$35,000
PC & Tablets: $9,096
Training & Monthly
fees: $57,164
Total: $66,260
PC & Tablets: $28,000
Training & Monthly
fees: $2,500
Developer: $70,000
Total: $100,500
Time to Implement
Immediate
6 months
12 months
Flexibility
None
Limited
High
Customization
None
Limited
High
Future Growth
None
Limited
High
Risk
None
Medium
High
Recommendation:
Based on the
This Project Charter was designed to combine all the previous team assignments in the course into one professional looking document. This assignment is the major artifact from the course that includes all the content coverage that was presented throughout the semester.
The Business Logistics Intelligence Systems (B.L.I.S.) project team presented a risk management plan for developing an Angel Pilots Program application. The application will automate the process of connecting patients with medical transportation needs to volunteer pilots. The plan outlines the project scope, schedule, budget, resources, risks and risk mitigation strategies. Key dates include a September 1st start and December 24th end date. The budget totals $45,000. The team identifies risks such as changes to scope, schedule and budget and strategies to address them like using contingency funds or carefully planning a data migration.
This is a project charter that I created in INFO 461 course at VCU. The project is to build an information system for the fictitious company Husky Air Pilot-Angels.
This document outlines a proposal for a new database system for Husky Air, a non-profit organization that uses volunteer pilots to transport patients. The goals of the new system are to reduce costs, decrease travel times for patients, and improve processes. Three alternatives are considered: maintaining the current manual system, purchasing a commercial software package, or developing a custom system. A cost-benefit analysis is provided showing that a custom system would provide the most benefits. The project is estimated to take two months to develop the database and implement the new system network-wide. The database aims to improve efficiency, increase the organization's size over three years, and achieve full customer satisfaction.
The document provides details about the Pilot Angels App project for Husky Air. It summarizes the current paper-based system and need for a new computer-based system. It then outlines the work completed so far, including creating a team charter, business case, project infrastructure plan, scope management plan, project plan/schedule/budget, risk management plan, and earned value/quality management plan. While good progress has been made, more work remains, such as stakeholder interviews, modeling, design, building, testing, training, and evaluation. Enhancements like video calling and artificial intelligence are recommended after a successful 6-month pilot period. The team charter establishes roles, responsibilities, communication guidelines, and expectations for team members
The team analyzed three options for Husky Air's new database system: maintaining the status quo, purchasing a software package, or building a custom system. They recommended building a custom system to give Husky Air the best benefits. A custom system would contain only necessary features, reducing training time and allowing more accurate and efficient work. While having a higher upfront cost than maintaining the current system, a custom system was estimated to have noticeably lower long-term costs than the other options. The team concluded the benefits of a custom system outweighed the costs in helping Husky Air meet patient and volunteer needs.
INFO 461 AS08 Project Charter, Implementation Strategy Plan & Change Manageme...Wesley Brown
The team proposes implementing the StudioCloud software and increasing MAA's social media presence to improve its student management system. StudioCloud is a free cloud-based software that provides features like client management and scheduling. The team estimates this will cost $6,679 initially for hardware and $1,859.88 annually for software subscriptions and WiFi. They expect the new system to be implemented within 1 month and increase new customers by 15% within 2 months. Resources needed include a project manager, technician, administrator, and business analyst. The team recommends StudioCloud and social media as an inexpensive and easy-to-use solution that meets MAA's goals.
This Project Charter was designed to combine all the previous team assignments in the course into one professional looking document. This assignment is the major artifact from the course that includes all the content coverage that was presented throughout the semester.
The Business Logistics Intelligence Systems (B.L.I.S.) project team presented a risk management plan for developing an Angel Pilots Program application. The application will automate the process of connecting patients with medical transportation needs to volunteer pilots. The plan outlines the project scope, schedule, budget, resources, risks and risk mitigation strategies. Key dates include a September 1st start and December 24th end date. The budget totals $45,000. The team identifies risks such as changes to scope, schedule and budget and strategies to address them like using contingency funds or carefully planning a data migration.
This is a project charter that I created in INFO 461 course at VCU. The project is to build an information system for the fictitious company Husky Air Pilot-Angels.
This document outlines a proposal for a new database system for Husky Air, a non-profit organization that uses volunteer pilots to transport patients. The goals of the new system are to reduce costs, decrease travel times for patients, and improve processes. Three alternatives are considered: maintaining the current manual system, purchasing a commercial software package, or developing a custom system. A cost-benefit analysis is provided showing that a custom system would provide the most benefits. The project is estimated to take two months to develop the database and implement the new system network-wide. The database aims to improve efficiency, increase the organization's size over three years, and achieve full customer satisfaction.
The document provides details about the Pilot Angels App project for Husky Air. It summarizes the current paper-based system and need for a new computer-based system. It then outlines the work completed so far, including creating a team charter, business case, project infrastructure plan, scope management plan, project plan/schedule/budget, risk management plan, and earned value/quality management plan. While good progress has been made, more work remains, such as stakeholder interviews, modeling, design, building, testing, training, and evaluation. Enhancements like video calling and artificial intelligence are recommended after a successful 6-month pilot period. The team charter establishes roles, responsibilities, communication guidelines, and expectations for team members
The team analyzed three options for Husky Air's new database system: maintaining the status quo, purchasing a software package, or building a custom system. They recommended building a custom system to give Husky Air the best benefits. A custom system would contain only necessary features, reducing training time and allowing more accurate and efficient work. While having a higher upfront cost than maintaining the current system, a custom system was estimated to have noticeably lower long-term costs than the other options. The team concluded the benefits of a custom system outweighed the costs in helping Husky Air meet patient and volunteer needs.
INFO 461 AS08 Project Charter, Implementation Strategy Plan & Change Manageme...Wesley Brown
The team proposes implementing the StudioCloud software and increasing MAA's social media presence to improve its student management system. StudioCloud is a free cloud-based software that provides features like client management and scheduling. The team estimates this will cost $6,679 initially for hardware and $1,859.88 annually for software subscriptions and WiFi. They expect the new system to be implemented within 1 month and increase new customers by 15% within 2 months. Resources needed include a project manager, technician, administrator, and business analyst. The team recommends StudioCloud and social media as an inexpensive and easy-to-use solution that meets MAA's goals.
The document is a project charter for a scheduling system project for Husky Air Pilot Angels. It includes an executive summary, description of the original case study, team charter, business case, infrastructure requirements, scope management report, project plan and schedule, risk management plan, and earned value and quality management plan. The project aims to develop a computer-based system to track Pilot Angels volunteers and flights to help match volunteers and planes to medical transport requests more efficiently. The team charter establishes expectations for team communication, meetings, roles and responsibilities.
This project aims to improve the martial arts academy's paper-based management system by implementing a new digital system. A team analyzed the academy's needs and proposed using free StudioCloud software, along with expanding their social media presence. This is expected to streamline operations, increase customer satisfaction by 15%, and bring in new customers through positive word-of-mouth within 6 months. The team created a plan outlining required resources like hardware, software, personnel and their estimated costs to successfully implement the new system.
The team charter establishes CGR IT Consulting Partners to complete the INFO 461 course project over 5 weeks. Team members are Charles Harrill, Gregory Eskridge, and Ruxandra Zait. Charles will initially lead but leadership will rotate. Strengths include Microsoft Project/Visio skills and academic achievement. Challenges are scheduling face-to-face meetings but they will use online tools. Roles include Charles integrating submissions, Gregory creating Project artifacts and presentations, and Ruxandra creating Visio diagrams and ensuring quality. They will collaborate and adjust roles based on assignment scope.
Systems Analysis and Design | Final Project Amber Raiford
The document analyzes and designs an inventory system for the Office of Information Technology at Winston-Salem State University. It finds that the current WASP Labeler system is outdated and recommends replacing it with the KACE System Management inventory system already in use by the university. A full analysis is provided of the organizational background, current system limitations, proposed KACE system benefits including improved access, reporting, and network security. Diagrams illustrate the current and proposed systems. The conclusion is that upgrading to KACE is feasible and will improve functionality with little cost or user impact.
The document outlines a project charter for an IT project proposed for Husky Air and their Pilot Angels program. The project aims to develop a computerized system to more efficiently track volunteer pilots, aircraft information, passenger data, and flight details, replacing their current manual paper-based system. The project charter includes a team charter, project description, measurable organizational value analysis, comparison of alternatives, and work plans. The goal of the new system is to reduce data processing time by 60% to allow resources to be reallocated for more strategic uses and improve customer service.
construction of Reservation software solution for Airline Companies project ...Hagi Sahib
The document describes a project to develop an airline reservation system (ARS) with three main goals:
1) Build an application to manage airline ticket reservations for passengers, travel agents, and airlines.
2) Interface the system with airline ticketing staff to search flights and make reservations for passengers.
3) Allow airline managers to maintain flight schedules, change fares and times, and add/remove flights and users.
Software Project Management: Project SummaryMinhas Kamal
Software Project Management: ResearchColab- Project Summary (Document-13)
Presented in 4th year of Bachelor of Science in Software Engineering (BSSE) course at Institute of Information Technology, University of Dhaka (IIT, DU).
The project charter outlines a plan to develop a structured onboarding system for new employees at Oregon Institute of Technology. The current onboarding process was paper-based with no formal orientation. The goals of the project are to create an online onboarding system with resources, videos, and forms to help new hires better integrate and acclimate to the university. Research including employee interviews will inform the design of the new system. It will be implemented in Spring 2017 and evaluated through employee surveys to measure the success of the project in helping new employees understand Oregon Tech's culture.
This company presentation provides an overview of Dropbox's business, products, growth strategies, and financial highlights. It notes that Dropbox has over 700 million registered users and 17.55 million paying users. The presentation outlines Dropbox's portfolio of individual and team products, its efficient go-to-market strategy focused on conversion and expansion, and new product experiences in development like Replay and Shop. Dropbox's financial strategy aims for long-term non-GAAP operating margins of 30-32% and over $1 billion in annual free cash flow by 2024. Key metrics show continued growth in revenue, paid users, and average revenue per user.
Offshore development center (odc) setup up by faichi solutions - Case StudyFaichi Solutions
Faichi Solutions proposes setting up an offshore development center (ODC) in India for a California-based client that develops interactive whiteboard technology. The client faces challenges around team expansion, engagement models, and technical expertise. Faichi recommends a cost-plus ODC model where the client has full control and flexibility over hiring, resources, culture and more. This model provides transparency into costs with no hidden fees. The outcome was a cohesive team using Agile methods to develop modules aligned with the client's business needs.
The document introduces an online admission system called "Online Admission System" developed by a team called "Dream Team". It discusses how the current manual admission process is time-consuming and effortful. The goal of the online system is to automate the admission process and make it faster and more transparent. It has three main modules for administrators, students, and the system. Administrators can manage admission criteria, verify forms, and generate merit lists. Students can fill forms, upload documents, and check results. The system compares marks and generates reports.
This document discusses evaluating and selecting a new student management system for Atonement Lutheran School. The school currently uses two systems - Edline for grades and communications, and Rediker for attendance and lunch counts. This causes redundancy and inefficiencies. The project aims to select a single, comprehensive system through a four-phase methodology: 1) Planning, 2) Analysis, 3) Design, and 4) Implementation. In the planning phase, requirements and selection criteria are identified. Potential vendors are then analyzed and one is selected. The new system aims to improve accuracy, safety, parental involvement, and use of data to support decision-making. Implementation will include training and developing consistent processes to maximize benefits and eliminate wasted time.
Taxi Booking System UML - Sequence DiagramTyler Mooney
The document describes two interactions between a customer, taxi booking system, car, driver, and booking. The first interaction shows a customer calling the taxi booking system to request a ride when there are less than 6 cars available. The system then checks a car, creates a booking, gets the first free driver, and assigns the driver to the car before storing and confirming the booking. The second interaction checks for a car with at least 4 seats if the time is 1:00pm and less than 10 bookings have been made, and then performs similar steps of checking, booking, storing, and confirming.
The Fruit Bazaar System allows users, administrators, and shipping agents to interact. Users can log in, add items to their cart, and check out to place orders. Administrators can log in with privileges to modify the catalog, maintain user data, and process orders. Shipping agents deliver ordered items from the warehouse to customers.
This document summarizes a school management system project submitted in partial fulfillment of a computer science degree. The project involved developing both a windows and web-based application to automate school management tasks like student registration, attendance tracking, report generation, and timetable production. The windows app handles offline registration and report generation while the web app allows teachers to record attendance and parents to view student status online. The system was designed to meet functional requirements like registration, attendance, reporting and timetabling as well as non-functional needs such as security, usability and performance. It was implemented using technologies like Java for the windows app and PHP for the web app, accessing a shared database.
This document describes Saraswati, a cloud-based education management system that aims to help educational institutions better manage administrative processes, reduce costs, and enhance the learning experience. Saraswati provides a unified platform for student learning, assessment, attendance tracking, fee collection, grade management, and communication between students, teachers, parents and management. It seeks to address challenges faced by educational institutions around high operating costs, limited funding opportunities, and maintaining quality of education through an integrated, automated system.
This document provides an overview and analysis of FedEx Corporation, including its mission, vision, strategies, financial performance, and corporate social responsibility initiatives. It analyzes FedEx's business segments, objectives to achieve 10% operating margin and increase earnings per share by 10-15% annually. The document also summarizes FedEx's strategies to grow its core business, expand internationally, strengthen its supply chain, and leverage e-commerce and technology.
The document describes an employee management system developed for GEA Process Engineering (India) Private Limited. It includes sections on the existing system, requirements for a new system, hardware and software needs, project management, system users, analysis, design, implementation, testing, screenshots and future enhancements. The system allows administrators to add, edit and verify employee information, line managers to access reports on their department employees, and employees to access their own details. It aims to reduce workload and improve information management over the previous system.
The WHIS team will develop an information system for Husky Air and its Pilot Angels program to more efficiently track volunteer pilots and their aircraft, as well as requests from hospitals, patients, and organ banks. This will replace Husky Air's current paper-based filing system. The goals are to provide faster service, lower costs, and increase business productivity. Key measurable outcomes include a 10% increase in aviation-related profits for partner hospitals within a year and decreasing customer wait and communication times by 80%. The system aims to benefit customers through increased convenience and hospitals through reduced costs and improved historic records.
The document is a project charter for a scheduling system project for Husky Air Pilot Angels. It includes an executive summary, description of the original case study, team charter, business case, infrastructure requirements, scope management report, project plan and schedule, risk management plan, and earned value and quality management plan. The project aims to develop a computer-based system to track Pilot Angels volunteers and flights to help match volunteers and planes to medical transport requests more efficiently. The team charter establishes expectations for team communication, meetings, roles and responsibilities.
This project aims to improve the martial arts academy's paper-based management system by implementing a new digital system. A team analyzed the academy's needs and proposed using free StudioCloud software, along with expanding their social media presence. This is expected to streamline operations, increase customer satisfaction by 15%, and bring in new customers through positive word-of-mouth within 6 months. The team created a plan outlining required resources like hardware, software, personnel and their estimated costs to successfully implement the new system.
The team charter establishes CGR IT Consulting Partners to complete the INFO 461 course project over 5 weeks. Team members are Charles Harrill, Gregory Eskridge, and Ruxandra Zait. Charles will initially lead but leadership will rotate. Strengths include Microsoft Project/Visio skills and academic achievement. Challenges are scheduling face-to-face meetings but they will use online tools. Roles include Charles integrating submissions, Gregory creating Project artifacts and presentations, and Ruxandra creating Visio diagrams and ensuring quality. They will collaborate and adjust roles based on assignment scope.
Systems Analysis and Design | Final Project Amber Raiford
The document analyzes and designs an inventory system for the Office of Information Technology at Winston-Salem State University. It finds that the current WASP Labeler system is outdated and recommends replacing it with the KACE System Management inventory system already in use by the university. A full analysis is provided of the organizational background, current system limitations, proposed KACE system benefits including improved access, reporting, and network security. Diagrams illustrate the current and proposed systems. The conclusion is that upgrading to KACE is feasible and will improve functionality with little cost or user impact.
The document outlines a project charter for an IT project proposed for Husky Air and their Pilot Angels program. The project aims to develop a computerized system to more efficiently track volunteer pilots, aircraft information, passenger data, and flight details, replacing their current manual paper-based system. The project charter includes a team charter, project description, measurable organizational value analysis, comparison of alternatives, and work plans. The goal of the new system is to reduce data processing time by 60% to allow resources to be reallocated for more strategic uses and improve customer service.
construction of Reservation software solution for Airline Companies project ...Hagi Sahib
The document describes a project to develop an airline reservation system (ARS) with three main goals:
1) Build an application to manage airline ticket reservations for passengers, travel agents, and airlines.
2) Interface the system with airline ticketing staff to search flights and make reservations for passengers.
3) Allow airline managers to maintain flight schedules, change fares and times, and add/remove flights and users.
Software Project Management: Project SummaryMinhas Kamal
Software Project Management: ResearchColab- Project Summary (Document-13)
Presented in 4th year of Bachelor of Science in Software Engineering (BSSE) course at Institute of Information Technology, University of Dhaka (IIT, DU).
The project charter outlines a plan to develop a structured onboarding system for new employees at Oregon Institute of Technology. The current onboarding process was paper-based with no formal orientation. The goals of the project are to create an online onboarding system with resources, videos, and forms to help new hires better integrate and acclimate to the university. Research including employee interviews will inform the design of the new system. It will be implemented in Spring 2017 and evaluated through employee surveys to measure the success of the project in helping new employees understand Oregon Tech's culture.
This company presentation provides an overview of Dropbox's business, products, growth strategies, and financial highlights. It notes that Dropbox has over 700 million registered users and 17.55 million paying users. The presentation outlines Dropbox's portfolio of individual and team products, its efficient go-to-market strategy focused on conversion and expansion, and new product experiences in development like Replay and Shop. Dropbox's financial strategy aims for long-term non-GAAP operating margins of 30-32% and over $1 billion in annual free cash flow by 2024. Key metrics show continued growth in revenue, paid users, and average revenue per user.
Offshore development center (odc) setup up by faichi solutions - Case StudyFaichi Solutions
Faichi Solutions proposes setting up an offshore development center (ODC) in India for a California-based client that develops interactive whiteboard technology. The client faces challenges around team expansion, engagement models, and technical expertise. Faichi recommends a cost-plus ODC model where the client has full control and flexibility over hiring, resources, culture and more. This model provides transparency into costs with no hidden fees. The outcome was a cohesive team using Agile methods to develop modules aligned with the client's business needs.
The document introduces an online admission system called "Online Admission System" developed by a team called "Dream Team". It discusses how the current manual admission process is time-consuming and effortful. The goal of the online system is to automate the admission process and make it faster and more transparent. It has three main modules for administrators, students, and the system. Administrators can manage admission criteria, verify forms, and generate merit lists. Students can fill forms, upload documents, and check results. The system compares marks and generates reports.
This document discusses evaluating and selecting a new student management system for Atonement Lutheran School. The school currently uses two systems - Edline for grades and communications, and Rediker for attendance and lunch counts. This causes redundancy and inefficiencies. The project aims to select a single, comprehensive system through a four-phase methodology: 1) Planning, 2) Analysis, 3) Design, and 4) Implementation. In the planning phase, requirements and selection criteria are identified. Potential vendors are then analyzed and one is selected. The new system aims to improve accuracy, safety, parental involvement, and use of data to support decision-making. Implementation will include training and developing consistent processes to maximize benefits and eliminate wasted time.
Taxi Booking System UML - Sequence DiagramTyler Mooney
The document describes two interactions between a customer, taxi booking system, car, driver, and booking. The first interaction shows a customer calling the taxi booking system to request a ride when there are less than 6 cars available. The system then checks a car, creates a booking, gets the first free driver, and assigns the driver to the car before storing and confirming the booking. The second interaction checks for a car with at least 4 seats if the time is 1:00pm and less than 10 bookings have been made, and then performs similar steps of checking, booking, storing, and confirming.
The Fruit Bazaar System allows users, administrators, and shipping agents to interact. Users can log in, add items to their cart, and check out to place orders. Administrators can log in with privileges to modify the catalog, maintain user data, and process orders. Shipping agents deliver ordered items from the warehouse to customers.
This document summarizes a school management system project submitted in partial fulfillment of a computer science degree. The project involved developing both a windows and web-based application to automate school management tasks like student registration, attendance tracking, report generation, and timetable production. The windows app handles offline registration and report generation while the web app allows teachers to record attendance and parents to view student status online. The system was designed to meet functional requirements like registration, attendance, reporting and timetabling as well as non-functional needs such as security, usability and performance. It was implemented using technologies like Java for the windows app and PHP for the web app, accessing a shared database.
This document describes Saraswati, a cloud-based education management system that aims to help educational institutions better manage administrative processes, reduce costs, and enhance the learning experience. Saraswati provides a unified platform for student learning, assessment, attendance tracking, fee collection, grade management, and communication between students, teachers, parents and management. It seeks to address challenges faced by educational institutions around high operating costs, limited funding opportunities, and maintaining quality of education through an integrated, automated system.
This document provides an overview and analysis of FedEx Corporation, including its mission, vision, strategies, financial performance, and corporate social responsibility initiatives. It analyzes FedEx's business segments, objectives to achieve 10% operating margin and increase earnings per share by 10-15% annually. The document also summarizes FedEx's strategies to grow its core business, expand internationally, strengthen its supply chain, and leverage e-commerce and technology.
The document describes an employee management system developed for GEA Process Engineering (India) Private Limited. It includes sections on the existing system, requirements for a new system, hardware and software needs, project management, system users, analysis, design, implementation, testing, screenshots and future enhancements. The system allows administrators to add, edit and verify employee information, line managers to access reports on their department employees, and employees to access their own details. It aims to reduce workload and improve information management over the previous system.
The WHIS team will develop an information system for Husky Air and its Pilot Angels program to more efficiently track volunteer pilots and their aircraft, as well as requests from hospitals, patients, and organ banks. This will replace Husky Air's current paper-based filing system. The goals are to provide faster service, lower costs, and increase business productivity. Key measurable outcomes include a 10% increase in aviation-related profits for partner hospitals within a year and decreasing customer wait and communication times by 80%. The system aims to benefit customers through increased convenience and hospitals through reduced costs and improved historic records.
Drawing And Writing Paper. Online assignment writing service.Nicole Savoie
The document outlines a 5-step process for requesting and receiving writing assistance from HelpWriting.net:
1. Create an account with a password and email.
2. Complete a 10-minute order form providing instructions, sources, deadline, and sample work.
3. Review bids from writers and choose one based on qualifications.
4. Receive the paper and authorize payment if satisfied. Revisions are free.
5. Request multiple revisions to ensure satisfaction. Plagiarized work results in a full refund.
Smartronix is an information technology company headquartered in Hollywood, Maryland that provides cybersecurity, software development, health IT, and other services. It has over 550 employees worldwide and achieves 20% annual growth. The company has a strong corporate culture that values work-life balance and benefits employees with competitive compensation and other perks. Smartronix invites qualified candidates to apply for current job openings on its website.
abillionofus.org - Initial Business PlanDouglas Maske
This business plan proposes a social networking platform and medical resource locator for people with disabilities, their families, and supporting professionals. Key points:
- The platform will allow users to connect with others sharing their diagnosis/condition and find relevant information and resources.
- It will be free for users but may later charge medical professionals for research access.
- The founders will seek investment to fund development and marketing.
- Financial projections estimate an initial loss followed by profitability in years 2-3 as sales double or triple annually through growth strategies like partnerships and advertising.
Peesh Chopra and his career spanning two decades where he has ventured into building enterprises from scratch and has become a venture capitalist. Peesh Chopra is providing mentorship and funding to help budding entrepreneurs with disruptive ideas start and grow a business confidently.
7Th Grade Essay Outline Template. 7Th Grade OutliniAna Morgan
The document provides considerations for designing an outdoor kitchen, including choosing durable materials that can withstand weather elements. Key factors include selecting appliances suited for outdoor use, such as a grill or stove. Counter space, storage, and a sink are also important. Location should allow for accessibility and views while taking wind direction into account. Electrical and plumbing need to be installed to code by licensed professionals. Budgeting adequately for quality materials and installation is advised to ensure a functional outdoor kitchen area.
The document outlines 8 strategies, called REACH-OUT, for educators to keep Generation Y (Gen Y) safe online based on how firefighters keep the public safe from fires. The strategies are: 1) Reach out to understand Gen Y's online challenges; 2) Evoke rules of acceptable online behavior; 3) Assess common cyber threats; 4) Raise awareness of threats through student campaigns; 5) Incentivize positive online behavior; 6) Provide enriching alternative activities; 7) Utilize community resources to support cyber safety; and 8) Use technology to monitor misuse and mitigate threats. The goal is to proactively identify, address, and respond to cyber threats through a combination of social and technological approaches
The ITE Student Chapter at Florida International University had an active year in 2013-2014. They hosted 16 guest speakers from academia and industry, including the Director of the Georgia Transportation Institute. Twenty-five members attended the Transportation Research Board annual meeting in Washington D.C. The chapter organized technical field trips and won a competitive proposal to assist with transportation data collection. They also helped establish a Women's Transportation Seminar student chapter at FIU.
Having Trouble Writing College Essay. How To Write An Exemplification ...Rebecca Bordes
The document provides instructions for how to request and complete an assignment writing request through the HelpWriting.net website. It outlines a 5-step process: 1) Create an account; 2) Complete an order form with instructions and deadline; 3) Review bids from writers and select one; 4) Receive the completed paper; 5) Request revisions if needed and authorize payment upon satisfaction. The process aims to match students with qualified writers to help complete assignments while allowing for revisions until the student is fully satisfied with the end product.
The project team has created a charter and laid the foundation for developing an information system for Husky Air's Pilot Angels program. Key deliverables created include a team charter establishing roles and communication protocols, a business case analyzing feasibility and costs/benefits, and a project plan defining scope, schedule, budget, and risks. Moving forward, the team needs to develop a prototype interface, create an implementation plan, conduct testing, and oversee system deployment before evaluating project outcomes and ongoing maintenance needs.
Fortune Teller Paper Game Activity ShelterKate Campbell
The document provides instructions for requesting writing assistance from HelpWriting.net. It outlines a 5 step process:
1. Create an account with a password and email.
2. Complete a 10-minute order form with instructions, sources, deadline and sample work.
3. Choose a writer bid based on qualifications, history and feedback then pay a deposit.
4. Review the completed paper and authorize full payment if satisfied, with free revisions available.
5. Request multiple revisions to ensure satisfaction, with a refund if work is plagiarized.
Valerie I. Trank-Jenny has over 14 years of experience in agency operations and sales. She is currently a Personal & Commercial Lines Producer and CSR at Trank & Associates Agency Inc., where she has helped grow the commercial book over 200% while maintaining a low loss ratio. She is seeking new career opportunities that allow her to utilize her social skills and education. She has multiple insurance licenses and designations, including INS, ACSR, AIS, and is working toward her CPCU designation. In her spare time she enjoys participating in a field hockey league and riding motorcycles with her husband.
The document provides an overview of news and events from the Hinds County Career and Technical Center. It discusses accomplishments and activities in various technical programs such as engineering, automotive technology, health science, and more. Upcoming events include fall leadership conferences, professional dress days, and guest speakers. Students are participating in skills competitions and student organizations like HOSA, DECA, and SkillsUSA. The counseling department provides academic support and assists with college and career planning.
This business plan outlines Fletch, a mobile app that aims to increase college retention rates. Fletch allows students to easily form study groups and get quick answers to questions from classmates. It collects user data to identify at-risk students and inform schools on engagement, collaboration, struggling topics, and more. The plan discusses Fletch's mission, management team, products, $150k startup budget, target markets, and SWOT analysis. It argues Fletch's retention algorithms, user-generated content, and status as a first-to-market product give it strengths over potential competitors.
Cyber Liability Insurance: An Essential and Urgently Needed Business InvestmentThomas LaPointe
The document discusses a cyber liability insurance webcast featuring several expert speakers. Tom Finan, a senior cybersecurity strategist with the Department of Homeland Security, will provide opening remarks on DHS's work related to cybersecurity insurance and risk management. Helen Christakos, a senior counsel specializing in intellectual property and data privacy, will then discuss assessing and mitigating cyber risks. Additional segments will focus on the cyber liability market, types of cyber insurance policies, and international vulnerability purchase programs. The goal is to explain why cyber liability insurance has become essential for businesses given increasing cyber attacks and regulation.
LEAP: Leadership Education and Advancement ProgramKate Zabriskie
The Leadership Education and Advancement Program (LEAP) is an exclusive offering designed for international groups seeking leadership skills training in the United States. This unique program combines classroom time with targeted site visits based on the participants’ interests and learning objectives. This document provides an overview of the program's content and costs.
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN CHART KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
KALYAN MATKA | MATKA RESULT | KALYAN MATKA TIPS | SATTA MATKA | MATKA.COM | MATKA PANA JODI TODAY | BATTA SATKA | MATKA PATTI JODI NUMBER | MATKA RESULTS | MATKA CHART | MATKA JODI | SATTA COM | FULL RATE GAME | MATKA GAME | MATKA WAPKA | ALL MATKA RESULT LIVE ONLINE | MATKA RESULT | KALYAN MATKA RESULT | DPBOSS MATKA 143 | MAIN MATKA
L'indice de performance des ports à conteneurs de l'année 2023SPATPortToamasina
Une évaluation comparable de la performance basée sur le temps d'escale des navires
L'objectif de l'ICPP est d'identifier les domaines d'amélioration qui peuvent en fin de compte bénéficier à toutes les parties concernées, des compagnies maritimes aux gouvernements nationaux en passant par les consommateurs. Il est conçu pour servir de point de référence aux principaux acteurs de l'économie mondiale, notamment les autorités et les opérateurs portuaires, les gouvernements nationaux, les organisations supranationales, les agences de développement, les divers intérêts maritimes et d'autres acteurs publics et privés du commerce, de la logistique et des services de la chaîne d'approvisionnement.
Le développement de l'ICPP repose sur le temps total passé par les porte-conteneurs dans les ports, de la manière expliquée dans les sections suivantes du rapport, et comme dans les itérations précédentes de l'ICPP. Cette quatrième itération utilise des données pour l'année civile complète 2023. Elle poursuit le changement introduit l'année dernière en n'incluant que les ports qui ont eu un minimum de 24 escales valides au cours de la période de 12 mois de l'étude. Le nombre de ports inclus dans l'ICPP 2023 est de 405.
Comme dans les éditions précédentes de l'ICPP, la production du classement fait appel à deux approches méthodologiques différentes : une approche administrative, ou technique, une méthodologie pragmatique reflétant les connaissances et le jugement des experts ; et une approche statistique, utilisant l'analyse factorielle (AF), ou plus précisément la factorisation matricielle. L'utilisation de ces deux approches vise à garantir que le classement des performances des ports à conteneurs reflète le plus fidèlement possible les performances réelles des ports, tout en étant statistiquement robuste.
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN CHART KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART INDIA MATKA KALYAN SATTA MATKA 420 INDIAN MATKA SATTA KING MATKA FIX JODI FIX FIX FIX SATTA NAMBAR MATKA INDIA SATTA BATTA
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN CHART KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN CHART KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka KALYAN MATKA | MATKA RESULT | KALYAN MATKA TIPS | SATTA MATKA | MATKA.COM | MATKA PANA JODI TODAY | BATTA SATKA | MATKA PATTI JODI NUMBER | MATKA RESULTS | MATKA CHART | MATKA JODI | SATTA COM | FULL RATE GAME | MATKA GAME | MATKA WAPKA | ALL MATKA RESULT LIVE ONLINE | MATKA RESULT | KALYAN MATKA RESULT | DPBOSS MATKA 143 | MAIN MATKA
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...Adani case
It will bring about growth and development not only in Maharashtra but also in our country as a whole, which will experience prosperity. The project will also give the Adani Group an opportunity to rise above the controversies that have been ongoing since the Adani CBI Investigation.
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...Adani case
Time and again, the business group has taken up new business ventures, each of which has allowed it to expand its horizons further and reach new heights. Even amidst the Adani CBI Investigation, the firm has always focused on improving its cement business.
japanese language course in delhi near meheyfairies7
Next is the Nihon Language Academy in East Delhi, renowned for its comprehensive curriculum and interactive teaching methods. They boast a faculty of experienced educators with a blend of both Indian and Japanese nationals. The academy provides extensive support for JLPT exam preparation along with personalized tutoring sessions if needed. Nihon Language Academy also arranges exchange programs with partner institutes in Japan, which provides students an opportunity to experience Japanese culture and language first-hand.
Enhancing Adoption of AI in Agri-food: IntroductionCor Verdouw
Introduction to the Panel on: Pathways and Challenges: AI-Driven Technology in Agri-Food, AI4Food, University of Guelph
“Enhancing Adoption of AI in Agri-food: a Path Forward”, 18 June 2024
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN CHART KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART
1. Husky Air Pilot Angels
Ingrid Salgado
INFO 461-001
Information System Planning and Project Management
2. 1
Table of Contents
Project Description…………………………………………………………....2
Executive Summary…………………………………………………………...2
Original Case Study…………………………………………………………...3
Team Charter………………………………………………………………..4-5
Business Case………………………………………………………….........6-12
Project Infrastructure…………………………………………………........13-17
Scope Management Plan…………………………………………………...18-20
Work Breakdown Structure, Schedule and
Budget………………………………………………………………...…....21-30
Risk Management Plan…………………………………………………….31-43
Earned Value and Quality Management
Plan………………………………………………………………………...44-51
MS Project Tutorial I……………………………………………………...52-56
MS Project Tutorial II…………………………………………………….57-65
MS Project Tutorial III……………………………………………………66-74
3. 2
Project Description
The Husky Air Information System project has consisted of system planning and project
management framework. The project team has completed numerous tasks, starting off with a
team charter to establish and follow a basis of rules, responsibilities and expectations throughout
the project’s lifecycle. A Business Case was created which included the development of the
MOV, comparison of alternatives and recommendation based on those alternatives. A Project
Infrastructure was then developed which consists of the resources needed, costs estimate and
types of payment that the project would entail. Following this, is the Scope Management Plan,
which provides the Deliverable Structure Chart, Use Case Diagram, Work Breakdown Structure
and the Scope Change Process. Then, the Project Plan Schedule, and Budget was created to
provide a more detailed project plan and address the allocation of resources and costs that were
analyzed. After this, the Risk Management Plan was developed to provide insight on any risks
that could possibly occur throughout the project. Lastly, an Earned Value Analysis and Quality
Management Plan was created that provided testing by BugBusters company and the costs
associated with it. It also reported the metrics, verification and validation of quality management.
In conclusion, the project was created to serve as a support to the creation of the Husky Air
Information System.
Executive Summary
The Project Team has completed the framework for the creation of the Husky Air Information
System, although there is still much more to be accomplished before starting the implementation
process of the system. The team will need to design a user interface prototype to test the system
and develop an implementation plan to follow. Later, stakeholders will need to be trained and
the Project Manager and Husky Air President will need to sign off and approve the system. Once
approved and tested, the team will proceed to the implementation phase and evaluate the project
and its MOV. After the completion and success of the implementation of the system,
maintenance will take place within 6 months following its utilization.
4. 3
Original Case Study
Background
Husky Air opened for business in January 2008 when L.T. Scully and several other investors
pooled their life savings and secured a rather large loan from a Chicago bank. Located at DeKalb
Taylor Municipal Airport (DKB) in DeKalb, Illinois, Husky Air is a fixed base Operator (FBO)
facility that offers a full range of services to the growing demands for business and private
aviation. Currently, the company has 23 employees composed of pilots, mechanics, and office
staff.
As an FBO, Husky Air provides:
• Business jet, propjet, helicopter, and propeller aircraft charter
• Refueling
• Airframe, engine, propeller, and avionics maintenance
• Aircraft rental
• Flight instruction
• Pilot supplies
Although FOB’s at other airports offer similar services, Husky Air has been receiving increased
attention through the Midwest for it charters service, maintenance, flight instruction.
Pilot Angels
In addition, Husky Air coordinates a charitable service called Pilot Angels. Working with
hospitals, health care agencies, and organ banks, Husky Air matches volunteer private pilots,
willing to donate their time and aircraft, with needy people whose health care problems require
them to travel to receive diagnostic or treatment services. In addition, Pilot Angels also will
provide transportation for donor organs, supplies, and medical personnel. All flights are free of
charge and the costs are paid for by the volunteer pilots who use their own aircraft.
The pilots who volunteer for the Pilot Angel program need no medical training and offer no
medical assistance. The planes do not carry any medical equipment and do not have to
accommodate any stretchers. Patients, however, must be medically stable and able to enter and
exit the aircraft with no or little assistance. The Pilot Angel passengers typically travel to or from
a hospital or clinic for diagnosis, surgery, or some other treatment. Travel companions, such as a
relative, friend, or nurse, are common.
Currently, a pool of pilot volunteers is kept in a file folder. If a hospital or person with a medical
or financial hardship contacts Husky Air, the name of the traveler, the destination, dates/times,
and the number of travel companions are requested. Because of limited weight restrictions in
small aircraft, the weights of the passengers and their luggage are needed as well.
After the initial information is provided, Husky Air contacts the volunteer pilots to determine
their availability. Although a volunteer pilot may be willing and available for a Pilot Angel
flight, the plane may not have the range or weight-carrying requirements. This may be an
inefficient use of time since many pilots may have to be contacted until a pilot and suitable plane
can be found.
5. 4
Team Charter
Team Name: WMIS
Name Email Phone Number
Ingrid Salgado salgadois@vcu.edu 703-853-6460
Shaswat Khatiwada khatiwadas@vcu.edu 703-577-9407
William Harris harriswm2@vcu.edu 804-519-0438
Marquis Bryant bryantml@vcu.edu 757-927-7334
Team Mission Statement:
To create value and provide excellence in our Information Systems and services to support
instructional and administrative functions.
Team Core Value
Teamwork: We believe we can get anything done when we are working in a team, because of the
support and motivation we get from each other. Teamwork can be overwhelming which is why
we are going to divide the work between each other.
Respect: Listening and being considerate of others.
Courtesy: Considering how one's actions can affect other individuals.
Individual Team Member Overview:
Team
Member
Strengths *Hot Buttons*
Reactions
under stress
How you can help
me when my hot
buttons are
pushed
Shaswat
Khatiwada
Organizational skills,
teamwork, good with
PC’s
N/A N/A
Try working on the
project.
Ingrid
Salgado
Organized, collaborative,
good listener
Not putting in work, not
turning assignments on
time
stress out
Give me space, try
to work out
issue(s).
William
Harris
Friendly, courtesy,
outside of the box
thinking
Lack of communication Silence Relax
Marquis
Bryant
Problem solving,
teamwork, analyzation
skill, respectfulness
people not doing their
part, not turning work in
on time
stressed out
or silence
give me space or try
to fix the problem
6. 5
Biography:
Marquis Bryant: I am currently a senior at VCU. My major is information systems. I am scheduled to
graduate in December 2018. I am from Newport News, Virginia. Some of my hobbies are listening to
music, sometimes playing it, surfing the internet. I chose to be information systems major because I
have enjoyed using computer since I was little and over years I wanted to learn more about them. I have
already got my associates degree in information technology from Thomas Nelson. Which is the college
that transferred from before I got here last year. My plan once I graduate from VCU is the work in IT
industry for a private company or for the government.
William Harris: I am a fourth year Information Systems student at Virginia Commonwealth University. I
was born on a military base in Lawton Oklahoma until I was 4 years old. I moved to North Carolina and
eventually Virginia when I was 5. I have grown in central Virginia most of life and find it hard to imagine
leaving Richmond. In a year or so I plan to pursue my passion for IT and start a career in either Atlanta,
Georgia or Portland, Oregon. In my free time, I also enjoy being outdoors and doing things such as
camping hiking and fishing. In contrast, video games used to be a major part of my life but I try to stray
away from them more these days, considering that they arguably wasted some of the best years of my
life. It is a shame because gaming in my rural community was one of the first, and one of the few small
chances for me to get interested in technology at all to begin with.
Ingrid Salgado: I am a senior at Virginia Commonwealth University. I transferred to VCU from Northern
Virginia where I attended NOVA community college and received my Associate’s Degree in Information
Technology. I consider myself as outgoing, laid-back, detail-oriented and hardworking. Some of my
hobbies include listening to music, watching television and hanging out with friends. My anticipated
graduation date is for December 2018, and my plans after graduating consists of moving back to NOVA
and working in the IT Field for a high innovative company. Still considering to pursue my masters as well
but would like to start working in the IT field first to get the career experience.
Shaswat Khatiwada: I am a senior at Virginia commonwealth University. I also transferred from NOVA
where I received my Associate degree in Computer Science. I am also from NOVA (Northern Virginia). I
love lived there for more than 10 years. I am originally from Nepal. In my free times I like playing video
games, watch movies or sometimes just take a nap. I love traveling so, every opportunity I get I always
travel. At the end of the year I am planning to travel to the West coast.
7. 6
Business Case
Project Description:
The Husky Air are collaborated with Pilot Angels group both of whom transport patients and/or
other important things to hospitals in case of emergency. Our Information system will help track
all Pilot Angels, the plane they fly, their schedule, and availability for volunteering. The
Information system will include a database that will store the Pilots, their information such as;
phone number, names, experience in the field, trip details. The system is also created to track the
Planes information such as fuel cost, their life, maintenance, clients that flew using those planes,
where the plane is located. The Information system will allow the hospital and the clients locate
the plane and the pilot both for a faster and safe journey for their care, while improving
documentation and easy retriever of the information.
Project Value:
With the new Information System Husky Air will be able to shorten their interaction time
with the volunteer and provide a more accurate and reliable service to their customer with the
new computer-based systems for both the volunteers and clients.
Project Goals:
● Provide volunteer’s personal information and schedule
● Keep track of customer information and their requests
● Lower cost
● Increase business productivity
● Patients to be helped in a 24-hour timeframe
Measurable Organizational Value(MOV):
Desired Area of Impact:
Customers: We will target convenience and efficiency of the hospitals and patients who use the
Pilot Angles service by overhauling their current file record keeping system and replacing it with
a database of the volunteer pilots’ information.
Strategic: One prospect of implementing our information system would be to give Husky Air a
competitive edge in accessibility compared to alternative services. This would allow the patients
to receive medical attention more quickly and increase their overall satisfaction with the Pilot
Angles
Financial: Since the Pilot Angels are volunteers they will not receive much direct benefit from
our system, however, the hospital with likely be able to use reduced slack time to focus on other
business improvement objectives.
Operational: Currently medical services are already semi-effective with their current paper
record keeping system but there is still room for improvement. Our information system would
increase efficiency by making the records pertaining the volunteers more readily accessible in a
8. 7
database. This would include everything from weight restrictions to destinations’ dates and
times.
Social: From a customer standpoint our information system would improve their quality of life
increasing their access to medical attention. Part of the Pilot Angles availability information
would be made accessible to the public to lookup so that they could request medical attention at
their convenience. This information would be made publicly available with limited access to
those in need of medical attention.
Desired Value of the IT Project
Better? Husky Air Pilot Angels currently use and paper and pencil record keeping system. This
works but could be greatly improved with increased accessibility through the implementation of
a database system
Faster? Finding out the availability of a Pilot and their corresponding weight and capacity
restrictions can be a tedious time-consuming process especially with a hard copy file system. The
increased accessibility of a database would certainly decrease the amount of time that it takes to
link hospitals, pilots, and patients.
Cheaper? Our information system has the potential to arrange husky refueling and maintenance
process by recording the dates and assigning new ones in the future. It would also help keep
inventory records to reduce waste and ensure all materials are being used efficiently.
Do More? Husky Air would like to know more information about the pilots and customers that
use their services. Other information that they would like to keep records of includes pilots’
ratings/contributions, passengers on board flights, planes used, time of flights, distance, and total
fuel used. This information could help benefit hospital by helping reduce costs and also benefit
customers by increasing historic awareness.
Appropriate Metric
The goal implementing our information system with Husky Air is increase the customer
satisfaction and the profits of the medical facilities who use their service. For the hospitals we
hope to target a 10% increase in aviation related profits made from patient request fulfillment.
This increase should come from an influx of patients using the convenience of our information to
make more frequent appointments and will be measured one year after the system goes live. We
also hope to see a decrease in customer wait time and also decreasing transportation and
communication time by 80%
Time Frame for Achieving the MOV
For the Customer area of impact should be achieved in 6 to 12 months for customers to see the
faster service because the system will have to build it first and the volunteers will need time to be
familiar with the system.
9. 8
For the Strategic area of impact should be achieved in 12 to 18 months. Since the company will
need to develop the strategy for the company to follow the next 10 years with the new
information system.
Financial area of impact will take 2 months to see the monetary effects of switching from a paper
and pencil system to computer information system. The switch between systems should save
husky air pilots and hospital a lot of money when it comes to record keeping.
The operational area of impact should be achieved in 12 to 18 months to be improved by the new
system. Since the system will need to be developed and volunteer and hospital being trained with
the new system.
Social area of impact should be achieved in 6 months after system built. With the new
information system, husky air pilots can begin to interact more with the patients with information
being more accessible for them. They will also be able to match patients to volunteer based on
their specific needs.
Summary of the MOV - Areas of impact
Area of Impact Value Metric Time frame
Customers Faster service for
customers who need
immediate
transportation for
treatment
Increase customer
satisfaction with the
service husky air
pilot angels
provides.
Lowering customers
wait time.
Decreasing
transportation and
communication time
by 80%
6- 12 months
Strategic Better system for
managing the
available pool of
volunteer Pilots,
finding planes that
able to manage the
require weight for
transportation.
Faster system of
finding available
pilots for customer
20% Increase in
available volunteer
pilots
12- 18 months
10. 9
transportation.
Increase number of
available pilots for
medical
transportation for
customers and
medical requested
supplies or
personnel
Financial Reduce the amount
of money spent on
record keeping
system by using a
computer based-
system instead of
paper and pencil
system.
40% reduction in
cost for record
keeping
6 months
Operation Better record
keeping system for
medical services to
increase accessibility
for Husky air pilot
angels and the
hospitals.
Better record
keeping system for
planes and fuel
levels
45% reduction in
time-frame
turnaround and
accessibility to the
patients
6 to 12 months
Social Increase customer
access for medical
transportation.
Make information
more accessible for
patients and future
patient of Husky air
pilot.
60% increase in
customer access for
medical
transportation
40% increase in
patient severed per
day
6 months
11. 10
Comparison of Alternatives
ALTERNATIVES
OPTIONS: Maintain Status
Quo
Purchase a Software
Package
Build a Custom
System
Direct costs none PC & Tablets:
$9,096
PC & Tablets:
$28,000
Ongoing Support/
Maintenance Costs
Administrator
Assistant:
$35,000
Consultant &
administrator:
$25,000
Developer &
administrator:
$70,000
Indirect Costs none Training & Monthly
fees: $57,164
Training & Monthly
fees: $2,500
Total Cost of Ownership
Maintain Status
Quo
Purchase Software
Package
Build a Custom
System
Development Costs
Hardware $ 0 $ 7,595.99 $ 8,000
Software $ 0 $ 1,500.00 $ 20,000
Development $ 0 $ 0 $ 55,000
Employee Training $ 0 $ 5,000 $ 2,500
Operational Cost (After year 1)
Hardware Upgrade $ 0 $ 5,000 $ 5,000
Maintenance $ 35,000 $ 25,000 $ 5,000
Software Monthly $ 0 $ 52,164 $ 0
12. 11
Fee(189*12)*23(users)
Total Cost $ 35,000 $ 96,259.99 $ 95,500
Total Benefit of Ownership
1 - low
10 - high
Maintain Status
Quo
Purchasing Build a custom
system
Optional
Description
Paper and Pencil
system
Duoserve
Scheduflow System
W.M.I.S. Database
System
Accuracy Medium accuracy,
depending on the
skills of the admin
and any mistakes
being made.
2
High accuracy. Will
allow for customers
to receive correct
information about the
volunteers and vice
versa.
4
High accuracy, the
system is customized
to the exact need for
the business, and
because of both
customer and
administration
involvement in the
project the Accuracy
high.
10
Efficiency Low efficiency. Work
may take weeks to
complete.
2
High efficiency.
Customers and
employees of Husky
Air Pilot Angels will
input and retrieve
data quickly and easy.
5
Medium efficiency.
The system takes
about 5 months but
after the system is
built it will run 24/7
7
Lowered Expenses The project won’t add
any cost the existing
system other then the
salary for the Office
Administrator
7
Few expenses
including the
software purchase, a
monthly maintenance
and upgrades every
year.
2
The project is lower
than the purchased
system, the system
cost after the first
year is lower
5
13. 12
Customer
Satisfaction
Because of the low
efficiency and
accuracy, the
customer satisfaction
if lower for the
current system.
1
High customer
satisfaction. The
system will be
reliable and provide
data for every
customer, pilot,
airplane and
additional volunteers.
6
High customer
satisfaction.
Since the software
was created targeting
the current or any
future problem, with
the help of the
customers that are
using the current
systems, we are
providing everything
the customer is
requiring, have issue
and fixing the
problems
10
Total Benefit: 12 17 32
Recommendation
The W.M.I.S.Database System shows the best alternative for Husky Air-Pilot Angels to build
Husky Air their own system. There are multiple reasons that our information system will not
only improve Husky Air Pilot Angels but also provide top benefits to their customers. One
reason pertains to the measurable organizational value (MOV) that the system will provide. The
MOV provides a solid foundation and framework that guarantees the success of our IS. This
will be accomplished by targeting specific target areas that will be improved such as the social
and operational values of the company. Other existing alternatives do not provide the same
well-defined solution that our approach intends to accomplish. This can also be quantified by
the low cost of the custom system that will be related to Husky Air Pilot Angels wants and
needs. With the purchase of a few computers and tablets for the pilots, this will aid everyone to
keep track of their schedules and to receive and provide information to customers efficiently. It
will reduce time for the employees to get their work done in a productive, accurately and timely
manner along with ongoing support from the administrator and developers that will be at reach
at all times. Per the comparison chart, the benefits from building their own system will allow
Husky Air Pilot Angels and their customers to have a close relationship and improve customer
transportation and satisfaction.
14. 13
Project Infrastructure
Resources Required Table
People and their roles ● Sponsor - Will oversee the managers work and will be
providing the financial support for the project.
● Project Managers - Will lead all the team efforts and guide
other employees. They will be responsible for schedule,
budget and scope.
● Developers - Person that will create, update and maintain
the software for Husky air.
Technology ● Workstations: Two PC with 1 home server and Tablets.
● Software: Custom made software / Outlook or Gmail for
emails
● Industrial printer/ scanner
● Telephone for additional customer support.
● Wi-Fi- Router and internet service from Google Fiber
Facilities ● Office Administrator to look at day-to-day work.
● Outsourcing: Office cleaners.
Other ● Maintenance - The developer will be responsible to
maintain the system.
● Training and Implementation: Will be conducted by the
Project Manager to ensure the customer can control and
maintain the systems if needed.
Resource Cost Table:
Resource Cost Source
Project Managers $40,000 during project time-
frame
glassdoor.com
Developers $45,000 during project time-
frame
glassdoor.com
Office Administrator $35,000 during and after
project time-frame
glassdoor.com
15. 14
Technology: Hardware/ Software:
Resource Cost Source
Workstation: PC Dell Desktop Workstation for
$574 a piece
Samsung Tablets for $60 a piece
HPE ML10 GEN9 Server for
$489 a piece
Misc: $3413.01 for wires, Dell
monitors and so on.
www.newegg.com
Software Custom built WMIS.com
Printer and Scanner Kyocera M3540IDN Printer and
Scanner @ 1989.99
www.faxexpress.com
Router Google Fiber router for $70 /
month
www.fiber.google.com
Telephone Google phone www.voice.google.com
Facilities:
Resource Cost Source
Office custodian $200 a month The cost is from their current
custodian contractor.
16. 15
Other
Resource Cost Source
Training and implementation $50 a day for training glassdoor.com
Maintenance $10 per hour for IT support
and maintenance
glassdoor.com
Contract Payment Method
Our direct and indirect costs will be covered by the Cost-plus-fee (CPF) or cost-plus-percentage-
of-cost (CPPC) contract type. This will be a varying predetermined fixed amount based on the
cost resource table. These values will fluctuate as the costs of the project change over time. This
contract method will also cover future labor costs associated with software updates and
maintenance.
Learning Cycle
What we know (facts) What we think we know
(assumptions)
What we don’t know (question
to be answered)
The company needs more
efficient system for keeping
records of flights
The reason for company not being
efficient is that they are still using
paper and pencil, and they have not
been kept records of volunteer
whereabouts, and fuel level
Why didn't the company try to
invent a new record keeping
system if they knew it was
ineffective?
Time spent on finding pilots
and specific planes for trips
need to decrease.
They spend a lot of time looking for
pilots and specific planes because of
the paper and pen system, they are
using.
How long does it take currently
to find pilots and what method
is used?
The company wants to
increase the number of pilots
available for faster service
All pilots are volunteers and donate
their time and resources for the
medical transport for the company
How exactly does husky air
pilot angels increase their
available pilots? Do they do
background checks on their
pilots to make sure they eligible
to fly and what is their process
for getting new pilots?
17. 16
Husky air wants a computer-
based system for record
keeping.
Do think they want this system
located on site or cloud based?
Computer based systems
required backups and
recovery plan to make sure no
data is loss or overwritten on
accident
Does husky air pilot angels have
any disaster recovery plan in
place in case of emergencies or
do they think do they at least
have funds or capabilities to
ensure that they won't lose their
data?
Team Learning Record
Who? Does What By when?
Will, Marquis, Ingrid, and
Shaswat
Understand and collect requirements from husky
air pilots to find out needs and wants for
information system
Thursday
Will Establishes the project’s value, metric, goals, and
overall MOV
Friday
Marquis Establishes a time frame for achieving the MOV in
various different areas of the company
Friday
Ingrid and Shaswat Find and perform a comparison of alternatives for
the company
Friday
Ingrid and Shaswat Produce and analyze TCO and TBO for the
company
Saturday
Will and Ingrid Provide a recommendation for the company Sunday
18. 17
Marquis Created a work breakdown structure to help
organize our tasks
Sunday
Ingrid and Shaswat Create a Resources Required table to find out what
is necessary for the project
Wednesday
Shaswat and Ingrid Resource Cost Table to find out what is cost for
those resources
Thursday
Will Create a contract payment for WMIS and husky air
pilot angles
Friday
Marquis Create a Learning cycle table Sunday
Marquis Create a Team learning Record for all deliverable Sunday
Marquis Update WBS Sunday
Team Assessment:
Our team has come a long way in learning how to delegate tasks and responsibilities. We start
by setting up two meetings a week where we conduct research and brainstorm about the
deliverables for projects. We have discovered that the most efficient way to complete work is to
initially collaborate and then divide up tasks to work on together. For example, Will helped
establish the MOV, while Marquis helped to incorporate an appropriate metrics and develop the
work breakdown structure. Ingrid and Shaswat worked on defining the total benefit of
ownership and the cost of ownership. The Team worked together helping each other in every
possible roadblock. No issues have arisen within the team, all members have work
cooperatively and effectively therefore no changes will be required in the project charter.
21. 20
Scope Management Change Process:
A scope change procedure is scheduled that will allow a scope change to occur per request after a review process.
The procedure will require a documented scope change request form and scope change request log. The request
will then be carefully considered. The decision to uphold the request will be based upon the impact and gains
derived from the change. A decision will be made at the end of the scope change review.
Scope Change Request Form
Request Name:__________WMIS__________
Requester Title:__________Date__________
Request Number:_______________________
Request Description:
One additional developer will be added to help further breakdown the work components. The scope is not a
part of the projects MOV.
Rationalization of Request:
Alternatives:
Impacts Alternative 1 Alternative 2 Alternative 3
Scope Total man hours will be increases with the
prospect of reducing the overall project duration
Schedule The overall project time would be decreased
Resources Required One additional developer
Cost + $120,00
Recommendation:
Project Sponsor:
Date_____3/9/18______
Request
Number
Request Title Date of
Request
Requested
by
Priority
(L,M,H)
Authority to
approve
Request
Expected
Response
Date
Scope
Change
Approved?
(Y/N)
22. 21
Work Breakdown Structure, Schedule and Budget
Original Project Plan, Schedule, and Budget
Resources Cost Table
Resource Cost
Project Manager $40,000
Developer $45,000
Office Administrator $35,000
Hardware (total) $8,497.99
Software Custom built
Office Cleaning $2400
Training $2400
Total $133,297.99
Resources Required Table
People and their roles ● Sponsor - Will oversee the managers work and will be
providing the financial support for the project.
● Project Managers - Will lead all the team efforts and guide
other employees. They will be responsible for schedule,
budget and scope.
● Developers - Person that will create, update and maintain
the software for Husky air.
Technology ● Workstations: Two PC with 1 home server and Tablets.
● Software: Custom made software / Outlook or Gmail for
emails
● Industrial printer/ scanner
● Telephone for additional customer support.
● Wi-Fi- Router and internet service from Google Fiber
23. 22
Facilities ● Office Administrator to look at day-to-day work.
● Outsourcing: Office cleaners.
Other ● Maintenance - The developer will be responsible to
maintain the system.
● Training and Implementation: Will be conducted by the
Project Manager to ensure the customer can control and
maintain the systems if needed.
Task Name Duration Resource
Husky Air Pilot Angels Information Systems 125 Days
Conceptualize and Initialize Project 51 Days
Team Charter 13 Days
Establish Team Members 1 Day Project Manager
Determine Strengths and Hot button issues of
team members
2 Days Project Team
Determine team rules 2 Days Project Team
Approve team’s Tops Document 5 Days Project Team
Business Case 31 Days
Background of Husky Air Pilot Angels 2 Days Project Team, Project Manager
The Project Description 4 Days Project Manager
Determine the requirements for the Project 5 Days Project Manager
Develop The MOV 8 Days Project Team
24. 23
Identify Areas of Impact 1 Day Project Team
Identify Desired Value of Project 1 Day Project Team, Project Manager
Develop appropriate metric 1 Day Project Team
Set Time Frame for achieving MOV 1 Day Project Team
Verify MOV 2 Days Project Team
Summarize MOV 1 Day Project Team
Approve MOV 2 Days Project Manager
Find Alternatives to the Project 1 Day Project Team
Define Total Cost of Ownership 3 Days Project Team
Direct/upfront costs 1 Day Project Team
Ongoing costs 1 Day Project Team
Indirect costs 1 Day Project Team
Define Total Benefits of Ownership 4 Days Project Team
Increase high value work 1 Day Project Team
Improve accuracy and efficiency 1 Day Project Team
Improve decision making 1 Day Project Team
Improve customer service 1 Day Project Team
25. 24
Recommendation 3 Days Project Team
Review Business Case 1 Day Project Team
Approve Business Case 2 Days Project Manager
Milestone: Conceptualize and Initialize Project
completed
0 Days
Project Charter 11 Days
Project Infrastructure 11 Days Project Team
Document the MOV for the project 0 Days Project Team
Define the Project Infrastructure 3 Days Project Team
Resource required table 2 Days Project Team
Resource cost table 1 Day Project Team
Contract Payment Method 2 Days Project Team
Learning Cycle Table 2 Days Project Team
Team Learning Record 2 Days Project Team
Team Assessment of Team Charter 2 Days Project Team
Review Project Infrastructure 1 Day Project Team
Approve Project Infrastructure 1 Day Project Team
Milestone: Project Infrastructure completed 0 Days
26. 25
Project Plan 28 Days
Scope Management Plan 15 Days Project Team
Revise Project MOV 1 Days Project Team
Determine Project’s Deliverables 1 Days Project Team
Create Deliverable Structure Chart 1 Days Project Team
Create a Gantt chart based off of DSC 1 Days Project Team
Create a Use case Diagram 1 Days Project Team
Scope Change Process 13 Days Project Team
Scope Change request form 4 Days Project Manager, Project Team
Scope Change request log 2 Days Project Manager
Review Scope Management 3 Day Project Team
Approve Scope Management 1 Day Project Manager
Execute and Control 43 Days
Analysis 3 Days Project Team
Create System Proposal 3 Days System Developer, Project
Team
Milestone: Analysis Completed 0 Days
Design 16 Days
27. 26
Design Information system Based system
Proposal
16 Days Project Team, System
Developer
Milestone: Design Phase Completed 0 Days
Construction 7 Days
WMIS Application System 7 Days Project Team , System
Developer
Milestone: Construction of WMIS Application
System Completed
0 Days
Testing 10 Days
Test Plan 2 Days Project Team
Test results report 2 Days
Review test plan with client 2 Days Project Team, Project Manager
Carry out test plan 2 Days Project Team
Analyze Results 2 Days Project Team
Prepare test results and presentation 2 Days Project Team
Present test results to client 2 Days Project Team
Address software issues or problems 1 Day Project Team
Milestone: Client signs off on test results 0 Days
Implementation 3 Days
28. 27
Create documentation for company 1 Day Project Manager , Project Team
Training program 1 Day Project Team
Conversion plan 1 Day Project Team , Project
Manager
Milestone:Execute and Control Completed 0 Days
Close Project 2 Days
Management Report 1 Days Project Team
Formal Acceptance 1 Days Project Team, Project Manager
Evaluate Project Success 5 Days Project Team
Conduct Project Evaluation 2 Days Project Team, Project Manager
Determine if project meets MOV 1 Day Project Team, Project Manager
Milestone: Project Completed 0 Days
32. 31
Risk Management Plan
Revised Project Plan, Schedule, and Budget
Resources Cost Table
Resource Cost
Project Managers (2) $80,000
Developers (2) $90,000
Office Administrator $35,000
Hardware (total) $8,497.99
Software Custom built
Office Cleaning $2400
Training $2400
Total $218,297.99
Resource Requirements Descriptions for why the cost are incurred:
Resource Description
Project Manager Needed to lead and manage the team and
help with developing.
System Developer Works with the manager and design the basic
structure and constructs the system.
Office Administrator The office administrator is responsible to
make sure the managers and developers have
all the necessary resources needed throughout
the project.
33. 32
Hardware The hardware includes, printers, scanner,
phone, router and other necessary things
needed to properly support the developers.
Software Will be custom built, to better serve
customers need which needs to download on
hardware to complete business process.
Office Maintenance(Cleaners) The office area will be cleaned with a year
contract with another service.
Training Training of the team to get to know the project
and the process for best performance.
Task Name Duration Resource
Husky Air Pilot Angels Information Systems 155 Days
Conceptualize and Initialize Project 51 Days
Team Charter 13 Days
Establish Team Members 1 Day Project Manager
Determine Strengths and Hot button issues of
team members
2 Days Project Team
Determine team rules 2 Days Project Team
Approve team’s Tops Document 5 Days Project Team
Business Case 37 Days
Background of Husky Air Pilot Angels 2 Days Project Team, Project Manager
34. 33
The Project Description 4 Days Project Manager
Determine the requirements for the Project 5 Days Project Manager
Develop The MOV 8 Days Project Team
Identify Areas of Impact 1 Day Project Team
Identify Desired Value of Project 1 Day Project Team, Project Manager
Develop appropriate metric 1 Day Project Team
Set Time Frame for achieving MOV 1 Day Project Team
Verify MOV 2 Days Project Team
Summarize MOV 1 Day Project Team
Approve MOV 2 Days Project Manager
Find Alternatives to the Project 1 Day Project Team
Define Total Cost of Ownership 3 Days Project Team
Direct/upfront costs 1 Day Project Team
Ongoing costs 1 Day Project Team
Indirect costs 1 Day Project Team
Define Total Benefits of Ownership 4 Days Project Team
Increase high value work 1 Day Project Team
35. 34
Improve accuracy and efficiency 1 Day Project Team
Improve decision making 1 Day Project Team
Improve customer service 1 Day Project Team
Recommendation 3 Days Project Team
Review Business Case 1 Day Project Team
Approve Business Case 2 Days Project Manager
Milestone: Conceptualize and Initialize Project
completed
0 Days
Project Charter 16 Days
Project Infrastructure 15 Days Project Team
Document the MOV for the project 0 Days Project Team
Define the Project Infrastructure 6 Days Project Team
Resource required table 3 Days Project Team
Resource cost table 1 Day Project Team
Contract Payment Method 2 Days Project Team
Learning Cycle Table 2 Days Project Team
Team Learning Record 2 Days Project Team
Team Assessment of Team Charter 2 Days Project Team
36. 35
Review Project Infrastructure 1 Day Project Team
Approve Project Infrastructure 1 Day Project Team
Milestone: Project Infrastructure completed 0 Days
Project Plan 28 Days
Scope Management Plan 3 Days Project Team
Revise Project MOV 3 Days Project Team
Determine Project’s Deliverables 3 Days Project Team
Create Deliverable Structure Chart 3 Days Project Team
Create a Gantt chart based off of DSC 3 Days Project Team
Create a Use case Diagram 3 Days Project Team
Scope Change Process 3 Days Project Team
Scope Change request form 3 Days Project Manager, Project Team
Scope Change request log 2 Days Project Manager
Review Scope Management 1 Day Project Team
Approve Scope Management 1 Day Project Manager
Execute and Control 51 Days
Analysis 5 Days Project Team
37. 36
Create System Proposal 3 Days System Developer, Project
Team
Milestone: Analysis Completed 0 Days
Design 15 Days
Design Information system Based system
Proposal
15 Days Project Team, System
Developer
Milestone: Design Phase Completed 0 Days
Construction 11 Days
WMIS Application System 8 Days Project Team, System
Developer
Milestone: Construction of WMIS Application
System Completed
0 Days
Testing 14 Days
Test Plan 2 Days Project Team
Test results report 11 Days
Review test plan with client 2 Days Project Team, Project Manager
Carry out test plan 2 Days Project Team
Analyze Results 2 Days Project Team
Prepare test results and presentation 2 Days Project Team
Present test results to client 2 Days Project Team
38. 37
Address software issues or problems 1 Day Project Team
Milestone: Client signs off on test results 0 Days
Implementation 3 Days
Create documentation for company 1 Day Project Manager, Project Team
Training program 1 Day Project Team
Conversion plan 1 Day Project Team, Project Manager
Milestone: Execute and Control Completed 0 Days
Close Project 5 Days
Management Report 2 Days Project Team
Formal Acceptance 2 Days Project Team, Project Manager
Evaluate Project Success 3 Days Project Team
Conduct Project Evaluation 2 Days Project Team, Project Manager
Determine if project meets MOV 1 Day Project Team, Project Manager
Milestone: Project Completed 0 Days
41. 40
Written Report:
The beginning date for the project is May 23, 2018 and the end date is December 25th, taking 155 total
days to complete. Our project does have a single critical path which is marked red in our network
diagram or anything that is highlight in yellow on the Gantt chart. The critical path is important because
it tells us the length and time of when the project will be completed and any change to the duration of a
task may affect the project schedule. There are no over allocated resources for the project.
42. 41
Risk Analysis Table
Conceptualize
and Initialize
Develop
Project Charter
and Plan
Execute and
Control Phase
Close Project Evaluate
Project
Success
Potential Risk A potential risk
could arise in
not correctly
collecting user
requirements.
Neglected to
gather them
correctly could
likely result in
error and
misunderstandi
ng that
transcends the
entire project.
Team not
agreeing on
points of
interest and
disinterest.
Husky Air is
unable to
adapt to the
new system.
The old system
is preferred
and transfer to
the new
system is not
worth the
cost.
Project is
delayed or
rejected.
The project
will need to
have a
management
report, and
formal
acceptance. If
either of these
deliverables
are not
fulfilled then it
will extend the
length of the
project until
they are
finished.
In what ways
could this risk
impact the
MOV?
Failing to
initialize the
project and
collect
requirements
could cause the
duration of the
project to
increase.
Conflict could
cause a lack of
progress and
decrease the
chances of
reaching the
target MOV.
If the new
system is
rejected then
the entire
project would
be a failure
because the
MOV would
not have been
reached.
If the project is
delayed then it
will increase
development
costs past the
original work
breakdown.
If the
evaluation
takes longer
than expected
then it will also
increase the
project's
duration until
it is fully
evaluated.
How could
this
potentially
impact the
project
objectives
(scope,
quality,
schedule,
budget)
If the
requirements
are not
correctly
acquired then
it could put the
project on the
wrong track.
The quality
would be
misdirected
If the team is
not cohesive it
could lengthen
the overall
project.
The project
failing to be
quickly
adapted would
increase the
time it takes to
get the system
fully online
and likely
increase in
cost because
If the project
was delayed or
rejected, then
the quality
would be
improved until
it was
expected. This
would
certainly
increase the
The project
duration
would be
extended as a
result of this
risk. There
would also be
added cost
associated
with the effort
to correct the
43. 42
and costs and
duration would
likely increase
to compensate
for error.
employees
would need
further
training.
overall costs
and time or
the project.
problem with
the project.
Source(s) of
project risk
(people, legal,
process,
environment,
technology,
organization,
project, other)
The source of
this risk would
mostly come
from the
environmental
social aspects
of the project.
It could also
come from an
organizational
issue if the
requirements
are not
disseminated
throughout the
project team.
This risk would
most likely
develop
internally as a
result of the
team have
conflict.
The cause of
these issues
would
probably be
from our team
itself. That
would also
include issues
that Husky air
had with our
project.
If the project is
delayed or
rejected it
would be
entirely our
teams’ fault.
The source of
this would
once again be
our teams
fault and not
Husky Air’s
Are the
sources of risk
internal or
external to
the project?
This could
possibly be
external.
This would be
an internal
source as a
result of the
team
members
actions.
The collective
environment
surrounding
the project
could affect
this aspect of
the project
This is an
internal risk.
This is also an
internal risk.
Is this risk
known, know-
unknown,
and/or
unknown-
unknown?
Unknown-
unknown
Known-
unknown
Known-
unknown
Unknown-
unknown
Known-
unknown
Risk Owner Project
Manager
Project
Manager
System
Developer
Project
Manager
Project
Manager
Risk
Management
Strategy
The project
manager will
keep thorough
The project
manager will
update the
They system
manager must
make sure that
The project
manager will
help ensure
A project
manager will
check back
44. 43
requirements
collection
process that is
triple verified
before the
project begins.
Regular check
up on the
requirements
will also ensure
that the project
stays on course
team charter
will be
reflected upon
frequently to
ensure that
the team is still
on the same
page.
the system is
accepted by
Husky Air. The
new system
must be
friendly
enough to be a
full
replacement
of the old
system.
that the
reports and
acceptance is
fully
completed.
after project
completion to
see that it has
been fully
adopted. They
will also
conduct
reports to
update
firmware if
necessary.
45. 44
Earned Value and Quality Management Plan
Earned Value Analysis:
Earned Value Analysis
Planned Value $13,280.00
Actual Cost $13,720.00
Earned Value $10,880
Schedule Variance $(2,400)
Cost Variance $(2,840)
Schedule Performance Index 0.8
Cost Performance Index 0.8
Budget at Completion $14,040
Estimate at Completion $17,704.87
Analysis of current status:
From our analysis, the cost variance is a negative $2840 with a negative schedule variance of
$2400. This puts the project at an estimated completion of $17,704.87. The project was
originally planned to cost $13,280 which shows us a $4,424.87 difference gap. Per the analysis it
does not seem that the original budget for the project completion is feasible and it would need to
be increased in order to get it on track with a reasonable time and cost.
Conclusion from Analysis:
The analysis computed concludes that we would refrain from outsourcing the system to
BugBuster, based on the conclusion that it causes an increase in budget of approximately $4,430.
This results a fall in budget and schedule and the earned value is not matching for future
spending costs. Therefore, the best option for Husky Air is to find a new firm to outsource the
current development of the system.
50. 49
Quality Management Plan
Introduction
The Management plan of Husky Air will install procedures to enclose and encase the quality
through the closure of the project and after the project. The Management Plan for Husky Air has
objectives and approaches that will reach and are the following:
I. Ensure Quality
II. Ensure Accessibility
III. Ensure Integrity and Reliability
IV. Ensure Expandability and Maintainability
Quality Management Procedure:
The Husky Air Quality Management Plan will validate and verify that the standard of
quality standards is in effect for the product metric and the process metric. This success in the
quality management plan is imperative for the future of the project.
Husky Air will ensure quality by ensuring that the process and the product are accessible and
correct to ensure that the use of the system is available and reliable. The product quality for
Husky Air will be defined by the product metric, which is defined by both the employees and the
Husky Air customer. Users will be behind the quality of the product to ensure maximum
acceptance by customers. The project team will assume the function of guaranteeing quality if
the product is acceptable to users.
Process Metric for Husky Air will focus on the process that Husky Air takes during its business
processes. This will ensure that the quality of the processes carried out complies with the
standards of the organization and the expectations of those who participate both the client and
Husky Air employees.
Quality Requirements/Standards:
Product Quality:
The product quality will be of high quality, the developers will develop the
product by keeping both the project sponsor and the users in mind. These requirements and needs
will be assessed and portrayed when defining the product and process metric. The product will
be controlled and monitoring highest customer satisfaction, reliability and security. The process
will be controlled through the monitory of defects and any glitches that may occur during the
process. The product will be validated multiple times before exporting it for business needs.
51. 50
Quality Metrics
Type Metric Description
Process Defects by Phase
Defects by Time
Defects by Content errors
Defect Backlog
Fix Response Time
Defective Fixes
Number of defects found during each phase of the project
Number of defects found over a period of time
Number of times an error appears dealing with a content-related
issue
Number of defects waiting to be fixed
Average time it takes to fix a defect
Number of fixes that created new defects
Product Customer Satisfaction
Customer Found Defects
System Failure
Reports Failure
Rating index to measure customer satisfaction or dissatisfaction,
scale 1 (unsatisfied) to 5 (satisfied)
Number of defects found by the customer
Number of times the system fails to operate
Number of defects when running reports through the system
Project Scope Change Requests
Scope Change Approval
Over Budgeted Tasks
Earned Value
Number of scope changes requested by client or sponsor
Number of scope changes that were approved
Number of tasks that cost more than expected
SV, CV, SPI, CPI, ETC, EAC
52. 51
Over Allocated Resources
Training Hours
Number of resources assigned to more than one task
Number of training hours per project team member to train
employees
Verification of Quality
The quality assurance of Husky Air will ensure that the final production of the information
system will be implemented and equipped effectively. The system will be constantly updated and
maintained for improvement and fix of bugs or problems. In order to ensure that the system is
adopted we will conduct walk-through sessions with the users to guarantee that they fully
understand the systems’ mechanics. This will ensure that the quality of the Husky Air
Information System is met throughout its lifecycle.
Technical Review: Our team will conduct a walk-through where the system developer
leads Husky Air to provide the opportunity for errors to be discovered and ensure that standards
are met. There will also be peer review inspections using a checklist to double check for
potential errors. This will be done to verify project deliverables throughout the entire project life
cycle by involving the users of the system and also providing a chance for them to ask questions.
Business Reviews: To ensure that all deliverables are met we will conduct business
reviews that will provide information for the next phases, make sure standards are met, and that
the project methodology is being conformed to. These reviews will be cross checked to make
sure that they align with the mission of Husky Air.
Management Reviews: We will also compare the baseline project plan against the actual
project progress by conducting management reviews. These will provide a clear picture of
progress, issues that need to be resolved, adjusted resources, and alternative decisions.
Management may also review that project to make sure that it meets the project’s MOV, scope,
budget, and quality objectives.
Validation of Quality:
After reviewing Customers Input, we can analyze and depict users concerns, wants, likes
and needs on regular basis to make changes to ensure customer satisfaction. This can help us
ensure the quality through customer satisfaction. Usability test, that validates that the system is
usable and run efficiently can ensure the quality of the system for the user and project sponsors.
Prototyping can also help validate that the system and or user interface is approved by user and
can help easily make changes and correction as needed before the final product can be delivered
and can ensure quality.