SlideShare a Scribd company logo
1 of 55
Chapter-01: Introduction
1.1 Introduction: The promising solutions to the environmental problems associated with
fossil fuels lies in the development and use of Renewable Energy Sources (RES). RES may be
obtained from solar radiation, wind power, waves, heat from earth’s core as well as animal and
plant wastes. They also provide diversity of energy supply given that they are products of nature
and there is no issue of reserves being depleted. Furthermore, its expansion offers economic
opportunities such as regional development and job opportunities.
However, the numerous benefits of RES are often ignored as investors have declined project
financing Renewable Energy Power Projects (REP) due to the high level of perceived risks
associated with them. Capital for project financing energy projects can be raised through a
combination of debt and equity investment.
In contrast to fossil fuels that were formed more than 300 million years ago, renewable energy
comes from sources that are constantly replenished. For example, the power of resources such as
the sun and the wind do not diminish over time. Renewable resources makes it possible to reduce
our dependence on foreign oil, increase the security of our energy supply, mitigate environmental
impacts, and provide economic development opportunities in rural areas.
There are many commercially proven renewable energy technologies which can help reduce the
amount of money spent on energy consumption and create additional revenues through the sale of
power to the electricity grid. These technologies can be used on a small-scale to support
operations on the farm or they can be large enough to provide power for an entire community.
Project finance has intrigued me ever since I was introduced to it while working as an intern at
Infrastructure Development Company Limited (IDCOL).I got more interested about the
uniqueness of project financing whenever I came to know that IDCOL is financing without any
security other than the project itself. Project financing may be defined as the raising of funds to
finance an economically separable capital investment project in which the providers of the funds
look primarily to the cash flow from the project as the source of funds to service their loans and
provide the return of and a return on their equity invested in the project (John D. Finnerty, 1996).
Project finance is the long term financing of infrastructure and industrial projects based upon the
projected cash flows of the project rather than the balance sheets of the project sponsors. Standard
& Poor's defines a project company as a group of agreements and contracts between lenders,
project sponsors, and other interested parties that creates a form of business organization that will
issue a finite amount of debt on inception; will operate in a focused line of business; and will ask
that lenders look only to a specific asset to generate cash flow as the sole source of principal and
interest payments and collateral. Usually, a project financing structure involves a number of
equity investors, known as sponsors, as well as a syndicate of banks or other lending institutions
that provide loans to the operation. The loans are most commonly non-recourse loans, which are
secured by the project assets and paid entirely from project cash flow, rather than from the
1
general assets or creditworthiness of the project sponsors. Project finance is only possible when
the project is capable of producing enough cash to cover all operating and debt-servicing
expenses over the whole tenor of the debt.
Project financing typically includes the following basic features:
1. An agreement by financially responsible parties to complete the project and, toward that end, to
make available to the project all funds necessary to achieve completion.
2. An agreement by financially responsible parties (typically taking the form of a contract for the
purchase of project output) that, when project completion occurs and operations commence, the
project will have available sufficient cash to enable it to meet all its operating expenses and debt
service requirements.
3. Assurances by financially responsible parties that, in the event a disruption in operation occurs
and funds are required to restore the project to operating condition, the necessary funds will be
made available through insurance recoveries, advances against future deliveries, or some other
means.
Project financing should be distinguished from conventional direct financing, or what may be
termed financing on a firm's general credit. In connection with a conventional direct financing,
lenders to the firm look to the firm's entire asset portfolio to generate the cash flow to service
their loans. The assets and their financing are integrated into the firm's asset and liability
portfolios. Often, such loans are not secured by any pledge of collateral. The critical
distinguishing feature of a project financing is that the project is a distinct legal entity; project
assets, project-related contracts, and project cash flow are segregated to a substantial degree from
the sponsoring entity. The financing structure is designed to allocate financial returns and risks
more efficiently than a conventional financing structure. In a project financing, the sponsors
provide, at most, limited recourse to cash flows from, their other assets that are not part of the
project. Also, they typically pledge the project assets, but none of their other assets, to secure the
project loans.
1.2 Statement of the Problem: Unlimited access to energy sources is essential for
modern development. Especially, for a developing country like Bangladesh, having a sustained
energy supply is a prerequisite for economic growth. To alleviate poverty in the face of limited
resources and high population density, Bangladesh requires a sustainable economic growth model
where renewable energy sources are used properly. Bangladesh has the opportunity to meet its
future power demands and thus economic growth through renewable energy. Using renewable
energy appropriately may improve rural people’s quality of life and provide income-generating
opportunities that redress social inequities and environmental damage in Bangladesh. To achieve
this objective proper channel of financing in renewable energy is extremely necessary. There has
been always a big question whether the financing in this sector is adequate or not, to what extent
the availability of project financing in renewable energy there is and whether the covenants of
loan or financing are logical and bearable or not.
2
1.3 Objectives of the Study: The size and economic potential of the renewable energy
resources in Bangladesh are yet to be determined and the capacity of renewable energy
development is presently low. Among others one of the objectives of the study is to explore
the extent to which renewable energy technologies (RETs), such as solar home systems
(SHS) and biogas digesters, can provide reliable and affordable energy services in the rural
regions of Bangladesh. The paper’s another objective is finding out how renewable energies are
different from conventional energy projects and what impact this has on their financing needs and
ability to attract finance. It describes the various types of financing instruments needed for RE
plant development and explains the barriers and financing gaps that today make it difficult to
raise capital for RE. The main objectives of this study are as follows:
• Assessing the current scenario of renewable energy project financing in Bangladesh.
• Comparing the Incentives in Renewable Energy Policies over the countries
• Measuring the impact of renewable energy projects towards the society.
• Defining the structures of project finance transactions in Bangladesh.
• Unveiling the factors that limit the project finance of renewable energy projects.
• Assessing the Renewable Energy Potential in Bangladesh.
• Evaluating the Role of IDCOL in renewable energy project financing in Bangladesh.
• Overall evaluation of Project Financing in Bangladesh.
Critically evaluating the renewable energy project financing, making some recommendations are
also the objective of this study to foster the growth of Renewable Energy Project Financing in
Bangladesh.
1.4 Rationale of the Study: Energy is a basic need of human society and has rightly
been termed by many as the „life-blood‟ which keeps human civilization progressing. Without
adequate access to modern energy, poor countries can be trapped in a vicious circle of poverty,
social instability and underdevelopment (World Energy Council 1999). One such energy starved
country is Bangladesh. In 2003, Bangladesh’s energy consumption per capita was only 157
kilograms of oil equivalent (Kgoe) which is one-tenth of the world’s energy consumption per
capita (Hussain et al. 2007). Bangladesh’s endowment of conventional energy resources is neither
adequate nor varied, as a result of which it suffers from an acute energy crisis and crippling
power shortages. However, Bangladesh is endowed with relatively abundant renewable energy
resources such as solar and biogas energy. Without proper financing the growth of this eco-
friendly renewable energy is impossible in countries like Bangladesh.
As a developing country, Bangladesh is facing intimidating energy challenges that are merely
likely to worsen over the next few years. Furthermore, over 50% of Bangladesh's inhabitants live
without electricity. Because it is expensive, village areas are generally not supplied by grid-
connected electricity. These issues really bring the necessity of finding some other ways to
improve this situation. That is why this study has been done.
3
1.5 Methodology: It is a desk research which has involved the collection of previous
research reports, newspapers and journal content also collection, collation and synthesis of
existing project reports of governmental and nongovernmental organizations interventions
relating to renewable energy infrastructure of Bangladesh. Here a real project of IDCOL is taken
to analyze the process of project financing in details. Beside of this, to get the real scenario of
renewable energy project financing several discussions was conducted with the officials of
IDCOL.
1.6 Limitation of the Study: Although this study is carefully prepared, I am still aware of
its limitations and shortcomings. Some of the limitations are as follows:
• Lack of proper knowledge on project financing and renewable energy as I am not an
expert in these fields.
• Lack of available prior research studies on the topic.
• Could not get access to the confidential information of IDCOL. As a result there might be
lacking of right or biased information.
• Lacking of real world experience as it was totally a desk research.
1.7 Literature Review:
The finance literature on the subject of project financing is still in its formative stages. Careful
analyses of the true benefits of project financing have only recently begun to appear. Shah and
Thakor (1987) were among the first to provide a carefully thought-out analysis of the rationale for
project financing. They explained why project financing seems most appropriate for very large,
high-risk projects. Unfortunately, their analysis was based on only two projects. Chen, Kensinger,
and Martin (1989) observed that project financing is widely used for medium-size, low-risk
projects, such as cogeneration facilities. They documented that project financing has become the
dominant method of financing independent electric power generating facilities, including
cogeneration projects developed for several Fortune 500 companies. At best, then, Shah and
Thakor's theory appears incomplete.
Mao (1982) noted that in order for a project to secure financing as a separate economic entity, the
relationships among the participants must be spelled out in detailed contracts.' Worenklein (1981)
addressed the project's requirement for "sources of credit support" in the form of contracts to
purchase output from the project and/or to supply the necessary inputs at controlled cost. The
project's sponsors typically do not guarantee repayment of the project's debt, so creditworthy
parties must provide credit support through such contractual undertakings.
4
Chapter-02: Renewable energy in Bangladesh
Electrification is a constitutional commitment of Bangladesh government. Despite this only 30%
of the entire population has access to electricity. Rural electrification Board (REB) provides
electricity to only a certain portion of more than 80% of population living in rural areas. Rural
electrification is primarily done through grid-expansion and in many remote areas of the country
electrification through conventional means is not economically viable. Bangladesh,
geographically being closest to the equator, is recipient of immense amount of solar energy
almost entire year. Solar energy thus presents an enormous potential for Bangladesh to be utilized
as an alternative to fossil fuel for production of energy.
Renewable energy is energy that is replenished by nature and comes from natural resources,
including the sun, tides, rain, wind, and geothermal sources. It is “captured” and distributed via a
number of technologies, including wind turbines, hydroelectric power stations, photovoltaic and
heat engines, ethanol fuel plants, and geothermal heat pumps, among others (Michael Waldhier,
May 2010). Renewable energy effectively utilizes natural resources such as sunlight, wind, tides
and geothermal heat, which are naturally replenished. Renewable energy technologies range from
solar power, wind power, and hydroelectricity to biomass and biofuels. About 13 percent of
world’s primary energy comes from renewable, with most of this coming from traditional
biomass like wood-burning. Hydropower is the next largest source, providing about 2-3%, and
modern technologies like geothermal, wind, solar, and marine energy together produce less than
1% of total world energy demand.
Renewable energy is a relatively new concept in Bangladesh. However, successful
implementation of renewable energy technology such as solar home system indicates that with
mass promotion, public awareness, private sector participation, and necessary financial and
government assistance, renewable energy sector is poised for long term sustainability in
Bangladesh. Renewable energy sources presently used in Bangladesh include solar, wind, hydro,
biogas and biomass. Of these solar has, so far, proven to be most popular and accessible in
Bangladesh. Total yearly amount of solar radiation available on surface of Bangladesh is about
2.4x10 14
kWh while at present electricity generation is 2.0 x 10 10
kWh. So, solar radiation
available is almost 10000 times the present electricity generation of Bangladesh. If 1/1000th
part
of Bangladesh is used to produce electricity from solar with 10% efficiency, same amount of
electricity may be generated as produced right now.
In rural areas of Bangladesh standalone solar home systems (SHS) are being used for basic
electrification purpose in absence of conventional grid electrification. About 180,000 households
are using SHS in Bangladesh which amounts to 0.60% of the country’s entire population.
Infrastructure Development Company Limited (IDCOL), with assistance from different local non
government organizations (NGOs) and micro finance institutions (MFIs), has been instrumental
in promotion and commercialization of SHS in Bangladesh.
5
2.1Energy Indicators of Bangladesh:2.1Energy Indicators of Bangladesh:
Total energy consumption :16.6 million tones oil equivalent
Per capita energy consumption :171 kg oil equivalent
Energy related CO2 emission :42.74 mmt
Per capital CO2 emission :0.3 mt
Energy consumption : Conventional energy (54%), Biomass(46%)
Conventional energy consumption : Natural gas: 1850-1900 MMscfd (April 2009)
Oil: 3.5 MT (2008)
Coal: 3.8 MT (2008)
Access to electricity : 45%
Per capital electricity consumption : 145 kWh annum
Source: http://data.un.org/CountryProfile.aspx?crName=Bangladesh#Environment
Conventional energy consumption (2007)
Oil (thousand barrels per day) 91
Natural gas (billion cubic feet) 554
Coal (million Short Tons) 0.8
Source: nationmaster (www.nationmaster.com/bangladesh
Sources of energy consumption-2007-http://www.nationmaster.com/red/country/bg-
bangladesh/ene-energy&b_define=1
Fig: Percentage of usage of Conventional and Biomass energy
Graph: Demand Supply Gap in Five Years
6
Year Demand-Supply Gap (MW)
2009 1777
2010 1427
2011 1843
2012 1853
2013 1485
2014 1763
Source: http://www.economywatch.com/economic-statistics/country/Bangladesh/
Assumptions
 Demand-Supply Gap (Load Shedding) is increasing. By the year 2014 this gap will be
around 1750 MW
 Gas supply uncertainty to 1620 MW projects under process may lead to more than 3000
MW load shedding in the year 2014
2.2 Role played by the government: The Government of Bangladesh is so generous
towards the financing of renewable energy project and to foster the growth of renewable energy
in Bangladesh.
 Renewable Energy Policy has been adopted by the Government of Bangladesh on 18
December 2008.
 The policy has set a target of generating 5% of the total electricity from renewable
sources by 2015 and 10% by 2020.
 A focal point called Sustainable Energy Development Agency (SEDA) will coordinate
activities related to the development of renewable energy technologies and financing
mechanisms.
7
 For electricity less than 5 MW generated from renewable energy projects may be
purchased by power utilities or any consumer.
 All renewable energy equipments and related raw materials will be exempt from 15%
VAT and companies will be exempt from corporate income tax for a period of 5 years;
 Private sector participation including joint venture initiatives in renewable energy
development will be encouraged and promoted;
 An incentive tariff has been proposed for electricity generated from renewable sources
which may be 10% higher than the highest purchase price of electricity.
 Bangladesh Bank, the Central Bank, has launched a revolving fund of BDT 2 billion for
refinancing renewable energy projects i.e. solar energy, biogas and effluent treatment
plants through commercials at concessionary terms and conditions.
2.3 Comparison of Incentives in Renewable Energy Policies over the
countries:
Incentives in RE Policy of
Bangladesh
Incentives in RE Policy of Other
Countries
Proposed Incentives
for RE Policy of
Bangladesh
Institutional Arrangement –
Sustainable Energy Development
Agency (SEDA) shall be established
VAT Exemption – All renewable
energy equipments and related raw
materials in producing renewable
energy equipments will be exempted
from charging 15% VAT.
Micro-credit Support System – In
addition to commercial lending, a
network of micro-credit support
system will be established especially
in rural and remote areas to provide
financial support for purchases of
renewable energy equipment.
Corporate Income Tax Exemption –
Renewable energy project investors
both in public and private sectors shall
be exempted from corporate income
tax for a period of 5 years.
Feed–in–Tariff – An incentive tariff
may be considered for electricity
generated from renewable energy
sources which may be 10% higher
than the highest purchase price of
electricity by the utility from private
generators.
France
Feed–in–Tariff: 28.8 BDT/kWh
Construction bonus: 24 BDT/kWh in the
mainland France.
Germany
The basic rate of payment for solar
generated electricity is 43.87 BDT/kWh
If the plant is attached to or integrated on
top of a building, the fee is 50-55
BDT/kWh
United Kingdom
Currently, price of electricity from
Renewable Obligation is 37.29 BDT/kWh
United States
Production tax credit (PTC) benefit: 2.37
BDT/ kWh generation
Investment tax credit (ITC): 30% for the
solar systems buyers
Grant: up to 30% of the property’s value.
India
Direct taxes - 100 per cent depreciation in
the first year of installation of the project
Exemption/reduction in excise duty
Exemption from Central Sales Tax and
customs duty concessions on the import
of material, components and equipment
used in RE projects
• Investment
subsidies or rebates
• Sales tax
exemptions – at the
point of sale
• Production tax
credit – tax credits
per kWh
generation
• Net metering – for
grid connected
systems
• Feed–in–Tariff –
more incentive
tariff is required
8
Chapter-03: Role of IDCOL in renewable energy project
financing in Bangladesh:
Infrastructure Development Company Limited (IDCOL) was established on 14 May 1997 as a
joint initiative of the Government of Bangladesh (GoB) and the World Bank. The Company was
licensed by the Bangladesh Bank as a Non Bank Financial Institution (NBFI) on 5 January 1998.
Since its inception, IDCOL is playing a major role in bridging the financing gap for developing
medium and large-scale infrastructure as well as renewable energy projects in Bangladesh.
Through its participation in financing of infrastructure projects, IDCOL expects to serve as a
catalyst in mobilizing private debt and equity financing. In renewable energy projects, however,
IDCOL provides subsidy, soft financing and necessary technical support to the private sector with
an objective to energize rural Bangladesh in a sustainable manner.
Renewable energy is a relatively new concept in Bangladesh. In 2002, IDCOL, with support from
the World Bank and Global Environmental Facility (GEF), started implementing the first
comprehensive renewable energy program in Bangladesh by disseminating solar home systems in
the off-grid rural areas. In 2006, with support from SNV, Netherlands and KfW, Germany,
IDCOL undertook a nationwide program on domestic biogas. Lately, IDCOL started promoting
new and emerging renewable energy technologies by financing several pilot projects i.e. biomass
gasification based power plant, electricity from biogas, solar irrigation pumps etc. Today, IDCOL
has emerged as the largest promoter and financier in the renewable energy sector of Bangladesh.
IDCOL’S INVESTMENT PORTFOLIO
Sector wise loan disbursement as of 30 June 2009
Power, 52.8%
Renewable Energy,
31.9%
Telecommunication,
14.1%ICT, 0.4%
Gas, 0.2%
Ports, 0.6%
Source: Investment department, IDCOL
9
Key Achievement (The Punch- line)
3.1 IDCOL’s role in power sector of Bangladesh: Until August 2009, IDCOL
financed a total of USD 103 million in traditional power projects financing a total generation
capacity of 725.35 MW. The USD 80 million loan channeled by IDCOL to the 450-MW
Meghnaghat Power Plan, sourced from the World Bank, is the largest private sector financing in
Bangladesh.
3.1.1 Telecommunication and IT Projects financed by IDCOL: IDCOL financed network
expansion projects of telecommunication operators, broadband a wireless access network project,
nationwide telecommunication transmission network project, VSAT hub station project,
international gateway services network, and several other IT projects. Total loan amounts in these
projects were BDT 2,500 million.
3.1.2 IDCOL’S Solar Home System (SHS) Program: IDCOL undertook its solar program
in January 2003 with the support from International Development Association (IDA) and Global
Environmental Facility (GEF) to fulfill basic electricity requirements in the rural areas of
Bangladesh. Under the program, IDCOL
intended to provide both grant and
refinancing to 50,000 solar home systems
(SHS) over a period of five-and-half years
[January 2003 - June 2008].
SHS is a convenient mode of supplying
power for small electrical loads such as
lights, radio/cassette players and black and
white TV. Although available for limited
number of hours in a day the supply is
reliable and the system can be managed
with a little training. The main
components of an SHS are a solar panel, a battery and a charge controller.
The program is being implemented through several Partner Organizations (POs) selected from
NGOs/MFIs/Private Companies. So far thirteen POs namely: Grameen Shakti, BRAC
Foundation, COAST Trust, TMSS, SRIZONY Bangladesh, CMES, IDF, Shubashati, SINGER
Bangladesh, UBOMUS, DORP, BRIDGE and PMUK have signed Participation Agreements
(PA) with IDCOL to participate in the solar program. The role of the PO is to select the project
areas and potential customers, extend loans, install the systems and provide maintenance support.
IDCOL provides grants and refinance, sets technical specification for solar equipment, develops
publicity materials, provides training, and monitors PO’s performance.
Grant is provided to lower costs of SHS and to build institutional capacity of the POs. IDCOL’s
principal objective is the commercialization of SHS. Therefore, it has adopted a policy of
reducing grant with the progress of the project. IDCOL also offers soft loans of 10-year maturity
with 2-year grace period at 6% interest per annum to its POs. Usually, IDCOL does not require
10
any collateral or security for the loan, except for a lien created on the project accounts. IDCOL
conducts physical verification of the SHSs installed. It releases grants and refinance amounts only
if the inspection result is satisfactory.
IDCOL has achieved the target installation of 50,000 SHSs in August 2005, three years ahead of
the project completion period and US$ 2 million below the estimated costs. Following the success
of IDCOL’s solar program, the World Bank has extended further support for financing of
additional 60,000 SHSs. KfW has also signed a Finance and Program Agreement to provide EUR
16.5 million as grant to government to be used for further expansion of the program. To mitigate
the gap between IDA and KfW financing, GTZ has agreed to provide grant financing for 28,000
SHSs. In total, IDCOL will finance 198,000 SHSs by 2009. Up to 30 June 2006, a total of 76,607
SHSs have been installed under the program. Division wise SHS installations up to 30 June 2006
are shown below:
Division No of
Installations
Division No of
Installations
Division No of
Installations
Barisal 11,385 Khulna 14,500 Rajshahi 9,886
Chittagong 18,085 Dhaka 13,303 Sylhet 9,447
Total 76,607
Source: Investment department, IDCOL
Two committees namely Operations Committee (OC) and Technical Standards Committee (TSC),
coordinate various aspects of implementation of the program. OC consisting of representatives
from POs and IDCOL officials meets once in every month to look after the operational aspects of
the solar program. TSC determines technical standards for equipment to be financed, review the
product credentials submitted by dealers, and approve the eligible equipment. IDCOL also
conducts training program to build awareness among the staff of the POs’ and the consumers.
11
Technical
Standards
Committee
Operations
Committee
Household
IDCOL MFIs
Suppliers
Seeks Approval
Provides Approval
Supplies
Equipment
Sell systems
& channel
Grant A
Seeks Grant & Refinancing
Provide Grant A, B & Refinancing
Seek
operations
related
solutions
Provide
solutions
Pays for
Equipment
Downpayment
& monthly
installments
Fig: IDCOL Solar Programme – At a Glance
The program has brought in positive changes in the economy of the rural people. Now customers
are using SHS in the advantage of their income generating activities. Students are also getting
benefits through extended hour of studies at night. In addition, the use of TV and radio has
enhanced rural people’s access to the outer world. A good number of job opportunities, both for
skilled and unskilled manpower, have been created. Till March 2006, some 1,000 new jobs have
been created by the program. The program also has a positive impact on our local manufacturing
industry. Except for the PV module, other components of SHS are now produced locally.
3.1.3 National Domestic Biogas and Manure Program:
IDCOL is implementing National Domestic Biogas and Manure Programme (NDBMP) with
support from GoB, SNV Netherlands and KfW. Under the project a total of 60,000 domestic
sized biogas plants will be financed during 2006-2009 all over Bangladesh. The overall objective
of the NDBMP is to further develop and disseminate domestic biogas plants in rural areas with
the ultimate goal to establish a sustainable and commercial biogas sector in Bangladesh.
12
Gas produced through these plants is used for cooking purposes and lighting of rural households.
In addition, the slurry, by-product of biogas plants, being a very good organic fertilizer is used to
maintain soil fertility and increase crop production. The slurry is also used as fish feed.
IDCOL is implementing this programme through partner organizations (PO) including private
companies, NGOs, Micro finance institute (MFIs). There are 4 types of POs: (a) Construction
Partner Organizations (CPOs), (b) Lending Partner Organizations (LPOs), (c) Lending and
Construction partner Organizations (LCPOs) and (d) Manufacturing Partner Organization
(MPOs). At present 19 POs are implementing NDBMP.
IDCOL provides Taka 9,000 as investment subsidy to the biogas households who install biogas
plants as per the specifications and standard set by IDCOL/SNV. IDCOL is also providing
refinance covering 80% of the LPOs and LCPOs loan to households at 6% interest rate and 7 year
tenor with 1 year grace period. Total project cost is estimated as EUR 23.61 million and will be
borne by individual households, SNV, KfW and GOB.
13
Chapter-4: Importance and limitations of REP financing
4.1 Importance of Project Financing For Rep:
•For REP, neither the developer nor the purchasers can self finance. Majorities are not sufficiently
capitalized and do not have enough track record to attempt corporate balance sheet financing.
•The public sector which has invested a considerable amount of tax payers’ money in the
technology through Research and Development (R&D) is typically not appropriate as the source
of finance. The funds that are available are also not adequate for such large scale deployment
efforts.
•In the private sector the traditional form of energy finance which is venture capital, is too
expensive to use for financing the REP.
•Developers may not want to solely bear risks associated with the project.
•Since it is an off balance sheet loan, small sized developers would be free to pursue several
projects at the same time with limited negative balance sheet impacts.
4.2 Factors limiting project finance of rep:
♦ Many projects are perceived by the financial community to have high resource and
technology risks. These real and perceived risks result in financing that is more costly than that
available to more traditional sources.
♦ Since RE technology is relatively new, financial institutions lack experience in evaluating
risks associated with REPP. Furthermore, rapidly changing technology and a shortage of RE
technology engineers means that lenders do not have the technical know how to assess and
monitor many REPs.
♦ The renewable industry and RE projects are small compared to traditional power plants.
Lenders are usually not interested in small transactions. Even where finance is available, the
transaction costs are much higher for smaller REP because many of the same financing and
documentation processes must be followed irrespective of the size of the project.
♦ REPP can only operate when their resources are available. The intermittent nature of RES
means they generate less cash flow than fossil fuel fired plants. This provides lower margins for
project financing and puts pressure on costs associated with overhead and maintenance costs.
♦ The process of arranging financing is time consuming.
4.3 Need for Renewable Energy4.3 Need for Renewable Energy
 To ensure energy security
– 70% of Bangladesh's total commercial energy is provided by natural gas and the
remainder almost entirely provided by imported oil, hydropower and coal.
– These sources are likely to be depleted by 2020.
 To reduce negative environmental consequences
– Climatic change will eventually cause increase in sea level- one meter sea level
rise will inundate more than 15 percent of Bangladesh, displacing more than 13
million people and cut into the crucial rice crop.
 To supplement Government’s view on:
14
– Electricity for all by 2020.
– Government has set a target to meet 5% of total power demand by 2015 and 10%
of total power demand by 2020 from renewable energy sources.
 To reach out to off-grid areas where grid electricity is not available:
– More than two third of the nearly 15 million households of Bangladesh lack
access to electricity
– Two approaches might be followed to provide electricity to off-grid areas:
• Individual or household options for dispersed population
• Community or private sector initiatives involving mini-grids for
distributed supply of power
4.4 Renewable Energy4.4 Renewable Energy PotentialPotential of Bangladeshof Bangladesh::
 Solar energy
– Being located near the Equator, the country is recipient of sufficient sunshine
round the year
– SHS can be easily installed and maintained with little training
– 6 million solar home systems in off-grid areas – 330 MW of electricity
– 2 hundred thousand solar irrigation pumps – 1000 MW of electricity
– Solar mini grid
– Solar thermal power plant
 Biogas
– Cattle population is about 24.19 million (1996) yielding about 242 million kg of
cattle wastes per day with a potential for construction of 3.46 million 2.4 m3
biogas plant.
– Moreover, using poultry droppings alone, domestic sized plants are technically
feasible in 80,000 poultry farms
Chapter-05: Introduction to Project Finance
15
5.1 What Is Project Finance?
The basic premise of project finance is that lenders loan money for the development of a project
solely based on the specific project’s risks and future cash flows. As such, project finance is a
method of financing in which the lenders to a project have either no recourse or only limited
recourse to the parent company that develops or “sponsors” the project (the “Sponsor”). Non-
recourse refers to the lenders’ inability to access the capital or assets of the Sponsor to repay the
debt incurred by the special purpose entity that owns the project (the “Project Company”). In
cases where project financings are limited recourse as opposed to truly non-recourse, the
Sponsor’s capital may be at risk only for specific purposes and in specific (limited) amounts set
forth in the project financing documentation.
Project financing has been used in various ways for many years, but in the 1970s and 1980s it
emerged as a leading way of financing large infrastructure projects that might otherwise be too
expensive or speculative for any one individual investor to carry on its corporate balance sheet.
Project financing has been particularly important to project development in emerging markets,
with participants often relying on guarantees, long-term off-take or purchase agreements, or other
contractual relationships with the host sovereign or its commercial appendages to ensure the long-
term viability of individual projects. These were typically backstopped by multilateral lending
agencies that mitigated some of the “political” risks to which the project lenders (and, sometimes,
equity investors) were exposed.
5.2 What Underpins Project Finance?
As a general (if not universal) rule, lenders will not forgo recourse to a project’s Sponsor unless
there is a projected revenue stream from the project that can be secured for purposes of ensuring
repayment of the loans. In the case of large wind and solar power projects, this revenue is
typically generated from a power purchase agreement (“PPA”) with the local utility, under which
the project may be able to utilize the creditworthiness of the utility to reduce its borrowing costs.
While the wind power market has matured significantly in the past five years, leading to the
successful project financing of “merchant” projects in the absence of long-term PPAs, Solar
Projects are generally not yet able to be project financed in such a manner. In merchant power
projects, lenders are able to receive assurance of the project’s ability to repay its debt by focusing
on commodity hedging, collateral values, and the income to be produced based on historical and
forward-looking power price curves and fully developed markets. In non-power generation
contexts, the project’s revenue stream may be a long-term operating agreement (e.g., in the case
of toll roads), a capacity purchase agreement (e.g., in the case of transmission lines), a production
sharing agreement (e.g., in the case of oil field development), or a series of short-term and spot
sales into commodity markets (e.g., in the case of biofuels projects).
While project finance lenders clearly prefer a long-term contract that ensures a relatively
consistent and guaranteed revenue stream (including assured margins over the cost of inputs), in
the context of some industries, lenders have determined that sufficient revenues to support the
project’s debt are of a high enough probability that they will provide debt financing without a
long-term off-take agreement. Solar Projects, due to their peak period production, high marginal
16
costs, and lack of demonstrated merchant capabilities, are not at this time viewed as “project
financeable” without PPAs that cover all or substantially all of their output. Solar Projects’ lack
of merchant viability is exacerbated by the fact that the southwest United States (the region most
appropriate for utility-scale solar power development) does not have a mature merchant power
market that functions in the absence of long-term bilateral sales agreements. The dependence of
large-scale solar projects on the PPA model is not expected to change in the short to intermediate
term.
5.3 When to Project Finance?
One of the primary benefits of project financing is that the debt is held at the level of the Project
Company and not on the corporate books of the Sponsor. When modeling projects and projected
income, the internal rate of return of Sponsors and other project-level equity investors can
increase dramatically once a project is fully leveraged. Sponsors are frequently able to recover
development costs at the closing of the project financing and put their money into other projects.
Another benefit of project financing is the protection of key Sponsor assets, such as intellectual
property, key personnel, and investments in other projects and other assets, in the case of the
Project Company’s bankruptcy, debt default, or foreclosure. Moreover, project financing allows
for a wide variety of tax structuring opportunities, particularly in the context of monetizing tax
incentives. On the other hand, project financing is document-intensive, time-consuming, and
expensive to consummate. It is not atypical that administrative and closing costs, when factoring
in lenders, consultants, and attorneys fees for all parties, equal several percentage points of the
amount of the loan commitment. Moreover, project financing imposes significant operating
restrictions on each Project Company, including its ability to make equity distributions to the
Sponsor prior to the payment of operating expenses, debt service, and a percentage “sweep” of
additional cash flow. The result is that the decision of whether to reinvest cash flow in the project
does not rest solely with the Sponsor.
Given the pros and cons of project finance, the most relevant initial inquiry for an investor or
developer may be when is project financing possible or most appropriate? The following
questions should be useful in determining if project financing is a realistic opportunity for any
given company:
 Is there an individual project or group of projects of a sufficient size to make either a
standalone or portfolio project financing worthwhile?
 Will there be a revenue stream from the project large enough to support a highly
leveraged debt financing? This is a prerequisite for project financing.
 Will the receipt of revenue be enforceable under contractual rights against a creditworthy
party? This is not necessarily a prerequisite for all project financings, but the absence of a
contract, or questionable creditworthiness of the purchaser, will prompt lender skepticism
and necessitate thorough due diligence regarding future revenue projections.
 Will there be physical assets sufficient to ensure lender repayment in case of foreclosure?
Lenders will want to know that even if the Project Company’s projected revenue stream
does not materialize, they will be able to foreclose on the project’s assets sufficient in
value to “make themselves whole,” either by selling the project outright or operating it
until the debt is repaid.
17
 Is there a significant level of technology risk? While in many project financings,
technology may be relatively new or cutting edge, project finance lenders almost never
want to be the first to finance an untested technology. Demonstrated successful use in
some context will often be necessary to secure project financing.
 Does the project have contractual relationships with reputable companies for services key
to the success of the project or the technology it employs? Lenders will be less likely to
lend to a project the success of which depends solely on a few talented individuals who
may depart, leaving the project unable to meet its potential.
 Is the Sponsor ultimately willing to “risk the project”? In other words, once project
financing is completed, the Sponsor loses the ability to determine how the vast majority
of the project’s revenue is spent. In the event a project becomes uneconomic and unable
to service its debt, the only option besides refinancing the debt may be to turn over the
project to the lenders (voluntarily or involuntarily), with the corresponding loss of the
Sponsor’s investment in the project.
 Is the Sponsor looking for a quick exit? Once project-financed, divestiture opportunities
are complicated by the requirement of lender consent, and potential purchasers will be
thoroughly examined by lenders for development and operational expertise as well as
creditworthiness.
 Are Sponsors willing to grant rights of high-level oversight regarding the project’s
development and operation to project finance lenders? In many cases the interests of the
Sponsor and the lenders will be aligned, and lenders will tend to defer to the Sponsor’s
developmental expertise. On the other hand, lenders must be viewed as additional project
partners, with veto rights over many significant decisions.
5.4 Project Financing Versus Direct Financing?
Project financing should be compared to direct financing on the sponsor's general credit, when
deciding how best to finance a project whose characteristics would make it suitable for project
financing. It is important to appreciate that just because project financing might be arranged does
not mean that the project should be financed in this manner.
The below figure compares direct financing by the sponsor and project financing, on the basis of
several criteria.
Criterion Direct Financing Project Financing
18
Organization  Large businesses are usually
organized in corporate form.
 Cash flows from different assets
and businesses are commingled.
 The project can be organized as a
partnership or limited liability
company to utilize more efficiently
the tax benefits of ownership.
 Project-related assets and cash
flows are segregated from the
sponsor's other activities.
Control and
monitoring
 Control is vested primarily in
management.
 Board of directors monitors
corporate performance on behalf of
the shareholders.
 Limited direct monitoring is done
by investors.
 Management remains in control but
is subject to closer monitoring than
in a typical corporation.
 Segregation of assets and cash
flows facilitates greater
accountability to investors.
 Contractual arrangements
governing the debt and equity
investments contain covenants and
other provisions that facilitate
monitoring.
Allocation of
risk
 Creditors have full recourse to the
project sponsor.
 Risks are diversified across the
sponsor's portfolio of assets.
 Certain risks can be transferred to
others by purchasing insurance,
engaging in hedging activities, and
so on.
 Creditors typically have limited
recourse-and in some cases, no
recourse-to the project sponsors.
 Creditors' financial exposure is
project specific, although
supplemental credit support
arrangements can at least partially
offset this risk exposure.
Contractual arrangements
redistribute project-related risks.
 Project risks can be allocated
among the parties who are best able
to bear them.
Financial
flexibility
Financing can typically be arranged
quickly.
Financing arrangements are highly
structured and very time-consuming.
structure of
debt
Creditors look to the sponsor's entire
asset portfolio for their debt service.
Creditors look to a specific asset or
pool of assets for their debt service.
Bankruptcy Lenders have the benefit of the
sponsor's entire asset portfolio.
The debt is generally not repayable
from the proceeds of other unrelated
projects.
19
23
Project Finance Corporate Finance
Concession
Contract
Project Company
(SPV)
Lenders
Government
Loan
Re-
paymentSponsor
1
Sponsor
2
Sponsor
3
Users
Tariffs
Services
Concession
Contract
Private Company
Lenders
Government
Loan
Re-
payment
Tariffs
Investment
SPV
Users
Services
Fig: Difference between Project and corporate finance
5.5 Participants of a project finance:
Sponsor:
 Developer of the project
 Project sponsor(s) may consist of an individual but more often is organized as a company
 Sponsors must demonstrate previous track record and experience in managing the project
 Sponsors Insist on long term predictable cash flows.
Project Company:
 Separate entity from sponsors
 Sponsor(s) generally form a special purpose vehicle ("SPV") to own and operate the
project. This SPV is known as Project Company
 Sponsor members are required to make capital investments in the SPV according to the
terms of their share holders’ agreement
 Lenders give loans to the SPV, not to the sponsors
Construction Contractor:
 Construction contractor is the entity that builds the project under an engineering
procurement and construction contract ("EPC").
 EPC contracts are generally fixed price – fixed term.
 Lenders prefer a single EPC contract because it gives them a single-point responsible
party for all activities.
20
 EPC contractor is subject to penalty payment for underperformance.
 Contractor’s involvement is short term in nature.
 Higher (and earlier) profitability.
Lenders:
1. Multilateral and Bilateral Agencies
 The World Bank, EBRD, ADB, African Development Bank etc.
 International Finance Corporation
 Regional development banks, etc.
2. Commercial Lenders
3. Export Credit Agencies
 US Export Import Bank ("US Exim")
 Export Credit Guarantee Department of the United Kingdom ("ECGD")
 Export Credit Agency of France ("COFACE")
 Export Credit Agency of Germany ("KfW").
4. Bond Markets
5. Insurance Companies
Off-taker:
 The entity that is the single purchaser of the project output
 More than one off-taker is very uncommon
 Some Project Financed deals do not have off-takers, e.g.
 toll road
Suppliers
Offtakers
Government
Project
Managers Engineers
Operators
Sponsors
Contractors
Local
Partners
InsurersEquity
Investors
Mezzanine
Investors
Banks
21
 container port
 mass transport system, etc.
 The off-take agreement guarantees purchase of project output
 The payments due under the off-take agreement constitute a major element in
determining the finance-ability of the project.
Operator:
 Responsible for the operation and maintenance of the project in exchange of fee
 Operator is subject to penalty payment for underperformance
 Project company can also be an operator
Input Supplier:
 Responsible for delivery of inputs to the project
 Input supply agreement may be entered into
 Take or pay contract
 Supplier is also subject to penalty payment for underperformance
5.6 Structures of project finance transactions:
Despite the complexity inherent in the nature of the financing, some contend that every project
financing can be fitted into the same basic structure and essentially has the same components.
One proponent of such thinking is Thomas H. Pyle, Managing Director of the Princeton Pacific
Group and project finance lecturer with the Euromoney Institute of Finance.
Pyle calls this prototypical structure “the project finance angel.” The halo of the angel is the
government; the project sponsor is the head; the contractor and operator serve as wings; the
project company is the body; the supplier and customer represent the arms; and, the banks are the
angel’s feet. The outspread arms and the body together also symbolize the project’s throughput -
the tollable commodity that creates the cashflow. The following diagrams illustrate the
transfiguration of the angel into a power plant. Of course, as transactions become more complex,
it is necessary to modify the basic structure.
22
The Project Angel
23
Chapter-06: IDCOL for project financing
6.1 Eligibility to get IDCOL loan for projects:
IDCOL will lend up to a maximum of 40 percent of the total project cost to private sector
sponsored infrastructure projects in Bangladesh that meet the following eligibility criteria:
24
• Priority: Projects should be an integral part of the GOB's priority plan for the relevant
sector/sub-sector.
• Ownership: The project must be majority-owned by the private sector parties. Private
sector parties must hold at least 51% of the project's equity and be significantly involved
in its management for a period of at least 10 years, or the life of the IDCOL loan,
whichever is longer;
• Viability: The sponsors should have a proven track record of successfully developing,
financing and operating similar infrastructure projects in countries at a similar level of
development in Bangladesh;
• Equity: To ensure sponsor's commitment to the project, equity should represent not less
than 20% of the total project cost;
• Technology: The technology proposed for a project should have a successful track record
in countries at a similar level of economic and technological development and
infrastructure support in Bangladesh;
• Procurement: IDCOL, generally, will finance GOB solicited projects. In those cases
where the solicited project satisfies IDA Procurement Guidelines (the Guidelines), the
sponsors will be allowed to follow their own procurement processes for downstream
purchases. In the case of unsolicited projects, or solicited projects that do not conform to
the Guidelines, IDCOL is required to satisfy itself that the "downstream procurement" for
the engineering, procurement and construction (EPC) services required to build the
facility equipment and/or works that are an integral part of such facility, are made in
accordance with the provisions of the Guidelines. In the latter case, IDCOL's loan support
will be limited to the value of the "downstream procurement" made following such
Guidelines;
• Limited Recourse: Projects should be financially viable on their own with robust and
predictable cash flows;
• Environment and Social Framework: Projects should meet GOB and IDCOL
environmental and social assessment criteria; and
• Economic Rate of Return: The economic rate of return of the project should be at least
12 percent.
6.2 Terms & Conditions of IDCOL for project financing:
Interest rates
IDCOL participates in a project's financing plan with either fixed or floating rate. IDCOL prices
its loans in reference to London Inter-Bank Offered Rate (LIBOR), a US dollar denominated
interest rate index that is prevalent in the Euro-markets. Under current pricing, all loans are priced
at a variable rate equal to the prevailing US dollar three-month LIBOR plus a margin set once
each year with reference to current market conditions. Currently, the margins for senior and
subordinated loans are 350 basis points and 400 basis points, respectively. For loans denominated
in BDT, IDCOL sets interest rates with reference to two years Govt. Treasury Bill plus 400 basis
points. Each year, IDCOL Board reviews the company's lending terms and conditions. In case of
syndicated financing IDCOL's interest rate may match with that of other lenders providing similar
25
loans.
As a prudent lender, IDCOL desires and at times may require the borrowers to enter into an
interest rate hedge arrangement to prevent potential project cash flow shortages should LIBOR
increase dramatically. Such a hedge may be arranged in the financial markets by borrowers or by
IDCOL itself. IDCOL provides soft loan in case of rural infrastructure having development
impact. In that case IDCOL’s interest rate may vary from 6% to 9.5% p.a.
Currencies
In cases of IDCOL's US Dollar funding resources, it generally prefers to lend in that currency if
borrowers generate their revenue in that currency or have an appropriate revenue contract
denominated in local currency with an embedded hedge i.e., indexed to US dollars. IDCOL may
also finance projects that do not generate hard currency or whose tariffs do not have indexation
provision, provided that the projects sponsors agree to create a currency depreciation reserve.
Repayment schedule for IDCOL loan is semi annually / quarterly and will be set forth in US
dollar. However, repayment in local currency is permitted provided that repayment is made in
equivalent Bangladesh Taka (BDT) converted at the rate of exchange prevailing at the time of
repayment.
However, IDCOL extends credit in BDT if a project does not have a revenue contract, generates
only local currency and is perceived to have high development impact.
Tenor
Loan tenor depends on the nature of the specific project and the life of the assets financed. Within
this constraint, the final maturity of a senior loan may be for up to 15 years while that for a
subordinated loan may be up to 23 years. The final maturity of a local currency loan is expected
to be between 5 and 10 years depending upon the specific attributes of the project.
Repayment
Repayment is normally in equal semi annually / quarterly installments of principal and interest
with a suitable grace period on repayment of principal. A maximum grace period of 4 years and 8
years, respectively for senior and subordinated loan is permitted and the construction period of
the project will be part of the allowed grace period. Depending upon project needs, the borrower
has the option of using its equity resources to fund the interest due during construction or,
otherwise, co-financing these amounts with draw downs forthcoming from debt commitments. In
the latter case, interest on the loan will be payable from the Commercial Operations Date.
Security
26
IDCOL requires appropriate security for its loans that include inter alia:
• Pledge of shares in the project company and creation of a voting trust permitting lenders to vote
the shares of the company in times of distress;
• Direct agreements with key project participants that allow lenders to "step in" and take over the
project when it is in trouble, without affecting the legality and validity of project agreements;
• First priority legal mortgage on all immovable assets as well as first priority hypothecation on
all movable assets of the project company;
• Assignment of project company rights under all project agreements;
• Assignment to the extent possible of all contractors' and manufacturers' warranties;
• Completion guarantee and other similar support from sponsors; and
• First loss payee on insurance policies on project assets or interruption against natural force
majeure as well as for business interruption or delayed start-up.
• Lien on project accounts.
6.3 IDCOL Project Cycle:
Loan application
The sponsor(s) will be required to provide certain specific financial and technical information. A
formal application must be submitted to IDCOL by the sponsor(s) containing required
information including, for this purpose, a feasibility study acceptable to IDCOL. The feasibility
study would be reviewed by IDCOL to ensure that it satisfies its requirements and those of
concerned parties. After an initial clearance-in-principle, a non-binding Preliminary Letter of
Support (PLS), including a draft Term Sheet and Loan Agreement would be issued to the
sponsor/borrower.
Appraisal
IDCOL carries out its own independent appraisal of the economic, technical and financial
viability of each project and ensures that the investment is in line with national policies and
priority development programmes of the GOB. During the appraisal, IDCOL also verifies
compliance with environmental protection and procurement regulations.
IDCOL treats any information received in the course of its operations as confidential.
Approval
Following a careful examination of the final appraisal report, the Board of Directors of IDCOL
will make final decision on the application.
Effectiveness of the loan from IDCOL will be subject to all other financing for the concerned
Project being irrevocably committed and effective.
27
Monitoring
IDCOL loan contracts provide for monitoring of implementation progress and expenditure. After
completion, a report is drawn up, which includes a comparison of actual with initial estimates.
Loan processing procedure along with Due Diligence process flow
Projects financed by IDCOL are typically funded on a limited recourse basis. The stages through
which IDCOL provides approval for a project are described below and summarised in the
following figure titled IDCOL's Project Cycle:
Step 1. Once approached by a potential sponsor/borrower(s), the Executive Director and Chief
Executive Officer (“CEO-IDCOL”) and/or other senior officials of the Company will meet with
the sponsor/borrower(s) to discuss the general terms and conditions of IDCOL loans as well as
the eligibility criteria and loan process.
Step 2. The project cycle will begin with the receipt of a completed loan application along with a
non-refundable application fee1
applicable for the project. Sponsors requiring foreign currency
loans are required to pay the application fee in US dollars; whereas domestic sponsors may pay
this amount in local currency. Upon receipt, the IDCOL staff will review the application to
ensure that all necessary information in the loan application has been included and that all
required documentation has been submitted.
For projects eligible for financing under Private Sector Infrastructure Development Project
(PSIDP), the Sponsor's ability or willingness to meet eligibility criteria such as IDA procurement
policy will have to be firmly established during steps 2-3. In cases where information or
documentation is missing, IDCOL will contact the Sponsor to complete the application.
IDCOL’s Project Cycle
1
28
Step 3. In case of projects eligible for financing, IDCOL officials conduct a procurement review
for the project as per the relevant procurement guidelines.
29
Appointmentof:
 Lenders'sCounsel
 IE
 MarketExpert
 Insurer
 FinancialmodelAuditor
Application
Received
Steps1&2
Procurement
Review
Step 3
Doesnot
meetICB
IDCOL Board
Step 5
Sponsorsdonot
agreeto
downstream
procurement
Sponsors agree
todownstream
procurement
IDCOLBoard
disapproves
IDCOLBoard
approves
Inform
Sponsors
Inform
Sponsors
Issuance of
PLS
Step 6
Project
Agreements
notsigned
Project
Agreements
signed
Letter of
Engagement
Steps 7 &8
Sponsorsdonot
agreewithterms
Sponsorsagree
withterms
Lenders' meetingand review of:
 Commontermsheet
 IEreport
 Marketexpert'sreport
 Insurancereviewreport
 Financialmodelaudit
Unsatisfactory
Review
Satisfactory
Review
IDCOLasks
Sponsorsfor
mitigants
Project
Appraisal
Steps 9 &10
IDCOL
Board
disapproves
IDCOL
Board
approves
IDA'sCertificate
of'NoObjection'
Inform
Sponsors
Loan
Documentation
Steps10-17
IDCOLdoesnot
participate
IDCOLdoesnot
participate
MeetsICB
Inform
Sponsors
IDCOLdoesnot
participate
Inform
Sponsors
IDCOLdoesnot
participate
Inform
Sponsors
IDCOLdoesnot
participate
Yes No
Financial
Closing
Step18
Preliminary Project
Appraisal
Step 4
In case of a solicited project eligible for financing under PSIDP, it must follow the IDA
Guidelines. Where the project is unsolicited, the Sponsor's agreement to conduct a "downstream"
ICB tender for the procurement of EPC services and works and/or equipment will have to be
secured. Then, CEO's comments and the procurement review will be submitted to IDA for their
clearance.
Step 4. Once all other information has been received, IDCOL will begin its preliminary project
appraisal. In this step, IDCOL will analyse the information and documentation submitted by the
Sponsor and prepare a preliminary project appraisal for review by the CEO-IDCOL prior to its
presentation to the IDCOL Board of Directors. The purpose of this step is to (i) assist the Board
in making a decision whether or not to proceed further with the project; ii) identify any weak
spots in the project; and (iii) initiate discussions of potential risk mitigation measures with the
Sponsors.
Step 5. Upon obtaining approval from the IDCOL Board, IDCOL will prepare an indicative draft
term sheet.
In case of projects eligible for financing under PSIDP, CEO-IDCOL will review the term sheet,
seek the views of IDA and the Company's legal counsel and then, submit it to the IDCOL Board
of Directors for approval.
Step 6. IDCOL will issue a Preliminary Letter of Support (“PLS”) to the Sponsor along with a
copy of the indicative draft term sheet. CEO-IDCOL will request from the Sponsors copies of all
signed project documents as they become available.
In case of PSIDP projects, issuance of the PLS will be subject to the Board approval, receipt of
procurement clearance from IDA, and receipt of the first part of the Project Examination Fee of
0.0625 percent of the financial assistance being sought (but not exceeding $25,000). If the project
was subject to a formal solicitation, CEO-IDCOL will request procurement clearance from IDA.
Step 7. For PSIDP projects, after receipt of the signed project documents, IDCOL will prepare an
engagement and indemnification letter which will be sent to the Sponsors, with a request for the
second half of the Project Examination Fee of 0.1875 percent of financial assistance sought. If the
project was an unsolicited proposal, the engagement letter and indicative draft term sheet must
limit IDCOL financing to no more than a) 100 percent of the cost of any portion of goods and
services which is subsequently tendered using IDA guidelines or b) 40% of project cost,
whichever is lower.
Step 8. CEO-IDCOL will request a letter ("Information Letter") from the Sponsor updating the
information provided in the original project proposal and discussing any changes and/or recent
developments. In addition, IDCOL will seek Board approval of any appointment by the lending
syndicate of lenders' legal counsel and technical advisors.
Step 9. IDCOL will prepare the Terms of Reference (“TOR”) for appraising the project eligible
for financing under PSIDP and commission necessary short-term technical advisers (“STTA”) in
30
consultation with CEO-IDCOL. With receipt of the Information Letter, engagement and
indemnification letters and applicable fee, CEO-IDCOL will seek approval from the Board to
initiate the formal project appraisal process.
Step 10. From time to time, IDCOL will participate in lenders’ meetings for the purpose of
reviewing the work of technical advisors and legal counsel as well as drafting common term
sheets.
Step 11. IDCOL officials (The STTAs, with the assistance of IDCOL officials, in case of projects
under PSIDP) will prepare the project appraisal report for submission to the CEO-IDCOL for his
review and comments.
Step 12. Based on lenders’ meetings and on the recommendations of the project appraisal report,
IDCOL will prepare a final draft loan term sheet, consistent with the lenders' common terms sheet
and any additional understandings that may exist with Sponsors, for review by the CEO-IDCOL
(and for comment from IDA for PSIDP projects.)
Step 13. Once the final draft term sheet has been prepared, a copy will be submitted along with
the completed project appraisal report to the Credit Committee of the IDCOL Board for approval.
Step 14. Once approval of the IDCOL’s Credit Committee is obtained, IDCOL will submit
recommendation of the Credit Committee to the Board of Directors for approval. Following
approval of loan terms by the Board, IDCOL will issue a loan sanction letter to the sponsor.
Subsequently, IDCOL will sign the loan agreements with the Sponsor, collect the other relevant
fees applicable for the project and close the loan sanctioning process
In case of projects eligible for financing under PSIDP, approval of project is subject to IDA’s “no
objection.”
Chapter-07: Case study Analysis of a renewable energy project
of IDCOL: PGEL 100 kW Solar Mini Grid at Sandip Island
The proposed project involves setting up of a 100-kW solar photovoltaic (PV) based micro-grid
by PUROBI Green Energy Limited (PGEL) at Sandip island, Chittagong. A 40-kW diesel
31
generator will be integrated into the proposed power plant in order to ensure adequate power
supply during periods of low solar radiation.Once completed, the Project is expected to supply
electricity to adjacent 390 shops, 5 health centers and 5 schools.
7.1 The Project
This chapter provides an overview of the project, rationale of the project, procurement of
machineries, implementation status, management team, project cost, and financing plan.
7.1.1 Project Description
The proposed project involves setting up of a 100-kW solar photovoltaic (PV) based micro-grid
by PUROBI Green Energy Limited (PGEL) at Sandip island, Chittagong. A 40-kW diesel
generator will be integrated into the proposed power plant in order to ensure adequate power
supply during periods of low solar radiation. PGEL is a consortium of four NGOs namely
Bangladesh Rural Integrated Development Grub-Street Economy (BRIDGE), Integrated
Development Foundation (IDF), Upokolio Bidyut and Mohila Unnoyon Samity (UBOMOUS)
and Rural Energy and Development Initiative (REDI). Once completed, the Project is expected to
supply electricity to adjacent 390 shops, 5 health centers and 5 schools.
Expected commercial operation date of the Project is within the first week of June 2012. The
following table presents key project information:
32
Particulars
Plant capacity 100-kW
Location Sandip Island, Chittagong
Project land area 8700 sq. ft.
Design SMA Technologies AG
Major equipment
Solar Modules (poly crystalline), batteries (48V, 18000 AH), grid tie,
SI inverter, backup diesel generator
Equipment Manufacturers
Solar Modules: KYOCERA, Japan (Assembled in China) Battery:
RIMSO Battery, Grid
Inverter: SMA Solar Technology AG of Germany
Engineering, Procurement and
Construction (EPC)
contractor
Asantys Systems
O&M contractor Prokousoli Sangshad Limited (PSL)
Table: Key Project Information
7.1.2Rationaleof theProject
Expanding rural electrification is the key to the prosperity and development of rural areas as well
as to fulfill the GOB’s vision of ensuring access to affordable and reliable electricity for all by
2020. It is well recognized that energy demand in our rural areas is increasing and supply of fossil
fuel at subsidized prices is becoming an ongoing challenge for the government. Moreover,
providing power without intensifying the effect of climate change is a priority for Bangladesh.
There is also increased emphasis on increasing the energy conversion efficiency and promoting
the use of alternate energy sources.
The island of Sandip is located in the south-eastern part of the country with an area of 700 square
kilometers. This island is a habitat to a population of 300,000 who are detached from Chittagong
mainland by a channel of about 75 kilometers. Because of its position and inaccessibility there is
no possibility of grid electrification service in this area in the distant future. However, the island
has a dynamic population with various public and private service offerings providing support to
the general public including educational institutions, health service centers, small and medium
enterprises, etc. Despite shortage of reliable and consistent supply of electricity, use and
willingness of use of various loads have been found in this region i.e. computers, printers,
scanners, photocopy machine, refrigerators, color television, etc.
At present, the electricity demand of general shops in the markets of Sandip are served by diesel
micro-grid run by several diesel generator operators who provide services for about 5 to 8 hours
33
per day. Besides, several diesel generators are used by several shop owners for captive
consumption. Average tariff rate being charged to the customers by the diesel operators currently
range between BDT 53 per kWh and BDT 60 per kWh.
The proposed Project envisages supplying reliable and consistent supply of quality electricity to
the local commercial shops, health centers and schools at an affordable, reasonable and
competitive price to encourage income generating activities more than before and enhance
standard of living of the local people.
7.1.3 Procurement of Machinery
The Sponsors are in the process of finalizing a contract with Asantys Systems which will be
responsible for supplying the required machineries and accessories and installing the grid. The
solar modules will be procured from KYOCERA and inverter, sunny Web box and battery fuse
will be procured from SMA Solar Technology AG of Germany. Batteries will be procured locally
from RIMSO Battery.
Moreover, PSL will provide O&M services and training to the management of the Project during
the first one year of operation.
7.1.4 Implementation Status
PGEL has been registered as a private limited company with Registrar of Joint Stock Companies
of Bangladesh. As discussed above, the Sponsors have finalized their choices of technologies and
equipment. The proposed Project land has already been identified which is owned by
UBOMOUS, one of the Sponsors. Once the Project gets approval for the required grant and
financing, UBOMOUS will duly transfer the ownership of the Project land to the proposed
Project Company and will enter into an equipment supply contract with Asantys Systems.
A detailed implementation plan showing the phase wise implementation of the Project activities
is provided in Annexure I.
7.1.5 Management Team
The Project management team of the Project Company will be formed after the formation of the
Company. The experience and expertise of the NGOs in the microfinance and renewable
energy businesses will be harnessed while formation of the Project management team by
transferring experienced and knowledgeable personnel to the proposed Project Company.
7.1.6 Project Cost
Total cost of the proposed Project has been estimated to be BDT 55.37 million. Breakdown of
total cost is shown below:
34
Table 7.1: Budgeted Project Cost
Particulars
Amount
(BDT)
Amount
(BDT) % of Project costs
Land and Land Development 1,260,000 2.28%
Civil Construction 2,400,000 4.33%
Equipment
-Solar Modules (100 kW) 21,000,000
-Grid Tie, SI Inverter 6,375,000
-Backup Diesel Generator – 40 kW 500,000
-Accessories 500,000
-Batteries – 48 V, 18000 Ah 11,161,700
39,536,700 71.41%
Transportation 725,000 1.31%
Distribution & Others
-Distribution Line (5 km) 1,050,000
-AC Household Meters 1,000,000
-Control Room, Structure & Others 800,000
2,850,000 5.15%
Import Duty & Clearance Cost 956,250 1.73%
Technical Assistance 2,866,200 5.18%
Contingency 4,772,795 8.61%
TOTAL PROJECT COST 55,366,945 100.00%
7.1.7 Financing Plan
The Project is proposed to be financed with a mix of debt, equity and GEF grant fund:
Table 2.4: Financing Plan
Amount
(in million BDT)
%
Debt 16.61 30%
Grant 27.69 50%
Equity 11.07 20%
Total 55.37 100%
7.2:TheSponsor
This chapter discusses about the sponsors of the Project, in particular its ability to provide
financial support ensuring the completion and subsequent operation of the Project. Within this
context, the chapter includes - corporate history and financial analysis of the sponsors, ownership
structure of the Project company, background and experiences of the owners, net worth analysis
of the owners and comments on sponsors' Credit Information Bureau (“CIB”) Report.
35
7.2.1 The Project Company
PGEL has been registered as a private limited company with Registrar of Joint Stock Companies
of Bangladesh on 17 December 2009 with an authorized capital BDT 20 million and paid up
capital of BDT 10 million.
7.2.2 Shareholding Structure
The proposed shareholding structure PGEL is shown below.
Table 3.1: Proposed shareholding Structure
No Name of the Shareholders Number of Shares %
1 BRIDGE 50 25
2 IDF 50 25
3 UBOMOUS 50 25
4 REDI 50 25
TOTAL 2,000 100.00%
7.2.3 Credit Information Bureau report
Credit Information Bureau ("CIB") report describing the status of the sponsors with other
banks/financial institutions is expected to be collected soon. However, clean CIB report on the
sponsor will be a condition precedent for disbursement of loan.
7.3: Technical Aspects
This chapter includes overview of technology used, plant design, technical review of major plant
equipment and comments from kfW consultant.
7.3.1ProjectOverview
7.3.1.1 Proposed Process and Technology
The proposed Project is to electricity production through solar micro-grid. The full technology
will be supplied by Asantys Systems on a turnkey basis.
7.3.1.2 Electricity Generation through Solar Micro-grid
36
Technology
The size of the solar micro-grid project under consideration is 100 kW accompanied by 40 kW
Diesel. The solar micro-grid is given in Figure 1, which is a combined operation of several sub-
systems.
The Solar PV modules are the main power generation system that is operational during daytime.
About 60 kW of the PV modules will be directly connected to 6 Sunny mini central (SMC with
MPPT) inverters which will convert from DC to AC power at 220V and supply to the micro-grid
distribution line at all times. Three phase configuration of the AC distribution line will be
configured through the Multi-cluster box, which is the interface for all connectors and control.
The unused portion of the power in the distribution line will be stored into the batteries through
12 bidirectional inverters called Sunny Islands in 4 clusters. During daytime additional 40 kW PV
power will be stored into the same battery bank through DC battery chargers (SIC40 with MPPT).
When the grid power is not available, mainly during evening hours the plant will use power from
the battery bank. During the worst season of solar radiation, and on cloudy days, backup power
will be provided by the 40kW Diesel generators.
Figure: Solar Micro Grid Layout using Four Cluster Sunny Island
Major Equipment:
List of major Equipment
37
Equipment Supplier Country of Origin
Photovoltaic Module Kyocera
KYOCERA, Japan
(Assembled in China)
Inverter SMA Solar Technology AG Germany
Battery RIMSO Bangladesh
Grid Inverter SMA Solar Technology AG Germany
Sunny Web box & Battery Fuse SMA Solar Technology AG Germany
Photovoltaic (PV) Module:
The PV Module is polycrystalline and highly efficient. There will be 500 nos. of 200Wp PV
Modules. The PV Module is expected to be procured from Kyocera.
The major features of the proposed PV module model KC200GH-2P are as follows:
Particulars Model KC200GH-2P
Maximum Power (Pmax) 200Wp (+10%/-5%)
Maximum Power Voltage (Vmp) 26.3V
Maximum Power Current (Imp) 7.61A
Open Circuit Voltage (Voc) 32.9V
Short Circuit Current (Isc) 8.21A
7.4 Market Analysis
This chapter provides a detailed analysis of the existing electricity consumption pattern of
electricity market of Sandip. Plant output, demand analysis, load distribution plan, electricity
tariff and revenue projection have also been discussed in this chapter.
7.4.1PlantOutput
According to the Assessment Report of PSE AG, electricity generated by an 80-kW solar mini-
grid at the project site would be able to meet 88,100 kWh of energy demand. Accordingly,
proposed 100 kW plant will satisfy 110,125 kWh demand. The total electricity generation of the
Project has been targeted to be 137,977 kWh per year. Therefore, the remaining 27,852 kWh will
be provided by a diesel generator.
7.4.2DemandAnalysisandPricing
7.4.2.1ConsumerComposition:
The Project plans to supply electricity to several areas adjacent to the project site namely Enam
Nahar Market, Malekmunsir Bazar, Khontarhat, Panditerhat, and Boktarhat. Three categories of
potential customers have been identified for supplying electricity in these areas as mentioned in
the following table:
5.1: Potential customer composition
Customer Total number of
potential
customers
Total number of
targeted
customers
Small shops 478 390
38
Health care 5 5
Schools 5 5
7.4.2.2 Load Consumption Pattern:
According to a survey conducted by the Sponsor in the proposed target market areas, the daily
electricity demand of those areas is more than 400 kWh per day. However, the Project expects to
provide electricity only to the adjacent small shops, health care and schools, satisfying
requirements for about 378 kWh per day. Proposed load distribution of the Project has been
summarized in the following table:
Table: Proposed load distribution of the Project
Service Type Appliance Type
Appliance per Consumer
Daily
Power
Usage
%
Actual
Load
(kWh)
No. of
Consu
mers
Total
load
(kWh)
Hrs. No.
Capacity
(W)
a. Small Shops
Basic
CFL Lamp 4 3 18 100% 0.216 390 84.24
Ceiling Fan 13 1 40 50% 0.26 390 101.4
Black & White TV 8 1 25 100% 0.2 100 20
Refrigerator 24 1 80 50% 0.96 20 19.2
Equipment
Computer 14 1 100 100% 1.4 50 70
Scanner 5 1 60 20% 0.06 20 1.2
Laser Printer 2 1 200 20% 0.08 20 1.6
Color Printer 8 1 100 20% 0.16 20 3.2
Laminating Machine 4 1 400 10% 0.16 5 0.8
Soldering Iron 9 1 200 100% 1.8 20 36
b. Health Centers
Basic
CFL Lamp 4 3 18 100% 0.216 5 1.08
Ceiling Fan 13 2 40 50% 0.52 5 2.6
Equipment
X-Ray Machine 0 1 20% 0 0 0
ECG Machine 0 1 20% 0 0 0
c. Schools
Basic
CFL Lamp 4 20 18 100% 1.44 5 7.2
Ceiling Fan 13 10 40 50% 2.6 5 13
Equipment
Computer 8 5 100 50% 2 5 10
Printer 13 5 100 20% 1.3 5 6.5
Total daily consumption (kWh) 378.02
Total yearly consumption (kWh) 137,977
Source: Investment department, IDCOL
The load consumption in different hours of the day has been assumed to appear according
to the following table:
Service
Type
Applia
nce
Type
AM PM Total
load in
kWhHours of the day
1 2 3 4 5 6 7 8 9
1
0
1
1
1
2
1
3
1
4
1
5
1
6
1
7
1
8
1
9
2
0
2
1
2
2
2
3
2
4
a. Small Shops
39
Basic CL 2
1
.
1
2
1
.
1
2
1
.
1
2
1
.
1 84.2
CF 7
.
8
7
.
8
7.
8
7
.
8
7
.
8
7
.
8
7
.
8
7
.
8
7
.
8
7
.
8
7
.
8
7
.
8
7
.
8 101.4
TV 2
.
5
2
.
5
2
.
5
2
.
5
2
.
5
2
.
5
2
.
5
2
.
5 20.0
RT 0.
8
0.
8
0
.
8
0.
8
0
.
8
0
.
8
0
.
8
0
.
8
0
.
8
0
.
8
0
.
8
0.
8
0
.
8
0
.
8
0
.
8
0
.
8
0
.
8
0
.
8
0
.
8
0
.
8
0
.
8
0
.
8
0
.
8
0
.
8 19.2
Equipm
ent
CR 5
.
0
5
.
0
5
.
0
5.
0
5
.
0
5
.
0
5
.
0
5
.
0
5
.
0
5
.
0
5
.
0
5
.
0
5
.
0
5
.
0 70.0
SR 0
.
2
0
.
2
0
.
2
0
.
2
0
.
2 1.2
LP 0
.
8
0
.
8 1.6
CP
0.
4
0
.
4
0
.
4
0
.
4
0
.
4
0
.
4
0
.
4
0
.
4 3.2
LM
0.
2
0
.
2
0
.
2
0
.
2 0.8
SI 4
.
0
4
.
0
4.
0
4
.
0
4
.
0
4
.
0
4
.
0
4
.
0
4
.
0 36.0
Sub-total 337.6
b. Health Centers
Basic CL 0
.
3
0
.
3
0
.
3
0
.
3 1.1
CF 0
.
2
0
.
2
0
.
2
0
.
2
0
.
2
0
.
2
0
.
2
0
.
2
0
.
2
0
.
2
0
.
2
0
.
2
0
.
2 2.6
Sub-total 3.7
c. Schools
Basic CL 1
.
8
1
.
8
1
.
8
1
.
8 7.2
CF 1
.
0
1
.
0
1
.
0
1
.
0
1
.
0
1
.
0
1
.
0
1
.
0
1
.
0
1
.
0
1
.
0
1
.
0
1
.
0 13.0
Equipm
ent
CR 1
.
3
1
.
3
1
.
3
1
.
3
1
.
3
1
.
3
1
.
3
1
.
3 10.0
PR 0
.
5
0
.
5
0
.
5
0
.
5
0
.
5
0
.
5
0
.
5
0
.
5
0
.
5
0
.
5
0
.
5
0
.
5
0
.
5 6.5
Sub-total 36.7
40
Total Load per day 378
Source: Investment department, IDCOL
*CFL Lamp=CL, Ceiling Fan=CF, Black & White TV=TV, Refrigerator=RT, Computer=CR, Scanner=SR,
Laser Printer=LP, Color Printer=CP, Laminating Machine=LM, Soldering Iron=SI, Printer=PR.
Graph 5.1: Daily load profile of the proposed Project[
7.4.2.3 Pricing
The pricing will be done in three categories: one time connection fee, monthly line rent and
regular tariff. The connection fee and line rent will vary depending on the category of consumers.
The following table represents the proposed pricing structure of the Project:
5.3: Pricing structure of the Project
Customer Type Small shops Health Center School
One Time Connection Fee (BDT) 4,000 6,000 6000
Monthly Line Rent (BDT) 100 100 100
Tariff (BDT per kWh) 27
Effective Tariff
(BDT per kWh)
30.53
7.5: Financial Analysis
41
This chapter focuses on the financial analysis of the proposed project. Key parameters examined
in the analysis include: (a) project cost, (b) debt plan, (c) sponsors’ equity support commitments,
(d) grant percentage determination, (d) financial statement analysis, and (e) sensitivity analysis
regarding debt service coverage ratio (“DSCR”) and other key variables.
7.5.1 ProjectCostandFinancingPlan
7.5.1.1BudgetedProjectCost
Budgeted project cost is BDT 55.37 million, break down of which is given below.
Table 7.1: Budgeted Project Cost
Particulars
Amount
(BDT)
Amount
(BDT)
% of Project
costs
Land and Land Development 1,260,000 2.28%
Civil Construction 2,400,000 4.33%
Equipment
-Solar Modules (100 kW) 21,000,000
-Grid Tie, SI Inverter 6,375,000
-Backup Diesel Generator – 40 kW 500,000
-Accessories 500,000
-Batteries – 48 V, 18000 Ah 11,161,700
39,536,700 71.41%
Transportation 725,000 1.31%
Distribution & Others
-Distribution Line (5 km) 1,050,000
-AC Household Meters 1,000,000
-Control Room, Structure & Others 800,000
2,850,000 5.15%
Import Duty & Clearance Cost 956,250 1.73%
Technical Assistance 2,866,200 5.18%
Contingency 4,772,795 8.61%
TOTAL PROJECT COST 55,366,945 100.00%
• Capital expenditure including land, land development, plant, machinery, and equipment and
42
other assets account for 84% of the total project cost.
• Machinery and equipment worth BDT 34 million is 71% of the total capital expenditure.
7.5.1.2 Financing Plan
The Project is proposed to be financed with a mix of debt, equity and grant fund
Table 7.2: Project Financing Plan
Amount
(in million BDT)
%
Debt 16.61 30%
Grant 27.69 50%
Equity 11.07 20%
Total 55.37 100%
Determination of grant percentage is discussed in Section 6.1.2.3.
7.5.1.2 Debt Plan
The key components of debt plan are shown in table below.
Table 7.3 Project Debt Facilities
Facility
Amount
(BDT million)
Interest
Rate
Tenor Grace Repayment
Term loan 16.61 6% p.a.
10
years
2 years
Annuity; In 16 (sixteen) semi-
annual installments
Table 7.4 Debt Repayment Schedule
Facility Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6
Yr
7
Yr
8
Yr
9
Yr 10
Term
loan
- - 10% 11% 11% 12% 13% 14% 14% 15%
7.5.1.3 Equity Plan
The sponsors will inject BDT 11.07 million in the Project as equity. The sponsors will provide
0.20 acre of land to the Project worth of BDT 0.9 million (valuation to be conducted) and invest
BDT 2.8 million for land development and civil construction.
Sponsors’ net worth analysis has been discussed in chapter 3 shows that the Sponsors have
adequate net worth to provide BDT 7.37 million remaining equity support to the Project. It also
ensures that the sponsors are able to source further equity in the Project in case of cost overrun.
As already mentioned three of four shareholders of the Project Company are Partner
Organizations of IDCOL under its solar energy program. They are successful in implementation
of the program and are regularly servicing the debt. This also illustrates their financial capability.
7.5.1.4 Grant Percentage Determination
43
As mentioned above, the project will be financed though a mix of debt, equity and grant. The
grant amount was determined based on the effect of the grant percentage on the debt service
coverage ratio (DSCR) of the sponsor which is the ratio of cash available for debt service in a
particular period to debt service requirement for that period. The following table illustrates
sponsor’s DSCR at different mix of debt and grant.
Table 6.5: Grant Percentage Determination
Debt and Grant Mix Minimum DSCR
Option I 40% debt and 40% grant 0.96x
Option II 35% debt and 45% grant 1.10x
Option III 30% debt and 50% grant 1.28x
Minimum DSCR requirement for the Project is 1.2x. The DSCR exceeds in the case of Option III
i.e. 30% debt and 50% grant. Therefore, 50% grant has been proposed for the Project.
7.6.2 Financial Projection
The Project’s projected financial statements have been generated based on a set of revenue, expense
and other relevant assumptions. These are summarized below.
7.6.2.1 Revenue Assumptions
The proposed Project has two major sources of revenue:
• Connection Fee
• Sale of electricity; and
• Line rent
7.6.2.1.1 Connection Fee:
Out of 400 customers, the Project Company will acquire 70% in year 1 and remaining 30% in
year 2. It will charge a connection fee for meeting the expenses to be incurred while providing
connection to the customers.
7.6.2.1.2 Sale of electricity :
Daily consumption required by the customers in the proposed project area has been discussed in
detail in the previous chapter i.e. in the Market analysis. The analysis showed that daily load
requirement of 400 potential customers is 378 kWh. Accordingly, yearly load demand is 137,977
kWh.
PSE AG has conducted technical assessment of the proposed Project considering installation of
an 80 kW plant in the Project area which has been discussed in Chapter IV. Their study has
shown that an 80 kW plant in the Project area will generate approx. 110,000 kWh of energy per
year (which also includes energy losses in the inverters) and will be able to meet 88,100 kWh of
energy demand. Hence, proposed 100 kW plant will be able to meet 110,125 kWh of energy
demand. The remaining 27,852 kWh of energy demand will be met by a 40 kW diesel generator.
44
7.6.2.1.3 Line Rent:
The Project Company will charge a fixed amount of line rent per month on each customer.
7.6.2.2 Pricing Assumptions
Electricity tariff for the first year would be BDT 27 per kWh and line rent would be BDT 100 per
connection per month. Pricing of each category of revenue components have been assumed to
increase by 5% a year after every three years of operation.
The following table shows the year-to-year electricity tariff and line rent during the loan life i.e.
first ten years of operation:
Table 6.6: Pricing Assumptions
Facility Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6
Yr
7
Yr
8
Yr
9
Yr 10
Connection Fee
(BDT/connection
)
600
0
6000
Electricity tariff
(BDT/kWh)
27.0 27.0 27.0 28.4 28.4 28.4 29.8 29.8 29.8 31.3
Line rent
(BDT/per month)
100 100 100 105 105 105 110 110 110 116
45
7.6.2.3 Revenue Composition of the Project
-
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
3,500,000
4,000,000
4,500,000
5,000,000
Taka
1 2 3 4 5 6 7 8 9 10
Year
Revenue from sale of Electricity Line Rent Connection Fee
Figure 6.1: Revenue composition of the Project
From the figure it can be seen that connection fee is more than the revenue from sale of electricity
in the first year of operation. This is due to the fact that the Project Company will acquire
customers in the first two years of its operation and 70% of the customers will be connected in the
first year. Moreover, the Project will run for only six months in the first year. From the second
year, sale of electricity becomes the main revenue source. Line rent comprises a small portion of
the revenue.
7.6.2.4 Operating Expenses Assumption
Expenses of the Project include the following:
• Utility
• Salary and allowances
• General and administrative expenses
• Insurance cost
7.6.2.4.1 Utility expenses:
Diesel and lubricating oil will be required to run the diesel generator. Pricing and
requirement of these are as follows:
Table 6.7: Utility Expenses
Price per Liter
(BDT)
Consumption per
kWh (Liter/kWh)
Cost per kWh
Diesel 45 0.20 9.00
Lubricating oil 250 0.0003 0.08
46
A general 5% cost escalation has been considered in each of these cost items.
7.6.2.4.2 Salary and Allowances:
Table 6.8: Salary and Allowances
Designation Number
Gross Salary
per Month
Yearly Salary &
Bonus
Manager 1 10,000 130,000
Accountant 1 8,000 96,000
Lineman / Electrician 2 6,000 72,000
Guard 2 4,000 48,000
346,000
A 5% yearly increment has been considered for each of the employees.
7.6.2.4.3 General and administrative expenses:
This category includes conveyance, postage, printing & stationary, entertainment, telephone,
internet and others. A general 5% cost escalation has been considered in each of these cost items.
General and administrative expenses in the first year of operation are as follows:
Table 7.9: General and Administrative Expenses
Item BDT
Conveyance 3,000
Postage 1,000
Printing & Stationary 6,000
Entertainment 1,000
Telephone/Mobile Bill 3,000
Internet 2,000
Others 12,000
28,000
7.6.2.4.4 Insurance:
It has been assumed to be 0.25% of capital costs per annum and this is a fixed amount.
7.6.2.5 Depreciation & Amortization Assumption
The following table shows the depreciation and amortization rates for different categories of
assets:
Table 6.10: Depreciation and Amortization
Depreciation No of years Rate
Plant, Machinery & Equipment 20 5%
Building and Civil Construction 20 5%
Battery 7 14%
Amortization
Technical assistance 5 20%
47
Battery accounts for 22% of the project cost though its life is only 7 years. Therefore, it has to be
replaced at least twice during the project cost.
7.6.2.6 Tax & Dividend Assumption
The project is expected to enjoy tax holiday. Therefore, no tax provisions have been made in the
model. After the loan life, 50% of the net profit has been considered to be distributed as dividends
in the model.
7.6.3 Key Financial Indicators
Key indicators of the Project are presented in the following table:
Table 7.11: Project’s Key Results
Ratio Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
DSCR 3.41 4.12 1.28 1.35 1.34 1.32 1.39 1.38 1.36 1.44
Average 1.84
Minimum 1.28
Average ROE 5.08%
IRR 10.27%
NPV BDT 23,229,468
The indicators represented in Table 6.11 express that the project has good cash flow.
7.6.4 Sensitivity Analysis
Sensitivity analysis has been done along a number of scenarios:
1. Increase in operating expenses
2. Reduction in tariff
3. Reduction in electricity generation
Table 6.12: Sensitivity Analysis
Case
DSCR
Average Minimum
Base case 1.84 1.28
Operation expenses increased by 30% 1.71 1.19
Tariff reduced by 15% 1.57 1.07
Electricity generation reduced by 30% 1.64 1.12
The above table shows that the Project is expected to have satisfactory DSCR in the base case and
apparently, it will be able to service the debt obligations even in much adverse scenarios.
48
7.6.5Pro-forma financial statements
The Projects’ pro-forma financial statements and ratio analysis are attached in the Annexure II.
Chapter-08: Findings and Conclusion
A Critical Evaluation of Project Financing in Bangladesh by IDCOL:
To evaluate the whole project financing program of IDCOL, the following ways can be
discussed:
8.1 Project Selection – Regional Imbalance: As IDCOL’s share is totally owned by
the government of Bangladesh, making a positive contribution towards the society is the
main objective of IDCOL rather than only making profit. That is why IDCOL mainly
invest in the off grid areas of the country and logically these off grid areas are the most
under developed portions of the country. IDCOL finance projects throughout the country
where it finds it necessary so there is no regional imbalance in renewable energy project
49
financing of IDCOL.
Source: Ahammed & Taufiq, 2008
Division wise SHS installations up to 30 June 2006 are shown below:
Division No of Division No of Division No of
50
Installations Installations Installations
Barisal 11,385 Khulna 14,500 Rajshahi 9,886
Chittagong 18,085 Dhaka 13,303 Sylhet 9,447
Total 76,607
Source: Investment department, IDCOL
8.2 Negative/positive Impacts of Projects: To find the impacts of the project we have to
compare these projects with the other alternatives. As the IDCOL financed projects are mainly in
the off grid areas, oil, petroleum etc are main source of energy in these areas. These sources of
energy are known as “fossil fuels” and they are composed of hydrocarbons and are formed by
nature over eons. These sources emit a huge amount of carbon to the nature and might become
the cause of natural disaster. Moreover, once these fossil fuels are combusted, they cannot be
replenished or renewed. Apart from this, these provide energy via combustion and, in the process
release toxic emissions into the atmosphere, harming humans, animals as well as plant life and
thus distort the overall ecological balance on Earth. In fact, each stage in the exploration,
extraction, processing, transportation and consumption of fossil fuels is harmful for humans and
ecosystems. Furthermore, the large fluctuations in prices of the fossil fuels over the years have
made these sources beyond the capacity of the poor people of Bangladesh.
Here to overcome these scenarios, the renewable energy projects are working well. This is
because, unlike the non-renewable fossil fuels, renewable energy sources capture their energy
from existing flows of energy, i.e. sunshine, wind, flowing water, biological processes, and
geothermal heat flows which are constantly and naturally being replenished. Thus, unlike the
non-renewable fossil fuels, renewable energies are not diminished by consumption. Therefore
they are providing a reliable and sustainable supply of energy almost indefinitely.
Moreover, the use of renewable energies produce minimal emissions and their increased share in
the mainstream energy system, provides a much cleaner energy system compared to fossil fuels,
which emit harmful gases like carbon dioxide into the atmosphere, via combustion, thus polluting
the environment. The latter fuels are currently emitting an increasing amount of Greenhouse
Gases like carbon dioxide, nitrogen oxides, sulfur oxides and un burnt methane into the
atmosphere, via combustion, which is the root cause of the much-spoken global warming, sea-
level rise and climate change.
In contrast to fossil fuel energy, renewable energies can be derived domestically from local
sources. This aspect is especially beneficial to Bangladesh to pursue locally applicable energy
51
strategies, more or less independent of the national network. It also enhances the access to energy
supplies in small, isolated rural areas and helps the rural poor to attain a higher quality of life by
providing better community health and educational services. This results in potential economic,
ecological, social, and security benefits for the rural poor.
Nothing has all the merits. This renewable energy projects might cause some problems as well.
For example for the solar energy project the batteries need to be changed after a certain time
frame. If they are not disposed properly, it might cause serious hazards for the nature.
Lastly here I should mention that through the renewable energy project financing of IDCOL
thousands of employment opportunities have been created that will make a positive contribution
to Bangladesh where a huge portion of the people is unemployed.
8.3 Financing Problems: It can be easily understood from the following table that the
financing or disbursement process is so lengthy and troublesome. If any party fails to disburse the
amount in time then the whole process will be delayed and in some cases will be destroyed.
IDCOL faces these problems time to time. For example if IDA does not disbursement the loan in
time, IDCOL will fail to finance the partner organization. Thus the consumer will not be able to
construct the energy plant or consume. These might happen due to:
o Non-compliance of the terms and conditions set by the upper level by the lower
lover agency.
o Inefficiency of the designated officials, etc.
52
Fig: The process of disbursement
8.4 Summary of Major Findings: Here are the summaries of major findings:
• All the renewable energy projects financing of IDCOL are funded by international
financial institution or development agencies. IDCOL is mainly working as the
intermediary in these cases.
• IDCOL’s principal objective is the commercialization of SHS. Therefore, it has adopted a
policy of reducing grant with the progress of the project. So in future it may be
impractical for the poor people to grab the benefit and this project might loss its
attractiveness.
• IDCOL does not require any collateral or security for the loan, except for a lien created
on the project accounts. This makes it possible for anyone without security to take the
opportunity of financing.
• IDCOL follows a very rigorous process in giving loan and subsidy; this sometimes makes
the process of financing lengthy.
• IDCOL is implementing its programme through partner organizations (PO) including
private companies, NGOs, Micro finance institute (MFIs). That’s makes the process
lengthy. Further studies can be done on whether these intermediaries or IDCOL itself
can fiancé directly to make the process easy.
53
Internship report reachers report about Renewable energy project financing of infrastructure development company limited (idcol) in bangladesh
Internship report reachers report about Renewable energy project financing of infrastructure development company limited (idcol) in bangladesh

More Related Content

What's hot

Finance dundee
Finance dundeeFinance dundee
Finance dundeetapask7889
 
Columbus gbc 2010 toby rittner
Columbus gbc   2010 toby rittnerColumbus gbc   2010 toby rittner
Columbus gbc 2010 toby rittnerEllieNowels
 
A Guide to Affordable Housing Midwest Housing Equity Group 3-2014
A Guide to Affordable Housing   Midwest Housing Equity Group 3-2014A Guide to Affordable Housing   Midwest Housing Equity Group 3-2014
A Guide to Affordable Housing Midwest Housing Equity Group 3-2014Midwest Housing Equity Group, Inc
 
Final roject higlighting the role of development banks in financing develop...
Final roject   higlighting the role of development banks in financing develop...Final roject   higlighting the role of development banks in financing develop...
Final roject higlighting the role of development banks in financing develop...JOSEPH SAMUEL K. ADUKU
 
Hb&c workshop summary final
Hb&c workshop summary finalHb&c workshop summary final
Hb&c workshop summary finalHarcourtBrownEF
 
Custom o105c399f97286
Custom o105c399f97286Custom o105c399f97286
Custom o105c399f97286venvetty
 
Special Remarks Bokhwan Yu
Special Remarks Bokhwan YuSpecial Remarks Bokhwan Yu
Special Remarks Bokhwan YuOECD Environment
 
Localism 2012: Looking Forward
Localism 2012: Looking ForwardLocalism 2012: Looking Forward
Localism 2012: Looking ForwardLocalDialogue
 
Social Finance for Social Housing
Social Finance for Social HousingSocial Finance for Social Housing
Social Finance for Social HousingAdam Spence
 
01. india's river linking project state of the debate- shah et al
01. india's river linking project   state of the debate- shah et al01. india's river linking project   state of the debate- shah et al
01. india's river linking project state of the debate- shah et alRavi Naid Gorle
 
Debt review presentation qecb-power saver, march 2012
Debt review presentation  qecb-power saver, march 2012Debt review presentation  qecb-power saver, march 2012
Debt review presentation qecb-power saver, march 2012HarcourtBrownEF
 
Conflict Dynamics & Peacebuilding Opportunities in Northern Nigeria Lake Chad
Conflict Dynamics & Peacebuilding Opportunities in Northern Nigeria Lake ChadConflict Dynamics & Peacebuilding Opportunities in Northern Nigeria Lake Chad
Conflict Dynamics & Peacebuilding Opportunities in Northern Nigeria Lake ChadAmira Noeuv
 
Pathway Lending - Loan Product Catalog 2014
Pathway Lending - Loan Product Catalog 2014Pathway Lending - Loan Product Catalog 2014
Pathway Lending - Loan Product Catalog 2014infopathway
 

What's hot (18)

Finance dundee
Finance dundeeFinance dundee
Finance dundee
 
Financing Infrastructure in U.S. Cities
Financing Infrastructure in U.S. CitiesFinancing Infrastructure in U.S. Cities
Financing Infrastructure in U.S. Cities
 
Columbus gbc 2010 toby rittner
Columbus gbc   2010 toby rittnerColumbus gbc   2010 toby rittner
Columbus gbc 2010 toby rittner
 
Gray - Cnu Denver And Hud
Gray - Cnu Denver And HudGray - Cnu Denver And Hud
Gray - Cnu Denver And Hud
 
A Guide to Affordable Housing Midwest Housing Equity Group 3-2014
A Guide to Affordable Housing   Midwest Housing Equity Group 3-2014A Guide to Affordable Housing   Midwest Housing Equity Group 3-2014
A Guide to Affordable Housing Midwest Housing Equity Group 3-2014
 
Final roject higlighting the role of development banks in financing develop...
Final roject   higlighting the role of development banks in financing develop...Final roject   higlighting the role of development banks in financing develop...
Final roject higlighting the role of development banks in financing develop...
 
Teohwernjun,+journal+editor,+m4
Teohwernjun,+journal+editor,+m4Teohwernjun,+journal+editor,+m4
Teohwernjun,+journal+editor,+m4
 
Hb&c workshop summary final
Hb&c workshop summary finalHb&c workshop summary final
Hb&c workshop summary final
 
Custom o105c399f97286
Custom o105c399f97286Custom o105c399f97286
Custom o105c399f97286
 
HB&C Workshop Summary
HB&C Workshop Summary HB&C Workshop Summary
HB&C Workshop Summary
 
Special Remarks Bokhwan Yu
Special Remarks Bokhwan YuSpecial Remarks Bokhwan Yu
Special Remarks Bokhwan Yu
 
Asian development bank
Asian development bankAsian development bank
Asian development bank
 
Localism 2012: Looking Forward
Localism 2012: Looking ForwardLocalism 2012: Looking Forward
Localism 2012: Looking Forward
 
Social Finance for Social Housing
Social Finance for Social HousingSocial Finance for Social Housing
Social Finance for Social Housing
 
01. india's river linking project state of the debate- shah et al
01. india's river linking project   state of the debate- shah et al01. india's river linking project   state of the debate- shah et al
01. india's river linking project state of the debate- shah et al
 
Debt review presentation qecb-power saver, march 2012
Debt review presentation  qecb-power saver, march 2012Debt review presentation  qecb-power saver, march 2012
Debt review presentation qecb-power saver, march 2012
 
Conflict Dynamics & Peacebuilding Opportunities in Northern Nigeria Lake Chad
Conflict Dynamics & Peacebuilding Opportunities in Northern Nigeria Lake ChadConflict Dynamics & Peacebuilding Opportunities in Northern Nigeria Lake Chad
Conflict Dynamics & Peacebuilding Opportunities in Northern Nigeria Lake Chad
 
Pathway Lending - Loan Product Catalog 2014
Pathway Lending - Loan Product Catalog 2014Pathway Lending - Loan Product Catalog 2014
Pathway Lending - Loan Product Catalog 2014
 

Viewers also liked

Indoor Air Pollution & Climate Change Contribute
Indoor Air Pollution & Climate Change ContributeIndoor Air Pollution & Climate Change Contribute
Indoor Air Pollution & Climate Change ContributeRai Hayn
 
C:\fakepath\bangladesh the biogas way
C:\fakepath\bangladesh the biogas wayC:\fakepath\bangladesh the biogas way
C:\fakepath\bangladesh the biogas wayNazmul Faisal
 
Renewable energy project financing of infrastructure development company limi...
Renewable energy project financing of infrastructure development company limi...Renewable energy project financing of infrastructure development company limi...
Renewable energy project financing of infrastructure development company limi...Mehdi Hassan
 
Brochure of AJA Bangladesh Ltd.
Brochure of AJA Bangladesh Ltd.Brochure of AJA Bangladesh Ltd.
Brochure of AJA Bangladesh Ltd.Zia Ul Karim
 
PERSONAL NOTEBOOK (2)
PERSONAL NOTEBOOK (2)PERSONAL NOTEBOOK (2)
PERSONAL NOTEBOOK (2)Zia Ul Karim
 
Energy efficient planning in towns of kmc
Energy efficient planning in towns of kmc Energy efficient planning in towns of kmc
Energy efficient planning in towns of kmc R_Sarita
 
sustainability study of biogas plant in mymensingh
sustainability study of biogas plant in mymensinghsustainability study of biogas plant in mymensingh
sustainability study of biogas plant in mymensinghMasrur Ahmed
 
Seo presentation for dfc stall in digital innovation fair 2107
Seo presentation for dfc stall in digital innovation fair 2107Seo presentation for dfc stall in digital innovation fair 2107
Seo presentation for dfc stall in digital innovation fair 2107Md Al Masud
 
Briefing For The FlashChatt App Project
Briefing For The FlashChatt App ProjectBriefing For The FlashChatt App Project
Briefing For The FlashChatt App ProjectDavid Gracia
 
Digital marketing and change
Digital marketing and changeDigital marketing and change
Digital marketing and changeAngelGuirado
 
Digital Marketing Strategy Project
Digital Marketing Strategy ProjectDigital Marketing Strategy Project
Digital Marketing Strategy ProjectIrina Anthony
 
Biogas plant project
Biogas plant projectBiogas plant project
Biogas plant projectTulika Ghosh
 
A Project on Digital Marketing Initiatives and E-commerce Perspectives in Ban...
A Project on Digital Marketing Initiatives and E-commerce Perspectives in Ban...A Project on Digital Marketing Initiatives and E-commerce Perspectives in Ban...
A Project on Digital Marketing Initiatives and E-commerce Perspectives in Ban...Pujan Kumar Saha
 
Digital Marketing Project Presentation
Digital Marketing Project PresentationDigital Marketing Project Presentation
Digital Marketing Project PresentationNikhil Thapar
 
Elementos Representativos Y De Transicion
Elementos Representativos Y De TransicionElementos Representativos Y De Transicion
Elementos Representativos Y De Transicionjebicasanova
 
2 a project report on internet as a marketing tool
2 a project report on internet as a marketing tool2 a project report on internet as a marketing tool
2 a project report on internet as a marketing toolJimish Panchal
 
Internet marketing full project report
Internet marketing full project reportInternet marketing full project report
Internet marketing full project reportGitika Kolli
 
Project report on- "A study of digital marketing services"
Project report on- "A study of digital marketing services" Project report on- "A study of digital marketing services"
Project report on- "A study of digital marketing services" MarketerBoard
 

Viewers also liked (20)

Indoor Air Pollution & Climate Change Contribute
Indoor Air Pollution & Climate Change ContributeIndoor Air Pollution & Climate Change Contribute
Indoor Air Pollution & Climate Change Contribute
 
C:\fakepath\bangladesh the biogas way
C:\fakepath\bangladesh the biogas wayC:\fakepath\bangladesh the biogas way
C:\fakepath\bangladesh the biogas way
 
Renewable energy project financing of infrastructure development company limi...
Renewable energy project financing of infrastructure development company limi...Renewable energy project financing of infrastructure development company limi...
Renewable energy project financing of infrastructure development company limi...
 
Brochure of AJA Bangladesh Ltd.
Brochure of AJA Bangladesh Ltd.Brochure of AJA Bangladesh Ltd.
Brochure of AJA Bangladesh Ltd.
 
PERSONAL NOTEBOOK (2)
PERSONAL NOTEBOOK (2)PERSONAL NOTEBOOK (2)
PERSONAL NOTEBOOK (2)
 
Energy efficient planning in towns of kmc
Energy efficient planning in towns of kmc Energy efficient planning in towns of kmc
Energy efficient planning in towns of kmc
 
sustainability study of biogas plant in mymensingh
sustainability study of biogas plant in mymensinghsustainability study of biogas plant in mymensingh
sustainability study of biogas plant in mymensingh
 
Seo presentation for dfc stall in digital innovation fair 2107
Seo presentation for dfc stall in digital innovation fair 2107Seo presentation for dfc stall in digital innovation fair 2107
Seo presentation for dfc stall in digital innovation fair 2107
 
Brick industries
Brick industriesBrick industries
Brick industries
 
Briefing For The FlashChatt App Project
Briefing For The FlashChatt App ProjectBriefing For The FlashChatt App Project
Briefing For The FlashChatt App Project
 
Digital marketing and change
Digital marketing and changeDigital marketing and change
Digital marketing and change
 
Digital Marketing Strategy Project
Digital Marketing Strategy ProjectDigital Marketing Strategy Project
Digital Marketing Strategy Project
 
Biogas plant project
Biogas plant projectBiogas plant project
Biogas plant project
 
A Project on Digital Marketing Initiatives and E-commerce Perspectives in Ban...
A Project on Digital Marketing Initiatives and E-commerce Perspectives in Ban...A Project on Digital Marketing Initiatives and E-commerce Perspectives in Ban...
A Project on Digital Marketing Initiatives and E-commerce Perspectives in Ban...
 
Digital Marketing Project Presentation
Digital Marketing Project PresentationDigital Marketing Project Presentation
Digital Marketing Project Presentation
 
Elementos Representativos Y De Transicion
Elementos Representativos Y De TransicionElementos Representativos Y De Transicion
Elementos Representativos Y De Transicion
 
2 a project report on internet as a marketing tool
2 a project report on internet as a marketing tool2 a project report on internet as a marketing tool
2 a project report on internet as a marketing tool
 
Internet marketing full project report
Internet marketing full project reportInternet marketing full project report
Internet marketing full project report
 
Digital marketing project
Digital marketing projectDigital marketing project
Digital marketing project
 
Project report on- "A study of digital marketing services"
Project report on- "A study of digital marketing services" Project report on- "A study of digital marketing services"
Project report on- "A study of digital marketing services"
 

Similar to Internship report reachers report about Renewable energy project financing of infrastructure development company limited (idcol) in bangladesh

How to finance and fund infrastructure and energy projects.pdf
How to finance and fund infrastructure and energy projects.pdfHow to finance and fund infrastructure and energy projects.pdf
How to finance and fund infrastructure and energy projects.pdfNative World
 
Importance of Sustainibility Finance Globally.pdf
Importance of Sustainibility Finance Globally.pdfImportance of Sustainibility Finance Globally.pdf
Importance of Sustainibility Finance Globally.pdfprabinkafle6
 
Project finance good one
Project finance good oneProject finance good one
Project finance good oneStudsPlanet.com
 
Green Bond Market
Green Bond MarketGreen Bond Market
Green Bond MarketAmolKusmude
 
Project finance
Project financeProject finance
Project financeDharmik
 
Venture capital 1
Venture capital 1Venture capital 1
Venture capital 1Dharmik
 
Harcourt Brown & Carey NGA State Clean Energy Financing Presentation
Harcourt Brown & Carey NGA State Clean Energy Financing PresentationHarcourt Brown & Carey NGA State Clean Energy Financing Presentation
Harcourt Brown & Carey NGA State Clean Energy Financing PresentationHarcourtBrownEF
 
Financing slide _India.docx
Financing slide _India.docxFinancing slide _India.docx
Financing slide _India.docxamitMishra732469
 
Developing Large-Scale Federal Renewable Energy Projects
Developing Large-Scale Federal Renewable Energy ProjectsDeveloping Large-Scale Federal Renewable Energy Projects
Developing Large-Scale Federal Renewable Energy ProjectsHaralambos V. Mouselimos
 
Wastewater Infrastructure_Jung_Spring 2016
Wastewater Infrastructure_Jung_Spring 2016Wastewater Infrastructure_Jung_Spring 2016
Wastewater Infrastructure_Jung_Spring 2016Jocelyn Jung
 
understand challenges for infrastructure
understand challenges for infrastructureunderstand challenges for infrastructure
understand challenges for infrastructurechristopher nyabulegesi
 
Report on ratio analysis
Report on ratio analysisReport on ratio analysis
Report on ratio analysisjcakj
 
Unlocking climate finance india
Unlocking climate finance indiaUnlocking climate finance india
Unlocking climate finance indiaAnkur Naik
 
HSBC - Project Finance
HSBC - Project FinanceHSBC - Project Finance
HSBC - Project FinanceAlbert Song
 
Investments in water private and public investments
Investments in water private and public investmentsInvestments in water private and public investments
Investments in water private and public investmentsEugene Chao
 
Introduction to Green Finance in the changing context.pptx
Introduction to Green Finance in the changing context.pptxIntroduction to Green Finance in the changing context.pptx
Introduction to Green Finance in the changing context.pptxprabinkafle6
 

Similar to Internship report reachers report about Renewable energy project financing of infrastructure development company limited (idcol) in bangladesh (20)

How to finance and fund infrastructure and energy projects.pdf
How to finance and fund infrastructure and energy projects.pdfHow to finance and fund infrastructure and energy projects.pdf
How to finance and fund infrastructure and energy projects.pdf
 
Green Finance.pptx
Green Finance.pptxGreen Finance.pptx
Green Finance.pptx
 
Importance of Sustainibility Finance Globally.pdf
Importance of Sustainibility Finance Globally.pdfImportance of Sustainibility Finance Globally.pdf
Importance of Sustainibility Finance Globally.pdf
 
Session 9 Suk Huyn
Session 9 Suk HuynSession 9 Suk Huyn
Session 9 Suk Huyn
 
Project finance good one
Project finance good oneProject finance good one
Project finance good one
 
Green Bond Market
Green Bond MarketGreen Bond Market
Green Bond Market
 
Project finance
Project financeProject finance
Project finance
 
Venture capital 1
Venture capital 1Venture capital 1
Venture capital 1
 
Harcourt Brown & Carey NGA State Clean Energy Financing Presentation
Harcourt Brown & Carey NGA State Clean Energy Financing PresentationHarcourt Brown & Carey NGA State Clean Energy Financing Presentation
Harcourt Brown & Carey NGA State Clean Energy Financing Presentation
 
Financing slide _India.docx
Financing slide _India.docxFinancing slide _India.docx
Financing slide _India.docx
 
Developing Large-Scale Federal Renewable Energy Projects
Developing Large-Scale Federal Renewable Energy ProjectsDeveloping Large-Scale Federal Renewable Energy Projects
Developing Large-Scale Federal Renewable Energy Projects
 
Wastewater Infrastructure_Jung_Spring 2016
Wastewater Infrastructure_Jung_Spring 2016Wastewater Infrastructure_Jung_Spring 2016
Wastewater Infrastructure_Jung_Spring 2016
 
understand challenges for infrastructure
understand challenges for infrastructureunderstand challenges for infrastructure
understand challenges for infrastructure
 
Financial for development final project
Financial for development final projectFinancial for development final project
Financial for development final project
 
Report on ratio analysis
Report on ratio analysisReport on ratio analysis
Report on ratio analysis
 
Unlocking climate finance india
Unlocking climate finance indiaUnlocking climate finance india
Unlocking climate finance india
 
Project financing
Project financingProject financing
Project financing
 
HSBC - Project Finance
HSBC - Project FinanceHSBC - Project Finance
HSBC - Project Finance
 
Investments in water private and public investments
Investments in water private and public investmentsInvestments in water private and public investments
Investments in water private and public investments
 
Introduction to Green Finance in the changing context.pptx
Introduction to Green Finance in the changing context.pptxIntroduction to Green Finance in the changing context.pptx
Introduction to Green Finance in the changing context.pptx
 

Recently uploaded

Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 

Recently uploaded (20)

Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 

Internship report reachers report about Renewable energy project financing of infrastructure development company limited (idcol) in bangladesh

  • 1. Chapter-01: Introduction 1.1 Introduction: The promising solutions to the environmental problems associated with fossil fuels lies in the development and use of Renewable Energy Sources (RES). RES may be obtained from solar radiation, wind power, waves, heat from earth’s core as well as animal and plant wastes. They also provide diversity of energy supply given that they are products of nature and there is no issue of reserves being depleted. Furthermore, its expansion offers economic opportunities such as regional development and job opportunities. However, the numerous benefits of RES are often ignored as investors have declined project financing Renewable Energy Power Projects (REP) due to the high level of perceived risks associated with them. Capital for project financing energy projects can be raised through a combination of debt and equity investment. In contrast to fossil fuels that were formed more than 300 million years ago, renewable energy comes from sources that are constantly replenished. For example, the power of resources such as the sun and the wind do not diminish over time. Renewable resources makes it possible to reduce our dependence on foreign oil, increase the security of our energy supply, mitigate environmental impacts, and provide economic development opportunities in rural areas. There are many commercially proven renewable energy technologies which can help reduce the amount of money spent on energy consumption and create additional revenues through the sale of power to the electricity grid. These technologies can be used on a small-scale to support operations on the farm or they can be large enough to provide power for an entire community. Project finance has intrigued me ever since I was introduced to it while working as an intern at Infrastructure Development Company Limited (IDCOL).I got more interested about the uniqueness of project financing whenever I came to know that IDCOL is financing without any security other than the project itself. Project financing may be defined as the raising of funds to finance an economically separable capital investment project in which the providers of the funds look primarily to the cash flow from the project as the source of funds to service their loans and provide the return of and a return on their equity invested in the project (John D. Finnerty, 1996). Project finance is the long term financing of infrastructure and industrial projects based upon the projected cash flows of the project rather than the balance sheets of the project sponsors. Standard & Poor's defines a project company as a group of agreements and contracts between lenders, project sponsors, and other interested parties that creates a form of business organization that will issue a finite amount of debt on inception; will operate in a focused line of business; and will ask that lenders look only to a specific asset to generate cash flow as the sole source of principal and interest payments and collateral. Usually, a project financing structure involves a number of equity investors, known as sponsors, as well as a syndicate of banks or other lending institutions that provide loans to the operation. The loans are most commonly non-recourse loans, which are secured by the project assets and paid entirely from project cash flow, rather than from the 1
  • 2. general assets or creditworthiness of the project sponsors. Project finance is only possible when the project is capable of producing enough cash to cover all operating and debt-servicing expenses over the whole tenor of the debt. Project financing typically includes the following basic features: 1. An agreement by financially responsible parties to complete the project and, toward that end, to make available to the project all funds necessary to achieve completion. 2. An agreement by financially responsible parties (typically taking the form of a contract for the purchase of project output) that, when project completion occurs and operations commence, the project will have available sufficient cash to enable it to meet all its operating expenses and debt service requirements. 3. Assurances by financially responsible parties that, in the event a disruption in operation occurs and funds are required to restore the project to operating condition, the necessary funds will be made available through insurance recoveries, advances against future deliveries, or some other means. Project financing should be distinguished from conventional direct financing, or what may be termed financing on a firm's general credit. In connection with a conventional direct financing, lenders to the firm look to the firm's entire asset portfolio to generate the cash flow to service their loans. The assets and their financing are integrated into the firm's asset and liability portfolios. Often, such loans are not secured by any pledge of collateral. The critical distinguishing feature of a project financing is that the project is a distinct legal entity; project assets, project-related contracts, and project cash flow are segregated to a substantial degree from the sponsoring entity. The financing structure is designed to allocate financial returns and risks more efficiently than a conventional financing structure. In a project financing, the sponsors provide, at most, limited recourse to cash flows from, their other assets that are not part of the project. Also, they typically pledge the project assets, but none of their other assets, to secure the project loans. 1.2 Statement of the Problem: Unlimited access to energy sources is essential for modern development. Especially, for a developing country like Bangladesh, having a sustained energy supply is a prerequisite for economic growth. To alleviate poverty in the face of limited resources and high population density, Bangladesh requires a sustainable economic growth model where renewable energy sources are used properly. Bangladesh has the opportunity to meet its future power demands and thus economic growth through renewable energy. Using renewable energy appropriately may improve rural people’s quality of life and provide income-generating opportunities that redress social inequities and environmental damage in Bangladesh. To achieve this objective proper channel of financing in renewable energy is extremely necessary. There has been always a big question whether the financing in this sector is adequate or not, to what extent the availability of project financing in renewable energy there is and whether the covenants of loan or financing are logical and bearable or not. 2
  • 3. 1.3 Objectives of the Study: The size and economic potential of the renewable energy resources in Bangladesh are yet to be determined and the capacity of renewable energy development is presently low. Among others one of the objectives of the study is to explore the extent to which renewable energy technologies (RETs), such as solar home systems (SHS) and biogas digesters, can provide reliable and affordable energy services in the rural regions of Bangladesh. The paper’s another objective is finding out how renewable energies are different from conventional energy projects and what impact this has on their financing needs and ability to attract finance. It describes the various types of financing instruments needed for RE plant development and explains the barriers and financing gaps that today make it difficult to raise capital for RE. The main objectives of this study are as follows: • Assessing the current scenario of renewable energy project financing in Bangladesh. • Comparing the Incentives in Renewable Energy Policies over the countries • Measuring the impact of renewable energy projects towards the society. • Defining the structures of project finance transactions in Bangladesh. • Unveiling the factors that limit the project finance of renewable energy projects. • Assessing the Renewable Energy Potential in Bangladesh. • Evaluating the Role of IDCOL in renewable energy project financing in Bangladesh. • Overall evaluation of Project Financing in Bangladesh. Critically evaluating the renewable energy project financing, making some recommendations are also the objective of this study to foster the growth of Renewable Energy Project Financing in Bangladesh. 1.4 Rationale of the Study: Energy is a basic need of human society and has rightly been termed by many as the „life-blood‟ which keeps human civilization progressing. Without adequate access to modern energy, poor countries can be trapped in a vicious circle of poverty, social instability and underdevelopment (World Energy Council 1999). One such energy starved country is Bangladesh. In 2003, Bangladesh’s energy consumption per capita was only 157 kilograms of oil equivalent (Kgoe) which is one-tenth of the world’s energy consumption per capita (Hussain et al. 2007). Bangladesh’s endowment of conventional energy resources is neither adequate nor varied, as a result of which it suffers from an acute energy crisis and crippling power shortages. However, Bangladesh is endowed with relatively abundant renewable energy resources such as solar and biogas energy. Without proper financing the growth of this eco- friendly renewable energy is impossible in countries like Bangladesh. As a developing country, Bangladesh is facing intimidating energy challenges that are merely likely to worsen over the next few years. Furthermore, over 50% of Bangladesh's inhabitants live without electricity. Because it is expensive, village areas are generally not supplied by grid- connected electricity. These issues really bring the necessity of finding some other ways to improve this situation. That is why this study has been done. 3
  • 4. 1.5 Methodology: It is a desk research which has involved the collection of previous research reports, newspapers and journal content also collection, collation and synthesis of existing project reports of governmental and nongovernmental organizations interventions relating to renewable energy infrastructure of Bangladesh. Here a real project of IDCOL is taken to analyze the process of project financing in details. Beside of this, to get the real scenario of renewable energy project financing several discussions was conducted with the officials of IDCOL. 1.6 Limitation of the Study: Although this study is carefully prepared, I am still aware of its limitations and shortcomings. Some of the limitations are as follows: • Lack of proper knowledge on project financing and renewable energy as I am not an expert in these fields. • Lack of available prior research studies on the topic. • Could not get access to the confidential information of IDCOL. As a result there might be lacking of right or biased information. • Lacking of real world experience as it was totally a desk research. 1.7 Literature Review: The finance literature on the subject of project financing is still in its formative stages. Careful analyses of the true benefits of project financing have only recently begun to appear. Shah and Thakor (1987) were among the first to provide a carefully thought-out analysis of the rationale for project financing. They explained why project financing seems most appropriate for very large, high-risk projects. Unfortunately, their analysis was based on only two projects. Chen, Kensinger, and Martin (1989) observed that project financing is widely used for medium-size, low-risk projects, such as cogeneration facilities. They documented that project financing has become the dominant method of financing independent electric power generating facilities, including cogeneration projects developed for several Fortune 500 companies. At best, then, Shah and Thakor's theory appears incomplete. Mao (1982) noted that in order for a project to secure financing as a separate economic entity, the relationships among the participants must be spelled out in detailed contracts.' Worenklein (1981) addressed the project's requirement for "sources of credit support" in the form of contracts to purchase output from the project and/or to supply the necessary inputs at controlled cost. The project's sponsors typically do not guarantee repayment of the project's debt, so creditworthy parties must provide credit support through such contractual undertakings. 4
  • 5. Chapter-02: Renewable energy in Bangladesh Electrification is a constitutional commitment of Bangladesh government. Despite this only 30% of the entire population has access to electricity. Rural electrification Board (REB) provides electricity to only a certain portion of more than 80% of population living in rural areas. Rural electrification is primarily done through grid-expansion and in many remote areas of the country electrification through conventional means is not economically viable. Bangladesh, geographically being closest to the equator, is recipient of immense amount of solar energy almost entire year. Solar energy thus presents an enormous potential for Bangladesh to be utilized as an alternative to fossil fuel for production of energy. Renewable energy is energy that is replenished by nature and comes from natural resources, including the sun, tides, rain, wind, and geothermal sources. It is “captured” and distributed via a number of technologies, including wind turbines, hydroelectric power stations, photovoltaic and heat engines, ethanol fuel plants, and geothermal heat pumps, among others (Michael Waldhier, May 2010). Renewable energy effectively utilizes natural resources such as sunlight, wind, tides and geothermal heat, which are naturally replenished. Renewable energy technologies range from solar power, wind power, and hydroelectricity to biomass and biofuels. About 13 percent of world’s primary energy comes from renewable, with most of this coming from traditional biomass like wood-burning. Hydropower is the next largest source, providing about 2-3%, and modern technologies like geothermal, wind, solar, and marine energy together produce less than 1% of total world energy demand. Renewable energy is a relatively new concept in Bangladesh. However, successful implementation of renewable energy technology such as solar home system indicates that with mass promotion, public awareness, private sector participation, and necessary financial and government assistance, renewable energy sector is poised for long term sustainability in Bangladesh. Renewable energy sources presently used in Bangladesh include solar, wind, hydro, biogas and biomass. Of these solar has, so far, proven to be most popular and accessible in Bangladesh. Total yearly amount of solar radiation available on surface of Bangladesh is about 2.4x10 14 kWh while at present electricity generation is 2.0 x 10 10 kWh. So, solar radiation available is almost 10000 times the present electricity generation of Bangladesh. If 1/1000th part of Bangladesh is used to produce electricity from solar with 10% efficiency, same amount of electricity may be generated as produced right now. In rural areas of Bangladesh standalone solar home systems (SHS) are being used for basic electrification purpose in absence of conventional grid electrification. About 180,000 households are using SHS in Bangladesh which amounts to 0.60% of the country’s entire population. Infrastructure Development Company Limited (IDCOL), with assistance from different local non government organizations (NGOs) and micro finance institutions (MFIs), has been instrumental in promotion and commercialization of SHS in Bangladesh. 5
  • 6. 2.1Energy Indicators of Bangladesh:2.1Energy Indicators of Bangladesh: Total energy consumption :16.6 million tones oil equivalent Per capita energy consumption :171 kg oil equivalent Energy related CO2 emission :42.74 mmt Per capital CO2 emission :0.3 mt Energy consumption : Conventional energy (54%), Biomass(46%) Conventional energy consumption : Natural gas: 1850-1900 MMscfd (April 2009) Oil: 3.5 MT (2008) Coal: 3.8 MT (2008) Access to electricity : 45% Per capital electricity consumption : 145 kWh annum Source: http://data.un.org/CountryProfile.aspx?crName=Bangladesh#Environment Conventional energy consumption (2007) Oil (thousand barrels per day) 91 Natural gas (billion cubic feet) 554 Coal (million Short Tons) 0.8 Source: nationmaster (www.nationmaster.com/bangladesh Sources of energy consumption-2007-http://www.nationmaster.com/red/country/bg- bangladesh/ene-energy&b_define=1 Fig: Percentage of usage of Conventional and Biomass energy Graph: Demand Supply Gap in Five Years 6
  • 7. Year Demand-Supply Gap (MW) 2009 1777 2010 1427 2011 1843 2012 1853 2013 1485 2014 1763 Source: http://www.economywatch.com/economic-statistics/country/Bangladesh/ Assumptions  Demand-Supply Gap (Load Shedding) is increasing. By the year 2014 this gap will be around 1750 MW  Gas supply uncertainty to 1620 MW projects under process may lead to more than 3000 MW load shedding in the year 2014 2.2 Role played by the government: The Government of Bangladesh is so generous towards the financing of renewable energy project and to foster the growth of renewable energy in Bangladesh.  Renewable Energy Policy has been adopted by the Government of Bangladesh on 18 December 2008.  The policy has set a target of generating 5% of the total electricity from renewable sources by 2015 and 10% by 2020.  A focal point called Sustainable Energy Development Agency (SEDA) will coordinate activities related to the development of renewable energy technologies and financing mechanisms. 7
  • 8.  For electricity less than 5 MW generated from renewable energy projects may be purchased by power utilities or any consumer.  All renewable energy equipments and related raw materials will be exempt from 15% VAT and companies will be exempt from corporate income tax for a period of 5 years;  Private sector participation including joint venture initiatives in renewable energy development will be encouraged and promoted;  An incentive tariff has been proposed for electricity generated from renewable sources which may be 10% higher than the highest purchase price of electricity.  Bangladesh Bank, the Central Bank, has launched a revolving fund of BDT 2 billion for refinancing renewable energy projects i.e. solar energy, biogas and effluent treatment plants through commercials at concessionary terms and conditions. 2.3 Comparison of Incentives in Renewable Energy Policies over the countries: Incentives in RE Policy of Bangladesh Incentives in RE Policy of Other Countries Proposed Incentives for RE Policy of Bangladesh Institutional Arrangement – Sustainable Energy Development Agency (SEDA) shall be established VAT Exemption – All renewable energy equipments and related raw materials in producing renewable energy equipments will be exempted from charging 15% VAT. Micro-credit Support System – In addition to commercial lending, a network of micro-credit support system will be established especially in rural and remote areas to provide financial support for purchases of renewable energy equipment. Corporate Income Tax Exemption – Renewable energy project investors both in public and private sectors shall be exempted from corporate income tax for a period of 5 years. Feed–in–Tariff – An incentive tariff may be considered for electricity generated from renewable energy sources which may be 10% higher than the highest purchase price of electricity by the utility from private generators. France Feed–in–Tariff: 28.8 BDT/kWh Construction bonus: 24 BDT/kWh in the mainland France. Germany The basic rate of payment for solar generated electricity is 43.87 BDT/kWh If the plant is attached to or integrated on top of a building, the fee is 50-55 BDT/kWh United Kingdom Currently, price of electricity from Renewable Obligation is 37.29 BDT/kWh United States Production tax credit (PTC) benefit: 2.37 BDT/ kWh generation Investment tax credit (ITC): 30% for the solar systems buyers Grant: up to 30% of the property’s value. India Direct taxes - 100 per cent depreciation in the first year of installation of the project Exemption/reduction in excise duty Exemption from Central Sales Tax and customs duty concessions on the import of material, components and equipment used in RE projects • Investment subsidies or rebates • Sales tax exemptions – at the point of sale • Production tax credit – tax credits per kWh generation • Net metering – for grid connected systems • Feed–in–Tariff – more incentive tariff is required 8
  • 9. Chapter-03: Role of IDCOL in renewable energy project financing in Bangladesh: Infrastructure Development Company Limited (IDCOL) was established on 14 May 1997 as a joint initiative of the Government of Bangladesh (GoB) and the World Bank. The Company was licensed by the Bangladesh Bank as a Non Bank Financial Institution (NBFI) on 5 January 1998. Since its inception, IDCOL is playing a major role in bridging the financing gap for developing medium and large-scale infrastructure as well as renewable energy projects in Bangladesh. Through its participation in financing of infrastructure projects, IDCOL expects to serve as a catalyst in mobilizing private debt and equity financing. In renewable energy projects, however, IDCOL provides subsidy, soft financing and necessary technical support to the private sector with an objective to energize rural Bangladesh in a sustainable manner. Renewable energy is a relatively new concept in Bangladesh. In 2002, IDCOL, with support from the World Bank and Global Environmental Facility (GEF), started implementing the first comprehensive renewable energy program in Bangladesh by disseminating solar home systems in the off-grid rural areas. In 2006, with support from SNV, Netherlands and KfW, Germany, IDCOL undertook a nationwide program on domestic biogas. Lately, IDCOL started promoting new and emerging renewable energy technologies by financing several pilot projects i.e. biomass gasification based power plant, electricity from biogas, solar irrigation pumps etc. Today, IDCOL has emerged as the largest promoter and financier in the renewable energy sector of Bangladesh. IDCOL’S INVESTMENT PORTFOLIO Sector wise loan disbursement as of 30 June 2009 Power, 52.8% Renewable Energy, 31.9% Telecommunication, 14.1%ICT, 0.4% Gas, 0.2% Ports, 0.6% Source: Investment department, IDCOL 9
  • 10. Key Achievement (The Punch- line) 3.1 IDCOL’s role in power sector of Bangladesh: Until August 2009, IDCOL financed a total of USD 103 million in traditional power projects financing a total generation capacity of 725.35 MW. The USD 80 million loan channeled by IDCOL to the 450-MW Meghnaghat Power Plan, sourced from the World Bank, is the largest private sector financing in Bangladesh. 3.1.1 Telecommunication and IT Projects financed by IDCOL: IDCOL financed network expansion projects of telecommunication operators, broadband a wireless access network project, nationwide telecommunication transmission network project, VSAT hub station project, international gateway services network, and several other IT projects. Total loan amounts in these projects were BDT 2,500 million. 3.1.2 IDCOL’S Solar Home System (SHS) Program: IDCOL undertook its solar program in January 2003 with the support from International Development Association (IDA) and Global Environmental Facility (GEF) to fulfill basic electricity requirements in the rural areas of Bangladesh. Under the program, IDCOL intended to provide both grant and refinancing to 50,000 solar home systems (SHS) over a period of five-and-half years [January 2003 - June 2008]. SHS is a convenient mode of supplying power for small electrical loads such as lights, radio/cassette players and black and white TV. Although available for limited number of hours in a day the supply is reliable and the system can be managed with a little training. The main components of an SHS are a solar panel, a battery and a charge controller. The program is being implemented through several Partner Organizations (POs) selected from NGOs/MFIs/Private Companies. So far thirteen POs namely: Grameen Shakti, BRAC Foundation, COAST Trust, TMSS, SRIZONY Bangladesh, CMES, IDF, Shubashati, SINGER Bangladesh, UBOMUS, DORP, BRIDGE and PMUK have signed Participation Agreements (PA) with IDCOL to participate in the solar program. The role of the PO is to select the project areas and potential customers, extend loans, install the systems and provide maintenance support. IDCOL provides grants and refinance, sets technical specification for solar equipment, develops publicity materials, provides training, and monitors PO’s performance. Grant is provided to lower costs of SHS and to build institutional capacity of the POs. IDCOL’s principal objective is the commercialization of SHS. Therefore, it has adopted a policy of reducing grant with the progress of the project. IDCOL also offers soft loans of 10-year maturity with 2-year grace period at 6% interest per annum to its POs. Usually, IDCOL does not require 10
  • 11. any collateral or security for the loan, except for a lien created on the project accounts. IDCOL conducts physical verification of the SHSs installed. It releases grants and refinance amounts only if the inspection result is satisfactory. IDCOL has achieved the target installation of 50,000 SHSs in August 2005, three years ahead of the project completion period and US$ 2 million below the estimated costs. Following the success of IDCOL’s solar program, the World Bank has extended further support for financing of additional 60,000 SHSs. KfW has also signed a Finance and Program Agreement to provide EUR 16.5 million as grant to government to be used for further expansion of the program. To mitigate the gap between IDA and KfW financing, GTZ has agreed to provide grant financing for 28,000 SHSs. In total, IDCOL will finance 198,000 SHSs by 2009. Up to 30 June 2006, a total of 76,607 SHSs have been installed under the program. Division wise SHS installations up to 30 June 2006 are shown below: Division No of Installations Division No of Installations Division No of Installations Barisal 11,385 Khulna 14,500 Rajshahi 9,886 Chittagong 18,085 Dhaka 13,303 Sylhet 9,447 Total 76,607 Source: Investment department, IDCOL Two committees namely Operations Committee (OC) and Technical Standards Committee (TSC), coordinate various aspects of implementation of the program. OC consisting of representatives from POs and IDCOL officials meets once in every month to look after the operational aspects of the solar program. TSC determines technical standards for equipment to be financed, review the product credentials submitted by dealers, and approve the eligible equipment. IDCOL also conducts training program to build awareness among the staff of the POs’ and the consumers. 11
  • 12. Technical Standards Committee Operations Committee Household IDCOL MFIs Suppliers Seeks Approval Provides Approval Supplies Equipment Sell systems & channel Grant A Seeks Grant & Refinancing Provide Grant A, B & Refinancing Seek operations related solutions Provide solutions Pays for Equipment Downpayment & monthly installments Fig: IDCOL Solar Programme – At a Glance The program has brought in positive changes in the economy of the rural people. Now customers are using SHS in the advantage of their income generating activities. Students are also getting benefits through extended hour of studies at night. In addition, the use of TV and radio has enhanced rural people’s access to the outer world. A good number of job opportunities, both for skilled and unskilled manpower, have been created. Till March 2006, some 1,000 new jobs have been created by the program. The program also has a positive impact on our local manufacturing industry. Except for the PV module, other components of SHS are now produced locally. 3.1.3 National Domestic Biogas and Manure Program: IDCOL is implementing National Domestic Biogas and Manure Programme (NDBMP) with support from GoB, SNV Netherlands and KfW. Under the project a total of 60,000 domestic sized biogas plants will be financed during 2006-2009 all over Bangladesh. The overall objective of the NDBMP is to further develop and disseminate domestic biogas plants in rural areas with the ultimate goal to establish a sustainable and commercial biogas sector in Bangladesh. 12
  • 13. Gas produced through these plants is used for cooking purposes and lighting of rural households. In addition, the slurry, by-product of biogas plants, being a very good organic fertilizer is used to maintain soil fertility and increase crop production. The slurry is also used as fish feed. IDCOL is implementing this programme through partner organizations (PO) including private companies, NGOs, Micro finance institute (MFIs). There are 4 types of POs: (a) Construction Partner Organizations (CPOs), (b) Lending Partner Organizations (LPOs), (c) Lending and Construction partner Organizations (LCPOs) and (d) Manufacturing Partner Organization (MPOs). At present 19 POs are implementing NDBMP. IDCOL provides Taka 9,000 as investment subsidy to the biogas households who install biogas plants as per the specifications and standard set by IDCOL/SNV. IDCOL is also providing refinance covering 80% of the LPOs and LCPOs loan to households at 6% interest rate and 7 year tenor with 1 year grace period. Total project cost is estimated as EUR 23.61 million and will be borne by individual households, SNV, KfW and GOB. 13
  • 14. Chapter-4: Importance and limitations of REP financing 4.1 Importance of Project Financing For Rep: •For REP, neither the developer nor the purchasers can self finance. Majorities are not sufficiently capitalized and do not have enough track record to attempt corporate balance sheet financing. •The public sector which has invested a considerable amount of tax payers’ money in the technology through Research and Development (R&D) is typically not appropriate as the source of finance. The funds that are available are also not adequate for such large scale deployment efforts. •In the private sector the traditional form of energy finance which is venture capital, is too expensive to use for financing the REP. •Developers may not want to solely bear risks associated with the project. •Since it is an off balance sheet loan, small sized developers would be free to pursue several projects at the same time with limited negative balance sheet impacts. 4.2 Factors limiting project finance of rep: ♦ Many projects are perceived by the financial community to have high resource and technology risks. These real and perceived risks result in financing that is more costly than that available to more traditional sources. ♦ Since RE technology is relatively new, financial institutions lack experience in evaluating risks associated with REPP. Furthermore, rapidly changing technology and a shortage of RE technology engineers means that lenders do not have the technical know how to assess and monitor many REPs. ♦ The renewable industry and RE projects are small compared to traditional power plants. Lenders are usually not interested in small transactions. Even where finance is available, the transaction costs are much higher for smaller REP because many of the same financing and documentation processes must be followed irrespective of the size of the project. ♦ REPP can only operate when their resources are available. The intermittent nature of RES means they generate less cash flow than fossil fuel fired plants. This provides lower margins for project financing and puts pressure on costs associated with overhead and maintenance costs. ♦ The process of arranging financing is time consuming. 4.3 Need for Renewable Energy4.3 Need for Renewable Energy  To ensure energy security – 70% of Bangladesh's total commercial energy is provided by natural gas and the remainder almost entirely provided by imported oil, hydropower and coal. – These sources are likely to be depleted by 2020.  To reduce negative environmental consequences – Climatic change will eventually cause increase in sea level- one meter sea level rise will inundate more than 15 percent of Bangladesh, displacing more than 13 million people and cut into the crucial rice crop.  To supplement Government’s view on: 14
  • 15. – Electricity for all by 2020. – Government has set a target to meet 5% of total power demand by 2015 and 10% of total power demand by 2020 from renewable energy sources.  To reach out to off-grid areas where grid electricity is not available: – More than two third of the nearly 15 million households of Bangladesh lack access to electricity – Two approaches might be followed to provide electricity to off-grid areas: • Individual or household options for dispersed population • Community or private sector initiatives involving mini-grids for distributed supply of power 4.4 Renewable Energy4.4 Renewable Energy PotentialPotential of Bangladeshof Bangladesh::  Solar energy – Being located near the Equator, the country is recipient of sufficient sunshine round the year – SHS can be easily installed and maintained with little training – 6 million solar home systems in off-grid areas – 330 MW of electricity – 2 hundred thousand solar irrigation pumps – 1000 MW of electricity – Solar mini grid – Solar thermal power plant  Biogas – Cattle population is about 24.19 million (1996) yielding about 242 million kg of cattle wastes per day with a potential for construction of 3.46 million 2.4 m3 biogas plant. – Moreover, using poultry droppings alone, domestic sized plants are technically feasible in 80,000 poultry farms Chapter-05: Introduction to Project Finance 15
  • 16. 5.1 What Is Project Finance? The basic premise of project finance is that lenders loan money for the development of a project solely based on the specific project’s risks and future cash flows. As such, project finance is a method of financing in which the lenders to a project have either no recourse or only limited recourse to the parent company that develops or “sponsors” the project (the “Sponsor”). Non- recourse refers to the lenders’ inability to access the capital or assets of the Sponsor to repay the debt incurred by the special purpose entity that owns the project (the “Project Company”). In cases where project financings are limited recourse as opposed to truly non-recourse, the Sponsor’s capital may be at risk only for specific purposes and in specific (limited) amounts set forth in the project financing documentation. Project financing has been used in various ways for many years, but in the 1970s and 1980s it emerged as a leading way of financing large infrastructure projects that might otherwise be too expensive or speculative for any one individual investor to carry on its corporate balance sheet. Project financing has been particularly important to project development in emerging markets, with participants often relying on guarantees, long-term off-take or purchase agreements, or other contractual relationships with the host sovereign or its commercial appendages to ensure the long- term viability of individual projects. These were typically backstopped by multilateral lending agencies that mitigated some of the “political” risks to which the project lenders (and, sometimes, equity investors) were exposed. 5.2 What Underpins Project Finance? As a general (if not universal) rule, lenders will not forgo recourse to a project’s Sponsor unless there is a projected revenue stream from the project that can be secured for purposes of ensuring repayment of the loans. In the case of large wind and solar power projects, this revenue is typically generated from a power purchase agreement (“PPA”) with the local utility, under which the project may be able to utilize the creditworthiness of the utility to reduce its borrowing costs. While the wind power market has matured significantly in the past five years, leading to the successful project financing of “merchant” projects in the absence of long-term PPAs, Solar Projects are generally not yet able to be project financed in such a manner. In merchant power projects, lenders are able to receive assurance of the project’s ability to repay its debt by focusing on commodity hedging, collateral values, and the income to be produced based on historical and forward-looking power price curves and fully developed markets. In non-power generation contexts, the project’s revenue stream may be a long-term operating agreement (e.g., in the case of toll roads), a capacity purchase agreement (e.g., in the case of transmission lines), a production sharing agreement (e.g., in the case of oil field development), or a series of short-term and spot sales into commodity markets (e.g., in the case of biofuels projects). While project finance lenders clearly prefer a long-term contract that ensures a relatively consistent and guaranteed revenue stream (including assured margins over the cost of inputs), in the context of some industries, lenders have determined that sufficient revenues to support the project’s debt are of a high enough probability that they will provide debt financing without a long-term off-take agreement. Solar Projects, due to their peak period production, high marginal 16
  • 17. costs, and lack of demonstrated merchant capabilities, are not at this time viewed as “project financeable” without PPAs that cover all or substantially all of their output. Solar Projects’ lack of merchant viability is exacerbated by the fact that the southwest United States (the region most appropriate for utility-scale solar power development) does not have a mature merchant power market that functions in the absence of long-term bilateral sales agreements. The dependence of large-scale solar projects on the PPA model is not expected to change in the short to intermediate term. 5.3 When to Project Finance? One of the primary benefits of project financing is that the debt is held at the level of the Project Company and not on the corporate books of the Sponsor. When modeling projects and projected income, the internal rate of return of Sponsors and other project-level equity investors can increase dramatically once a project is fully leveraged. Sponsors are frequently able to recover development costs at the closing of the project financing and put their money into other projects. Another benefit of project financing is the protection of key Sponsor assets, such as intellectual property, key personnel, and investments in other projects and other assets, in the case of the Project Company’s bankruptcy, debt default, or foreclosure. Moreover, project financing allows for a wide variety of tax structuring opportunities, particularly in the context of monetizing tax incentives. On the other hand, project financing is document-intensive, time-consuming, and expensive to consummate. It is not atypical that administrative and closing costs, when factoring in lenders, consultants, and attorneys fees for all parties, equal several percentage points of the amount of the loan commitment. Moreover, project financing imposes significant operating restrictions on each Project Company, including its ability to make equity distributions to the Sponsor prior to the payment of operating expenses, debt service, and a percentage “sweep” of additional cash flow. The result is that the decision of whether to reinvest cash flow in the project does not rest solely with the Sponsor. Given the pros and cons of project finance, the most relevant initial inquiry for an investor or developer may be when is project financing possible or most appropriate? The following questions should be useful in determining if project financing is a realistic opportunity for any given company:  Is there an individual project or group of projects of a sufficient size to make either a standalone or portfolio project financing worthwhile?  Will there be a revenue stream from the project large enough to support a highly leveraged debt financing? This is a prerequisite for project financing.  Will the receipt of revenue be enforceable under contractual rights against a creditworthy party? This is not necessarily a prerequisite for all project financings, but the absence of a contract, or questionable creditworthiness of the purchaser, will prompt lender skepticism and necessitate thorough due diligence regarding future revenue projections.  Will there be physical assets sufficient to ensure lender repayment in case of foreclosure? Lenders will want to know that even if the Project Company’s projected revenue stream does not materialize, they will be able to foreclose on the project’s assets sufficient in value to “make themselves whole,” either by selling the project outright or operating it until the debt is repaid. 17
  • 18.  Is there a significant level of technology risk? While in many project financings, technology may be relatively new or cutting edge, project finance lenders almost never want to be the first to finance an untested technology. Demonstrated successful use in some context will often be necessary to secure project financing.  Does the project have contractual relationships with reputable companies for services key to the success of the project or the technology it employs? Lenders will be less likely to lend to a project the success of which depends solely on a few talented individuals who may depart, leaving the project unable to meet its potential.  Is the Sponsor ultimately willing to “risk the project”? In other words, once project financing is completed, the Sponsor loses the ability to determine how the vast majority of the project’s revenue is spent. In the event a project becomes uneconomic and unable to service its debt, the only option besides refinancing the debt may be to turn over the project to the lenders (voluntarily or involuntarily), with the corresponding loss of the Sponsor’s investment in the project.  Is the Sponsor looking for a quick exit? Once project-financed, divestiture opportunities are complicated by the requirement of lender consent, and potential purchasers will be thoroughly examined by lenders for development and operational expertise as well as creditworthiness.  Are Sponsors willing to grant rights of high-level oversight regarding the project’s development and operation to project finance lenders? In many cases the interests of the Sponsor and the lenders will be aligned, and lenders will tend to defer to the Sponsor’s developmental expertise. On the other hand, lenders must be viewed as additional project partners, with veto rights over many significant decisions. 5.4 Project Financing Versus Direct Financing? Project financing should be compared to direct financing on the sponsor's general credit, when deciding how best to finance a project whose characteristics would make it suitable for project financing. It is important to appreciate that just because project financing might be arranged does not mean that the project should be financed in this manner. The below figure compares direct financing by the sponsor and project financing, on the basis of several criteria. Criterion Direct Financing Project Financing 18
  • 19. Organization  Large businesses are usually organized in corporate form.  Cash flows from different assets and businesses are commingled.  The project can be organized as a partnership or limited liability company to utilize more efficiently the tax benefits of ownership.  Project-related assets and cash flows are segregated from the sponsor's other activities. Control and monitoring  Control is vested primarily in management.  Board of directors monitors corporate performance on behalf of the shareholders.  Limited direct monitoring is done by investors.  Management remains in control but is subject to closer monitoring than in a typical corporation.  Segregation of assets and cash flows facilitates greater accountability to investors.  Contractual arrangements governing the debt and equity investments contain covenants and other provisions that facilitate monitoring. Allocation of risk  Creditors have full recourse to the project sponsor.  Risks are diversified across the sponsor's portfolio of assets.  Certain risks can be transferred to others by purchasing insurance, engaging in hedging activities, and so on.  Creditors typically have limited recourse-and in some cases, no recourse-to the project sponsors.  Creditors' financial exposure is project specific, although supplemental credit support arrangements can at least partially offset this risk exposure. Contractual arrangements redistribute project-related risks.  Project risks can be allocated among the parties who are best able to bear them. Financial flexibility Financing can typically be arranged quickly. Financing arrangements are highly structured and very time-consuming. structure of debt Creditors look to the sponsor's entire asset portfolio for their debt service. Creditors look to a specific asset or pool of assets for their debt service. Bankruptcy Lenders have the benefit of the sponsor's entire asset portfolio. The debt is generally not repayable from the proceeds of other unrelated projects. 19
  • 20. 23 Project Finance Corporate Finance Concession Contract Project Company (SPV) Lenders Government Loan Re- paymentSponsor 1 Sponsor 2 Sponsor 3 Users Tariffs Services Concession Contract Private Company Lenders Government Loan Re- payment Tariffs Investment SPV Users Services Fig: Difference between Project and corporate finance 5.5 Participants of a project finance: Sponsor:  Developer of the project  Project sponsor(s) may consist of an individual but more often is organized as a company  Sponsors must demonstrate previous track record and experience in managing the project  Sponsors Insist on long term predictable cash flows. Project Company:  Separate entity from sponsors  Sponsor(s) generally form a special purpose vehicle ("SPV") to own and operate the project. This SPV is known as Project Company  Sponsor members are required to make capital investments in the SPV according to the terms of their share holders’ agreement  Lenders give loans to the SPV, not to the sponsors Construction Contractor:  Construction contractor is the entity that builds the project under an engineering procurement and construction contract ("EPC").  EPC contracts are generally fixed price – fixed term.  Lenders prefer a single EPC contract because it gives them a single-point responsible party for all activities. 20
  • 21.  EPC contractor is subject to penalty payment for underperformance.  Contractor’s involvement is short term in nature.  Higher (and earlier) profitability. Lenders: 1. Multilateral and Bilateral Agencies  The World Bank, EBRD, ADB, African Development Bank etc.  International Finance Corporation  Regional development banks, etc. 2. Commercial Lenders 3. Export Credit Agencies  US Export Import Bank ("US Exim")  Export Credit Guarantee Department of the United Kingdom ("ECGD")  Export Credit Agency of France ("COFACE")  Export Credit Agency of Germany ("KfW"). 4. Bond Markets 5. Insurance Companies Off-taker:  The entity that is the single purchaser of the project output  More than one off-taker is very uncommon  Some Project Financed deals do not have off-takers, e.g.  toll road Suppliers Offtakers Government Project Managers Engineers Operators Sponsors Contractors Local Partners InsurersEquity Investors Mezzanine Investors Banks 21
  • 22.  container port  mass transport system, etc.  The off-take agreement guarantees purchase of project output  The payments due under the off-take agreement constitute a major element in determining the finance-ability of the project. Operator:  Responsible for the operation and maintenance of the project in exchange of fee  Operator is subject to penalty payment for underperformance  Project company can also be an operator Input Supplier:  Responsible for delivery of inputs to the project  Input supply agreement may be entered into  Take or pay contract  Supplier is also subject to penalty payment for underperformance 5.6 Structures of project finance transactions: Despite the complexity inherent in the nature of the financing, some contend that every project financing can be fitted into the same basic structure and essentially has the same components. One proponent of such thinking is Thomas H. Pyle, Managing Director of the Princeton Pacific Group and project finance lecturer with the Euromoney Institute of Finance. Pyle calls this prototypical structure “the project finance angel.” The halo of the angel is the government; the project sponsor is the head; the contractor and operator serve as wings; the project company is the body; the supplier and customer represent the arms; and, the banks are the angel’s feet. The outspread arms and the body together also symbolize the project’s throughput - the tollable commodity that creates the cashflow. The following diagrams illustrate the transfiguration of the angel into a power plant. Of course, as transactions become more complex, it is necessary to modify the basic structure. 22
  • 24. Chapter-06: IDCOL for project financing 6.1 Eligibility to get IDCOL loan for projects: IDCOL will lend up to a maximum of 40 percent of the total project cost to private sector sponsored infrastructure projects in Bangladesh that meet the following eligibility criteria: 24
  • 25. • Priority: Projects should be an integral part of the GOB's priority plan for the relevant sector/sub-sector. • Ownership: The project must be majority-owned by the private sector parties. Private sector parties must hold at least 51% of the project's equity and be significantly involved in its management for a period of at least 10 years, or the life of the IDCOL loan, whichever is longer; • Viability: The sponsors should have a proven track record of successfully developing, financing and operating similar infrastructure projects in countries at a similar level of development in Bangladesh; • Equity: To ensure sponsor's commitment to the project, equity should represent not less than 20% of the total project cost; • Technology: The technology proposed for a project should have a successful track record in countries at a similar level of economic and technological development and infrastructure support in Bangladesh; • Procurement: IDCOL, generally, will finance GOB solicited projects. In those cases where the solicited project satisfies IDA Procurement Guidelines (the Guidelines), the sponsors will be allowed to follow their own procurement processes for downstream purchases. In the case of unsolicited projects, or solicited projects that do not conform to the Guidelines, IDCOL is required to satisfy itself that the "downstream procurement" for the engineering, procurement and construction (EPC) services required to build the facility equipment and/or works that are an integral part of such facility, are made in accordance with the provisions of the Guidelines. In the latter case, IDCOL's loan support will be limited to the value of the "downstream procurement" made following such Guidelines; • Limited Recourse: Projects should be financially viable on their own with robust and predictable cash flows; • Environment and Social Framework: Projects should meet GOB and IDCOL environmental and social assessment criteria; and • Economic Rate of Return: The economic rate of return of the project should be at least 12 percent. 6.2 Terms & Conditions of IDCOL for project financing: Interest rates IDCOL participates in a project's financing plan with either fixed or floating rate. IDCOL prices its loans in reference to London Inter-Bank Offered Rate (LIBOR), a US dollar denominated interest rate index that is prevalent in the Euro-markets. Under current pricing, all loans are priced at a variable rate equal to the prevailing US dollar three-month LIBOR plus a margin set once each year with reference to current market conditions. Currently, the margins for senior and subordinated loans are 350 basis points and 400 basis points, respectively. For loans denominated in BDT, IDCOL sets interest rates with reference to two years Govt. Treasury Bill plus 400 basis points. Each year, IDCOL Board reviews the company's lending terms and conditions. In case of syndicated financing IDCOL's interest rate may match with that of other lenders providing similar 25
  • 26. loans. As a prudent lender, IDCOL desires and at times may require the borrowers to enter into an interest rate hedge arrangement to prevent potential project cash flow shortages should LIBOR increase dramatically. Such a hedge may be arranged in the financial markets by borrowers or by IDCOL itself. IDCOL provides soft loan in case of rural infrastructure having development impact. In that case IDCOL’s interest rate may vary from 6% to 9.5% p.a. Currencies In cases of IDCOL's US Dollar funding resources, it generally prefers to lend in that currency if borrowers generate their revenue in that currency or have an appropriate revenue contract denominated in local currency with an embedded hedge i.e., indexed to US dollars. IDCOL may also finance projects that do not generate hard currency or whose tariffs do not have indexation provision, provided that the projects sponsors agree to create a currency depreciation reserve. Repayment schedule for IDCOL loan is semi annually / quarterly and will be set forth in US dollar. However, repayment in local currency is permitted provided that repayment is made in equivalent Bangladesh Taka (BDT) converted at the rate of exchange prevailing at the time of repayment. However, IDCOL extends credit in BDT if a project does not have a revenue contract, generates only local currency and is perceived to have high development impact. Tenor Loan tenor depends on the nature of the specific project and the life of the assets financed. Within this constraint, the final maturity of a senior loan may be for up to 15 years while that for a subordinated loan may be up to 23 years. The final maturity of a local currency loan is expected to be between 5 and 10 years depending upon the specific attributes of the project. Repayment Repayment is normally in equal semi annually / quarterly installments of principal and interest with a suitable grace period on repayment of principal. A maximum grace period of 4 years and 8 years, respectively for senior and subordinated loan is permitted and the construction period of the project will be part of the allowed grace period. Depending upon project needs, the borrower has the option of using its equity resources to fund the interest due during construction or, otherwise, co-financing these amounts with draw downs forthcoming from debt commitments. In the latter case, interest on the loan will be payable from the Commercial Operations Date. Security 26
  • 27. IDCOL requires appropriate security for its loans that include inter alia: • Pledge of shares in the project company and creation of a voting trust permitting lenders to vote the shares of the company in times of distress; • Direct agreements with key project participants that allow lenders to "step in" and take over the project when it is in trouble, without affecting the legality and validity of project agreements; • First priority legal mortgage on all immovable assets as well as first priority hypothecation on all movable assets of the project company; • Assignment of project company rights under all project agreements; • Assignment to the extent possible of all contractors' and manufacturers' warranties; • Completion guarantee and other similar support from sponsors; and • First loss payee on insurance policies on project assets or interruption against natural force majeure as well as for business interruption or delayed start-up. • Lien on project accounts. 6.3 IDCOL Project Cycle: Loan application The sponsor(s) will be required to provide certain specific financial and technical information. A formal application must be submitted to IDCOL by the sponsor(s) containing required information including, for this purpose, a feasibility study acceptable to IDCOL. The feasibility study would be reviewed by IDCOL to ensure that it satisfies its requirements and those of concerned parties. After an initial clearance-in-principle, a non-binding Preliminary Letter of Support (PLS), including a draft Term Sheet and Loan Agreement would be issued to the sponsor/borrower. Appraisal IDCOL carries out its own independent appraisal of the economic, technical and financial viability of each project and ensures that the investment is in line with national policies and priority development programmes of the GOB. During the appraisal, IDCOL also verifies compliance with environmental protection and procurement regulations. IDCOL treats any information received in the course of its operations as confidential. Approval Following a careful examination of the final appraisal report, the Board of Directors of IDCOL will make final decision on the application. Effectiveness of the loan from IDCOL will be subject to all other financing for the concerned Project being irrevocably committed and effective. 27
  • 28. Monitoring IDCOL loan contracts provide for monitoring of implementation progress and expenditure. After completion, a report is drawn up, which includes a comparison of actual with initial estimates. Loan processing procedure along with Due Diligence process flow Projects financed by IDCOL are typically funded on a limited recourse basis. The stages through which IDCOL provides approval for a project are described below and summarised in the following figure titled IDCOL's Project Cycle: Step 1. Once approached by a potential sponsor/borrower(s), the Executive Director and Chief Executive Officer (“CEO-IDCOL”) and/or other senior officials of the Company will meet with the sponsor/borrower(s) to discuss the general terms and conditions of IDCOL loans as well as the eligibility criteria and loan process. Step 2. The project cycle will begin with the receipt of a completed loan application along with a non-refundable application fee1 applicable for the project. Sponsors requiring foreign currency loans are required to pay the application fee in US dollars; whereas domestic sponsors may pay this amount in local currency. Upon receipt, the IDCOL staff will review the application to ensure that all necessary information in the loan application has been included and that all required documentation has been submitted. For projects eligible for financing under Private Sector Infrastructure Development Project (PSIDP), the Sponsor's ability or willingness to meet eligibility criteria such as IDA procurement policy will have to be firmly established during steps 2-3. In cases where information or documentation is missing, IDCOL will contact the Sponsor to complete the application. IDCOL’s Project Cycle 1 28
  • 29. Step 3. In case of projects eligible for financing, IDCOL officials conduct a procurement review for the project as per the relevant procurement guidelines. 29 Appointmentof:  Lenders'sCounsel  IE  MarketExpert  Insurer  FinancialmodelAuditor Application Received Steps1&2 Procurement Review Step 3 Doesnot meetICB IDCOL Board Step 5 Sponsorsdonot agreeto downstream procurement Sponsors agree todownstream procurement IDCOLBoard disapproves IDCOLBoard approves Inform Sponsors Inform Sponsors Issuance of PLS Step 6 Project Agreements notsigned Project Agreements signed Letter of Engagement Steps 7 &8 Sponsorsdonot agreewithterms Sponsorsagree withterms Lenders' meetingand review of:  Commontermsheet  IEreport  Marketexpert'sreport  Insurancereviewreport  Financialmodelaudit Unsatisfactory Review Satisfactory Review IDCOLasks Sponsorsfor mitigants Project Appraisal Steps 9 &10 IDCOL Board disapproves IDCOL Board approves IDA'sCertificate of'NoObjection' Inform Sponsors Loan Documentation Steps10-17 IDCOLdoesnot participate IDCOLdoesnot participate MeetsICB Inform Sponsors IDCOLdoesnot participate Inform Sponsors IDCOLdoesnot participate Inform Sponsors IDCOLdoesnot participate Yes No Financial Closing Step18 Preliminary Project Appraisal Step 4
  • 30. In case of a solicited project eligible for financing under PSIDP, it must follow the IDA Guidelines. Where the project is unsolicited, the Sponsor's agreement to conduct a "downstream" ICB tender for the procurement of EPC services and works and/or equipment will have to be secured. Then, CEO's comments and the procurement review will be submitted to IDA for their clearance. Step 4. Once all other information has been received, IDCOL will begin its preliminary project appraisal. In this step, IDCOL will analyse the information and documentation submitted by the Sponsor and prepare a preliminary project appraisal for review by the CEO-IDCOL prior to its presentation to the IDCOL Board of Directors. The purpose of this step is to (i) assist the Board in making a decision whether or not to proceed further with the project; ii) identify any weak spots in the project; and (iii) initiate discussions of potential risk mitigation measures with the Sponsors. Step 5. Upon obtaining approval from the IDCOL Board, IDCOL will prepare an indicative draft term sheet. In case of projects eligible for financing under PSIDP, CEO-IDCOL will review the term sheet, seek the views of IDA and the Company's legal counsel and then, submit it to the IDCOL Board of Directors for approval. Step 6. IDCOL will issue a Preliminary Letter of Support (“PLS”) to the Sponsor along with a copy of the indicative draft term sheet. CEO-IDCOL will request from the Sponsors copies of all signed project documents as they become available. In case of PSIDP projects, issuance of the PLS will be subject to the Board approval, receipt of procurement clearance from IDA, and receipt of the first part of the Project Examination Fee of 0.0625 percent of the financial assistance being sought (but not exceeding $25,000). If the project was subject to a formal solicitation, CEO-IDCOL will request procurement clearance from IDA. Step 7. For PSIDP projects, after receipt of the signed project documents, IDCOL will prepare an engagement and indemnification letter which will be sent to the Sponsors, with a request for the second half of the Project Examination Fee of 0.1875 percent of financial assistance sought. If the project was an unsolicited proposal, the engagement letter and indicative draft term sheet must limit IDCOL financing to no more than a) 100 percent of the cost of any portion of goods and services which is subsequently tendered using IDA guidelines or b) 40% of project cost, whichever is lower. Step 8. CEO-IDCOL will request a letter ("Information Letter") from the Sponsor updating the information provided in the original project proposal and discussing any changes and/or recent developments. In addition, IDCOL will seek Board approval of any appointment by the lending syndicate of lenders' legal counsel and technical advisors. Step 9. IDCOL will prepare the Terms of Reference (“TOR”) for appraising the project eligible for financing under PSIDP and commission necessary short-term technical advisers (“STTA”) in 30
  • 31. consultation with CEO-IDCOL. With receipt of the Information Letter, engagement and indemnification letters and applicable fee, CEO-IDCOL will seek approval from the Board to initiate the formal project appraisal process. Step 10. From time to time, IDCOL will participate in lenders’ meetings for the purpose of reviewing the work of technical advisors and legal counsel as well as drafting common term sheets. Step 11. IDCOL officials (The STTAs, with the assistance of IDCOL officials, in case of projects under PSIDP) will prepare the project appraisal report for submission to the CEO-IDCOL for his review and comments. Step 12. Based on lenders’ meetings and on the recommendations of the project appraisal report, IDCOL will prepare a final draft loan term sheet, consistent with the lenders' common terms sheet and any additional understandings that may exist with Sponsors, for review by the CEO-IDCOL (and for comment from IDA for PSIDP projects.) Step 13. Once the final draft term sheet has been prepared, a copy will be submitted along with the completed project appraisal report to the Credit Committee of the IDCOL Board for approval. Step 14. Once approval of the IDCOL’s Credit Committee is obtained, IDCOL will submit recommendation of the Credit Committee to the Board of Directors for approval. Following approval of loan terms by the Board, IDCOL will issue a loan sanction letter to the sponsor. Subsequently, IDCOL will sign the loan agreements with the Sponsor, collect the other relevant fees applicable for the project and close the loan sanctioning process In case of projects eligible for financing under PSIDP, approval of project is subject to IDA’s “no objection.” Chapter-07: Case study Analysis of a renewable energy project of IDCOL: PGEL 100 kW Solar Mini Grid at Sandip Island The proposed project involves setting up of a 100-kW solar photovoltaic (PV) based micro-grid by PUROBI Green Energy Limited (PGEL) at Sandip island, Chittagong. A 40-kW diesel 31
  • 32. generator will be integrated into the proposed power plant in order to ensure adequate power supply during periods of low solar radiation.Once completed, the Project is expected to supply electricity to adjacent 390 shops, 5 health centers and 5 schools. 7.1 The Project This chapter provides an overview of the project, rationale of the project, procurement of machineries, implementation status, management team, project cost, and financing plan. 7.1.1 Project Description The proposed project involves setting up of a 100-kW solar photovoltaic (PV) based micro-grid by PUROBI Green Energy Limited (PGEL) at Sandip island, Chittagong. A 40-kW diesel generator will be integrated into the proposed power plant in order to ensure adequate power supply during periods of low solar radiation. PGEL is a consortium of four NGOs namely Bangladesh Rural Integrated Development Grub-Street Economy (BRIDGE), Integrated Development Foundation (IDF), Upokolio Bidyut and Mohila Unnoyon Samity (UBOMOUS) and Rural Energy and Development Initiative (REDI). Once completed, the Project is expected to supply electricity to adjacent 390 shops, 5 health centers and 5 schools. Expected commercial operation date of the Project is within the first week of June 2012. The following table presents key project information: 32
  • 33. Particulars Plant capacity 100-kW Location Sandip Island, Chittagong Project land area 8700 sq. ft. Design SMA Technologies AG Major equipment Solar Modules (poly crystalline), batteries (48V, 18000 AH), grid tie, SI inverter, backup diesel generator Equipment Manufacturers Solar Modules: KYOCERA, Japan (Assembled in China) Battery: RIMSO Battery, Grid Inverter: SMA Solar Technology AG of Germany Engineering, Procurement and Construction (EPC) contractor Asantys Systems O&M contractor Prokousoli Sangshad Limited (PSL) Table: Key Project Information 7.1.2Rationaleof theProject Expanding rural electrification is the key to the prosperity and development of rural areas as well as to fulfill the GOB’s vision of ensuring access to affordable and reliable electricity for all by 2020. It is well recognized that energy demand in our rural areas is increasing and supply of fossil fuel at subsidized prices is becoming an ongoing challenge for the government. Moreover, providing power without intensifying the effect of climate change is a priority for Bangladesh. There is also increased emphasis on increasing the energy conversion efficiency and promoting the use of alternate energy sources. The island of Sandip is located in the south-eastern part of the country with an area of 700 square kilometers. This island is a habitat to a population of 300,000 who are detached from Chittagong mainland by a channel of about 75 kilometers. Because of its position and inaccessibility there is no possibility of grid electrification service in this area in the distant future. However, the island has a dynamic population with various public and private service offerings providing support to the general public including educational institutions, health service centers, small and medium enterprises, etc. Despite shortage of reliable and consistent supply of electricity, use and willingness of use of various loads have been found in this region i.e. computers, printers, scanners, photocopy machine, refrigerators, color television, etc. At present, the electricity demand of general shops in the markets of Sandip are served by diesel micro-grid run by several diesel generator operators who provide services for about 5 to 8 hours 33
  • 34. per day. Besides, several diesel generators are used by several shop owners for captive consumption. Average tariff rate being charged to the customers by the diesel operators currently range between BDT 53 per kWh and BDT 60 per kWh. The proposed Project envisages supplying reliable and consistent supply of quality electricity to the local commercial shops, health centers and schools at an affordable, reasonable and competitive price to encourage income generating activities more than before and enhance standard of living of the local people. 7.1.3 Procurement of Machinery The Sponsors are in the process of finalizing a contract with Asantys Systems which will be responsible for supplying the required machineries and accessories and installing the grid. The solar modules will be procured from KYOCERA and inverter, sunny Web box and battery fuse will be procured from SMA Solar Technology AG of Germany. Batteries will be procured locally from RIMSO Battery. Moreover, PSL will provide O&M services and training to the management of the Project during the first one year of operation. 7.1.4 Implementation Status PGEL has been registered as a private limited company with Registrar of Joint Stock Companies of Bangladesh. As discussed above, the Sponsors have finalized their choices of technologies and equipment. The proposed Project land has already been identified which is owned by UBOMOUS, one of the Sponsors. Once the Project gets approval for the required grant and financing, UBOMOUS will duly transfer the ownership of the Project land to the proposed Project Company and will enter into an equipment supply contract with Asantys Systems. A detailed implementation plan showing the phase wise implementation of the Project activities is provided in Annexure I. 7.1.5 Management Team The Project management team of the Project Company will be formed after the formation of the Company. The experience and expertise of the NGOs in the microfinance and renewable energy businesses will be harnessed while formation of the Project management team by transferring experienced and knowledgeable personnel to the proposed Project Company. 7.1.6 Project Cost Total cost of the proposed Project has been estimated to be BDT 55.37 million. Breakdown of total cost is shown below: 34
  • 35. Table 7.1: Budgeted Project Cost Particulars Amount (BDT) Amount (BDT) % of Project costs Land and Land Development 1,260,000 2.28% Civil Construction 2,400,000 4.33% Equipment -Solar Modules (100 kW) 21,000,000 -Grid Tie, SI Inverter 6,375,000 -Backup Diesel Generator – 40 kW 500,000 -Accessories 500,000 -Batteries – 48 V, 18000 Ah 11,161,700 39,536,700 71.41% Transportation 725,000 1.31% Distribution & Others -Distribution Line (5 km) 1,050,000 -AC Household Meters 1,000,000 -Control Room, Structure & Others 800,000 2,850,000 5.15% Import Duty & Clearance Cost 956,250 1.73% Technical Assistance 2,866,200 5.18% Contingency 4,772,795 8.61% TOTAL PROJECT COST 55,366,945 100.00% 7.1.7 Financing Plan The Project is proposed to be financed with a mix of debt, equity and GEF grant fund: Table 2.4: Financing Plan Amount (in million BDT) % Debt 16.61 30% Grant 27.69 50% Equity 11.07 20% Total 55.37 100% 7.2:TheSponsor This chapter discusses about the sponsors of the Project, in particular its ability to provide financial support ensuring the completion and subsequent operation of the Project. Within this context, the chapter includes - corporate history and financial analysis of the sponsors, ownership structure of the Project company, background and experiences of the owners, net worth analysis of the owners and comments on sponsors' Credit Information Bureau (“CIB”) Report. 35
  • 36. 7.2.1 The Project Company PGEL has been registered as a private limited company with Registrar of Joint Stock Companies of Bangladesh on 17 December 2009 with an authorized capital BDT 20 million and paid up capital of BDT 10 million. 7.2.2 Shareholding Structure The proposed shareholding structure PGEL is shown below. Table 3.1: Proposed shareholding Structure No Name of the Shareholders Number of Shares % 1 BRIDGE 50 25 2 IDF 50 25 3 UBOMOUS 50 25 4 REDI 50 25 TOTAL 2,000 100.00% 7.2.3 Credit Information Bureau report Credit Information Bureau ("CIB") report describing the status of the sponsors with other banks/financial institutions is expected to be collected soon. However, clean CIB report on the sponsor will be a condition precedent for disbursement of loan. 7.3: Technical Aspects This chapter includes overview of technology used, plant design, technical review of major plant equipment and comments from kfW consultant. 7.3.1ProjectOverview 7.3.1.1 Proposed Process and Technology The proposed Project is to electricity production through solar micro-grid. The full technology will be supplied by Asantys Systems on a turnkey basis. 7.3.1.2 Electricity Generation through Solar Micro-grid 36
  • 37. Technology The size of the solar micro-grid project under consideration is 100 kW accompanied by 40 kW Diesel. The solar micro-grid is given in Figure 1, which is a combined operation of several sub- systems. The Solar PV modules are the main power generation system that is operational during daytime. About 60 kW of the PV modules will be directly connected to 6 Sunny mini central (SMC with MPPT) inverters which will convert from DC to AC power at 220V and supply to the micro-grid distribution line at all times. Three phase configuration of the AC distribution line will be configured through the Multi-cluster box, which is the interface for all connectors and control. The unused portion of the power in the distribution line will be stored into the batteries through 12 bidirectional inverters called Sunny Islands in 4 clusters. During daytime additional 40 kW PV power will be stored into the same battery bank through DC battery chargers (SIC40 with MPPT). When the grid power is not available, mainly during evening hours the plant will use power from the battery bank. During the worst season of solar radiation, and on cloudy days, backup power will be provided by the 40kW Diesel generators. Figure: Solar Micro Grid Layout using Four Cluster Sunny Island Major Equipment: List of major Equipment 37
  • 38. Equipment Supplier Country of Origin Photovoltaic Module Kyocera KYOCERA, Japan (Assembled in China) Inverter SMA Solar Technology AG Germany Battery RIMSO Bangladesh Grid Inverter SMA Solar Technology AG Germany Sunny Web box & Battery Fuse SMA Solar Technology AG Germany Photovoltaic (PV) Module: The PV Module is polycrystalline and highly efficient. There will be 500 nos. of 200Wp PV Modules. The PV Module is expected to be procured from Kyocera. The major features of the proposed PV module model KC200GH-2P are as follows: Particulars Model KC200GH-2P Maximum Power (Pmax) 200Wp (+10%/-5%) Maximum Power Voltage (Vmp) 26.3V Maximum Power Current (Imp) 7.61A Open Circuit Voltage (Voc) 32.9V Short Circuit Current (Isc) 8.21A 7.4 Market Analysis This chapter provides a detailed analysis of the existing electricity consumption pattern of electricity market of Sandip. Plant output, demand analysis, load distribution plan, electricity tariff and revenue projection have also been discussed in this chapter. 7.4.1PlantOutput According to the Assessment Report of PSE AG, electricity generated by an 80-kW solar mini- grid at the project site would be able to meet 88,100 kWh of energy demand. Accordingly, proposed 100 kW plant will satisfy 110,125 kWh demand. The total electricity generation of the Project has been targeted to be 137,977 kWh per year. Therefore, the remaining 27,852 kWh will be provided by a diesel generator. 7.4.2DemandAnalysisandPricing 7.4.2.1ConsumerComposition: The Project plans to supply electricity to several areas adjacent to the project site namely Enam Nahar Market, Malekmunsir Bazar, Khontarhat, Panditerhat, and Boktarhat. Three categories of potential customers have been identified for supplying electricity in these areas as mentioned in the following table: 5.1: Potential customer composition Customer Total number of potential customers Total number of targeted customers Small shops 478 390 38
  • 39. Health care 5 5 Schools 5 5 7.4.2.2 Load Consumption Pattern: According to a survey conducted by the Sponsor in the proposed target market areas, the daily electricity demand of those areas is more than 400 kWh per day. However, the Project expects to provide electricity only to the adjacent small shops, health care and schools, satisfying requirements for about 378 kWh per day. Proposed load distribution of the Project has been summarized in the following table: Table: Proposed load distribution of the Project Service Type Appliance Type Appliance per Consumer Daily Power Usage % Actual Load (kWh) No. of Consu mers Total load (kWh) Hrs. No. Capacity (W) a. Small Shops Basic CFL Lamp 4 3 18 100% 0.216 390 84.24 Ceiling Fan 13 1 40 50% 0.26 390 101.4 Black & White TV 8 1 25 100% 0.2 100 20 Refrigerator 24 1 80 50% 0.96 20 19.2 Equipment Computer 14 1 100 100% 1.4 50 70 Scanner 5 1 60 20% 0.06 20 1.2 Laser Printer 2 1 200 20% 0.08 20 1.6 Color Printer 8 1 100 20% 0.16 20 3.2 Laminating Machine 4 1 400 10% 0.16 5 0.8 Soldering Iron 9 1 200 100% 1.8 20 36 b. Health Centers Basic CFL Lamp 4 3 18 100% 0.216 5 1.08 Ceiling Fan 13 2 40 50% 0.52 5 2.6 Equipment X-Ray Machine 0 1 20% 0 0 0 ECG Machine 0 1 20% 0 0 0 c. Schools Basic CFL Lamp 4 20 18 100% 1.44 5 7.2 Ceiling Fan 13 10 40 50% 2.6 5 13 Equipment Computer 8 5 100 50% 2 5 10 Printer 13 5 100 20% 1.3 5 6.5 Total daily consumption (kWh) 378.02 Total yearly consumption (kWh) 137,977 Source: Investment department, IDCOL The load consumption in different hours of the day has been assumed to appear according to the following table: Service Type Applia nce Type AM PM Total load in kWhHours of the day 1 2 3 4 5 6 7 8 9 1 0 1 1 1 2 1 3 1 4 1 5 1 6 1 7 1 8 1 9 2 0 2 1 2 2 2 3 2 4 a. Small Shops 39
  • 40. Basic CL 2 1 . 1 2 1 . 1 2 1 . 1 2 1 . 1 84.2 CF 7 . 8 7 . 8 7. 8 7 . 8 7 . 8 7 . 8 7 . 8 7 . 8 7 . 8 7 . 8 7 . 8 7 . 8 7 . 8 101.4 TV 2 . 5 2 . 5 2 . 5 2 . 5 2 . 5 2 . 5 2 . 5 2 . 5 20.0 RT 0. 8 0. 8 0 . 8 0. 8 0 . 8 0 . 8 0 . 8 0 . 8 0 . 8 0 . 8 0 . 8 0. 8 0 . 8 0 . 8 0 . 8 0 . 8 0 . 8 0 . 8 0 . 8 0 . 8 0 . 8 0 . 8 0 . 8 0 . 8 19.2 Equipm ent CR 5 . 0 5 . 0 5 . 0 5. 0 5 . 0 5 . 0 5 . 0 5 . 0 5 . 0 5 . 0 5 . 0 5 . 0 5 . 0 5 . 0 70.0 SR 0 . 2 0 . 2 0 . 2 0 . 2 0 . 2 1.2 LP 0 . 8 0 . 8 1.6 CP 0. 4 0 . 4 0 . 4 0 . 4 0 . 4 0 . 4 0 . 4 0 . 4 3.2 LM 0. 2 0 . 2 0 . 2 0 . 2 0.8 SI 4 . 0 4 . 0 4. 0 4 . 0 4 . 0 4 . 0 4 . 0 4 . 0 4 . 0 36.0 Sub-total 337.6 b. Health Centers Basic CL 0 . 3 0 . 3 0 . 3 0 . 3 1.1 CF 0 . 2 0 . 2 0 . 2 0 . 2 0 . 2 0 . 2 0 . 2 0 . 2 0 . 2 0 . 2 0 . 2 0 . 2 0 . 2 2.6 Sub-total 3.7 c. Schools Basic CL 1 . 8 1 . 8 1 . 8 1 . 8 7.2 CF 1 . 0 1 . 0 1 . 0 1 . 0 1 . 0 1 . 0 1 . 0 1 . 0 1 . 0 1 . 0 1 . 0 1 . 0 1 . 0 13.0 Equipm ent CR 1 . 3 1 . 3 1 . 3 1 . 3 1 . 3 1 . 3 1 . 3 1 . 3 10.0 PR 0 . 5 0 . 5 0 . 5 0 . 5 0 . 5 0 . 5 0 . 5 0 . 5 0 . 5 0 . 5 0 . 5 0 . 5 0 . 5 6.5 Sub-total 36.7 40
  • 41. Total Load per day 378 Source: Investment department, IDCOL *CFL Lamp=CL, Ceiling Fan=CF, Black & White TV=TV, Refrigerator=RT, Computer=CR, Scanner=SR, Laser Printer=LP, Color Printer=CP, Laminating Machine=LM, Soldering Iron=SI, Printer=PR. Graph 5.1: Daily load profile of the proposed Project[ 7.4.2.3 Pricing The pricing will be done in three categories: one time connection fee, monthly line rent and regular tariff. The connection fee and line rent will vary depending on the category of consumers. The following table represents the proposed pricing structure of the Project: 5.3: Pricing structure of the Project Customer Type Small shops Health Center School One Time Connection Fee (BDT) 4,000 6,000 6000 Monthly Line Rent (BDT) 100 100 100 Tariff (BDT per kWh) 27 Effective Tariff (BDT per kWh) 30.53 7.5: Financial Analysis 41
  • 42. This chapter focuses on the financial analysis of the proposed project. Key parameters examined in the analysis include: (a) project cost, (b) debt plan, (c) sponsors’ equity support commitments, (d) grant percentage determination, (d) financial statement analysis, and (e) sensitivity analysis regarding debt service coverage ratio (“DSCR”) and other key variables. 7.5.1 ProjectCostandFinancingPlan 7.5.1.1BudgetedProjectCost Budgeted project cost is BDT 55.37 million, break down of which is given below. Table 7.1: Budgeted Project Cost Particulars Amount (BDT) Amount (BDT) % of Project costs Land and Land Development 1,260,000 2.28% Civil Construction 2,400,000 4.33% Equipment -Solar Modules (100 kW) 21,000,000 -Grid Tie, SI Inverter 6,375,000 -Backup Diesel Generator – 40 kW 500,000 -Accessories 500,000 -Batteries – 48 V, 18000 Ah 11,161,700 39,536,700 71.41% Transportation 725,000 1.31% Distribution & Others -Distribution Line (5 km) 1,050,000 -AC Household Meters 1,000,000 -Control Room, Structure & Others 800,000 2,850,000 5.15% Import Duty & Clearance Cost 956,250 1.73% Technical Assistance 2,866,200 5.18% Contingency 4,772,795 8.61% TOTAL PROJECT COST 55,366,945 100.00% • Capital expenditure including land, land development, plant, machinery, and equipment and 42
  • 43. other assets account for 84% of the total project cost. • Machinery and equipment worth BDT 34 million is 71% of the total capital expenditure. 7.5.1.2 Financing Plan The Project is proposed to be financed with a mix of debt, equity and grant fund Table 7.2: Project Financing Plan Amount (in million BDT) % Debt 16.61 30% Grant 27.69 50% Equity 11.07 20% Total 55.37 100% Determination of grant percentage is discussed in Section 6.1.2.3. 7.5.1.2 Debt Plan The key components of debt plan are shown in table below. Table 7.3 Project Debt Facilities Facility Amount (BDT million) Interest Rate Tenor Grace Repayment Term loan 16.61 6% p.a. 10 years 2 years Annuity; In 16 (sixteen) semi- annual installments Table 7.4 Debt Repayment Schedule Facility Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Term loan - - 10% 11% 11% 12% 13% 14% 14% 15% 7.5.1.3 Equity Plan The sponsors will inject BDT 11.07 million in the Project as equity. The sponsors will provide 0.20 acre of land to the Project worth of BDT 0.9 million (valuation to be conducted) and invest BDT 2.8 million for land development and civil construction. Sponsors’ net worth analysis has been discussed in chapter 3 shows that the Sponsors have adequate net worth to provide BDT 7.37 million remaining equity support to the Project. It also ensures that the sponsors are able to source further equity in the Project in case of cost overrun. As already mentioned three of four shareholders of the Project Company are Partner Organizations of IDCOL under its solar energy program. They are successful in implementation of the program and are regularly servicing the debt. This also illustrates their financial capability. 7.5.1.4 Grant Percentage Determination 43
  • 44. As mentioned above, the project will be financed though a mix of debt, equity and grant. The grant amount was determined based on the effect of the grant percentage on the debt service coverage ratio (DSCR) of the sponsor which is the ratio of cash available for debt service in a particular period to debt service requirement for that period. The following table illustrates sponsor’s DSCR at different mix of debt and grant. Table 6.5: Grant Percentage Determination Debt and Grant Mix Minimum DSCR Option I 40% debt and 40% grant 0.96x Option II 35% debt and 45% grant 1.10x Option III 30% debt and 50% grant 1.28x Minimum DSCR requirement for the Project is 1.2x. The DSCR exceeds in the case of Option III i.e. 30% debt and 50% grant. Therefore, 50% grant has been proposed for the Project. 7.6.2 Financial Projection The Project’s projected financial statements have been generated based on a set of revenue, expense and other relevant assumptions. These are summarized below. 7.6.2.1 Revenue Assumptions The proposed Project has two major sources of revenue: • Connection Fee • Sale of electricity; and • Line rent 7.6.2.1.1 Connection Fee: Out of 400 customers, the Project Company will acquire 70% in year 1 and remaining 30% in year 2. It will charge a connection fee for meeting the expenses to be incurred while providing connection to the customers. 7.6.2.1.2 Sale of electricity : Daily consumption required by the customers in the proposed project area has been discussed in detail in the previous chapter i.e. in the Market analysis. The analysis showed that daily load requirement of 400 potential customers is 378 kWh. Accordingly, yearly load demand is 137,977 kWh. PSE AG has conducted technical assessment of the proposed Project considering installation of an 80 kW plant in the Project area which has been discussed in Chapter IV. Their study has shown that an 80 kW plant in the Project area will generate approx. 110,000 kWh of energy per year (which also includes energy losses in the inverters) and will be able to meet 88,100 kWh of energy demand. Hence, proposed 100 kW plant will be able to meet 110,125 kWh of energy demand. The remaining 27,852 kWh of energy demand will be met by a 40 kW diesel generator. 44
  • 45. 7.6.2.1.3 Line Rent: The Project Company will charge a fixed amount of line rent per month on each customer. 7.6.2.2 Pricing Assumptions Electricity tariff for the first year would be BDT 27 per kWh and line rent would be BDT 100 per connection per month. Pricing of each category of revenue components have been assumed to increase by 5% a year after every three years of operation. The following table shows the year-to-year electricity tariff and line rent during the loan life i.e. first ten years of operation: Table 6.6: Pricing Assumptions Facility Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Connection Fee (BDT/connection ) 600 0 6000 Electricity tariff (BDT/kWh) 27.0 27.0 27.0 28.4 28.4 28.4 29.8 29.8 29.8 31.3 Line rent (BDT/per month) 100 100 100 105 105 105 110 110 110 116 45
  • 46. 7.6.2.3 Revenue Composition of the Project - 500,000 1,000,000 1,500,000 2,000,000 2,500,000 3,000,000 3,500,000 4,000,000 4,500,000 5,000,000 Taka 1 2 3 4 5 6 7 8 9 10 Year Revenue from sale of Electricity Line Rent Connection Fee Figure 6.1: Revenue composition of the Project From the figure it can be seen that connection fee is more than the revenue from sale of electricity in the first year of operation. This is due to the fact that the Project Company will acquire customers in the first two years of its operation and 70% of the customers will be connected in the first year. Moreover, the Project will run for only six months in the first year. From the second year, sale of electricity becomes the main revenue source. Line rent comprises a small portion of the revenue. 7.6.2.4 Operating Expenses Assumption Expenses of the Project include the following: • Utility • Salary and allowances • General and administrative expenses • Insurance cost 7.6.2.4.1 Utility expenses: Diesel and lubricating oil will be required to run the diesel generator. Pricing and requirement of these are as follows: Table 6.7: Utility Expenses Price per Liter (BDT) Consumption per kWh (Liter/kWh) Cost per kWh Diesel 45 0.20 9.00 Lubricating oil 250 0.0003 0.08 46
  • 47. A general 5% cost escalation has been considered in each of these cost items. 7.6.2.4.2 Salary and Allowances: Table 6.8: Salary and Allowances Designation Number Gross Salary per Month Yearly Salary & Bonus Manager 1 10,000 130,000 Accountant 1 8,000 96,000 Lineman / Electrician 2 6,000 72,000 Guard 2 4,000 48,000 346,000 A 5% yearly increment has been considered for each of the employees. 7.6.2.4.3 General and administrative expenses: This category includes conveyance, postage, printing & stationary, entertainment, telephone, internet and others. A general 5% cost escalation has been considered in each of these cost items. General and administrative expenses in the first year of operation are as follows: Table 7.9: General and Administrative Expenses Item BDT Conveyance 3,000 Postage 1,000 Printing & Stationary 6,000 Entertainment 1,000 Telephone/Mobile Bill 3,000 Internet 2,000 Others 12,000 28,000 7.6.2.4.4 Insurance: It has been assumed to be 0.25% of capital costs per annum and this is a fixed amount. 7.6.2.5 Depreciation & Amortization Assumption The following table shows the depreciation and amortization rates for different categories of assets: Table 6.10: Depreciation and Amortization Depreciation No of years Rate Plant, Machinery & Equipment 20 5% Building and Civil Construction 20 5% Battery 7 14% Amortization Technical assistance 5 20% 47
  • 48. Battery accounts for 22% of the project cost though its life is only 7 years. Therefore, it has to be replaced at least twice during the project cost. 7.6.2.6 Tax & Dividend Assumption The project is expected to enjoy tax holiday. Therefore, no tax provisions have been made in the model. After the loan life, 50% of the net profit has been considered to be distributed as dividends in the model. 7.6.3 Key Financial Indicators Key indicators of the Project are presented in the following table: Table 7.11: Project’s Key Results Ratio Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 DSCR 3.41 4.12 1.28 1.35 1.34 1.32 1.39 1.38 1.36 1.44 Average 1.84 Minimum 1.28 Average ROE 5.08% IRR 10.27% NPV BDT 23,229,468 The indicators represented in Table 6.11 express that the project has good cash flow. 7.6.4 Sensitivity Analysis Sensitivity analysis has been done along a number of scenarios: 1. Increase in operating expenses 2. Reduction in tariff 3. Reduction in electricity generation Table 6.12: Sensitivity Analysis Case DSCR Average Minimum Base case 1.84 1.28 Operation expenses increased by 30% 1.71 1.19 Tariff reduced by 15% 1.57 1.07 Electricity generation reduced by 30% 1.64 1.12 The above table shows that the Project is expected to have satisfactory DSCR in the base case and apparently, it will be able to service the debt obligations even in much adverse scenarios. 48
  • 49. 7.6.5Pro-forma financial statements The Projects’ pro-forma financial statements and ratio analysis are attached in the Annexure II. Chapter-08: Findings and Conclusion A Critical Evaluation of Project Financing in Bangladesh by IDCOL: To evaluate the whole project financing program of IDCOL, the following ways can be discussed: 8.1 Project Selection – Regional Imbalance: As IDCOL’s share is totally owned by the government of Bangladesh, making a positive contribution towards the society is the main objective of IDCOL rather than only making profit. That is why IDCOL mainly invest in the off grid areas of the country and logically these off grid areas are the most under developed portions of the country. IDCOL finance projects throughout the country where it finds it necessary so there is no regional imbalance in renewable energy project 49
  • 50. financing of IDCOL. Source: Ahammed & Taufiq, 2008 Division wise SHS installations up to 30 June 2006 are shown below: Division No of Division No of Division No of 50
  • 51. Installations Installations Installations Barisal 11,385 Khulna 14,500 Rajshahi 9,886 Chittagong 18,085 Dhaka 13,303 Sylhet 9,447 Total 76,607 Source: Investment department, IDCOL 8.2 Negative/positive Impacts of Projects: To find the impacts of the project we have to compare these projects with the other alternatives. As the IDCOL financed projects are mainly in the off grid areas, oil, petroleum etc are main source of energy in these areas. These sources of energy are known as “fossil fuels” and they are composed of hydrocarbons and are formed by nature over eons. These sources emit a huge amount of carbon to the nature and might become the cause of natural disaster. Moreover, once these fossil fuels are combusted, they cannot be replenished or renewed. Apart from this, these provide energy via combustion and, in the process release toxic emissions into the atmosphere, harming humans, animals as well as plant life and thus distort the overall ecological balance on Earth. In fact, each stage in the exploration, extraction, processing, transportation and consumption of fossil fuels is harmful for humans and ecosystems. Furthermore, the large fluctuations in prices of the fossil fuels over the years have made these sources beyond the capacity of the poor people of Bangladesh. Here to overcome these scenarios, the renewable energy projects are working well. This is because, unlike the non-renewable fossil fuels, renewable energy sources capture their energy from existing flows of energy, i.e. sunshine, wind, flowing water, biological processes, and geothermal heat flows which are constantly and naturally being replenished. Thus, unlike the non-renewable fossil fuels, renewable energies are not diminished by consumption. Therefore they are providing a reliable and sustainable supply of energy almost indefinitely. Moreover, the use of renewable energies produce minimal emissions and their increased share in the mainstream energy system, provides a much cleaner energy system compared to fossil fuels, which emit harmful gases like carbon dioxide into the atmosphere, via combustion, thus polluting the environment. The latter fuels are currently emitting an increasing amount of Greenhouse Gases like carbon dioxide, nitrogen oxides, sulfur oxides and un burnt methane into the atmosphere, via combustion, which is the root cause of the much-spoken global warming, sea- level rise and climate change. In contrast to fossil fuel energy, renewable energies can be derived domestically from local sources. This aspect is especially beneficial to Bangladesh to pursue locally applicable energy 51
  • 52. strategies, more or less independent of the national network. It also enhances the access to energy supplies in small, isolated rural areas and helps the rural poor to attain a higher quality of life by providing better community health and educational services. This results in potential economic, ecological, social, and security benefits for the rural poor. Nothing has all the merits. This renewable energy projects might cause some problems as well. For example for the solar energy project the batteries need to be changed after a certain time frame. If they are not disposed properly, it might cause serious hazards for the nature. Lastly here I should mention that through the renewable energy project financing of IDCOL thousands of employment opportunities have been created that will make a positive contribution to Bangladesh where a huge portion of the people is unemployed. 8.3 Financing Problems: It can be easily understood from the following table that the financing or disbursement process is so lengthy and troublesome. If any party fails to disburse the amount in time then the whole process will be delayed and in some cases will be destroyed. IDCOL faces these problems time to time. For example if IDA does not disbursement the loan in time, IDCOL will fail to finance the partner organization. Thus the consumer will not be able to construct the energy plant or consume. These might happen due to: o Non-compliance of the terms and conditions set by the upper level by the lower lover agency. o Inefficiency of the designated officials, etc. 52
  • 53. Fig: The process of disbursement 8.4 Summary of Major Findings: Here are the summaries of major findings: • All the renewable energy projects financing of IDCOL are funded by international financial institution or development agencies. IDCOL is mainly working as the intermediary in these cases. • IDCOL’s principal objective is the commercialization of SHS. Therefore, it has adopted a policy of reducing grant with the progress of the project. So in future it may be impractical for the poor people to grab the benefit and this project might loss its attractiveness. • IDCOL does not require any collateral or security for the loan, except for a lien created on the project accounts. This makes it possible for anyone without security to take the opportunity of financing. • IDCOL follows a very rigorous process in giving loan and subsidy; this sometimes makes the process of financing lengthy. • IDCOL is implementing its programme through partner organizations (PO) including private companies, NGOs, Micro finance institute (MFIs). That’s makes the process lengthy. Further studies can be done on whether these intermediaries or IDCOL itself can fiancé directly to make the process easy. 53