SlideShare a Scribd company logo
1 of 2
Download to read offline
ID

Task
Mode
1
2
3
4
5
6
7
8
9
10

Task Name

Duration

Start

Finish

Predecessors
Nov 17, '13
W

VERBE
PSD sclicing
Clone PC
Nos expertises metier
Nos clients
Google integration
News
Insights
Careers
WP security

18 days
5 days
2 days
2 days
2 days
1 day
3 days
1 day
2 days
0 days

T

F

S

Nov 24, '13
S
M

Mon 11/25/13Wed 12/18/13
Mon 11/25/13Fri 11/29/13
Mon 12/2/13 Tue 12/3/13 2
Wed 12/4/13 Thu 12/5/13 3
Fri 12/6/13 Mon 12/9/13 4
Tue 12/10/13 Tue 12/10/13 5
Wed 12/11/13Fri 12/13/13 6
Mon 12/16/13Mon 12/16/137
Tue 12/17/13 Wed 12/18/138
11/25

Task

Manual Summary Rollup

Split
Project: Plan_V1
Date: Thu 11/21/13

External Milestone
Inactive Task

Manual Summary

Milestone

Inactive Milestone

Start-only

Summary

Inactive Summary

Finish-only

Project Summary

Manual Task

Deadline

External Tasks

Duration-only

Progress

Page 1

T

W
W

T

F

S

Dec 1, '13
S
M

T

W

T

F

S

Dec 8, '13
S
M

T

W

T

F

S

Dec 15, '13
S
M

/25

Task

Manual Summary Rollup

Split
Project: Plan_V1
Date: Thu 11/21/13

External Milestone
Inactive Task

Manual Summary

Milestone

Inactive Milestone

Start-only

Summary

Inactive Summary

Finish-only

Project Summary

Manual Task

Deadline

External Tasks

Duration-only

Progress

Page 2

T

W

T

F

More Related Content

Viewers also liked

Viewers also liked (10)

While using ASCi values
While using ASCi valuesWhile using ASCi values
While using ASCi values
 
Hexadecimal base 16
Hexadecimal base 16Hexadecimal base 16
Hexadecimal base 16
 
Cp1
Cp1Cp1
Cp1
 
Natalia tecnologia
Natalia tecnologiaNatalia tecnologia
Natalia tecnologia
 
TOR employment
TOR employmentTOR employment
TOR employment
 
LinkedIn - 1500 N Shoreline Blvd
LinkedIn - 1500 N Shoreline BlvdLinkedIn - 1500 N Shoreline Blvd
LinkedIn - 1500 N Shoreline Blvd
 
MINDwell --- Integral Life Change Process
MINDwell --- Integral Life Change ProcessMINDwell --- Integral Life Change Process
MINDwell --- Integral Life Change Process
 
Madeleine Urzúa Gajardo
Madeleine Urzúa GajardoMadeleine Urzúa Gajardo
Madeleine Urzúa Gajardo
 
Sri
SriSri
Sri
 
Presentacion reunion slideshare
Presentacion reunion slidesharePresentacion reunion slideshare
Presentacion reunion slideshare
 

Similar to Verbe planning v1

Project schedule
Project scheduleProject schedule
Project schedulems72527
 
Project1 scheduale assignment 2
Project1   scheduale assignment 2Project1   scheduale assignment 2
Project1 scheduale assignment 2leeanne123
 
Gnatt chart outlining project
Gnatt chart outlining projectGnatt chart outlining project
Gnatt chart outlining projectms72527
 
Project plan
Project planProject plan
Project planLS66731
 
Project plan
Project planProject plan
Project planinwill12
 
Plan proyecto final- Jimmy Bedoya
Plan proyecto final- Jimmy BedoyaPlan proyecto final- Jimmy Bedoya
Plan proyecto final- Jimmy BedoyaJimmy Bedoya
 
WBS Olympic Simulation
WBS Olympic SimulationWBS Olympic Simulation
WBS Olympic SimulationAdam Edwards
 
Mohammad Gannt Chart
Mohammad Gannt ChartMohammad Gannt Chart
Mohammad Gannt Chartmohd3113
 
Microsoft Project Network Diagram
Microsoft Project Network DiagramMicrosoft Project Network Diagram
Microsoft Project Network DiagramMike Deskin
 
Gantt chart final
Gantt chart finalGantt chart final
Gantt chart finalDan Palmer
 
Project Brief Summary PowerPoint Presentation Slides
Project Brief Summary PowerPoint Presentation Slides Project Brief Summary PowerPoint Presentation Slides
Project Brief Summary PowerPoint Presentation Slides SlideTeam
 
Directions for Downloading and Installing OpenProjMGT 402_Pro.docx
Directions for Downloading and Installing OpenProjMGT 402_Pro.docxDirections for Downloading and Installing OpenProjMGT 402_Pro.docx
Directions for Downloading and Installing OpenProjMGT 402_Pro.docxduketjoy27252
 
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxSheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxmaoanderton
 

Similar to Verbe planning v1 (20)

Project schedule
Project scheduleProject schedule
Project schedule
 
Project1 scheduale assignment 2
Project1   scheduale assignment 2Project1   scheduale assignment 2
Project1 scheduale assignment 2
 
Gnatt chart outlining project
Gnatt chart outlining projectGnatt chart outlining project
Gnatt chart outlining project
 
Gant chart
Gant chartGant chart
Gant chart
 
Gant chart
Gant chartGant chart
Gant chart
 
Project plan
Project planProject plan
Project plan
 
Project plan
Project planProject plan
Project plan
 
Plan proyecto final- Jimmy Bedoya
Plan proyecto final- Jimmy BedoyaPlan proyecto final- Jimmy Bedoya
Plan proyecto final- Jimmy Bedoya
 
WBS Olympic Simulation
WBS Olympic SimulationWBS Olympic Simulation
WBS Olympic Simulation
 
Mohammad Gannt Chart
Mohammad Gannt ChartMohammad Gannt Chart
Mohammad Gannt Chart
 
Ner
  Ner  Ner
Ner
 
Project1
Project1Project1
Project1
 
Microsoft Project Network Diagram
Microsoft Project Network DiagramMicrosoft Project Network Diagram
Microsoft Project Network Diagram
 
Project10.mpp
Project10.mppProject10.mpp
Project10.mpp
 
Ariana
ArianaAriana
Ariana
 
Gant chart
Gant chartGant chart
Gant chart
 
Gantt chart final
Gantt chart finalGantt chart final
Gantt chart final
 
Project Brief Summary PowerPoint Presentation Slides
Project Brief Summary PowerPoint Presentation Slides Project Brief Summary PowerPoint Presentation Slides
Project Brief Summary PowerPoint Presentation Slides
 
Directions for Downloading and Installing OpenProjMGT 402_Pro.docx
Directions for Downloading and Installing OpenProjMGT 402_Pro.docxDirections for Downloading and Installing OpenProjMGT 402_Pro.docx
Directions for Downloading and Installing OpenProjMGT 402_Pro.docx
 
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxSheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
 

Verbe planning v1

  • 1. ID Task Mode 1 2 3 4 5 6 7 8 9 10 Task Name Duration Start Finish Predecessors Nov 17, '13 W VERBE PSD sclicing Clone PC Nos expertises metier Nos clients Google integration News Insights Careers WP security 18 days 5 days 2 days 2 days 2 days 1 day 3 days 1 day 2 days 0 days T F S Nov 24, '13 S M Mon 11/25/13Wed 12/18/13 Mon 11/25/13Fri 11/29/13 Mon 12/2/13 Tue 12/3/13 2 Wed 12/4/13 Thu 12/5/13 3 Fri 12/6/13 Mon 12/9/13 4 Tue 12/10/13 Tue 12/10/13 5 Wed 12/11/13Fri 12/13/13 6 Mon 12/16/13Mon 12/16/137 Tue 12/17/13 Wed 12/18/138 11/25 Task Manual Summary Rollup Split Project: Plan_V1 Date: Thu 11/21/13 External Milestone Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 1 T W
  • 2. W T F S Dec 1, '13 S M T W T F S Dec 8, '13 S M T W T F S Dec 15, '13 S M /25 Task Manual Summary Rollup Split Project: Plan_V1 Date: Thu 11/21/13 External Milestone Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 2 T W T F