SlideShare a Scribd company logo
California Practice
of Not Grounding
Overhead Distribution
Transformers
Background
The grounding practices and regulations for power systems and the associated equipment have evolved over
time based on experiences and knowledge that have been gained. The preponderance of power companies
outside of the state of California follow a practice of permanently grounding transformer cases. California power
companies typically do not permanently ground transformers. The question is why is California the only state
with this practice and why? This paper is intended to answer this question

Regulations
Regulations regarding power systems started to appear in the early 1900’s as a result of an abnormally high rate
of serious accidents to both lineworkers and the public. The first national efforts were undertaken in 1913 by the
National Bureau of Standards. This effort spawned the National Electrical Safety Code which is today’s national
standard. Individual states had the authority to issue their own regulations. While many states developed regulations for inside wiring few developed any for power lines. California was an exception and they recognized
the need for lineworker and public safety early on and established regulations for all power companies to follow.
Many power companies established their own standards based upon their experiences that were at least as stringent as the state requirements.

NESC
The NESC became the standard that many states adopted and typically becomes the standard for any legal
litigation in many states. The NESC has a general requirement for grounding equipment including transformer
cases but allows an exception for installations over 8 ft. above the ground.
NESC Rule 215 Grounding of circuits, supporting structures, and equipment
C. Non current-carrying parts
1. General
Metal or metal-reinforced supporting structures, including lamp posts; metal conduits and raceways; cable sheaths; messengers; metal frames, cases, and hangers of equipment; and metal switch handles and operating rods shall be effectively
grounded.
EXCEPTION 1: This rule does not apply to frames, cases, and hangers of equipment and switch
handles and operating rods that are 8 ft. or more above readily accessible surfaces or are otherwise
isolated or guarded and where the practice of not grounding such items has been a uniform practice
over a well-defined area.

California and its long standing practice of not grounding transformer cases is in compliance with the NESC. In
California G.O. 95 is applicable standard.

California Public Utilities Commission
California’s power line regulations can be traced back to 1911 and the Railroad Commission of the State of
California. At this time the Railroad Commission had jurisdiction over power companies. In 1911, the state passed
an act which created chapter 499 which regulated the erection and maintenance of overhead
lines. In 1929 the Railroad Commission issued its General Order No. 64-A covering the erection
and maintenance of overhead lines. G.O 64 did not include any requirements for grounding or
not grounding transformer cases.
In 1942 the Railroad Commission updated G.O. 64-A with many changes. Company representatives from power
companies including PG&E, SCE, SDG&E and LADWP were instrumental in the changes that were made. At
this time General Order 64-A was revised as General Order 95. G.O 95 included the following rule:
GO 95 Rule 58.3 - C(3):
Transformer Case Grounding or Bonding: Cases of transformers and metal parts in contact therewith shall not
be grounded where supported on wood poles or wood structures.
Exceptions
Any transformer whose high voltage winding is connected to a circuit of more than 14,000 volts, which may
have its case grounded provided that all such transformer installations on the system are so grounded, warning
signs calling attention to the case grounding condition are posted on the structure so as to be readily legible
from the climbing space and no such grounded transformer case is less than 8 ft. vertically or 4 ft. horizontally
from the unprotected conductors of any other supply-line circuit than those to which the transformer windings
are connected.
Any transformer whose high voltage winding is connected to a circuit of 750 -14,000 volts, which may have its
case grounded provided no unprotected conductors of 750-14,000 volts shall be less than 8 ft. vertically and or
4 ft. horizontally from the nearest part of such grounded case.
Any transformer which is less than 8 ft. above ground.
Keep in mind that in the 1940’s the majority of the distribution systems in California were 4 wire 2400/ 4160 volt
systems with a primary neutral conductor. Linemen were trained to work on these systems off the pole with rubber gloves. The preponderance of representatives from the power companies who worked on the revised G.O.
95 concluded that having the transformer case and hanger brackets grounding presented a significant hazard to
lineworkers as a second point of contact when working on the primary circuits with rubber gloves.
This conclusion resulted in the practice of not grounding transformer cases which is still followed to a large degree
in California.
The current GO 95 is somewhat silent to any requirement to ground or not to ground transformer cases.
GO 95 Rule 58.2 - A(3):
Transformer Case Grounding or Bonding: (See Rule 54.4–G for Grounded Equipment Clearances)
Transformers shall not be supported on metal poles or metal supports in contact with the ground unless the
cases are securely bonded to the metal poles or parts of structures in contact with the ground and such poles
or structures are effectively grounded. Where transformer cases are bonded, the case bonding system
shall not be electrically connected to any unassociated hardware or to other bonds.
Note: Revised January 13, 2005 by Decision No. 0501030.
GO 95 Rule 54.4 – G:
From Grounded Metal Boxes, Hardware and Equipment
All grounded metal boxes, hardware and grounded metal cases for equipment, on non–metallic poles or non–
metallic structures shall be a minimum of 36 inches above and 30 inches below the next level of unprotected
conductors. Such equipment shall have a minimum clearance of 48 inches above or 72 inches below communication line conductors, cables and messengers of different ownership.

Conclusion
There is no question that California’s regulations have resulted in safe and reliable line construction and maintenance performance over the years. This is particularly true for linemen working
off the pole. During the era of working off the pole linemen who had worked in other states were
always complementary of California’s line construction.
At the time the no transformer case grounding requirement was adopted one can readily understand the logic
behind eliminating a large mass of grounded metal as a second point of contact in the work area. Nationally, experience with maintaining and operating overhead lines has confirmed that best practice is to ground the transformer
case. This allows the transformer protection to isolate a transformer where the primary winding has shorted to
the case and minimize the chance of high voltage getting into the secondary winding.
It is possible over time California power companies will gradually shift over to grounding overhead transformer
cases. In the meantime lineworkers working on systems with ungrounded transformer cases should understand
that potentially the cases could be energized and take proper precautions.

More Related Content

What's hot

Hvdc stations
Hvdc stationsHvdc stations
Hvdc stations
RKFILMS2
 
High Voltage Direct Current(Hvdc) transmission
High Voltage Direct Current(Hvdc) transmissionHigh Voltage Direct Current(Hvdc) transmission
High Voltage Direct Current(Hvdc) transmission
University of Gujrat, Pakistan
 
High Voltage DC Transmission
High Voltage DC TransmissionHigh Voltage DC Transmission
High Voltage DC Transmission
krishna koundinya
 
ResShort Electric 2016
ResShort Electric 2016ResShort Electric 2016
ResShort Electric 2016Ledezma Ron
 
Power System with VSC-HVDC Interconnection
Power System with VSC-HVDC InterconnectionPower System with VSC-HVDC Interconnection
Power System with VSC-HVDC Interconnection
Bérengère VIGNAUX
 
Modern substation design
Modern substation designModern substation design
Modern substation design
rajesh18001 R
 
Heavy maintenance
Heavy maintenanceHeavy maintenance
Heavy maintenance
Dilan Atapattu
 
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
Pavan choudhary
 
Ushering in a new era in power transmission
Ushering in a new era in power transmissionUshering in a new era in power transmission
Ushering in a new era in power transmissionPavan Kumar
 
Emergingtrends
EmergingtrendsEmergingtrends
Emergingtrends
mkanth
 
TDU - Unit 02 - HVDC, FACTS and sub-stations
TDU - Unit  02 - HVDC, FACTS and sub-stations TDU - Unit  02 - HVDC, FACTS and sub-stations
TDU - Unit 02 - HVDC, FACTS and sub-stations
PremanandDesai
 
Install Guide - 3 panel fold out
Install Guide - 3 panel fold outInstall Guide - 3 panel fold out
Install Guide - 3 panel fold out
haven832
 
Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design conceptKumar VEL
 
Mechanical Design of Transmission Line (In context of Nepal)
Mechanical Design of Transmission Line (In context of Nepal)Mechanical Design of Transmission Line (In context of Nepal)
Mechanical Design of Transmission Line (In context of Nepal)
Kathmandu Univesity
 
HVDC Transmission lines Market, Technology and Geographical Trends 2016 Prese...
HVDC Transmission lines Market, Technology and Geographical Trends 2016 Prese...HVDC Transmission lines Market, Technology and Geographical Trends 2016 Prese...
HVDC Transmission lines Market, Technology and Geographical Trends 2016 Prese...
Yole Developpement
 
Gss herapura report
Gss herapura reportGss herapura report

What's hot (19)

Hvdc stations
Hvdc stationsHvdc stations
Hvdc stations
 
High Voltage Direct Current(Hvdc) transmission
High Voltage Direct Current(Hvdc) transmissionHigh Voltage Direct Current(Hvdc) transmission
High Voltage Direct Current(Hvdc) transmission
 
High Voltage DC Transmission
High Voltage DC TransmissionHigh Voltage DC Transmission
High Voltage DC Transmission
 
ResShort Electric 2016
ResShort Electric 2016ResShort Electric 2016
ResShort Electric 2016
 
Power System with VSC-HVDC Interconnection
Power System with VSC-HVDC InterconnectionPower System with VSC-HVDC Interconnection
Power System with VSC-HVDC Interconnection
 
Azadar_Training
Azadar_TrainingAzadar_Training
Azadar_Training
 
Modern substation design
Modern substation designModern substation design
Modern substation design
 
Heavy maintenance
Heavy maintenanceHeavy maintenance
Heavy maintenance
 
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
 
Ushering in a new era in power transmission
Ushering in a new era in power transmissionUshering in a new era in power transmission
Ushering in a new era in power transmission
 
Emergingtrends
EmergingtrendsEmergingtrends
Emergingtrends
 
TDU - Unit 02 - HVDC, FACTS and sub-stations
TDU - Unit  02 - HVDC, FACTS and sub-stations TDU - Unit  02 - HVDC, FACTS and sub-stations
TDU - Unit 02 - HVDC, FACTS and sub-stations
 
Track circuit
Track circuitTrack circuit
Track circuit
 
Install Guide - 3 panel fold out
Install Guide - 3 panel fold outInstall Guide - 3 panel fold out
Install Guide - 3 panel fold out
 
Boat outfit
Boat outfitBoat outfit
Boat outfit
 
Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design concept
 
Mechanical Design of Transmission Line (In context of Nepal)
Mechanical Design of Transmission Line (In context of Nepal)Mechanical Design of Transmission Line (In context of Nepal)
Mechanical Design of Transmission Line (In context of Nepal)
 
HVDC Transmission lines Market, Technology and Geographical Trends 2016 Prese...
HVDC Transmission lines Market, Technology and Geographical Trends 2016 Prese...HVDC Transmission lines Market, Technology and Geographical Trends 2016 Prese...
HVDC Transmission lines Market, Technology and Geographical Trends 2016 Prese...
 
Gss herapura report
Gss herapura reportGss herapura report
Gss herapura report
 

Similar to CA Practice of Not Grounding OH Distribution Transformers

Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Low
 
testing-grounding-systems.ppt
testing-grounding-systems.ppttesting-grounding-systems.ppt
testing-grounding-systems.ppt
BayuAnggoro46
 
CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165
michaeljmack
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02
Mohit Kothari
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Mohit Kothari
 
Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0
Mohit Kothari
 
200745907-CEA-Safety-Rules-2010.pptx
200745907-CEA-Safety-Rules-2010.pptx200745907-CEA-Safety-Rules-2010.pptx
200745907-CEA-Safety-Rules-2010.pptx
AmitNag22
 
State of the art of stator winding supports in slot area and winding overhang...
State of the art of stator winding supports in slot area and winding overhang...State of the art of stator winding supports in slot area and winding overhang...
State of the art of stator winding supports in slot area and winding overhang...
Power System Operation
 
State of the art of stator winding supports in slot area and winding overhang...
State of the art of stator winding supports in slot area and winding overhang...State of the art of stator winding supports in slot area and winding overhang...
State of the art of stator winding supports in slot area and winding overhang...
Power System Operation
 
electrical.ppt
electrical.pptelectrical.ppt
electrical.ppt
shivarajCSRaj
 
Nec and oesc-1
Nec and oesc-1Nec and oesc-1
Nec and oesc-1
grantlerc
 
PEC (1).pptx
PEC (1).pptxPEC (1).pptx
PEC (1).pptx
muelmarjanmara
 
Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...
Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...
Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...
Franco Moriconi
 
Chaper 4 Unit 1 Basics of HVDC Transmission.ppt
Chaper 4 Unit 1 Basics of HVDC Transmission.pptChaper 4 Unit 1 Basics of HVDC Transmission.ppt
Chaper 4 Unit 1 Basics of HVDC Transmission.ppt
onlystu007
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
Southern Railway
 
electrical cable crossing.pdf
electrical cable crossing.pdfelectrical cable crossing.pdf
electrical cable crossing.pdf
ssuser01e374
 
BEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
BEAMA Best Practice Guide to Cable Ladder & Cable Tray SystemsBEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
BEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
Thorne & Derrick International
 
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Living Online
 
2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_advertsKhalid Sithari
 
Selecting proper dg set
Selecting proper dg setSelecting proper dg set
Selecting proper dg setMKJain1511
 

Similar to CA Practice of Not Grounding OH Distribution Transformers (20)

Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015
 
testing-grounding-systems.ppt
testing-grounding-systems.ppttesting-grounding-systems.ppt
testing-grounding-systems.ppt
 
CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02
 
Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0
 
200745907-CEA-Safety-Rules-2010.pptx
200745907-CEA-Safety-Rules-2010.pptx200745907-CEA-Safety-Rules-2010.pptx
200745907-CEA-Safety-Rules-2010.pptx
 
State of the art of stator winding supports in slot area and winding overhang...
State of the art of stator winding supports in slot area and winding overhang...State of the art of stator winding supports in slot area and winding overhang...
State of the art of stator winding supports in slot area and winding overhang...
 
State of the art of stator winding supports in slot area and winding overhang...
State of the art of stator winding supports in slot area and winding overhang...State of the art of stator winding supports in slot area and winding overhang...
State of the art of stator winding supports in slot area and winding overhang...
 
electrical.ppt
electrical.pptelectrical.ppt
electrical.ppt
 
Nec and oesc-1
Nec and oesc-1Nec and oesc-1
Nec and oesc-1
 
PEC (1).pptx
PEC (1).pptxPEC (1).pptx
PEC (1).pptx
 
Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...
Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...
Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...
 
Chaper 4 Unit 1 Basics of HVDC Transmission.ppt
Chaper 4 Unit 1 Basics of HVDC Transmission.pptChaper 4 Unit 1 Basics of HVDC Transmission.ppt
Chaper 4 Unit 1 Basics of HVDC Transmission.ppt
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
 
electrical cable crossing.pdf
electrical cable crossing.pdfelectrical cable crossing.pdf
electrical cable crossing.pdf
 
BEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
BEAMA Best Practice Guide to Cable Ladder & Cable Tray SystemsBEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
BEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
 
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
 
2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts
 
Selecting proper dg set
Selecting proper dg setSelecting proper dg set
Selecting proper dg set
 

Recently uploaded

"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
SACHIN R KONDAGURI
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
Scholarhat
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
Mohammed Sikander
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
Peter Windle
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Akanksha trivedi rama nursing college kanpur.
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
Levi Shapiro
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
kimdan468
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
Krisztián Száraz
 

Recently uploaded (20)

"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
 

CA Practice of Not Grounding OH Distribution Transformers

  • 1. California Practice of Not Grounding Overhead Distribution Transformers
  • 2. Background The grounding practices and regulations for power systems and the associated equipment have evolved over time based on experiences and knowledge that have been gained. The preponderance of power companies outside of the state of California follow a practice of permanently grounding transformer cases. California power companies typically do not permanently ground transformers. The question is why is California the only state with this practice and why? This paper is intended to answer this question Regulations Regulations regarding power systems started to appear in the early 1900’s as a result of an abnormally high rate of serious accidents to both lineworkers and the public. The first national efforts were undertaken in 1913 by the National Bureau of Standards. This effort spawned the National Electrical Safety Code which is today’s national standard. Individual states had the authority to issue their own regulations. While many states developed regulations for inside wiring few developed any for power lines. California was an exception and they recognized the need for lineworker and public safety early on and established regulations for all power companies to follow. Many power companies established their own standards based upon their experiences that were at least as stringent as the state requirements. NESC The NESC became the standard that many states adopted and typically becomes the standard for any legal litigation in many states. The NESC has a general requirement for grounding equipment including transformer cases but allows an exception for installations over 8 ft. above the ground. NESC Rule 215 Grounding of circuits, supporting structures, and equipment C. Non current-carrying parts 1. General Metal or metal-reinforced supporting structures, including lamp posts; metal conduits and raceways; cable sheaths; messengers; metal frames, cases, and hangers of equipment; and metal switch handles and operating rods shall be effectively grounded. EXCEPTION 1: This rule does not apply to frames, cases, and hangers of equipment and switch handles and operating rods that are 8 ft. or more above readily accessible surfaces or are otherwise isolated or guarded and where the practice of not grounding such items has been a uniform practice over a well-defined area. California and its long standing practice of not grounding transformer cases is in compliance with the NESC. In California G.O. 95 is applicable standard. California Public Utilities Commission California’s power line regulations can be traced back to 1911 and the Railroad Commission of the State of California. At this time the Railroad Commission had jurisdiction over power companies. In 1911, the state passed an act which created chapter 499 which regulated the erection and maintenance of overhead lines. In 1929 the Railroad Commission issued its General Order No. 64-A covering the erection and maintenance of overhead lines. G.O 64 did not include any requirements for grounding or not grounding transformer cases.
  • 3. In 1942 the Railroad Commission updated G.O. 64-A with many changes. Company representatives from power companies including PG&E, SCE, SDG&E and LADWP were instrumental in the changes that were made. At this time General Order 64-A was revised as General Order 95. G.O 95 included the following rule: GO 95 Rule 58.3 - C(3): Transformer Case Grounding or Bonding: Cases of transformers and metal parts in contact therewith shall not be grounded where supported on wood poles or wood structures. Exceptions Any transformer whose high voltage winding is connected to a circuit of more than 14,000 volts, which may have its case grounded provided that all such transformer installations on the system are so grounded, warning signs calling attention to the case grounding condition are posted on the structure so as to be readily legible from the climbing space and no such grounded transformer case is less than 8 ft. vertically or 4 ft. horizontally from the unprotected conductors of any other supply-line circuit than those to which the transformer windings are connected. Any transformer whose high voltage winding is connected to a circuit of 750 -14,000 volts, which may have its case grounded provided no unprotected conductors of 750-14,000 volts shall be less than 8 ft. vertically and or 4 ft. horizontally from the nearest part of such grounded case. Any transformer which is less than 8 ft. above ground. Keep in mind that in the 1940’s the majority of the distribution systems in California were 4 wire 2400/ 4160 volt systems with a primary neutral conductor. Linemen were trained to work on these systems off the pole with rubber gloves. The preponderance of representatives from the power companies who worked on the revised G.O. 95 concluded that having the transformer case and hanger brackets grounding presented a significant hazard to lineworkers as a second point of contact when working on the primary circuits with rubber gloves. This conclusion resulted in the practice of not grounding transformer cases which is still followed to a large degree in California. The current GO 95 is somewhat silent to any requirement to ground or not to ground transformer cases. GO 95 Rule 58.2 - A(3): Transformer Case Grounding or Bonding: (See Rule 54.4–G for Grounded Equipment Clearances) Transformers shall not be supported on metal poles or metal supports in contact with the ground unless the cases are securely bonded to the metal poles or parts of structures in contact with the ground and such poles or structures are effectively grounded. Where transformer cases are bonded, the case bonding system shall not be electrically connected to any unassociated hardware or to other bonds. Note: Revised January 13, 2005 by Decision No. 0501030. GO 95 Rule 54.4 – G: From Grounded Metal Boxes, Hardware and Equipment All grounded metal boxes, hardware and grounded metal cases for equipment, on non–metallic poles or non– metallic structures shall be a minimum of 36 inches above and 30 inches below the next level of unprotected conductors. Such equipment shall have a minimum clearance of 48 inches above or 72 inches below communication line conductors, cables and messengers of different ownership. Conclusion There is no question that California’s regulations have resulted in safe and reliable line construction and maintenance performance over the years. This is particularly true for linemen working off the pole. During the era of working off the pole linemen who had worked in other states were always complementary of California’s line construction.
  • 4. At the time the no transformer case grounding requirement was adopted one can readily understand the logic behind eliminating a large mass of grounded metal as a second point of contact in the work area. Nationally, experience with maintaining and operating overhead lines has confirmed that best practice is to ground the transformer case. This allows the transformer protection to isolate a transformer where the primary winding has shorted to the case and minimize the chance of high voltage getting into the secondary winding. It is possible over time California power companies will gradually shift over to grounding overhead transformer cases. In the meantime lineworkers working on systems with ungrounded transformer cases should understand that potentially the cases could be energized and take proper precautions.