This document describes an experiment to optimize the required capacity of a re-regulating dam located downstream of a 2000 MW hydropower plant in Iran. The conventional method would require increasing the dam height by 6 meters at a high cost, but a new method takes advantage of variable power plant operations and water storage in the downstream river to need only a 1.5 meter increase. Modeling the river routing showed that variable outflows from the dam even out downstream. This optimized approach was successfully implemented, reducing construction costs while still providing sufficient flow regulation.
Rehabilitation of Three Equalization Basins and Ancillary Facilities Fairfax County
This project involved rehabilitating three equalization basins and ancillary facilities at the Noman M. Cole Jr. Pollution Control Plant. Work included constructing a new concrete liner for one basin, rehabilitating existing pump stations, and adding new pump stations. A new flood protection system was also constructed. The project was completed in March 2020 and improved the plant's ability to temporarily store overflow wastewater during heavy storms.
This project involves the design of an offshore ocean hydro energy storage system. The system uses two reservoirs - an upper and lower reservoir - to store energy similarly to conventional pumped storage hydro. Key deliverables included determining system efficiency (70.2% for a 10 MW, 3 hour storage design), a MATLAB program to size facilities, selecting power generation equipment (4 pole generator, transformer), and CAD modeling. A graphical user interface was developed to optimize system design based on user inputs. Solid modeling and finite element analysis was conducted to examine stresses on the upper reservoir dam.
EarthFx presentation on Assessing Cumulative Effects of SAGD Operations in the Mackay Watershed PowerPoint
To learn more visit us at http://www.earthfx.com/
Slide 33 video link https://www.youtube.com/watch?v=q95Zzt029E4
Slide 35 video link https://www.youtube.com/watch?v=v6siBetQgBI
The document summarizes the development of an integrated surface water and groundwater model of the MacKay River watershed in Alberta, Canada to assess cumulative effects of oil sands development on water resources. Key aspects of the model include: (1) A fully distributed representation of geology, hydrogeology, climate and land cover at a 400x400m resolution for groundwater and finer 200x200m resolution for surface water; (2) Calibration of both surface water and groundwater submodels to streamflow and groundwater level observations; and (3) Simulation of key hydrologic processes like groundwater-surface water interaction and frozen ground conditions. The calibrated model is able to match observed streamflow and groundwater levels over
The document summarizes an investigation into refining the reservoir capacity table for Hungry Horse Reservoir in Montana. It was found that the existing capacity table, based on mapping from 1954, underestimated the reservoir's active storage volume by 0.7% compared to a new capacity table developed using 1993 aerial photography and mapping when the reservoir level was low. This resulted in additional estimated power benefits of $1 million over 42.5 months. The document recommends reviewing capacity tables for other older reservoirs where mapping techniques have improved, to potentially improve water management and power production.
The Diadema underground gas storage facility in Argentina allows storing surplus natural gas from producing fields during summer for withdrawal in winter. It optimizes gas production and supply. The facility uses a depleted gas reservoir and injection/production wells connected to a gas pipeline and processing plant. Monitoring wells track reservoir pressures and protect aquifers. Gas volumes are balanced daily using the TOW system, reducing differences from 0.5% to 0.2-0.3% and administrative time by 90%. Future plans include reservoir modeling and remote well control. Automation through systems like Gasmed and TOW improve data quality, consistency, and decision-making.
Official Final Report Volterix COMPLETEKyler Lucas
This report evaluates the feasibility of a run-of-river hydroelectric system in Fintry, BC using Shorts Creek. Flow rate data collected shows sufficient flow for power generation. A diversion structure and Coanda screen would divert up to 1.14 m3/s into a penstock, with excess returning to the creek. A 15kW turbine was selected to operate under a 30m pressure head. Generated power would be stored in Tesla batteries and used to power sustainable homes constructed from reused shipping containers, with the development designed to have a total consumption of 108,209 kWh/yr, matching the hydroelectric output. Licenses and approvals are required for the project.
This document summarizes water supply projects being undertaken by the Guadalupe-Blanco River Authority (GBRA) in Central Texas. It discusses the Mid-Basin Water Supply Project (MBWSP) which is part of the regional water planning to supply surface water from the Guadalupe River to areas relying on depleting aquifers. The MBWSP would include an intake on the river, treatment plant, and pipelines to deliver 50,000 acre-feet of water per year. Alternative options discussed include an integrated project sharing facilities with nearby water suppliers or connecting the treated water to the cities of San Antonio or Austin. Estimated costs per acre-foot of water range from $1,467 to $1,
Rehabilitation of Three Equalization Basins and Ancillary Facilities Fairfax County
This project involved rehabilitating three equalization basins and ancillary facilities at the Noman M. Cole Jr. Pollution Control Plant. Work included constructing a new concrete liner for one basin, rehabilitating existing pump stations, and adding new pump stations. A new flood protection system was also constructed. The project was completed in March 2020 and improved the plant's ability to temporarily store overflow wastewater during heavy storms.
This project involves the design of an offshore ocean hydro energy storage system. The system uses two reservoirs - an upper and lower reservoir - to store energy similarly to conventional pumped storage hydro. Key deliverables included determining system efficiency (70.2% for a 10 MW, 3 hour storage design), a MATLAB program to size facilities, selecting power generation equipment (4 pole generator, transformer), and CAD modeling. A graphical user interface was developed to optimize system design based on user inputs. Solid modeling and finite element analysis was conducted to examine stresses on the upper reservoir dam.
EarthFx presentation on Assessing Cumulative Effects of SAGD Operations in the Mackay Watershed PowerPoint
To learn more visit us at http://www.earthfx.com/
Slide 33 video link https://www.youtube.com/watch?v=q95Zzt029E4
Slide 35 video link https://www.youtube.com/watch?v=v6siBetQgBI
The document summarizes the development of an integrated surface water and groundwater model of the MacKay River watershed in Alberta, Canada to assess cumulative effects of oil sands development on water resources. Key aspects of the model include: (1) A fully distributed representation of geology, hydrogeology, climate and land cover at a 400x400m resolution for groundwater and finer 200x200m resolution for surface water; (2) Calibration of both surface water and groundwater submodels to streamflow and groundwater level observations; and (3) Simulation of key hydrologic processes like groundwater-surface water interaction and frozen ground conditions. The calibrated model is able to match observed streamflow and groundwater levels over
The document summarizes an investigation into refining the reservoir capacity table for Hungry Horse Reservoir in Montana. It was found that the existing capacity table, based on mapping from 1954, underestimated the reservoir's active storage volume by 0.7% compared to a new capacity table developed using 1993 aerial photography and mapping when the reservoir level was low. This resulted in additional estimated power benefits of $1 million over 42.5 months. The document recommends reviewing capacity tables for other older reservoirs where mapping techniques have improved, to potentially improve water management and power production.
The Diadema underground gas storage facility in Argentina allows storing surplus natural gas from producing fields during summer for withdrawal in winter. It optimizes gas production and supply. The facility uses a depleted gas reservoir and injection/production wells connected to a gas pipeline and processing plant. Monitoring wells track reservoir pressures and protect aquifers. Gas volumes are balanced daily using the TOW system, reducing differences from 0.5% to 0.2-0.3% and administrative time by 90%. Future plans include reservoir modeling and remote well control. Automation through systems like Gasmed and TOW improve data quality, consistency, and decision-making.
Official Final Report Volterix COMPLETEKyler Lucas
This report evaluates the feasibility of a run-of-river hydroelectric system in Fintry, BC using Shorts Creek. Flow rate data collected shows sufficient flow for power generation. A diversion structure and Coanda screen would divert up to 1.14 m3/s into a penstock, with excess returning to the creek. A 15kW turbine was selected to operate under a 30m pressure head. Generated power would be stored in Tesla batteries and used to power sustainable homes constructed from reused shipping containers, with the development designed to have a total consumption of 108,209 kWh/yr, matching the hydroelectric output. Licenses and approvals are required for the project.
This document summarizes water supply projects being undertaken by the Guadalupe-Blanco River Authority (GBRA) in Central Texas. It discusses the Mid-Basin Water Supply Project (MBWSP) which is part of the regional water planning to supply surface water from the Guadalupe River to areas relying on depleting aquifers. The MBWSP would include an intake on the river, treatment plant, and pipelines to deliver 50,000 acre-feet of water per year. Alternative options discussed include an integrated project sharing facilities with nearby water suppliers or connecting the treated water to the cities of San Antonio or Austin. Estimated costs per acre-foot of water range from $1,467 to $1,
Ground Water Resources Estimation By GEC 2015 MethodologyAnand A.V.S.S
This is the approved method using which the ground water resources of the country (India) are to be assessed. This is a modified version of GEC 1997 methodology. Presently all states are busy in assessing the Ground Water Resources for the base year 2016 using this methodology.
This document discusses hydrology and site selection considerations for hydro power plants. It begins with an introduction to hydrology, including definitions and the hydrologic cycle. It then discusses various methods to measure runoff, including empirical formulas, runoff curves, and direct discharge observations. Hydrographs and unit hydrographs are explained as tools to understand water flow over time. Flow duration curves and mass curves are also summarized as useful for assessing available water supply. The document concludes with key factors to consider for site selection, such as available water supply, water storage capacity, water head, accessibility, distance to load centers, and land characteristics.
American Society of Civil Engineering Orange County Branch (ASCE OC) - Environmental And Water Resources Institute (EWRI) - February Luncheon Presentation: Mid-Basin Injection at Centennial Park Project. Ground Water Replenishment System (GWRS) Presentation by OCWD and Tetra Tech
This document describes the reservoir simulation model HEC-ResSim, developed by the U.S. Army Corps of Engineers as an advancement over the previous HEC-5 model. HEC-ResSim uses a rule-based approach to mimic actual reservoir operations and decision making. It can represent complex reservoir systems and operational requirements through features like outlet prioritization and conditional logic. The model accounts for both the physical characteristics of reservoirs and the operational goals and constraints that influence water management and release decisions.
The document provides a status update on the 2016 Desired Future Condition (DFC) planning process for various Groundwater Management Areas (GMAs) in Texas. It summarizes the progress that has been made in GMAs 2, 7, 11, and 13. For each GMA, it lists the aquifers being planned for and discusses the initial model runs, draft technical memorandums, or other work that has been completed. It indicates that further model runs and discussions are still needed for many of the aquifers in various GMAs. The next steps mentioned include completing additional simulations and holding future meetings to discuss results.
The document summarizes a student design project to create a hydraulic turbine capable of lifting a can of beans 10 feet using no more than 1 gallon of water from a reservoir no higher than 4 feet 3 inches. Key aspects of the project included:
- Designing and 3D printing Pelton buckets and a nozzle for a Pelton turbine.
- Creating a lightweight turbine wheel from plexiglass to house the buckets.
- Designing a piping system to efficiently deliver water from the reservoir to the turbine nozzle.
- Testing multiple design iterations to achieve a best time of 1.39 seconds to lift the can.
Gary Jackson has over 33 years of experience as a technical consultant providing engineering design and analysis for power plants. He has extensive leadership experience directing engineering change packages and evaluations for major projects involving piping systems, pipe supports, and modifications. His background includes involvement in projects related to power uprates, seismic qualifications, and hardened containment vent systems.
The document discusses site selection criteria for hydel power plants. It lists several important factors to consider: availability of water throughout the year, water storage capabilities either for yearly use or during dry periods, sufficient water head to generate requisite power, accessibility via rail and road, proximity to load centers to minimize transmission costs, suitable land that is rocky and earthquake-free, and minimal water pollution and sedimentation. It concludes by noting these criteria must be compared when selecting between hydel and other types of power plants.
ICOE2016 - A8 -VERS 3 Feb 18 -MERMAID POWER Paper Charles Haynes
The document summarizes key components of the Neptune 3 wave energy project. The Neptune 3 uses a point absorber buoy connected to a direct drive power takeoff system to convert wave motion into electricity. The point absorber is constrained by a framework anchored to the seabed and a tidal compensator adjusts the framework to account for tidal changes. Power is generated as the point absorber moves and transmitted via a custom generator, with test data showing 409 volts at 89 RPM from 1 meter waves.
This document discusses hydroelectric power generation and the components involved. It begins by outlining the objectives of understanding the vocabulary, workings, configurations, and components of hydroelectric power plants. It then discusses various methods for measuring water flow rates, including basic, refined, and sophisticated methods. The document goes on to explain the principles of hydroelectric power generation using Bernoulli's equation. It describes intake structures, penstocks, turbines, tailraces, and categorizes different types of power plants. Finally, it discusses the components involved in hydroelectric systems and different types of turbines, including impulse and reaction turbines.
Development of prototype turbine model for ultra-low head hydro power potenti...iosrjce
Clean source of energy is playing very vital role in today’s eco-friendly environment. Potential
energy available with water can be converted into useful work by maintaining the purpose of clean environment.
Hydro-power plant utilises the energy of water and can produce equivalent mechanical output. Hydro-electric
power plants are much more reliable and efficient as a renewable and clean source than the fossil fuel power
plants. The rivers in Western Maharashtra region flows from Sahyadri mountain towards Deccan platue with
steady gradient. In recent years, the environmental impacts are becoming difficult for developers to build new
dams because of opposition from environmentalists and people living on the land to be flooded. Therefore the
need has arisen to go for the small scale hydro power plants in the range of mini (few MW) and micro hydro
(kW) power plants. This paper discusses the conceptual design and development of a micro hydro power plant.
The developed model can be used at sites having head range of 0.5 to to 6 m. The required information was
collected from meteorological department and irrigation department of Kolhapur division of Government of
Maharashtra, India.
This document provides an overview of hydro power plant components and types. It discusses the three types of power houses: surface, semi-underground, and underground. Surface power houses have components on the surface but are limited by topography. Semi-underground power houses combine advantages of surface and underground. Underground power houses are located entirely inside mountains with access tunnels. The document also summarizes the main components of hydro power stations including dams/barrages, water conductor systems, and power houses as well as different types of hydro power projects.
The existing headworks facility at the Carters Creek WWTP, built in 1995, requires replacement and upgrades of major components to maintain efficiency and meet new design standards. A wastewater master plan identified potential new discharge permit restrictions requiring additional treatment processes, necessitating a complete rebuild of the headworks. To reduce costs, the project scope was narrowed to only essential elements, lowering the estimated budget from $3.5 million to $1.6 million.
The document discusses water conveyance and distribution systems. It covers the design of pressure pipes, pumps, and distribution networks. There are two stages of water conveyance: from the source to the treatment plant, and from the plant to the distribution system. Pipes are designed to balance flow velocities and pressure losses. Pumps are used to lift water at various stages. Distribution systems aim to deliver water to consumers with adequate quality, quantity and pressure through layouts like dead-end, radial, gridiron or ring systems. Water is distributed through gravity, pumping or combined systems using distribution reservoirs.
This document presents information about hydroelectric power plants in India. It discusses the key components of hydroelectric plants including dams, reservoirs, turbines, generators, and penstocks. It explains how the potential energy of stored water is converted to kinetic energy and then electrical energy. The document notes that hydroelectric power provides 30% of the world's energy and discusses the first hydroelectric plants constructed in India in the early 1900s. It outlines the advantages of hydroelectric power in being renewable with low operating costs but also notes disadvantages like high initial costs and dependence on water availability.
This document provides information about hydroelectric power plants. It discusses the basic components and principles of hydroelectric dams, including reservoirs, dams, penstocks, turbines, generators, and transformers. It also describes different types of hydroelectric plants based on factors like head, capacity, and location. Several major hydroelectric plants in India are discussed as examples, including Sardar Sarovar and Ukai. International examples of different types of dam structures are also summarized.
Hydrology and hydraulics for design designavirup naskar
This document provides an overview of hydrology and hydraulic considerations for bridge design. It discusses calculating design discharges using USGS reports, collecting channel and bridge characteristics through field surveys, performing hydraulic analysis using HEC-RAS software, meeting requirements of the National Flood Insurance Program, analyzing scour, and ODOT submittal requirements. The key steps involve estimating flood flows, modeling water surface profiles, evaluating flood risks and impacts, and designing protections against scour.
The document discusses a student project to test a homemade mini-hydro turbine using rainwater runoff. Key questions for the project include whether there is enough rainwater to produce energy and if a low-cost turbine can be made from repurposed materials. The students predict their turbine could produce around 2 watts of power from an 8 foot height water source. However, initial tests of a prototype produced no measurable energy. Improvements to the design are needed to effectively harness energy from small rainwater sources.
Real time decision support system in reserrvoir and flood management system f...HydrologyWebsite
This document describes a reservoir operation and flood management system framework. It discusses challenges like meeting multiple water usage objectives, forecasting floods and inflows, and optimizing reservoir operations. Modern IT solutions help manage large data and make robust decisions. The framework includes data collection, forecasting models, dissemination of warnings, and optimization of reservoir operations both for short-term flood management and long-term planning. Case studies from India demonstrate how the system improves flood forecasting and allows more optimal reservoir operations to meet demands while minimizing downstream flood impacts.
This document presents the basic design configuration of the proposed Wewathenna Pumped Storage Power Plant (PSPP) in Sri Lanka as a potential peaking power plant. The Wewathenna site was identified in Sri Lanka's 2018 Electricity Sector Master Plan as a potential PSPP location. The study develops the basic design for the Wewathenna PSPP using the existing Victoria reservoir as the lower pond and constructing an upper pond. The calculations determine the Wewathenna PSPP would have a maximum capacity of 500MW, with an upper reservoir volume of 1,870,560 cubic meters and maximum plant discharge of 86.6 cubic meters per second.
C. d. engin, a. yesildirek, designing and modeling of a point absorber wave e...Dogukan Engin
In this project, the primary aim is to produce optimum parameters for electric power generation via renewable sea wave energy for the Turkish sea coastlines. The modular system is composed of wave actuation mechanism, hydraulic system and generator. This system is used to model and compute the optimal parameters but also monitor the Turkish coastline characteristics. A hydrodynamic model based optimum PTO drives the generator that are further connected to other similar units to construct a wave energy farm. A testbench is created to mimic the operation of wave actuation in lab environment. This unit drives hydraulic system that can generate mechanical power to excite a generator shaft. Optimal wave actuation mechanism parameters suitable to our coastlines have been calculated. With these aims, the system designed on the basis of the mechanism that based on point absorber buoy. Initial design and hydrodynamic simulations in MATLAB/Simulink is given.
Ground Water Resources Estimation By GEC 2015 MethodologyAnand A.V.S.S
This is the approved method using which the ground water resources of the country (India) are to be assessed. This is a modified version of GEC 1997 methodology. Presently all states are busy in assessing the Ground Water Resources for the base year 2016 using this methodology.
This document discusses hydrology and site selection considerations for hydro power plants. It begins with an introduction to hydrology, including definitions and the hydrologic cycle. It then discusses various methods to measure runoff, including empirical formulas, runoff curves, and direct discharge observations. Hydrographs and unit hydrographs are explained as tools to understand water flow over time. Flow duration curves and mass curves are also summarized as useful for assessing available water supply. The document concludes with key factors to consider for site selection, such as available water supply, water storage capacity, water head, accessibility, distance to load centers, and land characteristics.
American Society of Civil Engineering Orange County Branch (ASCE OC) - Environmental And Water Resources Institute (EWRI) - February Luncheon Presentation: Mid-Basin Injection at Centennial Park Project. Ground Water Replenishment System (GWRS) Presentation by OCWD and Tetra Tech
This document describes the reservoir simulation model HEC-ResSim, developed by the U.S. Army Corps of Engineers as an advancement over the previous HEC-5 model. HEC-ResSim uses a rule-based approach to mimic actual reservoir operations and decision making. It can represent complex reservoir systems and operational requirements through features like outlet prioritization and conditional logic. The model accounts for both the physical characteristics of reservoirs and the operational goals and constraints that influence water management and release decisions.
The document provides a status update on the 2016 Desired Future Condition (DFC) planning process for various Groundwater Management Areas (GMAs) in Texas. It summarizes the progress that has been made in GMAs 2, 7, 11, and 13. For each GMA, it lists the aquifers being planned for and discusses the initial model runs, draft technical memorandums, or other work that has been completed. It indicates that further model runs and discussions are still needed for many of the aquifers in various GMAs. The next steps mentioned include completing additional simulations and holding future meetings to discuss results.
The document summarizes a student design project to create a hydraulic turbine capable of lifting a can of beans 10 feet using no more than 1 gallon of water from a reservoir no higher than 4 feet 3 inches. Key aspects of the project included:
- Designing and 3D printing Pelton buckets and a nozzle for a Pelton turbine.
- Creating a lightweight turbine wheel from plexiglass to house the buckets.
- Designing a piping system to efficiently deliver water from the reservoir to the turbine nozzle.
- Testing multiple design iterations to achieve a best time of 1.39 seconds to lift the can.
Gary Jackson has over 33 years of experience as a technical consultant providing engineering design and analysis for power plants. He has extensive leadership experience directing engineering change packages and evaluations for major projects involving piping systems, pipe supports, and modifications. His background includes involvement in projects related to power uprates, seismic qualifications, and hardened containment vent systems.
The document discusses site selection criteria for hydel power plants. It lists several important factors to consider: availability of water throughout the year, water storage capabilities either for yearly use or during dry periods, sufficient water head to generate requisite power, accessibility via rail and road, proximity to load centers to minimize transmission costs, suitable land that is rocky and earthquake-free, and minimal water pollution and sedimentation. It concludes by noting these criteria must be compared when selecting between hydel and other types of power plants.
ICOE2016 - A8 -VERS 3 Feb 18 -MERMAID POWER Paper Charles Haynes
The document summarizes key components of the Neptune 3 wave energy project. The Neptune 3 uses a point absorber buoy connected to a direct drive power takeoff system to convert wave motion into electricity. The point absorber is constrained by a framework anchored to the seabed and a tidal compensator adjusts the framework to account for tidal changes. Power is generated as the point absorber moves and transmitted via a custom generator, with test data showing 409 volts at 89 RPM from 1 meter waves.
This document discusses hydroelectric power generation and the components involved. It begins by outlining the objectives of understanding the vocabulary, workings, configurations, and components of hydroelectric power plants. It then discusses various methods for measuring water flow rates, including basic, refined, and sophisticated methods. The document goes on to explain the principles of hydroelectric power generation using Bernoulli's equation. It describes intake structures, penstocks, turbines, tailraces, and categorizes different types of power plants. Finally, it discusses the components involved in hydroelectric systems and different types of turbines, including impulse and reaction turbines.
Development of prototype turbine model for ultra-low head hydro power potenti...iosrjce
Clean source of energy is playing very vital role in today’s eco-friendly environment. Potential
energy available with water can be converted into useful work by maintaining the purpose of clean environment.
Hydro-power plant utilises the energy of water and can produce equivalent mechanical output. Hydro-electric
power plants are much more reliable and efficient as a renewable and clean source than the fossil fuel power
plants. The rivers in Western Maharashtra region flows from Sahyadri mountain towards Deccan platue with
steady gradient. In recent years, the environmental impacts are becoming difficult for developers to build new
dams because of opposition from environmentalists and people living on the land to be flooded. Therefore the
need has arisen to go for the small scale hydro power plants in the range of mini (few MW) and micro hydro
(kW) power plants. This paper discusses the conceptual design and development of a micro hydro power plant.
The developed model can be used at sites having head range of 0.5 to to 6 m. The required information was
collected from meteorological department and irrigation department of Kolhapur division of Government of
Maharashtra, India.
This document provides an overview of hydro power plant components and types. It discusses the three types of power houses: surface, semi-underground, and underground. Surface power houses have components on the surface but are limited by topography. Semi-underground power houses combine advantages of surface and underground. Underground power houses are located entirely inside mountains with access tunnels. The document also summarizes the main components of hydro power stations including dams/barrages, water conductor systems, and power houses as well as different types of hydro power projects.
The existing headworks facility at the Carters Creek WWTP, built in 1995, requires replacement and upgrades of major components to maintain efficiency and meet new design standards. A wastewater master plan identified potential new discharge permit restrictions requiring additional treatment processes, necessitating a complete rebuild of the headworks. To reduce costs, the project scope was narrowed to only essential elements, lowering the estimated budget from $3.5 million to $1.6 million.
The document discusses water conveyance and distribution systems. It covers the design of pressure pipes, pumps, and distribution networks. There are two stages of water conveyance: from the source to the treatment plant, and from the plant to the distribution system. Pipes are designed to balance flow velocities and pressure losses. Pumps are used to lift water at various stages. Distribution systems aim to deliver water to consumers with adequate quality, quantity and pressure through layouts like dead-end, radial, gridiron or ring systems. Water is distributed through gravity, pumping or combined systems using distribution reservoirs.
This document presents information about hydroelectric power plants in India. It discusses the key components of hydroelectric plants including dams, reservoirs, turbines, generators, and penstocks. It explains how the potential energy of stored water is converted to kinetic energy and then electrical energy. The document notes that hydroelectric power provides 30% of the world's energy and discusses the first hydroelectric plants constructed in India in the early 1900s. It outlines the advantages of hydroelectric power in being renewable with low operating costs but also notes disadvantages like high initial costs and dependence on water availability.
This document provides information about hydroelectric power plants. It discusses the basic components and principles of hydroelectric dams, including reservoirs, dams, penstocks, turbines, generators, and transformers. It also describes different types of hydroelectric plants based on factors like head, capacity, and location. Several major hydroelectric plants in India are discussed as examples, including Sardar Sarovar and Ukai. International examples of different types of dam structures are also summarized.
Hydrology and hydraulics for design designavirup naskar
This document provides an overview of hydrology and hydraulic considerations for bridge design. It discusses calculating design discharges using USGS reports, collecting channel and bridge characteristics through field surveys, performing hydraulic analysis using HEC-RAS software, meeting requirements of the National Flood Insurance Program, analyzing scour, and ODOT submittal requirements. The key steps involve estimating flood flows, modeling water surface profiles, evaluating flood risks and impacts, and designing protections against scour.
The document discusses a student project to test a homemade mini-hydro turbine using rainwater runoff. Key questions for the project include whether there is enough rainwater to produce energy and if a low-cost turbine can be made from repurposed materials. The students predict their turbine could produce around 2 watts of power from an 8 foot height water source. However, initial tests of a prototype produced no measurable energy. Improvements to the design are needed to effectively harness energy from small rainwater sources.
Real time decision support system in reserrvoir and flood management system f...HydrologyWebsite
This document describes a reservoir operation and flood management system framework. It discusses challenges like meeting multiple water usage objectives, forecasting floods and inflows, and optimizing reservoir operations. Modern IT solutions help manage large data and make robust decisions. The framework includes data collection, forecasting models, dissemination of warnings, and optimization of reservoir operations both for short-term flood management and long-term planning. Case studies from India demonstrate how the system improves flood forecasting and allows more optimal reservoir operations to meet demands while minimizing downstream flood impacts.
This document presents the basic design configuration of the proposed Wewathenna Pumped Storage Power Plant (PSPP) in Sri Lanka as a potential peaking power plant. The Wewathenna site was identified in Sri Lanka's 2018 Electricity Sector Master Plan as a potential PSPP location. The study develops the basic design for the Wewathenna PSPP using the existing Victoria reservoir as the lower pond and constructing an upper pond. The calculations determine the Wewathenna PSPP would have a maximum capacity of 500MW, with an upper reservoir volume of 1,870,560 cubic meters and maximum plant discharge of 86.6 cubic meters per second.
C. d. engin, a. yesildirek, designing and modeling of a point absorber wave e...Dogukan Engin
In this project, the primary aim is to produce optimum parameters for electric power generation via renewable sea wave energy for the Turkish sea coastlines. The modular system is composed of wave actuation mechanism, hydraulic system and generator. This system is used to model and compute the optimal parameters but also monitor the Turkish coastline characteristics. A hydrodynamic model based optimum PTO drives the generator that are further connected to other similar units to construct a wave energy farm. A testbench is created to mimic the operation of wave actuation in lab environment. This unit drives hydraulic system that can generate mechanical power to excite a generator shaft. Optimal wave actuation mechanism parameters suitable to our coastlines have been calculated. With these aims, the system designed on the basis of the mechanism that based on point absorber buoy. Initial design and hydrodynamic simulations in MATLAB/Simulink is given.
This document summarizes a student project on implementing a pumped storage hydroelectricity system at the Deir Ammar power plant in Lebanon. The power plant currently reduces output during low demand night hours, decreasing gas turbine efficiency. A pumped storage system was proposed to store excess nighttime energy as gravitational potential energy by pumping water to an upper reservoir. During peak daytime hours, the stored water would be released through reversible pump turbines to generate additional electricity. System design was based on plant data, with components sized to provide 120 MW of generation capacity and store 840,000 kWh daily. Economic analysis estimated costs around $156 million with profits of $23.7 million annually, yielding an 8 year payback period and 70 year
Tidal Power Development - Modes of operationkkk212
Tidal power stations harness the energy of tides by using high tide periods to fill reservoirs behind embankments. During low tides, the stored water flows through turbines to generate electricity. There are two main modes of operation - ebb generation, where turbines operate as tides fall; and pumping and turbining, where water is pumped in addition to natural filling to increase head for more power generation. While two-way generation produces power over longer periods, single ebb generation typically yields higher outputs with simpler design and lower costs.
This report describes the development of a power conversion system for a floating tidal stream generator called the Evopod. A prototype Evopod will generate 25kW and test the effects of the marine environment. Optima Control Solutions designed power conversion equipment including a regenerative power converter, transformers, cables, and control systems to maximize power generation at different tidal flows and minimize transmission losses. Extensive simulation and dynamometer testing validated the design's performance before sea trials.
The document summarizes a study tour to the Ghazi Barotha Hydropower Project in Pakistan. Key points:
- The tour visited the Ghazi Barotha dam project located 100km from Islamabad on the Indus River.
- The dam diverts water through a 52km channel to a 1,450MW powerhouse, dropping 76m over 63km.
- The project includes a dam, power channel, power complex, and 340km of transmission lines.
- The run-of-river project aims to meet Pakistan's peak electricity demand in the evenings.
MATHEMATICAL MODELING OF MAHESHWAR HYDRO-ELECTRIC PLANT AT NARMADA RIVERelelijjournal
Economic hydropower plant generation scheduling is an important feature from the utility point of view,
this scheduling is more important in that case when the plants are at the same river stream & owned by the
different utilities. Various Conventional & Artificial intelligence methods have been used earlier for the
hydro generation scheduling reported through researches and more, all are of them required the
mathematical modeling of each & every hydro power plant.
Theoretical account of problem solving in general and especially methodology to develop the mathematical
models of the hydroelectric power plants has been described in this paper. Reservoir elevation model, tail
race elevation model and hydro turbine model have been developed for Rani Avanti Bai Sagar river bed
hydroelectric power plants by collating actual plant data from competent authorities. Modeling of canal
head hydroelectric power plants have been also included in this paper. This hydro power project is a part
of cascade scheme at Narmada River in Madhya Pradesh, India.
Tidal energy can be harnessed by constructing dams or barrages between tidal basins and the sea. During high tide, seawater fills the basin through sluice gates and turbines. During low tide, the water flows back to the sea through the turbines, turning them to generate electricity. There are different types of tidal power plants based on the number of basins and generation cycles. Single basin one-way plants generate power during ebb tides only, while double basin plants alternate generation between two basins to provide continuous power. Tidal energy is a renewable source but has high capital costs and generation varies with tidal patterns.
International Journal of Engineering Research and Applications (IJERA) is an open access online peer reviewed international journal that publishes research and review articles in the fields of Computer Science, Neural Networks, Electrical Engineering, Software Engineering, Information Technology, Mechanical Engineering, Chemical Engineering, Plastic Engineering, Food Technology, Textile Engineering, Nano Technology & science, Power Electronics, Electronics & Communication Engineering, Computational mathematics, Image processing, Civil Engineering, Structural Engineering, Environmental Engineering, VLSI Testing & Low Power VLSI Design etc.
The document discusses the Eastern Siberia–Pacific Ocean oil pipeline (ESPO) project in Russia. The ESPO pipeline will transport oil over 4,857 km from Taishet in eastern Siberia to Kozmino on the Pacific coast. It will have an initial capacity of 30 million tonnes per year, expanding to 80 million tonnes. The pipeline uses booster pumping stations every 150-600 km to maintain pressure across changes in elevation. The pumping units for ESPO were designed with higher pump and motor rotation speeds of 3000 rpm compared to previous units, improving energy efficiency despite increasing costs. Testing facilities were also built to comprehensively test the pump units under all operating conditions.
This document summarizes hydrology and water engineering reports for a new water source and treatment plant for the greater Gort area in County Galway, Ireland. It identifies Lough Cutra as the chosen water source and provides calculations of its catchment area and average runoff. It also details preliminary designs for the main treatment processes at the new plant, including sizing calculations for sedimentation tanks, filters, and other units. Impoundment of Lough Cutra is recommended to ensure sufficient water flow during drought periods.
This document describes a student project to design and build a small-scale hydroelectric power system using a residential water supply. It includes:
1) Calculations to design a Pelton water turbine based on the water pressure and flow rate available from a typical home water system.
2) Design of 3D printed turbine runner molds and construction of prototype runners from the molds.
3) Plans to assemble the full system including a DC motor/generator, test the power output, and measure the maximum load the system can power.
The goal is to gain experience with combined electrical and mechanical applications, known as mechatronics, by designing and testing a working "green" power system for small
Applicability of pressure retarded osmosis power generationRajani Kanth
This document discusses the applicability of pressure retarded osmosis (PRO) power generation technology in Sri Lanka. It begins with an introduction to Sri Lanka's current electricity sources and demand. It then provides background on PRO technology, including the theoretical pressure difference that can be generated and equations for calculating power output. The methodology section describes analyzing several Sri Lankan river basins for their PRO generation potential. Results found that under 20% river flow rates, PRO could generate about 7.84% of Sri Lanka's electricity demand. The conclusion is that PRO shows promise as a renewable source in Sri Lanka.
The presentation provides an overview of hydro energy technology, including the advantages of hydro power, hydro power terminology, types of hydro turbines used in power stations, and details of major hydro power generating stations in Northern India operated by NHPC, SJVNL, THDC, BBMB, and independent power producers. Key advantages of hydro power discussed are that it is renewable, non-polluting, and has lower long-term costs compared to thermal power.
This document outlines a project to use soft computing techniques like artificial neural networks (ANNs) to predict monthly and annual power generation at the Kotmale hydropower plant in Sri Lanka. The objectives are to model ANNs and estimate future annual power predictions using inputs of rainfall data, reservoir inflow levels, and other factors. The methodology will collect 30 years of rainfall and inflow data, draw the catchment area, model different ANN algorithms like feed forward and back propagation, and analyze the results to establish relationships between inputs like rainfall and reservoir levels and the hydropower output. The expected outcome is a power prediction equation relating generated power to factors like flow rate, infiltration, temperature and gravity.
This document provides an overview of a hydro power plant project. It discusses site selection factors like water availability and storage. It describes the basic components and working of a hydro power plant including the catchment area, dam, penstocks, turbines, generators, and powerhouse. It classifies hydro plants by head, lists common turbine types, and discusses advantages like no fuel costs and disadvantages like high initial costs. Examples of hydro plants in Gujarat are also mentioned.
The document provides information about the Mahi Hydel Power Station located on the Mahi River near Banswara, Rajasthan. It has two power houses with a total installed capacity of 140MW. Power generation has decreased in recent years due to lower rainfall. There is a proposal to construct the Anas Reservoir and hydel channel which would increase power generation capacity. The power station utilizes a dam to store water which then flows through penstocks to power Francis turbines connected to generators. This converts the kinetic energy of the flowing water into electrical energy.
Power and Energy Potential Study hydrology.pptxMridu5
This document provides an overview of key concepts for assessing the power and energy potential of hydropower projects over a 16-hour study period. It discusses processing hydrological data including extreme and long-term flows, developing volume-elevation and area-elevation curves, and using flow duration curves to estimate primary, secondary, firm, and spill energy potentials. Key outputs of the analysis include estimating design discharge, installed capacity, and power duration curves to evaluate a project's technical feasibility and energy production capabilities.
1. Hydropower'15
Stavanger, Norway 15-16 June 2015
1
Towards Optimization of the Required Capacity of Re-regulating Dams:
results of an actual experiment
Hooshang Hassani
Project Manager, Mahab Ghodss Consulting Engineering Co. –Iran
(Hooshang.Hassani@gmail.com )
Alireza Zia (Alireza.Zia@gmail.com)
Assistant Professor at Qom University of Technology - Iran
Nasser Kamjou
Head of Dam, Hydropower and Infrastructures Dept. of Mahab Ghodss Consulting Engineering Co.
(N.Kamjou@yahoo.com)
ABSTRACT
Hydropower plants generally run for peak period of power demands and stop operating during off-peak
hours. Re-regulating dams are usually constructed downstream of these plants to guarantee uniform
release during non-operating hours. The required capacity of these dams is calculated based on the
difference between power plant outflow and re-regulating dam release during plant operation. By
modifying this common procedure and applying it to Gotvand re-regulating dam, an optimization was
achieved. Gotvand re-regulating dam is located downstream of a 2000 MW hydropower plant in
southern Iran. This optimization, which was obtained by taking into account the storing capacity of the
river reach at downstream of the dam axis, led to considerable savings in project costs. In this method,
the geometry of downstream plays a critical role in determining the required capacity.
This paper describes this modified procedure and presents results of its application to a real case.
Keywords: re-regulating dam, reservoir capacity, routing, peak hours
1. INTRUDUCTION
In most cases,any change to an already constructed hydraulic structure such as heightening of a dam
might be more difficult than the construction of the same dam from the beginning. The reason is the
constraints resulting from the operation of the foregoing structure and the work conditions around that
hydraulic structure. Gotvand Re-regulating/ Diversion Dam is one of those previously constructed
hydraulic structures that in view of the change in its upstream conditions, i.e. the construction of the
large Storage Dam of Upper Gotvand with the power generation capacity of 2000 MW, is now in need
of heightening. Gotvand Re-regulating/ Diversion Dam has been operational for 40 years and its aim
has been to provide the communities living downstream of the River Karun with the agricultural,
drinking, and industrial water. So as to avoid any interruption in the operation of the aforementioned
re-regulating dam and to provide adequate volume forregulation, a newapproach wasusedto determine
the required capacity.
2. PROBLEM STATEMENT
The operation of the 2000 MW powerhouse of UpperGotvand Damwithin the peak powerconsumption
hours gives raise to considerable fluctuation in the river flow. The conventional solution for this
problem is to heighten the existing downstream re-regulating dam to obtain the volume required for re-
regulating the downstream flow completely. Based on the existing situation, an additional required
volume of 20 MCM, corresponding to about 6 meter increase in the height of the re-regulating dam is
needed. However, there are structural and operational limitations as follow:
2. Hydropower'15
Stavanger, Norway 15-16 June 2015
2
The tailrace of the powerhouse of the main dam is located in the reservoir of the re-regulating
dam. Therefore any rise in the re-regulating dam height leads to a decrease in the generation of
power. As per the estimations made, 1 m of increase in the re-regulating dam height is equal to
30 GWh decrease in the annual generated power.
From the stability point of view, the foundation of the existing re-regulating dam is able to bear
maximum of 2 m of dam heightening. So, any further increase in the dam height entails
reinforcing the dam foundation and proceeding with huge and costly structural activities.
It is necessary to incessantly have the irrigation canals located in both sides of the regulation
dam operational. So, it makes problems for any structural activities on the dam body.
In addition, with regard to the topographic conditions of the region downstream of the existing
diversion dam, the construction of a new re-regulating dam with enough capacity entails having
a long dam crest which entails a significant cost apart from having a vast area of farmlands
inundated.
Seeing the problem encountered in the conventional method, several assessments were made to find
better solutions. The most appropriate method was to make use of the present structure and efficiently
control/manage the reservoir to attain flow regulation.
Layout of Upper Gotvand Storage Dam and Gotvand Re-regulating/ Diversion Dam is shown in figure
1.
Figure 1-Layout of Gotvand Dam and river in downstream
3. OPTIMIZED SOLUTION
In order for having an efficient management, the parameters that were studied in more detail include
the real operation of the powerhouse, the current function of the existing reservoir, and the
topography of the River Karun downstream".
3. Hydropower'15
Stavanger, Norway 15-16 June 2015
3
3.1 The Real Operation of the Powerhouse
The investigations made in this regard indicated that the powerhouse outflow is affected by the
following factors:
As prioritized, the total volume of the diurnal water release is determined by the downstream
agricultural demand.
The operation hours of the powerhouse units are determined by the national dispatching center
in accordance with the demands of the national grid network.
Normally, power units start/stop to operate in a given intervals, so it is not practical to start and
stop all units simultaneously.
In some days, the national grid network demand reaches its maximum amount in two peak
hours of midday and evening.
The national grid network demands in different days of the week are different. They reach their
minimum amount during the holidays.
In order to increase the scope for the maneuver of hydroelectric power plants of the national
grid network, in some hours, one of the powerhouse units starts giving service to the network
with minimum power generation capacity.
There are different peak hours in different seasons of the year.
A more precise study on the above data indicates that the real operation conditions are different from
the initial presumption pertaining to the 6 hours of uniform and non-stop operation. So as to obtain the
optimum volume of the re-regulating dam reservoir, it would be necessary to study different operation
scenarios for different seasons of the year. Figure 2 depicts a sample of different water release patterns
required for power dispatching.
Figure 2- Some of the patterns used as powerhouse daily power generation
4. Hydropower'15
Stavanger, Norway 15-16 June 2015
4
3.2 Reservoir Conditions of Existing Re-regulating Dam
Taking into consideration the problems articulated in Section 2, the computations showed that in case
of 1.5 m increase in the height gates of the existing-regulating dam, by adding a simple steel beam on
top of gates as shown in the figure 3, the corresponding reservoir volume would be equal to 8.0 MCM.
Figure 4 shows the Elevation –Volume Curve of the reservoir under new the condition.
Figure 3-Adding fix steel beam on top of gates
Figure 4-Elevation – Volume curve of the re-regulating reservoir
5. Hydropower'15
Stavanger, Norway 15-16 June 2015
5
So as to investigate the effects of the re-regulating dam reservoir on the powerhouse outflow, 100 cross
sections of the river were extracted from the area under consideration making use of the re-regulating
dam reservoir hydrographic results. Having entered the above sections data into HEC-RAS software,
the routing of the outflow of the Upper Gotvand Dam Powerhouse was computed for each power
generation patterns of the powerhouse starting in the powerhouse and ending in the re-regulating dam
reservoir.
The results are shown in Figure 5.
Figure 5– Result of intermediate model
The following results were obtained in accordance with the above computation:
The powerhouse outflow goes 10 km inside the re-regulating dam reservoir with delay and a
portion of it is routed (the green graph of Curve No. 1)
By foreseeing the total volume of the diurnal powerhouse outflow, it would be possible to
release water downstream in two steps in 24 hours (the blue graph of the Curve No. 1 depicts
the steps 250 and 600 m3
/ sec).
3.3 - Study of the River Downstream of Dam
At the second step of flow modeling, surveying of Karun cross sections was carried out up to 300 km
downstream of the re-regulating dam. River location and general layout is shown in figure 6.
6. Hydropower'15
Stavanger, Norway 15-16 June 2015
6
Figure6: Downstream river plan
Subsequently, a mathematical model of the River Karun was developed making use of HEC-RAS
software (750 sections were resorted to in creating the foregoing model). Besides, the boundary
conditions have also been applied for different water release scenarios. For implementing upstream
boundary condition of this model, the results presented in figure 5 are used. By running the model for
different operation conditions of the powerhouse,the velocity, watersurface level and discharge at each
point of the river were calculated. The results thus obtained are presented in Figures 7-9.
7. Hydropower'15
Stavanger, Norway 15-16 June 2015
7
Figure7: Flow in 30 km downstream
Figure No. 8: Flow conditions in 60 km downstream (middle of Shotayt River)
Figure 9: Flow in 120 km downstream (Ahwaz city)
Figures 7, 8, and 9 illustrate that the non-uniform discharge released from the re-regulating dam
gradually becomes uniform at downstream due to the temporary storage capacity of the river reach.
This makes it possible to divide the required capacity behind the re-regulating dam into two parts. The
first part is normally provided by the reservoir of the re-regulating dam and the second part is provided
by the river reach at downstream of the re-regulating dam. In case of no objections regarding the
8. Hydropower'15
Stavanger, Norway 15-16 June 2015
8
morphological, environmental and social conditions at the downstream reach of the re-regulating dam
for the non-uniform release of the water, the project would yield a considerable reduction in the re-
regulating dam costs.
4. CONCLUSION
The results of this experiment show that the conventional approach requires 20 million cubic meter
extra regulating capacity, which can be provided by heightening the existing dam by 6 meter. There
would be some time years interruption in the irrigation water supply canals, an annual 100 GWh
reduction of electrical energy due to the corresponding tail water rise of the power plant, and significant
construction costs.
Our new optimized approach, however, can fulfill the regulation requirement, employing only a simple
steel structure for 1.5 meter rise in water level which provides only 4 million cubic meter additional
volume, making use of routing capacity of the river downstream of the dam. There would be a limited
construction cost, negligible annual energy loss, and no interruption in water supply system.
It should be noted that the conventional approach described in this paper was originally used for detail
design of this project. However, in 2012 the subject was revisited, and based on the results of the
investigation presented here, the new optimized approach was adopted. The dam was therefore
modified accordingly and has successfully been operating since then.
In general, for all hydropower development projects with peak power generation, this method of
discharge regulation can be compared with that of the classical approach. Of course, specific
environmental and social aspects of each project must also be considered in order to achieve an
optimized solution.
5. REFFERNCES:
Mahab Ghodss consulting Engineer, 1999, Gotvand 2000 MW Power Plant Design report.
Mahab Ghodss consulting Engineer, 2007, Gotvand re-regulating dam Design report.
Hydrologic Engineering Centers River Analysis System (HEC-RAS),
http://www.hec.usace.army.mil/software/hec-ras