This document discusses inspection activities for plant turnaround shutdown management. It outlines the steps to review inspection activities, including defining activities, ensuring proper resource usage and schedule control, and accurate reporting. The outcomes of proper activity planning are also described, such as remaining on budget. Statistics from the last shutdown show inspection activities made up 73% of the tasks. The document recommends optimizing the number of inspection activities and using resources efficiently to improve tracking and control. Additional proposed activities need precise planning to avoid delays and justify any issues. The overall schedule may be affected if more inspection tasks are added without the proper logic.