Our project was to reduce the energy consumption on the air conditioning system from Jumeirah Group. We selected the energy manager’s office to conduct the test pilot. The site location is in the Jumeirah site management offices of Burj Al ARAB, Wild Wadi & Jumeirah beach hotel (See the map below). We conducted the test in collaboration with the Energy manager of the Jumeirah group and under the supervision of the technical director for 20 days and 24 hours per day. For the first seven days, the AC ran without AES as a normal situation. The following other (13) days, the AES was connected to AC to control and optimize the operations. Also, we have collected some data like the room temperature (electronic thermometer), the temperature targeted (AC), and the room temperature shown on the remote control to keep the same environmental situation during the test. The air conditioner acclimatizes every room in the site office. We demonstrated through this test pilot a positive achievement reaching an energy saving of 28%