Keynote Presentation
Cheryl Mele
Senior Vice President & Chief Operating Officer
November 14, 2018
PUBLIC 2
The interconnected
electrical system serving
most of Texas, with
limited external
connections
• 90% of Texas electric
load; 75% of Texas land
• 73,473 MW peak,
July 19, 2018
• More than 46,500 miles
of transmission lines
• 600+ generation units
ERCOT connections to other grids
are limited to ~1,250 MW of direct
current (DC) ties, which allow
control over flow of electricity
600 MW with SPP
30 MW with CENACE
at Eagle Pass
100 MW with CENACE
at Laredo 300 MW with CENACE at McAllen
220 MW with SPP
The ERCOT Region
Texas RE
PUBLIC
Installed Generating Capacity in ERCOT
3
2016
Generating
Capacity
Capacity available:
91,195 MW
2017
Generating
Capacity
Capacity available:
93,546 MW
• Summer generation capacity
information provided by December CDR
Reports for 2015, 2016 and 2017.
• Reflects operational installed capacity ―
excludes units designated as indefinitely
mothballed or under extended outage,
and accounts for rating changes
reported by resource owners.
• Other category includes hydro,
biomass-fired units and DC ties.
2018
Generating
Capacity
Capacity available:
94,626 MW
Natural
Gas
53%
Coal
21%
Nuclear
5%
Wind
20%
Other
2%
Natural
Gas
54%
Coal
22%
Nuclear
5%
Wind
18%
Other
1%
Natural
Gas
55%
Coal
17%
Nuclear
5%
Wind
21%
Other
2%
PUBLIC 4
2018 Actual Peak
Demand (7/19/18)
Final 2018 Summer
SARA*
Total Resources, MW 77,558 78,184
Thermal and Hydro 65,200 66,457
Private Use Networks, Net to Grid 3,019 3,298
Switchable Generation Resources 3,057 2,727
Wind Capacity Contribution 4,229 4,193
Solar Capacity Contribution 1,136 1,120
Non-Synchronous Ties 917 389
Peak Demand, MW 73,308 72,756
Reserve Capacity, MW 4,250 5,428
Total Outages, MW 2,075* 4,349
Extreme Outage Scenario 6,915
Capacity Available for Operating Reserves, MW 2,175 1,079
The Summer 2018 Seasonal Assessment of Resource
Adequacy (SARA) values vs. actuals at peak demand
No outages greater than
500 MW
Source: Final 2018 Summer SARA
* The totals for the Final 2018 Summer SARA column combine multiple
rows into a single row in some cases (E.g., already in-service Thermal and
Hydro Resources with planned Thermal and Hydro Resources).
** The outage information in this table was extracted on September 4, 2018.
PUBLIC
A closer look at the peak demand day of July 19
5
*Off-line capacity is a summation of capacity from resources that were simply off-line
and those providing non-spinning reserves as an off-line resource.
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
G,H,andI(MW)
A,B,C,D,EandF(MW)
Hour Ending
Hourly Average Demand, Capacity, and Reserves on 7/19/2018
A: Outages B: Quick-Start Resources C: Off-Line
D: Renewable HSL E: Non-renewable HSL F: Load
G: PRC H: Wind I: Solar
PRC = 2300
PUBLIC
Higher amount of Intermittent Renewable Resource (IRR) MW
occurred during the 2018 peak (7/19/18), relative to 2017 peak
(7/28/17)
6
0
1,500
3,000
4,500
6,000
7,500
9,000
10,500
12,000
13,500
15,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
Hour Ending
7/19/18 Wind 7/19/18 Solar
7/28/17 Wind 7/28/17 Solar
ERCOT IRR Generation
In the Final 2018 Summer SARA, wind contribution was 4,193 MW vs 4,229 MW actual and solar contribution was 1,120 MW vs 1,136 MW actual.
ERCOT “Peak” Hours
• Average wind generation during peak hours on July 19, 2018 was ~800 MW higher than on July 28,
2017. Average solar generation during peak hours on July 19, 2018 was ~400 MW higher than on
July 28, 2017.
• Average wind generation during peak hours on July 19, 2018 was ~1,900 MW lower than the average
for summer 2018 during those same hours of the day.

More Related Content

What's hot

Bob Smith Platts June 18 2014 Transmission Planning Development
Bob Smith Platts June 18 2014 Transmission Planning  DevelopmentBob Smith Platts June 18 2014 Transmission Planning  Development
Bob Smith Platts June 18 2014 Transmission Planning Development
Robert Smith
 
Brazil wind power sector opportunity analysis 2018
Brazil wind power sector opportunity analysis 2018Brazil wind power sector opportunity analysis 2018
Brazil wind power sector opportunity analysis 2018
KuicK Research
 

What's hot (20)

Energy Storage Innovation – Li-ion and beyond
Energy Storage Innovation – Li-ion and beyondEnergy Storage Innovation – Li-ion and beyond
Energy Storage Innovation – Li-ion and beyond
 
Nrel 80% renewable_electricity_integration_study
Nrel 80% renewable_electricity_integration_studyNrel 80% renewable_electricity_integration_study
Nrel 80% renewable_electricity_integration_study
 
Hybrid System for Electricity
Hybrid System for ElectricityHybrid System for Electricity
Hybrid System for Electricity
 
The Electric Grid 2.0 - Fergus Wheatly
The Electric Grid 2.0 - Fergus WheatlyThe Electric Grid 2.0 - Fergus Wheatly
The Electric Grid 2.0 - Fergus Wheatly
 
How to Prepare for the Next Big Thing – Storage
How to Prepare for the Next Big Thing – StorageHow to Prepare for the Next Big Thing – Storage
How to Prepare for the Next Big Thing – Storage
 
Microgrids for Mines : How to go green and reduce operation costs ?
Microgrids for Mines : How to go green and reduce operation costs ?Microgrids for Mines : How to go green and reduce operation costs ?
Microgrids for Mines : How to go green and reduce operation costs ?
 
Bob Smith Platts June 18 2014 Transmission Planning Development
Bob Smith Platts June 18 2014 Transmission Planning  DevelopmentBob Smith Platts June 18 2014 Transmission Planning  Development
Bob Smith Platts June 18 2014 Transmission Planning Development
 
Solar PV - Bangladesh - Solshare
Solar PV - Bangladesh - SolshareSolar PV - Bangladesh - Solshare
Solar PV - Bangladesh - Solshare
 
Energy, Grids and Microgrids
Energy, Grids and MicrogridsEnergy, Grids and Microgrids
Energy, Grids and Microgrids
 
NSW ggas scheme summary
NSW ggas scheme summaryNSW ggas scheme summary
NSW ggas scheme summary
 
Photovoltaic market and industry trends 2020 IEA PVPS
Photovoltaic market and industry trends 2020 IEA PVPSPhotovoltaic market and industry trends 2020 IEA PVPS
Photovoltaic market and industry trends 2020 IEA PVPS
 
Demand-Response in the Smart Grid Gotland project
Demand-Response in the Smart Grid Gotland projectDemand-Response in the Smart Grid Gotland project
Demand-Response in the Smart Grid Gotland project
 
Distributed Energy Resources in Brazil
Distributed Energy Resources in BrazilDistributed Energy Resources in Brazil
Distributed Energy Resources in Brazil
 
Brazil wind power sector opportunity analysis 2018
Brazil wind power sector opportunity analysis 2018Brazil wind power sector opportunity analysis 2018
Brazil wind power sector opportunity analysis 2018
 
Two difficulties
Two difficultiesTwo difficulties
Two difficulties
 
Smart Grid Gotland - Wind Power Integration
Smart Grid Gotland - Wind Power IntegrationSmart Grid Gotland - Wind Power Integration
Smart Grid Gotland - Wind Power Integration
 
GE Distributed Power - On Site Energy Solutions For Commercial And Industrial...
GE Distributed Power - On Site Energy Solutions For Commercial And Industrial...GE Distributed Power - On Site Energy Solutions For Commercial And Industrial...
GE Distributed Power - On Site Energy Solutions For Commercial And Industrial...
 
Resultat från Smart Grid Gotland
Resultat från Smart Grid GotlandResultat från Smart Grid Gotland
Resultat från Smart Grid Gotland
 
Increased need for flexibility in the European energy transition
Increased need for flexibility in the European energy transitionIncreased need for flexibility in the European energy transition
Increased need for flexibility in the European energy transition
 
Solar Ancillary industry news | Week 3 , July 2021
Solar Ancillary industry news | Week 3 , July 2021Solar Ancillary industry news | Week 3 , July 2021
Solar Ancillary industry news | Week 3 , July 2021
 

Similar to Keynote Interview: Texas as a U.S. Flagship for Energy Transition

Infrastructure Fact Sheet
Infrastructure Fact SheetInfrastructure Fact Sheet
Infrastructure Fact Sheet
Alyssa Norris
 
EnergySolutions_Mid-Hudson_RoadMap_2011_10_26_Summary
EnergySolutions_Mid-Hudson_RoadMap_2011_10_26_SummaryEnergySolutions_Mid-Hudson_RoadMap_2011_10_26_Summary
EnergySolutions_Mid-Hudson_RoadMap_2011_10_26_Summary
Leo Wiegman
 
What the duck curve tells us about managing a green grid
What the duck curve tells us about managing a green gridWhat the duck curve tells us about managing a green grid
What the duck curve tells us about managing a green grid
Andrew Gelston
 

Similar to Keynote Interview: Texas as a U.S. Flagship for Energy Transition (20)

L’esperienza della California, Mark Rothleder
L’esperienza della California, Mark RothlederL’esperienza della California, Mark Rothleder
L’esperienza della California, Mark Rothleder
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
 
Update on ERCOT Activities
Update on ERCOT ActivitiesUpdate on ERCOT Activities
Update on ERCOT Activities
 
Infrastructure Fact Sheet
Infrastructure Fact SheetInfrastructure Fact Sheet
Infrastructure Fact Sheet
 
EnergySolutions_Mid-Hudson_RoadMap_2011_10_26_Summary
EnergySolutions_Mid-Hudson_RoadMap_2011_10_26_SummaryEnergySolutions_Mid-Hudson_RoadMap_2011_10_26_Summary
EnergySolutions_Mid-Hudson_RoadMap_2011_10_26_Summary
 
High Penetration of Renewable Energy
High Penetration of Renewable EnergyHigh Penetration of Renewable Energy
High Penetration of Renewable Energy
 
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
 
SUSTAINABLE ENERGY SUPPLY
SUSTAINABLE ENERGY SUPPLYSUSTAINABLE ENERGY SUPPLY
SUSTAINABLE ENERGY SUPPLY
 
What the duck curve tells us about managing a green grid
What the duck curve tells us about managing a green gridWhat the duck curve tells us about managing a green grid
What the duck curve tells us about managing a green grid
 
+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf
+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf
+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf
 
Analysis of grid connected independent power plant capabilities on electricit...
Analysis of grid connected independent power plant capabilities on electricit...Analysis of grid connected independent power plant capabilities on electricit...
Analysis of grid connected independent power plant capabilities on electricit...
 
74481.pdf
74481.pdf74481.pdf
74481.pdf
 
Energy and Rice Deficiency: Reform Challenges for the Last Quarter of the Aqu...
Energy and Rice Deficiency: Reform Challenges for the Last Quarter of the Aqu...Energy and Rice Deficiency: Reform Challenges for the Last Quarter of the Aqu...
Energy and Rice Deficiency: Reform Challenges for the Last Quarter of the Aqu...
 
Extending the AMI Network with Intra-Grid Sensors
Extending the AMI Network with Intra-Grid SensorsExtending the AMI Network with Intra-Grid Sensors
Extending the AMI Network with Intra-Grid Sensors
 
Lecture on Ghana re unido isec
Lecture on Ghana re unido isecLecture on Ghana re unido isec
Lecture on Ghana re unido isec
 
VRE: Solar and Wind Energy
VRE: Solar and Wind EnergyVRE: Solar and Wind Energy
VRE: Solar and Wind Energy
 
World Energy Focus - Giugno 2017
World Energy Focus - Giugno 2017World Energy Focus - Giugno 2017
World Energy Focus - Giugno 2017
 
Is the PH power supply ready for the AEC?
Is the PH power supply ready for the AEC?Is the PH power supply ready for the AEC?
Is the PH power supply ready for the AEC?
 
Sgcp13smith
Sgcp13smithSgcp13smith
Sgcp13smith
 
RETOOLING NIGERIAS ELECTRICITY GENERATION SUB – SYSTEM FOR SUSTAINABLE GRID O...
RETOOLING NIGERIAS ELECTRICITY GENERATION SUB – SYSTEM FOR SUSTAINABLE GRID O...RETOOLING NIGERIAS ELECTRICITY GENERATION SUB – SYSTEM FOR SUSTAINABLE GRID O...
RETOOLING NIGERIAS ELECTRICITY GENERATION SUB – SYSTEM FOR SUSTAINABLE GRID O...
 

More from Nicole Green

More from Nicole Green (20)

Colin Smith and Dan Finn-Foley
Colin Smith and Dan Finn-FoleyColin Smith and Dan Finn-Foley
Colin Smith and Dan Finn-Foley
 
Wood Mackenzie Power & Renewables Breakfast Briefing II: Battery and Non-Batt...
Wood Mackenzie Power & Renewables Breakfast Briefing II: Battery and Non-Batt...Wood Mackenzie Power & Renewables Breakfast Briefing II: Battery and Non-Batt...
Wood Mackenzie Power & Renewables Breakfast Briefing II: Battery and Non-Batt...
 
Bridging the Gap in Long-Term Resource Planning for Utilities and Grid Operators
Bridging the Gap in Long-Term Resource Planning for Utilities and Grid OperatorsBridging the Gap in Long-Term Resource Planning for Utilities and Grid Operators
Bridging the Gap in Long-Term Resource Planning for Utilities and Grid Operators
 
How Distributed Resources Will Impact Wholesale Power Markets
How Distributed Resources Will Impact Wholesale Power MarketsHow Distributed Resources Will Impact Wholesale Power Markets
How Distributed Resources Will Impact Wholesale Power Markets
 
Ravi Manghani
Ravi ManghaniRavi Manghani
Ravi Manghani
 
Prajit ghosh-keynote
Prajit ghosh-keynotePrajit ghosh-keynote
Prajit ghosh-keynote
 
Wind-Plus-Storage Presentation
Wind-Plus-Storage PresentationWind-Plus-Storage Presentation
Wind-Plus-Storage Presentation
 
Opening MAKE Consulting Presentation
Opening MAKE Consulting PresentationOpening MAKE Consulting Presentation
Opening MAKE Consulting Presentation
 
The Evolving Power Market's Need for Storage
The Evolving Power Market's Need for StorageThe Evolving Power Market's Need for Storage
The Evolving Power Market's Need for Storage
 
Day 2 Slides
Day 2 SlidesDay 2 Slides
Day 2 Slides
 
Grid edge innovation summit day 1 track 2 slides
Grid edge innovation summit day 1 track 2 slidesGrid edge innovation summit day 1 track 2 slides
Grid edge innovation summit day 1 track 2 slides
 
Day 1 june 20 morning and track 1
Day 1 june 20 morning and track 1Day 1 june 20 morning and track 1
Day 1 june 20 morning and track 1
 
Day 2
Day 2 Day 2
Day 2
 
GTM Research Welcome Presentation
GTM Research Welcome PresentationGTM Research Welcome Presentation
GTM Research Welcome Presentation
 
Opening slides
Opening slidesOpening slides
Opening slides
 
Customer Centricity
Customer CentricityCustomer Centricity
Customer Centricity
 
IBM Blockchain Case Study
IBM Blockchain Case StudyIBM Blockchain Case Study
IBM Blockchain Case Study
 
GTM Research Presentation with ComEd
GTM Research Presentation with ComEdGTM Research Presentation with ComEd
GTM Research Presentation with ComEd
 
S&C Electric and FP&L Case Study
S&C Electric and FP&L Case StudyS&C Electric and FP&L Case Study
S&C Electric and FP&L Case Study
 
Track 1 intro presentation
Track 1 intro presentationTrack 1 intro presentation
Track 1 intro presentation
 

Recently uploaded

一比一原版(Southern Cross毕业证)南十字星大学毕业证成绩单
一比一原版(Southern Cross毕业证)南十字星大学毕业证成绩单一比一原版(Southern Cross毕业证)南十字星大学毕业证成绩单
一比一原版(Southern Cross毕业证)南十字星大学毕业证成绩单
yegohah
 
一比一原版(SUT毕业证)斯威本科技大学毕业证成绩单
一比一原版(SUT毕业证)斯威本科技大学毕业证成绩单一比一原版(SUT毕业证)斯威本科技大学毕业证成绩单
一比一原版(SUT毕业证)斯威本科技大学毕业证成绩单
pcoow
 
一比一原版EUR毕业证鹿特丹伊拉斯姆斯大学毕业证成绩单如何办理
一比一原版EUR毕业证鹿特丹伊拉斯姆斯大学毕业证成绩单如何办理一比一原版EUR毕业证鹿特丹伊拉斯姆斯大学毕业证成绩单如何办理
一比一原版EUR毕业证鹿特丹伊拉斯姆斯大学毕业证成绩单如何办理
exehay
 
一比一原版(Lincoln毕业证)新西兰林肯大学毕业证成绩单
一比一原版(Lincoln毕业证)新西兰林肯大学毕业证成绩单一比一原版(Lincoln毕业证)新西兰林肯大学毕业证成绩单
一比一原版(Lincoln毕业证)新西兰林肯大学毕业证成绩单
tyvaq
 
Prevalence, biochemical and hematological study of diabetic patients
Prevalence, biochemical and hematological study of diabetic patientsPrevalence, biochemical and hematological study of diabetic patients
Prevalence, biochemical and hematological study of diabetic patients
Open Access Research Paper
 
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Open Access Research Paper
 
一比一原版(Massey毕业证)梅西大学毕业证成绩单
一比一原版(Massey毕业证)梅西大学毕业证成绩单一比一原版(Massey毕业证)梅西大学毕业证成绩单
一比一原版(Massey毕业证)梅西大学毕业证成绩单
tyvaq
 

Recently uploaded (20)

IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
 
DESERT ECOSYSTEM AND ITS CHARACTERISTICS AND TYPES
DESERT ECOSYSTEM AND ITS CHARACTERISTICS AND TYPESDESERT ECOSYSTEM AND ITS CHARACTERISTICS AND TYPES
DESERT ECOSYSTEM AND ITS CHARACTERISTICS AND TYPES
 
一比一原版(Southern Cross毕业证)南十字星大学毕业证成绩单
一比一原版(Southern Cross毕业证)南十字星大学毕业证成绩单一比一原版(Southern Cross毕业证)南十字星大学毕业证成绩单
一比一原版(Southern Cross毕业证)南十字星大学毕业证成绩单
 
一比一原版(SUT毕业证)斯威本科技大学毕业证成绩单
一比一原版(SUT毕业证)斯威本科技大学毕业证成绩单一比一原版(SUT毕业证)斯威本科技大学毕业证成绩单
一比一原版(SUT毕业证)斯威本科技大学毕业证成绩单
 
一比一原版EUR毕业证鹿特丹伊拉斯姆斯大学毕业证成绩单如何办理
一比一原版EUR毕业证鹿特丹伊拉斯姆斯大学毕业证成绩单如何办理一比一原版EUR毕业证鹿特丹伊拉斯姆斯大学毕业证成绩单如何办理
一比一原版EUR毕业证鹿特丹伊拉斯姆斯大学毕业证成绩单如何办理
 
@@how to Join @occult for money ritual..☎️+2349022657119.
@@how to Join @occult for money ritual..☎️+2349022657119.@@how to Join @occult for money ritual..☎️+2349022657119.
@@how to Join @occult for money ritual..☎️+2349022657119.
 
DRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving togetherDRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving together
 
ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
 
The State Board for Water Pollution - The Water Act 1974 .pptx
The State Board for  Water Pollution - The Water Act 1974  .pptxThe State Board for  Water Pollution - The Water Act 1974  .pptx
The State Board for Water Pollution - The Water Act 1974 .pptx
 
Bhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of deathBhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of death
 
一比一原版(Lincoln毕业证)新西兰林肯大学毕业证成绩单
一比一原版(Lincoln毕业证)新西兰林肯大学毕业证成绩单一比一原版(Lincoln毕业证)新西兰林肯大学毕业证成绩单
一比一原版(Lincoln毕业证)新西兰林肯大学毕业证成绩单
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
 
Prevalence, biochemical and hematological study of diabetic patients
Prevalence, biochemical and hematological study of diabetic patientsPrevalence, biochemical and hematological study of diabetic patients
Prevalence, biochemical and hematological study of diabetic patients
 
Prevention and Control of Water Pollution
Prevention and Control of Water PollutionPrevention and Control of Water Pollution
Prevention and Control of Water Pollution
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
 
Major-Environmental-Problems and Proven Solutions.pdf
Major-Environmental-Problems and Proven Solutions.pdfMajor-Environmental-Problems and Proven Solutions.pdf
Major-Environmental-Problems and Proven Solutions.pdf
 
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
 
一比一原版(Massey毕业证)梅西大学毕业证成绩单
一比一原版(Massey毕业证)梅西大学毕业证成绩单一比一原版(Massey毕业证)梅西大学毕业证成绩单
一比一原版(Massey毕业证)梅西大学毕业证成绩单
 

Keynote Interview: Texas as a U.S. Flagship for Energy Transition

  • 1. Power & Renewables Summit 2018 Keynote Presentation Cheryl Mele Senior Vice President & Chief Operating Officer November 14, 2018
  • 2. PUBLIC 2 The interconnected electrical system serving most of Texas, with limited external connections • 90% of Texas electric load; 75% of Texas land • 73,473 MW peak, July 19, 2018 • More than 46,500 miles of transmission lines • 600+ generation units ERCOT connections to other grids are limited to ~1,250 MW of direct current (DC) ties, which allow control over flow of electricity 600 MW with SPP 30 MW with CENACE at Eagle Pass 100 MW with CENACE at Laredo 300 MW with CENACE at McAllen 220 MW with SPP The ERCOT Region Texas RE
  • 3. PUBLIC Installed Generating Capacity in ERCOT 3 2016 Generating Capacity Capacity available: 91,195 MW 2017 Generating Capacity Capacity available: 93,546 MW • Summer generation capacity information provided by December CDR Reports for 2015, 2016 and 2017. • Reflects operational installed capacity ― excludes units designated as indefinitely mothballed or under extended outage, and accounts for rating changes reported by resource owners. • Other category includes hydro, biomass-fired units and DC ties. 2018 Generating Capacity Capacity available: 94,626 MW Natural Gas 53% Coal 21% Nuclear 5% Wind 20% Other 2% Natural Gas 54% Coal 22% Nuclear 5% Wind 18% Other 1% Natural Gas 55% Coal 17% Nuclear 5% Wind 21% Other 2%
  • 4. PUBLIC 4 2018 Actual Peak Demand (7/19/18) Final 2018 Summer SARA* Total Resources, MW 77,558 78,184 Thermal and Hydro 65,200 66,457 Private Use Networks, Net to Grid 3,019 3,298 Switchable Generation Resources 3,057 2,727 Wind Capacity Contribution 4,229 4,193 Solar Capacity Contribution 1,136 1,120 Non-Synchronous Ties 917 389 Peak Demand, MW 73,308 72,756 Reserve Capacity, MW 4,250 5,428 Total Outages, MW 2,075* 4,349 Extreme Outage Scenario 6,915 Capacity Available for Operating Reserves, MW 2,175 1,079 The Summer 2018 Seasonal Assessment of Resource Adequacy (SARA) values vs. actuals at peak demand No outages greater than 500 MW Source: Final 2018 Summer SARA * The totals for the Final 2018 Summer SARA column combine multiple rows into a single row in some cases (E.g., already in-service Thermal and Hydro Resources with planned Thermal and Hydro Resources). ** The outage information in this table was extracted on September 4, 2018.
  • 5. PUBLIC A closer look at the peak demand day of July 19 5 *Off-line capacity is a summation of capacity from resources that were simply off-line and those providing non-spinning reserves as an off-line resource. 0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 0 10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 G,H,andI(MW) A,B,C,D,EandF(MW) Hour Ending Hourly Average Demand, Capacity, and Reserves on 7/19/2018 A: Outages B: Quick-Start Resources C: Off-Line D: Renewable HSL E: Non-renewable HSL F: Load G: PRC H: Wind I: Solar PRC = 2300
  • 6. PUBLIC Higher amount of Intermittent Renewable Resource (IRR) MW occurred during the 2018 peak (7/19/18), relative to 2017 peak (7/28/17) 6 0 1,500 3,000 4,500 6,000 7,500 9,000 10,500 12,000 13,500 15,000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MW Hour Ending 7/19/18 Wind 7/19/18 Solar 7/28/17 Wind 7/28/17 Solar ERCOT IRR Generation In the Final 2018 Summer SARA, wind contribution was 4,193 MW vs 4,229 MW actual and solar contribution was 1,120 MW vs 1,136 MW actual. ERCOT “Peak” Hours • Average wind generation during peak hours on July 19, 2018 was ~800 MW higher than on July 28, 2017. Average solar generation during peak hours on July 19, 2018 was ~400 MW higher than on July 28, 2017. • Average wind generation during peak hours on July 19, 2018 was ~1,900 MW lower than the average for summer 2018 during those same hours of the day.