsidence (sink holes).
Bachaquero, Middle East Sour, and Mexican Heavy) The proposed route extends through relatively flat
and the timeframe selected, and (2) study and stable areas and the potential for these events is
assumptions, such as the extraction method and the low. The pipeline would not cross any known active
mix of crudes that would be transported by the faults with confirmed surface offsets. During
pipeline. construction, land clearing could increase the risk of
landslides and erosion. Keystone agreed to construct
For example, the Department of Energy’s National
temporary erosion control systems and revegetate the
Environmental Technology Lab (NETL) study
right-of-way after construction.
indicated that the life-cycle greenhouse gas
emissions of gasoline produced from Canadian oil There is a risk of subsidence (sink holes) where the
sands crude are approximately 17 percent higher proposed route potentially crosses karst formations in
than gasoline from the 2005 average mix of crude oil Nebraska, Oklahoma, and Texas. Site-specific
consumed in the U.S. The NETL study serves as a studies would be conducted as necessary to
key input for analyses conducted by EPA and DOE. characterize the karst features, if they are
In comparison, a study conducted by TIAX, LLC, encountered, and evaluate and modify construction
found that the greenhouse gas emissions from techniques as necessary in these areas. The overall
gasoline produced from Canadian oil sands crude are risk to the pipeline from karst-related subsidence is
only 2 percent higher when compared to gasoline expected to be minimal.
from Venezuelan heavy crude, a type of crude oil that
Soils and Sediments: Potential impacts to soils
is similar to the crude oil that would be transported by
include soil erosion, loss of topsoil, soil compaction,
soil contamination, damage to existing tile drainage
ES-15
19. Keystone XL Project Executive Summary − Final EIS
systems, and permanent increases in the proportion crossing location and the requirements of the
of large rocks in the topsoil. However, Keystone permitting agencies.
agreed to construction procedures that are designed
The open-cut wet method, which involves trenching
to reduce the likelihood and severity of Project
while the stream is flowing, would result in temporary
impacts to soils and sediments, including topsoil
increases in turbidity and bank erosion where
segregation methods, and to mitigate impacts to the
vegetation is removed. The dry-cut method, which
extent practicable.
involves diverting stream flow around the construction
Sand Hills Region: Of particular concern is the soil site, results in lower increases in turbidity than the
of the Sand Hills region of Nebraska, which is open-cut wet method.
particularly vulnerable to wind erosion. To address
Horizontal directional drilling would minimize impacts
this concern, Keystone developed and agreed to
to the stream or river because it involves drilling well
construction, reclamation, and post-construction
below the streambed. This method would be selected
procedures specifically for this area in consultation
at large body crossings to avoid disturbing the
with local experts and state agencies. The goal of the
streambeds and streamflow and to reduce the
Sand Hills region reclamation plan is to protect this
potential that deep scour during flooding would
sensitive area by maintaining soil structure and
endanger pipeline integrity. Figure ES-9 presents a
stability, stabilizing slopes to prevent erosion,
cross section of a river crossing using the horizontal
restoring native grass species, and maintaining
directional drilling method.
wildlife habitat and livestock grazing areas. Keystone
agreed to monitor the right-of-way through the Sand At all water crossings, Keystone agreed to use
Hills region for several years to ensure that vegetative buffer strips, drainage diversion structures,
reclamation and revegetation efforts are successful. and sediment barriers, and limit vegetation clearing to
reduce siltation and erosion. After construction, the
Water Resources right-of-way would be restored and revegetated to
reduce the potential for erosion of the stream bank.
Groundwater: Many of the aquifers along the
proposed route are isolated from the surface due to Hydrostatic Test Water: Water used to pressure test
soil types above the aquifers that prevent or slow the pipeline during construction would be discharged
downward migration of water. However, shallow or to its source waters or to an approved upland area
near-surface aquifers are also present along the within the same drainage and tested to ensure it
proposed route, as discussed above. Construction of meets applicable water quality standards and
the proposed Project may result in temporary to short- discharge rates.
term increases in suspended solids in the shallow
aquifers. The risk of dewatering shallow groundwater Wetlands
aquifers during construction or reducing groundwater The proposed Project route crosses emergent,
quality due to increased sediments in the water would scrub/shrub, and forested wetlands that are protected
be temporary to short term. by the U.S. Army Corps of Engineers (USACE) and
At some locations, groundwater may be used as a applicable state agencies under the review of EPA
source of water for pressure testing the pipeline through Section 401 and 404 of the Clean Water Act.
during construction. Keystone must obtain all Specific plans regarding wetland avoidance and
applicable water withdrawal and discharge permits minimization of impacts, and the development of
prior to testing, and the test water would be tested mitigation to compensate for the permanent loss or
and discharged in accordance with permit conversion of forested to emergent wetlands would
requirements. be further developed during the permitting process.
Wetland impacts presented in the EIS represent
River and Stream Crossings: Surface water bodies preliminary estimates based on the best available
would be crossed using one of three methods: the wetland information. DOS reviewed potential impacts
open-cut wet method, the dry-cut method, or the to wetlands and the avoidance, minimization, and
horizontal directional drilling method. The method mitigation process that would be followed with
selected would be based on the characteristics of the USACE and EPA.
ES-16
20. Keystone XL Project Executive Summary − Final EIS
Figure ES-9
Cross Section of Horizontal Directional Drilling Method
Most wetlands crossed by the proposed Project in Texas Bottomland Hardwood Wetlands: These are
Montana, South Dakota, and Nebraska are emergent forested wetlands with trees, such as Bald Cypress,
wetlands, and most wetlands crossed by the Water Oak, Water Hickory, and Swamp Tupelo that
proposed Project in Oklahoma and Texas are can exist in lowland floodplains in the Gulf Coast
forested wetlands. Construction of the pipeline would states. Clearing bottomland hardwood trees during
affect wetlands and their functions primarily during construction would result in long-term to permanent
and immediately after construction activities, but impacts because forests require decades to re-
permanent changes also are possible. Keystone establish and would mature over the span of
agreed to use construction methods that avoid or centuries. DOS reviewed potential Project impacts on
minimize impacts to wetlands. These measures bottomland hardwood wetlands with EPA and
include installing trench breakers and/or sealing the USACE. Preliminary mitigation measures to protect
trench to maintain the original wetland hydrology to bottomland hardwood wetlands are discussed in the
avoid draining wetlands, using timber mats to protect EIS and would be developed further by the USACE
wetlands during construction, and restoring wetland during the wetland permitting process.
areas to a level consistent with the requirements of
the applicable permits. Figure ES-10
Most wetland vegetation communities would transition Texas Bottomland Hardwood Wetland
back into a community that would function similarly to
the previously undisturbed wetland. Because most
wetlands would be restored, the overall impact of the
proposed Project to wetlands would be minor to
moderate and would range in duration from short term
to the life of the proposed Project. However, some
forested and scrub-shrub wetlands over the pipeline
would be converted to herbaceous wetlands since
trees and shrubs would not be allowed to grow over
the pipeline for inspection and integrity purposes.
Keystone is working with each USACE district along
the proposed route to identify wetlands and to
develop wetland mitigation and compensation plans
for the permanent conversion of forested wetland to
herbaceous wetland.
ES-13
21. Keystone XL Project Executive Summary − Final EIS
Terrestrial Vegetation communities would result in long-term impacts
because trees would be required to remain outside of
The proposed Project crosses primarily grasslands
the 50-foot-wide permanent right-of-way. These
and rangelands, followed by croplands, upland
impacts would last throughout the life of the proposed
forests, developed lands, and wetlands. After
Project because trees would not be allowed to
construction, Keystone agreed to restore topsoil,
reestablish within the permanent right-of-way and
slopes, contours, and drainage patterns to
because forests require decades to re-establish and
preconstruction conditions as practicable and to
would mature over the span of centuries.
reseed disturbed areas to restore vegetation cover,
prevent erosion, and control noxious weeds.
Wildlife
Keystone committed to controlling the introduction
and spread of noxious weeds and pests by adhering Big game animals, small game animals and
to construction and restoration procedures furbearers, waterfowl and game birds, and other
recommended by local, state, and federal agencies. nongame animals use habitats in and around the six
Soils and vegetation over the pipeline would be states crossed by the proposed Project. Construction
warmed slightly compared to surrounding soils by would result in the temporary and permanent loss and
heat loss from the pipeline during operation. alteration of habitats which provide foraging, cover,
and breeding habitats for wildlife. Most habitat loss
Native Grasslands and Rangelands: Native mixed
would be temporary as vegetation cover would be re-
shrub rangelands would be crossed by the proposed
established after construction and would be small in
Project in Montana and South Dakota and native
context to habitats available throughout the region
grasslands would be crossed by the proposed Project
crossed by the proposed Project. Loss of shrublands
in the Sand Hills region in Nebraska. Both of these
and wooded habitats would be long-term (from 5 to
native prairie habitats would be challenging to
20 years or more), however; and trees and tall shrubs
reclaim. In recognition of these challenges, Keystone
would not be allowed to re-establish over the pipeline
developed specific construction and reclamation
for inspection and integrity purposes. Aboveground
methods for the proposed Project in consultation with
facilities would result in some permanent habitat loss.
local, state, and federal agencies and local experts to
Power lines to pump stations can provide vantage
ensure that sagebrush and native grasses are
perches for raptors that lead to increased predation
restored to rangelands in Montana and South Dakota
on ground nesting birds and small mammals.
and that fragile soils and diverse native vegetation
Construction can produce short-term barriers to
cover are re-established in the Sand Hills region of
wildlife movement, direct and indirect mortality, and
Nebraska.
reduced survival and reproduction. Disturbance from
Figure ES-11 construction activities may have moderate local
Sand Hills Grassland affects on wildlife if important remnant habitats are
crossed or when sensitive breeding or overwintering
periods are not avoided. Habitat alteration and
fragmentation caused by the pipeline right-of-way
may reduce habitat suitability and use by wildlife.
Construction could also produce short-term barriers to
wildlife movement, direct and indirect mortality, and
reduced survival and reproduction. Disturbance from
construction activities would have moderate local
affects on wildlife if important remnant habitats are
crossed or when sensitive breeding or overwintering
periods are not avoided. Habitat alteration and
fragmentation caused by construction of the pipeline
could reduce habitat suitability and use by wildlife.
Upland and Riparian Forests: Native forests, During the environmental review of the proposed
Project, state and federal wildlife management
especially forested floodplains, were once an integral
component of the landscape throughout the Great agencies were contacted and they provided
Plains and they provide important habitats for wildlife. information on sensitive seasons and wildlife habitats
such as big game overwintering habitats, important
Clearing trees in upland and riparian forest
riparian corridors, and raptor and other migratory bird
ES-18
22. Keystone XL Project Executive Summary − Final EIS
nesting habitats. In addition state and federal wildlife impacts from construction of stream crossings include
management agencies provided recommendations for siltation, sedimentation, bank erosion, sediment
surveys to more specifically locate areas such as deposition, short-term delays in movements of fish,
raptor nests and prairie dog colonies that could and transport and spread of aquatic invasive animals
potentially be avoided. Keystone is working with state and plants. Keystone has agreed to minimize vehicle
and federal wildlife management agencies to contact with surface waters and to clean equipment to
minimize impacts to wildlife during sensitive breeding prevent transportation of aquatic invasive animals and
periods. Measures developed to minimize impacts to plants on equipment.
wildlife include development of a Migratory Bird
Most streams would be crossed using one of several
Conservation Plan in consultation with the USFWS,
trenching methods. Trenching stream crossings
removal of litter and garbage that could attract
when water is still flowing through the stream bed can
wildlife, control of unauthorized off-road vehicle
result in destruction of fish that do not avoid the
access to the construction right-of-way, and
construction area. Trenching methods may also use
reclamation of native range with native seed mixes.
dams, pumps, and flumes to divert the stream flow
Overall, the impact of construction to wildlife is
around the trench location to allow a “dry” trenching
expected to be minor and would be primarily
method. However, direct disturbance to the stream
temporary to short term. Normal Project operation
bed can release fine sediments during construction
would result in negligible effects to wildlife.
through flowing waters or after the flow is returned to
Figure ES-12 the stream bed. Sediment would be transported
Mule Deer downstream and could affect fish, other aquatic life,
and aquatic habitats through either direct exposure or
smothering. Most stream crossings would be
completed in less than 2 days, grading and
disturbance to waterbody banks would be minimized,
and crossings would be timed to avoid sensitive
spawning periods, such that resulting steam bed
disturbance and sediment impacts would be
temporary and minor.
Most large rivers would be crossed using the
horizontal directional drilling method which would
install the pipeline well below the active river bed. As
a result, direct disturbance to the river bed, fish,
aquatic animals and plants, and river banks would be
avoided. Keystone has developed site specific plans
for horizontal directional drill crossings and has
agreed to develop site-specific contingency plans to
address unintended releases of drilling fluids that
include preventative measures and a spill response
plan.
Keystone must work with state and federal wildlife
management agencies to minimize impacts to wildlife Figure ES-13
during sensitive breeding periods. Overall, the impact Recreational Fishing
of construction to wildlife is expected to be minor and
would be primarily temporary to short term. Normal
Project operation would result in negligible effects to
wildlife.
Fisheries Resources
The proposed route would cross rivers and streams,
including perennial streams that support recreational
or commercial fisheries. Most potential impacts to
fisheries resources would occur during construction
and would be temporary to short term. Potential
ES-19