SlideShare a Scribd company logo
1 of 13
Issue Date: June 14, 2017 / By Tassanai Cheangban, Field Application Engineer, Delta Electronics
How to Operate Parallel and Series Connection
2
In general, when selecting a power supply, it is important to choose one with appropriate voltage and current rating to
support the system requirements. Typically, power supplies are connected in parallel to increase the power/current rating
and also to increase the system reliability by providing redundancy function. Series connection of power supplies can
cater to special needs of the system when requiring higher output voltages.
Parallel or Series?
3
The purpose of parallel operation is to get increased output current. When in 1+1 connection, the total output current will
be maximum 2x of each individual power supply rating. Load sharing between the 2 supplies can also be achieved. (See
“Load Sharing” topic below). When connecting more than one power supply (N+1), it is recommended to connect using
external ORing diodes (Delta recommends the use of DRR-20N or DRR-40N). See Figure 2.
To achieve redundancy function, the system current demand should not be greater than the rating of a single power
supply. More details are available under the “Redundancy” topic later in this article. In the case of redundant connection,
system operation is not disrupted when there is a failure in one of the power supply. This prevents overall system
downtime. Load Sharing
Load Sharing Concept
1. Parallel Operation
Figure 1. Load Sharing Connection Diagram (1+1)
4
1. Parallel Operation
Figure 2. Load Sharing Connection Diagram (N+1)
The power supplies can be connected together for parallel operation to increase the output current. See Figure 1 below.
To achieve this, it is important that the output voltages of both power supplies must be within 25mV difference of each
other. The output voltage adjustment must be done at 50% of max load current or at a load current 25% and above
ensuring that both the power supplies have been adjusted at the same current level independently.
5
1. Parallel Operation
Figure 3. Redundant Connection Diagram
Redundancy Concept
Power supplies must be connected using ORing diodes to achieve redundant operation. The output voltage difference
between the two power supplies is kept typically at 2% of the output voltage. For a 24V power supply, keep a gap of 0.48V
(0.45~0.50V). In the event of a failure with one of the power supply, the other power supply will take over the system load.
Ensure that the selected power supply is capable of providing the system load (current rating of the power supply must not
be lower than system current demand). See Figure 3 below for connection diagram.
6
Notes:
The selection criteria for individual ORing diode must be;
 current rating at least 4x of the output load current
 reverse voltage rating 2x of the power supply output voltage
 heat sink with the ORing diode
1. Parallel Operation
7
1. Parallel Operation
Increase operational reliability of the system with Delta Redundancy Module
Delta redundancy modules DRR-20N and DRR-40N use Schottky diodes to keep the conduction losses at a minimum.
The modules also use potential free contacts to provide an external signal when the failure from either power supply.
Delta recommend the use of DRR-20N and DRR-40N for load sharing and redundant operations. Product details are
available via these links DRR-20N and DRR-40N.
8
1. Parallel Operation
Steps to using DRR Module for parallel operation (redundant and load sharing)
Follow the steps below to use DRR-20N and DRR-40N modules
Step 1: Measure and set output voltage
For redundant operation;
Measure the output voltages (VO) of PSU 1 and PSU 2. If PSU 1 is the master unit, then VO of PSU 1 must be higher
than PSU 2 (0.45~0.50V for 24V or 0.90~1.00V for 48V). To correctly set the output voltage, individually connect each
power supply to 50% of the rated load between 85-264Vac input voltage before making the adjustments.
For the load sharing operation;
Measure VO of PSU 1 and PSU 2. The VO difference of PSU 1 and PSU 2 must be within 25mV of each other. To
correctly set the output voltage, individually connect each power supply to 50% of the rated load between 85-264Vac input
voltage before making the adjustments.
Step 2: Connect power supply units to DRR module
Connect the power supplies PSU 1 and PSU 2 to Vin 1 & Vin 2 of the DRR module. Refer to Figure 4.
Step 3: Connect the system load to Vout
Connect the system load to Vout. Note the output voltage Vout from DRR module = VO (output voltage of power supply) –
Vdrop* (DRR module).
*Vdrop will vary from 0.60V to 0.90V (Typical 0.65V) depending on the load current and surrounding air temperature.
9
1. Parallel Operation
Figure 4. DRR Module Connection Diagram
**The Signal GND in the DRR module is for the LED and DC OK signals located in the module. The Output GND terminals from the two PSU’s do
not need to be connected to the Signal GND terminal.
10
Power supplies can be connected in series to increase the output voltage as shown in Figure 5. Only power supply from
the same product series and with same rated output current should be used.
The maximum load current should not exceed the smallest rated output current, when selecting power supplies with
different current ratings. Any number of power supplies can be connected in series. System designers must note that an
output voltage > 60Vdc will not meet SELV requirements, and can be dangerous. Under no circumstances the total
voltage should exceed 150Vdc. When the total voltage exceeds the SELV limit of 60Vdc, a protective barrier against
touching the output terminals must be installed, together with connecting the output ground (-V2 DC Return) terminal of
power supply to Earth ground. See Figure 5.
2. Series Operation
Figure 5. Series Operation Diagram
An ORing diode in reverse bias must be added
across output terminals of each power supply. This
is to prevent -V voltage being applied to other
power supply in fault conditions such as short
circuit across load. During a short circuit, -V1 &
+V1 will be connected across +V2 & -V2 which
means the 2 power supplies output will be
connected in opposite polarity and will cause
damage to the power supplies.
With diode connected in reverse bias across the
output, the voltage across each power supply
output will be restricted to one diode drop –
approximately 0.7V to 1.0V. It is recommended to
provide sufficient voltage de-rating for diodes with
2x the voltage rating of series output voltage.
11
Example: When two 24V power supplies are connected in series, the total voltage will be 48V. During a short circuit, the
current through the ORing diodes will be very high. Therefore, use ORing diodes with reverse voltage rating of at least 2 ×
48 = 96V.
2. Series Operation
Figure 6. Non-monotonic Turn-on Waveform
When power supplies are used in parallel and series operations, parameters such as EMI, inrush current, leakage current,
PARD, and startup time will be different compared to a standalone power supply. The system designer must consider
these parameters on a system level.
12
To learn more how to execute series and parallel operation,
kindly contact your local distributor or please visit
www.DeltaPSU.com for more information and other types
of Delta power supplies.
Ask Question
Learn More
Send Me More Article
Smarter. Greener. Together.
www.DeltaPSU.com
To be the first person who
know about our new
product and other news
update, subscribe to
DeltaPSU newsletter now.
Click Subscribe

More Related Content

What's hot

Design of a 400kv Transmission network
Design of a 400kv Transmission networkDesign of a 400kv Transmission network
Design of a 400kv Transmission networkIsaac Muyinza
 
Digital phase changer ppt
Digital phase changer pptDigital phase changer ppt
Digital phase changer pptAshish Verma
 
Presentation on power distribution, operation and maintenance in comilla pbs 1
Presentation on power distribution, operation and maintenance in comilla pbs 1Presentation on power distribution, operation and maintenance in comilla pbs 1
Presentation on power distribution, operation and maintenance in comilla pbs 1Kawsar Ahmed
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLyohannes feleke
 
auto-matic phase changer
auto-matic phase changerauto-matic phase changer
auto-matic phase changerWaj Jenny Bunny
 
POWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxPOWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxJeffrey Dorsey
 
PPT ON 400KV GSS HEERAPURA JAIPUR
PPT ON 400KV GSS HEERAPURA JAIPUR PPT ON 400KV GSS HEERAPURA JAIPUR
PPT ON 400KV GSS HEERAPURA JAIPUR Amit kumar
 
protection scheme of a grid substation prsentation
protection scheme of a grid substation prsentationprotection scheme of a grid substation prsentation
protection scheme of a grid substation prsentationabu jubayer
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level CalculationDinesh Sarda
 
132 kv substation
132 kv substation132 kv substation
132 kv substationWipro
 
Front pages of report 132kv gss sitapura jaipur
Front pages of report 132kv gss sitapura jaipurFront pages of report 132kv gss sitapura jaipur
Front pages of report 132kv gss sitapura jaipurkishankky
 
Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationshivashankar307
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 

What's hot (20)

Design of a 400kv Transmission network
Design of a 400kv Transmission networkDesign of a 400kv Transmission network
Design of a 400kv Transmission network
 
132 kv
132 kv132 kv
132 kv
 
Digital phase changer ppt
Digital phase changer pptDigital phase changer ppt
Digital phase changer ppt
 
Presentation on power distribution, operation and maintenance in comilla pbs 1
Presentation on power distribution, operation and maintenance in comilla pbs 1Presentation on power distribution, operation and maintenance in comilla pbs 1
Presentation on power distribution, operation and maintenance in comilla pbs 1
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
 
auto-matic phase changer
auto-matic phase changerauto-matic phase changer
auto-matic phase changer
 
POWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxPOWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docx
 
46584589 substation-design-data
46584589 substation-design-data46584589 substation-design-data
46584589 substation-design-data
 
PPT ON 400KV GSS HEERAPURA JAIPUR
PPT ON 400KV GSS HEERAPURA JAIPUR PPT ON 400KV GSS HEERAPURA JAIPUR
PPT ON 400KV GSS HEERAPURA JAIPUR
 
132 kv seminar ppt
132 kv seminar ppt132 kv seminar ppt
132 kv seminar ppt
 
protection scheme of a grid substation prsentation
protection scheme of a grid substation prsentationprotection scheme of a grid substation prsentation
protection scheme of a grid substation prsentation
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
ECNG 3015 chapter 1 - Basics
ECNG 3015  chapter 1 - BasicsECNG 3015  chapter 1 - Basics
ECNG 3015 chapter 1 - Basics
 
ppt
pptppt
ppt
 
132 kv substation
132 kv substation132 kv substation
132 kv substation
 
Front pages of report 132kv gss sitapura jaipur
Front pages of report 132kv gss sitapura jaipurFront pages of report 132kv gss sitapura jaipur
Front pages of report 132kv gss sitapura jaipur
 
1.substation layouts
1.substation  layouts1.substation  layouts
1.substation layouts
 
Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substation
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 

Similar to How to Operate Parallel and Series Connection

Applied motion products regen clamp
Applied motion products regen clampApplied motion products regen clamp
Applied motion products regen clampElectromate
 
Power-System-Slide-1.pptx
Power-System-Slide-1.pptxPower-System-Slide-1.pptx
Power-System-Slide-1.pptxssuser99d6551
 
Control of parallel dc dc converters in a dc microgrid
Control of parallel dc dc converters in a dc microgridControl of parallel dc dc converters in a dc microgrid
Control of parallel dc dc converters in a dc microgridSushil Aggarwal
 
Original High Performance Off-Line Controller IC ACT30 CT30 30 New Active-Semi
Original High Performance Off-Line Controller IC ACT30 CT30 30 New Active-SemiOriginal High Performance Off-Line Controller IC ACT30 CT30 30 New Active-Semi
Original High Performance Off-Line Controller IC ACT30 CT30 30 New Active-SemiAUTHELECTRONIC
 
To Diminish the Voltage Sag Replaced DVR with Generalized Modulation Strategy...
To Diminish the Voltage Sag Replaced DVR with Generalized Modulation Strategy...To Diminish the Voltage Sag Replaced DVR with Generalized Modulation Strategy...
To Diminish the Voltage Sag Replaced DVR with Generalized Modulation Strategy...IRJET Journal
 
IRJET- Automatic Load Sharing of Transformer
IRJET- Automatic Load Sharing of TransformerIRJET- Automatic Load Sharing of Transformer
IRJET- Automatic Load Sharing of TransformerIRJET Journal
 
Design of transformer less power supply for low power application
Design of transformer less power supply for low power applicationDesign of transformer less power supply for low power application
Design of transformer less power supply for low power applicationeSAT Journals
 
Electric bus best public transport(hum safar)
Electric bus best public transport(hum safar)Electric bus best public transport(hum safar)
Electric bus best public transport(hum safar)Mahesh Chandra Manav
 
Review on Automatic Power Factor Improvement of Induction Motor
Review on Automatic Power Factor Improvement of Induction MotorReview on Automatic Power Factor Improvement of Induction Motor
Review on Automatic Power Factor Improvement of Induction MotorIRJET Journal
 
Amp regen clamp_specsheet
Amp regen clamp_specsheetAmp regen clamp_specsheet
Amp regen clamp_specsheetElectromate
 
IRJET- A Comparative Study of Multilevel Inverter Topologies
IRJET- A Comparative Study of Multilevel Inverter TopologiesIRJET- A Comparative Study of Multilevel Inverter Topologies
IRJET- A Comparative Study of Multilevel Inverter TopologiesIRJET Journal
 
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...IRJET Journal
 
India great intiative a carbon free silent road transportaion electric vehicle
India great intiative a carbon free silent road transportaion electric vehicleIndia great intiative a carbon free silent road transportaion electric vehicle
India great intiative a carbon free silent road transportaion electric vehicleMahesh Chandra Manav
 
ISL6257: Highly Integrated Battery Charger Controller for Li-Ion/Li-Ion Polym...
ISL6257: Highly Integrated Battery Charger Controller for Li-Ion/Li-Ion Polym...ISL6257: Highly Integrated Battery Charger Controller for Li-Ion/Li-Ion Polym...
ISL6257: Highly Integrated Battery Charger Controller for Li-Ion/Li-Ion Polym...Premier Farnell
 
Simplify Power Disruption Management for Higher Efficiency and Lower Cost wit...
Simplify Power Disruption Management for Higher Efficiency and Lower Cost wit...Simplify Power Disruption Management for Higher Efficiency and Lower Cost wit...
Simplify Power Disruption Management for Higher Efficiency and Lower Cost wit...Delta Electronics Power Supply
 
Ser2200 linpwrsuppyspecsappnote
Ser2200 linpwrsuppyspecsappnoteSer2200 linpwrsuppyspecsappnote
Ser2200 linpwrsuppyspecsappnotePawar Chander
 

Similar to How to Operate Parallel and Series Connection (20)

Applied motion products regen clamp
Applied motion products regen clampApplied motion products regen clamp
Applied motion products regen clamp
 
Power-System-Slide-1.pptx
Power-System-Slide-1.pptxPower-System-Slide-1.pptx
Power-System-Slide-1.pptx
 
Control of parallel dc dc converters in a dc microgrid
Control of parallel dc dc converters in a dc microgridControl of parallel dc dc converters in a dc microgrid
Control of parallel dc dc converters in a dc microgrid
 
Original High Performance Off-Line Controller IC ACT30 CT30 30 New Active-Semi
Original High Performance Off-Line Controller IC ACT30 CT30 30 New Active-SemiOriginal High Performance Off-Line Controller IC ACT30 CT30 30 New Active-Semi
Original High Performance Off-Line Controller IC ACT30 CT30 30 New Active-Semi
 
To Diminish the Voltage Sag Replaced DVR with Generalized Modulation Strategy...
To Diminish the Voltage Sag Replaced DVR with Generalized Modulation Strategy...To Diminish the Voltage Sag Replaced DVR with Generalized Modulation Strategy...
To Diminish the Voltage Sag Replaced DVR with Generalized Modulation Strategy...
 
IRJET- Automatic Load Sharing of Transformer
IRJET- Automatic Load Sharing of TransformerIRJET- Automatic Load Sharing of Transformer
IRJET- Automatic Load Sharing of Transformer
 
Design of transformer less power supply for low power application
Design of transformer less power supply for low power applicationDesign of transformer less power supply for low power application
Design of transformer less power supply for low power application
 
L 21(dp)(pe) ((ee)nptel)
L 21(dp)(pe) ((ee)nptel)L 21(dp)(pe) ((ee)nptel)
L 21(dp)(pe) ((ee)nptel)
 
Electric bus best public transport(hum safar)
Electric bus best public transport(hum safar)Electric bus best public transport(hum safar)
Electric bus best public transport(hum safar)
 
Review on Automatic Power Factor Improvement of Induction Motor
Review on Automatic Power Factor Improvement of Induction MotorReview on Automatic Power Factor Improvement of Induction Motor
Review on Automatic Power Factor Improvement of Induction Motor
 
Amp regen clamp_specsheet
Amp regen clamp_specsheetAmp regen clamp_specsheet
Amp regen clamp_specsheet
 
IRJET- A Comparative Study of Multilevel Inverter Topologies
IRJET- A Comparative Study of Multilevel Inverter TopologiesIRJET- A Comparative Study of Multilevel Inverter Topologies
IRJET- A Comparative Study of Multilevel Inverter Topologies
 
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
 
India great intiative a carbon free silent road transportaion electric vehicle
India great intiative a carbon free silent road transportaion electric vehicleIndia great intiative a carbon free silent road transportaion electric vehicle
India great intiative a carbon free silent road transportaion electric vehicle
 
Series2200 app note
Series2200 app noteSeries2200 app note
Series2200 app note
 
N1103048593
N1103048593N1103048593
N1103048593
 
Gl3112351241
Gl3112351241Gl3112351241
Gl3112351241
 
ISL6257: Highly Integrated Battery Charger Controller for Li-Ion/Li-Ion Polym...
ISL6257: Highly Integrated Battery Charger Controller for Li-Ion/Li-Ion Polym...ISL6257: Highly Integrated Battery Charger Controller for Li-Ion/Li-Ion Polym...
ISL6257: Highly Integrated Battery Charger Controller for Li-Ion/Li-Ion Polym...
 
Simplify Power Disruption Management for Higher Efficiency and Lower Cost wit...
Simplify Power Disruption Management for Higher Efficiency and Lower Cost wit...Simplify Power Disruption Management for Higher Efficiency and Lower Cost wit...
Simplify Power Disruption Management for Higher Efficiency and Lower Cost wit...
 
Ser2200 linpwrsuppyspecsappnote
Ser2200 linpwrsuppyspecsappnoteSer2200 linpwrsuppyspecsappnote
Ser2200 linpwrsuppyspecsappnote
 

More from Delta Electronics Power Supply

New CliQ VA Series of DIN Rail Power Supply with Integrated LCD Display for O...
New CliQ VA Series of DIN Rail Power Supply with Integrated LCD Display for O...New CliQ VA Series of DIN Rail Power Supply with Integrated LCD Display for O...
New CliQ VA Series of DIN Rail Power Supply with Integrated LCD Display for O...Delta Electronics Power Supply
 
Delta PMH Series of Panel Mount Power Supply Expands to Pollution Degree 3 fo...
Delta PMH Series of Panel Mount Power Supply Expands to Pollution Degree 3 fo...Delta PMH Series of Panel Mount Power Supply Expands to Pollution Degree 3 fo...
Delta PMH Series of Panel Mount Power Supply Expands to Pollution Degree 3 fo...Delta Electronics Power Supply
 
Delta New LNP-C Series of LED Driver with Constant Current for Indoor Applica...
Delta New LNP-C Series of LED Driver with Constant Current for Indoor Applica...Delta New LNP-C Series of LED Driver with Constant Current for Indoor Applica...
Delta New LNP-C Series of LED Driver with Constant Current for Indoor Applica...Delta Electronics Power Supply
 
Delta Extends the Chrome DIN Rail Power Supply Series with 12V 100W Model
Delta Extends the Chrome DIN Rail Power Supply Series with 12V 100W ModelDelta Extends the Chrome DIN Rail Power Supply Series with 12V 100W Model
Delta Extends the Chrome DIN Rail Power Supply Series with 12V 100W ModelDelta Electronics Power Supply
 
Delta Introduces 24V 480W DIN Rail Power Supply with Maritime Approval
Delta Introduces 24V 480W DIN Rail Power Supply with Maritime ApprovalDelta Introduces 24V 480W DIN Rail Power Supply with Maritime Approval
Delta Introduces 24V 480W DIN Rail Power Supply with Maritime ApprovalDelta Electronics Power Supply
 
Delta Extends Its Lyte DIN Rail Power Supply Series with 240W and 480W for 24...
Delta Extends Its Lyte DIN Rail Power Supply Series with 240W and 480W for 24...Delta Extends Its Lyte DIN Rail Power Supply Series with 240W and 480W for 24...
Delta Extends Its Lyte DIN Rail Power Supply Series with 240W and 480W for 24...Delta Electronics Power Supply
 
Delta Introduces the DRS-30W Series as an Addition to its DIN Rail Power Supp...
Delta Introduces the DRS-30W Series as an Addition to its DIN Rail Power Supp...Delta Introduces the DRS-30W Series as an Addition to its DIN Rail Power Supp...
Delta Introduces the DRS-30W Series as an Addition to its DIN Rail Power Supp...Delta Electronics Power Supply
 
Delta Introduces 24V/10A Output to its CliQ II Two Phase Series
Delta Introduces 24V/10A Output to its CliQ II Two Phase SeriesDelta Introduces 24V/10A Output to its CliQ II Two Phase Series
Delta Introduces 24V/10A Output to its CliQ II Two Phase SeriesDelta Electronics Power Supply
 
Delta Panel Mount Power Supply Brochure (September 2014)
Delta Panel Mount Power Supply Brochure (September 2014)Delta Panel Mount Power Supply Brochure (September 2014)
Delta Panel Mount Power Supply Brochure (September 2014)Delta Electronics Power Supply
 
Delta Open Frame Power Supply Brochure (September 2014)
Delta Open Frame Power Supply Brochure (September 2014)Delta Open Frame Power Supply Brochure (September 2014)
Delta Open Frame Power Supply Brochure (September 2014)Delta Electronics Power Supply
 
Delta Panel Mount Power Supplies for LED Signage Brochure (EN, JUN-2014)
Delta Panel Mount Power Supplies for LED Signage Brochure (EN, JUN-2014)Delta Panel Mount Power Supplies for LED Signage Brochure (EN, JUN-2014)
Delta Panel Mount Power Supplies for LED Signage Brochure (EN, JUN-2014)Delta Electronics Power Supply
 
Delta Open Frame Power Supply Brochure (Rev. March 2014)
Delta Open Frame Power Supply Brochure (Rev. March 2014)Delta Open Frame Power Supply Brochure (Rev. March 2014)
Delta Open Frame Power Supply Brochure (Rev. March 2014)Delta Electronics Power Supply
 
Delta Panel Mount Power Supply Brochure. March 2014 edition
Delta Panel Mount Power Supply Brochure. March 2014 editionDelta Panel Mount Power Supply Brochure. March 2014 edition
Delta Panel Mount Power Supply Brochure. March 2014 editionDelta Electronics Power Supply
 

More from Delta Electronics Power Supply (20)

New CliQ VA Series of DIN Rail Power Supply with Integrated LCD Display for O...
New CliQ VA Series of DIN Rail Power Supply with Integrated LCD Display for O...New CliQ VA Series of DIN Rail Power Supply with Integrated LCD Display for O...
New CliQ VA Series of DIN Rail Power Supply with Integrated LCD Display for O...
 
Delta PMH Series of Panel Mount Power Supply Expands to Pollution Degree 3 fo...
Delta PMH Series of Panel Mount Power Supply Expands to Pollution Degree 3 fo...Delta PMH Series of Panel Mount Power Supply Expands to Pollution Degree 3 fo...
Delta PMH Series of Panel Mount Power Supply Expands to Pollution Degree 3 fo...
 
Delta New LNP-C Series of LED Driver with Constant Current for Indoor Applica...
Delta New LNP-C Series of LED Driver with Constant Current for Indoor Applica...Delta New LNP-C Series of LED Driver with Constant Current for Indoor Applica...
Delta New LNP-C Series of LED Driver with Constant Current for Indoor Applica...
 
Delta Extends the Chrome DIN Rail Power Supply Series with 12V 100W Model
Delta Extends the Chrome DIN Rail Power Supply Series with 12V 100W ModelDelta Extends the Chrome DIN Rail Power Supply Series with 12V 100W Model
Delta Extends the Chrome DIN Rail Power Supply Series with 12V 100W Model
 
Delta Introduces 24V 480W DIN Rail Power Supply with Maritime Approval
Delta Introduces 24V 480W DIN Rail Power Supply with Maritime ApprovalDelta Introduces 24V 480W DIN Rail Power Supply with Maritime Approval
Delta Introduces 24V 480W DIN Rail Power Supply with Maritime Approval
 
Delta Extends Its Lyte DIN Rail Power Supply Series with 240W and 480W for 24...
Delta Extends Its Lyte DIN Rail Power Supply Series with 240W and 480W for 24...Delta Extends Its Lyte DIN Rail Power Supply Series with 240W and 480W for 24...
Delta Extends Its Lyte DIN Rail Power Supply Series with 240W and 480W for 24...
 
Delta Introduces the DRS-30W Series as an Addition to its DIN Rail Power Supp...
Delta Introduces the DRS-30W Series as an Addition to its DIN Rail Power Supp...Delta Introduces the DRS-30W Series as an Addition to its DIN Rail Power Supp...
Delta Introduces the DRS-30W Series as an Addition to its DIN Rail Power Supp...
 
Delta Introduces 24V/10A Output to its CliQ II Two Phase Series
Delta Introduces 24V/10A Output to its CliQ II Two Phase SeriesDelta Introduces 24V/10A Output to its CliQ II Two Phase Series
Delta Introduces 24V/10A Output to its CliQ II Two Phase Series
 
台达标准型电源供应器 (2014 年 9月)
台达标准型电源供应器 (2014 年 9月)台达标准型电源供应器 (2014 年 9月)
台达标准型电源供应器 (2014 年 9月)
 
台达平板型电源供应器 (2014 年 9月)
台达平板型电源供应器 (2014 年 9月)台达平板型电源供应器 (2014 年 9月)
台达平板型电源供应器 (2014 年 9月)
 
台达开架型电源供应器 (2014 年 9月)
台达开架型电源供应器 (2014 年 9月)台达开架型电源供应器 (2014 年 9月)
台达开架型电源供应器 (2014 年 9月)
 
Delta Standard Power Supplies Catalog (August 2014)
Delta Standard Power Supplies Catalog (August 2014)Delta Standard Power Supplies Catalog (August 2014)
Delta Standard Power Supplies Catalog (August 2014)
 
Delta DIN Rail Power Supply Brochure (September 2014)
Delta DIN Rail Power Supply Brochure (September 2014)Delta DIN Rail Power Supply Brochure (September 2014)
Delta DIN Rail Power Supply Brochure (September 2014)
 
Delta Panel Mount Power Supply Brochure (September 2014)
Delta Panel Mount Power Supply Brochure (September 2014)Delta Panel Mount Power Supply Brochure (September 2014)
Delta Panel Mount Power Supply Brochure (September 2014)
 
Delta Open Frame Power Supply Brochure (September 2014)
Delta Open Frame Power Supply Brochure (September 2014)Delta Open Frame Power Supply Brochure (September 2014)
Delta Open Frame Power Supply Brochure (September 2014)
 
Delta Panel Mount Power Supplies for LED Signage Brochure (EN, JUN-2014)
Delta Panel Mount Power Supplies for LED Signage Brochure (EN, JUN-2014)Delta Panel Mount Power Supplies for LED Signage Brochure (EN, JUN-2014)
Delta Panel Mount Power Supplies for LED Signage Brochure (EN, JUN-2014)
 
台达LED显示屏专用电源2014年6月版
台达LED显示屏专用电源2014年6月版台达LED显示屏专用电源2014年6月版
台达LED显示屏专用电源2014年6月版
 
台达工业直流电源供应器型录
台达工业直流电源供应器型录台达工业直流电源供应器型录
台达工业直流电源供应器型录
 
Delta Open Frame Power Supply Brochure (Rev. March 2014)
Delta Open Frame Power Supply Brochure (Rev. March 2014)Delta Open Frame Power Supply Brochure (Rev. March 2014)
Delta Open Frame Power Supply Brochure (Rev. March 2014)
 
Delta Panel Mount Power Supply Brochure. March 2014 edition
Delta Panel Mount Power Supply Brochure. March 2014 editionDelta Panel Mount Power Supply Brochure. March 2014 edition
Delta Panel Mount Power Supply Brochure. March 2014 edition
 

Recently uploaded

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 

Recently uploaded (20)

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 

How to Operate Parallel and Series Connection

  • 1. Issue Date: June 14, 2017 / By Tassanai Cheangban, Field Application Engineer, Delta Electronics How to Operate Parallel and Series Connection
  • 2. 2 In general, when selecting a power supply, it is important to choose one with appropriate voltage and current rating to support the system requirements. Typically, power supplies are connected in parallel to increase the power/current rating and also to increase the system reliability by providing redundancy function. Series connection of power supplies can cater to special needs of the system when requiring higher output voltages. Parallel or Series?
  • 3. 3 The purpose of parallel operation is to get increased output current. When in 1+1 connection, the total output current will be maximum 2x of each individual power supply rating. Load sharing between the 2 supplies can also be achieved. (See “Load Sharing” topic below). When connecting more than one power supply (N+1), it is recommended to connect using external ORing diodes (Delta recommends the use of DRR-20N or DRR-40N). See Figure 2. To achieve redundancy function, the system current demand should not be greater than the rating of a single power supply. More details are available under the “Redundancy” topic later in this article. In the case of redundant connection, system operation is not disrupted when there is a failure in one of the power supply. This prevents overall system downtime. Load Sharing Load Sharing Concept 1. Parallel Operation Figure 1. Load Sharing Connection Diagram (1+1)
  • 4. 4 1. Parallel Operation Figure 2. Load Sharing Connection Diagram (N+1) The power supplies can be connected together for parallel operation to increase the output current. See Figure 1 below. To achieve this, it is important that the output voltages of both power supplies must be within 25mV difference of each other. The output voltage adjustment must be done at 50% of max load current or at a load current 25% and above ensuring that both the power supplies have been adjusted at the same current level independently.
  • 5. 5 1. Parallel Operation Figure 3. Redundant Connection Diagram Redundancy Concept Power supplies must be connected using ORing diodes to achieve redundant operation. The output voltage difference between the two power supplies is kept typically at 2% of the output voltage. For a 24V power supply, keep a gap of 0.48V (0.45~0.50V). In the event of a failure with one of the power supply, the other power supply will take over the system load. Ensure that the selected power supply is capable of providing the system load (current rating of the power supply must not be lower than system current demand). See Figure 3 below for connection diagram.
  • 6. 6 Notes: The selection criteria for individual ORing diode must be;  current rating at least 4x of the output load current  reverse voltage rating 2x of the power supply output voltage  heat sink with the ORing diode 1. Parallel Operation
  • 7. 7 1. Parallel Operation Increase operational reliability of the system with Delta Redundancy Module Delta redundancy modules DRR-20N and DRR-40N use Schottky diodes to keep the conduction losses at a minimum. The modules also use potential free contacts to provide an external signal when the failure from either power supply. Delta recommend the use of DRR-20N and DRR-40N for load sharing and redundant operations. Product details are available via these links DRR-20N and DRR-40N.
  • 8. 8 1. Parallel Operation Steps to using DRR Module for parallel operation (redundant and load sharing) Follow the steps below to use DRR-20N and DRR-40N modules Step 1: Measure and set output voltage For redundant operation; Measure the output voltages (VO) of PSU 1 and PSU 2. If PSU 1 is the master unit, then VO of PSU 1 must be higher than PSU 2 (0.45~0.50V for 24V or 0.90~1.00V for 48V). To correctly set the output voltage, individually connect each power supply to 50% of the rated load between 85-264Vac input voltage before making the adjustments. For the load sharing operation; Measure VO of PSU 1 and PSU 2. The VO difference of PSU 1 and PSU 2 must be within 25mV of each other. To correctly set the output voltage, individually connect each power supply to 50% of the rated load between 85-264Vac input voltage before making the adjustments. Step 2: Connect power supply units to DRR module Connect the power supplies PSU 1 and PSU 2 to Vin 1 & Vin 2 of the DRR module. Refer to Figure 4. Step 3: Connect the system load to Vout Connect the system load to Vout. Note the output voltage Vout from DRR module = VO (output voltage of power supply) – Vdrop* (DRR module). *Vdrop will vary from 0.60V to 0.90V (Typical 0.65V) depending on the load current and surrounding air temperature.
  • 9. 9 1. Parallel Operation Figure 4. DRR Module Connection Diagram **The Signal GND in the DRR module is for the LED and DC OK signals located in the module. The Output GND terminals from the two PSU’s do not need to be connected to the Signal GND terminal.
  • 10. 10 Power supplies can be connected in series to increase the output voltage as shown in Figure 5. Only power supply from the same product series and with same rated output current should be used. The maximum load current should not exceed the smallest rated output current, when selecting power supplies with different current ratings. Any number of power supplies can be connected in series. System designers must note that an output voltage > 60Vdc will not meet SELV requirements, and can be dangerous. Under no circumstances the total voltage should exceed 150Vdc. When the total voltage exceeds the SELV limit of 60Vdc, a protective barrier against touching the output terminals must be installed, together with connecting the output ground (-V2 DC Return) terminal of power supply to Earth ground. See Figure 5. 2. Series Operation Figure 5. Series Operation Diagram An ORing diode in reverse bias must be added across output terminals of each power supply. This is to prevent -V voltage being applied to other power supply in fault conditions such as short circuit across load. During a short circuit, -V1 & +V1 will be connected across +V2 & -V2 which means the 2 power supplies output will be connected in opposite polarity and will cause damage to the power supplies. With diode connected in reverse bias across the output, the voltage across each power supply output will be restricted to one diode drop – approximately 0.7V to 1.0V. It is recommended to provide sufficient voltage de-rating for diodes with 2x the voltage rating of series output voltage.
  • 11. 11 Example: When two 24V power supplies are connected in series, the total voltage will be 48V. During a short circuit, the current through the ORing diodes will be very high. Therefore, use ORing diodes with reverse voltage rating of at least 2 × 48 = 96V. 2. Series Operation Figure 6. Non-monotonic Turn-on Waveform When power supplies are used in parallel and series operations, parameters such as EMI, inrush current, leakage current, PARD, and startup time will be different compared to a standalone power supply. The system designer must consider these parameters on a system level.
  • 12. 12 To learn more how to execute series and parallel operation, kindly contact your local distributor or please visit www.DeltaPSU.com for more information and other types of Delta power supplies. Ask Question Learn More Send Me More Article
  • 13. Smarter. Greener. Together. www.DeltaPSU.com To be the first person who know about our new product and other news update, subscribe to DeltaPSU newsletter now. Click Subscribe

Editor's Notes

  1. 1