SlideShare a Scribd company logo
1 of 28
Download to read offline
Holland BPW P21 Decision:
          Internal or External Resources

                   ELECTRIC TRANSMISSION CONSIDERATIONS IN
                           POWER SUPPLY DECISIONS




Jennings, Strouss & Salmon
HBPW P21 Decision – Electric Transmission
                      Overview of Presentation


  Everything you never wanted to know about Electric
     Transmission in one presentation:
      If base load generation is the goal, why discuss transmission?
      What is Electric Transmission?
      A Short History of Electric Transmission
      Transmission today – ISOs, RTOs and more
      Transmission considerations in electric power supply decisions
       – local resource or remote resource?
  Giving away the ending – transmission considerations are
     almost certain to be a factor, but unlikely to the major
     factor in the P21 Decision

Jennings, Strouss & Salmon                                              2
HBPW P21 Decision – Electric Transmission
     Why Discuss Transmission in the P21 Decision Process?


  Electric Transmission can be the means to the end
        Think of a roadway. It isn’t where you want to go, but it can
         get you there
  Some generating resources can’t or won’t be placed
     inside Holland.
        For those external resources, electric transmission is needed
         to deliver the power and energy
  Electric transmission can add economic, logistical and
     administrative considerations that become part of the
     electric power supply decision

Jennings, Strouss & Salmon                                               3
HBPW P21 Decision – Electric Transmission
                   What is Electric Transmission?


  Electric Transmission is designed to move large amounts
   of electric energy over long distances
  Physically, electric transmission structures and wires are
   taller and heavier
  The operating voltage for electric transmission is higher
      This allows the movement of larger amounts of electricity
       more efficiently
      This also requires more equipment to raise the voltage for
       transmission, then lower it for use by the customer



Jennings, Strouss & Salmon                                          4
HBPW P21 Decision – Electric Transmission
                   What is Electric Transmission?




                       345 kv



Jennings, Strouss & Salmon                                 5
HBPW P21 Decision – Electric Transmission
                   A Short History – the Early Days


  At the start of the electric industry, electric transmission
   didn’t exist
  The earliest electric systems were built for towns and
   cities
  The generation and load were close together, so the
   same lines and voltages (or close to it) could be used to
   generate and distribute the electricity
  This made for a simple system




Jennings, Strouss & Salmon                                        6
HBPW P21 Decision – Electric Transmission
                The Early Days – A Simple System Analogy


    Note: to make this accurate, the lake has no storage, so pumping must match use




Jennings, Strouss & Salmon                                                        7
HBPW P21 Decision – Electric Transmission
     A Short History – Larger Generators call for Transmission


  Electric loads increased as more areas were served by
   electric utilities
  The electric industry entered a period of positive
   economies of scale for electric generators – larger plants
   cost less per kilowatt to build and produced electricity
   more cheaply than smaller plants
  Due to land use, environmental and fuel supply
   considerations, the larger generators were generally built
   at sites remote from the loads
  This resulted in need for more efficient, higher capacity
   lines – so electric transmission was built

Jennings, Strouss & Salmon                                       8
HBPW P21 Decision – Electric Transmission
      A Short History - Larger Generators were Built Remotely




Jennings, Strouss & Salmon                                      9
HBPW P21 Decision – Electric Transmission
        A Short History – the Interconnected System Appears


  As electric utilities expanded and more lines were built to
   connect generators, electric utilities began to
   interconnect their transmission systems with others
  This allowed utilities to support each other when
   generators dropped off line
  This also allowed utilities to make both short term and
   longer term sales between each other with economic
   benefits to both utilities and their customers
  The interconnection process continued to today’s tightly-
   interconnected systems

Jennings, Strouss & Salmon                                     10
HBPW P21 Decision – Electric Transmission
        A Short History – the Interconnected System Appears




Jennings, Strouss & Salmon                                    11
HBPW P21 Decision – Electric Transmission
         A Short History – with Complexity Comes Complication


  The creation of the interconnected transmission grid gave
     substantial benefits, but also created concerns
      As utilities began to compete to sell electricity to other than
       their retail customers, control of transmission became an
       advantage and a potential competitive tool (or weapon)
      The flip side of reliability – just as utilities could help support
       each other, a collapsing utility system could drag others down
      As the network became more complex, a single utility could no
       longer develop the most effective and reliable transmission
       system plan
  So a broader solution was developed

Jennings, Strouss & Salmon                                               12
HBPW P21 Decision – Electric Transmission
         Regional Transmission Overseers – ISOs and RTOs


  The concerns about discrimination by transmission
   owners, network reliability, and efficient planning led to a
   search for regional solutions
  The idea of an independent regional transmission entity
   was one of those solutions
        This type of organization is called a Regional Transmission
         Operator
  The Midwest Independent System Operator – MISO –
     was created as the transmission overseer for Michigan
     and much of this part of the United States

Jennings, Strouss & Salmon                                             13
HBPW P21 Decision – Electric Transmission
                Regional Transmission Overseers – MISO




Jennings, Strouss & Salmon                                 14
HBPW P21 Decision – Electric Transmission
                Regional Transmission Overseers – MISO


  MISO’s original mission was limited to transmission
    MISO became the Transmission Provider for all of the
     transmission customers in MISO’s footprint
      Even the transmission owners who joined MISO buy transmission
       service from MISO for their bundled customers
    The transmission owning MISO members agreed to allow
     MISO to tell them how to operate their systems and collect
     the transmission revenues
      In return, MISO pays the transmission owners the costs of owning
       and operating their transmission
  Then MISO’s mission expanded, affecting generation
     decisions…

Jennings, Strouss & Salmon                                            15
HBPW P21 Decision – Electric Transmission
                Regional Transmission Overseers – MISO


  In following an economic theory on how an electricity
     market should operate, MISO’s role expanded so MISO
     moved into the middle of all electric transactions in its
     footprint
      Pragmatically, all electric energy and system support services
       generated are sold to MISO
      All users of electricity buy their needs from MISO, either
       directly or through their local utility
  The only significant exception to this is electricity
     generated and used within a municipality like Holland

Jennings, Strouss & Salmon                                              16
HBPW P21 Decision – Electric Transmission
                Regional Transmission Overseers – MISO


  MISO’s energy market isn’t a cost-based market
    MISO’s energy prices are based on supplier offer costs which
     may not be actual production costs
    MISO charges all energy purchasers the marginal (highest
     accepted offer) cost of energy needed to meet load
      All suppliers are paid the marginal price, regardless of cost
      All purchasers pay that marginal cost
    This means a single high-cost generator can (and often does)
     drive the purchased energy cost far above the actual average
     production cost of units supplying the energy
    Owning a resource can provide a hedge against MISO energy
     prices

Jennings, Strouss & Salmon                                             17
HBPW P21 Decision – Electric Transmission
                Regional Transmission Overseers – MISO


  MISO’s position between Holland’s customers and
     resources outside of Holland’s system is a factor to
     consider in power supply decisions
      Resources located outside of Holland BPW’s system are
       subject to administrative and operating requirements that
       won’t apply to a resource inside of Holland’s system
      MISO also charges for transmission losses across its system.
       Those external losses aren’t a factor for a generator inside of
       Holland
      MISO provides a reliable highway to a broad area, allowing far
       more generating resource options than available internally

Jennings, Strouss & Salmon                                               18
HBPW P21 Decision – Electric Transmission
                Regional Transmission Overseers – MISO


  MISO has proposed a new capacity market and resource
     requirements program
      MISO has filed this plan with the Federal Energy Regulatory
       Commission (FERC). FERC is considering the plan
      One part of MISO’s capacity proposal is to have a potential
       additional delivery charge for generating resources that are
       outside of a utility’s home Local Resource Zone
      The Local Resource Zone for Holland BPW is lower Michigan
      This adds cost risk for Holland for resources outside of
       Michigan
      Until FERC rules on MISO’s proposal, the impact of this factor
       can’t be quantified

Jennings, Strouss & Salmon                                              19
HBPW P21 Decision – Electric Transmission
                   System Reliability Requirements


  There is a body of reliability standards requirements that
   applies to all entities that affect the bulk electric system
   (the transmission system)
  While the same rules apply to all generating resources,
   the location of the resource may have an effect on
   Holland BPW.
      A large resource internal to Holland’s system may make
       Holland BPW subject to additional reliability standards
      This depends on many factors and may or may not be a
       consideration in power supply choices


Jennings, Strouss & Salmon                                        20
HBPW P21 Decision – Electric Transmission
      Bringing it Home – Transmission Considerations for P21


  There are considerations related to transmission that
   may be factors in the choice of a base load generating
   resource for Holland BPW
  The main positive consideration is that the electric
   transmission system provides the opportunity to gain
   access to resources that can’t or shouldn’t be built in
   Holland
        This provides an option to obtain additional fuel diversity,
         economies of scale through joint ownership arrangements,
         and access to resources not available locally for whatever
         reason


Jennings, Strouss & Salmon                                              21
HBPW P21 Decision – Electric Transmission
      Bringing it Home – Transmission Considerations for P21


  One transmission consideration – reliability - is a very
     small concern
      As shown on the system map, there are many alternative
       paths for electric power, so line outages generally have little
       effect
      While there have been outages of wide parts of the bulk
       transmission system, those have been rare, with much effort
       to see they don’t happen again
      The main concern for delivery of external resources for
       Holland is the loss of the external substation that ties Holland
       to the bulk transmission system

Jennings, Strouss & Salmon                                                22
HBPW P21 Decision – Electric Transmission
  Much Redundancy between Holland and External Resources




Jennings, Strouss & Salmon                             23
HBPW P21 Decision – Electric Transmission
    The Greatest Interruption Risk is the HBPW/Transmission Connection




Jennings, Strouss & Salmon                                               24
HBPW P21 Decision – Electric Transmission
      Bringing it Home – Transmission Considerations for P21


  MISO – the Transmission Provider for this part of the
     country – is a factor
      MISO will likely add some extra administrative costs for
       resources external to Holland
      MISO will add transmission loss costs for resources external to
       Holland
      MISO’s capacity market and resource requirements proposal
       may add costs for resources outside of lower Michigan
      MISO will assure reasonable access to external resources

      MISO will make it easy to sell surplus energy from external
       resources. That may not be true for internal resources

Jennings, Strouss & Salmon                                           25
HBPW P21 Decision – Electric Transmission
      Bringing it Home – Transmission Considerations for P21


  Bulk electric transmission system reliability
     considerations may favor external resources
      A large generating resource inside of Holland may result in
       Holland being subject to additional reliability standards
       requirements
      The same is not true for external resources

      This area is subject to many other factors that will affect
       Holland BPW’s reliability standards obligations
      The ultimate conclusion on Holland BPW’s reliability standards
       obligations will determine whether or not they are a factor in
       the P21 Decision.

Jennings, Strouss & Salmon                                          26
HBPW P21 Decision – Electric Transmission
      Bringing it Home – Transmission Considerations for P21


  In the end, the impact of electric transmission
   considerations on the P21 Decision will likely end up
   being an incremental cost factor difference between
   internal and external resources
  There may also be an incremental external transmission
   cost difference between different external resources
  As an incremental cost factor, electric transmission
   considerations may sway, but won’t determine, the final
   decision


Jennings, Strouss & Salmon                                     27
HBPW P21 Decision – Electric Transmission
              Transmission Considerations
                  for the P21 Decision


               QUESTIONS AND DISCUSSION




Jennings, Strouss & Salmon

More Related Content

What's hot

Green Power Superhighways
Green Power SuperhighwaysGreen Power Superhighways
Green Power Superhighwaysmegglest
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...paperpublications3
 
Power Purchase Agreement Workshop
Power Purchase Agreement WorkshopPower Purchase Agreement Workshop
Power Purchase Agreement WorkshopRaluca Dirjan
 
An analysis of california’s electric utility industry introducing competitio...
An analysis of california’s electric utility industry  introducing competitio...An analysis of california’s electric utility industry  introducing competitio...
An analysis of california’s electric utility industry introducing competitio...Blake Wedekind
 
Ontario’s renewable energy, smart grid and EV policy
Ontario’s renewable energy, smart grid and EV policyOntario’s renewable energy, smart grid and EV policy
Ontario’s renewable energy, smart grid and EV policySuncharge Corporation
 
Improving Distribution System Performance in Deregulated Electricity Industry...
Improving Distribution System Performance in Deregulated Electricity Industry...Improving Distribution System Performance in Deregulated Electricity Industry...
Improving Distribution System Performance in Deregulated Electricity Industry...IOSRJEEE
 
High Step-Up Converter with Voltage Multiplier Module for Renewable Energy Sy...
High Step-Up Converter with Voltage Multiplier Module for Renewable Energy Sy...High Step-Up Converter with Voltage Multiplier Module for Renewable Energy Sy...
High Step-Up Converter with Voltage Multiplier Module for Renewable Energy Sy...IJRES Journal
 
Practical Problems in Implementation of Open Access : Discom Perspective
Practical Problems in Implementation of Open Access : Discom PerspectivePractical Problems in Implementation of Open Access : Discom Perspective
Practical Problems in Implementation of Open Access : Discom PerspectiveIPPAI
 
AC Distribution System in Bangladesh
AC Distribution System in BangladeshAC Distribution System in Bangladesh
AC Distribution System in BangladeshRidwanul Hoque
 
The Experience of the Energy Regulatory Commission
The Experience of the Energy Regulatory CommissionThe Experience of the Energy Regulatory Commission
The Experience of the Energy Regulatory Commissionelectricitygovernance
 
Course on Regulation and Sustainable Energy in Developing Countries - Session 2
Course on Regulation and Sustainable Energy in Developing Countries - Session 2Course on Regulation and Sustainable Energy in Developing Countries - Session 2
Course on Regulation and Sustainable Energy in Developing Countries - Session 2Leonardo ENERGY
 

What's hot (17)

Green Power Superhighways
Green Power SuperhighwaysGreen Power Superhighways
Green Power Superhighways
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
Hydrolink yous strategic_partner_ahead
Hydrolink yous strategic_partner_aheadHydrolink yous strategic_partner_ahead
Hydrolink yous strategic_partner_ahead
 
Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...
 
Wesm 101 20151230
Wesm 101 20151230Wesm 101 20151230
Wesm 101 20151230
 
Power Purchase Agreement Workshop
Power Purchase Agreement WorkshopPower Purchase Agreement Workshop
Power Purchase Agreement Workshop
 
Mike Montoya - SCE
Mike Montoya - SCEMike Montoya - SCE
Mike Montoya - SCE
 
An analysis of california’s electric utility industry introducing competitio...
An analysis of california’s electric utility industry  introducing competitio...An analysis of california’s electric utility industry  introducing competitio...
An analysis of california’s electric utility industry introducing competitio...
 
Ontario’s renewable energy, smart grid and EV policy
Ontario’s renewable energy, smart grid and EV policyOntario’s renewable energy, smart grid and EV policy
Ontario’s renewable energy, smart grid and EV policy
 
Improving Distribution System Performance in Deregulated Electricity Industry...
Improving Distribution System Performance in Deregulated Electricity Industry...Improving Distribution System Performance in Deregulated Electricity Industry...
Improving Distribution System Performance in Deregulated Electricity Industry...
 
B0451217
B0451217B0451217
B0451217
 
High Step-Up Converter with Voltage Multiplier Module for Renewable Energy Sy...
High Step-Up Converter with Voltage Multiplier Module for Renewable Energy Sy...High Step-Up Converter with Voltage Multiplier Module for Renewable Energy Sy...
High Step-Up Converter with Voltage Multiplier Module for Renewable Energy Sy...
 
Practical Problems in Implementation of Open Access : Discom Perspective
Practical Problems in Implementation of Open Access : Discom PerspectivePractical Problems in Implementation of Open Access : Discom Perspective
Practical Problems in Implementation of Open Access : Discom Perspective
 
2017 Policy Forum - Panelist slides combined
2017 Policy Forum - Panelist slides combined2017 Policy Forum - Panelist slides combined
2017 Policy Forum - Panelist slides combined
 
AC Distribution System in Bangladesh
AC Distribution System in BangladeshAC Distribution System in Bangladesh
AC Distribution System in Bangladesh
 
The Experience of the Energy Regulatory Commission
The Experience of the Energy Regulatory CommissionThe Experience of the Energy Regulatory Commission
The Experience of the Energy Regulatory Commission
 
Course on Regulation and Sustainable Energy in Developing Countries - Session 2
Course on Regulation and Sustainable Energy in Developing Countries - Session 2Course on Regulation and Sustainable Energy in Developing Countries - Session 2
Course on Regulation and Sustainable Energy in Developing Countries - Session 2
 

Viewers also liked

Martin Kushler - November 17, 2011
Martin Kushler - November 17, 2011Martin Kushler - November 17, 2011
Martin Kushler - November 17, 2011p21decision
 
Julie Baldwin - October 6, 2011
Julie Baldwin - October 6, 2011Julie Baldwin - October 6, 2011
Julie Baldwin - October 6, 2011p21decision
 
Bill Carlson - October 13, 2011
Bill Carlson - October 13, 2011Bill Carlson - October 13, 2011
Bill Carlson - October 13, 2011p21decision
 
Technology in Our Lower School
Technology in Our Lower SchoolTechnology in Our Lower School
Technology in Our Lower SchoolKimberly Bushman
 
Janet Gellici - October 6, 2011
Janet Gellici - October 6, 2011Janet Gellici - October 6, 2011
Janet Gellici - October 6, 2011p21decision
 
John Doggett - December 13, 2011
John Doggett - December 13, 2011John Doggett - December 13, 2011
John Doggett - December 13, 2011p21decision
 
Doug Carter - October 20
Doug Carter - October 20Doug Carter - October 20
Doug Carter - October 20p21decision
 
Catherine Elder - October 6, 2011
Catherine Elder - October 6, 2011Catherine Elder - October 6, 2011
Catherine Elder - October 6, 2011p21decision
 
Randy Kuipers - October 6, 2011
Randy Kuipers - October 6, 2011Randy Kuipers - October 6, 2011
Randy Kuipers - October 6, 2011p21decision
 
Con información a nivel de distritos y centros poblados de san roque
Con información a nivel de distritos y centros poblados de san roqueCon información a nivel de distritos y centros poblados de san roque
Con información a nivel de distritos y centros poblados de san roqueHECTOR MOISES CHAVEZ VARGAS
 
Holland Board of Public Works P21 Communications Plan
Holland Board of Public Works P21 Communications PlanHolland Board of Public Works P21 Communications Plan
Holland Board of Public Works P21 Communications Planp21decision
 
Geometria Cuarto Gradon
Geometria  Cuarto GradonGeometria  Cuarto Gradon
Geometria Cuarto Gradonyoemar1969
 
Visual Documentation Of My Creative Spectrum
Visual Documentation Of My Creative SpectrumVisual Documentation Of My Creative Spectrum
Visual Documentation Of My Creative SpectrumKatieBonesz
 
James R. Connell P.E. - October 13, 2011
James R. Connell P.E. - October 13, 2011James R. Connell P.E. - October 13, 2011
James R. Connell P.E. - October 13, 2011p21decision
 
Reponsive web design (HTML5 + css3)
Reponsive web design (HTML5 + css3)Reponsive web design (HTML5 + css3)
Reponsive web design (HTML5 + css3)Sandip Jadhav
 
Graph database & neo4j
Graph database & neo4jGraph database & neo4j
Graph database & neo4jSandip Jadhav
 
Socializing your application ( Facebook )
Socializing your application ( Facebook )Socializing your application ( Facebook )
Socializing your application ( Facebook )Sandip Jadhav
 
Beginning Coding Vocabulary for Elementary Students
Beginning Coding Vocabulary for Elementary StudentsBeginning Coding Vocabulary for Elementary Students
Beginning Coding Vocabulary for Elementary StudentsKimberly Bushman
 

Viewers also liked (19)

Martin Kushler - November 17, 2011
Martin Kushler - November 17, 2011Martin Kushler - November 17, 2011
Martin Kushler - November 17, 2011
 
Julie Baldwin - October 6, 2011
Julie Baldwin - October 6, 2011Julie Baldwin - October 6, 2011
Julie Baldwin - October 6, 2011
 
Bill Carlson - October 13, 2011
Bill Carlson - October 13, 2011Bill Carlson - October 13, 2011
Bill Carlson - October 13, 2011
 
Technology in Our Lower School
Technology in Our Lower SchoolTechnology in Our Lower School
Technology in Our Lower School
 
Janet Gellici - October 6, 2011
Janet Gellici - October 6, 2011Janet Gellici - October 6, 2011
Janet Gellici - October 6, 2011
 
John Doggett - December 13, 2011
John Doggett - December 13, 2011John Doggett - December 13, 2011
John Doggett - December 13, 2011
 
Doug Carter - October 20
Doug Carter - October 20Doug Carter - October 20
Doug Carter - October 20
 
Catherine Elder - October 6, 2011
Catherine Elder - October 6, 2011Catherine Elder - October 6, 2011
Catherine Elder - October 6, 2011
 
Randy Kuipers - October 6, 2011
Randy Kuipers - October 6, 2011Randy Kuipers - October 6, 2011
Randy Kuipers - October 6, 2011
 
Idiem fitting ppr
Idiem   fitting pprIdiem   fitting ppr
Idiem fitting ppr
 
Con información a nivel de distritos y centros poblados de san roque
Con información a nivel de distritos y centros poblados de san roqueCon información a nivel de distritos y centros poblados de san roque
Con información a nivel de distritos y centros poblados de san roque
 
Holland Board of Public Works P21 Communications Plan
Holland Board of Public Works P21 Communications PlanHolland Board of Public Works P21 Communications Plan
Holland Board of Public Works P21 Communications Plan
 
Geometria Cuarto Gradon
Geometria  Cuarto GradonGeometria  Cuarto Gradon
Geometria Cuarto Gradon
 
Visual Documentation Of My Creative Spectrum
Visual Documentation Of My Creative SpectrumVisual Documentation Of My Creative Spectrum
Visual Documentation Of My Creative Spectrum
 
James R. Connell P.E. - October 13, 2011
James R. Connell P.E. - October 13, 2011James R. Connell P.E. - October 13, 2011
James R. Connell P.E. - October 13, 2011
 
Reponsive web design (HTML5 + css3)
Reponsive web design (HTML5 + css3)Reponsive web design (HTML5 + css3)
Reponsive web design (HTML5 + css3)
 
Graph database & neo4j
Graph database & neo4jGraph database & neo4j
Graph database & neo4j
 
Socializing your application ( Facebook )
Socializing your application ( Facebook )Socializing your application ( Facebook )
Socializing your application ( Facebook )
 
Beginning Coding Vocabulary for Elementary Students
Beginning Coding Vocabulary for Elementary StudentsBeginning Coding Vocabulary for Elementary Students
Beginning Coding Vocabulary for Elementary Students
 

Similar to Daniel Cooper - November 11, 2011

Analysis of Community Microgrids: The path to resilient and sustainable commu...
Analysis of Community Microgrids: The path to resilient and sustainable commu...Analysis of Community Microgrids: The path to resilient and sustainable commu...
Analysis of Community Microgrids: The path to resilient and sustainable commu...Clean Coalition
 
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy GenerationGBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy GenerationToronto 2030 District
 
Why And Why Not To Go For HVDC?
Why And Why Not To Go For HVDC?Why And Why Not To Go For HVDC?
Why And Why Not To Go For HVDC?IOSR Journals
 
NPWZ Energy Storage Solution
NPWZ Energy Storage SolutionNPWZ Energy Storage Solution
NPWZ Energy Storage Solutionnpwzpr
 
Neah Power Systems White Paper
Neah Power Systems White PaperNeah Power Systems White Paper
Neah Power Systems White Papernpwzpr
 
Ctws ocean energy lovely
Ctws ocean energy lovelyCtws ocean energy lovely
Ctws ocean energy lovelyblemon
 
The Intelligent Energy System Infrastructure For The Future
The Intelligent Energy System Infrastructure For The FutureThe Intelligent Energy System Infrastructure For The Future
The Intelligent Energy System Infrastructure For The FutureGlenn Klith Andersen
 
Hector Pearson, National Grid, NAAONB Conference 2015
Hector Pearson, National Grid, NAAONB Conference 2015Hector Pearson, National Grid, NAAONB Conference 2015
Hector Pearson, National Grid, NAAONB Conference 2015NAAONB landscapesforlife
 
2001 fp5 brochure_energy_env
2001 fp5 brochure_energy_env2001 fp5 brochure_energy_env
2001 fp5 brochure_energy_envngocdung04
 
Work example: wind energy and storage 2012
Work example: wind energy and storage 2012Work example: wind energy and storage 2012
Work example: wind energy and storage 2012Paisha Coffey
 
Work example; wind energy and storage 2012
Work example; wind energy and storage 2012Work example; wind energy and storage 2012
Work example; wind energy and storage 2012Paisha Coffey
 
Hubert lemmens | Netbalans bij een wisselende energieproductie
Hubert lemmens  |  Netbalans bij een wisselende energieproductieHubert lemmens  |  Netbalans bij een wisselende energieproductie
Hubert lemmens | Netbalans bij een wisselende energieproductieGreenbridge nv
 
EEI State of Distribution, 2012
EEI State of Distribution, 2012EEI State of Distribution, 2012
EEI State of Distribution, 2012Paul De Martini
 
rice_solar_panels
rice_solar_panelsrice_solar_panels
rice_solar_panelsMatt Rice
 
Optimal Placement of Distributed Generation on Radial Distribution System for...
Optimal Placement of Distributed Generation on Radial Distribution System for...Optimal Placement of Distributed Generation on Radial Distribution System for...
Optimal Placement of Distributed Generation on Radial Distribution System for...IJMER
 

Similar to Daniel Cooper - November 11, 2011 (20)

Analysis of Community Microgrids: The path to resilient and sustainable commu...
Analysis of Community Microgrids: The path to resilient and sustainable commu...Analysis of Community Microgrids: The path to resilient and sustainable commu...
Analysis of Community Microgrids: The path to resilient and sustainable commu...
 
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy GenerationGBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
 
Why And Why Not To Go For HVDC?
Why And Why Not To Go For HVDC?Why And Why Not To Go For HVDC?
Why And Why Not To Go For HVDC?
 
F010143843
F010143843F010143843
F010143843
 
Unit1
Unit1Unit1
Unit1
 
NPWZ Energy Storage Solution
NPWZ Energy Storage SolutionNPWZ Energy Storage Solution
NPWZ Energy Storage Solution
 
Neah Power Systems White Paper
Neah Power Systems White PaperNeah Power Systems White Paper
Neah Power Systems White Paper
 
Ctws ocean energy lovely
Ctws ocean energy lovelyCtws ocean energy lovely
Ctws ocean energy lovely
 
The Intelligent Energy System Infrastructure For The Future
The Intelligent Energy System Infrastructure For The FutureThe Intelligent Energy System Infrastructure For The Future
The Intelligent Energy System Infrastructure For The Future
 
DISTRIBUTE GENERATION
DISTRIBUTE GENERATIONDISTRIBUTE GENERATION
DISTRIBUTE GENERATION
 
00 peg71-120dpi
00 peg71-120dpi00 peg71-120dpi
00 peg71-120dpi
 
Hector Pearson, National Grid, NAAONB Conference 2015
Hector Pearson, National Grid, NAAONB Conference 2015Hector Pearson, National Grid, NAAONB Conference 2015
Hector Pearson, National Grid, NAAONB Conference 2015
 
2001 fp5 brochure_energy_env
2001 fp5 brochure_energy_env2001 fp5 brochure_energy_env
2001 fp5 brochure_energy_env
 
Work example: wind energy and storage 2012
Work example: wind energy and storage 2012Work example: wind energy and storage 2012
Work example: wind energy and storage 2012
 
Work example; wind energy and storage 2012
Work example; wind energy and storage 2012Work example; wind energy and storage 2012
Work example; wind energy and storage 2012
 
Hubert lemmens | Netbalans bij een wisselende energieproductie
Hubert lemmens  |  Netbalans bij een wisselende energieproductieHubert lemmens  |  Netbalans bij een wisselende energieproductie
Hubert lemmens | Netbalans bij een wisselende energieproductie
 
EEI State of Distribution, 2012
EEI State of Distribution, 2012EEI State of Distribution, 2012
EEI State of Distribution, 2012
 
Cired2011 0405 final
Cired2011 0405 finalCired2011 0405 final
Cired2011 0405 final
 
rice_solar_panels
rice_solar_panelsrice_solar_panels
rice_solar_panels
 
Optimal Placement of Distributed Generation on Radial Distribution System for...
Optimal Placement of Distributed Generation on Radial Distribution System for...Optimal Placement of Distributed Generation on Radial Distribution System for...
Optimal Placement of Distributed Generation on Radial Distribution System for...
 

Recently uploaded

Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
DEPED Work From Home WORKWEEK-PLAN.docx
DEPED Work From Home  WORKWEEK-PLAN.docxDEPED Work From Home  WORKWEEK-PLAN.docx
DEPED Work From Home WORKWEEK-PLAN.docxRodelinaLaud
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 

Recently uploaded (20)

Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
DEPED Work From Home WORKWEEK-PLAN.docx
DEPED Work From Home  WORKWEEK-PLAN.docxDEPED Work From Home  WORKWEEK-PLAN.docx
DEPED Work From Home WORKWEEK-PLAN.docx
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 

Daniel Cooper - November 11, 2011

  • 1. Holland BPW P21 Decision: Internal or External Resources ELECTRIC TRANSMISSION CONSIDERATIONS IN POWER SUPPLY DECISIONS Jennings, Strouss & Salmon
  • 2. HBPW P21 Decision – Electric Transmission Overview of Presentation  Everything you never wanted to know about Electric Transmission in one presentation:  If base load generation is the goal, why discuss transmission?  What is Electric Transmission?  A Short History of Electric Transmission  Transmission today – ISOs, RTOs and more  Transmission considerations in electric power supply decisions – local resource or remote resource?  Giving away the ending – transmission considerations are almost certain to be a factor, but unlikely to the major factor in the P21 Decision Jennings, Strouss & Salmon 2
  • 3. HBPW P21 Decision – Electric Transmission Why Discuss Transmission in the P21 Decision Process?  Electric Transmission can be the means to the end  Think of a roadway. It isn’t where you want to go, but it can get you there  Some generating resources can’t or won’t be placed inside Holland.  For those external resources, electric transmission is needed to deliver the power and energy  Electric transmission can add economic, logistical and administrative considerations that become part of the electric power supply decision Jennings, Strouss & Salmon 3
  • 4. HBPW P21 Decision – Electric Transmission What is Electric Transmission?  Electric Transmission is designed to move large amounts of electric energy over long distances  Physically, electric transmission structures and wires are taller and heavier  The operating voltage for electric transmission is higher  This allows the movement of larger amounts of electricity more efficiently  This also requires more equipment to raise the voltage for transmission, then lower it for use by the customer Jennings, Strouss & Salmon 4
  • 5. HBPW P21 Decision – Electric Transmission What is Electric Transmission? 345 kv Jennings, Strouss & Salmon 5
  • 6. HBPW P21 Decision – Electric Transmission A Short History – the Early Days  At the start of the electric industry, electric transmission didn’t exist  The earliest electric systems were built for towns and cities  The generation and load were close together, so the same lines and voltages (or close to it) could be used to generate and distribute the electricity  This made for a simple system Jennings, Strouss & Salmon 6
  • 7. HBPW P21 Decision – Electric Transmission The Early Days – A Simple System Analogy Note: to make this accurate, the lake has no storage, so pumping must match use Jennings, Strouss & Salmon 7
  • 8. HBPW P21 Decision – Electric Transmission A Short History – Larger Generators call for Transmission  Electric loads increased as more areas were served by electric utilities  The electric industry entered a period of positive economies of scale for electric generators – larger plants cost less per kilowatt to build and produced electricity more cheaply than smaller plants  Due to land use, environmental and fuel supply considerations, the larger generators were generally built at sites remote from the loads  This resulted in need for more efficient, higher capacity lines – so electric transmission was built Jennings, Strouss & Salmon 8
  • 9. HBPW P21 Decision – Electric Transmission A Short History - Larger Generators were Built Remotely Jennings, Strouss & Salmon 9
  • 10. HBPW P21 Decision – Electric Transmission A Short History – the Interconnected System Appears  As electric utilities expanded and more lines were built to connect generators, electric utilities began to interconnect their transmission systems with others  This allowed utilities to support each other when generators dropped off line  This also allowed utilities to make both short term and longer term sales between each other with economic benefits to both utilities and their customers  The interconnection process continued to today’s tightly- interconnected systems Jennings, Strouss & Salmon 10
  • 11. HBPW P21 Decision – Electric Transmission A Short History – the Interconnected System Appears Jennings, Strouss & Salmon 11
  • 12. HBPW P21 Decision – Electric Transmission A Short History – with Complexity Comes Complication  The creation of the interconnected transmission grid gave substantial benefits, but also created concerns  As utilities began to compete to sell electricity to other than their retail customers, control of transmission became an advantage and a potential competitive tool (or weapon)  The flip side of reliability – just as utilities could help support each other, a collapsing utility system could drag others down  As the network became more complex, a single utility could no longer develop the most effective and reliable transmission system plan  So a broader solution was developed Jennings, Strouss & Salmon 12
  • 13. HBPW P21 Decision – Electric Transmission Regional Transmission Overseers – ISOs and RTOs  The concerns about discrimination by transmission owners, network reliability, and efficient planning led to a search for regional solutions  The idea of an independent regional transmission entity was one of those solutions  This type of organization is called a Regional Transmission Operator  The Midwest Independent System Operator – MISO – was created as the transmission overseer for Michigan and much of this part of the United States Jennings, Strouss & Salmon 13
  • 14. HBPW P21 Decision – Electric Transmission Regional Transmission Overseers – MISO Jennings, Strouss & Salmon 14
  • 15. HBPW P21 Decision – Electric Transmission Regional Transmission Overseers – MISO  MISO’s original mission was limited to transmission  MISO became the Transmission Provider for all of the transmission customers in MISO’s footprint  Even the transmission owners who joined MISO buy transmission service from MISO for their bundled customers  The transmission owning MISO members agreed to allow MISO to tell them how to operate their systems and collect the transmission revenues  In return, MISO pays the transmission owners the costs of owning and operating their transmission  Then MISO’s mission expanded, affecting generation decisions… Jennings, Strouss & Salmon 15
  • 16. HBPW P21 Decision – Electric Transmission Regional Transmission Overseers – MISO  In following an economic theory on how an electricity market should operate, MISO’s role expanded so MISO moved into the middle of all electric transactions in its footprint  Pragmatically, all electric energy and system support services generated are sold to MISO  All users of electricity buy their needs from MISO, either directly or through their local utility  The only significant exception to this is electricity generated and used within a municipality like Holland Jennings, Strouss & Salmon 16
  • 17. HBPW P21 Decision – Electric Transmission Regional Transmission Overseers – MISO  MISO’s energy market isn’t a cost-based market  MISO’s energy prices are based on supplier offer costs which may not be actual production costs  MISO charges all energy purchasers the marginal (highest accepted offer) cost of energy needed to meet load  All suppliers are paid the marginal price, regardless of cost  All purchasers pay that marginal cost  This means a single high-cost generator can (and often does) drive the purchased energy cost far above the actual average production cost of units supplying the energy  Owning a resource can provide a hedge against MISO energy prices Jennings, Strouss & Salmon 17
  • 18. HBPW P21 Decision – Electric Transmission Regional Transmission Overseers – MISO  MISO’s position between Holland’s customers and resources outside of Holland’s system is a factor to consider in power supply decisions  Resources located outside of Holland BPW’s system are subject to administrative and operating requirements that won’t apply to a resource inside of Holland’s system  MISO also charges for transmission losses across its system. Those external losses aren’t a factor for a generator inside of Holland  MISO provides a reliable highway to a broad area, allowing far more generating resource options than available internally Jennings, Strouss & Salmon 18
  • 19. HBPW P21 Decision – Electric Transmission Regional Transmission Overseers – MISO  MISO has proposed a new capacity market and resource requirements program  MISO has filed this plan with the Federal Energy Regulatory Commission (FERC). FERC is considering the plan  One part of MISO’s capacity proposal is to have a potential additional delivery charge for generating resources that are outside of a utility’s home Local Resource Zone  The Local Resource Zone for Holland BPW is lower Michigan  This adds cost risk for Holland for resources outside of Michigan  Until FERC rules on MISO’s proposal, the impact of this factor can’t be quantified Jennings, Strouss & Salmon 19
  • 20. HBPW P21 Decision – Electric Transmission System Reliability Requirements  There is a body of reliability standards requirements that applies to all entities that affect the bulk electric system (the transmission system)  While the same rules apply to all generating resources, the location of the resource may have an effect on Holland BPW.  A large resource internal to Holland’s system may make Holland BPW subject to additional reliability standards  This depends on many factors and may or may not be a consideration in power supply choices Jennings, Strouss & Salmon 20
  • 21. HBPW P21 Decision – Electric Transmission Bringing it Home – Transmission Considerations for P21  There are considerations related to transmission that may be factors in the choice of a base load generating resource for Holland BPW  The main positive consideration is that the electric transmission system provides the opportunity to gain access to resources that can’t or shouldn’t be built in Holland  This provides an option to obtain additional fuel diversity, economies of scale through joint ownership arrangements, and access to resources not available locally for whatever reason Jennings, Strouss & Salmon 21
  • 22. HBPW P21 Decision – Electric Transmission Bringing it Home – Transmission Considerations for P21  One transmission consideration – reliability - is a very small concern  As shown on the system map, there are many alternative paths for electric power, so line outages generally have little effect  While there have been outages of wide parts of the bulk transmission system, those have been rare, with much effort to see they don’t happen again  The main concern for delivery of external resources for Holland is the loss of the external substation that ties Holland to the bulk transmission system Jennings, Strouss & Salmon 22
  • 23. HBPW P21 Decision – Electric Transmission Much Redundancy between Holland and External Resources Jennings, Strouss & Salmon 23
  • 24. HBPW P21 Decision – Electric Transmission The Greatest Interruption Risk is the HBPW/Transmission Connection Jennings, Strouss & Salmon 24
  • 25. HBPW P21 Decision – Electric Transmission Bringing it Home – Transmission Considerations for P21  MISO – the Transmission Provider for this part of the country – is a factor  MISO will likely add some extra administrative costs for resources external to Holland  MISO will add transmission loss costs for resources external to Holland  MISO’s capacity market and resource requirements proposal may add costs for resources outside of lower Michigan  MISO will assure reasonable access to external resources  MISO will make it easy to sell surplus energy from external resources. That may not be true for internal resources Jennings, Strouss & Salmon 25
  • 26. HBPW P21 Decision – Electric Transmission Bringing it Home – Transmission Considerations for P21  Bulk electric transmission system reliability considerations may favor external resources  A large generating resource inside of Holland may result in Holland being subject to additional reliability standards requirements  The same is not true for external resources  This area is subject to many other factors that will affect Holland BPW’s reliability standards obligations  The ultimate conclusion on Holland BPW’s reliability standards obligations will determine whether or not they are a factor in the P21 Decision. Jennings, Strouss & Salmon 26
  • 27. HBPW P21 Decision – Electric Transmission Bringing it Home – Transmission Considerations for P21  In the end, the impact of electric transmission considerations on the P21 Decision will likely end up being an incremental cost factor difference between internal and external resources  There may also be an incremental external transmission cost difference between different external resources  As an incremental cost factor, electric transmission considerations may sway, but won’t determine, the final decision Jennings, Strouss & Salmon 27
  • 28. HBPW P21 Decision – Electric Transmission Transmission Considerations for the P21 Decision QUESTIONS AND DISCUSSION Jennings, Strouss & Salmon