The CMO Survey - Highlights and Insights Report - Spring 2024
Daniel Cooper - November 11, 2011
1. Holland BPW P21 Decision:
Internal or External Resources
ELECTRIC TRANSMISSION CONSIDERATIONS IN
POWER SUPPLY DECISIONS
Jennings, Strouss & Salmon
2. HBPW P21 Decision – Electric Transmission
Overview of Presentation
Everything you never wanted to know about Electric
Transmission in one presentation:
If base load generation is the goal, why discuss transmission?
What is Electric Transmission?
A Short History of Electric Transmission
Transmission today – ISOs, RTOs and more
Transmission considerations in electric power supply decisions
– local resource or remote resource?
Giving away the ending – transmission considerations are
almost certain to be a factor, but unlikely to the major
factor in the P21 Decision
Jennings, Strouss & Salmon 2
3. HBPW P21 Decision – Electric Transmission
Why Discuss Transmission in the P21 Decision Process?
Electric Transmission can be the means to the end
Think of a roadway. It isn’t where you want to go, but it can
get you there
Some generating resources can’t or won’t be placed
inside Holland.
For those external resources, electric transmission is needed
to deliver the power and energy
Electric transmission can add economic, logistical and
administrative considerations that become part of the
electric power supply decision
Jennings, Strouss & Salmon 3
4. HBPW P21 Decision – Electric Transmission
What is Electric Transmission?
Electric Transmission is designed to move large amounts
of electric energy over long distances
Physically, electric transmission structures and wires are
taller and heavier
The operating voltage for electric transmission is higher
This allows the movement of larger amounts of electricity
more efficiently
This also requires more equipment to raise the voltage for
transmission, then lower it for use by the customer
Jennings, Strouss & Salmon 4
5. HBPW P21 Decision – Electric Transmission
What is Electric Transmission?
345 kv
Jennings, Strouss & Salmon 5
6. HBPW P21 Decision – Electric Transmission
A Short History – the Early Days
At the start of the electric industry, electric transmission
didn’t exist
The earliest electric systems were built for towns and
cities
The generation and load were close together, so the
same lines and voltages (or close to it) could be used to
generate and distribute the electricity
This made for a simple system
Jennings, Strouss & Salmon 6
7. HBPW P21 Decision – Electric Transmission
The Early Days – A Simple System Analogy
Note: to make this accurate, the lake has no storage, so pumping must match use
Jennings, Strouss & Salmon 7
8. HBPW P21 Decision – Electric Transmission
A Short History – Larger Generators call for Transmission
Electric loads increased as more areas were served by
electric utilities
The electric industry entered a period of positive
economies of scale for electric generators – larger plants
cost less per kilowatt to build and produced electricity
more cheaply than smaller plants
Due to land use, environmental and fuel supply
considerations, the larger generators were generally built
at sites remote from the loads
This resulted in need for more efficient, higher capacity
lines – so electric transmission was built
Jennings, Strouss & Salmon 8
9. HBPW P21 Decision – Electric Transmission
A Short History - Larger Generators were Built Remotely
Jennings, Strouss & Salmon 9
10. HBPW P21 Decision – Electric Transmission
A Short History – the Interconnected System Appears
As electric utilities expanded and more lines were built to
connect generators, electric utilities began to
interconnect their transmission systems with others
This allowed utilities to support each other when
generators dropped off line
This also allowed utilities to make both short term and
longer term sales between each other with economic
benefits to both utilities and their customers
The interconnection process continued to today’s tightly-
interconnected systems
Jennings, Strouss & Salmon 10
11. HBPW P21 Decision – Electric Transmission
A Short History – the Interconnected System Appears
Jennings, Strouss & Salmon 11
12. HBPW P21 Decision – Electric Transmission
A Short History – with Complexity Comes Complication
The creation of the interconnected transmission grid gave
substantial benefits, but also created concerns
As utilities began to compete to sell electricity to other than
their retail customers, control of transmission became an
advantage and a potential competitive tool (or weapon)
The flip side of reliability – just as utilities could help support
each other, a collapsing utility system could drag others down
As the network became more complex, a single utility could no
longer develop the most effective and reliable transmission
system plan
So a broader solution was developed
Jennings, Strouss & Salmon 12
13. HBPW P21 Decision – Electric Transmission
Regional Transmission Overseers – ISOs and RTOs
The concerns about discrimination by transmission
owners, network reliability, and efficient planning led to a
search for regional solutions
The idea of an independent regional transmission entity
was one of those solutions
This type of organization is called a Regional Transmission
Operator
The Midwest Independent System Operator – MISO –
was created as the transmission overseer for Michigan
and much of this part of the United States
Jennings, Strouss & Salmon 13
15. HBPW P21 Decision – Electric Transmission
Regional Transmission Overseers – MISO
MISO’s original mission was limited to transmission
MISO became the Transmission Provider for all of the
transmission customers in MISO’s footprint
Even the transmission owners who joined MISO buy transmission
service from MISO for their bundled customers
The transmission owning MISO members agreed to allow
MISO to tell them how to operate their systems and collect
the transmission revenues
In return, MISO pays the transmission owners the costs of owning
and operating their transmission
Then MISO’s mission expanded, affecting generation
decisions…
Jennings, Strouss & Salmon 15
16. HBPW P21 Decision – Electric Transmission
Regional Transmission Overseers – MISO
In following an economic theory on how an electricity
market should operate, MISO’s role expanded so MISO
moved into the middle of all electric transactions in its
footprint
Pragmatically, all electric energy and system support services
generated are sold to MISO
All users of electricity buy their needs from MISO, either
directly or through their local utility
The only significant exception to this is electricity
generated and used within a municipality like Holland
Jennings, Strouss & Salmon 16
17. HBPW P21 Decision – Electric Transmission
Regional Transmission Overseers – MISO
MISO’s energy market isn’t a cost-based market
MISO’s energy prices are based on supplier offer costs which
may not be actual production costs
MISO charges all energy purchasers the marginal (highest
accepted offer) cost of energy needed to meet load
All suppliers are paid the marginal price, regardless of cost
All purchasers pay that marginal cost
This means a single high-cost generator can (and often does)
drive the purchased energy cost far above the actual average
production cost of units supplying the energy
Owning a resource can provide a hedge against MISO energy
prices
Jennings, Strouss & Salmon 17
18. HBPW P21 Decision – Electric Transmission
Regional Transmission Overseers – MISO
MISO’s position between Holland’s customers and
resources outside of Holland’s system is a factor to
consider in power supply decisions
Resources located outside of Holland BPW’s system are
subject to administrative and operating requirements that
won’t apply to a resource inside of Holland’s system
MISO also charges for transmission losses across its system.
Those external losses aren’t a factor for a generator inside of
Holland
MISO provides a reliable highway to a broad area, allowing far
more generating resource options than available internally
Jennings, Strouss & Salmon 18
19. HBPW P21 Decision – Electric Transmission
Regional Transmission Overseers – MISO
MISO has proposed a new capacity market and resource
requirements program
MISO has filed this plan with the Federal Energy Regulatory
Commission (FERC). FERC is considering the plan
One part of MISO’s capacity proposal is to have a potential
additional delivery charge for generating resources that are
outside of a utility’s home Local Resource Zone
The Local Resource Zone for Holland BPW is lower Michigan
This adds cost risk for Holland for resources outside of
Michigan
Until FERC rules on MISO’s proposal, the impact of this factor
can’t be quantified
Jennings, Strouss & Salmon 19
20. HBPW P21 Decision – Electric Transmission
System Reliability Requirements
There is a body of reliability standards requirements that
applies to all entities that affect the bulk electric system
(the transmission system)
While the same rules apply to all generating resources,
the location of the resource may have an effect on
Holland BPW.
A large resource internal to Holland’s system may make
Holland BPW subject to additional reliability standards
This depends on many factors and may or may not be a
consideration in power supply choices
Jennings, Strouss & Salmon 20
21. HBPW P21 Decision – Electric Transmission
Bringing it Home – Transmission Considerations for P21
There are considerations related to transmission that
may be factors in the choice of a base load generating
resource for Holland BPW
The main positive consideration is that the electric
transmission system provides the opportunity to gain
access to resources that can’t or shouldn’t be built in
Holland
This provides an option to obtain additional fuel diversity,
economies of scale through joint ownership arrangements,
and access to resources not available locally for whatever
reason
Jennings, Strouss & Salmon 21
22. HBPW P21 Decision – Electric Transmission
Bringing it Home – Transmission Considerations for P21
One transmission consideration – reliability - is a very
small concern
As shown on the system map, there are many alternative
paths for electric power, so line outages generally have little
effect
While there have been outages of wide parts of the bulk
transmission system, those have been rare, with much effort
to see they don’t happen again
The main concern for delivery of external resources for
Holland is the loss of the external substation that ties Holland
to the bulk transmission system
Jennings, Strouss & Salmon 22
23. HBPW P21 Decision – Electric Transmission
Much Redundancy between Holland and External Resources
Jennings, Strouss & Salmon 23
24. HBPW P21 Decision – Electric Transmission
The Greatest Interruption Risk is the HBPW/Transmission Connection
Jennings, Strouss & Salmon 24
25. HBPW P21 Decision – Electric Transmission
Bringing it Home – Transmission Considerations for P21
MISO – the Transmission Provider for this part of the
country – is a factor
MISO will likely add some extra administrative costs for
resources external to Holland
MISO will add transmission loss costs for resources external to
Holland
MISO’s capacity market and resource requirements proposal
may add costs for resources outside of lower Michigan
MISO will assure reasonable access to external resources
MISO will make it easy to sell surplus energy from external
resources. That may not be true for internal resources
Jennings, Strouss & Salmon 25
26. HBPW P21 Decision – Electric Transmission
Bringing it Home – Transmission Considerations for P21
Bulk electric transmission system reliability
considerations may favor external resources
A large generating resource inside of Holland may result in
Holland being subject to additional reliability standards
requirements
The same is not true for external resources
This area is subject to many other factors that will affect
Holland BPW’s reliability standards obligations
The ultimate conclusion on Holland BPW’s reliability standards
obligations will determine whether or not they are a factor in
the P21 Decision.
Jennings, Strouss & Salmon 26
27. HBPW P21 Decision – Electric Transmission
Bringing it Home – Transmission Considerations for P21
In the end, the impact of electric transmission
considerations on the P21 Decision will likely end up
being an incremental cost factor difference between
internal and external resources
There may also be an incremental external transmission
cost difference between different external resources
As an incremental cost factor, electric transmission
considerations may sway, but won’t determine, the final
decision
Jennings, Strouss & Salmon 27
28. HBPW P21 Decision – Electric Transmission
Transmission Considerations
for the P21 Decision
QUESTIONS AND DISCUSSION
Jennings, Strouss & Salmon