Project Server 2010 Overview with Project Web App
January 2013
INTRODUCTION
» Purpose: Overview of Project Server and Project Plan Model
» Part 1: Project Plans; and Part 2: SharePoint
» How does this relate to you?
» Agenda
• Overview of Project Server
• PWA Environment
• Project Professional Environment
• IEE Project Plan Model
• Future Plans
OVERVIEW
» Project Server vs. MS Project
• Database vs. file
• Connect through SharePoint or Project Professional
• Enterprise resource pool
• SharePoint infrastructure
- Excel Services
- Visio Services
- Lists & Document Libraries
- Dashboards
- Performance Scoring
OVERVIEW
» Requirements
• MS Project Professional to connect from desktop
• PWA license to connect through SharePoint
OVERVIEW
» Architecture
PROJECT WEB APP
» PWA Environment
• Start Page
• Project Center
• Ribbon
» Limitations
• Editing master projects is not supported
• Non-standard calendars aren't supported
• Spaces (blank tasks) aren't supported
• Closing browser does not check-in projects
» Recommendation: use Project Pro to edit your projects
PROJECT WEB APP
» Editing in PWA
1
2
3
PROJECT WEB APP
» Closing in PWA
1
2
3
4
PROJECT PROFESSIONAL
» Connecting with Project Professional
PROJECT PROFESSIONAL
» New IEE Project in Project
Professional
» Template includes
SharePoint layout for IEE
PROJECT PROFESSIONAL
» Closing in Project Professional
IEE PROJECT PLAN STRATEGY
» Project and Release Plan Model
» Resource Planning
» Baselines
PROJECT AND RELEASE PLAN MODEL
» Project and Sub-Project Strategy
» Single-owner/single-discipline plans
» Master Plans for project managers and release managers
» Cross project dependencies (linked tasks)
Project and Sub-Project
PROJECT AND RELEASE PLAN MODEL
» Project and Sub-project Strategy
• Benefits
- Single-owner plans
- Reduce or eliminate check-out conflicts
- Reduce multiplication of task entries
- Consolidates reporting at each level
Project and Sub-Project
PROJECT AND RELEASE PLAN MODEL
» Single-owner/single-discipline plans
• One owner of each plan
• Dev, QA and Doc plans remain separate but share dependencies at
higher level
» Master plans consolidate release project plans into larger objectives
» Master plans create task dependencies (e.g., finish to start
predecessors)
Project and Sub-Project
PROJECT AND RELEASE PLAN MODEL
Detailed Level
Project Plan
Owner: R&D Mgr
Project Plan (Department
Level)
Owner: R&D or Proj Mgr
Project Master Plan
(Release Plan)
Owner: Release Manager
Project / Sub-Project Relationship
RESOURCE PLANNING
Resource Pool
RESOURCE PLANNING
Resource Pool
RESOURCE PLANNING
» Other resource tools:
• Resource Leveling
• Substituting
PROJECT BASELINES
» Snapshot current project plan
» Snapshot plan at different stages of the project
» Run comparison reports between original plan and actual performance
UPCOMING
» Do we have the need for detailed training?
» Request licensing for project leads
» Request administrative permissions for IEE/Raleigh
» Enable portfolio reporting dashboards
» Enable Performance Point services
» Bi-monthly update presentations as functionality developed and rolled
out
Questions?
THANK YOU
www.itron.com
START PAGE
Back
PROJECT CENTER
Back
PWA RIBBON
Back
Project Center
Project
Project Task

Department Project Server Overview Part 1

  • 1.
    GLOBAL SOFTWARE Project Server2010 Overview with Project Web App January 2013
  • 2.
    INTRODUCTION » Purpose: Overviewof Project Server and Project Plan Model » Part 1: Project Plans; and Part 2: SharePoint » How does this relate to you? » Agenda • Overview of Project Server • PWA Environment • Project Professional Environment • IEE Project Plan Model • Future Plans
  • 3.
    OVERVIEW » Project Servervs. MS Project • Database vs. file • Connect through SharePoint or Project Professional • Enterprise resource pool • SharePoint infrastructure - Excel Services - Visio Services - Lists & Document Libraries - Dashboards - Performance Scoring
  • 4.
    OVERVIEW » Requirements • MSProject Professional to connect from desktop • PWA license to connect through SharePoint
  • 5.
  • 6.
    PROJECT WEB APP »PWA Environment • Start Page • Project Center • Ribbon » Limitations • Editing master projects is not supported • Non-standard calendars aren't supported • Spaces (blank tasks) aren't supported • Closing browser does not check-in projects » Recommendation: use Project Pro to edit your projects
  • 7.
    PROJECT WEB APP »Editing in PWA 1 2 3
  • 8.
    PROJECT WEB APP »Closing in PWA 1 2 3 4
  • 9.
    PROJECT PROFESSIONAL » Connectingwith Project Professional
  • 10.
    PROJECT PROFESSIONAL » NewIEE Project in Project Professional » Template includes SharePoint layout for IEE
  • 11.
    PROJECT PROFESSIONAL » Closingin Project Professional
  • 12.
    IEE PROJECT PLANSTRATEGY » Project and Release Plan Model » Resource Planning » Baselines
  • 13.
    PROJECT AND RELEASEPLAN MODEL » Project and Sub-Project Strategy » Single-owner/single-discipline plans » Master Plans for project managers and release managers » Cross project dependencies (linked tasks) Project and Sub-Project
  • 14.
    PROJECT AND RELEASEPLAN MODEL » Project and Sub-project Strategy • Benefits - Single-owner plans - Reduce or eliminate check-out conflicts - Reduce multiplication of task entries - Consolidates reporting at each level Project and Sub-Project
  • 15.
    PROJECT AND RELEASEPLAN MODEL » Single-owner/single-discipline plans • One owner of each plan • Dev, QA and Doc plans remain separate but share dependencies at higher level » Master plans consolidate release project plans into larger objectives » Master plans create task dependencies (e.g., finish to start predecessors) Project and Sub-Project
  • 16.
    PROJECT AND RELEASEPLAN MODEL Detailed Level Project Plan Owner: R&D Mgr Project Plan (Department Level) Owner: R&D or Proj Mgr Project Master Plan (Release Plan) Owner: Release Manager Project / Sub-Project Relationship
  • 17.
  • 18.
  • 19.
    RESOURCE PLANNING » Otherresource tools: • Resource Leveling • Substituting
  • 20.
    PROJECT BASELINES » Snapshotcurrent project plan » Snapshot plan at different stages of the project » Run comparison reports between original plan and actual performance
  • 21.
    UPCOMING » Do wehave the need for detailed training? » Request licensing for project leads » Request administrative permissions for IEE/Raleigh » Enable portfolio reporting dashboards » Enable Performance Point services » Bi-monthly update presentations as functionality developed and rolled out