AS08 Project Charter, Implementation Strategy Plan
& Change Management Plan
Gold Team 2: The Goldening
Wesley Brown
Project Charter
Project Stakeholders + Team Charter:
Team Charter INFO 461
Team Name: Gold Team 2: The Goldening
Team Leader: Michael Miller
Team Members:
Name Email Phone#
Unzila Baig Baiguf@vcu.edu 703-401-1192
Joshua Allen Allenj5@vcu.edu 757- 645-8221
Wesley Brown Brownwr2@vcu.edu 757- 880-4554
Michael Miller Millermc4@vcu.edu 757-817-4628
Team Strengths:
Unzila Baig: I do well in group related projects by providing direction and my technical input.
Being a senior in the field of Information Systems I have worked in many group projects and
enjoy the experience that I gain from each team. I’m a quick learner and hard worker. I have
worked with all the Microsoft application that we will using such as Project, Visio and Excel. I
have experiences with programming languages such as HTML, CSS, JavaScript and C#.
Josh Allen: I have worked in several groups throughout my time at VCU. I excel at providing
documentation of work and extensive work in Visio. I have worked with various systems and
offer input from a network/system perspective.
Michael Miller: Like my peers, I have worked in numerous group projects related to information
systems. I’m an easy-going person and always a team player, but I’m not afraid to step up into a
leadership position if needed. I perform well with bookkeeping, Visio, and maintaining a positive
environment.
Wesley Brown: I have had extensive group work experience, and of late have been specialized
to our Major, Information Systems. In the past I have been able to contribute to the team by
remaining punctual, and always contributing to the team by submitting new ideas, and ultimately
able to perform technically using MS: Visio, Project, Excel, HTML, SQL and Linux.
**Roles: We will have rotating roles as the semester goes on.
Availability Times:
Unzila Baig:
Monday: 1pm-3:50pm
Tuesday: N/A
Wednesday:1pm-3:50pm
Thursday: After 6:45
Friday: 1pm- All day after
Saturday: All day
Sunday: All day
Michael Miller:
Monday: Before 2pm and after 6:45 pm
Tuesday: 3:15pm - 7 pm
Wednesday: Before 2pm and after 6:45 pm
Thursday: After 3:15pm
Friday, Saturday and Sunday: All Day
Wesley Brown:
Monday: Before 4 pm
Tuesday: 7 am - 12:15pm, 3:15pm - 530 pm
Wednesday: Before 4 pm
Thursday: 7 am - 12:15pm, 3:15pm - 530 pm, 6:45 pm - Night
Friday: Before 5 pm
Saturday: N/A
Sunday: N/A
***Every day except Tuesdays available 9:30 pm
Short Bio
Unzila Baig:
I’m currently a senior at Virginia Commonwealth University. I transferred to VCU during Fall
2014 from Northern Virginia Community College. My major is Information Systems. I’m currently
looking for an internship that is more narrow down towards the IT field. I wanted to pursue this
major due to the fact I’m fairly interested in learning different programs languages. Furthermore,
I want to learn more about network security so eventually I can pursue my career in
cybersecurity.
Josh Allen:
I am a senior at VCU majoring in Information Systems. I transferred from Thomas Nelson
Community College in 2012, and have enjoyed my experience at VCU tremendously. I currently
live in Williamsburg, although I lived here in Richmond for 3 years while attending school. I am
most interested in the network and security side of Information Systems, and would like to
pursue a career in Network Administration or Cybersecurity.
Michael Miller:
I’ve been a student at VCU since the fall of 2010. I’m double majoring in Psychology and
Information Systems. As much as I enjoy learning about Psychology, I realized late in my school
career that I wanted to pursue a career in Information Systems. Gloucester County is my
hometown, but I have been living in Richmond since attending VCU. At the moment, I would like
to pursue a career in network administration. Outside of school, I like movies, gaming, music
and playing with my cat. I would like to create my own indie game at some point in my life, or
make some short videos for YouTube.
Wesley Brown:
28 year old student, 2nd attempt at college. Currently employed at CarMax as a Sales
Consultant where 90% of my job is problem solving and building rapport with my customers
within a short time period. Have worked as a Food and Beverage manager for 5 years with 60+
multi-national employees, therefore large experience with training, communication skills,
operations and logistics. Currently busy with my 15 credits at VCU, my not-so part-time job (I
work about 30hrs a week) and constant home maintenance with a house which is occupied by 6
animals, my girlfriend, and a roommate.
Team Rules: Finish the task assigned. If you can’t complete then let the group members know
so we can plan accordingly. Have your task done before coming to group meetings. You cannot
miss more than three group meetings. Respect everyone’s ideas and comments. If you are to
miss more than three meetings and give no input into the project then you will be given a lower
letter grade than the groups. If there is a conflict among group members we will all meet
together to resolve the conflict before going higher in the chain of command.
Code of ethics: Each member is required to be honest about their strengths and weaknesses
and if a problem occurs, then ask for help.
All members of Gold Team I have read, understood, and agree to adhere by the rules and
regulations outlined in the team charter. The submission of this charter indicates that every
member of the team has agreed to provide a positive learning environment for themselves and
their peers to produce quality projects in systems analysis and design. This charter signifies the
opportunity for each member to learn about information systems, acquire skills regarding project
management and designing a system, and gain better understanding of technical skills through
the completion of group assignments.
Signatures of Agreement Date
Unzila Baig 1/31/2016
Josh Allen 2/1/2016
Michael Miller 2/1/2016
Wes Brown 2/2/2016
Project Description:
The Martial Arts Academy (MAA) is a martial arts studio that teaches both
children and adults. The owners of the studio, Geoff and Julie, would like to manage
their business more efficiently. Geoff and Julie currently use a completely paper-based
system of tracking students, as well as tracking their billing. This paper system has led
to errors in the past, such as losing track of when a particular student has received
enough training to test for their next belt. Geoff and Julie would like to be able to retain
their current customers, as well as bring in new ones, and their reputation may be
hindered by failing to properly manage their studio. They would also like to make sure
that any new system is worth the cost and bring extra revenue to the business.
We would like to propose several options to Geoff and Julie to improve their
management system. We will research existing management systems that can be
purchased, as well as research what would need to be done to build a custom system
for MAA. We will focus on cost-efficiency in both cases, and we will focus on ensuring
that the system is easy to use. If neither of those approaches are cost-effective, as well
as technically feasible for Geoff and Julie, we will suggest that they use the system they
currently have.
Learning Record:
Facts Assumptions Questions to be Answered
The studio has a poor
management system.
It needs to be more
organized.
How can we have a better
organized system?
No technical experience Need to have an easy-
to-use system
How can we make an intuitive
management system?
Any software for the system
must “pay for itself” and bring
tangible benefits to the
Academy.
Will need spend a lump
sum for studio cloud
monthly
How can we provide the best
system for our customers while
spending the least amount of
money?
Action Plan:
Who? Does What? By When?
Unzila Baig Requirements and Time Frame February 8, 2016
Joshua Allen MOV Metrics and Alternatives February 12, 2016
Wesley Brown MOV Summary February 16, 2016
Michael Miller Recommendation February 19, 2016
Measurable Organizational Value (MOV):
Desired Area of Impact: Business management system
Desired Value of the IT Project:
Improve the customer experience by updating the current system handling student
information into a more dependable, streamlined information system. As a result,
current customers satisfied with the overhauled system and a stronger social media
presence can provide stronger customer retention as well as introducing new customers
via positive word of mouth.
Develop an Appropriate Metric:
 15% increase in new customers
 Time Frame for Achieving the MOV
 It will take approximately 1 month to integrate and learn the new system.
After implementing the new system, we predict that results will begin to
show within 1 month. The total time frame for achieving the MOV, therefor,
is predicted to be 2 months.
 Summarize the MOV in a Clear, Concise Statement or Table -Areas of Impact
Summary of MOV:
This project will be successful if an information system that organizes and presents data
on customer, employees and over martial arts academy as business. Our goal is to
deliver an improvement to the overall existing system. The new system will execute the
business rules faster and increase social connections which will provide an 15%
increase in new customers base
Comparison of Alternatives:
1. Off-the-shelf software:
http://studiocloud.com/
“StudioCloud is a FREE, easy-to-use, business management software that works on
both Mac and PC and includes free cloud services. StudioCloud provides an integrated
system including Cloud Syncing, Client Management, Scheduling, Point-of-Sale,
Bookkeeping, Reporting, Marketing Campaigns, Project/Event/Order Management and
much more! The free version of StudioCloud even provides mobility for one user by
syncing all of your StudioCloud data between the cloud, or online server, and all of your
internet enabled devices. With the integration of direct StudioCloud integration into
ProSelect you can now add business management, for one user, to ProSelect for free.
As your business grows, you can subscribe to add more features, services and
workstations to StudioCloud as needed.”
2. Build a System:
Building a system would provide the opportunity to cater specifically to the needs
of MAA, but at a greater cost than buying off-the-shelf software. It also would not
be as viable due to MAA owners Geoff and Julie’s lack of technical expertise.
They would likely need to hire an IT associate to help with their system.
3. Do Nothing:
Using their old system not expanding on the existing system at all.
Total Cost of Ownership (TCO):
.
Total Benefits of Ownership (TBO):
 A more dependable system for managing the studio.
o Managing will be more streamlined and less prone to mistakes. This
means the owners can spend less time fixing mistakes, and more time
improving the experience for their customers. A better system also allows
for scaling if they see a large increase in customers, and will help
streamline the process.
 Increased customer satisfaction
o A better system means less mistakes, which can improve the reputation of
MAA. Good word-of-mouth from current customers can bring new
customers to the studio
 Increasing MAA’s presence in the community
o By creating a social media presence, MAA can draw in more customers to
their studio. Combined with good recommendations from current
customers, MAA can greatly increase their customer base.
Recommendation:
In order for Geoff and Julie to get the most out of improving their management
system for the Martial Arts Academy, we recommend that they incorporate a service
known as StudioCloud. StudioCloud is a free service that provides cloud storage, client
management, and bookkeeping to name a few of their features. Geoff and Julie
requested that they would like a relatively inexpensive and streamlined solution to their
current management system. If they are open to the idea, Geoff and Julie can utilize the
free version of StudioCloud and give it a test run to see if it best fits their need for a new
management system. If they like the service and it provides positive results for the
Academy, they have the option to pay for a subscription to StudioCloud that can provide
more services for the Academy as it continues growing.
Geoff and Julie hope that overhauling the Academy’s current management
system will draw new customers to their business. In addition to using StudioCloud, our
team recommends that they expand their social media presence to advertise why
people should join their academy over others in the area. Creating a Facebook page,
Instagram, and Twitter feed would be very beneficial for spreading information about the
Academy and its new system. All three of these social media outlets would provide the
opportunity for customers to voice their feedback, see pictures about what goes on
during regular business hours, and get a live feed about certain martial arts classes and
activities that are currently happening.
In conclusion, our team believes that using StudioCloud and creating a stronger social
media presence can fulfill the project scope that both Geoff and Julie want to achieve. If
they are supportive of these ideas, then we can move on to the next steps of the project
which involve setting an elaborate budget and detailed work breakdown structure.
Project Description & MOV
This project will be successful if an information system that organizes and presents data
on customer, employees and over martial arts academy as business. Our goal is to
deliver an improvement to the overall existing system. The new system will execute the
business rules faster and increase social connections which will provide a 20% increase
of new customer’s per month.
The MOV will be achieved over a period of 6 months, with an improved customer
experience bringing in new customers through good word of mouth. The implementation
of the new system and the launching of a social media presence will be completed
within the first month. A return on investment is expected in one year after
implementation.
Resources needed for Martial Arts Academy:
1. People: This team will consist of strong individuals from different technical fields
to create a well round team. The people will need to sure the successful creation,
execution, implementation and training for system for the Material Art Academy.
Individuals as, Project Manager, Computer Technician, Network Administrator
and Business Analyst.
2. Technical: We need varies different components of the hardware, network
resources and software. All these components being added to the Academy will
deliver the customer satisfaction and increase business process. Some of the
these components are: Desktop Computer, Printer, Two tablets, StudioCloud
Software and Wi-Fi
3. Facilities: Remote desktop connection will be used due to the fact we can’t work
on sight. We will remotely implement the software. However, will have the
computer technician install all the hardware required for the Academy. For the
installing the Wi-Fi throughout the Academy there will be network engineer
provided by FiSO to install all the routers and network cables.
Resource Cost Table (an estimate for the cost of each resource)
Fixed Cost
Recurring Cost
Product Cost Quantity Total
Desktop $700.00 1 $700.00
Printer $199.99 1 $199.99
Tablet $399.00 2 $789.00
Consulting Fee $5000.00 1 $5000.00
Overall Total $6,6679.00
Personnel Cost/Average Description
Project Manager $84,797 annually
The projectmanager will be in charge
of making sure that the deliverables
are done ina timelymanner.Theywill
be required to seek out solutions to
problems that may arise in the
developmentof the project. They will
do thisbycollaboratingwiththe team
in a professional manner.
Computer Technician $38,120 annually
They will perform duties such
installing the updated hardware and
software through the academy. Also
they will provide technical support
through phone or email or onsite
visits. Also if any hardware is
damagedtheyhave the responsibility
to fix the issue.
Network Administrator $52,919 annually
To manage the system provided and
make sure all programs are running
smoothly and keep the software and
hardware updated as needed.
Business Analyst $66,913 annually
Responsible for improving Martial
Arts Academy competitiveness and
performance across the spectrum.
Translating project requirements and
manage communication from the
team to the business owners.
Contract Payment Method:
Product Cost Payments/Year Total
StudioCloud $65.00 12 $790.00
FiOS Wi-Fi $89.99 12 $1,079.88
Yearly Total $1,859.88
We will be using a fixed cost structure for our contract with MAA. This contract will be in
the form of a consulting fee, as we will not be building a system ourselves. Instead we
are recommending off-the-shelf software and offering advice on implementation.
Project Scope & Scope Management Plan:
Deliverable Structure Chart (DSC):
Use Case Diagram:
Work Break Structure
-0.0 Martial Arts Academy Project
-1.0 Initialize and Conceptualize project
-1.1 Develop Business Case
1.1.1 Consult with clients
1.1.2 Gather information
1.1.3 Develop Learning Record
1.1.4 Develop Action Plan
1.1.5 Define MOV
1.1.6 Compare alternatives
1.1.7 Identify Costs
1.1.8 Milestone: Business Case Completed
-1.2 Present Business Case to client
1.2.1 Review business case with client
1.2.2 Make recommendation to client
1.2.3 Milestone: client signs off on recommendation
-1.3 Milestone: Business case completed
-2.0 Develop Charter and plan
-2.1 Identify resources and costs
-2.1.1 Identify resources
-2.1.2 Develop resource cost table
-2.2 Milestone: Project charter and plan completed
-3.0 Implementation
-3.1 Buy equipment and software
-3.1.1 Purchase items
-3.1.2 Create invoice for client
-3.2 Set up equipment
-3.2.1 Bring hardware into the Martial Arts Academy
-3.2.2 Install software on new equipment
-3.3 Train clients to use new software
-3.3.1 Set up training directly with software vendor
-3.4 Milestone: System implemented
-4.0 Close Project
-4.1 Invoice clients
-4.2 Final Documentation
-5.0 Evaluate Project
-6.0 Milestone: Project complete
Scope Change Process
If a change to the project scope is desired for the Martial Arts Academy’s new system,
the project team will have to utilize a scope change process. A change to the project
scope may only be approved if it provides a strong benefit to the measurable
organizational value or if the change is critical to the project’s completion. To start the
scope change process, a member of the project team must fill out and submit a scope
change request form to the team leader. Once submitted, the request will be recorded in
a scope change request log. The scope change process is designed in a way so that
scope creep can be prevented and that all of the tasks on the critical path can still be
completed on time.
Scope change request
Schedule and Budget:
Project Plan:
Risk ManagementPlan:
Revised ProjectPlan:
Risk Plan
Possible Risks to the Martial Arts Academy
1. Scope creep
2. Improperly managed resources
3. Proposed technology requires a lot of debugging and extra testing
4. Users may not be receptive to the new system
5. Going over budget
Risk Owner Response/Strategy
Scope Creep Project Manager Changes will only occur when
scope change request form is
approved. Complete only
MOV related tasks while
adhering to the scope
management plan.
Earned Value Analysis & Quality ManagementPlan
Improperly managed
resources
Project Manager Follow the structure of the
project charter and strategy
plan
Proposed technology
requires a lot of debugging
and extra testing
Computer Technician Training session with users
including troubleshooting
technique
Users may not be receptive
to the new system
Customer and Business
Owners
Ensure customer needs are
explored thoroughly and
clearly defined
Going over budget Business Analyst Decrease the cost of
hardware and software.
Initial WBS / Estimated Project Progress
Baseline Plan / Updated Project Progress
Earned Value Analysis:
AdditionalReports:
TestIt4U Analysis
Analyzing the data from the initial project time scope to the new project plan there moderate
time delay. Phase one and three both have increase of two days when compared to the initial
plan. Phase two has the greatest time delay and is the most expensive phase. Phase two which
increases from initial 20 days to 27 days and will cost about $5,000 dollars. The only phase that
hasn’t changed was phase four because it has not been completed yet. The overall project with
82% completed should cost about $11,680 dollars with phase four being our remaining cost of
$2,220 dollars. However, the amount of each resource was allocated and didn’t change from the
initial cost of the project.
Project Summary Report
Quality Management Plan:
Team Objective Statement:
Gold Team 2: The Goldening aims to ensure the best quality for our customers. We achieve this
by focusing on the small details that often get overlooked. By working side-by-side with our
customers, we are able to ensure that their needs are met in a timely manner. After
implementation, we will be available as a resource for our customers if they have any questions
or concerns about the system that we have implemented.
Quality Based Metrics:
Type Metric Description
Process 1. Number of Errors
2. Time to Defect
1. Errors encountered by the user
2. Time until an error is encountered
Product 1. Product Defects
2. Customer Response
time
1. Defects people may have found when
training.
2. Amount of time it takes to respond to
customer requests
Project 1. Budget Deficit
2. Schedule Deficit
1. Measures how far below budget the project
is
2. Measures how far ahead of schedule the
project is
Verification Activities:
We will perform a business and management review to ensure that the project will be completed
on time and within the budget. If it has not, we will identify the problem areas in the project and
correct the mistakes. We will ensure that the project is within the agreed-upon scope. We will
also perform a technical review to ensure that the product meets initial requirement.
Validation Activities:
We will present a system review with the customer to ensure that all of their needs are met. We
will ensure that all technical specifications have been met, as well as being feasible for them to
use.
Implementation& ProjectClosurePlan:
Conversion Strategy:
Since the Martial Arts Academy is currently operating with its paper-based management
system and due to the nature of the new computer-based system incorporating
StudioCloud, Gold Team II has decided to use the parallel implementation approach for
the following reasons:
 It will provide a steady process for the employees to become familiar with the
new system.
 Can easily function side-by-side with the current paper system.
 Provides a safety net if the system encounters any problems.
·
Gold Team II will not be using the direct cutover implementation approach for the
following reasons:
 It will place unneeded stress on the employees of the Martial Arts Academy
because they are not familiar with the new system.
 It would be risky if there was a hidden bug in the system that would cause it to
break after implementation, thus halting/delaying the Martial Arts Academy from
performing its day to day operations.
 Puts stress under the project team to meet implementation deadlines.
·
Gold Team II will not be using the phased implementation approach for the following
reasons:
 Contains unnecessary costs and takes longer for the system to be implemented.
 Does not account for the employees that may be having trouble becoming
familiar with the new system.
 Problems encountered in the early phases can impact the overall implementation
schedule.
·
Closure Checklist:
1) Gold Team II will begin the closure procedure by ensuring that all deliverables are
completed and meet the stakeholder’s requirements.
2) Gold Team II will archive all deliverables and documentation related to the project
and store them in an organized fashion.
3) Meet with the stakeholders to have a final validation of the project.
4) Gold team II will invoice the sponsor company for the hardware required to complete
the project. Gold Team II will also provide an invoice to the sponsor for the fees
associated with consulting.
5) Gold Team II will show MMA the new system and will be assisting in teaching the
employees and owners the system.
6) Provide the company an executive summary on the final project.
7) Once the implementation of the project is done then the computer technician will
continuously maintain the system.
8) Coordinate between all Gold Team II members and MMA staff for a brief cocktail
party, celebrating the successful completion of the project.
Project Evaluation:
Individual Performance Review:
The project manager will hold individual performance reviews for each of the team
members in Gold Team II. These reviews will include measuring each individual based
on:
· Having the team member review themselves first, then moving on to the manager’s
review of the team member
· Team members’ general performance throughout the project
· Behavioral characteristics both individually and towards the team
· Team members’ best contribution to the project
· Recommendations and constructive criticism on how they can improve their
performance on the next project
Postmortem Review:
After the project has been completed and implemented into the Martial Arts Academy,
Gold Team II will hold a meeting led by the project manager to evaluate the project as a
whole. The postmortem review will consist of these objectives:
· Review the project’s MOV and evaluate its success
· Review of the scope, schedule, budget, and quality objectives
· Review each of the project’s deliverables such as the risk management plan to see
what can be improved on in the future
· Review overall team performance
Project Audit:
In conjunction with the postmortem review amongst Gold Team II, an outside
perspective from an auditor that is unrelated to the Martial Arts Academy will be utilized
to uncover any problems or opportunities for improvement that Gold Team II may have
missed. The auditor in question will be someone who does not have a personal stake in
the project, who will act in the Martial Arts Academy’s best interest, and who will have a
base of industry experience so they can provide a valid review of the project and its
team. The review from the auditor will function very similarly to the postmortem review
and consist of these objectives:
· Review the project’s MOV
· Review how well the project was managed and executed
· Review the project plans, processes, and project methodologies used throughout
the project
· Assess whether the project manager and team operated in a professional and
ethical manner.
Evaluating Project Success – The MOV:
The MOV that was defined at the beginning of the project will be able to provide results
at 1 month, 6 months, and 1 year after the system is implemented into the Martial Arts
Academy. After 1 month, the new computer-based StudioCloud system will be
implemented and the launch of the Academy’s new social media campaign can begin to
attract new customers. Through the social media campaign and the streamlined
experience for the customers due to the new computer-based management system,
good word of mouth will proceed to attract additional people to become new customers
of the Martial Arts Academy. The amount of new customers for the Academy will be
able to be measured after 6 months. Finally, whether or not a return on investment was
achieved for contracting a team to create and implement a new system will be
measurable 1 year after the system’s implementation. Once the project is completed,
Gold Team II will meet with Geoff and Julie, two of the stakeholders for the project,
where they will determine whether the completed project meets their specific
requirements and if they believe it will meet their customer’s needs.
Change Management Plan:
List of Change Sponsor(s), Target(s), and Agent(s) of Change:
Sponsors of change: Geoff and Julie (Owners of MAA), Cersei Lannister’s co-workers at MAA,
Tyrion Lannister’s co-workers at MAA, Gold Team II and its manager
Targets of change: Cersei and Tyrion
Agents of change: Co-workers of Cersei and Tyrion
Change Assessment: Assessing the two employee’s willingness, readiness, and ability to
change
Cersei:
 Sponsor: Cersei’s boss is who will be able to authorize the changes to the project. The
boss will provide guidance about learning how to use the new system. This will help her
overcome any fear she had about the implementation of the new system.
 Change Agent: The sponsor that will assist Cersei (her other co-workers) will help her
overcome her fear of learning the new system. She will be taught the new system by
someone she trusts and who knows the new system well. This will make her more
comfortable using the new system at her workstation.
Tyrion:
 Sponsor: Tyrion’s sponsor will be his bosses. They have the authority to instruct Tyrion
to do what is expected of him for his job and to decrease any slack in his activities. The
sponsor also has the authority to terminate or put him on probation if he is violating the
code of ethics, procedures or rules of the Academy.
 Change Agent: The change agent will consist of a group of Tyrion’s co-workers. They
will assist in enabling to warn him whenever he is violating any rules. They will help him
realize he is on probation from work and his time should be spent learning the new
system. That will help him once he will rejoin the workforce.
Change Strategy:
Cersei:
Rational-Empirical Approach:
 Convince, explain, and demonstrate how a particular change will benefit the target of
change.
 Provide consistent and timely information to prevent any misinformation from being
spread.
 Be honest with everybody and stress that there is no news so that rumors will not spread
throughout the organization.
Tyrion:
Normative-Re-education Approach:
 The changes will appeal to the social norms of the individuals affected by it.
 Give examples of the new system assisting the users. Compare the new system with the
old to show the improvements.
 A slow change that will affect the culture which will dictate the social norms of the
company.
Process for tracking change management plan:
Keep an open line of communication between change sponsors and the targets of change.
Additionally, if the employees are open to it, monitor social media to see what they think about
the new system. For a face-to-face approach to communicating, the change sponsors and the
owners of MAA could individual meetings so that they may voice their concerns or criticisms
about the new system.Training programs will be in the next phase. A training program outline
will be given to each employee to reference. Once the final examination of the project is finished
the training program will be developed, test and then approved. The implementation will to train
and test hardware. Every task has a set date that will serve as deliverable for the project.

More Related Content

What's hot

Husky Air Project Charter
Husky Air Project CharterHusky Air Project Charter
Husky Air Project Charter
Adam Ransom
 
Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08Greg Eskridge
 
AS08 Project Charter
AS08 Project CharterAS08 Project Charter
AS08 Project Charter
Sabrina Rusli
 
school management system by partha deb nath
school management system by partha deb nathschool management system by partha deb nath
school management system by partha deb nath
partha deb nath
 
School management system
School management systemSchool management system
School management system
deva491
 
Salesforce Application Lifecycle Management presented to EA Forum by Sam Garf...
Salesforce Application Lifecycle Management presented to EA Forum by Sam Garf...Salesforce Application Lifecycle Management presented to EA Forum by Sam Garf...
Salesforce Application Lifecycle Management presented to EA Forum by Sam Garf...
Sam Garforth
 
School Management System
School Management SystemSchool Management System
School Management System
krishna panchal
 
Training management
Training managementTraining management
Training management
Mezbah Uddin
 
site design project charter
site design project chartersite design project charter
site design project charter
Amr Zoair
 
Project Charter Final Report
Project Charter Final Report Project Charter Final Report
Project Charter Final Report
Alex Truong
 
School management system
School management systemSchool management system
School management system
sonetmicrosystem pvt. ltd.
 
School Management Software Proposal
School Management Software ProposalSchool Management Software Proposal
School Management Software Proposal
Mohammad Sayem
 
Online school management system new
Online school management  system newOnline school management  system new
Online school management system neweasysolutionsindia
 
Company Achievements And Challenges PowerPoint Presentation Slides
Company Achievements And Challenges PowerPoint Presentation SlidesCompany Achievements And Challenges PowerPoint Presentation Slides
Company Achievements And Challenges PowerPoint Presentation Slides
SlideTeam
 
School management software proposal
School management software proposalSchool management software proposal
School management software proposal
Mohammad Sayem
 
ERP - Campus Management
ERP - Campus ManagementERP - Campus Management
ERP - Campus Management
Jaspal Singh
 
School softwer slide
School softwer  slideSchool softwer  slide
School softwer slide
Proshanta Halder
 
Software Project Management Plan
Software Project Management PlanSoftware Project Management Plan
Software Project Management Plan
Seval Çapraz
 
School Management System Presentation mss
School Management System Presentation mssSchool Management System Presentation mss
School Management System Presentation mss
Denis kisina
 

What's hot (20)

Project Charter 461
Project Charter 461Project Charter 461
Project Charter 461
 
Husky Air Project Charter
Husky Air Project CharterHusky Air Project Charter
Husky Air Project Charter
 
Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08
 
AS08 Project Charter
AS08 Project CharterAS08 Project Charter
AS08 Project Charter
 
school management system by partha deb nath
school management system by partha deb nathschool management system by partha deb nath
school management system by partha deb nath
 
School management system
School management systemSchool management system
School management system
 
Salesforce Application Lifecycle Management presented to EA Forum by Sam Garf...
Salesforce Application Lifecycle Management presented to EA Forum by Sam Garf...Salesforce Application Lifecycle Management presented to EA Forum by Sam Garf...
Salesforce Application Lifecycle Management presented to EA Forum by Sam Garf...
 
School Management System
School Management SystemSchool Management System
School Management System
 
Training management
Training managementTraining management
Training management
 
site design project charter
site design project chartersite design project charter
site design project charter
 
Project Charter Final Report
Project Charter Final Report Project Charter Final Report
Project Charter Final Report
 
School management system
School management systemSchool management system
School management system
 
School Management Software Proposal
School Management Software ProposalSchool Management Software Proposal
School Management Software Proposal
 
Online school management system new
Online school management  system newOnline school management  system new
Online school management system new
 
Company Achievements And Challenges PowerPoint Presentation Slides
Company Achievements And Challenges PowerPoint Presentation SlidesCompany Achievements And Challenges PowerPoint Presentation Slides
Company Achievements And Challenges PowerPoint Presentation Slides
 
School management software proposal
School management software proposalSchool management software proposal
School management software proposal
 
ERP - Campus Management
ERP - Campus ManagementERP - Campus Management
ERP - Campus Management
 
School softwer slide
School softwer  slideSchool softwer  slide
School softwer slide
 
Software Project Management Plan
Software Project Management PlanSoftware Project Management Plan
Software Project Management Plan
 
School Management System Presentation mss
School Management System Presentation mssSchool Management System Presentation mss
School Management System Presentation mss
 

Similar to INFO 461 AS08 Project Charter, Implementation Strategy Plan & Change Management Plan

Liam Bamford - CV NEW
Liam Bamford - CV NEWLiam Bamford - CV NEW
Liam Bamford - CV NEWLiam Bamford
 
ITM310_001FiliasW16
ITM310_001FiliasW16ITM310_001FiliasW16
ITM310_001FiliasW16Peter Filias
 
Project management presentation.pptx
Project management presentation.pptxProject management presentation.pptx
Project management presentation.pptx
AsadAli719
 
Project report titles for mba in human resources
Project report titles for mba in human resourcesProject report titles for mba in human resources
Project report titles for mba in human resources
mbaprojectconsultacy2014
 
Write A Short Essay On Beauty Of Nature Essay
Write A Short Essay On Beauty Of Nature EssayWrite A Short Essay On Beauty Of Nature Essay
Write A Short Essay On Beauty Of Nature Essay
Melissa Ward
 
Fall 2013 Syllabus: Social Media in Public Relations
Fall 2013 Syllabus: Social Media in Public RelationsFall 2013 Syllabus: Social Media in Public Relations
Fall 2013 Syllabus: Social Media in Public Relations
Vinita Agarwal
 
List of mba institutes in vellore
List of mba institutes in velloreList of mba institutes in vellore
List of mba institutes in vellore
mbaprojectconsultacy2014
 
7 Best Practices for your Moodle RFP
7 Best Practices for your Moodle RFP 7 Best Practices for your Moodle RFP
7 Best Practices for your Moodle RFP
Lambda Solutions
 
Onlearn4
Onlearn4Onlearn4
Revolutionizing the Employee with 1st United Services Credit Union
Revolutionizing the Employee with 1st United Services Credit UnionRevolutionizing the Employee with 1st United Services Credit Union
Revolutionizing the Employee with 1st United Services Credit Union
Silver cloud
 
Development, Frameworks and Methods
Development, Frameworks and MethodsDevelopment, Frameworks and Methods
Development, Frameworks and MethodsMd. Mahbub Alam
 
Expert-Led Online Training for Nonprofit Changemakers on TechSoup Courses- Au...
Expert-Led Online Training for Nonprofit Changemakers on TechSoup Courses- Au...Expert-Led Online Training for Nonprofit Changemakers on TechSoup Courses- Au...
Expert-Led Online Training for Nonprofit Changemakers on TechSoup Courses- Au...
TechSoup
 
Email project
Email  projectEmail  project
Email project
EmanHisham5
 
ILEA Conference - June 2011
ILEA Conference - June 2011ILEA Conference - June 2011
ILEA Conference - June 2011Scott Harringotn
 
Michael C. Rimkus Resume
Michael C. Rimkus ResumeMichael C. Rimkus Resume
Michael C. Rimkus ResumeMichael Rimkus
 
CC 207 Module.docx
CC 207 Module.docxCC 207 Module.docx
CC 207 Module.docx
PaulineTorion1
 
E learning Presentation (.pptx)
E learning Presentation (.pptx)E learning Presentation (.pptx)
E learning Presentation (.pptx)
MarjoToska
 

Similar to INFO 461 AS08 Project Charter, Implementation Strategy Plan & Change Management Plan (20)

Liam Bamford - CV NEW
Liam Bamford - CV NEWLiam Bamford - CV NEW
Liam Bamford - CV NEW
 
ACME Final to share
ACME Final to shareACME Final to share
ACME Final to share
 
ITM310_001FiliasW16
ITM310_001FiliasW16ITM310_001FiliasW16
ITM310_001FiliasW16
 
Project management presentation.pptx
Project management presentation.pptxProject management presentation.pptx
Project management presentation.pptx
 
Project report titles for mba in human resources
Project report titles for mba in human resourcesProject report titles for mba in human resources
Project report titles for mba in human resources
 
Write A Short Essay On Beauty Of Nature Essay
Write A Short Essay On Beauty Of Nature EssayWrite A Short Essay On Beauty Of Nature Essay
Write A Short Essay On Beauty Of Nature Essay
 
AS08Final
AS08FinalAS08Final
AS08Final
 
Fall 2013 Syllabus: Social Media in Public Relations
Fall 2013 Syllabus: Social Media in Public RelationsFall 2013 Syllabus: Social Media in Public Relations
Fall 2013 Syllabus: Social Media in Public Relations
 
List of mba institutes in vellore
List of mba institutes in velloreList of mba institutes in vellore
List of mba institutes in vellore
 
7 Best Practices for your Moodle RFP
7 Best Practices for your Moodle RFP 7 Best Practices for your Moodle RFP
7 Best Practices for your Moodle RFP
 
Onlearn4
Onlearn4Onlearn4
Onlearn4
 
Sanjay_Resume.doc
Sanjay_Resume.docSanjay_Resume.doc
Sanjay_Resume.doc
 
Revolutionizing the Employee with 1st United Services Credit Union
Revolutionizing the Employee with 1st United Services Credit UnionRevolutionizing the Employee with 1st United Services Credit Union
Revolutionizing the Employee with 1st United Services Credit Union
 
Development, Frameworks and Methods
Development, Frameworks and MethodsDevelopment, Frameworks and Methods
Development, Frameworks and Methods
 
Expert-Led Online Training for Nonprofit Changemakers on TechSoup Courses- Au...
Expert-Led Online Training for Nonprofit Changemakers on TechSoup Courses- Au...Expert-Led Online Training for Nonprofit Changemakers on TechSoup Courses- Au...
Expert-Led Online Training for Nonprofit Changemakers on TechSoup Courses- Au...
 
Email project
Email  projectEmail  project
Email project
 
ILEA Conference - June 2011
ILEA Conference - June 2011ILEA Conference - June 2011
ILEA Conference - June 2011
 
Michael C. Rimkus Resume
Michael C. Rimkus ResumeMichael C. Rimkus Resume
Michael C. Rimkus Resume
 
CC 207 Module.docx
CC 207 Module.docxCC 207 Module.docx
CC 207 Module.docx
 
E learning Presentation (.pptx)
E learning Presentation (.pptx)E learning Presentation (.pptx)
E learning Presentation (.pptx)
 

INFO 461 AS08 Project Charter, Implementation Strategy Plan & Change Management Plan

  • 1. Martial Arts Academy INFO 461-001 AS08 Project Charter, Implementation Strategy Plan & Change Management Plan Gold Team 2: The Goldening Wesley Brown
  • 2. Project Charter Project Stakeholders + Team Charter: Team Charter INFO 461 Team Name: Gold Team 2: The Goldening Team Leader: Michael Miller Team Members: Name Email Phone# Unzila Baig Baiguf@vcu.edu 703-401-1192 Joshua Allen Allenj5@vcu.edu 757- 645-8221 Wesley Brown Brownwr2@vcu.edu 757- 880-4554 Michael Miller Millermc4@vcu.edu 757-817-4628 Team Strengths: Unzila Baig: I do well in group related projects by providing direction and my technical input. Being a senior in the field of Information Systems I have worked in many group projects and enjoy the experience that I gain from each team. I’m a quick learner and hard worker. I have worked with all the Microsoft application that we will using such as Project, Visio and Excel. I have experiences with programming languages such as HTML, CSS, JavaScript and C#. Josh Allen: I have worked in several groups throughout my time at VCU. I excel at providing documentation of work and extensive work in Visio. I have worked with various systems and offer input from a network/system perspective. Michael Miller: Like my peers, I have worked in numerous group projects related to information systems. I’m an easy-going person and always a team player, but I’m not afraid to step up into a leadership position if needed. I perform well with bookkeeping, Visio, and maintaining a positive environment. Wesley Brown: I have had extensive group work experience, and of late have been specialized to our Major, Information Systems. In the past I have been able to contribute to the team by remaining punctual, and always contributing to the team by submitting new ideas, and ultimately able to perform technically using MS: Visio, Project, Excel, HTML, SQL and Linux. **Roles: We will have rotating roles as the semester goes on.
  • 3. Availability Times: Unzila Baig: Monday: 1pm-3:50pm Tuesday: N/A Wednesday:1pm-3:50pm Thursday: After 6:45 Friday: 1pm- All day after Saturday: All day Sunday: All day Michael Miller: Monday: Before 2pm and after 6:45 pm Tuesday: 3:15pm - 7 pm Wednesday: Before 2pm and after 6:45 pm Thursday: After 3:15pm Friday, Saturday and Sunday: All Day Wesley Brown: Monday: Before 4 pm Tuesday: 7 am - 12:15pm, 3:15pm - 530 pm Wednesday: Before 4 pm Thursday: 7 am - 12:15pm, 3:15pm - 530 pm, 6:45 pm - Night Friday: Before 5 pm Saturday: N/A Sunday: N/A ***Every day except Tuesdays available 9:30 pm Short Bio Unzila Baig: I’m currently a senior at Virginia Commonwealth University. I transferred to VCU during Fall 2014 from Northern Virginia Community College. My major is Information Systems. I’m currently looking for an internship that is more narrow down towards the IT field. I wanted to pursue this major due to the fact I’m fairly interested in learning different programs languages. Furthermore, I want to learn more about network security so eventually I can pursue my career in cybersecurity. Josh Allen: I am a senior at VCU majoring in Information Systems. I transferred from Thomas Nelson Community College in 2012, and have enjoyed my experience at VCU tremendously. I currently live in Williamsburg, although I lived here in Richmond for 3 years while attending school. I am
  • 4. most interested in the network and security side of Information Systems, and would like to pursue a career in Network Administration or Cybersecurity. Michael Miller: I’ve been a student at VCU since the fall of 2010. I’m double majoring in Psychology and Information Systems. As much as I enjoy learning about Psychology, I realized late in my school career that I wanted to pursue a career in Information Systems. Gloucester County is my hometown, but I have been living in Richmond since attending VCU. At the moment, I would like to pursue a career in network administration. Outside of school, I like movies, gaming, music and playing with my cat. I would like to create my own indie game at some point in my life, or make some short videos for YouTube. Wesley Brown: 28 year old student, 2nd attempt at college. Currently employed at CarMax as a Sales Consultant where 90% of my job is problem solving and building rapport with my customers within a short time period. Have worked as a Food and Beverage manager for 5 years with 60+ multi-national employees, therefore large experience with training, communication skills, operations and logistics. Currently busy with my 15 credits at VCU, my not-so part-time job (I work about 30hrs a week) and constant home maintenance with a house which is occupied by 6 animals, my girlfriend, and a roommate. Team Rules: Finish the task assigned. If you can’t complete then let the group members know so we can plan accordingly. Have your task done before coming to group meetings. You cannot miss more than three group meetings. Respect everyone’s ideas and comments. If you are to miss more than three meetings and give no input into the project then you will be given a lower letter grade than the groups. If there is a conflict among group members we will all meet together to resolve the conflict before going higher in the chain of command. Code of ethics: Each member is required to be honest about their strengths and weaknesses and if a problem occurs, then ask for help. All members of Gold Team I have read, understood, and agree to adhere by the rules and regulations outlined in the team charter. The submission of this charter indicates that every member of the team has agreed to provide a positive learning environment for themselves and their peers to produce quality projects in systems analysis and design. This charter signifies the opportunity for each member to learn about information systems, acquire skills regarding project management and designing a system, and gain better understanding of technical skills through the completion of group assignments. Signatures of Agreement Date Unzila Baig 1/31/2016
  • 5. Josh Allen 2/1/2016 Michael Miller 2/1/2016 Wes Brown 2/2/2016
  • 6. Project Description: The Martial Arts Academy (MAA) is a martial arts studio that teaches both children and adults. The owners of the studio, Geoff and Julie, would like to manage their business more efficiently. Geoff and Julie currently use a completely paper-based system of tracking students, as well as tracking their billing. This paper system has led to errors in the past, such as losing track of when a particular student has received enough training to test for their next belt. Geoff and Julie would like to be able to retain their current customers, as well as bring in new ones, and their reputation may be hindered by failing to properly manage their studio. They would also like to make sure that any new system is worth the cost and bring extra revenue to the business. We would like to propose several options to Geoff and Julie to improve their management system. We will research existing management systems that can be purchased, as well as research what would need to be done to build a custom system for MAA. We will focus on cost-efficiency in both cases, and we will focus on ensuring that the system is easy to use. If neither of those approaches are cost-effective, as well as technically feasible for Geoff and Julie, we will suggest that they use the system they currently have. Learning Record: Facts Assumptions Questions to be Answered The studio has a poor management system. It needs to be more organized. How can we have a better organized system? No technical experience Need to have an easy- to-use system How can we make an intuitive management system? Any software for the system must “pay for itself” and bring tangible benefits to the Academy. Will need spend a lump sum for studio cloud monthly How can we provide the best system for our customers while spending the least amount of money?
  • 7. Action Plan: Who? Does What? By When? Unzila Baig Requirements and Time Frame February 8, 2016 Joshua Allen MOV Metrics and Alternatives February 12, 2016 Wesley Brown MOV Summary February 16, 2016 Michael Miller Recommendation February 19, 2016 Measurable Organizational Value (MOV): Desired Area of Impact: Business management system
  • 8. Desired Value of the IT Project: Improve the customer experience by updating the current system handling student information into a more dependable, streamlined information system. As a result, current customers satisfied with the overhauled system and a stronger social media presence can provide stronger customer retention as well as introducing new customers via positive word of mouth. Develop an Appropriate Metric:  15% increase in new customers  Time Frame for Achieving the MOV  It will take approximately 1 month to integrate and learn the new system. After implementing the new system, we predict that results will begin to show within 1 month. The total time frame for achieving the MOV, therefor, is predicted to be 2 months.  Summarize the MOV in a Clear, Concise Statement or Table -Areas of Impact Summary of MOV: This project will be successful if an information system that organizes and presents data on customer, employees and over martial arts academy as business. Our goal is to deliver an improvement to the overall existing system. The new system will execute the business rules faster and increase social connections which will provide an 15% increase in new customers base Comparison of Alternatives: 1. Off-the-shelf software: http://studiocloud.com/ “StudioCloud is a FREE, easy-to-use, business management software that works on both Mac and PC and includes free cloud services. StudioCloud provides an integrated system including Cloud Syncing, Client Management, Scheduling, Point-of-Sale, Bookkeeping, Reporting, Marketing Campaigns, Project/Event/Order Management and much more! The free version of StudioCloud even provides mobility for one user by syncing all of your StudioCloud data between the cloud, or online server, and all of your internet enabled devices. With the integration of direct StudioCloud integration into ProSelect you can now add business management, for one user, to ProSelect for free. As your business grows, you can subscribe to add more features, services and workstations to StudioCloud as needed.”
  • 9. 2. Build a System: Building a system would provide the opportunity to cater specifically to the needs of MAA, but at a greater cost than buying off-the-shelf software. It also would not be as viable due to MAA owners Geoff and Julie’s lack of technical expertise. They would likely need to hire an IT associate to help with their system. 3. Do Nothing: Using their old system not expanding on the existing system at all. Total Cost of Ownership (TCO): . Total Benefits of Ownership (TBO):  A more dependable system for managing the studio. o Managing will be more streamlined and less prone to mistakes. This means the owners can spend less time fixing mistakes, and more time improving the experience for their customers. A better system also allows for scaling if they see a large increase in customers, and will help streamline the process.  Increased customer satisfaction o A better system means less mistakes, which can improve the reputation of MAA. Good word-of-mouth from current customers can bring new customers to the studio  Increasing MAA’s presence in the community o By creating a social media presence, MAA can draw in more customers to their studio. Combined with good recommendations from current customers, MAA can greatly increase their customer base.
  • 10. Recommendation: In order for Geoff and Julie to get the most out of improving their management system for the Martial Arts Academy, we recommend that they incorporate a service known as StudioCloud. StudioCloud is a free service that provides cloud storage, client management, and bookkeeping to name a few of their features. Geoff and Julie requested that they would like a relatively inexpensive and streamlined solution to their current management system. If they are open to the idea, Geoff and Julie can utilize the free version of StudioCloud and give it a test run to see if it best fits their need for a new management system. If they like the service and it provides positive results for the Academy, they have the option to pay for a subscription to StudioCloud that can provide more services for the Academy as it continues growing. Geoff and Julie hope that overhauling the Academy’s current management system will draw new customers to their business. In addition to using StudioCloud, our team recommends that they expand their social media presence to advertise why people should join their academy over others in the area. Creating a Facebook page, Instagram, and Twitter feed would be very beneficial for spreading information about the Academy and its new system. All three of these social media outlets would provide the opportunity for customers to voice their feedback, see pictures about what goes on during regular business hours, and get a live feed about certain martial arts classes and activities that are currently happening. In conclusion, our team believes that using StudioCloud and creating a stronger social media presence can fulfill the project scope that both Geoff and Julie want to achieve. If they are supportive of these ideas, then we can move on to the next steps of the project which involve setting an elaborate budget and detailed work breakdown structure. Project Description & MOV This project will be successful if an information system that organizes and presents data on customer, employees and over martial arts academy as business. Our goal is to deliver an improvement to the overall existing system. The new system will execute the business rules faster and increase social connections which will provide a 20% increase of new customer’s per month. The MOV will be achieved over a period of 6 months, with an improved customer experience bringing in new customers through good word of mouth. The implementation of the new system and the launching of a social media presence will be completed within the first month. A return on investment is expected in one year after implementation.
  • 11. Resources needed for Martial Arts Academy: 1. People: This team will consist of strong individuals from different technical fields to create a well round team. The people will need to sure the successful creation, execution, implementation and training for system for the Material Art Academy. Individuals as, Project Manager, Computer Technician, Network Administrator and Business Analyst. 2. Technical: We need varies different components of the hardware, network resources and software. All these components being added to the Academy will deliver the customer satisfaction and increase business process. Some of the these components are: Desktop Computer, Printer, Two tablets, StudioCloud Software and Wi-Fi 3. Facilities: Remote desktop connection will be used due to the fact we can’t work on sight. We will remotely implement the software. However, will have the computer technician install all the hardware required for the Academy. For the installing the Wi-Fi throughout the Academy there will be network engineer provided by FiSO to install all the routers and network cables. Resource Cost Table (an estimate for the cost of each resource) Fixed Cost Recurring Cost Product Cost Quantity Total Desktop $700.00 1 $700.00 Printer $199.99 1 $199.99 Tablet $399.00 2 $789.00 Consulting Fee $5000.00 1 $5000.00 Overall Total $6,6679.00
  • 12. Personnel Cost/Average Description Project Manager $84,797 annually The projectmanager will be in charge of making sure that the deliverables are done ina timelymanner.Theywill be required to seek out solutions to problems that may arise in the developmentof the project. They will do thisbycollaboratingwiththe team in a professional manner. Computer Technician $38,120 annually They will perform duties such installing the updated hardware and software through the academy. Also they will provide technical support through phone or email or onsite visits. Also if any hardware is damagedtheyhave the responsibility to fix the issue. Network Administrator $52,919 annually To manage the system provided and make sure all programs are running smoothly and keep the software and hardware updated as needed. Business Analyst $66,913 annually Responsible for improving Martial Arts Academy competitiveness and performance across the spectrum. Translating project requirements and manage communication from the team to the business owners. Contract Payment Method: Product Cost Payments/Year Total StudioCloud $65.00 12 $790.00 FiOS Wi-Fi $89.99 12 $1,079.88 Yearly Total $1,859.88
  • 13. We will be using a fixed cost structure for our contract with MAA. This contract will be in the form of a consulting fee, as we will not be building a system ourselves. Instead we are recommending off-the-shelf software and offering advice on implementation. Project Scope & Scope Management Plan: Deliverable Structure Chart (DSC):
  • 15. Work Break Structure -0.0 Martial Arts Academy Project -1.0 Initialize and Conceptualize project -1.1 Develop Business Case 1.1.1 Consult with clients 1.1.2 Gather information 1.1.3 Develop Learning Record 1.1.4 Develop Action Plan 1.1.5 Define MOV 1.1.6 Compare alternatives 1.1.7 Identify Costs 1.1.8 Milestone: Business Case Completed -1.2 Present Business Case to client 1.2.1 Review business case with client 1.2.2 Make recommendation to client 1.2.3 Milestone: client signs off on recommendation -1.3 Milestone: Business case completed -2.0 Develop Charter and plan -2.1 Identify resources and costs -2.1.1 Identify resources -2.1.2 Develop resource cost table -2.2 Milestone: Project charter and plan completed -3.0 Implementation -3.1 Buy equipment and software -3.1.1 Purchase items -3.1.2 Create invoice for client -3.2 Set up equipment -3.2.1 Bring hardware into the Martial Arts Academy -3.2.2 Install software on new equipment -3.3 Train clients to use new software -3.3.1 Set up training directly with software vendor -3.4 Milestone: System implemented -4.0 Close Project -4.1 Invoice clients -4.2 Final Documentation -5.0 Evaluate Project -6.0 Milestone: Project complete
  • 16. Scope Change Process If a change to the project scope is desired for the Martial Arts Academy’s new system, the project team will have to utilize a scope change process. A change to the project scope may only be approved if it provides a strong benefit to the measurable organizational value or if the change is critical to the project’s completion. To start the scope change process, a member of the project team must fill out and submit a scope change request form to the team leader. Once submitted, the request will be recorded in a scope change request log. The scope change process is designed in a way so that scope creep can be prevented and that all of the tasks on the critical path can still be completed on time. Scope change request
  • 19. Risk Plan Possible Risks to the Martial Arts Academy 1. Scope creep 2. Improperly managed resources 3. Proposed technology requires a lot of debugging and extra testing 4. Users may not be receptive to the new system 5. Going over budget Risk Owner Response/Strategy Scope Creep Project Manager Changes will only occur when scope change request form is approved. Complete only MOV related tasks while adhering to the scope management plan.
  • 20. Earned Value Analysis & Quality ManagementPlan Improperly managed resources Project Manager Follow the structure of the project charter and strategy plan Proposed technology requires a lot of debugging and extra testing Computer Technician Training session with users including troubleshooting technique Users may not be receptive to the new system Customer and Business Owners Ensure customer needs are explored thoroughly and clearly defined Going over budget Business Analyst Decrease the cost of hardware and software.
  • 21. Initial WBS / Estimated Project Progress Baseline Plan / Updated Project Progress
  • 24. TestIt4U Analysis Analyzing the data from the initial project time scope to the new project plan there moderate time delay. Phase one and three both have increase of two days when compared to the initial plan. Phase two has the greatest time delay and is the most expensive phase. Phase two which increases from initial 20 days to 27 days and will cost about $5,000 dollars. The only phase that hasn’t changed was phase four because it has not been completed yet. The overall project with 82% completed should cost about $11,680 dollars with phase four being our remaining cost of $2,220 dollars. However, the amount of each resource was allocated and didn’t change from the initial cost of the project. Project Summary Report Quality Management Plan: Team Objective Statement: Gold Team 2: The Goldening aims to ensure the best quality for our customers. We achieve this by focusing on the small details that often get overlooked. By working side-by-side with our customers, we are able to ensure that their needs are met in a timely manner. After implementation, we will be available as a resource for our customers if they have any questions or concerns about the system that we have implemented.
  • 25. Quality Based Metrics: Type Metric Description Process 1. Number of Errors 2. Time to Defect 1. Errors encountered by the user 2. Time until an error is encountered Product 1. Product Defects 2. Customer Response time 1. Defects people may have found when training. 2. Amount of time it takes to respond to customer requests Project 1. Budget Deficit 2. Schedule Deficit 1. Measures how far below budget the project is 2. Measures how far ahead of schedule the project is Verification Activities: We will perform a business and management review to ensure that the project will be completed on time and within the budget. If it has not, we will identify the problem areas in the project and correct the mistakes. We will ensure that the project is within the agreed-upon scope. We will also perform a technical review to ensure that the product meets initial requirement. Validation Activities: We will present a system review with the customer to ensure that all of their needs are met. We will ensure that all technical specifications have been met, as well as being feasible for them to use.
  • 26. Implementation& ProjectClosurePlan: Conversion Strategy: Since the Martial Arts Academy is currently operating with its paper-based management system and due to the nature of the new computer-based system incorporating StudioCloud, Gold Team II has decided to use the parallel implementation approach for the following reasons:  It will provide a steady process for the employees to become familiar with the new system.  Can easily function side-by-side with the current paper system.  Provides a safety net if the system encounters any problems. · Gold Team II will not be using the direct cutover implementation approach for the following reasons:  It will place unneeded stress on the employees of the Martial Arts Academy because they are not familiar with the new system.  It would be risky if there was a hidden bug in the system that would cause it to break after implementation, thus halting/delaying the Martial Arts Academy from performing its day to day operations.  Puts stress under the project team to meet implementation deadlines. · Gold Team II will not be using the phased implementation approach for the following reasons:  Contains unnecessary costs and takes longer for the system to be implemented.  Does not account for the employees that may be having trouble becoming familiar with the new system.  Problems encountered in the early phases can impact the overall implementation schedule. · Closure Checklist: 1) Gold Team II will begin the closure procedure by ensuring that all deliverables are completed and meet the stakeholder’s requirements. 2) Gold Team II will archive all deliverables and documentation related to the project and store them in an organized fashion. 3) Meet with the stakeholders to have a final validation of the project. 4) Gold team II will invoice the sponsor company for the hardware required to complete the project. Gold Team II will also provide an invoice to the sponsor for the fees associated with consulting. 5) Gold Team II will show MMA the new system and will be assisting in teaching the employees and owners the system. 6) Provide the company an executive summary on the final project. 7) Once the implementation of the project is done then the computer technician will continuously maintain the system.
  • 27. 8) Coordinate between all Gold Team II members and MMA staff for a brief cocktail party, celebrating the successful completion of the project. Project Evaluation: Individual Performance Review: The project manager will hold individual performance reviews for each of the team members in Gold Team II. These reviews will include measuring each individual based on: · Having the team member review themselves first, then moving on to the manager’s review of the team member · Team members’ general performance throughout the project · Behavioral characteristics both individually and towards the team · Team members’ best contribution to the project · Recommendations and constructive criticism on how they can improve their performance on the next project Postmortem Review: After the project has been completed and implemented into the Martial Arts Academy, Gold Team II will hold a meeting led by the project manager to evaluate the project as a whole. The postmortem review will consist of these objectives: · Review the project’s MOV and evaluate its success · Review of the scope, schedule, budget, and quality objectives · Review each of the project’s deliverables such as the risk management plan to see what can be improved on in the future · Review overall team performance Project Audit: In conjunction with the postmortem review amongst Gold Team II, an outside perspective from an auditor that is unrelated to the Martial Arts Academy will be utilized to uncover any problems or opportunities for improvement that Gold Team II may have missed. The auditor in question will be someone who does not have a personal stake in the project, who will act in the Martial Arts Academy’s best interest, and who will have a base of industry experience so they can provide a valid review of the project and its team. The review from the auditor will function very similarly to the postmortem review and consist of these objectives: · Review the project’s MOV · Review how well the project was managed and executed · Review the project plans, processes, and project methodologies used throughout the project · Assess whether the project manager and team operated in a professional and ethical manner.
  • 28. Evaluating Project Success – The MOV: The MOV that was defined at the beginning of the project will be able to provide results at 1 month, 6 months, and 1 year after the system is implemented into the Martial Arts Academy. After 1 month, the new computer-based StudioCloud system will be implemented and the launch of the Academy’s new social media campaign can begin to attract new customers. Through the social media campaign and the streamlined experience for the customers due to the new computer-based management system, good word of mouth will proceed to attract additional people to become new customers of the Martial Arts Academy. The amount of new customers for the Academy will be able to be measured after 6 months. Finally, whether or not a return on investment was achieved for contracting a team to create and implement a new system will be measurable 1 year after the system’s implementation. Once the project is completed, Gold Team II will meet with Geoff and Julie, two of the stakeholders for the project, where they will determine whether the completed project meets their specific requirements and if they believe it will meet their customer’s needs. Change Management Plan: List of Change Sponsor(s), Target(s), and Agent(s) of Change: Sponsors of change: Geoff and Julie (Owners of MAA), Cersei Lannister’s co-workers at MAA, Tyrion Lannister’s co-workers at MAA, Gold Team II and its manager Targets of change: Cersei and Tyrion Agents of change: Co-workers of Cersei and Tyrion Change Assessment: Assessing the two employee’s willingness, readiness, and ability to change Cersei:  Sponsor: Cersei’s boss is who will be able to authorize the changes to the project. The boss will provide guidance about learning how to use the new system. This will help her overcome any fear she had about the implementation of the new system.  Change Agent: The sponsor that will assist Cersei (her other co-workers) will help her overcome her fear of learning the new system. She will be taught the new system by someone she trusts and who knows the new system well. This will make her more comfortable using the new system at her workstation. Tyrion:  Sponsor: Tyrion’s sponsor will be his bosses. They have the authority to instruct Tyrion to do what is expected of him for his job and to decrease any slack in his activities. The sponsor also has the authority to terminate or put him on probation if he is violating the code of ethics, procedures or rules of the Academy.  Change Agent: The change agent will consist of a group of Tyrion’s co-workers. They will assist in enabling to warn him whenever he is violating any rules. They will help him realize he is on probation from work and his time should be spent learning the new system. That will help him once he will rejoin the workforce.
  • 29. Change Strategy: Cersei: Rational-Empirical Approach:  Convince, explain, and demonstrate how a particular change will benefit the target of change.  Provide consistent and timely information to prevent any misinformation from being spread.  Be honest with everybody and stress that there is no news so that rumors will not spread throughout the organization. Tyrion: Normative-Re-education Approach:  The changes will appeal to the social norms of the individuals affected by it.  Give examples of the new system assisting the users. Compare the new system with the old to show the improvements.  A slow change that will affect the culture which will dictate the social norms of the company. Process for tracking change management plan: Keep an open line of communication between change sponsors and the targets of change. Additionally, if the employees are open to it, monitor social media to see what they think about the new system. For a face-to-face approach to communicating, the change sponsors and the owners of MAA could individual meetings so that they may voice their concerns or criticisms about the new system.Training programs will be in the next phase. A training program outline will be given to each employee to reference. Once the final examination of the project is finished the training program will be developed, test and then approved. The implementation will to train and test hardware. Every task has a set date that will serve as deliverable for the project.