SlideShare a Scribd company logo
1 of 74
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
1
4. GENERATOR
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
2
CONTENTS
4.1 DESCRIPTION OF THE GENERATOR
4.1.1 GENERATOR DESIGN
4.1.2 GENERATOR CONSTRUCTION
4.1.3 GENERATOR MONITORING INSTRUMENTS
4.1.4 GENERATOR INSPECTION AND
MAINTENANCE
4.2 EXCITATION SYSTEM
4.2.1 DESCRIPTION OF EXCITATION SYSTEM
4.2.2 AVR CUBICLE
4.2.3 EXCITATION SYSTEM MAINTENANCE
CONTENTS
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
3
4.1 DESCRIPTION OF THE GENERATOR
DESCRIPTION OF THE GENERATOR
4.1.1 GENERATOR DESIGN
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
4
GENERATOR DESIGN
Air Cooling System (Capacity: 170 MVA or Less)
Hydrogen Cooling System (Capacity: Between 170 and 350 MVA)
(For Direct Rotor Winding and Indirect Stator Winding)
Water Cooling System (Capacity: More Than 370 MVA)
(For Stator Winding)
TYPES OF GENERATOR COOLING SYSTEMS
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
5
GENERATOR DESIGN
a.Type
b.Cooling System
c.Excitation System
d.Rating
- Nominal rated capacity
- Power factor
- Rated hydrogen pressure
- Number of phases
- Frequency / Speed
- Terminal voltage
- Shot circuit ratio
- Insulation class-Stator
- Temperature rise
e.Cooling Gas Data
- Cooling Gas Flow Rate through Generator
- Cooling gas inlet temperature
- Cooling gas outlet temperature
f.Water Flow Through Stator Winding (If Applied)
g.Cooling Gas (Hydrogen/Air)Cooler
- Quantity
- Cooling water flow rate per unit
- Total cooling water flow
- Cooling water inlet temperature
- Cooling water outlet temperature
- Head loss
DESIGN DATA ITEMS
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
6
4.1.2 GENERATOR CONSTRUCTION
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
7
GENERATOR CONSTRUCTION
CROSS SECTION
Collector
& Brush
H2 Gas Cooler
Rotor
Stator Core
Bearing
Stator Frame
Stator Winding
Rotor Winding
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
8
GENERATOR CONSTRUCTION
SPRING SUPPORT OF STATOR CORE
Stator Core
Flange
Key Bars
Section Plates
Spring Plates
Core
Laminations
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
9
GENERATOR CONSTRUCTION
CONNECTION OF STATOR WINDING
Neutral
Line
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
10
STATOR WINDING COOLING WATER FLOW
Collector
Side
Supply
Water
Drain
VENT
Return
Water
Turbine
Side
Upper Coil
Inlet
Header
Outlet
Header
Bottom Coil
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
Wedge
Slide Wedge
Filler
Hollow Copper Strand
Solid Copper Strand
Grand Insulation
Side Filler
Filler Between Crossovers
Vertical Separator
Filler Strip
11
STATOR COIL
Stator Frame
Cross Section Of
Stator Coil
Stator
Coil Assembly(Transposition Arrangement)
RTD or Filler
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
12
STATOR END WINDING SUPPORT SYSTEM
GENERATOR CONSTRUCTION
Stator End Winding
Nose Ring
Binding Ring
Binding Ring
Support
Permanent Ring
Strap
Inner End Shield
Core End
Core End
Flange
Support
Brackets
Sliding Pin
Sliding Pin
Bearing Pad
Support
Brackets
Sliding
Directions
Glass Fiber Strapping
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
13
TERMINAL BOX
Lead
Connection
Ring
Flexible Lead
High Pressure Area
LOW PRESSURE AREA
Terminal Box
Terminal Box
Bottom Plate
High Voltage
Bushing
Low Pressure Area
GENERATOR CONSTRUCTION
3 Pieces per
Each Bushing
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
14
Connector
In
Holes
Out
VENT TUBU
Guiding Disc
Duct
In
Insulator
Tube
Flange
B.C.T
Conductor
BUSHING
Vent Tube
GENERATOR CONSTRUCTION
Seal
3 Pieces per
Each Bushing
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
15
Shaft Rotor Wedge
Retaining
Ring
Field(Rotor)
Winding
Axial
Flow
Fan
Balance
Weight
Iron Core
Cross Section
Axial Flow Fan
Mounting Position
ROTOR ASSEMBLY
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
16
GENERATOR CONSTRUCTION
CONNECTION OF ROTOR WINDING
Pole 1
Pole 2
Collector Ring
Internal (+)
Terminal Stud
Collector Ring
External(-)
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
17
ROTOR COIL END
DUMPER RING
Creepage
Block
Retaining
ring
Armortisseur Insulation
To Collector Ring
Coil End
End ring
Support
Coil
Slot
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
18
DIRECT-CONDUCTOR-COOLED ROTOR
Wedge
Creepage Block
Inlet Scoop
(Cooled Gas) Rotation
Flush Inlet
Scoop
Turn
Insulation
Outlet
Region
Extruded
Copper
Channel
Slot
Armor
Inlet
Region
Creepage
Block
Wedge
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
19
COLLECTOR RING
Exhaust
Handle
Brush
Collector Ring
Brush Holder
Cooled
Air
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
20
BRUSH
Terminal
Pigtail Wire
Brush To Be Replaced(Consumed Brush)
Low Pressure
Spring
New
Brush
GENERATOR CONSTRUCTION
Brush Holder
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
21
H2 GAS COOLERS
COOLER- A
COOLER- B COOLER- D
COOLER- C
TURBINE END
TOP VIEW
COLLECTOR END
C1
C2
C6
C5
C7
C8
C4
C3
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
22
ROTOR & STATOR COOLING ZONE
H2 Gas Cooler
Rotor Fan
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
23
Gap Baffle
Cold Gas
Hot
Gas
Hot
Gas
Rotor
Stator Core
STATOR SEGREGATING BAFFLE
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
24
GENERATOR CONSTRUCTION
BEARING ASSEMBLY Generator BRG
(Turbine Side)
Generator BRG
(Exciter Side)
Steady Support
(Exciter Bearing)
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
25
BEARING
Turbine
Side
Inside
Collector
Side
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
26
Turbine
Side
Inside
Collector
Side
SEAL CASING
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
27
Turbine
Side
Inside
Collector
Side
INNER OIL DEFLECTOR
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
28
Turbine
Side
Inside
Collector
Side
OUTER OIL DEFLECTOR
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
29
Turbine
Side
Inside
Collector
Side
BEARING RING
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
30
Turbine
Side
Inside
Collector
Side
ALIGNMENT KEY
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
31
GENERATOR CONSTRUCTION
HYDROGEN SEAL
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
32
BEARING BRACKET
GENERATOR CONSTRUCTION
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
33
GENERATOR COOLING WATER SYSTEM
GENERATOR CONSTRUCTION
H2 Gas Coolers
Stator Cooling
Water Coolers
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
34
GENERATOR MONITORING INSTRUMENTS
4.1.3 GENERATOR MONITORING
INSTRUMENTS
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
35
GENERATOR MONITORING INSTRUMENTS
GENERATOR MONITORING INSTRUMENTS
- STATOR COIL TEMPERATURE: RTD
- H2 GAS TEMPERATURE: RTD
- STATOR CORE END TEMPERATURE: TC
- BEARING METAL TEMPERATURE: TC
- BEARING VIBRATION DETECTOR: Gap Sensor
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
36
GENERATOR MONITORING INSTRUMENTS
STATOR COIL RTD (1/2)
Wedge
Stator Core
Upper Coil
Insulation
RTD
Bottom Coil
RTDs Are Installed Between The
Upper Coil And Bottom Coil.
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
37
GENERATOR MONITORING INSTRUMENTS
STATOR COIL RTD (2/2)
RTD
STATOR WEDGE
Maintain spaces
where detectors
are not provided.
White Red
TOP COIL
BOTTOM COIL
RTD:Platinum
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
38
GENERATOR MONITORING INSTRUMENTS
Cross Section Of Stator Frame
RTD For
H2 Gas
Coolers
RTDs Are Arranged In The Ventilation Course Entrance
Of Each H2 Gas Cooler.
HYDROGEN GAS RTDs
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
39
GENERATOR MONITORING INSTRUMENTS
HYDROGEN GAS COOLER RTDs
COOLER A COOLER C
COOLER B COOLER D
RTD
C1
RTD
C5
RTD
C2
RTD
C6
RTD
C4
RTD
C8
RTD
C3
RTD
C7
RTD’s are not
provided.
Cold gas temp. not
controlled automatically.
Total of 8 RTD’s
are used for
monitoring
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
40
GENERATOR MONITORING INSTRUMENTS
STATOR CORE END THERMOCOUPLES (1/2)
Gen. Center
Packing Gland
Packing Gland
Lead Pipe
View From Turbine End
Detector
Marker Tube
Marker Tube
Packing
Gland
Terminal
Thermocouples Are Provided at
The Stator Core End.
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
41
GENERATOR MONITORING INSTRUMENTS
Stator Winding
Wedge
Copper Shield Stator Clamping Plate
Outside Space Block
Stator Core
Core End
Thermocouple
STATOR CORE END THERMOCOUPLES (2/2)
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
42
GENERATOR MONITORING INSTRUMENTS
BEARING METAL THERMOCOUPLES
Thermocouple Thermocouple
BRG
Metal
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
43
GENERATOR MONITORING INSTRUMENTS
BEARING VIBRATION DETECTORS
Vibration
Detector
Bearing And Steady
Support Are Equipped
With Vibration Detectors.
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
44
GENERATOR INSPECTION AND MAINTENANCE
4.1.4 GENERATOR INSPECTION AND
MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
45
PERIODIC INSPECTIONS
& TESTS FOR THE GENERATOR
1. Generator Inspection During Each Shift
2. Daily Generator Inspection & Test
3. Weekly Generator Inspection & Test
4. Generator Inspection & Tests Every 3 to 6 Months
5. Generator Inspection & Tests Every 6 to 12 Months
6. Complete Generator Inspection During Scheduled Shutdown
GENERATOR INSPECTION AND MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
46
1. Generator Inspection During Each Shift
(1) Check the water pressure and water temperature of each gas cooler,
and vent out the air collected in the cooler.
(2) Visually check the condition of the generator collector rings and brushes.
GENERATOR INSPECTION AND MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
47
2. Daily Generator Inspection and Test
(1) Turn the handle on the seal oil filter.
(2) Check the difference between the generator hydrogen pressure
and the seal oil pressure.
(3) Check the oil level in the vacuum tank and oil trap chamber.
(4) Check the drain indicator window of the drain alarm inside the generator.
(5) Check the hydrogen purity meter and the hydrogen flow meter indications.
(6) Check the operation and oil level of the vacuum pump and open the drain
in the drain separator.
(7) Check the brushes and collector rings.
GENERATOR INSPECTION AND MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
48
3. Weekly Generator Inspection and Test
(1) Test that the emergency seal oil pump starts.
(2) Test the various hydrogen alarms.
(3) Check the air filters at the generator brush and collector cooling air intake.
GENERATOR INSPECTION AND MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
49
4. Generator Inspection and Test Every Three to Six Months
(1) Calibrate the hydrogen gas purity meter on the hydrogen control board.
(2) Check the alarm contacts at the hydrogen control board.
(3) Change the oil in the vacuum pump and in the reduction gears.
(4) Refill the float the drain alarm in the generator interior and expansion
tank with oil, and check the alarm operation.
(5) Measure the insulation resistance of the generator bearing insulation
and seal casing insulation for the collector side.
GENERATOR INSPECTION AND MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
50
5. Generator Inspection and Test Every Six to Twelve Months
(1) Test the operation of the alarms on the hydrogen control board.
(2) Perform leak tests for hydrogen gas, including the generator.
(3) Calibrate the hydrogen and seal oil control device meters.
GENERATOR INSPECTION AND MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
51
6. Complete Generator Inspection During Scheduled Shutdown
(1) The person in charge of overhauling work, or the inspector, should affix their
signature to the inspection report upon completion of each item.
(2) Work not performed or work not applicable is to be excluded from the report.
(3) The work sequence may be changed depending on the conditions.
GENERATOR INSPECTION AND MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
52
ADJUSTMENT OF BRUSH HOLDER GAP
15mm
Brush
Pigtail
Wire
Holder
GENERATOR INSPECTION AND MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
53
REPLACING BRUSHES DURING OPERATION
CAUTION: A brush should be replaced if its top is 15mm below the edge of
the brush holder opening ( i.e. the remaining brush length is 55mm. )
When replacing brushes while the generator is in operation, removal of
magazines, one at a time, from a single pole is permissible.
CAUTION: Do not remove more than one magazine from a pole at a time.
Brush replacement should be performed under the supervision of a competent
engineer or an experienced operator.
GENERATOR INSPECTION AND MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
54
HYDROGEN GAS COOLER TROUBLESHOOTING
Symptom
Potential
Causes
Countermeasures
Generator
Operation
Feasibility
Water
leakage
from water
box
Loose bolts ;
Deteriorated
gasket
Additional
torquing ;
Gasket
replacement
Possible ;
Stop Operation
Corrosion and
pitting of cooling
tube
Plugging Stop Operation
Water
leakage
from tube
bundle
Loose joint
between tube and
tube sheet
Flaring Stop Operation
Fouled tubes Tube cleaning Stop Operation
High cooling
water
temperature
Reduction of
generator load
Possible
Generator
overheating
Air pocket in the
top of water box
Air venting Possible
GENERATOR INSPECTION AND MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
55
AIR FILTER INSPECTION & RECYCLING
Filter
Frame
Stud Bolt
Holder
Wing Nut
Air Filter Unit
Air Flow Direction
Detailed View Of Air Filter
GENERATOR INSPECTION AND MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
56
EXCITATION SYSTEM
4.2 EXCITATION SYSTEM
4.2.1 DESCRIPTION OF EXCITATION SYSTEM
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
57
DESCRIPTION OF EXCITATION SYSTEM
TYPE OF EXCITATION SYSTEM
DC Excitation System
Rectifier Excitation
System
Excitation
System
AC Excitation System
Brushless Excitation System
Self-Excited AC Generator System
Thyristor Excitation System
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
58
DESCRIPTION OF EXCITATION SYSTEM
EXCITATION SYSTEM KEY ONELINE
G
AVR
Generator
GEN
Transformer
Excitation
Transformer
GEN.
C.B.
CT's
PT’s
DIGITAL AVR
FCB Thyristor
Component Equipment
- Automatic Voltage Regulator (AVR)
- Thyristor Rectifier
- Field Circuit Breaker (FCB)
- Excitation Transformer
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
59
DESCRIPTION OF EXCITATION SYSTEM
DIGITAL-AVR EXCITATION SYSTEM
G
TRD PHC PLA
PIO
SYSTEM
BUS
MC
SC
GENERATOR
GEN
TRANSF.
EXCITATION
TRANS.
GEN.
C.B.
ABBREVIATIONS
SC: SYSTEM CONTROLLER
MC: MASTER CONTROLLER
PHC: PHASE CONTROL UNIT
PLA: PULSE AMPLIFIER
TRD: TRANSDUCER
CT's
PT’s
FROM UNIT
CONTROL
SYSTEM
PLANT
INTERFACE
DIGITAL AVR
FIELD
THYRISTOR
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
60
AVR CUBICLE
4.2.2 AVR CUBICLE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
61
AVR CUBICLE
A
V
R
c
u
b
i
c
l
e
Internal arrangement
POWER
DISTRIBOTION
RY-UNIT
BP
U-ISO
DUCT
DUCT
RADIATOR UNIT
T T
5
T T
1
T T
6
T T
2
T T
7
T T
3
T T
8
T T
4
MC-B
(9 SLOT)
MC-A
(9 SLOT)
S.C
(19 SLOT)
PWU-B
BP
PWU-A
8
7
6
5
4
3
2
1
FAN UNIT
ARRANGEMENT
OF AVR
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
62
AVR CUBICLE
Device Functions
AVR
(Automatic Voltage Regulator)
To adjust the terminal voltage by automatic
voltage regulator (90R).
UEL
(Under excitation limit)
To prevent the generator from phase -lead
operation under low field current.
OEL
(Over Excitation Limiter)
To prevent the generator from phase -delay
operation under high field current.
VPFL
(V/F Limiter)
To limit overfluxing of the generator and
the generator transformer.
PSS
(Power System Stabilizer)
To add a delta-P stabilizing signal to AVR.
AFU
(Automatic Follow-up of 90R)
To make 90R of the standby system
follow that of the working system.
MEC
(Manual Excitation Controller)
To adjust the field current by manual
voltage regulator(70R).
CONTROL FUNCTIONS
RCC
(Reactive Current Compensator)
To add a voltage droop characteristic
according to reactive current
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
63
AVR CUBICLE
System Controller
COM80
CHO CH1
GIF2
CHO
GPIB
CH0
COM85
CH2
DDCP03
B
CH0
COM85
CH2
DDCP03
B
CN1
EL
Display
Master
Controller
- A
Master
Controller
- B
LOCAL INTERFACE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
64
EXCITATION SYSTEM MAINTENANCE
4.2.3 EXCITATION SYSTEM
MAINTENANCE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
EXCITATION SYSTEM MAINTENANCE
Indicator Explanation
A channel selected This is lit when A-system master
controller is in operation.
B channel selected This is lit when B-system master
controller is in operation.
AVR in service This is lit when AVR is in use.
AFU in service This is lit when AFU is in use.
PSS in service This is lit when PSS is selected.
Field circuit breaker
closed
This is lit when the field circuit breaker
is closed.
Generator circuit
breaker closed
This is lit when the generator
circuit breaker is closed.
OEL operated This is lit when the
overexcitation limit (OEL) is in
operation.
UEL operated This is lit when the
underexcitation limit (UEL) is in
operation.
VPFL operated This is lit when the V / F over
voltage limit (VPFL) is in operation.
STATUS INDICATION OF EL DISPLAY FOR AVR
65
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
66
EXCITATION SYSTEM MAINTENANCE
No. Inspection Items to be confirmed Frequency
1 Visual check ① Are environmental conditions of specification met?
② No dust has accumulated?
③ No direct sun light?
④ No corrosive gas?
⑤ Is ventilation good?
⑥ No vibration?
Any time
2 Check mounting
condition
① Fastenings are tight?
② Connector firmly mounted?
③ Cable and wiring intact?
At regular inspection
3 Check on power unit ① Input/output voltage within the specified range?
②Ripples within the specified range?
At regular inspection
4 Check on interface with
external circuit
①Check the level of analog input signal.
②Check the sequence of contact signal.
③Are these signals input to TOSMAP correctly?
At regular inspection
5 Components ①Is [RUN] LED lit?
②Is the input/output characteristic good?
③Is the program uncorrupted?
④Are set values unchanged? Check on ③ and ④
is made by comparing the memory card and the
floppy disk.
At regular inspection
6 Others ① Are lamps and indicators functional?
② Is the operation of relays normal?
③ Are there any anomalies with other devices?
At regular inspection
MAINTENANCE AND INSPECTION FOR AVR
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
67
EXCITATION SYSTEM MAINTENANCE
THYRISTOR RECTIFIER
FRONT VIEW RIGHT SIDE VIEW
COOLING FAN
AIR EXHAUST AIR EXHAUST
DC BUS DUCT
AC BUS DUCT
AIR FILTER
DC BUS DUCT
COOLING
AIR INLET
THYRISTOR
UNIT
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
68
EXCITATION SYSTEM MAINTENANCE
THYRISTOR BRIDGE
● ● ●
● ●
● ●
●
●
●
●
●
●
●
●
●
●
● ●
●
●
●
●
●
U
V
W
●
P
N
TRAY
THYRISTOR
TRAY
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
69
EXCITATION SYSTEM MAINTENANCE
THYRISTOR FAN REPLACEMENT
REPLACING THE UPPER FAN REPLACING THE LOWER FAN
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
70
EXCITATION SYSTEM MAINTENANCE
THYRISTOR TRAY WITHDRAWAL
CAUTION:
BE SURE TO USE THE
THYRISTOR LIFTER
OUTLINE
REMOVAL
MOUNTING
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
71
EXCITATION SYSTEM MAINTENANCE
FIELD CIRCUIT BREAKER CUBICLE
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
74
EXCITATION SYSTEM MAINTENANCE
FIELD CIRCUIT BREAKER POSITION
The circuit breaker compartment has three functional positions:
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
75
EXCITATION SYSTEM MAINTENANCE
EXCITATION TRANSFORMER
Ventilator
Net
HV Terminals
LV Terminals
Panel
Nameplate
Nameplate
HV BCT
GENERATOR
Classroom Lecture Series for Steam Turbine Generator TOSHIBA
79
END GENERATOR

More Related Content

Similar to Generator description for Tosiba manufacturer.ppt

Evaporator heat pump_product guide
Evaporator heat pump_product guideEvaporator heat pump_product guide
Evaporator heat pump_product guideYury Naumov
 
Marine engineering pump
Marine engineering pumpMarine engineering pump
Marine engineering pumpZeeshan Ahmed
 
42GWC Hydronic Cassette Fan Coil Units.pdf
42GWC Hydronic Cassette Fan Coil Units.pdf42GWC Hydronic Cassette Fan Coil Units.pdf
42GWC Hydronic Cassette Fan Coil Units.pdfCarrier Singapore
 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineeringMobinVarghese8
 
ajeep_04a_energy_eficient_chiller - Mitsu.pdf
ajeep_04a_energy_eficient_chiller - Mitsu.pdfajeep_04a_energy_eficient_chiller - Mitsu.pdf
ajeep_04a_energy_eficient_chiller - Mitsu.pdfbui thequan
 
Sb ls scroll_ver.3.0_en
Sb ls scroll_ver.3.0_enSb ls scroll_ver.3.0_en
Sb ls scroll_ver.3.0_enYury Naumov
 
MULTI V 5 Catalogue_Small[20231107_182247769].pdf
MULTI V 5 Catalogue_Small[20231107_182247769].pdfMULTI V 5 Catalogue_Small[20231107_182247769].pdf
MULTI V 5 Catalogue_Small[20231107_182247769].pdfAnkitavaghela5
 
01 Introduction 8 series toyota presentation.pdf
01 Introduction 8 series toyota presentation.pdf01 Introduction 8 series toyota presentation.pdf
01 Introduction 8 series toyota presentation.pdfjcardy1985
 
3800 series -prv-installation-and-maint-instructions_-802_t_-r2
3800 series -prv-installation-and-maint-instructions_-802_t_-r23800 series -prv-installation-and-maint-instructions_-802_t_-r2
3800 series -prv-installation-and-maint-instructions_-802_t_-r2roberto de la cruz
 
Shell and tube heat exchanger
Shell and tube heat exchangerShell and tube heat exchanger
Shell and tube heat exchangerPraveen Sharma
 
ADVISORY SPARE-TPP.pdf
ADVISORY SPARE-TPP.pdfADVISORY SPARE-TPP.pdf
ADVISORY SPARE-TPP.pdfssuser62a594
 
طلمبات السحب الطرفية - أحادية المراحل
طلمبات السحب الطرفية - أحادية المراحلطلمبات السحب الطرفية - أحادية المراحل
طلمبات السحب الطرفية - أحادية المراحلRheoserve Industrial Solutions
 

Similar to Generator description for Tosiba manufacturer.ppt (20)

Bhel ppt
Bhel pptBhel ppt
Bhel ppt
 
Evaporator heat pump_product guide
Evaporator heat pump_product guideEvaporator heat pump_product guide
Evaporator heat pump_product guide
 
Marine engineering pump
Marine engineering pumpMarine engineering pump
Marine engineering pump
 
tbaux
tbauxtbaux
tbaux
 
42GWC Hydronic Cassette Fan Coil Units.pdf
42GWC Hydronic Cassette Fan Coil Units.pdf42GWC Hydronic Cassette Fan Coil Units.pdf
42GWC Hydronic Cassette Fan Coil Units.pdf
 
61677859-Nooter-Eriksen-Presentation-2.pdf
61677859-Nooter-Eriksen-Presentation-2.pdf61677859-Nooter-Eriksen-Presentation-2.pdf
61677859-Nooter-Eriksen-Presentation-2.pdf
 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineering
 
ajeep_04a_energy_eficient_chiller - Mitsu.pdf
ajeep_04a_energy_eficient_chiller - Mitsu.pdfajeep_04a_energy_eficient_chiller - Mitsu.pdf
ajeep_04a_energy_eficient_chiller - Mitsu.pdf
 
Bujias Delco
Bujias DelcoBujias Delco
Bujias Delco
 
Sb ls scroll_ver.3.0_en
Sb ls scroll_ver.3.0_enSb ls scroll_ver.3.0_en
Sb ls scroll_ver.3.0_en
 
MULTI V 5 Catalogue_Small[20231107_182247769].pdf
MULTI V 5 Catalogue_Small[20231107_182247769].pdfMULTI V 5 Catalogue_Small[20231107_182247769].pdf
MULTI V 5 Catalogue_Small[20231107_182247769].pdf
 
01 Introduction 8 series toyota presentation.pdf
01 Introduction 8 series toyota presentation.pdf01 Introduction 8 series toyota presentation.pdf
01 Introduction 8 series toyota presentation.pdf
 
3800 series -prv-installation-and-maint-instructions_-802_t_-r2
3800 series -prv-installation-and-maint-instructions_-802_t_-r23800 series -prv-installation-and-maint-instructions_-802_t_-r2
3800 series -prv-installation-and-maint-instructions_-802_t_-r2
 
Shell and tube heat exchanger
Shell and tube heat exchangerShell and tube heat exchanger
Shell and tube heat exchanger
 
Estimated Civil & Structural Quantities
Estimated Civil & Structural QuantitiesEstimated Civil & Structural Quantities
Estimated Civil & Structural Quantities
 
M%26m brochure en
M%26m brochure enM%26m brochure en
M%26m brochure en
 
ADVISORY SPARE-TPP.pdf
ADVISORY SPARE-TPP.pdfADVISORY SPARE-TPP.pdf
ADVISORY SPARE-TPP.pdf
 
Bitzer compressor rack
Bitzer compressor rackBitzer compressor rack
Bitzer compressor rack
 
طلمبات السحب الطرفية - أحادية المراحل
طلمبات السحب الطرفية - أحادية المراحلطلمبات السحب الطرفية - أحادية المراحل
طلمبات السحب الطرفية - أحادية المراحل
 
Thermal Group
Thermal GroupThermal Group
Thermal Group
 

Recently uploaded

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 

Recently uploaded (20)

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 

Generator description for Tosiba manufacturer.ppt

  • 1. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 1 4. GENERATOR
  • 2. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 2 CONTENTS 4.1 DESCRIPTION OF THE GENERATOR 4.1.1 GENERATOR DESIGN 4.1.2 GENERATOR CONSTRUCTION 4.1.3 GENERATOR MONITORING INSTRUMENTS 4.1.4 GENERATOR INSPECTION AND MAINTENANCE 4.2 EXCITATION SYSTEM 4.2.1 DESCRIPTION OF EXCITATION SYSTEM 4.2.2 AVR CUBICLE 4.2.3 EXCITATION SYSTEM MAINTENANCE CONTENTS
  • 3. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 3 4.1 DESCRIPTION OF THE GENERATOR DESCRIPTION OF THE GENERATOR 4.1.1 GENERATOR DESIGN
  • 4. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 4 GENERATOR DESIGN Air Cooling System (Capacity: 170 MVA or Less) Hydrogen Cooling System (Capacity: Between 170 and 350 MVA) (For Direct Rotor Winding and Indirect Stator Winding) Water Cooling System (Capacity: More Than 370 MVA) (For Stator Winding) TYPES OF GENERATOR COOLING SYSTEMS
  • 5. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 5 GENERATOR DESIGN a.Type b.Cooling System c.Excitation System d.Rating - Nominal rated capacity - Power factor - Rated hydrogen pressure - Number of phases - Frequency / Speed - Terminal voltage - Shot circuit ratio - Insulation class-Stator - Temperature rise e.Cooling Gas Data - Cooling Gas Flow Rate through Generator - Cooling gas inlet temperature - Cooling gas outlet temperature f.Water Flow Through Stator Winding (If Applied) g.Cooling Gas (Hydrogen/Air)Cooler - Quantity - Cooling water flow rate per unit - Total cooling water flow - Cooling water inlet temperature - Cooling water outlet temperature - Head loss DESIGN DATA ITEMS
  • 6. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 6 4.1.2 GENERATOR CONSTRUCTION GENERATOR CONSTRUCTION
  • 7. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 7 GENERATOR CONSTRUCTION CROSS SECTION Collector & Brush H2 Gas Cooler Rotor Stator Core Bearing Stator Frame Stator Winding Rotor Winding
  • 8. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 8 GENERATOR CONSTRUCTION SPRING SUPPORT OF STATOR CORE Stator Core Flange Key Bars Section Plates Spring Plates Core Laminations
  • 9. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 9 GENERATOR CONSTRUCTION CONNECTION OF STATOR WINDING Neutral Line
  • 10. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 10 STATOR WINDING COOLING WATER FLOW Collector Side Supply Water Drain VENT Return Water Turbine Side Upper Coil Inlet Header Outlet Header Bottom Coil GENERATOR CONSTRUCTION
  • 11. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA Wedge Slide Wedge Filler Hollow Copper Strand Solid Copper Strand Grand Insulation Side Filler Filler Between Crossovers Vertical Separator Filler Strip 11 STATOR COIL Stator Frame Cross Section Of Stator Coil Stator Coil Assembly(Transposition Arrangement) RTD or Filler GENERATOR CONSTRUCTION
  • 12. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 12 STATOR END WINDING SUPPORT SYSTEM GENERATOR CONSTRUCTION Stator End Winding Nose Ring Binding Ring Binding Ring Support Permanent Ring Strap Inner End Shield Core End Core End Flange Support Brackets Sliding Pin Sliding Pin Bearing Pad Support Brackets Sliding Directions Glass Fiber Strapping
  • 13. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 13 TERMINAL BOX Lead Connection Ring Flexible Lead High Pressure Area LOW PRESSURE AREA Terminal Box Terminal Box Bottom Plate High Voltage Bushing Low Pressure Area GENERATOR CONSTRUCTION 3 Pieces per Each Bushing
  • 14. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 14 Connector In Holes Out VENT TUBU Guiding Disc Duct In Insulator Tube Flange B.C.T Conductor BUSHING Vent Tube GENERATOR CONSTRUCTION Seal 3 Pieces per Each Bushing
  • 15. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 15 Shaft Rotor Wedge Retaining Ring Field(Rotor) Winding Axial Flow Fan Balance Weight Iron Core Cross Section Axial Flow Fan Mounting Position ROTOR ASSEMBLY GENERATOR CONSTRUCTION
  • 16. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 16 GENERATOR CONSTRUCTION CONNECTION OF ROTOR WINDING Pole 1 Pole 2 Collector Ring Internal (+) Terminal Stud Collector Ring External(-)
  • 17. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 17 ROTOR COIL END DUMPER RING Creepage Block Retaining ring Armortisseur Insulation To Collector Ring Coil End End ring Support Coil Slot GENERATOR CONSTRUCTION
  • 18. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 18 DIRECT-CONDUCTOR-COOLED ROTOR Wedge Creepage Block Inlet Scoop (Cooled Gas) Rotation Flush Inlet Scoop Turn Insulation Outlet Region Extruded Copper Channel Slot Armor Inlet Region Creepage Block Wedge GENERATOR CONSTRUCTION
  • 19. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 19 COLLECTOR RING Exhaust Handle Brush Collector Ring Brush Holder Cooled Air GENERATOR CONSTRUCTION
  • 20. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 20 BRUSH Terminal Pigtail Wire Brush To Be Replaced(Consumed Brush) Low Pressure Spring New Brush GENERATOR CONSTRUCTION Brush Holder
  • 21. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 21 H2 GAS COOLERS COOLER- A COOLER- B COOLER- D COOLER- C TURBINE END TOP VIEW COLLECTOR END C1 C2 C6 C5 C7 C8 C4 C3 GENERATOR CONSTRUCTION
  • 22. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 22 ROTOR & STATOR COOLING ZONE H2 Gas Cooler Rotor Fan GENERATOR CONSTRUCTION
  • 23. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 23 Gap Baffle Cold Gas Hot Gas Hot Gas Rotor Stator Core STATOR SEGREGATING BAFFLE GENERATOR CONSTRUCTION
  • 24. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 24 GENERATOR CONSTRUCTION BEARING ASSEMBLY Generator BRG (Turbine Side) Generator BRG (Exciter Side) Steady Support (Exciter Bearing)
  • 25. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 25 BEARING Turbine Side Inside Collector Side GENERATOR CONSTRUCTION
  • 26. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 26 Turbine Side Inside Collector Side SEAL CASING GENERATOR CONSTRUCTION
  • 27. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 27 Turbine Side Inside Collector Side INNER OIL DEFLECTOR GENERATOR CONSTRUCTION
  • 28. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 28 Turbine Side Inside Collector Side OUTER OIL DEFLECTOR GENERATOR CONSTRUCTION
  • 29. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 29 Turbine Side Inside Collector Side BEARING RING GENERATOR CONSTRUCTION
  • 30. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 30 Turbine Side Inside Collector Side ALIGNMENT KEY GENERATOR CONSTRUCTION
  • 31. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 31 GENERATOR CONSTRUCTION HYDROGEN SEAL
  • 32. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 32 BEARING BRACKET GENERATOR CONSTRUCTION
  • 33. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 33 GENERATOR COOLING WATER SYSTEM GENERATOR CONSTRUCTION H2 Gas Coolers Stator Cooling Water Coolers
  • 34. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 34 GENERATOR MONITORING INSTRUMENTS 4.1.3 GENERATOR MONITORING INSTRUMENTS
  • 35. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 35 GENERATOR MONITORING INSTRUMENTS GENERATOR MONITORING INSTRUMENTS - STATOR COIL TEMPERATURE: RTD - H2 GAS TEMPERATURE: RTD - STATOR CORE END TEMPERATURE: TC - BEARING METAL TEMPERATURE: TC - BEARING VIBRATION DETECTOR: Gap Sensor
  • 36. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 36 GENERATOR MONITORING INSTRUMENTS STATOR COIL RTD (1/2) Wedge Stator Core Upper Coil Insulation RTD Bottom Coil RTDs Are Installed Between The Upper Coil And Bottom Coil.
  • 37. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 37 GENERATOR MONITORING INSTRUMENTS STATOR COIL RTD (2/2) RTD STATOR WEDGE Maintain spaces where detectors are not provided. White Red TOP COIL BOTTOM COIL RTD:Platinum
  • 38. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 38 GENERATOR MONITORING INSTRUMENTS Cross Section Of Stator Frame RTD For H2 Gas Coolers RTDs Are Arranged In The Ventilation Course Entrance Of Each H2 Gas Cooler. HYDROGEN GAS RTDs
  • 39. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 39 GENERATOR MONITORING INSTRUMENTS HYDROGEN GAS COOLER RTDs COOLER A COOLER C COOLER B COOLER D RTD C1 RTD C5 RTD C2 RTD C6 RTD C4 RTD C8 RTD C3 RTD C7 RTD’s are not provided. Cold gas temp. not controlled automatically. Total of 8 RTD’s are used for monitoring
  • 40. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 40 GENERATOR MONITORING INSTRUMENTS STATOR CORE END THERMOCOUPLES (1/2) Gen. Center Packing Gland Packing Gland Lead Pipe View From Turbine End Detector Marker Tube Marker Tube Packing Gland Terminal Thermocouples Are Provided at The Stator Core End.
  • 41. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 41 GENERATOR MONITORING INSTRUMENTS Stator Winding Wedge Copper Shield Stator Clamping Plate Outside Space Block Stator Core Core End Thermocouple STATOR CORE END THERMOCOUPLES (2/2)
  • 42. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 42 GENERATOR MONITORING INSTRUMENTS BEARING METAL THERMOCOUPLES Thermocouple Thermocouple BRG Metal
  • 43. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 43 GENERATOR MONITORING INSTRUMENTS BEARING VIBRATION DETECTORS Vibration Detector Bearing And Steady Support Are Equipped With Vibration Detectors.
  • 44. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 44 GENERATOR INSPECTION AND MAINTENANCE 4.1.4 GENERATOR INSPECTION AND MAINTENANCE
  • 45. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 45 PERIODIC INSPECTIONS & TESTS FOR THE GENERATOR 1. Generator Inspection During Each Shift 2. Daily Generator Inspection & Test 3. Weekly Generator Inspection & Test 4. Generator Inspection & Tests Every 3 to 6 Months 5. Generator Inspection & Tests Every 6 to 12 Months 6. Complete Generator Inspection During Scheduled Shutdown GENERATOR INSPECTION AND MAINTENANCE
  • 46. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 46 1. Generator Inspection During Each Shift (1) Check the water pressure and water temperature of each gas cooler, and vent out the air collected in the cooler. (2) Visually check the condition of the generator collector rings and brushes. GENERATOR INSPECTION AND MAINTENANCE
  • 47. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 47 2. Daily Generator Inspection and Test (1) Turn the handle on the seal oil filter. (2) Check the difference between the generator hydrogen pressure and the seal oil pressure. (3) Check the oil level in the vacuum tank and oil trap chamber. (4) Check the drain indicator window of the drain alarm inside the generator. (5) Check the hydrogen purity meter and the hydrogen flow meter indications. (6) Check the operation and oil level of the vacuum pump and open the drain in the drain separator. (7) Check the brushes and collector rings. GENERATOR INSPECTION AND MAINTENANCE
  • 48. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 48 3. Weekly Generator Inspection and Test (1) Test that the emergency seal oil pump starts. (2) Test the various hydrogen alarms. (3) Check the air filters at the generator brush and collector cooling air intake. GENERATOR INSPECTION AND MAINTENANCE
  • 49. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 49 4. Generator Inspection and Test Every Three to Six Months (1) Calibrate the hydrogen gas purity meter on the hydrogen control board. (2) Check the alarm contacts at the hydrogen control board. (3) Change the oil in the vacuum pump and in the reduction gears. (4) Refill the float the drain alarm in the generator interior and expansion tank with oil, and check the alarm operation. (5) Measure the insulation resistance of the generator bearing insulation and seal casing insulation for the collector side. GENERATOR INSPECTION AND MAINTENANCE
  • 50. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 50 5. Generator Inspection and Test Every Six to Twelve Months (1) Test the operation of the alarms on the hydrogen control board. (2) Perform leak tests for hydrogen gas, including the generator. (3) Calibrate the hydrogen and seal oil control device meters. GENERATOR INSPECTION AND MAINTENANCE
  • 51. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 51 6. Complete Generator Inspection During Scheduled Shutdown (1) The person in charge of overhauling work, or the inspector, should affix their signature to the inspection report upon completion of each item. (2) Work not performed or work not applicable is to be excluded from the report. (3) The work sequence may be changed depending on the conditions. GENERATOR INSPECTION AND MAINTENANCE
  • 52. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 52 ADJUSTMENT OF BRUSH HOLDER GAP 15mm Brush Pigtail Wire Holder GENERATOR INSPECTION AND MAINTENANCE
  • 53. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 53 REPLACING BRUSHES DURING OPERATION CAUTION: A brush should be replaced if its top is 15mm below the edge of the brush holder opening ( i.e. the remaining brush length is 55mm. ) When replacing brushes while the generator is in operation, removal of magazines, one at a time, from a single pole is permissible. CAUTION: Do not remove more than one magazine from a pole at a time. Brush replacement should be performed under the supervision of a competent engineer or an experienced operator. GENERATOR INSPECTION AND MAINTENANCE
  • 54. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 54 HYDROGEN GAS COOLER TROUBLESHOOTING Symptom Potential Causes Countermeasures Generator Operation Feasibility Water leakage from water box Loose bolts ; Deteriorated gasket Additional torquing ; Gasket replacement Possible ; Stop Operation Corrosion and pitting of cooling tube Plugging Stop Operation Water leakage from tube bundle Loose joint between tube and tube sheet Flaring Stop Operation Fouled tubes Tube cleaning Stop Operation High cooling water temperature Reduction of generator load Possible Generator overheating Air pocket in the top of water box Air venting Possible GENERATOR INSPECTION AND MAINTENANCE
  • 55. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 55 AIR FILTER INSPECTION & RECYCLING Filter Frame Stud Bolt Holder Wing Nut Air Filter Unit Air Flow Direction Detailed View Of Air Filter GENERATOR INSPECTION AND MAINTENANCE
  • 56. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 56 EXCITATION SYSTEM 4.2 EXCITATION SYSTEM 4.2.1 DESCRIPTION OF EXCITATION SYSTEM
  • 57. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 57 DESCRIPTION OF EXCITATION SYSTEM TYPE OF EXCITATION SYSTEM DC Excitation System Rectifier Excitation System Excitation System AC Excitation System Brushless Excitation System Self-Excited AC Generator System Thyristor Excitation System
  • 58. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 58 DESCRIPTION OF EXCITATION SYSTEM EXCITATION SYSTEM KEY ONELINE G AVR Generator GEN Transformer Excitation Transformer GEN. C.B. CT's PT’s DIGITAL AVR FCB Thyristor Component Equipment - Automatic Voltage Regulator (AVR) - Thyristor Rectifier - Field Circuit Breaker (FCB) - Excitation Transformer
  • 59. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 59 DESCRIPTION OF EXCITATION SYSTEM DIGITAL-AVR EXCITATION SYSTEM G TRD PHC PLA PIO SYSTEM BUS MC SC GENERATOR GEN TRANSF. EXCITATION TRANS. GEN. C.B. ABBREVIATIONS SC: SYSTEM CONTROLLER MC: MASTER CONTROLLER PHC: PHASE CONTROL UNIT PLA: PULSE AMPLIFIER TRD: TRANSDUCER CT's PT’s FROM UNIT CONTROL SYSTEM PLANT INTERFACE DIGITAL AVR FIELD THYRISTOR
  • 60. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 60 AVR CUBICLE 4.2.2 AVR CUBICLE
  • 61. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 61 AVR CUBICLE A V R c u b i c l e Internal arrangement POWER DISTRIBOTION RY-UNIT BP U-ISO DUCT DUCT RADIATOR UNIT T T 5 T T 1 T T 6 T T 2 T T 7 T T 3 T T 8 T T 4 MC-B (9 SLOT) MC-A (9 SLOT) S.C (19 SLOT) PWU-B BP PWU-A 8 7 6 5 4 3 2 1 FAN UNIT ARRANGEMENT OF AVR
  • 62. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 62 AVR CUBICLE Device Functions AVR (Automatic Voltage Regulator) To adjust the terminal voltage by automatic voltage regulator (90R). UEL (Under excitation limit) To prevent the generator from phase -lead operation under low field current. OEL (Over Excitation Limiter) To prevent the generator from phase -delay operation under high field current. VPFL (V/F Limiter) To limit overfluxing of the generator and the generator transformer. PSS (Power System Stabilizer) To add a delta-P stabilizing signal to AVR. AFU (Automatic Follow-up of 90R) To make 90R of the standby system follow that of the working system. MEC (Manual Excitation Controller) To adjust the field current by manual voltage regulator(70R). CONTROL FUNCTIONS RCC (Reactive Current Compensator) To add a voltage droop characteristic according to reactive current
  • 63. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 63 AVR CUBICLE System Controller COM80 CHO CH1 GIF2 CHO GPIB CH0 COM85 CH2 DDCP03 B CH0 COM85 CH2 DDCP03 B CN1 EL Display Master Controller - A Master Controller - B LOCAL INTERFACE
  • 64. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 64 EXCITATION SYSTEM MAINTENANCE 4.2.3 EXCITATION SYSTEM MAINTENANCE
  • 65. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA EXCITATION SYSTEM MAINTENANCE Indicator Explanation A channel selected This is lit when A-system master controller is in operation. B channel selected This is lit when B-system master controller is in operation. AVR in service This is lit when AVR is in use. AFU in service This is lit when AFU is in use. PSS in service This is lit when PSS is selected. Field circuit breaker closed This is lit when the field circuit breaker is closed. Generator circuit breaker closed This is lit when the generator circuit breaker is closed. OEL operated This is lit when the overexcitation limit (OEL) is in operation. UEL operated This is lit when the underexcitation limit (UEL) is in operation. VPFL operated This is lit when the V / F over voltage limit (VPFL) is in operation. STATUS INDICATION OF EL DISPLAY FOR AVR 65
  • 66. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 66 EXCITATION SYSTEM MAINTENANCE No. Inspection Items to be confirmed Frequency 1 Visual check ① Are environmental conditions of specification met? ② No dust has accumulated? ③ No direct sun light? ④ No corrosive gas? ⑤ Is ventilation good? ⑥ No vibration? Any time 2 Check mounting condition ① Fastenings are tight? ② Connector firmly mounted? ③ Cable and wiring intact? At regular inspection 3 Check on power unit ① Input/output voltage within the specified range? ②Ripples within the specified range? At regular inspection 4 Check on interface with external circuit ①Check the level of analog input signal. ②Check the sequence of contact signal. ③Are these signals input to TOSMAP correctly? At regular inspection 5 Components ①Is [RUN] LED lit? ②Is the input/output characteristic good? ③Is the program uncorrupted? ④Are set values unchanged? Check on ③ and ④ is made by comparing the memory card and the floppy disk. At regular inspection 6 Others ① Are lamps and indicators functional? ② Is the operation of relays normal? ③ Are there any anomalies with other devices? At regular inspection MAINTENANCE AND INSPECTION FOR AVR
  • 67. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 67 EXCITATION SYSTEM MAINTENANCE THYRISTOR RECTIFIER FRONT VIEW RIGHT SIDE VIEW COOLING FAN AIR EXHAUST AIR EXHAUST DC BUS DUCT AC BUS DUCT AIR FILTER DC BUS DUCT COOLING AIR INLET THYRISTOR UNIT
  • 68. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 68 EXCITATION SYSTEM MAINTENANCE THYRISTOR BRIDGE ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● U V W ● P N TRAY THYRISTOR TRAY
  • 69. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 69 EXCITATION SYSTEM MAINTENANCE THYRISTOR FAN REPLACEMENT REPLACING THE UPPER FAN REPLACING THE LOWER FAN
  • 70. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 70 EXCITATION SYSTEM MAINTENANCE THYRISTOR TRAY WITHDRAWAL CAUTION: BE SURE TO USE THE THYRISTOR LIFTER OUTLINE REMOVAL MOUNTING
  • 71. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 71 EXCITATION SYSTEM MAINTENANCE FIELD CIRCUIT BREAKER CUBICLE
  • 72. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 74 EXCITATION SYSTEM MAINTENANCE FIELD CIRCUIT BREAKER POSITION The circuit breaker compartment has three functional positions:
  • 73. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 75 EXCITATION SYSTEM MAINTENANCE EXCITATION TRANSFORMER Ventilator Net HV Terminals LV Terminals Panel Nameplate Nameplate HV BCT
  • 74. GENERATOR Classroom Lecture Series for Steam Turbine Generator TOSHIBA 79 END GENERATOR