OEE definition
iper – Industrial Performance 2015-01-19 joao.leite@iper.pt
OEE - Overall equipment effectiveness
OEE breaks the performance of a manufacturing unit into three separate
but measurable components:
 Availability
Availability = uptime/ available time
 Performance
Performance = (Parts Produced * Ideal Cycle Time) / Operating time
 Quality
Quality = (Units produced - defective units) / (Units produced)
Reliability applied to the Availability
iper – Industrial Performance 2015-01-19 joao.leite@iper.pt
How to improve:
- Sample productions
prior to start of the
serial production
( TRIAL RUNS )
- Operators training
How to improve:
- Implementation of a
robust maintenance plan
- Machine FMEA
Reliability applied to the Performance
iper – Industrial Performance 2015-01-19 joao.leite@iper.pt
How to improve:
- Sample productions
prior to start of the
serial production
( TRIAL RUNS )
How to improve:
- Implementation of a
robust maintenance plan
- Machine FMEA
Reliability applied to the Quality
iper – Industrial Performance 2015-01-19 joao.leite@iper.pt
How to improve:
- Feasibility Analysis
- Product FMEA
- Process FMEA
How to improve:
- Implementation of a
robust maintenance plan
iper – Industrial Performance 2015-01-19 joao.leite@iper.pt
To be continued…

More Related Content

What's hot

Steam Turbine Department Brochure
Steam Turbine Department BrochureSteam Turbine Department Brochure
Steam Turbine Department BrochureKIMI SA
 
Commercial Service Sales Presentation
Commercial Service Sales PresentationCommercial Service Sales Presentation
Commercial Service Sales Presentationrobwhite1
 
Type of work undertaken
Type of work undertakenType of work undertaken
Type of work undertakenPaul Doughty
 
Eduardo Neira - Project Experience
Eduardo Neira - Project ExperienceEduardo Neira - Project Experience
Eduardo Neira - Project ExperienceEduardo Neira
 
Imafs presentation general_eng
Imafs presentation general_engImafs presentation general_eng
Imafs presentation general_engIMAFS
 
Corporate presentation teknocrat's [ms india] 110719
Corporate presentation teknocrat's [ms india] 110719Corporate presentation teknocrat's [ms india] 110719
Corporate presentation teknocrat's [ms india] 110719Akash Yadav
 
IMAFS Manage your inventory levels with state of the art optimization tools
IMAFS Manage your inventory levels with state of the art optimization toolsIMAFS Manage your inventory levels with state of the art optimization tools
IMAFS Manage your inventory levels with state of the art optimization toolsIMAFS
 
Article from National newspaper : IL GIORNALE
Article from National newspaper : IL GIORNALEArticle from National newspaper : IL GIORNALE
Article from National newspaper : IL GIORNALEO.M.S. s.r.l.
 

What's hot (18)

DAVID RESUME
DAVID  RESUMEDAVID  RESUME
DAVID RESUME
 
Resume 16-3
Resume 16-3Resume 16-3
Resume 16-3
 
Steam Turbine Department Brochure
Steam Turbine Department BrochureSteam Turbine Department Brochure
Steam Turbine Department Brochure
 
Commercial Service Sales Presentation
Commercial Service Sales PresentationCommercial Service Sales Presentation
Commercial Service Sales Presentation
 
resume-public
resume-publicresume-public
resume-public
 
Phil Hunnicut CV4
Phil Hunnicut CV4Phil Hunnicut CV4
Phil Hunnicut CV4
 
ASHOK KUMAR
ASHOK KUMARASHOK KUMAR
ASHOK KUMAR
 
Type of work undertaken
Type of work undertakenType of work undertaken
Type of work undertaken
 
Eduardo Neira - Project Experience
Eduardo Neira - Project ExperienceEduardo Neira - Project Experience
Eduardo Neira - Project Experience
 
Imafs presentation general_eng
Imafs presentation general_engImafs presentation general_eng
Imafs presentation general_eng
 
Corporate presentation teknocrat's [ms india] 110719
Corporate presentation teknocrat's [ms india] 110719Corporate presentation teknocrat's [ms india] 110719
Corporate presentation teknocrat's [ms india] 110719
 
Maintenance Benchmarking (3)
Maintenance Benchmarking (3)Maintenance Benchmarking (3)
Maintenance Benchmarking (3)
 
Auto Industrija_EN (1)
Auto Industrija_EN (1)Auto Industrija_EN (1)
Auto Industrija_EN (1)
 
IMAFS Manage your inventory levels with state of the art optimization tools
IMAFS Manage your inventory levels with state of the art optimization toolsIMAFS Manage your inventory levels with state of the art optimization tools
IMAFS Manage your inventory levels with state of the art optimization tools
 
mycv17
mycv17mycv17
mycv17
 
Article from National newspaper : IL GIORNALE
Article from National newspaper : IL GIORNALEArticle from National newspaper : IL GIORNALE
Article from National newspaper : IL GIORNALE
 
resume
resumeresume
resume
 
ALameResume
ALameResumeALameResume
ALameResume
 

Viewers also liked

NOT ENOUGH SAMPLES FOR RELIABILITY?
NOT ENOUGH SAMPLES FOR RELIABILITY?NOT ENOUGH SAMPLES FOR RELIABILITY?
NOT ENOUGH SAMPLES FOR RELIABILITY?Allyson Hartzell
 
Narrativa educativa
Narrativa educativaNarrativa educativa
Narrativa educativaangiep11
 
Reliability math and the exponential distribution
Reliability math and the exponential distributionReliability math and the exponential distribution
Reliability math and the exponential distributionAccendo Reliability
 
Reliability engineering chapter-2 reliability of systems
Reliability engineering chapter-2 reliability of systemsReliability engineering chapter-2 reliability of systems
Reliability engineering chapter-2 reliability of systemsCharlton Inao
 
Presentation Validity & Reliability
Presentation Validity & ReliabilityPresentation Validity & Reliability
Presentation Validity & Reliabilitysongoten77
 
State of the Word 2011
State of the Word 2011State of the Word 2011
State of the Word 2011photomatt
 

Viewers also liked (8)

NOT ENOUGH SAMPLES FOR RELIABILITY?
NOT ENOUGH SAMPLES FOR RELIABILITY?NOT ENOUGH SAMPLES FOR RELIABILITY?
NOT ENOUGH SAMPLES FOR RELIABILITY?
 
Narrativa educativa
Narrativa educativaNarrativa educativa
Narrativa educativa
 
DFR Methods Survey 2014
DFR Methods Survey 2014DFR Methods Survey 2014
DFR Methods Survey 2014
 
Reliability math and the exponential distribution
Reliability math and the exponential distributionReliability math and the exponential distribution
Reliability math and the exponential distribution
 
Reliability engineering chapter-2 reliability of systems
Reliability engineering chapter-2 reliability of systemsReliability engineering chapter-2 reliability of systems
Reliability engineering chapter-2 reliability of systems
 
Presentation Validity & Reliability
Presentation Validity & ReliabilityPresentation Validity & Reliability
Presentation Validity & Reliability
 
Reliability engineering ppt-Internship
Reliability engineering ppt-InternshipReliability engineering ppt-Internship
Reliability engineering ppt-Internship
 
State of the Word 2011
State of the Word 2011State of the Word 2011
State of the Word 2011
 

Similar to The reliability of the OEE indicator

Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1Matthew Clemens
 
Maintainance engineering and management
Maintainance engineering and managementMaintainance engineering and management
Maintainance engineering and managementbahir dar university
 
OEE Target - ¿What is the basis for your current OEE goal?
OEE Target - ¿What is the basis for your current OEE goal?OEE Target - ¿What is the basis for your current OEE goal?
OEE Target - ¿What is the basis for your current OEE goal?Jesús Cañada
 
Equipment reliability l2
Equipment reliability l2Equipment reliability l2
Equipment reliability l2Matthew Clemens
 
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...IRJET Journal
 
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...IRJET Journal
 
Industrial Engineering Tools & Activities of a RMG !!!
Industrial Engineering Tools & Activities of a RMG !!!Industrial Engineering Tools & Activities of a RMG !!!
Industrial Engineering Tools & Activities of a RMG !!!Mahibur Rahman
 
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing IndustryOverall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing IndustryInfoStream Solutions
 
Test Metrics in Agile - powerful tool to support changes - Zavertailo Iuliia
Test Metrics in Agile - powerful tool to support changes - Zavertailo IuliiaTest Metrics in Agile - powerful tool to support changes - Zavertailo Iuliia
Test Metrics in Agile - powerful tool to support changes - Zavertailo IuliiaYulia Zavertailo
 
The Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing ProductivityThe Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing ProductivityCorey Vodvarka
 
The Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing ProductivityThe Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing ProductivityJason Corder
 
OEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityOEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityParsec_Automation_Corp
 

Similar to The reliability of the OEE indicator (20)

OEE.pptx
OEE.pptxOEE.pptx
OEE.pptx
 
Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1
 
TPM Loss Analysis
TPM  Loss AnalysisTPM  Loss Analysis
TPM Loss Analysis
 
Maintainance engineering and management
Maintainance engineering and managementMaintainance engineering and management
Maintainance engineering and management
 
OEE Target - ¿What is the basis for your current OEE goal?
OEE Target - ¿What is the basis for your current OEE goal?OEE Target - ¿What is the basis for your current OEE goal?
OEE Target - ¿What is the basis for your current OEE goal?
 
Equipment reliability l2
Equipment reliability l2Equipment reliability l2
Equipment reliability l2
 
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
 
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
 
Industrial Engineering Tools & Activities of a RMG !!!
Industrial Engineering Tools & Activities of a RMG !!!Industrial Engineering Tools & Activities of a RMG !!!
Industrial Engineering Tools & Activities of a RMG !!!
 
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing IndustryOverall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
 
lean & agile
lean & agilelean & agile
lean & agile
 
The mystery of OEE
The mystery of OEEThe mystery of OEE
The mystery of OEE
 
Satish.S -Resume.
Satish.S -Resume.Satish.S -Resume.
Satish.S -Resume.
 
Test Metrics in Agile - powerful tool to support changes - Zavertailo Iuliia
Test Metrics in Agile - powerful tool to support changes - Zavertailo IuliiaTest Metrics in Agile - powerful tool to support changes - Zavertailo Iuliia
Test Metrics in Agile - powerful tool to support changes - Zavertailo Iuliia
 
The Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing ProductivityThe Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing Productivity
 
My path to you
My path to youMy path to you
My path to you
 
The Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing ProductivityThe Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing Productivity
 
OEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityOEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing Productivity
 
I012536474
I012536474I012536474
I012536474
 
Ofs whitepaper
Ofs whitepaperOfs whitepaper
Ofs whitepaper
 

Recently uploaded

Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfAyahmorsy
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfAbrahamGadissa
 
Pharmacy management system project report..pdf
Pharmacy management system project report..pdfPharmacy management system project report..pdf
Pharmacy management system project report..pdfKamal Acharya
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringDr. Radhey Shyam
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringC Sai Kiran
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edgePaco Orozco
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGKOUSTAV SARKAR
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxVishalDeshpande27
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industriesMuhammadTufail242431
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopEmre Günaydın
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationDr. Radhey Shyam
 
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfKamal Acharya
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsAtif Razi
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
AI for workflow automation Use cases applications benefits and development.pdf
AI for workflow automation Use cases applications benefits and development.pdfAI for workflow automation Use cases applications benefits and development.pdf
AI for workflow automation Use cases applications benefits and development.pdfmahaffeycheryld
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfKamal Acharya
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationRobbie Edward Sayers
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Krakówbim.edu.pl
 

Recently uploaded (20)

Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 
Pharmacy management system project report..pdf
Pharmacy management system project report..pdfPharmacy management system project report..pdf
Pharmacy management system project report..pdf
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptx
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
 
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
AI for workflow automation Use cases applications benefits and development.pdf
AI for workflow automation Use cases applications benefits and development.pdfAI for workflow automation Use cases applications benefits and development.pdf
AI for workflow automation Use cases applications benefits and development.pdf
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 

The reliability of the OEE indicator

  • 1. The reliability of the OEE indicator iper – Industrial Performance 2015-01-19 joao.leite@iper.pt Reliability bathtub curve applied to the OEE measurable components
  • 2. OEE definition iper – Industrial Performance 2015-01-19 joao.leite@iper.pt OEE - Overall equipment effectiveness OEE breaks the performance of a manufacturing unit into three separate but measurable components:  Availability Availability = uptime/ available time  Performance Performance = (Parts Produced * Ideal Cycle Time) / Operating time  Quality Quality = (Units produced - defective units) / (Units produced)
  • 3. Reliability applied to the Availability iper – Industrial Performance 2015-01-19 joao.leite@iper.pt How to improve: - Sample productions prior to start of the serial production ( TRIAL RUNS ) - Operators training How to improve: - Implementation of a robust maintenance plan - Machine FMEA
  • 4. Reliability applied to the Performance iper – Industrial Performance 2015-01-19 joao.leite@iper.pt How to improve: - Sample productions prior to start of the serial production ( TRIAL RUNS ) How to improve: - Implementation of a robust maintenance plan - Machine FMEA
  • 5. Reliability applied to the Quality iper – Industrial Performance 2015-01-19 joao.leite@iper.pt How to improve: - Feasibility Analysis - Product FMEA - Process FMEA How to improve: - Implementation of a robust maintenance plan
  • 6. iper – Industrial Performance 2015-01-19 joao.leite@iper.pt To be continued…